Building construction

Excavation Backfill Compaction Anti termite PCC Reinforcement Foundation concrete Slab on grade
Columns Beams Slabs Core wall Shear wall

Project Manager/Construction Manager:


 The PM/Construction Manager is responsible for the implementation of Method
Statement.
 The PM/Construction Manager shall ensure that the key personnel are well aware of the
Specification and Method Statement.
 The Construction Manager shall ensure that all resources like Manpower, Material and
Equipment are available to carry out the work as planned and without any delay or
confusions.
 Coordinate with the QC and EHS team for proper execution of work in a safe
environment.
 Implement and monitor effectiveness of the risk assessment program.
 Regularly discuss OSH at periodic meetings.
 Ensure availability of welfare facility for the workforce.
Project Engineer/Site Engineer:

 The Project Engineer is responsible to carry out the work as per the Method Statement,
Specification and Approved Drawings.
 The Project Engineer shall ensure that the resources are available to carry out the works
as scheduled.
 Ensure that MSRA trained to site supervisors upon approval and prior to work
executions, in additional to periodic training for the MSRA.
 Ensure reporting of any new hazard/incidents/ unplanned events to EHS team to review
of the MSRA.
 Ensure that all workforces are fully aware about the emergency response and
evacuation procedure.
 Ensure full compliance with EHS recommendations during ejection of the activity.
QA/QC Engineer/Inspector:

 The QA/QC Engineer/Inspector is responsible for the effective monitoring,


implementation & documentation of QA/QC Procedures.
 The QA/QC Engineer/Inspector shall ensure the implementation of ITP and Method
Statements.
 The QA/QC Engineer/Inspector shall ensure that all the approvals are available for the
safe movements of works.
 The QA/QC Engineer/Inspector will coordinate with the consultant for site work
inspection.
Foreman:
 The Foreman is responsible to carry out the work as per the Method Statement,
Specification and Approved Drawings.
 The Foreman shall be available at site full time for the execution of works.
 Ensure that workforce is trained about the MSRA.
 Ensure that welfare facilities are well maintained and housekeeping is proper during
work execution.
 Ensure that daily task briefing is conducted prior to work commencement.
 Ensure that head counting is in place after break hours.
Surveyor:
 The Surveyor shall ensure that all the survey related works carried out as per the
approved drawings.
 The Surveyor shall ensure that setting out and level carried out with Total station and
Auto level.
 For all survey related works he shall be available at site full time.
Safety Engineer/Officer:
 The Safety officer shall observe and advise all site personnel of all safety requirements
in addition to giving safety inductions on regular basis or whenever necessary.
 Conduct induction/training to site staff/workers.
 Conduct site inspection and report deficiencies to project manager/HSE Manager.
Sub-Contractor:

 Ensure the work is carried out as per the Method Statement, Specification and
Approved Drawings.
 Ensure that the resources are available to carry out the works as scheduled.
 Ensure that MSRA trained to site supervisors upon approval and prior to work
executions, in additional to periodic training for the MSRA.
 Ensure reporting of any new hazard/incidents/ unplanned events to EHS team to review
of the MSRA.
 Ensure the availability of competent employees to complete the task
 Ensure the availability of adequate welfare facilities at site
 Ensure the availability of required PPE at site
 Delivered paint material shall be checked for the following things: Expiry
date, original labeled containers, and manufacturer’s name, type of
paint, brand name, color designation and instruction for mixing.
 Material shall be stored in a cool, well ventilated and dry place, away
from direct sunlight.
 Paint material shall be kept away from heat sources.
All materials must be returned to designated storage area after working hours
and properly secured.