Documente Academic
Documente Profesional
Documente Cultură
Chapter 8
Insulation Coordination
1
INTRODUCTION INSULATION COORDINATION
• Insulation coordination is the correlation of electrical
equipment insulation with the characteristics of
protective devices such that the insulation is protected
from excessive overvoltages
basic
insulation
level
Deterministic
approach
2
INTRODUCTION INSULATION COORDINATION
3
INTRODUCTION INSULATION COORDINATION
4
INTRODUCTION INSULATION COORDINATION
5
INSULATION COORDINATION
Types of Insulation:
EXTERNAL INSULATION
INTERNAL INSULATION
External Insulation
• the distances in open air or across the surfaces of solid insulation in
contact with open air that are subjected to dielectric stress and to the
effects of the atmosphere
• Examples: the porcelain shell of a bushing, bus support insulators
and disconnecting switches
Internal insulation
• the internal solid, liquid, or gaseous parts of the insulation of
equipment that are protected by the equipment enclosures from the
effects of the atmosphere
• Examples: transformer insulation, the internal insulation of bushings
• Equipment may be a combination of external and internal insulation
INSULATION COORDINATION
Types of Insulation
SR insulation
• that completely recovers insulating properties after a
disruptive discharge (flashover) caused by the
application of a voltage
• This type of insulation is generally external insulation
9
BASIC INSULATION LEVEL (BIL)
1. Statistical BIL is applicable only to SR insulations
– Statistical BIL - the crest value of standard lightning
impulse for which the insulation exhibits a 90%
probability of withstand, a 10% probability of
failure
10
INSULATION COORDINATION
Statistical BIL/BSL
• Statistical BIL and BSL is defined statistically or
probabilistically
• The insulation strength characteristics may be
represented by a cumulative Gaussian
distribution as shown on the right
• The mean of this distribution is defined as the
critical flashover voltage or CFO
• Applying the CFO voltage to the insulation results
in a 50% probability of flashover
• Locating the BIL or BSL at the 10% point results
in the definition that the BIL or BSL is 1.28
standard deviations, σf, below the CFO
f
BSL CFO1 1.28
CFO
f
BIL CFO1 1.28
CFO
INSULATION COORDINATION
Statistical BIL/BSL
• Explanation on cumulative Gaussian distribution
• For voltages below point A, no breakdown occurs (P = 0)
• For voltages above point B, breakdown will definitely occur (P = 1)
• At point C, there is a 50% probability of breakdown to occur at that
voltage magnitude (P = 0.5)
• 50% or the mean of this distribution is also defined as critical
flashover voltage or CFO
probability for
breakdown, P
0.5
voltage
0 A C B magnitude
INSULATION COORDINATION
Conventional BIL/BSL
• The mean value at 50% probability obtained from the plot is the CFO
• As mentioned before, this type of testing is normally performed only for switching
impulses.
• Limited test for lightning impulse indicate that σf/CFO is much less than that for
switching impulses, i.e. in the range of 2 to 3%
• CFO is universally defined at standard atmospheric conditions
INSULATION COORDINATION
CFO Voltage – Up and Down Method
• Tests may be performed to obtain the entire characteristics or just the CFO
• In many cases, an investigator is only interested in obtaining the CFO
• The procedure employed is called the up and down method:
a) estimate the CFO. Apply one shot. If flashover occurs, lower the
voltage by 3%. If no flashover occurs, increase the voltage by 3%. If upon
application of this voltage, flashover occurs, decrease the voltage by 3%
or if no flashover occurs, increase the voltage by 3%
b) continue for about 50 shots. Discard the shots until one flashover
occurs. The CFO is the average applied voltage used in the remaining
shots.
• This up and down method in a modified form may also be used to
determine a lower probability point.
TIME LAGS FOR BREAKDOWN
• Mechanism of breakdown is a function of ionization
processes
• In practical engineering however, breakdowns are usually
due to rapidly changing voltages, i.e. surge voltage
• Consider an impulse voltage of amplitude V applied to a
gap that breaks down at Vb after a period of time (V>Vb)
• The time which elapses between the application of V and
the breakdown is called the time lag
• It consists of two components:
statistical
time lag,
ts
time
lags
formative
time lag,
tf
25
TIME LAGS FOR BREAKDOWN
• Statistical time lag is the time taken to produce primary
electron to cause initial ionization
• The amount of such electron to be produced is statistical
in nature
• Formative time lag is the time taken for breakdown to
occur once the primary electron has been initiated
voltage
breakdown occurs
V
Vb
time
time lag
26
INSULATION COORDINATION
Time Lags for Breakdown
• Mechanism of breakdown is a function of ionization processes
• In practical engineering however, breakdowns are usually due to rapidly changing
voltages, i.e. surge voltage
• Consider an impulse voltage of amplitude V applied to a gap that breaks down at Vb
after a period of time (V>Vb)
• The time which elapses between the application of V and the breakdown is called
the time lag
• Statistical time lag: The time which lapses between
the application of the voltage (sufficient to cause
breakdown) and the appearance of the initiating voltag
e
electron V
breakdown
occurs
• Formative time lag: The time lag, after the
appearance of free e-, required for the ionization
Vb
processes to develop fully to cause breakdown of the
gap
time
• Time lag: Total time between the application of time
lag
voltage (sufficient to cause breakdown) and the
occurrence of breakdown
INSULATION COORDINATION
Time Lags for Breakdown
• Breakdown with step function voltage pulse show the statistical time lag (ts),
formative time lag (tf) and total time lag (t).
statistical
time lag,
ts
time
lags
formative
time lag,
tf
VOLT-TIME CHARACTERISTICS
• On different impulse voltages applied, breakdown will
occur and the time lag will depend on the rate of rise of
the applied voltage and the field geometry
• Thus for each gap configuration it is possible to construct
a volt-time characteristic
• A number of impulse of increasing level is applied and
time lag for breakdown is recorded using an oscilloscope
• Thus, voltage-time characteristic can be constructed
voltage voltage
volt-time
characteristic
time time
29
VOLT-TIME CHARACTERISTICS
• Typical volt-time curve for transformer & classification of
surge
1 For steep fronted lightning surge
2 Slow fronted lightning surge
3 Fast switching surge
4 Slow switching surge
5 Power frequency
30
VOLT-TIME CHARACTERISTICS
voltage
insulation to
be protected
protecting
device
safety margin
time
• For breakdown to occur the applied voltage (V a) should be greater than the
statistical breakdown voltage (V s)
• The difference in voltage (DV = V a - V s) is known as over-voltage
• Ratio V a/V s is know as impulse ratio
• The volt-time characteristic is very important in insulation co-ordination of the
power electrical apparatus in power system
INSULATION COORDINATION
Time-Lag Curves
A-transformer
B-rod gap 1
C-rod gap 2
D-surge diverter
INSULATION COORDINATION
Time-Lag Curves-Illustrated Protection Example
A-transformer
B-rod gap 1
C-rod gap 2
D-surge diverter
• The rod gap 1 will only protect the transformer until the critical slope line X.
• If the impulse slope is high than the critical slope line X, the rod gap 1 will
not be able to protect transformer.
• Rod gap 2 will be able to protect the transformer until slope 2 but with very
small safety margin.
• The surge diverter which have the volt-time curve as given by the D will be
able protected the transformer for most of the time.
INSULATION COORDINATION
Time-Lag Curves-Illustrated Protection Example
• Although from volt-time curve it seem that the surge diverter can protected
transformer, some other factors need to be considered especially at the substation
In a steep fronted traveling wave, the voltage at different point in the
substation can exceed the protection level. Therefore, more that one lightning
arrester may be needed
The arching horn operation may chopped the wave, the chopped waveform
may harmful to the transformer winding.
The distance of the equipment from the lightning arrester may give rise to
the voltage because of the sucessive reflection between two terminals
STATISTICAL APPROACH
• In extra high voltage (EHV) and ultra high voltage (UHV)
systems, it is not practical to have insulation levels that
could withstand all forms of overvoltages
• It is also impossible to have 100% failure free insulation
since the current in the lightning stroke can be 200kA
• This is because the insulation needs to be extremely high
due to the magnitude of voltage applied and this cannot
be achieved from economical point of view
• Thus protective devices need to be employed at sensitive
points that would limit overvoltages at those points
where a little risk for failure is permitted in the interest of
economic consideration.
• Current practice of insulation coordination rely on
statistical approach which relates directly the electrical
stress and electrical strength
• In other words, the coordination for insulation is based on
its risk of failure
37
STATISTICAL APPROACH
• Consider a case of an occurrence of overvoltage
represented by probability density Po(Vi)dVi (a Gaussian
distribution) between Vi and (Vi + dVi)
• Pd(Vi) is the probability for flashover of the insulation
can be represented by the normal S curve
• The probability of both event occurring simultaneously
at an overvoltage Vi is Pd(Vi) Po(Vi) dVi
• Risk of failure (R) is given by Integration of Pd(Vi)
Po(Vi)dVi from zero to Vi
• Knowledge of these distributions determines the ‘risk of
failure’ (represented by the shaded area under curve R)
insulation
Po breakdown Pb
overvoltage
distribution
voltage 38
applied, Vi
STATISTICAL APPROACH
39
STATISTICAL APPROACH
• However, it would be uneconomical to consider the
complete distribution functions for overvoltage and
withstand of insulation because the samples can be very
large
• A simplified procedure (given by IEC) is to be based on:
-statistical overvoltage, Vs that has a 2% probability for
overvoltage to reach Vs
-withstand voltage, Vw that has a 10% probability that
breakdown will occur in insulation
Po Pb
2%
10 %
voltage voltage
Vs applied, V Vw applied, V
40
STATISTICAL APPROACH
• Statistical safety factor, γ is given as
R1
R2
10 % R3
voltage safety
Vw1 Vw2 Vw3 applied, V γ1 γ2 γ3 factor, γ
41
STATISTICAL APPROACH
• Consider a case of an insulator string protected by a spark
gap of lower breakdown strength
• Both are subjected to the same overvoltage represented by
Po, and probability of breakdown for spark gap and
insulation string are given as Pg and Pi respectively
• Risk of failure for spark gap is much higher than that of
insulation string
• Safety margin is defined as the voltage difference
between 50% flashover values of protecting gap and
insulation
Po Pg Pi Pb
50 %
voltage
applied, V
safety
margin
42
INSULATION COORDINATION
Summary