AVANCE COMPARATIVO - ESTRUCTURAS

DEL 01 AL 31 JULIO 2016


OBRA: REFACCION Y ACONDICIONAMIENTO DE LA SEDE INTENDENCIA DE ADUANA PAITA
UBICACIÓN : Reg. Piura, Prov. Piura, Dist. Paita
Contratista Consorcio Zavaleta
Supervisor Consorcio Supervisor Paita MES.VAL : Jul-16

AVANCE FISICO AVANCE FISICO (%)


Programado Contractual Real Programado Contractual Real
Valorizacion
Parcial Acumulado Parcial Acumulado Parcial Acumulado Parcial Acumulado
VAL-01 171,282.12 171,282.12 157,043.65 157,043.65 10.58% 10.58% 9.70% 9.70%
VAL-02 460,421.92 631,704.04 348,523.15 505,566.80 28.44% 39.02% 21.53% 31.23%
VAL-03 57,574.83 689,278.87 113,534.01 619,100.81 3.56% 42.58% 7.01% 38.24%
VAL-04 297,966.91 987,245.78 84,399.99 703,500.80 18.40% 60.98% 5.21% 43.45%
VAL-05 0.00 987,245.78 0.00 703,500.80 0.00% 60.98% 0.00% 43.45%
VAL-06 16,680.39 1,003,926.17 145,833.61 849,334.41 1.03% 62.01% 9.01% 52.46%
VAL-07 340,276.37 1,344,202.54 542,072.02 1,391,406.43 21.02% 83.03% 33.48% 85.94%
VAL-08 274,765.71 1,618,968.25 16.97%

1,618,968.25 1,391,406.43 100.00%


VALORES AFECTADOS POR EL FACTOR DE RELACION 0.95000, SIN IGV

AVANCES FISICOS PARCIALES AVANCES FISICOS ACUMULADOS


PORCENTAJE

PORCENTAJE
40.00% 100.00%

35.00% 90.00%
80.00%
30.00%
70.00%
25.00%
60.00%
Programado
20.00% 50.00% Programado Real
Real

15.00% 40.00%
30.00%
10.00%
20.00%
AVANCES FISICOS PARCIALES AVANCES FISICOS ACUMULADOS
PORCENTAJE

PORCENTAJE
40.00% 100.00%

35.00% 90.00%
80.00%
30.00%
70.00%
25.00%
60.00%
Programado
20.00% 50.00% Programado Real
Real

15.00% 40.00%
30.00%
10.00%
20.00%
5.00%
10.00%
0.00% 0.00%

MESES MESES
MPARATIVO - ESTRUCTURAS
AVANCE COMPARATIVO - ARQUITECTURA
DEL 01 AL 31 DE JULIO 2016

OBRA: REFACCION Y ACONDICIONAMIENTO DE LA SEDE INTENDENCIA DE ADUANA PAITA


UBICACIÓN : Reg. Piura, Prov. Piura, Dist. Paita
Contratista Consorcio Zavaleta
Supervisor Consorcio Supervisor Paita MES VAL : JULIO 2016.

AVANCE FISICO AVANCE FISICO (%)


Programado Contractual Real Programado Contractual Real
Valorizacion
Parcial Acumulado Parcial Acumulado Parcial Acumulado Parcial Acumulado
VAL-01 72.29 72.29 13,686.57 13,686.57 0.00% 0.00% 0.67% 0.67%
VAL-02 170,265.11 170,337.40 158,230.14 171,916.71 8.34% 8.35% 7.75% 8.42%
VAL-03 278,512.65 448,850.05 282,972.27 454,888.98 13.65% 21.99% 13.86% 22.29%
VAL-04 12,149.93 460,999.98 39,215.38 494,104.36 0.60% 22.59% 1.92% 24.21%
VAL-05 0.00 460,999.98 0.00 494,104.36 0.00% 22.59% 0.00% 24.21%
VAL-06 21.90 461,021.88 0.00 494,104.36 0.00% 22.59% 0.00% 24.21%
VAL-07 100,167.21 561,189.09 212,684.81 706,789.17 4.91% 27.50% 10.42% 34.63%
VAL-08 1,479,848.95 2,041,038.03 72.50%

2,041,038.03 706,789.17 100.00%


VALORES AFECTADO POR FACTOR DE RELACION 0.95000 (SIN IGV)

AVANCE FISICOS ACUMULADOS


AVANCE FISICOS PARCIALES
80.00% 40.00%
72.50% PROGRAMADO ACUMULADO
70.00% 35.00% REAL ACUMULADO

60.00% 30.00% 27.50%

25.00%
50.00% 21.99%22.59% 22.59% 22.59%

40.00% PROGRAMADO 20.00%


EJECUTADO
30.00%
15.00%

10.00% 8.35%
20.00%
13.65%

10.00% 8.34% 5.00%


AVANCE FISICOS ACUMULADOS
AVANCE FISICOS PARCIALES
80.00% 40.00%
72.50% PROGRAMADO ACUMULADO
70.00% 35.00% REAL ACUMULADO

60.00% 30.00% 27.50%

25.00%
50.00% 21.99%22.59% 22.59% 22.59%

40.00% PROGRAMADO 20.00%


EJECUTADO
30.00%
15.00%

10.00% 8.35%
20.00%
13.65%

10.00% 8.34% 5.00%


4.91%
0.67%
0.00%
0.60% 0.00% 0.00%
0.00%
0.00% 0.00% 1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9 10

MESES
MESES
OBRA:
REFACCION
Y
ACONDICION
AMIENTO DE AVANCE COMPARATIVO - INSTALACIONES ELECTRICAS
LA SEDE
INTENDENCI
DEL 01 AL 31 JULIO 2016
A DE
OBRA:
ADUANAREFACCION Y ACONDICIONAMIENTO DE LA SEDE INTENDENCIA DE ADUANA PAITA
PAITA Reg. Piura, Prov. Piura, Dist. Paita
UBICACIÓN : Consorcio Zavaleta
Contratista Consorcio Supervisor Paita MES VAL. : JULIO 2016.

AVANCE FISICO AVANCE FISICO (%)


Programado Contractual Real Programado Contractual Real
Valorizacion
Parcial Acumulado Parcial Acumulado Parcial Acumulado Parcial Acumulado
VAL-01 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00%
VAL-02 14,262.38 14,262.38 412,954.89 412,954.89 0.71% 0.71% 20.56% 20.56%
VAL-03 320,597.74 334,860.12 304,186.66 717,141.55 15.96% 16.67% 15.15% 35.71%
VAL-04 201,093.70 535,953.82 134,507.87 851,649.42 10.01% 26.69% 6.70% 42.41%
VAL-05 0.00 535,953.81 0.00 851,649.42 0.00% 26.69% 0.00% 42.41%
VAL-06 0.01 535,953.83 #REF! #REF! 0.00% 26.69% #REF! #REF!
VAL-07 305,518.84 841,472.67 120,886.55 #REF! 15.21% 41.90% 0.00% 0.00%
VAL-08 1,166,724.39 2,008,197.07 58.10%

2,008,197.07 #REF! 100.00%


VALORES AFECTADO POR FACTOR DE RELACION 0.95000 (SIN IGV)

AVANCES FISICOS PARCIALES


AVANCE FISICO ACUMULADOS
70.00% 45.00%
41.90%

60.00% PROGRAMADO PARCIAL 58.10% 40.00% PROGRAMADO


ACUMULADO
REAL PARCIAL
35.00%
REAL ACUMULADO
50.00%
30.00%
26.69% 26.69% 26.69%
40.00%
25.00%

30.00% 20.00%
16.67%
15.00%
20.00%
15.96% 15.21%
10.00%
10.01%
30.00%
26.69% 26.69% 26.69%
40.00%
25.00%

30.00% 20.00%
16.67%
15.00%
20.00%
15.96% 15.21%
10.00%
10.01%
10.00%
5.00%
0.71% 0.00% 0.71%
0.00% 0.00%
0.00% 0.00%
1 2 3 4 5 6 7 8 9 0.00%
1 2 3 4 5 6 7 8 9
OBRA:
REFACCION
Y
ACONDICION
AMIENTO DE AVANCE COMPARATIVO - INSTALACIONES SANITARIAS
LA SEDE
INTENDENCI DEL 23 AL 30 JUNIO 2016
A DE
OBRA:
ADUANAREFACCION Y ACONDICIONAMIENTO DE LA SEDE INTENDENCIA DE ADUANA PAITA
PAITA Reg. Piura, Prov. Piura, Dist. Paita
UBICACIÓN : Consorcio Zavaleta
Contratista Consorcio Supervisor Paita MES VAL. : JULIO 2016.

AVANCE FISICO AVANCE FISICO (%)


Programado Contractual Real Programado Contractual Real
Valorizacion
Parcial Acumulado Parcial Acumulado Parcial Acumulado Parcial Acumulado
VAL-01 3,511.21 3,511.21 0.00 0.00 0.57% 0.57% 0.00% 0.00%
VAL-02 194,442.03 197,953.24 103,190.22 103,190.22 31.60% 32.17% 16.77% 16.77%
VAL-03 261,068.90 459,022.14 110,204.34 213,394.56 42.42% 74.59% 17.91% 34.68%
VAL-04 38,142.21 497,164.35 393.09 213,787.65 6.20% 80.79% 0.06% 34.74%
VAL-05 49,887.67 547,052.02 0.00 213,787.65 8.11% 88.90% 0.00% 34.74%
VAL-06 68,334.48 615,386.50 0.00 213,787.65 11.10% 100.00% 0.00% 34.74%
VAL-07 0.00 615,386.50 64,775.61 278,563.26 0.00% 100.00% 10.53% 45.27%
VAL-07

615,386.50 278,563.26 100.00%

VALORES AFECTADO POR FACTOR DE RELACION 0.95000 (SIN IGV)

AVANCES FISICOS PARCIALES AVANCE FISICOS


ACUMULADOS
120.00%
45.00% 42.42% PROGRAMADO ACUMULADO

40.00% REAL ACUMULADO 100.00% 100.00%


100.00%
88.90%
35.00% PROGRAMADO PARCIAL
31.60% 80.79%
REAL PARCIAL 80.00% 74.59%
30.00%

25.00%
60.00%
20.00%

15.00% 40.00%
32.17%
11.10%
40.00% REAL ACUMULADO 100.00% 100.00%
100.00%
88.90%
35.00% PROGRAMADO PARCIAL
31.60% 80.79%
REAL PARCIAL 80.00% 74.59%
30.00%

25.00%
60.00%
20.00%

15.00% 40.00%
32.17%
11.10%
10.00% 8.11%
6.20% 20.00%
5.00%
0.57% 0.57%
0.00% 0.00%
0.00%
1 2 3 4 5 6 7 8 9 1 2 3 4 5 6 7 8 9

MESES MESES
OBRA:
REFACCION
Y
ACONDICION RESUMEN DE AVANCE FISICO GENERAL
AMIENTO DE
LA SEDE DEL 01 AL 30 JULIO DEL 2016
INTENDENCI
A DE
OBRA:
ADUANAREFACCION Y ACONDICIONAMIENTO DE LA SEDE INTENDENCIA DE ADUANA PAITA
PAITA Reg. Piura, Prov. Piura, Dist. Paita
UBICACIÓN : Consorcio Zavaleta
Contratista Consorcio Supervisor Paita MES VAL. :

AVANCE FISICO AVANCE FISICO (%)


Programado Contractual Real Programado Contractual Real
Valorizacion
Parcial Acumulado Parcial Acumulado Parcial Acumulado Parcial
VAL-01 174,865.61 174,865.61 170,730.22 170,730.22 2.78% 2.78% 2.72%
VAL-02 839,391.44 1,014,257.05 1,022,898.40 1,193,628.62 13.36% 16.15% 16.28%
VAL-03 917,754.13 1,932,011.18 810,897.28 2,004,525.90 14.61% 30.76% 12.91%
VAL-04 530,281.68 2,462,292.86 258,516.33 2,263,042.23 8.44% 39.20% 4.12%
VAL-05 0.00 2,462,292.86 0.00 2,263,042.23 0.00% 39.20% 0.00%
VAL-06 17,722.27 2,480,015.13 163,863.58 2,426,905.81 0.28% 39.48% 2.61%
VAL-07 798,660.57 3,278,675.70 940,418.99 3,367,324.80 12.71% 52.19% 14.97%
VAL - 08 3,002,914.15 6,281,589.85 47.81% 100.00%

6,281,589.85 3,367,324.80 100.00% 53.61%


VALORES CON AFECTACION DE FACTOR DE RELACION 0.95000,(SIN IGV)

AVANCES FISICOS PARCIALES AVANCES FISICOS ACUMULADOS EN %


PORCENTAJE

PORCENTAJE
60.00% 120.00%

50.00% 100.00%

40.00% 80.00%

PROGRAMADO PROGRA
30.00% 60.00%
EJECUTADO EJECUTA

20.00% 40.00%
50.00% 100.00%

PORC

PORC
40.00% 80.00%

PROGRAMADO PROGRA
30.00% 60.00%
EJECUTADO EJECUTA

20.00% 40.00%

10.00% 20.00%

0.00% 0.00%

MESES MESES
N DE AVANCE FISICO GENERAL

JULIO 216

AVANCE FISICO (%)


Real
Acumulado
2.72%
19.00%
31.91%
36.03%
36.03%
38.64%
53.61%

AVANCES FISICOS ACUMULADOS EN %


PORCENTAJE

120.00%

100.00%

80.00%

PROGRAMADO
60.00%
EJECUTADO

40.00%
100.00%

PORC
80.00%

PROGRAMADO
60.00%
EJECUTADO

40.00%

20.00%

0.00%

MESES
CURVA "S"
CURVAS DE AVANCE FISICO PROGRAMADO VS AVANCE FISI

MEJORAMIENTO Y REHABILITACION DEL CAMINO VECINAL EMPALME R58 - RIO MOCHE, LOCALIDAD DE LAREDO -
DEPARTAMENTO DE LA LIBERTAD
OBRA

CONCURSO PROCEDIMIENTO DE CONTRATACION PUBLICA ESPECIAL No 01-2018-MDL/CS


CONTRATO CONTRATO N° 07-2018-MDL
MODAL. DE EJECUCI PRECIOS UNITARIOS
UBICACIÓN LAREDO - TRUJILLO - LA LIBERTAD
CONTRATISTA CONSORCIO LAREDO NORTE
INSPECTOR HERNAN TORRES BUSTAMANTE
RESIDENTE LUIS ALBERTO RODRIGUEZ MALCA
MONTO EN NUEVOS SOLES

GRAFICO DE AVANCE FISICO - FINANCIERO PROGRAMADO Vs EJECUT

900,000.00

8
800,000.00

700,000.00

600,000.00

500,000.00
600,000.00

500,000.00

400,000.00
401,878.28

300,000.00

200,000.00

100,000.00

17,006.59 80,912.84
0.00
0.00
26/01/2019 31/01/2019 28/02/2019 31/03/2019 2
PLAZO DE EJECUCION 90
DIAS CALENDARIOS

MONTOS VALORIZADOS PROGRAMADOS MONT

MONTOS (Inc IGV) PORCENTAJES MONTOS (I


MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES
S/. S/. % %
26/01/2019 0.00 0.00 0.00% 0.00% 26/01/2019
31/01/2019 17,006.59 17,006.59 2.10% 2.10% 31/01/2019
28/02/2019 63,906.25 80,912.84 7.88% 9.98% 28/02/2019
31/03/2019 320,965.44 401,878.28 39.59% 49.57% 31/03/2019
25/04/2019 408,852.23 810,730.51 50.43% 100.00% 25/04/2019
TOTAL 810,730.51 100.00% TOTAL
17006.58 63906.24 320965.44
CURVA "S"
AMADO VS AVANCE FISICO EJECUTADO

RIO MOCHE, LOCALIDAD DE LAREDO - DISTRITO DE LAREDO - PROVINCIA DE TRUJILLO -

PRESUPÙESTO REFERENCIAL S/. 810,730.51 INCL. IGV


PRESUPUESTO CONTRATADO S/. 810,730.51 INCL. IGV
PRESUPUESTO CONTRATADO S/. 687,059.75 SIN. IGV
PLAZO DE EJECUCION 90 DIAS CALENDARIOS
FACTOR DE RELACION 1.00000 INCL. IGV
ADELANTO DIRECTO NO SE CONSIDERA ADELANTOS INCL. IGV
ADELANTO POR MATERIALES NO SE CONSIDERA ADELANTOS

INANCIERO PROGRAMADO Vs EJECUTADO

810,730.51

Column D
Column D

401,878.28

84

019 31/03/2019 25/04/2019


EJECUCION 90
ALENDARIOS

MONTOS VALORIZADOS EJECUTADOS

MONTOS (Inc IGV) PORCENTAJES


PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % %
408852.23
CURVA "CAMPANA"
CURVAS DE AVANCE FISICO PROGRAMADO VS AVANCE FISI

MEJORAMIENTO Y REHABILITACION DEL CAMINO VECINAL EMPALME R58 - RIO MOCHE, LOCALIDAD DE LAREDO -
DEPARTAMENTO DE LA LIBERTAD
OBRA

CONCURSO PROCEDIMIENTO DE CONTRATACION PUBLICA ESPECIAL No 01-2018-MDL/CS


CONTRATO CONTRATO N° 07-2018-MDL
MODAL. DE EJECUCI PRECIOS UNITARIOS
UBICACIÓN LAREDO - TRUJILLO - LA LIBERTAD
CONTRATISTA CONSORCIO LAREDO NORTE
INSPECTOR HERNAN TORRES BUSTAMANTE
RESIDENTE LUIS ALBERTO RODRIGUEZ MALCA
MONTO EN NUEVOS SOLES

GRAFICO DE AVANCE FISICO - FINANCIERO PROGRAMADO Vs EJECUT

900,000.00

800,000.00

700,000.00

600,000.00

500,000.00
600,000.00

500,000.00

4
400,000.00

320,965.44
300,000.00

200,000.00

100,000.00

17,006.59 63,906.25
0.00
0.00
26/01/2019 31/01/2019 28/02/2019 31/03/2019 2
PLAZO DE EJECUCION 90
DIAS CALENDARIOS

MONTOS VALORIZADOS PROGRAMADOS MONT

MONTOS (Inc IGV) PORCENTAJES MONTOS (I


MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES
S/. S/. % %
26/01/2019 0.00 0.00 0.00% 0.00% 26/01/2019
31/01/2019 17,006.59 17,006.59 2.10% 2.10% 31/01/2019
28/02/2019 63,906.25 80,912.84 7.88% 9.98% 28/02/2019
31/03/2019 320,965.44 401,878.28 39.59% 49.57% 31/03/2019
25/04/2019 408,852.23 810,730.51 50.43% 100.00% 25/04/2019
TOTAL 810,730.51 100.00% TOTAL
RVA "CAMPANA"
AMADO VS AVANCE FISICO EJECUTADO

RIO MOCHE, LOCALIDAD DE LAREDO - DISTRITO DE LAREDO - PROVINCIA DE TRUJILLO -

PRESUPÙESTO REFERENCIAL S/. 810,730.51 INCL. IGV


PRESUPUESTO CONTRATADO S/. 810,730.51 INCL. IGV
PRESUPUESTO CONTRATADO S/. 687,059.75 SIN. IGV
PLAZO DE EJECUCION 90 DIAS CALENDARIOS
FACTOR DE RELACION 1.00000 INCL. IGV
ADELANTO DIRECTO NO SE CONSIDERA ADELANTOS INCL. IGV
ADELANTO POR MATERIALES NO SE CONSIDERA ADELANTOS

INANCIERO PROGRAMADO Vs EJECUTADO

Column C
Column C

408,852.23

320,965.44

25

019 31/03/2019 25/04/2019


EJECUCION 90
ALENDARIOS

MONTOS VALORIZADOS EJECUTADOS

MONTOS (Inc IGV) PORCENTAJES


PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % %