Documente Academic
Documente Profesional
Documente Cultură
PORCENTAJE
40.00% 100.00%
35.00% 90.00%
80.00%
30.00%
70.00%
25.00%
60.00%
Programado
20.00% 50.00% Programado Real
Real
15.00% 40.00%
30.00%
10.00%
20.00%
AVANCES FISICOS PARCIALES AVANCES FISICOS ACUMULADOS
PORCENTAJE
PORCENTAJE
40.00% 100.00%
35.00% 90.00%
80.00%
30.00%
70.00%
25.00%
60.00%
Programado
20.00% 50.00% Programado Real
Real
15.00% 40.00%
30.00%
10.00%
20.00%
5.00%
10.00%
0.00% 0.00%
MESES MESES
MPARATIVO - ESTRUCTURAS
AVANCE COMPARATIVO - ARQUITECTURA
DEL 01 AL 31 DE JULIO 2016
25.00%
50.00% 21.99%22.59% 22.59% 22.59%
10.00% 8.35%
20.00%
13.65%
25.00%
50.00% 21.99%22.59% 22.59% 22.59%
10.00% 8.35%
20.00%
13.65%
MESES
MESES
OBRA:
REFACCION
Y
ACONDICION
AMIENTO DE AVANCE COMPARATIVO - INSTALACIONES ELECTRICAS
LA SEDE
INTENDENCI
DEL 01 AL 31 JULIO 2016
A DE
OBRA:
ADUANAREFACCION Y ACONDICIONAMIENTO DE LA SEDE INTENDENCIA DE ADUANA PAITA
PAITA Reg. Piura, Prov. Piura, Dist. Paita
UBICACIÓN : Consorcio Zavaleta
Contratista Consorcio Supervisor Paita MES VAL. : JULIO 2016.
30.00% 20.00%
16.67%
15.00%
20.00%
15.96% 15.21%
10.00%
10.01%
30.00%
26.69% 26.69% 26.69%
40.00%
25.00%
30.00% 20.00%
16.67%
15.00%
20.00%
15.96% 15.21%
10.00%
10.01%
10.00%
5.00%
0.71% 0.00% 0.71%
0.00% 0.00%
0.00% 0.00%
1 2 3 4 5 6 7 8 9 0.00%
1 2 3 4 5 6 7 8 9
OBRA:
REFACCION
Y
ACONDICION
AMIENTO DE AVANCE COMPARATIVO - INSTALACIONES SANITARIAS
LA SEDE
INTENDENCI DEL 23 AL 30 JUNIO 2016
A DE
OBRA:
ADUANAREFACCION Y ACONDICIONAMIENTO DE LA SEDE INTENDENCIA DE ADUANA PAITA
PAITA Reg. Piura, Prov. Piura, Dist. Paita
UBICACIÓN : Consorcio Zavaleta
Contratista Consorcio Supervisor Paita MES VAL. : JULIO 2016.
25.00%
60.00%
20.00%
15.00% 40.00%
32.17%
11.10%
40.00% REAL ACUMULADO 100.00% 100.00%
100.00%
88.90%
35.00% PROGRAMADO PARCIAL
31.60% 80.79%
REAL PARCIAL 80.00% 74.59%
30.00%
25.00%
60.00%
20.00%
15.00% 40.00%
32.17%
11.10%
10.00% 8.11%
6.20% 20.00%
5.00%
0.57% 0.57%
0.00% 0.00%
0.00%
1 2 3 4 5 6 7 8 9 1 2 3 4 5 6 7 8 9
MESES MESES
OBRA:
REFACCION
Y
ACONDICION RESUMEN DE AVANCE FISICO GENERAL
AMIENTO DE
LA SEDE DEL 01 AL 30 JULIO DEL 2016
INTENDENCI
A DE
OBRA:
ADUANAREFACCION Y ACONDICIONAMIENTO DE LA SEDE INTENDENCIA DE ADUANA PAITA
PAITA Reg. Piura, Prov. Piura, Dist. Paita
UBICACIÓN : Consorcio Zavaleta
Contratista Consorcio Supervisor Paita MES VAL. :
PORCENTAJE
60.00% 120.00%
50.00% 100.00%
40.00% 80.00%
PROGRAMADO PROGRA
30.00% 60.00%
EJECUTADO EJECUTA
20.00% 40.00%
50.00% 100.00%
PORC
PORC
40.00% 80.00%
PROGRAMADO PROGRA
30.00% 60.00%
EJECUTADO EJECUTA
20.00% 40.00%
10.00% 20.00%
0.00% 0.00%
MESES MESES
N DE AVANCE FISICO GENERAL
JULIO 216
120.00%
100.00%
80.00%
PROGRAMADO
60.00%
EJECUTADO
40.00%
100.00%
PORC
80.00%
PROGRAMADO
60.00%
EJECUTADO
40.00%
20.00%
0.00%
MESES
CURVA "S"
CURVAS DE AVANCE FISICO PROGRAMADO VS AVANCE FISI
MEJORAMIENTO Y REHABILITACION DEL CAMINO VECINAL EMPALME R58 - RIO MOCHE, LOCALIDAD DE LAREDO -
DEPARTAMENTO DE LA LIBERTAD
OBRA
900,000.00
8
800,000.00
700,000.00
600,000.00
500,000.00
600,000.00
500,000.00
400,000.00
401,878.28
300,000.00
200,000.00
100,000.00
17,006.59 80,912.84
0.00
0.00
26/01/2019 31/01/2019 28/02/2019 31/03/2019 2
PLAZO DE EJECUCION 90
DIAS CALENDARIOS
810,730.51
Column D
Column D
401,878.28
84
MEJORAMIENTO Y REHABILITACION DEL CAMINO VECINAL EMPALME R58 - RIO MOCHE, LOCALIDAD DE LAREDO -
DEPARTAMENTO DE LA LIBERTAD
OBRA
900,000.00
800,000.00
700,000.00
600,000.00
500,000.00
600,000.00
500,000.00
4
400,000.00
320,965.44
300,000.00
200,000.00
100,000.00
17,006.59 63,906.25
0.00
0.00
26/01/2019 31/01/2019 28/02/2019 31/03/2019 2
PLAZO DE EJECUCION 90
DIAS CALENDARIOS
Column C
Column C
408,852.23
320,965.44
25