Sr.No.

Sub Cluase Descripition

1 11.3 Extension of Defect Notification Period

2 17.3 Employer's Risks

3 2.2 Permits, Licences or Approvals


PCC GCC

Delete the words "However, a Defects Notification Period


shall not be extended by more than two years."

pressure waves caused by aircraft or other


Delete whole of subparagraph (e) of Sub clause 17.3 and aerial devices travelling at sonic or
insert “(Number Not used)” supersonic speeds ,

Add new clause 28 - The Employer shall (where he is in a


The Contractor shall apply for and obtain all government position to do so) provide reasonable
consents, approvals and permits where necessary for the assistance to the Contractor at the request
performance of its obligations under this Contract. The of the Contractor: (a) by
responsibility of obtaining regulatory approval, permits and obtaining copies of the Laws of the Country
licenses required for the performance of its obligations is with which are relevant to the Contract but are
the Contractor including necessary approvals from statutory not readily available , and
authorities for BOI duty free imports. As the Contract is (b) for the Contractor's applications for any
entirely a Design & Build Contract the Contractor is permits , licences or approvals required
responsible to obtain approvals for his construction activities by the Laws of the Country:
and for the design. The Contractor shall also be responsible to (i) which the Contractor is required to
meet the statutory requirements in relation to Design & Build obtain under Sub-Clause 1 .13
Works· and prepare and furnish necessary document required [Compliance with Laws] ,
for such approvals. The Contractor shall be responsible for (ii) for the delivery of Goods, including
obtaining Certificate of Conformity and all other confirmation clearance through customs, and
required for operation on time in relation to the completion (iii) for the export of Contractor's
date mentioned herein, for the relevant Statutory Authorities Equipment when it is removed from the
as described in Sub-clause 1 .13 (c) above. Site .
THEC Comment

Add the following paragraph " Defect notification period


which state in the appendix to tender shall not be change
under Sub- Clause 2.5 [ Employer's Claims]

Shall not be effect from the pressure waves by aircraft or any


aerial device. Because distance between airport and site
have 31 KM. and flight flying height shall be more than 300m
above site

Employer already obtained following approvals


1. Development Permit from UDA
& PPC
2. NWSDB – Water Clearance
3. CEB Clearance
4. CMC Drainage Division Clearance for Sewerage and Storm
Water and
Approval to Lay Sewer Pipes
5. Civil Aviation Authority Clearance
6. Solid Waste Management System Approval
7. Fire Department Clearance
8. PPC from Condominium Management Authority
9. MOD Clearance
10.TIA Clearance & Environmental Clearance
11.Survey Plan of the Site
Clarification request by the Employer

Please Add the following paragraph " Defect notification


period which state in the appendix to tender shall not be
change under Sub- Clause 2.5 [ Employer's Claims]

Please clarify What are the balance approvals & permit need
to be obtain by the Contractor