Sunteți pe pagina 1din 2

RESEARCH PAYS OFF

U.S. AND EUROPEAN


ASPHALT TECHNOLOGIES
A Perfect Marriage
HAROLD R. PAUL AND LOUAY N. MOHAMMAD

he Hale Boggs Bridge over the new mix design that would resist permanent

T Mississippi River at Luling, Louisiana,


is a cable-stayed bridge with a steel
deck. It is part of an important Interstate loop
that carries a large traffic volume around the
deformation and provide extended fatigue life
was therefore needed.

New Orleans metropolitan area. The bridge has SOLUTION


four lanes—two in each direction. The design
of the wearing surface for the steel deck stipu- Investigation indicated that the steel deck
lated an epoxy asphalt layer less than 100 mm was reaching a temperature as high as 77°C
thick because of that material's lower dead load inside the box girders. The high temperature
weight, impermeability, and resistance to per- was causing a loss of bond between the as-
manent deformation and fatigue. In early 1983 phalt binder and the steel deck, resulting in
the wearing surface was constructed, and later the observed shoving. At that time Louisiana
that year the bridge was opened to local traffic. did not have SuperpaveTM mix design capa-
The area of the asphalt-covered deck was bilities, so a latex modified concrete (LMC)
12,240 m2. or a PMAC overlay was proposed. LMC was
eliminated after an off-site trial. The ob-
served performance of PMAC under service
PROBLEM conditions was better, but not satisfactory.
Therefore, the Louisiana Transportation Re-
Before construction had been completed, blis- search Center recommended a merging of
ters started to form on the epoxy asphalt two technologies: use of the SuperpaveTM
wearing surface. These blisters were the result method to specify a performance graded
of the entrapment of water vapor from mois- (PG) asphalt binder and incorporation of the
ture in the mix during construction. More than selected binder in a European stone mastic
3,000 blisters had been repaired by the time the asphalt (SMA).
bridge was opened to local traffic. Yet break- Several polymer modified asphalt binders
down of the epoxy system continued, and re- were tested using the SuperpaveTM method. A
sulted in distress of the wearing surface in the laboratory program was established to test as-
form of shoving and rutting. phalt mixes containing the selected asphalt
By 1986, shoving and rutting of the mix binders. Each mix was tested for indirect ten-
were limited to three areas. With the connec- sile strength, strain at failure, indirect tensile
tion of the southbound approach to a major
TR NEWS 193 NOVEMBER–DECEMBER 1997

creep, and fatigue. The test results were then


highway in 1988, however, traffic volume statistically evaluated. On the basis of the test
increased to 9,000 average daily traffic results, field implementation of a modified
(ADT), and the distress increased. In 1992 a asphalt SMA containing the selected PG as-
maintenance overlay was placed on the three phalt binder was recommended.
worst areas, approximately 280 m2, using a
polymer modified asphalt concrete (PMAC).
The cost of this maintenance patching was
$40,000. In 1993 the north approach was con-
APPLICATION
nected to the 1-310 loop, and traffic increased To evaluate production, handling, and compaction
to over 28,000 ADT. Many new distressed issues before deck construction, an off-site test
24 areas formed in the wearing surface. A was conducted. The bridge deck construction
sequence consisted of removing the existing maintenance patching at a cost of $40,000
epoxy asphalt, replacing the primer coat where within a few years after placement.
necessary, and applying the tack coat and the The SMA mix designed using the Super-
modified asphalt SMA. The PG asphalt binder paveTM PG asphalt binder has satisfactorily car-
was also used as the tack coat material because ried the high traffic volume on the bridge with-
of the high-temperature concerns. out requiring any maintenance for 2 years. The
During the actual paving operation, a mate- cost of the SMA mix was $94/Mg in 1995, and a
rial transfer device was used to facilitate a total of 2,000 Mg of the mix was used. Use of
continuous paving operation, which was es- the SMA mix resulted in a significant savings on
sential for smooth placement of the stiff mix. initial costs as compared with the epoxy asphalt
The bridge was closed in one direction for the mix: the Louisiana Department of Transporta-
paving operation, which was limited to Sun- tion and Development estimates savings of at
days. least $500,000. Additional savings have accrued
To maintain a continuous operation on the during the last 2 years because no maintenance
bridge deck, the plant production rate was work has been needed. This marriage of U.S.
greatly reduced, which resulted in several and European technologies has therefore proven
unscheduled construction stoppages. In ad- to yield significant benefits.
dition, the viscous asphalt with its high For further information contact Harold R.
polymer content plugged the asphalt lines, Paul, Louisiana Department of Transportation,
and the fine-sized material needed for the and associate director, Research, Louisiana
SMA sometimes had problems with the cold Transportation Research Center, 4101 Gourrier
feed. Other than these problems, the con- Avenue, Baton Rouge, LA 70808-4443 (tele-
struction of the modified asphalt SMA over- phone 504/767-9102; fax 504/767-9108), or
lay was a success. Louay N. Mohammad, assistant professor, Lou-
After 2 years the mix is performing well and isiana State University, and manager, Engi-
shows only minor distress. The distress is lim- neering Materials Characterization and Re-
ited, however, to four areas that are directly re- search Facility, Louisiana Transportation Re-
lated to the construction problems noted earlier. search Center (telephone 504/767-9126; fax
504/767-9108).

BENEFITS
TR NEWS 193 NOVEMBER–DECEMBER 1997

EDITOR'S NOTE: Special appreciation is ex-


The design load limitations on the Hale Boggs pressed to Frederick Hejl and G. P. Jayapra-
Bridge dictated that a wearing surface of less kash, Transportation Research Board, for their
than 100 mm be used. The epoxy asphalt efforts in developing this article.
mix originally used for the wearing surface
broke down under the extreme service condi- Suggestions for "Research Pays off" Topics
tions imposed by the Louisiana environment. are welcome. Contact G. P. Jayaprakash,
The cost of the epoxy asphalt mix was Transportation Research Board, 2101 Con-
$400/Mg in 1983. Monthly repairs were stitution Avenue, N.W., Washington, D.C.
needed before the construction was com- 20418 (telephone 202-334-2952; e-mail
pleted, and major areas of the bridge required giayapra@nas.edu).
25

S-ar putea să vă placă și