Andermac RESUMEN EJECUTIVO

FECHA: sábado, 8 de Junio de 2019

PERFORACIÓN
MALLA
GUARDIA EQUIPO Hrs. Netas TAJO BANCO № TAL Mtrs. Perf. Altura Prom. Burden Espac. ø Tal. (Pulg.) Efic.
Día Rock-Drill 1.17 T-CN (ESTE) 4320 Y 4305 36 10.8 0.30 - - 3.5 10.61 %
Día Track-Drill N° 1 3.17 T-CN (ESTE) 4305 14 92.0 6.57 - - 3.5 28.79 %
TOTAL 4.33 - - 50 102.8

COMPRENSORA

GUARDIA EQUIPO Hrs. Netas COMENTARIOS Efic.


Día Compresora Sullair 750 H 3.80 Suministro de aire. 34.55 %
TOTAL 3.80

ACARREO

№ DE VIAJES
Tacaza Tacaza Cofre Cofre Min. B.L. Min. B.L.
GUARDIA VOLQUETE Hrs. Netas TAJO BANCO VOLADURA Desmonte Desbroce Deslizado Top-Soil № viajes Efic.
Cu Pb Cu Pb Cu Pb
T-CN (ESTE) 4320 39 15 0 0 0 0 0 0 0 0 0
Día COV-920 10.25 27 93.18 %
T-CN (OESTE) 4360 38 0 0 0 0 0 0 12 0 0 0
COEMPSA

T-CN (ESTE) 4320 39 15 0 0 0 0 0 0 0 0 0


Día V9S-730 9.75 25 88.64 %
T-CN (OESTE) 4320 39 0 0 0 0 0 0 10 0 0 0
T-CN (ESTE) 4320 39 16 0 0 0 0 0 0 0 0 0
Día F4Z-911 10.23 26 93.03 %
T-CN (OESTE) 4320 39 0 0 0 0 0 0 10 0 0 0
T-CN (ESTE) 4320 39 14 0 0 0 0 0 0 0 0 0
Día AXK-714 10.02 27 91.06 %
T-CN (OESTE) 4360 38 0 0 0 0 0 0 13 0 0 0
Día V4B-942 5.25 T-CN (OESTE) 4360 38 0 0 0 0 0 0 21 0 0 0 21 47.73 %
ANDERMAC

Día AAR-896 9.25 T-CN (OESTE) 4360 38 0 0 0 0 0 0 37 0 0 0 37 84.09 %


T-CN (ESTE) 4320 39 14 0 0 0 0 0 0 0 0 0
Día C0P-920 8.38 24 76.18 %
T-CN (OESTE) 4320 39 0 0 0 0 0 0 10 0 0 0
Día V7C-893 9.25 T-CN (OESTE) 4360 38 0 0 0 0 0 0 37 0 0 0 37 84.09 %
Día F6X-918 9.50 T-CN (OESTE) 4360 38 0 0 0 0 0 0 38 0 0 0 38 86.36 %
Día B5F-782 9.75 T-CN (OESTE) 4360 38 0 0 0 0 0 0 29 0 0 0 39 88.64 %
Día AJK-810 5.50 T-CN (OESTE) 4360 38 0 0 0 0 0 0 12 0 0 0 22 50.00 %
TOTAL 97.13 TAJO-CENTRAL NORTE (ESTE) 74 0 0 0 0 0 0 0 0 0
TOTAL 323

CARGUIO

GUARDIA EQUIPO Hrs. Netas COMENTARIO Efic.


Día Jhon Deere (Coempsa) 9.98 Carguio de Desmonte roto 90.76%
Día Hyundai 360 (coempsa) 10.08 Carguio de Mineral y Desmonte roto 91.67%
TOTAL 20.07

RESUMEN EJECUTIVO CTA-CIA

Ciemsa FECHA: sábado, 8 de Junio de 2019

AUXILIARES

GUARDIA EQUIPO Hrs. Netas COMENTARIO Efic.


Día Motoniveladora 4.75 Mantenmiento de accesos 43.18 %
TOTAL 4.75
PROGRAMA Y CUMPLIMIENTO MENSUAL JUNIO - 2019
FECHA: sábado, 8 de Junio de 2019
DESCRIPCION UM PROGRAMA EJECUCION CUMPLIMIENTO Cumpl. GLOBAL PU SUB TOTAL
Mineral Plomo TMS 0.00 0.00 N.P. S/ 8.86 S/ -
Mineral Cobre TMS 30,000.00 17,330.33 57.77% 57.77% S/ 9.23 S/ 159,958.97
Mineral a COFRE TMS 0.00 0.00 N.P. S/ 7.20 S/ -
Desmonte Roto m3 60,000.00 24,520.00 40.87% S/ 12.30 S/ 301,596.00
49.25%
Desmonte Excavado m3 15,000.00 12,420.00 82.80% S/ 7.30 S/ 90,666.00
Mineral de Segunda TMS 0.00 0.00 0.00% S/ 6.65 S/ -
Produccion GLOBAL M3 87,345.68 44,071.82 50.46% TOTAL S/ 552,220.97

TODO EN M³
EJECUCIÓN Y CUMPLIMIENTO - MAYO 2019
RESUMEN EJECUTIVO MENSUAL Junio-2019
FECHA:
90.00% sábado, 8 de Junio de 2019 82.80%
DESCRIPCION
80.00% UM PROGRAMA EJECUCION CUMPLIMIENTO Cumpl. GLOBAL
Mineral Plomo m3 0.00 0.00 N.P.
70.00% 57.8%
Mineral Cobre m3 12,345.68 7,131.82 57.77%
57.77%
Mineral a COFRE 60.00% m3 0.00 0.00 N.P.
Desmonte Roto m3 60,000.00 24,520.00 40.87%
49.3%
Desmonte Excavado 50.00% m3 15,000.00 12,420.00 82.80% 40.87%
40.00%
Mineral de Segunda m3 0.00 0.00 0.00%
30.00%
Produccion GLOBAL M3 87,345.68 44,071.82 50.46%
20.00%
10.00%
0.00%
0.00%
m3 m3 m3 m3
Mineral a Desmonte Desmonte
Mineral Cobre
COFRE Roto Excavado
PROGRAMA 12,345.68 0.00 60,000.00 15,000.00
EJECUCION 7,131.82 0.00 24,520.00 12,420.00
CUMPLIMIENTO 57.77% 0.00% 40.87% 82.80%