Sunteți pe pagina 1din 24

Installation Manual

Bushings, IEEE/ANSI Standard


Type COTA 150….2050 for Transformers
Type COBA for OCB Bushing Replacement
E 8322.72 2007
Contents Page

1. Introduction 3
2. Scope 3
3. Construction 3-5
4. Nameplate 5
5. Application 6-9
6. Packaging and Transportation 9
7. Receiving and Initial Inspection 9
8. Cleaning 10
9. Installation 10-17
10. Commissioning 17-18
11. Maintenance 18-19
12. Storage 19
13. After Sales Service 19
14. Draw Lead Adapters 19-20
15. Technical Ordering Data 20-22
Notes 23

2
1. Introduction
This manual is protected by copyright. Imparting to any The COBA condenser bushings are constructed for oil
third party and reproduction of any kind without written circuit breaker (OCB) applications and meet or exceed
permission from Trench is strictly prohibited. all applicable dimensional, electrical and mechanical
requirements of the IEEE/ANSI Standard C57.19.00 -
Trench is not responsible for any damage or failure that 1995 and IEEE/ANSI Standard C57.19.01 – 2000,
would result from improper operation, customer Annex A.
furnished materials or failure to observe the
recommendations contained in this manual. This For typical construction details see cut view section
applies even if there is no specific instruction included figures 1.1, 1.2 and 1.3.
for the erection or operation of the particular bushing.
3.2 Active Part (Condenser)
All information contained in this manual is subject to
change without notice and does not represent a The active part of the bushing is made of an oil-
commitment on the part of Trench. impregnated insulating paper with layers of aluminum
foil positioned to ensure radial and axial homogeneity of
Based on Trench's experience and industry standard the electric field. The paper and foil are wound around
practices the highest level of reliability is achieved when either a central aluminum tube or a copper conductor.
the recommendations regarding handling, operation
and maintenance, as outlined in this manual, are
followed. 3.3 Housing

The housing is made of a cast aluminum head, outdoor


2. Scope insulator, mounting flange, ground sleeve (COTA 250
and above), epoxy insulator (Fig. 1.1 & 1.3), or
The material that is provided in this manual does not fiberglass insulator (Fig.1.2) all held together by the
cover all possible conditions; any specific questions central aluminum tube or the copper conductor. Pre-
regarding this manual should be directed to Trench or tensioned cone spring washers provide mechanical
its authorized service representative. Trench assumes stability over the entire temperature range, ensuring a
no liability or responsibility for any damage or failure that leak free bushing. The sealing between all joints is
would result from improper handling, application, accomplished with 0 - Ring gaskets.
installation or use of this product.
Each bushing is hermetically sealed and equipped with
This manual covers all Trench bushings, Type COTA, its own independent oil system, separate from the
that are designed for draw lead or fixed conductor transformer’s oil.
application mounted vertically or horizontally based on
the specific capability of the bushing applied on liquid 3.4 Head
filled transformers and reactors. This manual also
covers all Trench bushings, Type COBA, which are The cast aluminum head serves as an oil expansion
designed specifically for replacement of bushings for oil tank and is designed as a high voltage electrode. The
circuit breakers. design of the head allows for horizontal storage,
shipping and inclination in service up to 40° from
vertical. The oil level can be monitored over the entire
3. Construction temperature range using the oil level indicator in the
head.
3.1 Function
When the design of the head is rectangular this bushing
The COTA condenser bushings are constructed for will allow vertical or horizontal mounting without
transformer applications and meet or exceed all modifying or de-rating the bushing. The oil level
applicable dimensional, electrical and mechanical indicator on this head will only indicate that the bushing
requirements of the IEEE/ANSI Standard C57.19.00 - has an adequate level of oil.
1995 and IEEE/ANSI Standard C57.19.01 – 2000.

3
4
Fig. 1.1 Typical Design COTA 250 - Fig. 1.2 Typical Design COTA 150 Fig. 1.3 Typical Design COTA 250 -
COTA 1175 Draw Lead & COTA 200 Fixed Conductor COTA 1675 Fixed Conductor

Top terminal

Top terminal Top terminal

Draw lead stud

Oil level indicator


Oil level indicator
Oil level indicator
Head housing Head housing

Head housing

Insulator
Insulator
Insulator Active part
Name plate
Active part Active part
Name plate

Air escape plug


Voltage Tap
Test tap (COTA 1050 and above)
Air escape plug (COTA 550 and above)
Voltage Tap
(COTA 1050 and above)
(COTA 550 and above)

Mounting flange

Mounting flange

Mounting flange Grounding sleeve


Test tap
Grounding sleeve (COTA 350 and below)
Test tap
(COTA 350 and below) FRP tube

Conductor

Epoxy insulator

Epoxy insulator

Bottom Terminal
Bottom terminal
3.5 Mounting Flange 4. Nameplate
The cast aluminum mounting flange on COTA and
Each COTA and COBA bushing is supplied with a
COBA 550 and above has two lifting lugs and a
nameplate incorporating the information required by
voltage tap. COTA 150…350 are equipped with a
IEEE/ANSI C57.19.00. In addition to these minimum
test tap. On COTA and COBA 250 and above, the
requirements, Trench nameplates include the voltage
porcelain insulator is secured to the mounting
class and the weight. The weight shown will be
flange using special cement and an 0-Ring gasket.
pounds. The ANSI “L” dimension shown on the
nameplate will be with and without the removable or
3.6 Inboard End Insulator “Split-Conductor”. For the layout of the nameplate
information see figure 2.
The inboard end insulator of the COTA 150, 200
and some models of the COTA 250 and 350 are an Fig. 2
explosion resistant, void free, fiberglass tube.

The inboard end insulator of the COTA and COBA 250


and above are protected by a cone shaped, shatter
resistant, vacuum molded, epoxy-resin insulator.
The epoxy-resin insulator is designed to be installed
during the in-tank drying process of the active part of
the transformer and can withstand temperatures up
to 130º C.

A special aluminum electrode is embedded into the end


of the epoxy-resin insulator to control the electrical field
strength in this area of the bushing.
4.1 Key to Nameplate:
3.7 Outdoor Insulator
1. Technical Ordering Number without accessories,
The standard outdoor insulator for COTA and COBA see Annex for details.
bushings is porcelain. The porcelain is manufactured 2. Voltage Class
by the wet process, is homogeneous and free from 3. Maximum Current Rating. (For draw lead
laminations, cavities or other flaws affecting its
bushings this rating is based on the rating of
mechanical strength or dielectric quality.
the “Split-Conductor”)
One-piece porcelain is standard on all COTA and COBA 4. Maximum Line to Ground Voltage
bushings through 900 kV BIL. 1050 kV BIL and above 5. Outline Drawing Number (As originally sold)
can be provided with one-piece porcelain upon request. 6. Lightning Impulse and Dry Test Voltage
No porcelain will be provided with gasket joints 7. Inboard end length
between pieces of porcelain. 8. Percent Maximum Power Factor
9. Capacitance between Test Tap and
All COTA bushings can be provided with a non-ceramic Conductor (150…350)
insulator. These insulators consist of an explosion Capacitance between Voltage Tap and
resistant fiberglass tube with silicone rubber sheds Conductor (550…2150)
molded over the tube. 10. Capacitance between Voltage Tap and flange
(not available on 150…350)
11. Approximate weight including “Split-Conductor”
CAUTION: Special care must be taken when
in pounds.
handling COTA bushings with Silicone Rubber
12. Year of Manufacture
Insulators (SRI). Slings must not be placed between
the sheds and lifting must follow recommendations 13. Serial Number (Includes accessory codes as
in Section 9. originally sold)

5
5. Application The oil level indicator on these bushings is only an
indication of the amount of oil in the bushing, not the
actual oil level. The oil level indicator has a red floater
5.1 Bushing Mounting behind the glass. In normal operation the red floater will
be at the top of indicator, indicating sufficient oil is in
5.1.1 Bushing for Vertical Mounting the bushing. If the floater is at the bottom of the
indicator this indicates a low oil volume.
Trench COTA bushings that are designed for vertical
mounting is very simple to apply. The only consideration It is important to consider the location of the oil level
is the inclination of mounting from vertical and indicator when applying these bushings on new or
orientation of the oil level indicator. re-manufactured transformers. For proper location of
the oil level indicator for vertical or horizontal application
All COTA and COBA bushings designed for vertical see figure 3, A and B.
mounting may be inclined up to 40° from vertical. When
inclined, the oil level indicator must be orientated facing It is sometimes desirable to incline vertically mounted
out, allowing easy viewing of the oil level from the bushings. For these applications the following
ground. guidelines are offered to maintain proper oil level
indication:
Mounting at inclinations greater than 40° from vertical
may be allowed only after consultation with Trench. In •W
 ith the oil level indicator facing down the maximum
most cases of allowed mounting greater than 40° from angle of inclination from vertical is 12º.
vertical the oil level indicator will be required to face the
ground. In this position the oil level indicator will not •W
 ith the oil level indicator at its highest point (bushing
provide true oil level indication. Trench will provide turned 90º) the maximum angle of inclination from
special instructions for reading the oil level of the vertical is 18º.
bushing when inclined greater than 40° from vertical.
The heads of these bushings are rectangle and the
5.1.2 Bushing for Vertical or orientation of the bushing can affect the phase to phase
Horizontal Mounting spacing in air. Consideration of this fact must be taken
into account when applying these bushings.
Trench COTA bushings that are designed for vertical
and horizontal mounting, are very simple to apply. The Contact Trench if you have any questions on the
only items that need to be considered are the location application of these bushings designed for vertical or
of oil level indication and the orientation of the head. horizontal mounting.

Fig. 3 Proper location of Oil Level Indicator

6
5.2 Current Path Options Oil Condition
Oil Mineral
A key item to consider when applying bushings is the Water <15 PPM
current path options. Trench COTA bushings offer two Particles Max. 39,630 per gallon
current path options, draw lead or fixed conductor.
Size 59 to 2362 µ inch
Oil Strength >70 kV per 0.1 inch
5.2.1 Draw lead
The following figure provides recommendations for
5.2.1.1 Draw lead cable(s) application applying the insulated draw lead conductor to the
Trench COTA bushings.
Current path via the transformer’s copper cable(s) to a
silver-plated copper cable terminal through multi spring Fig. 4.2
contacts to the copper alloy top terminal. For selection
of the appropriate draw lead cable terminal refer to
section 5 or contact Trench.

When the draw lead cable option is selected, the


embedded aluminum end shield allows simple, space
saving assembly without additional shields and barriers.
For reference, the following table provides typical
distances from the centerline of the bushing to the
nearest grounded part.

Fig. 4.1 5.2.1.2 Draw Lead Cable Loading

The following guidelines are offered for selecting and


applying flexible, copper draw lead conductor with
more than 200 strands with a strand diameter less than
.03 inch and the cable insulated with 5 mils of index
105 insulation.

COTA Cross Max.


BIL Section Load
Rating mm Amps A/mm
150 70 215 3.10
and 95 265 3.07
200 150 385 2.57
285 640 2.25
350 750 2.14
250 70 200 2.86
R Minimum
and 95 250 2.63
COTA (mm) (inch) 350 150 360 2.40
150 65 2.56 285 600 2.11
200 75 2.95 350 700 2.00
250 85 3.35 550 70 190 2.71
350 120 4.72 to 95 235 2.47
750 150 340 2.27
550 145 5.71
285 540 1.89
650 180 7.09 490 815 1.66
750 225 8.86 900 95 180 1.89
900 270 10.63 to 150 265 1.77
1175 300 11.81 1175 285 430 1.56
450 600 1.33
The above table is based on the following transformer 665 800 1.20
or reactor oil condition.
7
The values on the previous page are based on a The only other consideration is the design of the
maximum ambient temperature of 40°C, an average mounting flange shipping cover. (All COTA “Split-
24 hour ambient of 30°C at a frequency of 60 Hz and Conductor” bushings) The shipping cover will require a
a maximum rise of the transformer oil of 65°C. supporting bar welded to the center underside of the
shipping cover. This supporting bar must have
Contact your local Trench representative with any matching threaded holes to allow the inboard section of
questions regarding the above recommendations. the “Split-Conductor” to be secured during transport of
the transformer. In addition, some provisions should be
5.2.1.3 “Split-conductor” Application considered to lift the shipping cover when the bushing
is installed. “Split-Conductors” when attached to the
Current path via Trench’s copper “Split-Conductor” winding leads can be very heavy.
draw lead conductor through multi spring contacts to
the copper alloy top terminal. For specific shipping cover design requirements and
detailed drawings of the required “Split-Conductor”
Application of “Split-Conductor” bushings, COTA 150 contact Trench.
through 350, through 2,000 A, for new or
re-manufactured transformers require some special When the "Split-Conductor" option is selected
consideration at the time the transformer is designed. additional shields or barriers may be required
The split of the “Split-Conductor” is located 1/2” (12.5 depending on the applied voltage and/or mounting
mm) below the gasket surface of the bushing mounting conditions, see figure 5.1-5.4.
flange. The inside diameter of the mounting flange does
not allow enough space to assemble or disassemble 5.2.2 Fixed conductor application
the “Split-Conductor”. For this reason the transformer
design must allow the “Split-Conductor” to be lifted Current path via a fixed copper conductor.
vertically 6” (150 mm). This additional vertical lift
capability is not required when these bushings are When the fixed conductor option is selected additional
applied as replacement bushings on existing shields or barriers may be required depending on the
transformers. applied voltage and/or mounting conditions.

When the 3,000 amp “Split-Conductor” is applied the 5.2.2.1 Terminals and Shields
weight of the conductor as well as the winding leads
may make it difficult to allow vertical lift of the The following figures 5.1-5.4 show some of the many
conductor. For this reason the location of the split may different terminals and shields that are available from
need to be changed from the location indicated above. Trench for COTA bushings.
Please consult Trench on your specific requirement.

It is recommended that when selecting a “Split- Fig. 5.1 Two Hole Spade
Conductor” application for new or re-manufactured
transformers that the Trench holding tool be supplied
with the transformer. It will make installation easier and
safer for the transformer.

Tool Type Part No.


150...350 up to 1,5000 A 804-0001
150...200, 3,000 A 804-0002
250...350, 2,000 A 804-0005
550...750 up to 1,400 A 804-0002 Fig. 5.2 Four Hole Spade
900...1175 up to 1,600 A 804-0004
1300 up to 1,600 A 804-0006

8
Fig. 5.3 Thread Stud
7. R
 eceiving and
Initial Inspection
As a general rule, every bushing should be unpacked in
a dry place (shop). Once unpacked, the bushing should
be kept in a dry room and protected from atmospheric
influence.

Before unloading, complete a visual inspection of the


crate and note any apparent damage on the bill of
Fig. 5.4 Typical Shield & Terminal lading. After unloading, open the top of the crate, being
careful not to damage the porcelain and other bushing
parts, and thoroughly inspect each bushing. The
following areas should be closely examined:

•V
 isual inspection of insulator for chips cracks or other
visible damage.

•C
 heck for extensive oil traces. Small traces of oil on
the inboard end are insignificant; they occur during
factory tests prior to shipping or after factory testing
of the transformer.

Should there be any signs of damage, evidence of


rough handling in transit and/or parts shortage, contact
the carrier at once. Also notify Trench or its authorized
For additional application information on Trench COTA representative.
bushings, contact the nearest Trench factory.
For more information about unloading the bushings,
see section 9.1. Unpacking and handling.
6. P
 ackaging and We recommend not to damage or destroy the original
Transportation shipping crate(s). They may be re-used for the same
purpose when the transformer is delivered to its final
Standard shipping crates, from the factory, contain destination.
1, 3 or 4 bushings.
If it is desired to perform electrical tests on the bushing
before it is installed in the transformer refer to section
10, Commissioning for instructions.
CAUTION: When the bushing is placed in the crate
the oil level indicator must be facing down and
remain in this position whenever the bushing is in a
horizontal position. PRECAUTION: The bushing must not be tested
while still in the shipping crate and the bushing must
be in a vertical position away from other structures.
Failure to follow these precautions may result in
Factory shipping crates are marked with arrows inaccurate reading and test results.
indicating the correct orientation requirement. Each
bushing designed for vertical mounting has a special
decal on the head as a reminder.

9
8. Cleaning two passes should be made with dry clean rags.
When a compressed air-bottle is available, all grooves,
comers, drillings and other cavities should be blown off
Before mounting the bushing it should be thoroughly
thoroughly.
cleaned.
A visual control should make sure that all residues of
8.1 Cleaning medium and accessories oil, cleanser and cleaning accessories have been
removed. Including the central tube of draw lead
The following cleaning medium may be used for wiping bushings.
oil remaining on the surface of the bushing:

• Industrial or similar solvents 9. Installation


Necessary accessories: 9.1 Unpacking and handling
• Dust and lint-free rags Before lifting the bushing out of the shipping crate,
• A dust free brush or large paint brush remove all supports from above and remove the bolts
• Washing bottle connecting the mounting flange to the crate.
• Length of insulated wire or cotton cord
• Compressed dry air A crane and two textile slings are required for lifting the
• Silk Paper bushing out of the shipping crate. The following
procedure must be followed while lifting the bushing
(see figure 6.1):
8.2 Cleaning Procedure

The following areas of the bushing must receive a CAUTION: The bushing shall not be subjected to
thorough cleaning: radial rotation in the crate or after removal. The oil
level indicator shall always be facing downward. The
• The outdoor insulator bushing should be suspended with its head up. The
• The inboard insulator and metal ground sleeve if so maximum permissible inclination with the head
equipped downward is 15º as shown in figure 6.1.
• The interior of the central tube of draw lead bushings
• The bottom terminal connection surface
Draw Lead bushings may require that the “Split-
• The inside area of the voltage tap or test tap
Conductor” be installed prior to being installed into the
• The gasket surface of the mounting flange
transformer. In this case the bushing should be
• The gasket surface of the bolted top terminal on draw
positioned horizontally outside of the crate, with the oil
lead bushings
level indicator facing downward, as shown in figure 6.1.
• The oil level indicator sight glass
The maximum rotation tolerance is +30º, as shown in
Detail A. No additional radial rotation is permitted.
The insulator and metallic parts are to be wiped with
the specified rags with the indicated cleanser. Grooves, The “Split-Conductor” must be reassembled prior to
corners and drillings or any other cavities are to be being installed into the bushing. Once assembled
rinsed with the washing bottle or the recommended carefully insert the “Split-Conductor” into the bushing
brush or paint brush. from the bottom following the instruction detailed later
in this section.
Remaining residues, possible lint or hairs should be
wiped off by a final cleaning. To place the bushing in the vertical position:
The insulator and the metallic parts should be For COTA 150 and COTA 350 bushings, which are not
eventually wiped with a clean silk-paper. heavy, this is possible with only one sling. Attach the
sling under the uppermost shed around the insulator.
A rag soaked with the available cleaning medium
As you lift the bushing, hold the lower end with one
should be attached to one end of the wire or cord and
hand so that the bushing does not touch the ground
the other end drawn through the central tube of the
while it is moving to the vertical position. For putting
bushing (draw lead bushings only). Pull the rag, one
COTA 550 and above bushings to the vertical position,
direction only, through the tube several times. The last
one crane and one hoist is necessary because the
bushings are very heavy.
10
Fig. 6.1

The basic procedure with crane and hoist is as follows Lift the bushing high enough to ensure that it will not
(see figure 6.2): touch the ground when it is moving to the vertical
position. Actuate the hoist until the bushing is
Attach one end of each sling to each of the two lifting positioned vertically. Check the oil level as described in
lugs on the mounting flange. Attach the free ends to section 11.1 "checking the oil level".
the bottom of the hoist. Attach the hoist to the crane
hook. Adjust the hoist to ensure that the crane's If the bushing is to be installed vertically (no inclination),
boom will be long enough to let down the bushing to no further adjustments are necessary. It can be moved
the vertical position. to the transformer for installation.

Attach two guide slings around the outdoor insulator If the bushing is to be installed at an inclination (≤ 40º),
between the head and the uppermost shed. the following considerations must be done.

Attach two more long slings to the crane hook. Draw If the oil level indication over the entire operating
the free ends of the slings through the guide slings temperature range is desired, the oil level indicator
and then attach them to the lifting lugs on the must face to the side.
mounting flange using shackles.
Other installation positions with the oil level indicator
Adjust the suspension equipment to ensure that the facing down are acceptable under certain conditions.
bushing will remain in the horizontal position with the Such installations may allow only minimum oil level
oil level indicator facing downward during lifting. If the monitoring. Installation positions in which the oil level
bushing is inclined during lifting, the head must be in indicator faces up are never permitted. To install the
the highest position. bushing at an inclination (≤ 40º) with the oil level
indicator facing to the side, the following procedures
must be followed (see figure 6.3):

11
Fig. 6.2

For bushings COTA 150 through COTA 350, the The bushing can now be moved to the transformer for
inclination can be adjusted by hand because the installation.
bushings are not heavy. It is not necessary to change
the slings after lifting. For bushings COTA 550 and Bushings designed for horizontal mounting require the
above the following points must be followed: following installation procedures.

•P
 osition the bushing vertically in a frame or in a cavity •B
 ushing must be in a vertical position for a minimum
with its mounting flange resting on a soft surface. 4 hours then gradually tilted to the horizontal position
before mounting in the transformer. Care should be
•R
 emove the shackle connection, which were taken with the sight glass location.
positioned downward if the bushing is inclined.
•T
 here are two considerations to be made when
•R
 emove both slings connecting the bushing to the positioning horizontally mounted bushings on the
hoist. A single sling through both lifting lugs and transformer. First is to maintain the functionality of the
around the body of the mounting flange will be used oil level indicator. Second is the ability to visually see
to attach the bushing to the hoist. the oil level indicator from the ground. Take these
considerations into account before applying slings.
•N
 ow lift the bushing carefully. Set the desired
inclination by adjusting the hoist. •W
 hen these bushings are mounted horizontally on
the transformer sidewall the oil level indicator should
be positioned so that the indicator is located at the
highest point on the side of the bushing head.

12
Fig. 6.3

•W
 hen these bushings are mounting vertically on the The transformer and bushing mounting flange should
transformer cover the oil level indicator should be be clean and free of foreign material with the gasket
orientated so that the indicator can be viewed from in place before the bushing is set. After the bushing
the ground. has been set in place on the mounting flange install all
the washers and bolts until finger tight. Then tighten
•A
 ttach the sling between the two lowest sheds of the the bolts a fraction of a turn at a time, working
outdoor insulator. As you lift the bushing, hold the progressively in a crisscross (star) pattern until all bolts
inboard end with one hand to balance the bushing. are uniformly tight.
Now install the bushing into the transformer. Be
careful not to drag or bang the inboard end on the
mounting flange while it is moved into the transformer
Typical Torque Values
sidewall.
Bolt Size Foot pounds Newton meters
9.2 Bolting to the transformer 1/2” – 13 threads 35 47
5/8” – 11 threads 65 88
The following instructions are only valid when the 3/4” – 10 threads 100 135
gasket between the bushing and the transformer-
1” – 8 threads 260 352
mounting flange is a 0-Ring. For flat gaskets, the
instructions are valid if the mounting flange is equipped 1 1/8” – 8 threads 260 352
with a mechanical gasket stop. For all other
arrangements, the torque requirement depends on the
type of gasket system used. Trench takes no Trench recommends washers when bolting the bushing
responsibility for damage caused by over torque in to the transformer.
other arrangements.

13
9.3 External electrical connections
CAUTION: Do not attempt to rotate the top
External connections to the bushing must be sufficiently terminal. The top terminal itself is not threaded to
slack or flexible to avoid putting a mechanical strain on the draw lead cable terminal or the top of the
the bushing parts. Terminal connectors should be of “Split-Conductor”.
ample size to minimize bushing overheating during
possible overloads. For the procedure to reassemble the top terminal after
draw lead cable or “Split-Conductor” installation, see
Ridged buss connection to bushings is not sections 9.4.2.
recommended in areas of seismic concern and
because of transformer tank flexing during vacuum 9.4.2 Draw lead cable connection
filling operations.
COTA draw lead bushings are designed with a hollow
9.4 Connection to transformer tube through which the flexible draw lead cable(s) can
be pulled. The cable is considered a component of the
9.4.1 Top terminal assembly transformer and is not supplied as part of the bushing.

The typical top end of a COTA draw lead bushing is For new transformers there are two ways to connect a
shown in figure 7. If the bushing is applied with draw draw lead cable terminal to the transformer cable,
lead cable(s) or a “Split-Conductor” the top terminal has crimping or brazing. Trench makes no endorsement on
to be removed. If the bushing is equipped with a “Split- which method used. It is entirely up to the transformer
Conductor” and is replacing a bottom connected manufacturer and their customer. However, brazing the
bushing there is no need to remove the top terminal. cable to the terminal requires special care to avoid
effecting the silver-plating that provides the high current
To remove the top terminal the procedure is as follows: interface between the draw lead cable terminal and the
multiple spring contacts in the bolted top terminal.
Remove the four fixing screws. The terminal can be
pulled off axially using a force of approximately 44 lb.
(200 N).
CAUTION: When brazing, the temperature at the
current interface should not exceed 650º C.
The bolts, cone spring washers and the 0-Ring gasket
must be stored in a safe place.

If lifting off the top terminal is difficult, use two of the The selection of the draw lead cable terminal for the
bolts removed and thread them into the two threaded specific connection method and size cable is covered
holes as shown in figure 7. By tightening the bolts by the technical ordering data in section 5.
into these holes the top terminal will become lose and
further removal by hand will be possible.
CAUTION: Once the draw lead cable terminal has
been attached and before it is installed in the
Fig. 7
bushing it must be protected from damage to the
contact surface. If it becomes damaged it will have
to be replaced

After mounting the bushing on the transformer, secure


the draw lead cable terminal with the retaining pin and
locking device. The retaining pin must pass through the
corresponding hole in the central tube of the bushing.
Install the 0-Ring and place the top terminal over the
draw lead cable terminal. Fasten the top terminal to the
head with the four screws and cone spring washers
provided (torque = 15 ft. lb. /20 Nm).

14
When the bushing is installed on the transformer, the
optional (Standard on COTA 1050 and above) air CAUTION: Once the lower end of the “Split-
escaping screw (7.4 ft. lb./10 Nm) located on the top Conductor” has been attached to the winding lead and
terminal can be used for the air release while oil filling before it is installed in the bushing the split joint must
the transformer. This option is recommended when be protected from damage to the contact surface. If it
bushings are installed on transformers with conservator becomes damaged it will have to be replaced.
type oil preservation systems.

9.4.3 “Split-Conductor” connection 9.5 “Split-Conductor” installation


When the applied current exceeds the rating of draw The “Split-Conductor” joint is designed to be located
lead cable(s), the COTA bushing can be supplied with 1/2” (12.5 mm) below the gasket surface of the
Trench's "Split-Conductor". The “Split-Conductor” is an bushing mounting flange. (For 3,000 amp “Split-
accessory supplied by Trench as part of the bushing. Conductors” the split may have a different location.
The “Split-Conductor” can be removed from the Refer to the outline drawing of the bushing to confirm
bushing for connection to the transformer winding lead location.) Because of the limited space of the mounting
or installed in the bushing and connected to the flange inside diameter on bushings through 69 kV it is
winding leads after the bushing has been installed in necessary to lift this joint above the gasket surface of
the transformer the mounting flange and hold the conductor in this
position during assembly of the “Split-Conductor”.
If the “Split-Conductor” has been shipped separately Trench has designed a tool for holding the conductor in
from the bushing and the bushing is to be installed place. If not available a hardened steel rod, 1/4” (6 mm)
with the “Split-Conductor” in place the following must in diameter, 12” (300 mm) long can be used. If a rod is
be done: used, extra care must be taken to avoid dropping any
Installing the “Split-Conductor” is done with the hardware into the transformer tank.
bushing in a horizontal position with the oil level
indicator facing down. Installation steps:

First remove the top terminal. Carefully slide the top of •P  repare the bushing for installation by removing the
the “Split-Conductor” into the bottom of the bushing top terminal and retaining pin with locking device,
until the upper end extends beyond the central tube. then place a cord or wire through the central tube of
Care should be taken not to scratch the “Split- the bushing.
Conductor” or the central tube of the bushing during • Locate the upper part of the “Split-Conductor”, which
installation. should be located in the crate with the bushing or it
may have been installed in the bushing during
Next install the retaining pin with locking device and transport. At the top end of the upper part of the
re-install the top terminal. The locking pin rests on the “Split-Conductor” you will find a 5/16” - 18 UNC
top of the central tube, not through the hole used for tapped hole. Install an eye bolt into the hole for
draw lead. This allows the “Split-Conductor” to rotate attachment of the cord or wire from the bushing.
for easy alignment inside the transformer. Then install
the bushing in the transformer and make the
connection to the bottom of the bushings in the same CAUTION: Care must be taken to protect the
manner as a COTA bushing with a fixed conductor. contact surfaces at both ends of upper part of the
“Split-Conductor”. If it becomes damaged it will have
The other method is to separate the “Split-Conductor” to be replaced
at the joint, take the lower end with the bottom terminal
and make the connection to the transformer active part
winding lead. Then re-connect the upper part of the •R
 emove the hardware from the bushing flange
“Split-Conductor” as shown in figure 7.0 when ready to shipping cover and lift the cover 6” (150 mm). The
install the bushing. Use only the screws and washers lower end of the “Split-Conductor” will be attached to
provided with the Split-Conductor. the underside of the shipping cover. The lower end of
the “Split-Conductor” will weigh between 5.7 and 7.5
kg (12.5 and 16.5 lb.) and will be connected to the
transformer winding lead, adding additional weight.

15
Fig. 8 Split Conductor Assembly

•W
 ith the shipping cover lifted install the Trench •A
 ssemble the upper part of the “Split-Conductor”
holding tool (or steel rod) using the small through hole using the hardware used the secure the shipping
located 1/2” (12.5 mm) below the joint of the “Split- cover. Torque the cap screws to 17 ft. lb. (23 Nm).
Conductor”.
•A
 ttach the cord or wire, which exits the lower end of
•W
 ith the lower end of the “Split-Conductor” the bushing, to the lifting eye previously installed to
supported remove the hardware that attaches the the top of the Split-Conductor.
shipping cover to the “Split-Conductor”. This will be
the same hardware that will be used to assemble the
upper part of the “Split-Conductor”. An 8 mm or CAUTION: When handling the bushing in a horizontal
5/16” Allen wrench can be used to remove the cap position make sure that the oil level indicator is
screws. always facing down to prevent the gas in the head
from entering the condenser part of the bushing.
CAUTION: if the steel rod is used care must be taken
not to drop any hardware into the transformer tank.

16
•B
 egin to install the bushing over the “Split-Conductor” 9.6 Fixed conductor installation
while pulling on the cord or wire. As the bushing is
being lowered over the “Split-Conductor” align the oil Bottom connected bushings with a fixed conductor are
level indicator to the desired final position. designed for highest current ratings. They carry the
current through the center conductor that is not
•A
 s the bushing lower end approaches the Trench removable. It is not necessary to remove the top
holding tool (or steel rod) remove the holding tool (or terminal on such bushings. The connection to the
steel rod). At this point the full weight of the “Split- winding leads depends on the design of the
Conductor”, between 11.2 and 17.5 kg (24.6 and transformer.
38.5 lb.), will be supported by the cord or wire. The
“Split-Conductor” must not be allowed to drop into
the transformer tank. 10. Commissioning
•C
 ontinue lowering the bushing, while pulling on the 10.1 General check
cord or wire until the bushing rests on the mounting
flange. With the “Split-Conductor” still supported by The following procedures must be completed before
the cord or wire install the retaining pin with locking placing the bushing under voltage:
device through to small hole near the top of the
“Split-Conductor”. •C
 heck the oil level (see section 11.1, "Checking the
oil level").
•S
 ecure the bushing to the mounting flange and install
the top terminal to the head using the four screws •W
 ait at least 24 hours after the bushing has been
and washers provided. Torque to 15 ft. lb. (20 Nm). placed in the vertical position before applying voltage.

•P
 ower factor and bushing capacitance measurements
CAUTION: For “Split-Conductor” applications, the can be made for comparison with subsequent field
retaining pin does not pass through the measurements.
corresponding hole in the central tube of the
bushing. The retaining pin with locking device will 10.2 Test tap
rest on top of the central tube, supporting the “Split-
Conductor” during service. Bushings for insulation class of 69 kV and lower are
provided with a test tap. The test tap shown in figure
9.0 is located just above the mounting flange and
After the bushing has been installed in the transformer, provides measuring power factor and capacitance of
the optional air escape plug (7.4 ft. lb./10 Nm) located the bushing. In order to connect to the test tap, remove
on the top terminal can be used for air release while the threaded cap and connect the lead of the power
filling the transformer. factor with the measuring equipment. After the
measurement has been completed, re-assembling the
If the “Split-Conductor” is delivered installed in the sealing cap (torque = 15 ft. lb./20 Nm). This will ground
bushing and it is to be removed, the following should the test tap for proper operation of the bushing.
be done:

With the bushing in a horizontal position with the oil CAUTION: There is a high voltage output if the test
level indicator facing down, remove the top terminal. tap is not grounded. Always keep it grounded with
With the top terminal removed, remove the retaining pin either an over-measuring circuit, sealing cap or
and carefully pull the ”Split-Conductor” from the bottom grounding link.
of the bushing. Caution must be used in removing the
“Split-Conductor”, as it can be heavy and as long as
the bushing. Care must also be taken not to scratch The test tap can withstand a power frequency voltage
the “Split-Conductor” or the central tube of the test of 2 kV. Many bushing users measure the power
bushing. factor and the capacitance of the bushing as a field
test. For more information on this practice, refer to
section 11, "Maintenance".

17
Fig. 9 COTA 150…COTA 350 Test tap Fig. 10 COTA 550 and above Voltage Tap

Sealing cap Oil plug


Sealing cap

10.3 Voltage tap 11. Maintenance


Bushings for insulation class of 115 kV and higher are
Under normal operating conditions Trench type COTA
provided with a voltage tap. The voltage tap shown in
bushings require no maintenance. As a guideline the
figure 10.0 is located just above the mounting flange
following routine checks can be performed.
and can be used for connecting voltage measuring
equipment (e.g. a bushing potential device) or for
measuring the power factor and capacitance of the 11.1 Checking the oil level
bushing. In order to connect the tap outlet, remove the
sealing cap and connect the measuring equipment. Trench COTA bushings covered by this instruction
manual have prismatic glass oil level indicators. As long
If a bushing potential device is connected, remove the as oil is visible within the view of the prismatic glass oil
oil plug and fill the cavity with clean, dry transformer oil. level is within acceptable limits. This rule is valid for all
To permit oil expansion, allow a 5/8" (16 mm) clearance acceptable mounting positions up to a 40º inclination
between the seal and the surface of the oil. Then from vertical.
replace the plug and gasket with a torque of 7.4 ft. lb.
(1O Nm). CAUTION: If the oil level is at the bottom of the oil
level indicator, it indicates a low oil level. The bushing
Under these conditions, the voltage tap will withstand a must be taken out of operation immediately. No
20 kV power frequency voltage test. voltage may be applied to a bushing under such
conditions due to the danger of explosion. Check
It is not necessary to fill the cavity with oil for power the bushing for leaks and contact Trench.
factors or capacitance measurement devices below
10 kV.

After the measurement has been completed, 11.2 PF and capacitance measurement
re-assemble of the sealing cap (torque = 30 ft. lb./40
Nm) This will ground the voltage tap for proper Field measurements of power factor and capacitance
operation of the bushing. can differ from measurements made under the
controlled conditions in the factory. The bushing power
factor and capacitance should be measured at the time
CAUTION: There is a high voltage output if the of commissioning and these values should be used as
voltage tap is not grounded. Always keep it a base to compare future measurements.
grounded with either an over-measuring circuit,
sealing cap or grounding link. Please contact Trench should:

As mentioned in section 11.1 many bushing users •T


 he power factor doubles from the original
measure the power factor and the capacitance of the commissioning value.
bushing as a field test. For more information on this
practice, refer to Section 11, "Maintenance". •T
 he capacitance increases to 110 % of the original
commissioning value.

18
factory shipping crate is not available the bushing must
CAUTION: These measurements may only be be stored upright in a suitable support frame. The
performed when the bushing is not in operation. preferred storage location is indoors, however, if indoor
Removing or replacing these caps under voltage is storage is not available, the bushing may be stored
strictly prohibited: Dangerous high voltage! outdoors for short periods of time. If stored outdoors, it
is highly recommended to enclose the inboard end of
The test or voltage tap sealing cap must be screwed on the bushing in protective plastic to prevent
tightly during operation with the following torque values: contamination of this side of the bushing.

COTA and COBA bushing inboard ends are susceptible


• Test tap sealing cap: 15 ft. lb. /20 Nm
to UV de-coloration when stored outdoors unprotected.
• Voltage tap sealing cap: 30 lb. /40 Nm.
Extensive testing has shown that prolonged exposure,
more than 10 years, can damage this component of
11.3 C2 Measurements 69 kV Class
the bushing. Shorter periods of exposure will not effect
and below.
the functionality of the bushing but may change its
Trench has conducted extensive investigations into the appearance. Should this occur treat the insulator with
phenomenon of erratic C2 and PF field measurement ethanol and a Scotch-Brite pad to restore the original
on new Trench bushings, 69 kV and below. From the appearance.
results of this investigation Trench has determined,
without exception, that when the C1 and PF are as
indicated on the nameplate that the bushing is in good 13. After Sales Service
working condition and fit for a lifetime of trouble free
Should any malfunction occur with a COTA or COBA
service.
bushing, inform Trench or its authorized representative.
Include with your report complete identification of the
11.4 C2 Measurements 115 kV Class bushing, including serial number, type designation and
and above. nature of malfunction. This report must be in writing.
Erratic field measurements of the C2 capacitance on
bushings 115 kV and above have been reported to
Trench. In these cases one or more of the following
14. Draw Lead Adapters
situations existed, that when corrected, brought the When selecting Trench COTA bushings as replacements
measured values back in line with the nameplate value. for other brands of draw lead bushings it will be
necessary to apply a Trench draw lead adapter. For
•T  he bushing was not vertical with the inboard end most applications a thread-on type adapter can be
resting within the shipping crate. applied.
• The leads connected to the test equipment were
long and not calibrated for the length.
• The test voltage was below 1 kV.
14.1 Instructions
• The bushing was tested near a steel reinforced The following instructions are offered for use when
concrete column or concrete floor. applying the thread-on adapter: Before beginning the
• The voltage tap compartment was contaminated installation refer to the preceding instruction in this
with moisture. manual pertaining to the new COTA bushing.

11.5 Units with Oil Sampling Valve 14.2 Measuring


Contact Trench prior to taking an oil sample. Before removing the old draw lead bushing it is
recommended that the amount of slack in the draw
lead cable be measured. This is accomplished by
12. Storage pulling up the draw lead terminal by hand to determine
the amount of slack that may exist. Note that in many
Storage practices for COTA bushings depend on where
cases there may not be any slack. Take note of the
stored and for how long. It is always preferable to store
approximate slack or lack of slack that is present, this
the bushing horizontally in its original factory shipping
information will be used when the new Trench COTA
crate, regardless of storage duration. If the original
bushing is installed.
19
14.3 Inspection 15. Technical Ordering
After removing old draw lead bushing inspect the draw
lead cable insulation for any signs of burning or over
Data
heating. If there are indications of burning or over
Trench has developed a technical ordering data system
heating you should note this condition, as it may be an
that is “user friendly”. It is designed to allow you to build
indication of severe overload or of an inadequately
your own bushing from a selection of standard
sized draw lead conductor. If this condition exists,
accessories and options that meet your specific
consider replacing the insulation with a high
application requirement.
temperature, class F, insulation material.
The technical ordering data system is made from three
14.4 Installation
components, the bushing Type, the bushing Style
With the existing threaded draw lead terminal held away number and the bushing Options. At the end of this
from the bushing opening on the transformer cover, section are Code tables that list the available options.
install the lock nut supplied with the adapter. The lock
nut must be threaded all the way onto the old threaded 1. Type Code
draw lead terminal.
COTA, which stands for Condenser Oil Transformer
Thread the female end of the draw lead adapter onto bushing designed according to ANSI Standards. COBA,
the existing threaded draw lead terminal until it is tight. which stands for Condenser Oil Breaker bushing
Then tighten the lock nut against the adapter using designed according to ANSI Standards. The type is
wrenches on the flats of the lock nut and adapter. always at the beginning of the technical ordering data.

With the draw lead adapter installed you can now install 2. Style Number
the new Trench COTA bushing following the instructions
in this manual. The style number is made up seven sets of numbers
and/or letters that will provide specific information about
Before installing the retaining pin in the Trench draw the specific bushing.
lead terminal again determine the amount of slack in
the draw lead cable. It should be the same as when
checked before the old bushing was removed. If there COTA __ __ __ - __ __ __ __ - __ __ - __ __ __ - __ __
is more than 2 inches (50 mm) of additional slack or if it Set 1 2 3 4 5 6 7
takes a large amount of force to pull the terminal to the
top of the bushing during the last few inches, it is
recommended to stop and contact Trench. Applying The first set of numbers states the BIL (Basic Insulation
too much force in pulling up the draw lead cable may Level) of the bushing. The table for Code 1 lists the
damage the transformer. standard BIL available.

The next set of 1 letter and 3 numbers, state the


CAUTION: The above instructions do not cover all maximum through current rating of the bushing. The
possible conditions that can arise when replacing old letter designates the current path option, F for fixed
draw lead bushings. Trench assumes no responsibility conductor or H for draw lead. The numbers designates
for any damage or failure, which would result from the maximum through current for the bushing X100.
conditions not known to Trench or by materials not (Example 015 = 1,500 amperes) A listing of available
furnished as part of the Trench bushing. ratings is listed in the table for Code 2.

The next set of numbers designates the CT pocket


14.5 Other adapter types length. The CT pocket is the space, just below the
There may be some instances that a Trench thread-on mounting flange of the bushing, provided by the last
adapter can not be applied. In those cases an adapter grounded foil layer of the bushing’s active apart. The
will be provided by Trench, which will require cutting off table for Code 3 lists the available CT pocket lengths
the old draw lead terminal. If this type of adapter is by style.
required Trench will provide detailed instructions to
perform the installation.

20
The next letter designates the mounting flange CODE 2, Maximum Current Ratings
configuration. The IEEE/ANSI Standards dictate the ODE
C DESCRIPTION
mounting flange arrangements for most bushings,
H014 1,400 A, 250….1175
however, there are a number of exceptions that must
be considered when applying bushings as H015 1,500 A, 150…200
replacements. The table for Code 4 will provide specific H016 1,600 A, 900…1300
letter code designations for each available mounting H020 2,000 A, 250…350
flange configuration by bushing style. H030 3,000 A, 150…200
F020 2,000 A, 150…2050
The next letter designates the outdoor insulator material F023 2,350 A, 200
and color. There are 3 options available for the outdoor
F027 2,700 A, 150
insulator and are listed in the table for Code 5.
F030 3,000 A, 150…2050
The next number designates the outdoor insulator’s F050 5,000 A, 150…900
creep distance in accordance with the four F075 7,500 A, 150…200
contamination levels as described in the IEEE Guide for F100 10,000 A, 150
Application of Power Apparatus Bushings, C57.19.100. F125 12,500 A, 150
The table for Code 6 list the 4 options.
CODE 3, CT Pocket Length
The last set of numbers is the Trench factory code ODE
C DESCRIPTION
designation that determines a specific bushing’s
10 10” CT Pocket (Special)
compatibility with other bushings within the same
rating. 16 16.5 “ CT Pocket (Special)
21 21” CT Pocket (Std. 150…350)
3. Options 23 23” CT Pocket (Std. 550….2050)
26 26.75” CT Pocket (Special)
The last sets of letters are the Option Codes. The 27 27” CT Pocket (Special)
option codes are the accessories that are added to a
basic bushing to suit the specific requirement or CODE 4, Mounting Flange Configuration
application. These option codes will appear on the
CODE kV Class Amps Flange
bushing nameplate as part of the serial number and will
appear on the bushing outline drawing. The specific A 25 1,500 7¼” – 4 HOLE
outline drawing number will appear on the bushing A 34.5 1,500 7¼” – 4 HOLE
nameplate. There are presently 4 sets of options B 25 3,000 7¼” – 4 HOLE
available for Trench bushings. B 34.5 3,000 7¼” – 4 HOLE
C 25 3,000 8¼” – 4 HOLE
CODE 1, Basic Insulation Levels C 34.5 3,000 8¼” – 4 HOLE
D 25 3,000 9¼” – 6 HOLE
ODE
C DESCRIPTION
D 34.5 3,000 9¼” – 6 HOLE
150 25 kV, 150 kV BIL
A 35.5 5,000 14 ¼” – 9 HOLE
200 34.5 kV, 200 kV BIL A 46 2,000 8¼” – 4 HOLE
250 46 kV, 250 kV BIL A 46 3,000 9¼” – 6 HOLE
350 69 kV, 350 kV BIL A 69 2,000 9¼” – 6 HOLE
550 115 kV, 550 kV BIL A 69 3,000 10 ¼” – 6 HOLE
650 138 kV, 650 kV BIL E 69 3,000 10.88” – 6 HOLE
750 161 kV, 750 kV BIL A 115 3,000 13¼” – 6 HOLE
900 230 kV, 900 kV BIL A 115 3,000 13¼” – 6 HOLE
1050 345 kV, 1050 kV BIL A 138 3,000 14¼” – 6 HOLE
A 138 3,000 14¼” – 6 HOLE
1175 345 kV, 1175 kV BIL
A 161 3,000 15¾” – 8 HOLE
1300 345 kV, 1300 kV BIL
A 230 5,000 21” – 12 HOLE
1550 500 kV, 1550 kV BIL A 345 3,000 21” – 12 HOLE
1675 500 kV, 1675 kV BIL A 500 3,000 25” – 12 HOLE
1800 500 or 765 kV, 1800 kV BIL F 500 3,000 31” – 16 HOLE
2050 756 kV, 2050 kV BIL A 765 2,000 35” – 16 HOLE
21
CODE 5, Outdoor Insulator OPTION CODE 9, Bottom Terminal
CODE DESCRIPTION when Ordering Code 10 = P, Plate (Breaker)
G #70 Gray Porcelain CODE DESCRIPTION
B Brown Porcelain D IEEE/ANSI FIG. 3.4
C #70 Gray Silicone Rubber E IEEE/ANSI FIG. 3.5
F IEEE/ANSI FIG, 3.6
CODE 6, Minimum Insulator Creep Distance Z Special Plate
CODE DESCRIPTION
1 28mm/kV* (optional) OPTION CODE 9, Bottom Terminal
2 35mm/kV* (optional) when Ordering Code 10 = S, Spade
3 44mm/kV* (standard) CODE DESCRIPTION
4 54mm/kV* (optional)
Y 2 Hole Spade
X 4 Hole Spade
OPTION CODE 8, Top Terminal Plating Z Special Spade
CODE DESCRIPTION
A Silver Plated OPTION CODE 10
T Tin Plated CODE DESCRIPTION
N No Plating P Bottom Terminal is a Plate
R Crimp Type Draw Lead Terminal
OPTION CODE 9, Draw Lead Terminal S Bottom Terminal is a Spade
when Ordering Code 10 = R, Crimp Type T Bottom Terminal is a Threaded Stud
CODE DESCRIPTION CABLE SIZE mm_ W Braze Type Draw Lead Terminal
H ID = 0.433" 1/0 50 Z Special
J ID = 0.500" 2/0 70
K ID = 0.625" 4/0 95
L ID = 0.720" 300 KCMIL 150 OPTION CODE 11 & 12 (For future use)
N ID = 0.830" 400 KCMIL 185
O ID = 0.925" 535 KCMIL 395 Code Z indicates something special is required. If a
Z Special Specify specific requirement is not covered by the above codes
the letter Z can be used in the option code. The
required special option or accessory must be fully
OPTION CODE 9, Draw Lead Terminal
detailed and be reviewed by Trench before an order is
when Ordering code 10 = W, Braze Type
accepted. If a Z option code does not appear in a
CODE DESCRIPTION specific option code table there can not be a special
M 0.315" Pilot Hole requirement for the option or accessory.
P Spade
If a bushing is ordered with or without a draw lead
Z Special Size
terminal, option codes 9 and 10 will not appear on the
outline drawing. The draw lead terminal option codes
OPTION CODE 9, Bottom Terminal will appear on the order acknowledgment if ordered
when Ordering Code 10 = T, threads with the bushing.
CODE DESCRIPTION
If a bushing is ordered with a draw lead adapter then
X 1 1/2" - 12 UNF Threads codes 9 and 10 will be Z. The Z will not appear on the
K 2" - 12 UNF Threads outline drawing for that bushing.
L 3" - 12 UNF Threads
Z Special Threads A special paint color on the bushing head would appear
as a Z in ordering code 11 and then be assigned a
specific option code for the color.

22
Notes

23
Trench Facilities

Trench® Austria GmbH Trench® Limited


Paschinger Strasse 49 Instrument Transformer Division
Postfach 13 390 Midwest Road
A-4060 Linz-Leonding Scarborough, Ontario
Austria Canada M1P 3B5
Phone: 43-732-6793-0 Phone: 416-751-8570
Fax: 43-732-671341 Fax: 416-751-6952

Trench® Brasil Ltda Trench® Limited


Via Expressa de Contagem, 2685 Power Line Carrier Division
Contagem, Minas Gerais 815 Middlefield Road, Unit 6A
CEP 32370-485 Scarborough, Ontario
Brazil Canada M1V 1R9
Phone: 55-31-3391-5959 Phone: 416-291-8544
Fax: 55-31-3391-1828 Fax: 416-291-5581

Trench® China Trench® France S.A.


MWB (Shanghai) Co., Ltd. 16, Rue du Général Cassagnou
No. 3658, Jiancheng Road B.P. 70 F-68 302
Minhang, Shanghai St. Louis, Cedex
The Trench Group is your Peoples Republic of China France
200245 Phone: 33-3 89-70-2323
partner of choice for electrical Phone: 86-21-54720088 Fax: 33-3 89-67-2663
Fax: 86-21-54723118
Trench® Germany GmbH
power transmission and Trench® Fushun Nürnberger Strasse 199
Dong Er Dao, Shuncheng District D-96050 Bamberg
Fushun, Liaoning Province Germany
distribution solutions today; Peoples Republic of China Phone: 49-951-1803-0
113126 Fax: 49-951-1803-224
Phone: 86-413-7644009/7644007
and for the development of Fax: 86-413-7641423 Trench® Switzerland AG
Lehenmattstrasse 353
Trench® Limited CH-4052
your new technology solutions Bushing Division Basel
432 Monarch Avenue Switzerland
of tomorrow. Ajax, Ontario Phone: 41-61-315-51-11
Canada L1S 2G7 Fax: 41-61-315-59-00
Phone: 905-426-2665
Fax: 905-426-2671 Trench® (UK) Limited
South Drive
Trench® Limited Hebburn
Coil Product Division Tyne & Wear
71 Maybrook Drive NE 31 1 UW
Scarborough, Ontario Phone: 44-191-483-4711
Canada M1V 4B6 Fax: 44-191-430-0633
Phone: 416-298-8108
Fax: 416-298-2209

www.trenchgroup.com
Bulletin E8322.72
Subject to change without notice (07.2007)
Printed in Canada.

S-ar putea să vă placă și