Documente Academic
Documente Profesional
Documente Cultură
Abstract: This paper describes a Monte Carlo simulation approach to overall distribution system
reliability worth assessment and illustrates it by application to the distribution systems of all the five
load buses associated with a complex test system. The paper presents the results of a series of
simulations studying the impacts of various probability distributions for restoration times on the two
reliability worth indices, namely load point expected cost (ECOST) and interrupted energy assessment
rate (IEAR). Different radial system operating philosophies are incorporated and their impacts are
analysed. Furthermore, the contributions from radial segment and subtransmission failure modes,
such as fxst-order active failures, first-order total failures and all the possible second-order
overlapping failures, to overall distribution worth indices are analysed. AU the mformation generated
by the simulation studies can provide useful reference to the electric power utilities and planners in the
decision-making stage.
536 IEE Proc.-Gener. Transm. Distrih., Vol. 146, No. 5. September 1999
repair, time to switching and time to reclosure are assumed which have no transformer, the component repair time and
to be exponential in a Markov system. Transition rates are switching time are much smaller and the effect of the non-
constant, which implies that the time duration spent in the linearity of SCDF is relatively small. Therefore, their IEAR
state is exponentially distributed. But in reality, the assump- obey similar changing patterns for various restoration time
tion of exponential state residence times may be invalid for probability distributions.
many restorable components. The time to failure can in
many cases be considered exponentially distributed but the
time to restore (repair, switching and reclosure) cannot be 90
assumed to be exponentially distributed [3, 61. Therefore,
there is a need to investigate the impacts of various distri- 70
butions of restoration times on load point ECOST and
IEAR. k
\
60
Exponential, normal, lognormal and gamma distribu- 50
tions are the four important distributions in reliability eval- I-
In LO
0
uation [3]. Six combinations of repair time and other 30
restoration time (switching time and reclosure time) distri-
butions were studied and are described in ths paper, whch 20
were also chosen by many researchers [3, 71. It must be 10
clearly emphasised that any nonexponential probability dis- 0
tribution could have been easily selected for the simulation cosel case2 cose 3 coseL cose 5 cose 6
a
studies. However, only a few selected probability distribu-
tions were used to describe the restoration times (switching/
25
repairheplacement), as these have been widely used in the m
reported literature [3]. Only scheduled maintenance outage
is not a random event. In addition, the times to failure of
all components were assumed to be exponentially distrib-
uted because the components operate in their useful or
operating life periods. These six cases are listed as follows:
repair time other restoration time
Case 1: exponential exponential
c o s e l cose 2 case3 cose L cose 5 c a s e 6
Case 2: exponential lognormal b
Case 3: lognormal exponential bus3 LP27(o)
bus2. L p 1 bus3.LP27 [ X I b u s ~ ; ~ p 1 6 ( b )
Case 4: gamma, exponential 0bus 1,LP16 bus 5 , LP17 bus 6, LP18
Case 5: normal lognormal Fig. 1 Loadpoint ECOST & IEAR ofloarlpointswhich have trmformers
a ECOST
b IEAR
Case 6: lognormal lognormal
The results of load point ECOST and IEAR due to overall
distribution system outages for all the five load buses of the
RBTS for all these six combinations are shown in Appen- n
dix C.l of [8]; the results of selected load points in the L 12
RBTS are shown in Figs. la, lb, 2a and 2b. %
sunilar and comparable for all the six cases. This suggests I
Y
6 '
that for such load points, IEAR is a relatively stable index w
and it is possible to use case 1 to represent other cases. 2
The difference between the changing law of ECOST and
0 9,
IEAR is due to the nonlinearity of SCDF. For those which
c a s e 1 cos1 ! c a s e 3 cos1 l case5 cose6
have transformer, the transformer repair time (200h) is b
large and it may result in a very large SCDF value. For the
load point 32 of bus 6, because there is no disconnect after bus 3, LP8 [XI bus L , L P 8 bus 6. LP15 m bus 6.LP32
line segment 44, transformer repair time of many load Fig.2 h a d p o i n t ECOST & IEAR of loadpoints which have 110 t r m f i i m -
ers mui loud point 32 of ha 6
points can affect its IEAR, which makes the effect of non- a ECOST
linearity of SCDF not obvious. For those load points b IEAR
Table 2: Overall load point ECOST and IEAR for six operating philosophies
538 IEE Proc-Gener. Trunsm. Distrib., Vol. 146, No. 5, September 1999
Table 3: Load point ECOST for selected load points
ECOST (k$/yr)
Load point
Total Active Istorder pp Pm Pt trn
7 Contributions from subtransmission system and load point ECOST, consequently reducing the correspond-
radial system ing contribution from the subtransmission system outages.
The effect of subtransmission system failures at office
The percentage contributions from the subtransmission sys- building users (bus 3 & bus 5) can also be explained due to
tem and the radial system outages to overall distribution the steep changing characteristics of the SCDF for ofice
system load point ECOST values at each customer type users.
load point are shown for the RBTS buses 2, 3,4, 5 and 6 in
Figs. 3 4 3b, 4 4 4b and 5. It can be seen from the results
that, in general, most of the cost of interruptions is due to 100 -
failures in the radial networks. Relatively speaking, the cost L
the transformers in the laterals at these load points are not resid. smoll G& I com.
included in the analyses. The transformer repair time is
very large and if its outage is included in the radial system
100 -
analysis it may increase significantly the contribution from x
L
the radial system outage to the overall distribution system 2 80-
Y
1oor
s- 60-
0
80 - z] LO-
\"
2 60-
- 20 -
-t 0~ I I
cn
0 LO- resid. smoll com.
U
W
b
20 - 0Yo Sub. % rod.
o r
resid.
I
smoll
rcorn. ,large. off.
I
Fig.4 Percenta e contributions to the overall distribution system ECOST at
h e s 2, 3, 4, 5 umf6
a Bus 2
a b Bus 4
I2Or
100-
L
\" 80-
t
Ye
,-- 60-
In
LO-
W
20 -
0 I I
IEE Proc.-Gener. Transm. Distrih., Vol. 146, No. 5, September 1999 539
The results for all the buses are summarised in Table 4, reliability worth indices and the existence of disconnects,
which shows the ECOST and its percentage contributions fuses and alternative supply can also greatly decrease the
from the subtransmission and radial segments withm the cost of customers due to overall distribution system fail-
RBTS. The statistics shown in Table 4 indicate that radial ures. Contributions from different failure outages from
system outages contribute significantly to the total load subtransmission systems and from radial systems to the
point monetary losses (more than 84.97%). The subtrans- overall distribution system worth indices are presented.
mission system failures at bus 3 and 5, however, also affect Most of the monetary losses are due to radial system out-
the total monetary losses significantly (more than 6.52%). ages, but the total failure of 138kV busbar also contributes
much towards the total losses. The information presented
Table 4: Customer load point ECOSTand its percentagecon- in ths paper can be used in making judicious planning
tributions from the subtransmissionand radial systems decisions for overall distribution systems comprising radial
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
segments and subtransmission segments.
ECOST (k$/yr)
Bus %Sub. %Rad.
Total Sub. Rad. 9 References
Bus 2 9.055E+02 3.640E+00 9.019E+02 0.40 99.60 1 DIXON, G.F.L., and HAMMERSLEY, H.: ‘Reliability and its cost
Bus 3 9.902E+02 1.489E+02 8.413E+02 15.03 84.97 on distribution systems’. International conference on Reliability of
power supply system, 1977, pp. 81-84 (IEE Conference Publication
Bus 4 8.505E+02 1.413E+01 8.363E+02 1.66 98.33 148)
2 Canadian Electrical Association, Equipment reliability information
Bus 5 1.008E+03 6.566E+01 9.419E+02 6.52 93.48 systems, ‘1990 Annual Service Continuity Report on Distribution sys-
Bus 6 5.488E+02 2.340E+00 5.465E+02 0.43 99.57 tem performance in Canadian electrical utilities’. Final Report, 1991
3 BILLINTON, R., and LI, W.: ‘Reliability evaluation of electric power
systems using Monte Carlo methods’ (Plenum Press, New York, 1994)
8 Conclusions 4 BILLINTON, R., and JONNAVITHULA, S.: ‘A test system for
teaching overall power system reliability assessment’, IEEE Trcms.
Power Syst., 1996, 11, (4), pp. 167G1676
The application of a Monte Carlo simulation technique to 5 ALLAN, R.N., BILLINTON, R., SJARIEF, I., GOEL, L., and
reliability worth assessment in overall distribution systems SO, K.S.: ‘A reliability test system for educational purposes-basic dis-
tribution system data and results’, IEEE Trans. Power Syst., 1991, 6,
of all the five load buses of the RBTS has been illustrated (2), pp. 813-820
in t h s paper. Combining the worth indices due to radial 6 BILLINTON, R., KUMAR, S., GOEL, L., CHOWDURY, N.,
segment outages with those due to subtransmission system CHU, K., DEBNATH, K., KHAN, E., KOS, P., NOWBAKHSH,
G., and OTENG-ADJEI, J.: ‘A reliability test system for educational
outages, overall distribution system reliability worth indices purposes - basic data’, IEEE Trans. Power Appar. Syst., 1989, 4, (3),
are deduced. The impacts of six combinations of probabil- pp. 1238-1244
ity distributions of the restoration times and the effects of 7 GOEL, L.: ‘Adequacy worth evaluation in electric power systems’.
PhD Thesis, University of Saskatchewan, Canada, 1991
six radial system operating philosophies on overall distribu- 8 OU, Y.: ‘Reliability worth assessment in distribution systems utilizing
tion system reliability worth indices are presented. Load Monte Carlo simulation techniques’. M.Eng thesis, School of EEE,
point ECOST and IEAR for some distributions of restora- Nanyang Technological University, Singapore, 1999
9 BILLINTON, R., and ALLAN, R.N.: ‘Reliability evaluation of
tion times are comparable with each other while others are power systems’ (Plenum Press, New York, 1996, 2nd edn.)
not. The operating philosophy of replacing the failed trans-
former with spare is the most effective way to reduce the 10 Appendix
540 IEE Proc-Gener. Trunsm. Disfrib., Vol. 146, No. 5, September 1999