NOMBRE DE LA TAREA DURACIÓN COSTO

SEMANA 1
PROYECTO DE CONSTRUCCIÓN
PRELIMINARES
Preliminares 5 $ 14,690,000 X X X X
DESMONTES Y DEMOLICIONES
Desmontes y Demoliciones 10 $ 15,898,000 X X
CIMENTACIÓN Y ESTRUCTURA
Cimentación y estructura 35 $ 126,235,000
INSTALACIÓN HIDRÁULICA AGUAS LLUVIAS Y
SISTEMA CONTRA INCENDIO
Red Sanitaria 24 $ 29,129,000
Red Aguas Lluvias 18 $ 11,096,000
Cajas de Inspección 12 $ 13,108,000
Reventilación 7 $ 9,336,000
Red Agua Fría 11 $ 36,182,000
Red Agua Caliente 11 $ 7,383,000
TOTAL $ 263,057,000
TIEMPOS DE EJECUCIÓN DE LA OBRA

SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5

X X X X X X X X

X X X X X X X X X X X X X X X X X X X

X X X X X X X X X X X X X X X X X
X X X X X X X X X X X X
X X X X X X X X X X X
X X X X X X X
X X X X X X X X X X
X X X X X X X X X X
PORCENTAJE DE EJECUCIÓN

MANA 5 SEMANA 6 SEMANA 1 SEMANA 2 SEMANA 3

100% 0% 0%

40% 60% 0%

X X X X X X X 0% 6% 17%

X X X X X X X 0% 0% 25%
X 0% 0% 6%
X 0% 0% 0%
0% 0% 0%
X 0% 0% 0%
X 0% 0% 0%
8% 6% 11%
CENTAJE DE EJECUCIÓN TOTAL PORCENTAJE
EJECUTADO
SEMANA 4 SEMANA 5 SEMANA 6

0% 0% 0% 100%

0% 0% 0% 100%

17% 17% 17% 74%

25% 25% 25% 100%


33% 33% 0% 72%
50% 50% 0% 100%
43% 57% 0% 100%
45% 55% 0% 100%
45% 55% 0% 100%
24% 26% 11% 86%
COSTO EJECUTADO

SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4

$ 14,690,000 $ - $ - $ -

$ 6,359,200 $ 9,538,800 $ - $ -

$ - $ 7,213,429 $ 21,640,286 $ 21,640,286

$ - $ - $ 7,282,250 $ 7,282,250
$ - $ - $ 616,444 $ 3,698,667
$ - $ - $ - $ 6,554,000
$ - $ - $ - $ 4,001,143
$ - $ - $ - $ 16,446,364
$ - $ - $ - $ 3,355,909
$ 21,049,200 $ 16,752,229 $ 29,538,980 $ 62,978,618
O TOTAL DE COSTO
EJECUTADO
SEMANA 5 SEMANA 6

$ - $ - $ 14,690,000
$ -
$ - $ - $ 15,898,000
$ -
$ 21,640,286 $ 21,640,286 $ 93,774,571

$ -
$ 7,282,250 $ 7,282,250 $ 29,129,000
$ 3,698,667 $ - $ 8,013,778
$ 6,554,000 $ - $ 13,108,000
$ 5,334,857 $ - $ 9,336,000
$ 19,735,636 $ - $ 36,182,000
$ 4,027,091 $ - $ 7,383,000
$ 68,272,787 $ 28,922,536 $ 227,514,349