Sunteți pe pagina 1din 21

P . J. F .

WINGATE
M.A., M.I.H . E. , Opera tion s G roup, Road Research l a boratory, Ministry of Transpo rt, England

USE OF CRITICAL PATH METHOD TO PLAN


AND CONTROL ROAD CONSTRUCTION
PROJECTS *
(Paper No . 278)

This report cOlltains a number of case studies of the use of the critical
path method for planning and programming road construction projects,
togeth er with a brief review of th e scope and limitations of CPM and its
practical app lication, eM a background to th e stlldy of its lise all such
projects.
Th e studies showed that th e general trelld amongst those /lsiJlg th e
critical' path m eth od in road constructio n schem es was away from the use
of large deta iled network diagrams necessitating computers and towards
small broadly based diagrams computed manually . Separate diagrams
were, however, extensively used to show in detail portions of projects,
such as bridges, wh ich required more d etailed planning. Som e use was
being made of the critical path m eth od for programming the planning and
design stages of projects as well as for th eir execution .
The m ethod was found to be a valuab le aid to the programming of
road construction projects pro vided its scope and limitations w ere realized.
Th is report also dis cusses possible futur e tren ds in th e lise of th e
critical path method. It suggests that, with greater ex perience of critical
path m eth od networks, planners m ay recognize th e particular advalltages
offered by computers and revert to th eir use.

INTRODUCTION of the problems involved in applying the


1. The general principles of the criti- CPM to road construction projects and an
cal path m ethod (CPM) and similar tech- evalu ation of its use, based on limited
niqu es for planning and progr amming are practical experience to date.
now widely known in this country and are 2. The report contains a brief review
being used in a variety of industries, 10- of the scope and limitations of CPM and of
eluding building and civil engineering. So its practical application as a background to
far, however, comparatively little use of the study of the particular applications to
these techniques has been made in road road construction projects.
construction projects. This may be mainly ADVANTAGES AND LIMITATIONS OF THE
due to a general feeling that such projects CRITICAL PATH METHOD
do not lend them selves to the rather pre- 3. There are two main stages in carry-
cise mathematical solutions produced by ing out a project: the planning of the
CPM, because estimates of completion work and its execution. Each stage in-
times are vulnerable to adverse weather volves the making of decisions, and CPM
and site conditions. This report is a study is a technique which helps in the making

' ACKNOWLEDG EMENTS - T ha nks are due to the undermentio ned for the very valuable assistance
given during this study:
Richard Costain (Civil Engineering) Ltd. , W. and C. French Ltd., J ohn L a ing Construction Ltd. , Ro bert
McGregor and Sons Ltd ., The County Surveyor, Durham County Council, and The County Surveyor,
Northamptonshire County Council.
This paper is co ntri buted b y permission of the D irector of R oad Research . Crown Copyright. Re-
produced by permission of the Controller of H .M.S .O .

866 A .R.R.B. P ROCEEDINGS


WINGATE - CPM TO PLAN AND CONTROL ROAD CONSTRUCTION PROJECTS

of these decisions. In the planning stage are common to other types of construc-
it helps the creation of the plan by clarify- tion work, but they are often accentuated
ing the problem of relating duration time, by the nature of the work and the site. The
resource requirements and costs to the main problems are due to the vulnerability
practical limitations of the project. During of completion times to adverse conditions,
execution, it provides a basis for control the extent and nature of the site and the
and helps to indicate the course of action method of tendering.
necessary when the plan goes wrong. CPM TENDERING
provides mathematically correct solutions
6. Most road construction projects are
in accordance with the logic and data pro-
concerned with public highways and the
vided. The quality of these solutions de-
form of tendering for such works almost
pends upon the accuracy of the logic and
entirely excludes the contractor from any
data . CPM is no substitute for proper
participation in the design stages. Not until
planning, good estimating and effective
he receives the tender documents does the
control, but it does enable those concerned
contractor obtain any detailed knowledge
to make the best use of their skill and the
of the project. Some of the information
available data.
contained in these documents, which will
4. The advantages generally claimed have a considerable bearing on his plan, is
for CPM are that it: incomplete and provisional. This applies
(a) compels a thorough and detailed ex- particularly to information on the location
amination of the project, of statutory undertakings' services and the
(b) provides a programme based upon work required to relocate them, dates for
logical sequence and interdependence entry on to land, the site survey etc. About
of activities and restraints, two months is usually allowed for the pre-
paration and submission of the tender,
(c) pIOvides a useful and systematic
which includes not only pricing the bill of
method of allocating resources to the
quantities but planning the work and mak-
best advantage,
ing arrangements for supply of materials,
(d) provides a clear and easily under- sites for spoil dumps and offices, and sub-
stood method of communicating the contracts . The contractor is therefore
engineer's plan to all concerned, faced with the problems of producing in a
(e) indicates and emphasizes likely areas relatively short time a plan which is de-
of trouble and delay, tailed enough for the estimators to make
( f) provides a basis for reporting pro- a precisely calculated and competitive bid,
gress, yet broad and flexible enough to allow for
(g ) indicates, if progress lags, where extra changes in some of the basic information
effort is required to restore progress upon which it is based. These two require-
and where extra effort would have no ments are conflicting. CPM shows to best
useful effect, and advantage in detailed planning and may
( h) facilitates amendment of the pro- require extensive revision if changes have
gramme when the situation requires it. to be made in the basic logic, but other
methods of planning offer no special ad-
APPLICATION OF THE CRITICAL PATH
vantages in this respect.
METHOD TO ROAD CONSTRUCTION
PROJECTS NATURE AND CONDITION OF THE SITE
5. Most of the plallIling problems 7. Road construction sites, particu-
which arise in road construction projects larly on major projects, may by their

Volume 3, Part 2 (1966) 867


WINGATE - CPM TO PLAN AND CONTROL ROAD CONSTR UCTION PROJECTS

length traverse areas with considerable dif- special conditions of the contract such as
ferences in topographical and geological the nature and condition of the soil, time
conditions. The forme r are obviously ap- of year at which each activity is likely to
parent and can be al lowed for in planning, be carried out, local climate etc. The
but the latter often are not revealed until method of programming should be suf-
the ground is opened up, despite extensive ficiently flexible to allow completion times
soil surveys . Unexpected conditions will to be altered with a minimum of replan-
upset any programme, whether based upon ning. CPM meets this requirement satis-
CPM or not, but, if extensive revision does factorily, provided the basic logic of the
become necessary, the effects of unexpected network is unaltered ; new completion
changes on other parts of the programme times can be inserted and their effects on
are very clearly indicated on a network th e subsequent works determined very
programme. The problems encountered easily. The lines upon which any replan-
differ with the type of project; thus a re- ning should follow are also made clear. The
construction over the original alignment is vulnerability of completion times to the
usually more complex than construction effects of weather is probably the least re-
over a new alignment. Reconstruction has levant argument against the use of CPM
greater problems with the maintenance of on road construction projects; instead it is
traffic flow, not only across the site but one of the most compelling in its favour.
along it and this in turn makes the re-
9. Other problems may arise which
location of statutory undertakings' services
involve difficulties of timing. Portions of
more complicated, particularly if changes
the site may be particularly vulnerable to
in levels between the old and new road
wet weather and may need completion
are necessary. Bridges and junctions can
during the most likely dry periods. A con -
produce difficult problems of timing which
crete pavement needs careful timing so that
are particu larly suitable for solution by
the p aving train can run through with the
CPM. The main difficulty is usually un-
minimum of moves. CPM planning shows
certainty about the exact location of the
with great clarity the effects of such time
underground services, complicated by the
restraints and possible difficulties.
fact that it is often necessary to move the
services very early in the contract. Un- DETA IL RE QUIRED
expected conditions at this time may throw 10. There does not seem to be any
out the whole programme. On new align- great advantage in preparing the network
ments these problems still exist but not to for the whole of a road construction pro-
the same degree. ject in great detail. It is probably better
ESTIM A TION OF COMPLETI ON TI M ES
to base acti vi ties on collective operations,
otherwise it is difficult to know where to
8. The problem of variations from the
sto p in the breakdown of activities. This
estimated completion times of different helps to retain the flexibility necessary to
activities is present in any form of manu- deal with minor day to day changes which
facturing and construction work, but is are likely to occur owing to changes in con-
probably most acute in road construction ditions on site, without altering the actual
since the site is a natural one and is ex- programme. Where greater detail is re-
posed to the weather the whole time. Esti- quired, for structures and areas where diffi-
mation of completion times should follow cu lt problems of timing may arise, separate
established practice, i.e. it should be based diagrams can be used. It is also helpful to
upon past experiences and varied by the show extensive operations such as drain-

868 A.R.R .B. PROCEEDINGS


WINGATE - CPM TO PLAN AND CONTROL ROAD CONSTRUCTION PROJECTS

age on separate di agrams. They can be one per area network) which are nearly
shown in broad outline on the main dia- critical and which would become so if
gram, while on the su bsidiary diagram even a short delay occurred in one or more
greater detail can be used to show move- of their activi ties . In the practical applica-
ment of labou r groups, plant etc. and a tio n of CPM it is preferable to make these
breakdown of activities. Only activities and near-criti cal paths critical by slight in-
restraints which really affect the main dia- creases in completion times, thus introduc-
gram need be shown on it. T he subsidi ary in g several criti cal paths into the network.
diagram will indicate those peculiar to the This is qui te logical and could always occur
type of operation dep icted. by chance in the most precisely calculated
network. The reason for doing this is that
11. The amount of detail and number
it shows how delays on part of the site
of activities shown on the main diagram
may affect work on another and forewarns
will generall y determine whether a com-
the engin eer in charge how and where
puter should be used . Generally, networks
trouble may develop. A n alternative way
for road construction projects do not h ave
of dealing with this is to mark th e near-
a large number of activities, so manual
cri tical paths in a distinctive manner so
computation is usually possible. However,
that they may be distinguished from the
the use of a computer does facilitate the
non-critical paths. Whether a path is near-
resource all ocation and future revisions,
criti cal or not can be detern1in ed b y some
and these factors should be considered
arbitrary standard such as the total flo at
when the decision on the use of a com-
being less than a certain amount or less
p uter is made. F urthermore, the com-
th an a certain percentage of the total
puter print-out is a very useful document
co mpl etion time in the path.
fo r communication and control.
PRESENTATION
THE CRITICAL PATH 13. Because road construction projects
12. Road construction projects tend to tend to conform to a set pattern, network
confo rm to a general pattern, i.e. concen- diagrams are particularly adaptable to pre-
trations of work at bridge sites, junctions, sentati on on a locati on bas is which greatly
etc., linked by conti nu ous activities such increases their clarity and usefulness as a
as earthworks , drainage, pavement con- means of comm uni cation of the pl an (this
struction , etc. along the site. Work is is of course already done in th e more
usually started more or less simultaneously ophi sticated forms of bar charts). The
at these different points of concentrated CPM convention of tim e advancing from
effort and to so me extent is continu ed in- left to right across the diagram is~ main-
dependently of work at other points, but tained, but instead of a haphazard group-
gradually becoming more and more inter- ing of chains of activities all over the dia-
dependent as tim e advances. T he general gram they are located in the same relative
pattern of the network therefore resolves positions in whi ch they occur on the site.
itself into a number of semi-independent On the verti cal left-hand m argin of the dia-
networks at bridge areas etc. linked by gra m a scale plan of the site is drawn with
dumm y activiti es and normal activities particular features marked , i.e. bridges,
along th e carriageways. Precise planning junctions, service crossi ngs, areas of cut
wi ll generally res ult in one critical path and fill , layout of drainage etc. Chains of
which may move from one area to another activiti es are th en drawn against the rele-
th rough the dummy activities. There are, vant point in the plan. Acti vities at points
however , likely to be other paths (at least such as bridges are shown horizontally, and

Vo lum e 3, P art 2 ( 1966 ) 869


WINGATE - CPM TO PLAN AND CONTROL ROAD CONSTRUCTlO PROJECTS

continuous activities such as earthworks are ways, but in the course of the investiga-
shown by slanting lines drawn from the tions one fact in particular emerged: as
point in time at which work starts on the experience in the use of CPM was gained
site to the finishing point. Dummy activi- there was a general trend away from the
ties are shown by dotted slanting lines conventional method of detailed applica-
connecting the relevant events. Detailed tion towards simpler methods , more in
bridge diagrams can often be shown in the keeping with the practical, site-office ap-
sa me way using a formalized plan of the proach needed by the engineer in charge.
bridge in the left-hand margin. F in ality in this had not been reached and
the method s employed were largely influ-
14. In general, time spent on presenta-
enced by the size, organization, experience
tion of the final network diagrams is well
in the use of CPM and method of work-
worthwhile. They should be well anno-
ing of each contractor.
tated to indicate restraints such as the use
of roads by traffic, switching of traffic to PROJ ECT A : NEW DUAL CARRIAGEWAY ROAD
new construction or diversions, dates of 17. The contractor (a medium-sized
entry onto land , moves of services, and firm) was making his first use of CPM on
moves of plant, equipment and labour this contract. Planning was approached on
gangs. These may have already been in- conventional lines, and a very detailed net-
cluded as dummy activities, but if time and work was p roduced and processed by a
effort are consumed , e.g. when a concrete computer using a simple programme. Re-
trai n is moved from one carriageway to visions were also made on a computer. This
another, they become normal activities with project was not studied in any detail. The
a completion time. contractor's experience on this project
showed that the use of CPM was well
15 . The general pattern of CPM plan- worthwhile, but the approach had been
ning therefore evolves on conventional too elaborate. A more simple approach
lines. Duri ng tendering, a broadly based was therefore tri ed out on his next con-
network is produced from the avail able tract, project B.
data and developed to give the require-
ments of resources with, if possible, de- PROJ ECT B: RECONSTRUCTION TO DUAL
CARRIAGEWAYS
tailed networks for the more definite por-
tion s of the project, such as the bridges. ] 8. This contract was for the recon-
On acceptance of the tender, the network structi on of an existing straight, narrow,
is reviewed as soon as the missing and undul ating, heavily trafficked road to dual
incomplete data are obtained and con- carriageways with improved levels and
firmed . Greater detai l will probably be put grade separation at junctions. Concrete
into the network and further subsidiary construction was specified for the carriage-
diagrams drawn as required. As work on ways. This project contained most of the
the project proceeds, progress is com- cl assic problems, i.e. mainten ance of flow
pared with the programme and the latter of a large volume of traffic through th e
is updated where necessary. site at all times (diversions off the align-
ment were virtually impossible owing to
CA SE STU DIES O F THE US E OF THE CRITIC AL the unsuitability of alternative routes
PATH METHOD ON ROAD CONSTRUCTION through the area), services crossing at
PROJECTS right angles at road junctions and in-
16. On the different projects visited, adequately recorded, delayed land entry at
CPM was being applied in many different one bridge site, a soil which became un-

870 A.R.R.B. PROCEEDINGS


WINGATE - C PM TO PLAN AND CONTROL ROAD CONSTRUCTION P R OJECTS

workable when wet, a bad starting date 20. Owing to initial delays du e to the
(January 1 ) and a form of pavement con- weather and other complications, progress
struction which could not be laid in short lagged behind the programme. However,
lengths. In addition , there was bad weather with the coming of better weather progress
up to the middle of April. The contractor improved considerably but it was decided
was able to release the agent designate for not to make any revision of the network
th e tender planning and he produced a net- until about August. This was done for
work di agram on rather broad lines on a several reasons: the work, although behind
ca lend ar time basis for the bid. Bridges schedule, was catching up and adju stments
were shown as single activities based upon to timings were quite adequate to provide
detail ed networks drawn by the contrac- th e necessary short-term guidance, and a
tor's bridge engineer. The bridge areas revision at this stage did not seem worth
stood out as the main centres of work the time and effort th at would be entailed.
during th e first third of the two-year con- Also, as the key operations - the con-
tract period , with the construction of the struction of the bridges - were proceed-
pavement as the main work for the re- in g sati sfactorily, it was felt better to wait
maind er of the period . Provision was until the completion of these was in sight
made for work being stopped during three before progress and future work were sub-
winter months, completion times were only stantially reviewed. As work proceeded,
roughly calculated and the network was minor adjustments were made to the logic
not arithmetically computed but drawn sequences to assist progress.
onto the time scale from the logic dia-
2 1. The major review was made in mid-
gram ; it was, in fact, computed graphically.
August and the remainder of the network
No critical path or fioat was shown. The
was recast upon the basis of progress to
requirements of the main resources were
date. Th e later part of the programme had
assessed by means of histograms.
always been considered somewhat pro-
19. On acceptance of the tender the visional. Some alterations were made to
programme was put into operation but im- the basic logic, mainly to make up for lack
mediately ran into difficulties because of of progress in some portions of the pro-
the weather and complications over moves ject, to allow for changes in the logic al-
of services. The agent set abou t re-plan- ready made, and to make provision for
ning th e programm e in grea ter detail, but so me work durin g the winter period. Non-
owing to pressure of work (he had no critical activities during thi s period were
planning assistant to do it) he was unable given ample fioat, and the one critical ac-
to complete the re-planning until about the tivity was safeguard ed with a generous
middle of March . The revi sed plan, which completion time. In tbe event, laying of
took into account all known restraints, co ncrete pavements was continued into
was essentially simil ar to the tender plan December.
but was more deta iled (it contained 164 22. Work was carried on during the
activities instead of the 126 of the ori ginal) . second yea r in general accordance with the
It was drawn on a calendar time scale using network programm e and no major revisions
a time un it of one week. Float was shown , were mad e. Minor changes were made on
but no moves of plant, though these were two diversions which enabled excavation
mostly readi ly apparent. It was not fo und and concreting on the main carriageways
necessa ry to make any changes to the to be speeded up. Des pite cement short-
bridge diagrams. ages, the concrete carriageways were com-

Volume 3, P a rt 2 ( 1966) 87 1
WI GATE - CPM TO PLA AND CONTROL RO AD CONSTRUCTIO PROJECTS

pleted about four weeks ahead of schedule. in the project. There was little cross traffic
Joint-seaLing proved to be a bottleneck but over the site and alterations to under-
a generous allowance of time in the pro- gro und services were not extensive. The
gramme for curing prevented this from agent designated carried out the tender
causing any delay. planning using CPM networks of 40 to 50
activities. Three alternative networks were
23. T he contractor's approach to this
drawn to study different methods of phas-
project was partly dictated by the small
ing the work. Separate, more detailed
number of staff employed, but experience on
bridge diagrams were used, two on one
project A had shown that flexibility in the
sheet and three on another, to allow the
use of CPM was essential and that the agent
diagrams to be linked through moves of
should not become the slave of the net-
sh uttering etc. Bridge construction could
work programme. Detailed planning was
be phased into the embankment construc-
very necessary since work at the bridge
tion and paving programmes at the most
areas required precise timing and inter-
suitab le times. The networks were drawn
dependence of activities. The agent, how-
against a time scale and were manually
ever, used the network mainly as a guide
computed. Resources were assessed suf-
and appreciated, very rightly in this case,
ficiently for estimating purposes.
that frequent revisions would not have any
practical use. His major revision was 25. A serious difficuity arose over the
timed for a point when substantial progress source of the imported fill at the start of
had been achieved and the emphasis of the contract. Because of this, construc-
work was changing from bridge to carriage- tion of the embankments was lagging con-
way construction. Although a schedule of siderably behind the tender programme
events and times was drawn up in the con- when the agent started on his firm plan. It
ventional manner, virtually no use was was also found that the quantity of un-
made of it once the network had been suitable material to be removed was about
completed on a time scale. The computa- double the estimated amount. Owing to
tion of the revision was carried out entirely these unresolved problems the agent drew
graph ically, in fact as it was being drawn up a new plan, on very similar lines to
out. A further review, which was to have hi s tender plan, against a horizontal time
been carried out when work was largely scale and vertical site plan. No float was
stopped by the winter, was found to be shown as the agent preferred not to reveal
unnecessary. this (details of float were of course shown
on the manual tabulation). Before this
PROJECT c: RECONSTRUCTION TO DUAL
CARRIAGEWAYS
plan was complete a further complication
24. This contract (by the same con- arose, in that it was decided to use the
tractor as for projects A and B) was the project as a full scale trial of a slip form
dualling of a heavily trafficked trunk road, paver. Another programme was drawn up
using concrete construction, and included to all ow for this , but it was never really
a length of by-pass over a new alignment. used. Long term planning had to be sub-
The site was in a low lying flood plain so ordinated to th e short term needs of the
the road was designed to be carried on a trial.
low embankment built from self-draining 26. The agent considered that CPM
imported fill. The only excavation was for had been particularly useful during ten-
bridge foundations and removal of unsu it- dering since it enabled him to investigate,
able material. There were five small bridges very rapidly , different methods of carrying

872 A.R.R.B. PROCE ED INGS


WINGATE - C PM TO PLAN AND CONTROL ROAD CONSTRUCTION PROJECTS

out the project. In its original form , the was a pure logic diagram showing move-
project had no particular complications and ment of form work but with no other re-
the use of a broadly based network with a straints; the second diagram, which was the
small number of activities seemed to be working programme, included all restraints
the right solution. and was based upon a realistic allocation
of resources. In later revisions only the
PROJECT D: MOTORWAY
second diagram was altered and issued.
27 . The contract for this project fin-
R esource requirements were planned from
is hed at the lean concrete base level (a
the diagrams and recorded on them in
separate contract was to be let for the re-
histogram form . Movements of resources
mainder of the work). Bridges and ser-
such as plant and labour were recorded by
vices produced no special complications.
notes at appropriate points. The diagrams
The contractor (a large firm) had previous
were given a wide distribution in addition
experie nce of CPM and maintains a large
to being well displayed in the planning en-
planning section which carried out the
gineer's office. They were used to record
planning at the tender stage. The main
progress and were the basis of planning by
programme consisted of a CPM network
site engineers and foremen.
on a ca lendar time basis, with completion
times roughly estimated. Detailed networks 29. The plan for the project was largely
were drawn for the bridges. On acceptance based upon the sequences for the bridge
of the contract, the planning engineer ap- construction, and no particular difficulties
pointed to the contract revised the pro- were anticipated on the earthworks even
gramme and bridge networks in the light though large volumes were involved. Be-
of additional information. The main pro- cause of the very ti ght, self-imposed sched-
gramme was drawn in the form of a linked ule, and the fact th at virtually every activ-
bar chart with activities shown against ity had been made critical, it was found
their location on a plan of the site (show- necessary to make frequent revisions of
ing location of bridges and cut and fill the programme at intervals of four to five
areas). It was in effect a modified network weeks. Opportunity was taken at these re-
diagram and included considerable use of visions to improve the form of presenta-
dummy activities. Events were not num- tion of the programme, so the later edi-
bered and no schedule of activities was tions differ somewhat in layout from the
prepared (computation was graphical). In earlier ones. The final form adopted was
general, the presentation of all diagrams that described earlier (para. 13).
was excellent, and they were of a conveni-
ent size for handling. 30. Progress was well maintained for
the first ten months ( up to early in the
28. For his own reasons, the contrac- fir st summer) but then a problem arose
tor planned to complete the project two which eventually caused a major delay and
months ahead of the contract date, and to completely upset the earthworks pro-
achieve this he virtually had to make all gramme. The bulk of the material to be
activities critical. When this was done, no placed in the embankments was a marl
critical paths were shown on the diagrams. which was very difficult to compact to
The main diagram was on broad lines and specification unless the moisture content
a separate one was produced to show the was exactly right. The dry summer and
ea rthworks and drainage in detail. The the laying of the marl in thin layers (as
separate bridge diagram s were reviewed required in the specification) caused it to
and two were drawn for each bridge: one dry out rapidly and considerable difficulty

Volume 3, P art 2 ( 1966 ) 873


WINGATE - CPM TO PLAN AND CONTROL ROAD CONSTRUCTION PROJECTS

was experienced in bringing it up to the PROJECT E: NEW DUAL CARRIAGEWAY ROAD

correct moisture content. The difficulty 33. The construction of this road, over
became so acute that forward planning be- a new alignment, call ed for some grade
came impossible. T he earthworks part of separation and several bridges including
the CPM diagram had to be abandoned one over a single line railway. Like pro-
but the bridgeworks were continued largely ject C, the whole of the carriageway was
accordin g to plan , except where they were carried on embankment and the only ex-
affected by the earthworks. A further cavation was for bridge foundations and
difficulty arose owing to changes in the removal of some unsuitable soil. The con-
design of a service area and this was not tractor was the sa me as that for project D.
resolved until late in the contract. Eventu-
34. Preliminary planning was carried
ally an extension of 16 weeks had to be
out in the contractor's head office. A two
granted.
months' delay in the acceptance of the
tender allowed the contractor to review the
31. T he fact that the plan broke down
pl anning before the work was started. This
was not the fa ult of the technique or those
was done by the project chief engineer
who applied it. The situation became such
who was subsequently responsible for
that forward planning of the earthworks by
planning and progressing the contract.
any method became impossible. To have
continued to revise the diagrams to the 35. The construction of the embank-
rapidly changing situation would merely ments presented no particular difficulties,
have been to record past history. The and there were no special time restraints
value of CPM is shown by the fact that so it was decided to base the programme
individual bridge construction could still entirely on the most convenient timings for
follow the network diagrams and that the the bridge construction. The bridges were
sequ ence of bridge construction in the main all of different design and allowed little
plan still remai ned largely valid . Difficul- in terchange of shuttering. The supply of
ties on bridge construction due to failure concrete was the main problem (there
of the earthworks programme were clearly were ten different mixes required) so the
seen and the course of action could be de- periods during which bridges were con-
termined . structed were adjusted to produce as level
a demand for concrete as possible. Other
32. The contractor adapted and de- resources were also considered, particularly
veloped the CPM technique to meet his the requirement of cranes, but were largely
particular needs on this project. Because subordinated to the demand for concrete.
of the tight schedule he needed the close With the relative positions in time of the
control which CPM gave him, though at bridges settled , the main programme was
the expense of frequent revisions of the then drawn up. The rate of embankment
networks. These must have absorbed a construction was based upon an economi-
great deal of time and effort not only by cal rate of output from the borrow pits
the planning engineer but also by the and the maintenance of the embankments
drawing office staff. This was a project on at a roughly equal level during construc-
which the use of a computer might have tion along the site. The final main pro-
been well worthwhile, if only for the re- gramme was virtually a bar chart (but
visions. A suitable programme would also based upon a network) drawn to a weekly
have saved the extensive redrawing by giv- time scale. 0 critical path was shown.
ing the print-out in bar chart form. The pavement construction (flexible) was

874 A.R.R.B. PROCEEDINGS


WINGATE - CPM TO PLAN AND CONTROL ROAD CONSTRU CTION PROJECTS

only shown in very broad outline since programme and the detailed bridge net-
this presented no planning problems. The works were always available to the sub-
duration time of the project as planned agents , but in fact they planned their own
was about 25 per cent less than the con- work from bar charts covering three
tract time. months' work which were drawn from the
main programme by the . chief engineer.
36. At the start of the project progress
Foremen were given similar bar charts
was extremely good. The site was poten-
covering two weeks' work (issued weekly) .
tially very wet, but the dry summer had
In planning the project the contractor took
reduced the level of the water table so ad-
full advantage of the resource allocation
vantage was taken of this to advance the
characteristic of CPM.
foundation construction of one of the
bridges, and the main diagram was amend- 38. It had been anticipated that no
ed to show this. There were some minor major revision of the programme would be
changes in embankment construction, necessary. When the source of imported
partly due to difficulty of access to one fill failed, the CPM programme clearly
part of the site, but mainly because the showed th at the main framework - the
output of the borrow pits was stepped up. construction of the bridges - would be
Later, however, there was an unexpected un affected, and that emergency action for
failure to obtain planning permission for drawing up a whole new programme was
the use of a further source of imported not required . E mbankment construction
fi ll. Construction of the embankments was could be carried on as fill became avail-
reduced to a very slow rate while alter- able. The tentative plan for paving was
native so urces were sought. Work on the altered to fit the new circumstances, but
bridges was continued according to the fortunately the paving sub-contractor was
programme but progress slipped behind also working on an adjoining contract and
slightly, particularly on one major bridge, was able to adjust his output between the
owing to unforeseen complications in its two projects.
construction. Although the programme had PROJECT F: MOTORWAY
been based upon full completion of each
39. The contractor for this project was
bridge before subsequent activities were to
a large firm with a planning department
be started, it was . found that these could
and experience of CPM on construction
in fact be started before the bridges were
work. Only limited use of CPM was made
entirely complete and no time was lost.
on this project. The main programme was
Delay on the embankments did not materi-
a sophisticated form of bar chart developed
ally affect the bridge construction, but the
by the contractor, drawn on a time and
tentative paving plan, which had envisaged
location basis, but network diagrams were
a continuous run through for each layer
used for individual bridges. In this con-
from end to end, had to be abandoned for
tract there were no important outside re-
piecemeal work as lengths of embankment
straints, and the order and time of con-
became avai lable. However, it was antici-
struction of the bridges could be arranged
pated that the project would be completed
entirely at the contractor's convenience.
within the time the contractor had origin-
This was a considerable advantage since
ally planned .
part of the pavement was to be constructed
37. Again, th is appeared to be a in concrete. It was considered that it was
straightforward project which would not in correct to base a logic network on purely
need a very detailed programme. The main arbitrary decisions which could be altered

Volume 3, Part 2 (1966) 875


WINGATE - C PM TO PLAN AND CONTROL ROAD CONSTRUCTION PROJECTS

at will. The method of programming gave 42. The tender programme was a con-
adequate but flexibl e control and a good ventional bar chart drawn up by the con-
means of resource allocation. Control on tract planning engineer. Work on a CPM
the contract was exercised firmly by a pro- network was started in M arch , as soon as
ject planning engineer and two assistants. the contract was let by the planning en-
It was, however, considered that in the gineer in conjunction with a consultant. A
later stages of the contract, when comple- very detailed examination of the project
tion on time finally depended upon com- was made and the resultant network con-
pletion of a number of converging activi- tained over 2,000 activlues (including
ties , a network diagram would be drawn dummies) . Everything was contained in
to ensure adequate control at this critical one large diagram (some 16 ft long); it
stage. In the event, this was not found to was not drawn to a time scale nor was any
be necessary. location separation used. Estimated com-
pletion times were given in days. The
40. On this project, the contractor was general basis of the pl an was to space out
still experimenting with CPM for road th e construction of the bridges to the
construction and he had a well tried and period s most convenient for the contractor
satisfactory alternative method of program- within the limitations imposed by other
ming. The circumstances of the project did factors, such as maintenance of traffic
not warrant a tight, rigid plan and schedule across the site, relocation of the under-
in the early stages . He did appreciate how- ground services, th e earthworks , and the
ever, th at in the latter stages more definite need to allow the concreting train an un-
planning might become necessary and that interrupted run. It was known that a con-
CPM would be the best method of achiev- siderable amount of soil would have to be
ing it. However, a broadly based CPM rejected as unsuitable. Naturally, a com-
network could well have been substituted puter was used to compute the large net-
for his own type of programming technique work , and the programme required separ-
from the very beginning, and should prob- ate run s for solving the netwo rk and
lems have arisen CPM would more likely allocating resources. The first run for
have indicated their solution. durati on time gave an excessive and un-
acceptable answer largely owing to re-
PROJE CT G : NEW DUAL CA RR IAG EWA Y ROAD
straints imposed upon earthworks during
41 . This project was a by-pass about 5 th e winter months. The network was ad-
miles long with two-lane dual carriageways justed manually, using more realistic inter-
and concrete pavements. It had grade- pretations of the restraints, and a second
separated roundabouts at either end and run on the computer gave a sati sfactory
grade separation at all crossings through- duration time. The resource allocation
out its length. The route lay partly through run (for the more important resources
low lying agricultural land and partly only ) was then made. This planning took
through a built-up area, but had been pro- about four months to complete. Subse-
tected by the county plan. There were quently, some re-pl anning of the carriage-
considerable problems over the relocation way construction was carried out and this
of statutory undertakin gs' services, the full part of the network was re-drawn . This
extent of which were not apparent at the re-planning was the result of second
time of tendering. The contractor was a thoughts and was not caused by events
large firm making its second full scale use occurring during the execution of the pro-
of CPM on a road construction project. ject.

876 A.R.R.B . PROCEED INGS


WINGATE - CPM T O PLAN AND CONTROL ROAD CONSTRUCTION PROJECTS

43. Little use was made of the actual print-out was similarly limited since only
network diagram, the computer print-out three copies were available. Planning from
being the main reference document. This the programme using the print-out was
showed the sched uled starting time, latest carried out mainly at the weekly confer-
starting tim e and latest finishing time for ence. The contractor, however, considered
all activities, marked the critical activities that the very detailed approach was well
and gave the resources required where worth the effort put into it. It revealed not
these were assessed . Activities were listed only the major problems on the project but
in order of their scheduled starting time also the smaller details which might other-
and increasing amount of float. wise have been overlooked only to cause
trouble later. It was considered that separ-
44. During the early stages of the pro-
ate diagrams for structures, etc. were not
ject several minor changes were made in
necessary. Since every aspect of the pro-
the logic of the network, but it was not
ject was considered in equal detail this was
re-computed. The main reason for the
logical, and was more convenient for solv-
changes was to take advantage of the dry ing the network on the computer. It did ,
summer and autumn by pressing ahead however, result in an unwieldy and com-
with earthworks wherever possible. Changes
plicated diagram which was little used ex-
were also necessary because the amount of
cept by the planning engineer. The com-
unsuitable material to be removed was
puter print-out, however, was invaluable.
found to be considerably more than had The extra cost of the CPM planning was
been estimated. Others were made because
considered to be small compared with the
of compli cations both in the construction
cost of the project (some £Sterling31h
of retaining walls in a narrow cutting and million) and the benefits obtained. The re-
on the moves of underground services.
source allocation alone, if done by normal
45. It was anticipated that an extensive manual methods, would have been a
review and revision of the programme Jengthy and unreliable process. Once the
would be necessary during the first winter. data were on the cards, revision was simple
However, progress was so good that no and cheap. The use of the network, was,
changes were required and work was con- like that of other contractors using CPM,
tinued after the winter on the lines of the realistic and flexible.
programme as it stood . Completion of the PROJECT H : RECONSTRUCTION TO DUAL
project was expected to take place about CARRIAGEWAYS
four months ahead of schedule. 48. The project was the dualling of a
length of class 1 road feeding a motorway
46. Progress was recorded on the chart and was carried out by the direct labour
and the print-out by marking off com- force of a county surveyor. A preliminary
pleted activities , the information being ob- logic network was drawn to ascertain
tained at weekly conferences. There was whether or not the project could be carried
no special progressing routine organized out economically by the available direct
on the basis of the network. labour force within the time allowed. The
47. This contractor's use of CPM was network was computed both manually and
rather different from that of the others on a computer and assessed for labour re-
visited. The network was complex and not quirements. The solution confirmed that
used outside the pl anning engineer's office, direct labour could meet the requirement.
except for copies sent to the resident en- A second network was drawn in greater de-
gineer and head office. Distribution of the tail , based upon an outline plan devised

Vol um e 3, P art 2 ( 1966) 877


WINGATE - CPM TO PLAN AND CONTROL ROAD CONSTRUCTION PROJECTS

by the engineer in charge, which would per cent of the total cost of the project
maintain traffic flow without interruption (£ Sterling152,000) and of this about one-
throughout the duration of the job. Com- third could fairly be attributable to the
putation of this network revealed some training of those concerned in the use of
discrepancies in the logic, so it was revised CPM.
to correct these and re-computed. The net- 52. Further uses of CPM within the de-
works were drawn against a time scale partment are being investigated, including
(one-day units) with activity times already programming of design work, maintenance
estimated. The networks were adjusted as sched ules and new construction projects.
drawing proceeded so that the duration The second phase of the dualling of the
time equalled the allowed period (120 feeder road is also being planned with
days) and no further adjustment for this CPM.
was required. In effect, graphical com-
CASE J : PROGRAMMING THE DESIGN STAGE OF
putation was used for the critical path, but PROJECTS
the computer was needed to give the re- 53 . A county highway department was
maining information since the number of faced with a four-fold increase in its an-
activities (750) was far too great for nual volume of work and a deadline of
manual method s. Only a simple print-out five years in which to spend a special allo-
was obtained. cation of funds. A study of the manpower
49. The county surveyor's department required showed that very careful organiza-
had had little experience of CPM but had tion of the design stage of the programme
a considerable amount of data on the would be necessary to bring projects to the
labour and plant content and standard construction stage early enough for the
minute values of jobs, accumulated by its funds to be spent. The department already
work study section. It was decided, there- had experience of the use of computers so
fore, to base the breakdown of activities it was decided to make use of computer-
and all estimated completion times on based critical-path networks to plan the
these data and for this reason a very de- programme. A three-man project planning
tailed network was used. The use of these unit was set up to do this.
estimates based upon work-measurement 54. Five different sections were involved
studies gave the planner (the work study in the whole county programme: direct
engineer) considerable confidence in his labour, bridges; traffic planning and
programme and, in the event, the duration laboratory ; motorways; trunk classified
time was only very slightly exceeded . One roads. The project planners had to work
revision was made on the computer during in close co-operation with the principal
the execution of the project. officers of the five sections , who provided
50. Neither the engineer in charge nor the data on which the networks were based.
his foreman had previously had any know- The data consisted of target dates, details
ledge of CPM, but both found the network of legal procedures and design processes
programme of considerable help through- (which included tasks to be carried out by
out in timing material supply, plant require- the Ministry of Transport and other depart-
ments and the movement of labour to and ments) and information on the staff and
from other works in the county as the time required to accomplish these tasks.
labour requirement on the job varied. 55. The first step was to draw out the
51. The cost of the planning, including whole motorway programme on a CPM
the computer time, was approximately 0.35 network, as this was the immediate work

878 A.R.R.B. PROCEEDINGS


WINGATE - C PM TO PLA AND CO TROL ROAD CONSTR UCTIO PROJECTS

and was already in progress. The remain- as necessary. Networks were re-computed
der of the programme (special priority if significant changes were made. Records
projects, conurbation projects, normal road were kept of progress made and this was
programme projects over £ Sterling 100,000 shown in outline on lists of projects by
and other projects under £SterlinglOO,OOO) recording against target dates the actual
was phased in broadly at suitable times completion dates of key stages.
according to priorities allotted. Networks
57. A specially adapted programme
were then drawn for these other projects.
was used for computing the networks and
After close checks had been made of all
gave the following:
networks to ensure the logic was correct
and all necessary procedures and processes (a) earliest and latest starting and finish-
had been included, timings were added (on ing times as calendar dates,
the computer) and the networks adjusted (b) very full activity descriptions,
to comply as far as possible with the given (c) choice of time units: months, weeks
target dates. Staff requirements were then or days (five- or six-day working
assessed and adjustments made to ensure weeks) ,
that the best use was made of staff available. (d) choice of print-outs: master, critical,
These adjustments included alterations to the section or team,
networks and to the numbers of staff allot- (e) references to reports, and
ted to individual activities. Where consider- (f) skeleton master print-outs for quick
able float time was available it was often checking of revisions.
useful to reduce the numbers employed on 58 . The skeleton print-out proved ex-
the relevant activities, thus releasing staff tremely useful. It allowed the engineer
for other work and absorbing the float. On concerned to check that the logic and data
the other hand , it was sometimes prefer- of a revision were correct before a full run
able to increase the staff and speed up and print-out were made.
activities, thus releasing whole teams for
other work, earlier. To control the deploy- 59. A year's experience in the use of
ment of staff, charts were drawn up show- the system has shown that the effort put in
ing what each man would be working on to devising and operating it has been in-
at any given time. Any necessary re- valuable in enabling management to keep
deployment of staff to meet changing con- control of this large and expanding pro-
ditions could be clearly seen on these gramme. Without this use of CPM it
charts which covered a period up to six wou ld have been almost impossible to
months ahead. Only engineers were shown plan the work with any degree of certainty,
on these charts - draughtsmen were not and forecasts of expenditure of funds and
included. starting dates for construction work could
have been seriously wrong. The efficacy of
56. The programme was monitored so the system has been shown by the fact that
that each project came under scrutiny progress has kept remarkably close to the
about once every two months. Monitoring programm e, that changes have been fore-
consisted of very careful checks by the seen well in advance and that generally
head of the project planning unit in con- schemes have been brought to the con-
junction with all concerned including any struction stage quicker than in the past.
outside departments involved. Progress CASE K: DIREC T LAB O UR PRO J ECTS
was checked and alterations to the logic 60. As a second stage in the application
sequences and staff deployment were made of CPM, the county highway authority

Volume 3, Part 2 ( 1966) 879


WINGATE - CPM TO PLAN AND CONTROL ROAD CONSTRUCTION PROJECTS

concerned in case J above has started to LESSONS LEARNT


use CPM on its direct labour projects, 64. Although the different users have
which vary widely in size. The use of the developed their own individual ways of
technique was still in the experimental app lying CPM their experience does point
stage and no attempt had been made to to certain basic principles which have a
optimize resource allocation through CPM. common appli cation in road construction.
Networks were broadly based and com- These are:
puted on a computer. The planning sys-
tem used was different from the other pro- (a) CPM can be a very flexible planning
jects studied in that the engineer con- method and full advantage should be
cerned only listed the activities together taken of this characteristic.
with their completion times, and indicated (b) The possibility of I arge changes m
against each activity those which immedi- the completion times of activities is
ately preceded it. The actual network was no hindrance to the use of CPM. In-
drawn by the project planning unit using stead, CPM is probably the best plan-
the information provided by the engineer. ning technique for dealing with this
The system saved the engineer a consider- situation.
able amount of time, but very careful (c) In a complete project there are al-
thought was required in making out the ways likely to be several alternative
li sts. logic sequences. In the initial plan-
ning the most suitable logic network
61. The actlVlty lists, which also to suit the existing circumstances
showed quantities and estimated costs of should be aimed at, but it should not
activities, will be used to record expendi- be rigidly adhered to when circum-
ture. stances change, particularly if the
changes are favourable to more rapid
62. So far, these networks have only
progress. The effect of alterations to
been used by the engineer himself and have
the logic sequences of the network
not been used to communicate the plan to
can be readily foreseen and evaluated.
subordinates.
(d) Although studies in detail will always
produce valuable information they
COST OF USING THE CRITICAL PATH METHOD
will often be unnecessary and not
63. Except in the case of project H, it worth the effort if carried out on the
was difficult to determine the extra cost of whole project. Detailed studies can be
the CPM planning over normal methods. limited to areas where difficult prob-
The figure of 0.35 per cent of the total cost lems arise such as structures, junc-
of project H included the initial training tions , etc.
of the staff in the use of CPM. Omitting (e) Frequent revisions of the network are
this, the true cost was more nearly 0.22 not usually necessary in the early
per cent. It is thought that the cost is stages. Revisions are best carried out
unlikely to exceed 0.25 per cent of the after the completion of some definite
total cost of a project, even when a com- stage in the project. Towards the end
puter is used. This amount might well be of a project, when tight control may
less than the labour, plant and overhead be necessary to achieve completion by
costs for one week. If one week could be the due date, frequent revisions may
saved on the duration time, the extra cost become more necessary together with
of CPM planning could thus be covered. more detailed planning.

880 A.R.R.B. PROCEEDINGS


WINGATE - CPM TO PLAN AND CONTROL ROAD CO STRUCTlON PROJECTS

(f) If the full benefits of CPM are to be fore be marked on the networks or
gained, the highway authority should print-outs, in addition to any other
supply the contractor with more and method used. In only one instance
better information about the project was there any attempt to link the net-
than is usual at present when tenders work with expenditure. Cost control
are called for. More time should be by means of the network is a field
allowed for tendering so that the con- which might well repay further study.
tractor can place more reliance on the (j) CPM can be used equally well on
information he has to collect for him- large or small projects though its use
self. There should be no need for on the latter would be more usefully
sketchy or preliminary programmes. confined to those with complicated
The programme the contractor pro- timings and numerous restraints, such
duces for himself during tendering as works in urban areas.
should be sufficiently complete and 65. All the contractors visited agreed
reliable to be used throughout the that CPM was a considerable help to them
execution of the project (unless un- in planning and controlling their projects,
foreseen circumstances arise later). and that they would continue to use and
(g) CPM should be applied and controlled develop it. R esident engineers also con-
from the site office. Where possible sidered that they benefited from the con-
the CPM planning should be carried tractor's use of CPM as they were pre-
out from the start by someone who sented with a better picture of the con-
will be a member of the site staff. Pre- tractor's plan and intentions.
ferably, the initial planning should be
OTHER USES AND FUTURE TRENDS
carried out by the contractor's agent
designate, but he may need additional 66. It is likely that much more use will
assistance once the contract has been be made of CPM in the future for program-
started. ming the pre-construction work on pro-
jects, i.e. design and adm inistrative work,
( h ) CPM can be used to programme any which is one of the main tasks of highway
series of related activities and to allo- au thorities. Work done in the United
cate the necessary resources. It is States on this aspect has shown that stan-
particularly valu able in programming dard logic networks can be prepared for
the planning and design stages of the complete processing of projects from
highway authorities' road programmes their inception right up to the start of con-
since it will ensure that the best use stru ction. These standard networks are
is made of the staff available and that then adapted to suit tbe needs of individual
projects reach the construction stage projects, e.g. activities not required are
at predicted times. omitted by giving them zero completion
(i) Comparatively little use has been time. Experience in this country is also
made of CPM networks for recording showing the value of this use of CPM. In
progress, since many engineers prefer the same way contractors can plan their
to use other methods such as cumu- tendering procedures to enable them to
lative graphs of expenditure or pro- produce their bids more efficiently and
duction . It is, however, essential that quickly. (Indeed one of the contractors
any differences between the pro- visited is already using this method for
gramme and the actual situation are planning 'design and build' civil engineer-
always known; progress should there- ing contracts.)

Volume 3, Part 2 ( 1966) 881


WINGATE - CPM TO PLAN AND CONTROL ROAD CONSTRUCTION PROJECTS

67. Some highway authorities in the ence is gained of their use on other civil
United States produce their own CPM net- engineering works. The contractor in pro-
works for the construction phase of con- ject F showed that such detailed networks
tract projects. This practice helps to re- and computer solutions with simple re-
veal any special problems that are likely to so urce allocations are by no means im-
arise and enables the highway authority to practicable and have their advantages. On
make a realistic estimate of the duration complex projects in urban areas and others
of the project. That there is a need for where frequent revision might be necessary,
such an approach can be illustrated by the suc h as project C, the use of detailed net-
following example. Projects Band D both works and computers would be well worth-
had a contract period of two years. Pro- while.
ject B had to be on a very tight schedule
to ensure completion within the time CONCLUSIONS
allowed, whereas project D had so much 69. The general experience of those
time allowed that it could be planned for who have used CPM on road construction
completion well within its contract period. projects shows that there are no serious
Such wide differences cannot be to any- difficulties in this particular application.
one's advantage. The networks produced The most quoted problem of the variability
by American highway authorities are either of completion times is not peculiar to pro-
sent out with the contract documents or gramming with CPM; it is inherent in the
else explained at meetings with those in- road construction industry. It affects any
tending to tender. This ensures that all method of programming and has to be ac-
the contractors concerned are fully con- cepted and overcome. CPM provides a
versant with the project and its special very satisfactory way of dealing with this
problems before they bid and have no ex- problem since the effect of delays is clearly
cuse for their bids not being realistic. The shown, and the flexibility of the method
successful contractors are not obliged to faci litates amendments to reflect the
use the networks and they remain free to changed situation.
programme the work to suit their own
70. CPM probably costs more to im-
methods and resources. The networks do,
plement than other planning methods since
however, provide a yardstick by which the
it compels a very close study of projects,
highway authorities can judge the merits of
but careful planning and sound control
programmes submitted with tenders.
should save this cost by enabling the en-
68. The general tendency in road con- gineer to foresee and eliminate problems
struction projects has been to move away without wasted effort and extended dura-
from large detailed networks, thereby re- tion time. CPM has this advantage to offer
ducing the number of activities to within provided it is applied intelligently and with
the limits of manual computation. Even conviction . The problems peculiar to road
manual computation is being abandoned in construction are no bar to its use.
favour of graphical methods, although the 71. CPM has its limitations and prob-
arithmetical method is preferred for the lems; a particular difficulty is choosing the
more complex networks required for most su itable computer programme. Any-
bridges. This may only be a temporary one using CPM for the first time would be
phase of over-simplification, and there may well advised not to be too ambitious in its
be a swing back to more detailed networks application without first taking expert ad-
and the use of computers as more experi- vice.

882 A.R.R.B. PROCEED INGS


WINGATE - CPM TO PLAN AND CONTROL ROAD CONSTRUCTION PROJECTS
(DISCUSSIONS BY BLUNDELL AND HEALEY)

72. All the possible uses and advant- Further study and research, particularly by
ages of CPM on road construction projects users themselves, are essential if the maxi-
have probably not yet been fully explored. mum benefit from its use is to be obtained .

BIBLIOGRAPHY
1. Lockyer, K. G., A n Introduction to Critical Path Analysis, Sir Isaac Pitman
and Sons Ltd. (London, 1964) .
For the American view on the principles and application of CPM, the under-
mentioned are suggested.
2. O'Brien, J. J., CPM in Construction Management, McGraw Hill Book Co.
Inc. (New York, 1965) .
3. Antill, J. M. and Woodhead, R. W. , Critical Path Methods in Construction
Practice, John Wiley & Sons Inc. (New York, 1965) .

DISCUSSIONS

P. A. B L U N D EL L, B.E., M.Tech ., A .M.I.E.Aust., T he Shell Co. of Aust. Ltd ., New


South Wales
73. In many cases it would appear that in Australia we are using critical path
networks for the wrong purposes. It seems fair to state that networks are often
not constructed until after the commencement and completion dates of a project
are nominated, generally for other than engineering reasons. This then forces
engineers to construct a network to fit in with the stated completion time. Surely
we should first construct the network based on minimum cost and, if this com-
pletion time is unsatisfactory, the programme should then be 'crashed' until a
satisfactory completion date is obtained.

B. O. HE ALE Y, B.E. , A.M.I.E.Aust., Associate, R ankine and Hill, North Sydney, New
South Wales
74. The real valu e of critical path networks seems to the writer to have been
that, as a result, the familiar Gintt bar chart now means something. It has be-
come a factual expression of a situation when prepared on a basis that takes
account of the interrelationship between activities. To quote the author of the
paper, 'the networks do provide a yardstick by which the highway authorities can
judge the merits of programmes submitted with tenders.' This is the crux of it.
75. However, the emphasis throughout the paper is on the network. The
writer is reminded of a large multi-storey building project, where there was a
magnificent network on the wall of the site office. The site architect commented,
'that is of no use except to the man who drew it up. ' That was true.
76. CPM is a tool for management - not for the man on the job. The writer
has heard a management consultant suggest that the man on the job should be
given only the start date for each activity, not the fini sh dates, and obviously not

Volume 3, Part 2 (1966) 88>


WINGATE - C PM TO PLAN AND CONTROL ROAD C ONSTRU CTIO N PROJECTS
(DISC USSION BY MOFFAT)

the network. Once the job is planned by management, the tool is no longer re-
quired, the network is not referred to again, unless revisions are necessary.
77. There is no need to mark up critical lines on the network as suggested -
the critical activities are obvious on the bar chart if floats are shown there. The
critical activities have no float.
78. The appreciation of the existence of float times is the second great benefit
conferred by CPM. It is surprising that the author did not find contractors mak-
ing greater use of follow-up procedures after preparation of the bar chart by
adjusting activities within the float time to:
(a) even out manpower requirements,
(b) even out plant requirements, and
(c) adjust plant requirements to suit other concurrent jobs.
79 . It is also significant that no attempt is being made to 'crash' activities with
a view to cost reduction by a study of the project cost curve. Similarly, the owner
is not receiving the opportunity to use the float times to his advantage. It has been
calculated that if the late start is used on each activity instead of the early start
on each activity, on a $Aust.4m. job, with interest at 6 per cent, the saving to
the owner is $Aust.24,000 for the same date of completion.
80. It is agreed that 'all possible uses and advantages of CPM on road con-
struction projects have probably not yet been fully explored.' The author has
rendered the industry a great service in this review of present practice. It is to be
hoped that realization of the advantages will not be delayed further by failure to
appreciate that the advantages are beyond, and not inherent in, the network dia-
gram.
D. W. M 0 F FAT, B.E., A.M.I .E.Aust., Supervising Roads and Aerodromes Engineer,
Commonwealth Department of Work, New South Wales
81. The writer would agree with the statements in para. 11 but would add that,
whilst manual computation with up to say 90 to 100 activities is relatively easy, the
use of a computer is extremely economic of time, and as the author has stated,
the print-out is more easily understood than the network diagram for control
purposes.
82. The case histories quoted are most interesting but project D certainly
called for some positive thinking. It is difficult to understand how the embank-
ment construction mentioned in para. 30 could be allowed to cause the planning
to break down. Surely some estimate of time could have been made which, in
itself, would have constituted a target. Also, changes in design are certainly not
unknown and times can even be estimated for these in spite of the fact that
most designers affirm that one cannot programme inventiveness.
83. In para. 43 it is stated that little use was made of the actual network dia-
gram . This the writer understands and agrees with, but would suggest, however,
that an abridged time-scaled network diagram banded into like activities is of
great value for overall technical management.

884 A.R.R .B. PROCEEDINGS


WINGATE - CPM TO PLAN AND CONTROL ROAD CONSTRUCTION PROJECTS
(DISCUSSION BY TlNNI)

A. TIN N I, B.E., Department of Main Roads, New South Wales


84. After reading paper No. 278, persons unacquainted with CPM scheduling
could be left with an impression that the CPM is an all important discovery that
makes engineering decisions and saves the contractor's money. That this is not the
case deserves more emphasis. The CPM provides a means of graphically record-
ing logical engineering thought, whether simple or complex in nature. From this ,
deductions or decisions are made.

85. In para. 10, the author discusses the level of breakdown of activities. A
point that could be added to this is that the amount of detail in a network is
directly proportional to the quantity or output control methods required. If the
control unit or units for a particular activity are very small, the plotting, record-
ing and evaluating of them becomes very time consuming. Hence too much
detail in a network should be avoided.

86. In addition to the notes on the critical path in para. 12, the writer would
like to add that often it is beneficial to break up large activities, such as earth-
works, into various specific categories, e.g. earthworks requiring drilling and
blasting, winning by ripping and scraping or ripping and dozing and carting with
lorries. This automatically breaks up the work into sections and simultaneously
provides for better resources control and allocation requirement. It also provides
simpler means to exercise cost control.

87. The method of presentation, as described in para. 13, can vary of course.
The following has been used by the Department of Main Roads, New South
Wales, and has proved quite successful. On the vertical left-hand margin a dia-
grammatic sketch plan of the job is drawn. This shows the spli t-up of the job
into various sections of different characteristics. There is one basic chain of
activities for each section which is drawn horizontally. Along the various chains,
activities are grouped so that similar activities are shown in the same section of
the horizontal scale. The general break-up might take the form of: clearing,
drainage , earthworks, etc. Using this method, activities of a particular type can
quickly be identified in the network. The timings of the activities are presented
in the conventional CPM technique. The activity arrows could also show the
percentage split-up of the activity and be coloured in as the job progresses. The
progress of the job can be checked at any time by drawing an isochrone through
the network. Activities, that are to the left of thi s line and are not coloured in,
would be lagging. Those to the right of the line and are coloured, would be ahead
of schedule. Thus, if the network is kept up to date, progress can be evaluated at
a glance.

88. It is noted that the author does not mention job control methods in any
of the case history studies. It must be remembered that, to obtain full benefit
from a CPM network, strict and efficient job control methods must be developed
and used. The network becomes redundant to the organization if this is not done.

Volume 3, P art 2 (1966 )


WINGATE - C PM TO PLAN AND CONTROL ROAD CONSTRUCTION PROJECTS
(AUTHOR 'S CLOSURE)

AUTHOR ' S CLOSURE

89. The author disagrees with the view expressed that CPM is only a tool
for management, not for the engineer in charge of the job. The amount of detail
and type of information to be conveyed by the network can be varied to suit the
requirements of the main recipient. Top management will usually require differ-
ent information from that which the resident engineer and his staff require. But
the network itself (or a bar chart based upon the network) has important uses
throughout the execution of the project including forward planning on the site at
all levels. The issue of bar charts to site engineers and foremen, mentioned in
project E , illustrates this.
90. Some engineers no doubt prefer not to reveal finishing dates to their sub-
ordinates, and computer print-outs omitting this information are often used. The
practice is, however, of doubtful value particularly on the higher levels.
91. The author agrees that one of the main advantages of CPM is its ability
to point the way to the best use of resources. This characteristic was made use of
to some extent in all of the projects described. More can be done in this direction.
More too should be done on minimizing indirect costs, even at the expense of
direct costs on individual activities.
92. However, it must be remembered that road construction works are particu-
larly vulnerable to delays through adverse weather. Float times act as a buffer
against this and give flexibility to the plan. To eliminate float completely by using
all late starting times would eliminate flexibility. The savings gained could very
easily be lost and more.

886 A.R.R.B. PROCEEDINGS

S-ar putea să vă placă și