DIAL ‐ Phase 3A Expansion

Sensitivity: Unclassified
Date – 1St May 2019
Content
• Scope of Work & Completion target
• Phasing
• Airside
• Terminal
• Landside
• Progress
• Mobilization
• Engineering
• Procurement
• Construction

Sensitivity: Unclassified
Phase‐3A Works 2019…
Transition from Yr

Sensitivity: Unclassified
Phase‐3A Works
….To Yr 2022 NTP: 7th Mar 2019
Completion Timeline

Contractual Team’s target

39 36
Months Months
May ‘ 22 Feb’ 22

Sensitivity: Unclassified
Phase‐3A Works

Operational Requirements ‐
During Entire Construction
• 33 Operational Apron Stands

• 3 Operational Runways

• Two Taxiway access for Military Aircraft

• Three taxiway access to Runway 11‐29

• Three operational Check‐in Island and associated BHS in T1 Departure

Sensitivity: Unclassified
Phase‐3A Works‐ Terminal 1 New Domestic 
Terminal

• 40 MPPA
• 120 check‐in counters
• 74 security screening 
positions
• 22 Contact Gates
• 10 Arrival Baggage 
Belts

Terminal 1
Arrival‐ Part A Jun 20 (M16)
Node for Bussing Feb 21 (M24)
Balance Feb 22 (M36)
Sensitivity: Unclassified
Phase‐3A Works‐ Runways

Runways
New RWY 11L‐29R Sep 20 (M19)
Connected TWY to  Jun 21 (M27.5)
RWY11R‐29L
Refurbished RWY 09‐ Feb 22 (M36)
27
Sensitivity: Unclassified
Phase‐3A Works‐ Taxiways

Taxiways
North of  Apr 21 (M25.5)
RWY10‐28
Echo 2 Feb 22 (M36)
Sensitivity: Unclassified
Phase‐3A Works‐ Apron with New Stands

Apron with New Stands
Phase‐1:  Apr 20 (M14)
19 Stands
Phase‐2: Nov 20 (M21)
33 Stands
Phase‐3: Jun 21 (M27.5)
44 Stands
Phase‐4: Feb 22 (M36)
82 Stands
Sensitivity: Unclassified
Phase‐3A Works‐ Eastern Cross Taxiway
Eastern Cross 
Taxiway
• Elevated dual TWY‐
2.2km
• On bridge over central 
spine
• At grade over 
Radisson road 
underpass

Eastern Cross TWY
ECT Jun 21 (M28)

Sensitivity: Unclassified
Phase‐3A Works‐ Landside & Terminal 3
Area 
4

Area 
3
Landside & Terminal 3 Works
Landside Works
Area 
2
Area 1: Nov 21 (M33)
Access roads for T1
Area 2:  Dec 21 (M34)
Central Spine Road
Northern Access Road
Cargo Road
Aero city flyover
Cargo flyover
Area 3: Aug 21 (M30)
Area 
1 Radisson Road 
Area 4: Mar 21 (M25)
Terminal 3 modifications
Sensitivity: Unclassified
Phase‐3A Works

Target 
Completion

36

Months
Feb’ 22
Sensitivity: Unclassified
Ground Breaking Ceremony on 18th Apr’19 

T1 C DIAL Office Area ECT


Sensitivity: Unclassified
Content
• Phasing
• Airside
• Terminal
• Landside
• Progress
• Mobilization
• Engineering
• Procurement
• Construction

Sensitivity: Unclassified
Airside

Sensitivity: Unclassified
Work 
Commenced 
in Apr’ 19 
(M2)

Sensitivity: Unclassified
Apr’ 20 (M14)

19 Apron 
Stands

Sensitivity: Unclassified
Sep’ 20 (M19)

Runway 
11L‐29R

Sensitivity: Unclassified
Nov’ 20 
(M21)

33 Apron 
Stands 

Sensitivity: Unclassified
Apr’ 21 (M25.5)

Associated 
Taxiways 
to Runway 
10‐28

Sensitivity: Unclassified
Jun’ 21 (M27.5)

44 Apron 
Stands

Associated 
Taxiways 
to Runway 
11R‐29L

Sensitivity: Unclassified
Jun’ 21 (M28)

Eastern 
Cross 
Taxiways

Sensitivity: Unclassified
Feb’ 22 (M36)

82 Apron 
Stands

Runway 
09‐27

Taxiway 
Echo 2

Sensitivity: Unclassified
Content
• Phasing
• Airside
• Terminal
• Landside
• Progress
• Mobilization
• Engineering
• Procurement
• Construction

Sensitivity: Unclassified
Terminal

Sensitivity: Unclassified
Work 
Commenced 
in Apr’ 19 
(M2)

Sensitivity: Unclassified
Jun’ 20 (M16)

Terminal 
1 Arrival 
– Part A

Sensitivity: Unclassified
Nov’ 20 (M21)

Taxiway 
Charlie

Sensitivity: Unclassified
Feb’ 21 (M24)

Node ‐
Bussing

Sensitivity: Unclassified
Feb’ 22 (M36)

Terminal 
1D

Node & 
Pier

Terminal 
1A – Part 
B

Sensitivity: Unclassified
Terminal 3 Modifications
• Completion by 
Mar’21 (M25)

• Terminal 3 Upgradations 7th Check In Counter to be similar to 


present Counters
• Introduction of 7th Check In  6 13
Island
• Additional Baggage Reclaim Belt
• International to International  L
Transfers
• High Level Control Upgradation P

31
Sensitivity: Unclassified
Content
• Phasing
• Airside
• Terminal
• Landside
• Progress
• Mobilization
• Engineering
• Procurement
• Construction

Sensitivity: Unclassified
Landside

Sensitivity: Unclassified
Jun’ 20 (M16)

Roads in 
Front of 
T1 Arrival  T1 Arrival
Part A

Sensitivity: Unclassified
Nov’ 20 (M21)

Entry 
Ramp & 
Forecourt

Sensitivity: Unclassified
Oct’ 21 (M32)

Exit 
Ramp

Sensitivity: Unclassified
Nov’ 21 (M33)

All Works 
in front 
of T1

Sensitivity: Unclassified
Aug’ 21 (M30)

Radisson 
road and 
underpass

Sensitivity: Unclassified
Nov’ 21 (M33)

Roads
• NA
• CS 
• Cargo

Flyovers
• Aerocity 
• Cargo

• NA ‐ Northern Access Road
• CS ‐ Central Spine Road
•Sensitivity: Unclassified
Cargo Road
Content
• Phasing
• Airside
• Terminal
• Landside
• Progress
• Mobilization
• Engineering
• Procurement
• Construction

Sensitivity: Unclassified
EHS Implementation

Tool box talk conducted by P&M Department Pep Talk/ Tool box talk

Safety Statistics Status (As on Date)

Total Man‐hours worked 1,24,864

Sensitivity: Unclassified
Mobilisation
Staff – 217 Staff mobilised on site.

Workmen ‐ 359 Workmen mobilised on site.

P&M – Major P&M on site include
• 1 Batching Plant
• 7 Excavators
• 1 Grader
• 2 Soil Compactors
Lab Trials
Office & Lab Setup
• T1D Office is operational.
• PCC Works ongoing at DIAL office.
• L&T Office in Jet Warehouse is 50% completed
• L&T Office in T1C Mezzanine floor is completed
• Various Satellite offices are planned and under progress.
• Concrete and soil lab under progress

Source Identification and approval  T1 Departure Office
• Aggregate and soil
Sensitivity: Unclassified
Content
• Phasing
• Airside
• Terminal
• Landside
• Progress
• Mobilization
• Engineering
• Procurement
• Construction

Sensitivity: Unclassified
Engineering
Design Delivery Target
• Detailed Design & Drawings in BIM ‐ 6th Sep’19
• Shop Drawings & Construction Details – As per construction Schedule

Month Wise Projection
1800 1634
1600 1499
1400 1277
1200 1098
1000
800 712
600
400 313
200
0
April May June July Aug Sep
Planned Actual

Total Drawings – 6,533
Sensitivity: Unclassified
Content
• Phasing
• Airside
• Terminal
• Landside
• Progress
• Mobilization
• Engineering
• Procurement
• Construction

Sensitivity: Unclassified
Procurement Status
Order 
# Description  Remarks
Finalization

1 BHS, AGL & Earthwork Mid May Most critical. In Advanced stages.

2 Chillers End of May Technical discussions ongoing.

3 Electrical, HVAC, PHE, FDS, FPS End of Jun Site visit by vendors conducted.

Structural Steel, Façade, Roof 
4 End of Jul Enquiries floated.
Sheeting, Interior

5 Airport Systems End of Aug Enquiries floated.

80% orders targeted to be placed by end of Aug’19
Sensitivity: Unclassified
Content
• Phasing
• Airside
• Terminal
• Landside
• Progress
• Mobilization
• Engineering
• Procurement
• Construction

Sensitivity: Unclassified
Progress of Enabling Works
Laydown Yards

BP,  Rebar and 
F/W yard
BP, Aggregate stock area, 
Precast Yard, Central Lab., 
Satellite Office

HMP, WMM 
plant, BP

Rebar, Shuttering 
P&M Workshop,  Yard
Store Soil Stock area
Labour Colony HMP, WMM, 
Sensitivity: Unclassified Stockpile Area
Progress Photographs – Laydown Areas
Major Activities Ongoing
• Clearing & Grubbing
• Construction of Labour Colony
• Construction of Satellite Offices
• Earth Stockpiling

Sensitivity: Unclassified
Progress of Construction Works
Terminal
Completed (As 
# Area Activity Start Date Target End Date UOM Scope Remarks
on Date)
1 T1 C Part A Excavation 12‐04‐19 15‐06‐19 Cum 31,307 11,205 ‐
Just 
2 T1C Part A PCC 18‐04‐19 27‐06‐19 Cum 361
Commenced
3 Utility Building Excavation 24‐04‐19 25‐07‐19 Cum 38,676 177

Airside/Cityside
Completed (As 
# Area Activity Start Date Target End Date UOM Scope Remarks
on Date)
Clearing & 
1 ECT 4‐4‐19 30‐6‐19 Hectare 44 8.22
Grubbing

2 ECT E/W Filling 22‐4‐19 06‐10‐20 Cum 16 Lacs 1,250

Sensitivity: Unclassified
Progress Photographs

T1C – Excavation Works Barricading Works – Formwork Yard

Sensitivity: Unclassified
Progress Photographs

Works in ECT Area

Sensitivity: Unclassified
DIAL Phase 3A Project Team: 160 Staff (35 DIAL Staff + 125 Turner), 03 June 2019

Executive Director
IP Rao

Chief Development Officer


TJ Reddy

PMC In Charge Technical Assistant Officer / DC HR HSE Landside HSE Airside


Risk Manager TBD
Michael Slade TBD Diksha Singh Uddham Kumar S. Khurshid

DC Manager Safety Engineer 1


HR team to support Safety Engineer 1
Secretary Jitendra Bist Prabhat Narayan
Anjali Simon
DC Executive 1 DC Executive 4
Safety Engineer 2 Safety Engineer 2
GENERAL / Admin Personel
Rajesh Gupta Lakshmi Shreshta
Turner Subject
ADMINISTRATIVE, AND Matter Experts A. Srivastava
DC Executive 2 DC Executive 5
SAFETY TBD TBD
Safety Engineer 3

27 (10 DIAL + 17 TURNER) IT Support


Ved DC Executive 3
TBD

PLANNING DESIGN & ENGINEERING MEP & AIRPORT SYSTEMS LEGAL PROCUREMENT & CONTRACTS
Rajiv Ojha Darius Olczak H.S. Ahluwalia Hoysala Grandhi Rishi Joshi

Coordinated AEP Project Reporter Mgr. Civil 1 Sr. Architect Mgr SPTB Systems Mgr. Mechanical Electical Airport Systems Legal team to Asst. Manager Lead Contracts
Surender Baisoya Amogh Guru Amitava Samanta Subhadeep Gupta Varaprasad Kalari D.S. Chawla Prabhu Nanda Varun Gaud support Krishna Kumar Mhmd Hidayatulla
Planning MEP Sr. Eng IT Function Fuel / Utilities Mgr. Elec & PBB/VDGS/VHT
Plan Elec Sr. Eng. Planning Head Civil Mgr. Civil 2 Jr. Arch / Façade 1 Eng Sr. QS 1 Sr. QS 2
Sr.Eng /PTB Systems Sr. Eng - Ajay Krishan Chang
TBD Ashutosh Mourya Subrata Sen TBD TBD Vipul Muradia TBD
Niranjan Kr. TBD Singh Tyagi
PBB/VDGS/VHT
Airside Sr. Eng. Mgr. MEPF Jr. Arch / Façade 2 Fuel MEPF Eng 1 Sr. Electrical Eng Jr. QS
Eng
TBD Asjad Hameed Riddhi Takyar Hirak Mukherjee S.S. Negi TBD
TBD

PTB+Land Sr. Eng. Sr. Eng. AGL Engineer Fuel MEPF Eng 2 AGL Engineer BHS+X Ray Eng
Priya Singh Abhishek Verma TBD TBD TBD TBD

AGM BHS+X Ray Eng


ECT Sr. Eng. Jr. Eng. / D’man D’Man HVAC/PHE/FDP
Meenakshi Raina TBD TBD TBD
Joy Sadhu Khan

BIM Manager HVAC Engineer


TBD Praveen Barthwal

HVAC Sr. Eng. 1


Sr. Eng. Electrical
Chetan Jugran
TBD

HVAC Sr. Eng. 2


PLANNING, ENGINEERING, Sr. Engineer M&P
TBD
TBD
AND PROCUREMENT
HVAC Sr. Eng. 3
53 (16 DIAL + 37 TURNER) TBD
STAFFING KEY:
Turner Turner Turner Turner
DIAL
(Joined) (Approved) (Pending Approval) (Vacant)

CLIENT LOGO/NAME OR PROJECT TITLE


Sensitivity: Unclassified
DIAL Phase 3A Project Team

AIRSIDE PTB & Landside Lead QAQC


Nikolaos Karagiannidis William Steward Lovneed Jandu

Airside North Sr. Field Surveyor Airside South and ECT Interface Manager QAQC QAQC Sr. Eng
TBD TBD CB Prasad Sourabh Chourasia Regie Koshy D.S. Chouchan
Node/Pier Sr. Eng.
AGM Apron & Drain RWY / TXY Sr. Eng Field Surveyor 1 ECT and Roads RWY 11-29 Mgr. Landside Mgr PTB Manager T3 Sr. Engineer QAQC Eng. 1 QAQC Sr. Eng
1 Sr. Field Surveyor
TBD TBD Amit Malik SK Chauhan Paramhans Rai Vipin Chaudhari Amit Kumar Sinha Neeraj Thakur Ranvir Kr. Singh Ravi Sharma
Mukesh Roy
Sr. Engineer 1 Node/Pier Sr. Eng.
Apron Eng 1 RWY / TXY Eng 1 Field Surveyor 2 RWY 11-29 Sr. Eng. Landside Eng PTB Manager Field Surveyor T3 Engineer QAQC Eng. 2 QAQC Eng Elect
Shivakant 2
TBD TBD TBD Manumitra Singh TBD TBD TBD TBD Kuldeep Khandwal Pankaj Singh
Kushwaha TBD
Apron Eng 2 RWY / TXY Eng 2 Sr. Engineer 2 RWY 11-29 Eng. 1 Landscape Eng PTB Sr. Eng. 1 Node/Pier Eng. 1 QAQC Eng. 3 Comm. Mgr HOTO
TBD TBD TBD TBD TBD Amar Dev SIngh TBD Gaurav Tyagi TBD
RWY/TXY Asst Eng Engineer 1 RWY 11-29 Eng. 2 PTB Sr. Eng. 2
Apron Eng 3 Node/Pier Eng. 2 QAQC Eng. 4
1 TBD TBD TBD
TBD TBD Sudhakar Kumar
TBD
RWY/TXY Asst Eng Engineer 2 RWY 11-29 Eng. 3 PTB Civil Eng.
Apron Eng 4 Node/Pier Eng. 3
2 TBD TBD Tasaduq Shah
TBD TBD
TBD
Drain System Mgr Engineer 3 RWY 11-29 Eng. 4 PTB Civil Eng. 1
TBD TBD TBD TBD

Drain System Eng Engineer 4 PTB Civil Eng. 2


Pravindra Singh TBD TBD

AIRSIDE, TERMINAL
BUILDING, AND LANDSIDE
62 (9 DIAL + 53 TURNER)

Project Manager (Night Shift)


TBD
QAQC Eng. 1
Engineer 1 (Night) MEP Eng. 1 Jr. MEP Eng. 1 Safety Eng. 1
Engineer 4 (Night) (Night)
Manjeet Kumar TBD TBD TBD
Sabir Ali Khan
QAQC Eng. 2
Engineer 2 (Night) Engineer 5 (Night) MEP Eng. 2 Jr. MEP Eng. 2 Safety Eng. 2
(Night)
TBD TBD TBD TBD TBD
TBD
Safety Eng. 3 QAQC Eng. 3
Engineer 3 (Night) MEP Eng. 3
TBD (Night)
TBD TBD
TBD
QAQC Eng. 4
(Night)
TBD

NIGHT SHIFT
18 (0 DIAL + 18 TURNER)
STAFFING KEY:
Turner Turner Turner Turner
DIAL
(Joined) (Approved) (Pending Approval) (Vacant)

CLIENT LOGO/NAME OR PROJECT TITLE


Sensitivity: Unclassified
Thank You
Sensitivity: Unclassified

S-ar putea să vă placă și