From, To,
Sri USN Murthy, M Tech, MBA, LLM. The M/s Mega Engineering&Infrastructure Ltd,
SuperintendingEngineer, S-2, Technocrat Indl.Estate, Balanagar,
RWS& S-Circle,Adilabad, Balanagar,
Adilabad Dist. Hyderabad,Telangana-500037
Gentele Men,
Ref: 1)Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2)Agreement.No 04/2016-17,Dated:04/2016-17 of Superintending
Engineer,TDWSP Circle,Nirmal.
3)Minutes of Meetings of Hon’ble Chief Minister Review meeting held on
24.01.2017&01.05.2017&23.09.2017.
*****
With reference to the subject and vide reference 2nd cited,M/s Megha Engineering&Infrastructure
limited entered into the agreement for the work “Providing Drinking Water to Habitations in SRSP-
Adilabad segment in Adilabad district“Est.Cost 1530.00 Cr of SE TDWSP,Adilabad Dist including
Operation and maintenance for 10 years.
Vide reference 3rd cited during the review meeting conducted by Hon’ble Chief Minister on
24.01.2017, M/s Megha Engineering&Infrastructure limited was instructed to speed up the work
and it was agreed to complete the project on schedule time lines but not later than December 2017
.
And also during the review meeting held on 01.05.2017& 23.09.2017 by the Hon’ble Chief
Minister it was instructed to supply water upto village OHSR’s by 31st Dec 2017.Inspite of all these
instructions progress of work in SRSP Adilabad segement is very poor & not upto the mark .The
status of work as on today as follows.
Structures
Pipeline&Valves
Superintending Engineer,
RWS&S,Adilabad-Circle.
GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri USN Murthy, M Tech, MBA, LLM. The Superintending Engineer,
SuperintendingEngineer, RWS&S Circle,Mancherial.
RWS& S-Circle,Adilabad,
Sir,
*****
With advert to the subject and vide reference 1st cited above ,the agreement period for the work
“Design,Supply,Erection,Testing,Comissioning of electro mechanical works with SCADA &
Instrumentation along with associated substation and switch gear including all connected for various
pumping station located at various places in erstwhile Adilabad,Nizamabad&Karimnagar,including
defect liability period and operation and maintainance for 10 years”,concluded on 17.01.2018.
Vide reference 2nd&3rd cited above ,the Executive Engineer,RWS&S,MB Grid Nirmal & the
Executive Engineer,RWS&S,MB Grid Adilabad have submitted EOAT proposals for above said work
in SRSP Adilabad segment duly recommending EOAT upto 30th April,2018 based on the reasons
explained by the agency.
Hence,I request the Superintending Engineer,RWS&S,Circle Mancherial to grant EOAT upto 30th
April 2018 for SRSP Adilabad segment,for taking further necessary action.
Your’s faithfully,
Superintending Engineer,
RWS&S Circle,Adilabad.
From, To,
Sri USN Murthy, M Tech, MBA, LLM. The M/s Mega Engineering&Infrastructure Ltd,
SuperintendingEngineer, S-2, Technocrat Indl.Estate, Balanagar,
RWS& S-Circle,Adilabad, Balanagar,
Adilabad Dist. Hyderabad,Telangana-500037
Gentile Men,
Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No 04/2016-17,Dated:04/2016-17 of Superintending
Engineer,TDWSP Circle,Nirmal.
3) Standing Committee meeting of Zilla Parishad Adilabad on 10.02.2018.
*****
With reference to the subject and vide reference 2nd cited above, M/s Megha
Engineering&Infrastructure limited entered into the agreement for the work “Providing Drinking
Water to Habitations in SRSP-Adilabad segment in Adilabad district “Est.Cost 1530.00 Cr of SE
TDWSP,Adilabad Dist including Operation and maintenance for 10 years.
Vide reference 3rd cited during the standing committee meeting of Zilla Parishad
Adilabad on 10.02.2018, Chairperson, Zilla Parishad Adilabadexpressed displeasure regarding the
damages done to roads in Erstwhile Adilabad district during excavation for pipelines and instructed
to clear the debris on roads and complete the restoration of damaged roads immediately to avoid
any accidents and discomfort to the pelple.
In view of the same ,the agency M/s Megha Engineering&Infrastructure limited instructed to
restore damaged roads immediately while executing Mission Bhagiratha works and clear the debris
on roads and requested further to intimate the same to this office for record.
Superintending Engineer,
RWS&S,Adilabad-Circle.
GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri USN Murthy, M Tech, MBA, LLM. The Project Director,
SuperintendingEngineer, WAPCOS,AC Guards,
RWS& S-Circle,Adilabad, Hyderabad,Telangana-500004
Adilabad Dist.
Sir,
Hence it is requested to vet the above designs and drawings as per agreement conditions at an
early date and communicate.
Encl: As above
Yours Faithfully,
Superintending Engineer,
RWS&S,Adilabad-Circle.
GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
*****
Superintending Engineer,
RWS&S Circle,Adilabad.
To,
The Executive Engineer,RWS&S,MB Grid Division, Nirmal/Adilabad for necessary action.
The Deputy Executive Engineer,RWS&S,MB Grid Sub Division Nirmal/Bhainsa/Ichoda/Adilabad
for necessary action.
Copy Submitted to Chief Engineer-III,TDWSP Hyderabad for favour of information.
GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri USN Murthy, M Tech, MBA, LLM. The Chief Engineer-III,
SuperintendingEngineer, TDWSP,
RWS& S-Circle,Adilabad, Hyderabad.
Lr.No.06/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /EM Works/2017-18, Dt:03.01.2018
Sir,
*****
With reference to the subject and vide reference 2nd cited above ,the Executive
Engineer,RWS&S,MB Grid Adilabad has submitted the revised head calculations &Pump Performance
curves for the pumps at following Pump House.
1.Addagutta Sump to Mangurla OHBR
Your’s faithfully,
Superintending Engineer,
RWS&S Circle,Adilabad.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY AND SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri USN Murthy, M Tech, MBA, LLM. The Chief Engineer,
SuperintendingEngineer, TDWSP-III,RWS&S,
RWS& S-Circle,Adilabad, Hyderabad.
Sir,
Hence it is requested to vet the above designs and drawings as per agreement conditions at an
early date and communicate.
Encl: As above
Yours Faithfully,
Superintending Engineer,
RWS&S,Adilabad-Circle.
GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri USN Murthy, M Tech, MBA, LLM. The M/s Mega Engineering&Infrastructure Ltd,
SuperintendingEngineer, S-2, Technocrat Indl.Estate, Balanagar,
RWS& S-Circle,Adilabad, Balanagar,
Adilabad Dist. Hyderabad,Telangana-500037
Gentile Men,
Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No 04/2016-17,Dated:04/2016-17 of Superintending
Engineer,TDWSP Circle,Nirmal.
3) Standing Committee meeting of Zilla Parishad Adilabad on 10.02.2018.
*****
With reference to the subject and vide reference 2nd cited above, M/s Megha
Engineering&Infrastructure limited entered into the agreement for the work “Providing Drinking
Water to Habitations in SRSP-Adilabad segment in Adilabad district “Est.Cost 1530.00 Cr of SE
TDWSP,Adilabad Dist including Operation and maintenance for 10 years.
Vide reference 3rd cited during the standing committee meeting of Zilla Parishad
Adilabad on 10.02.2018, Chairperson, Zilla Parishad Adilabad expressed displeasure regarding the
damages done to roads in Erstwhile Adilabad district during excavation for pipelines and instructed
to clear the debris on roads and complete the restoration of damaged roads immediately to avoid
any accidents and discomfort to the pelple.
In view of the same ,the agency M/s Megha Engineering&Infrastructure limited instructed to
restore damaged roads immediately while executing Mission Bhagiratha works and clear the debris
on roads and requested further to intimate the same to this office for record.
Superintending Engineer,
RWS&S,Adilabad-Circle.
GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri USN Murthy, M Tech, MBA, LLM. The M/s Raghava Constructions,
SuperintendingEngineer, Narayanapuram(V),Peruvancha(P),
RWS& S-Circle,Adilabad, Khammam-507209.
Adilabad Dist.
GentleMen,
Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No AEE/01/2017-18,Dated:18.04.2017 of Superintending
Engineer,TDWSP Circle,Nirmal.
3) Minutes of Review meeting by Hon’ble Chief Minister,Telangana held on
24.08.2017
4) Inspection Report of Engineer-in-Chief RWS&S,Hyderabad,Dated:23.12.2017
5)Minutes of review meeting by Hon’ble Vice Chairman,TDWSCL,on 31.01.2018
6) Review and instructions of Secretary,RWS&S on 07.02.2018
7) Lr.No.Mission Bhagiratha/Pump Sets 1/2018,Dt:08.02.2018 of Chief Engineer,
TDWSP-III,Hyderabad.
8)Minutes of Meeting held on 20.03.2018 at Aranya Bhavan by Hon’ble
MLA’s,MLC’s of Erstwhile Adilabad District
9) Minutes of review meeting held on 12.04.2018 by Superintending
Engineer,RWS&S Circle,Adilabad.
*****
With reference to the subject and vide reference 2nd cited above, M/s Raghava Constructions
entered into the agreement for the work “Design, Supply, Erection, Testing and commissioning of
Electro mechanical works with SCADA & Instrumentation along with associated substation and
switch gear including all connected accessories for various Pumping stations located at various places
in erstwhile districts Adilabad,Nizamabad and Karimnagar Including, defects liability period and
operation and maintenance for 10 years (Package No.III).
Vide reference 3rd cited during the review meeting conducted by the Hon’ble Chief
Minister,Telangana on 24.08.2017,M/s.Raghava Construction was instructed to
procure,erect,commission all the pumpsets in phased manner from September to November 2017 .
Vide reference 5th&6th cited, during the review meetings with Hon’ble Vice Chairman,TDWSCL
&Secretary to Governament,RWS&S target dates for commissioning pumpsets and districts with bulk
water supply Were agreed and same were communicated through vide reference 7th cited for completing
the errection of pumpsets.
And also Hon’ble Minister For BC Welfare, Forest and Environment expressed displeasure
regarding progress of pumpsets in the review meeting held on 20.03.2018 and the agency M/s.Raghava
Constructions assured that by 05.04.2018 all the pumps will be errected
But it is regretted to inform thatInspite of all these several instructions the pace of erection of
pumpsets in SRSP-Adilabad Segment isVery poor due to which commissioning of bulk water supply
is getting delayed.Hence,M/s.Raghava Constructions Is hereby instructed to take necessary action
to increase the pace of erection of pumpsets so as to avoid any delays in commissioning bulk water
supply as it immensely benefits the public with potable water supply.
Superintending Engineer,
RWS&S,Adilabad-Circle.
GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Superintending Engineer
Mission Bhagiratha Circle-Adilabad
To,
Executive Engineer,RWS&S,MB Grid Division,Nirmal
Copy to Executive Engineer,(R&B) NH Division,Perkit for information.
Copy Submitted to Chief Engineer,TDWSP-III,Hyderabad for favour of information.
NOTICE-I
GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
And also vide reference 3rd cited the agreement period for the above work was completed
On 27.04.2018.But still as per the ground reports the pipeline laying ,errection of valves e.t.c are still in progress
due to which most of the habitations are not getting bulk water which include fluoride affected and
critical(transportation&hiring) habs.
Under these circumstances it is inevitable to the department to initiate action against you for
Failing in executions as per the agreed dates which is of serious concern as it is the flagship programme of
Governament which is aimed at drought free future of Telangana and also it immensely benifitis the public with
potable water supply.
The reasons for delay occurred regarding the above should be submitted to the undersigned with
in 48 hours for taking further necessary action.
Superintending Engineer
Mission Bhagiratha Circle-Adilabad
To,
M/s.Megha Engineering and Infrastructure Limited, S-2, Technocrat Indl.Estate,
Balanagar,Hyderabad,Telangana-500037.(emailed copy to the following email
ids:project4124@meilgroup.info,khs@meilgroup.com).
The Executive Engineers,RWS&S,MB Grid, Adilabad&Nirmal for initiating action against agency.
Copy submitted to Chief Engineer,TDWSP-III,Hyderabad for favour of information
Copy submitted to Engineer-in-Chief ,Hyderabad for favour of information
GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Ref:1.I&CAD (WRC-GRC)Dept,G.O.Rt.No.885,Dt:30.10.2017
Superintending Engineer
Mission Bhagiratha Circle-Adilabad
To,
Executive Engineer,RWS&S,MB Grid Division,Nirmal for taking necessary action.
Copy Submitted to Chief Engineer-III,TDWSP,Hyderabad for favour of information
GOVERNMENT OF TELANGANA
OFFICE OF THE Dy.EXECUTIVE ENGINEER, RWS&S SUB DIVISION, ADILABAD
From, To,
SriN.V.Ramana B.Tech. The Manager ,
Dy.Executive Engineer, Bharathi Airtel Limited,
RWS& S-Sub Division,Adilabad, Hyderabad.
Adilabad Dist.
It is to inform you that ,the department AIRTEL SIM card bearing No: 7995660
696 has been damaged on Dt:31.05.2018.
Your’s faithfully,
Dy.Executive Engineer,
RWS&S SD,Adilabad
NOTICE-I
GOVERNMENT OF TELANGANA
OFFICE OF THE EXECUTIVE ENGINEER, RWS&S,MB GRID DIVISION, ADILABAD
Inspite of all these instructions,based on ground report it was found that Pumpsets for Addagutta
Pumphouse are still not procured.
Under these circumstances it is inevitable to the department to initiate action against you as
even procurement of pumpsets is not completed which is of serious concern.
The reasons for delay occurred regarding the above should be submitted to the undersigned with
in 48 hours for taking further necessary action.
Superintending Engineer
Mission Bhagiratha Circle-Adilabad
To,
M/s.Raghava Constructions,Narayanapuram(V),Peruvancha(P),Khammam-507209.(emailed copy to the
following email id:sanath2@eivipl.com).
Copy submitted to Superintending Engineer,Mission Bhagiratha Circle,Adilabad for favour of information.
Copy submitted to Chief Engineer-III,TDWSP,Hyderabad for favour of information
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's),. The Branch Manager,
SuperintendingEngineer(FAC), Large Corporate Branch,
RWS& S-Circle,Adilabad, Bank of Commerce,
Adilabad Dist. Hyderabad,Telangana-500033
GentleMen,
*****
A copy of Bank Guarantee Extension for ₹:8,00,00,000-00 vide B.G.No.11100029316, Dated: 30.11.2016 of Oriental
Bank of Commerce,Large Corporate Branch,Hyderabad extended upto 28.05.2019issued to M/s. Megha Engineering
& Infrastructures Ltd., Hyderabadfor the work ““Construction of Intake well, WTP and Raw Water Pumping
main in Adilabad segment, Kaddam segment, Asifabad segment and Mancherial segment of
Telangana drinking Water supply project (TDWSP)”Est.cost of Rs.440.50 Crs is here with communicated
with a request to confirm the genuineness of the BGs extension at the earliest.
Yours faithfully,
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's),. The Zonal Manager,
SuperintendingEngineer(FAC), Hyderabad Zone,
RWS& S-Circle,Adilabad, Bank of India,
Adilabad Dist. Hyderabad,Telangana-500004
GentleMen,
Sub:- RWS&S Circle-Adilabad –SRSP Adilabad Segment-Extension of Validity of Bank
Guarantee-Confirmation of genuineness-Requested-Reg.
*****
Yours faithfully,
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's),. The Branch Manager,
SuperintendingEngineer(FAC), Large Corporate Branch,
RWS& S-Circle,Adilabad, Oriental Bank of Commerce,
Adilabad Dist. Hyderabad,Telangana-500033
GentleMen,
*****
A copy of Bank Guarantee Extension for ₹:8,00,00,000-00 vide B.G.No.11100029216, Dated: 30.11.2016 of Oriental
Bank of Commerce,Large Corporate Branch,Hyderabad extended upto 28.05.2019 issued to M/s. Megha
Engineering & Infrastructures Ltd., Hyderabadfor the work ““Adilabad District-TDWSP-Providing Drinking
Water to Habitations in SRSP-Adilabad segment in Adilabad District”under Telangana Drinking Water
Supply Project with an estimated cost of Rs.1530.00 Crs is here with communicated with a request to confirm
the genuineness of the BGs extension at the earliest.
Yours faithfully,
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer,
SuperintendingEngineer(FAC), TDWSP-III,RWS&S,
RWS& S-Circle,Adilabad, Hyderabad.
Adilabad Dist.
Lr.No.04/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Small Pumpset/2018-19, Dt:04.07.2018
Sir,
Vide reference 3rd cited above, the agency M/s Raghava Constructions which is executing the
Electromechanical works under SRSP Adilabad segment intimated that they are unable to execute the
Design, supply, Erection, testing &commissioning of pumpsets other than their scope of work(pumpsets
below 15 HP).
Where as Vide reference 4th cited Executive Engineer,RWS&S,MB Grid Division informed that
M/s.Megha Engineering & Infrastructure Ltd which is executing civil works has also given its unwillingness
in executing pumpsets other than in Electromechanical Agreement in Nirmal District and requested this
office to accord permission for entrusting pumpsets other than Electromechanical agreement to the third
party.
Hence,The Chief Engineer-III,TDWSP is hereby requested to accord permission for entrusting
pumpsets other than in Electromechanical agreement to third party in order to supply bulk water to all
the habitations in Nirmal district under SRSP Adilabad Segment within the targeted date.
Your’s faithfully,
Superintending Engineer(FAC),
RWS&S Circle,Adilabad.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer,
SuperintendingEngineer(FAC), TDWSP-III,RWS&S,
RWS& S-Circle,Adilabad, Hyderabad.
Adilabad Dist.
Lr.No.05/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Small Pumpset/2018-19, Dt:04.07.2018
Sir,
*****
With advert to the subject and vide references 1st and 2nd cited above, the work " Providing Drinking
Water to habitations under SRSP Adilabad segment in Adilabad district Est. cost 1530. Crores of SE,
TDWSP, Adilabad district including Operation & maintenance for 10 years.” is sanctioned under Mission
Bhagiratha and a provision is made in the approved estimate for the Erection of submersible pumpsets.
In this regard I am herewith submitting the 7 No. of approved Sub Estimates along with general
abstract for further scrutiny and technical approval.
Your’s faithfully,
Encls: Sub Estimates(7 Nos.)
Superintending Engineer(FAC),
RWS&S Circle,Adilabad.
GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
The immediate personal attention of the Executive Engineers,RWS&S,MB Grid & Intra
Divisions of Adilabad circle is invited to reference cited wherein it was informed that at certain locations BSNL
underground cables(Both Copper&OFC) were damaged due to Mission Bhagiratha works and accordingly
demand notes were raised and and payment for the same is pending.
In this regard,while enlcosing the copy of reference cited,all the Executive
Engineers,RWS&S,MB Grid & Intra Divisions of Adilabad circle hereby directed to go through the points raised
by BSNL and and submit a detailed report on the points related to their respective juirsidictions for taking
further necessary action.
Superintending Engineer(FAC)
RWS&S Circle-Adilabad
To,
The Executive Engineers,RWS&S,MB Intra Divisions,Nirmal&Adilabad.
The Executive Engineers,RWS&S,MB Grid Divisions,Nirmal&Adilabad.
Copy to the General Manager,BSNL,Adilabad for information.
Copy submitted to Collector&District Magistrate,Adilabad for favour of information
Copy submitted to Collector&District Magistrate,Nirmal for favour of information
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer,
SuperintendingEngineer(FAC), TDWSP-III,RWS&S,
RWS& S-Circle,Adilabad, Hyderabad.
Adilabad Dist.
Lr.No.06/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /EMW/2018-19, Dt:17.07.2018
Sir,
Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No AEE/01/2017-18,Dated:18.04.2017 of Superintending
Engineer,TDWSP Circle,Nirmal.
3)Lr.No.01/AEE1/ EE / SRSP-ADB /EMW/ADDAGUTTA/2018-19,Dated:13.07.2017 of Executive
Engineer,RWS&S,MB Grid Division,Adilabad.
*****
Vide reference 3rd cited, the Executive Engineer RWS&S, MB Grid Division,Adilabad has submitted the
Quality Plan,General Arrangement,Cross sectional drawings and Performance curves for Pumpsets and Motors at
Addagutta Sumpfor the work “Design, Supply, Erection, Testing and commissioning of Electro mechanical works
with SCADA & Instrumentation along with associated substation and switch gear including all connected
accessories for various Pumping stations located at various places in erstwhile districts Adilabad,Nizamabad and
Karimnagar Including, defects liability period and operation and maintenance for 10 years (Package No.III)” for
obtaining approval.
Hence,I kindly request sir to kindly approve the above at an early date.
Yours faithfully
Encl;As above
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Pay and Accounts Officer,
SuperintendingEngineer(FAC), Nirmal District.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Lr.No.07/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Bank Guarantee/2018-19, Dt:18.07.2018
Sir,
Sub: RWS&S Circle-Adilabad –SRSP Adilabad Segment- Extension of Validity of Bank Guarantee-
Submitted-Reg.
Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No 04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP
,Nirmal.
3) Lr.No.AEE1/TDWSP Nirmal Circle/SRSP-Adilabad Seg(Phase-II)/BG-Retention,
Dated :07.12.2016 of Superintending Engineer,TDWSP Circle,Nirmal.
4) Lr.No. AEE1/Extension BG(FSD)/MB Grid/2018,Dated:22.06.2018 of Executive
Engineer,RWS&S,MB Grid Division Nirmal.
5) CN/1110/LOANS/BG/2018-19,Dated:05.07.2018 of Oriental Bank of Commerce
.
*****
It is to submit that Vide reference 3rdcited a bank guarantee bearing No.11100029216, Dated:30.11.2016
issued on behalf of M/s.Megha Engineering and Infrastructure Limited,Hyderabad for the work “Adilabad
District-TDWSP-Providing Drinking Water to Habitations in SRSP-Adilabad Segment in Adilabad District” by
Oriental Bank commercefor an amount of Rs.8,00,00,00/- was submitted and the same was expired on
Dt:28.05.2018.
Whereas Vide reference 4th cited Executive Engineer,RWS&S,MB Grid Division,Nirmal has
submitted the Extension letter of above Bank Guarantee issued by bank upto 28.05.2019 and the Genuniess of
same was confirmed by the bank vide reference 5th cited.
Hence,I am herewith submitting the Extension letter of above Bank guarantee along with
Genuiness confirmation letter for taking further necessary action.
Yours faithfully
Encl;As above
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
.
Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of information.
Copy submitted to the Chief Engineer-III,RWS&S,Hyderabad for favour of information.
Copy to Executive Engineer,RWS&S,MB Grid Division,Adilabad for information.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Pay and Accounts Officer,
SuperintendingEngineer(FAC), Nirmal District.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Lr.No.08/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Bank Guarantee/2018-19, Dt:18.07.2018
Sir,
Sub: RWS&S Circle-Adilabad –SRSP Adilabad Segment- Extension of Validity of Bank Guarantee-
Submitted-Reg.
Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No 04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP
,Nirmal.
3) Lr.No.AEE1/TDWSP Nirmal Circle/SRSP-Adilabad Segment/BG-Retention,
Dated :07.12.2016 of Superintending Engineer,TDWSP Circle,Nirmal.
4) Lr.No. AEE1/Extension BG(FSD)/MB Grid/2018,Dated:22.06.2018 of Executive
Engineer,RWS&S,MB Grid Division Nirmal.
5) CN/1110/LOANS/BG/2018-19,Dated:05.07.2018 of Oriental Bank of Commerce
.
*****
It is to submit that Vide reference 3rd cited a bank guarantee bearing No.11100029316,
Dated:30.11.2016 issued on behalf of M/s.Megha Engineering and Infrastructure Limited,Hyderabad for the
work “RWS&S Circle,Adilabad-TDWSP-Construction of Intakewell,WTP and Raw Water Pumping Main in
Adilabad Segment,Kaddam Segment,Asifabad Segment and Mancherial Segment of Telangana Drinking Water
Supply Project(TDWSP)” by Oriental Bank commerce for an amount of Rs.8,00,00,00/- was submitted and the
same was expired on Dt:28.05.2018.
Whereas Vide reference 4th cited Executive Engineer,RWS&S,MB Grid Division,Nirmal has
submitted the Extension letter of above Bank Guarantee issued by bank upto 28.05.2019 and the Genuniess of
same was confirmed by the bank vide reference 5th cited.
Hence,I am herewith submitting the Extension letter of above Bank guarantee along with
Genuiness confirmation letter for taking further necessary action.
Yours faithfully
Encl;As above
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of information.
Copy submitted to the Chief Engineer-III,RWS&S,Hyderabad for favour of information.
Copy to Executive Engineer,RWS&S,MB Grid Division,Adilabad for information.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Pay and Accounts Officer,
SuperintendingEngineer(FAC), Nirmal District.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Lr.No.09/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Bank Guarantee/2018-19, Dt:23.07.2018
Sir,
Sub: RWS&S Circle-Adilabad –SRSP Adilabad Segment- Extension of Validity of Bank Guarantee-
Submitted-Reg.
Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No 04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP
,Nirmal.
3) Lr.No.01/AEE3/SE/RWSS(Adilabad)/BG/SRSP-ADB/,Dated:02.01.2018 of Superintending
Engineer,RWS&S Circle,Adilabad.
Dated :07.12.2016 of Superintending Engineer,TDWSP Circle,Nirmal.
4) Lr.No. AEE1/Extension BG(FSD)/MB Grid/2018,Dated:22.06.2018 of Executive
Engineer,RWS&S,MB Grid Division Nirmal.
5) Ref No.TZO:CR:BGC:2018-19:93,Dated:21.07.2018 of Bank of India.
.
*****
It is to submit that Vide reference 3rd cited a bank guarantee bearing No.5625IPEBG170124,
Dated:27.12.2017 issued on behalf of M/s.Megha Engineering and Infrastructure Limited,Hyderabad for the
work “Adilabad District-TDWSP-Providing Drinking Water to Habitations in SRSP-Adilabad Segment in Adilabad
District” by Bank of India for an amount of Rs.25,50,00,00/- was submitted and the same was expired on
Dt:26.06.2018.
Whereas Vide reference 4th cited Executive Engineer,RWS&S,MB Grid Division,Nirmal has
submitted the Extension letter of above Bank Guarantee issued by bank upto 26.06.2019 and the Genuniess of
same was confirmed by the bank vide reference 5th cited.
Hence,I am herewith submitting the Extension letter of above Bank guarantee along with
Genuiness confirmation letter for taking further necessary action.
Yours faithfully
Encl;As above
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of information.
Copy submitted to the Chief Engineer-III,RWS&S,Hyderabad for favour of information.
Copy to Executive Engineer,RWS&S,MB Grid Division,Adilabad for information.
Yours faithfully
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
To,
All the Executive Engineers,RWS&S,MB Grid &Intra of Adilabad circle for necessary action
Copy submitted to Chief Engineer-III,TDWSP,Hyderabad for favour of information
Copy submitted to Engineer-in-Chief,Hyderabad for favour of information
GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
The immediate personal attention of the Executive Engineers,RWS&S,MB Grid & Intra
Divisions of Adilabad circle noted in the address entry is invited to subject cited wherein a new form was
deployed &Instructions were issued to update the status of daily water supply to those habitations for which
bulk supply was already made on regular basis resembling the actual status.
Wherein it was observed by undersigned that updation is not done regularaly even after
several instructions.
Hence all the Executive Engineers,RWS&S,MB Grid&Intra of Adilabad circle are hereby
requested to issue necessary instructions to the field engineers to update the above form on daily basis as the
daily reports will be shared to the CMO dashboard for regular review.
Further it is to inform that if any deviations from the above will be viewed seriously and
necessary action will be initated against the defaulters.
Superintending Engineer(FAC)
RWS&S Circle-Adilabad
To,
The Executive Engineers,RWS&S,MB Intra Divisions,Nirmal&Adilabad.
The Executive Engineers,RWS&S,MB Grid Divisions,Nirmal&Adilabad.
Copy Submitted to the Chief Engineer-III,TDWSP,Hyderabad for favour of information
Copy submitted to the Engineer-in-Chief ,RWS&S,Hyderabad for favour of information
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad
RWS& S-Circle,Adilabad,
Adilabad Dist.
Sir,
Wherein the EOAT-I & EOAT-II which were accorded vide References 5th& 6th cited for the above
work are expired on 31st July 2018.Accordingly vide reference 7th cited M/s.Raghava Constructions submitted
the proposals for EOAT with for Electromechanical works of SRSP-Adilabad segment and requested for further
EOAT upto 30th November 2018.
And also the Executive Engineers MB Grid,Division, Nirmal has submitted the EOAT Proposals duly
recommending EOAT upto 30th November 2018 without imposing any penalty based on the reasons explained
by the agency, and further enclosed item wise details such as Check slip.
Hence I request the Chief Engineer-IV,TDWSP,Hyderabad to take further necessary action regarding
issuing of EOAT up to 30thNovember without imposing Penality.
Yours faithfully,
Encl;As above
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
Sir,
It is to submit that videreferences 1st, 2nd & 3rd cited, the Government has accorded administrative
sanction for the work “Design, Supply, Erection, Testing and commissioning of Electro mechanical works
with SCADA & Instrumentation along with associated substation and switch gear including all connected
accessories for various Pumping stations located at various places in erstwhile districts Adilabad,
Nizamabad and Karimnagar. Including, defects liability period and operation and maintenance for 10
years Package-III”. Further through the reference 4th cited agreement was concluded with M/s Raghava
Constructions Khammam for the same.
Wherein the EOAT-I & EOAT-II which were accorded vide References 5th& 6th cited for the above
work are expired on 31st July 2018.Accordingly vide reference 7th cited M/s.Raghava Constructions submitted
the proposals for EOAT with for Electromechanical works of SRSP-Adilabad segment and requested for further
EOAT upto 30th November 2018.
And also the Executive Engineers MB Grid,Division, Adilabad has submitted the EOAT Proposals duly
recommending EOAT upto 30th November 2018 without imposing any penalty based on the reasons explained
by the agency, and further enclosed item wise details such as Check slip.
Hence I request the Chief Engineer-I,TDWSP,Hyderabad to take further necessary action regarding
issuing of EOAT up to 30thNovember without imposing Penality.
Encl: EOAT Check slip, Revised Action plan.
Yours faithfully,
Encl;As above
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
****
Vide reference 2nd cited, all the Executive Engineers under this circle were requested to furnish
the detailed report on the damages done to BSNL underground cables due to Mission Bhagiratha works for
taking further necessary action.But the informations is still awaited by this office as on 07.09.2018.
In view of the above all the Executive Engineers under this cirlce are hereby directed to
furnish the above information immediately without further delay.
Superintending Engineer(FAC)
RWS&S Circle-Adilabad
To,
The Executive Engineers,RWS&S,MB Intra Divisions,Nirmal&Adilabad.
The Executive Engineers,RWS&S,MB Grid Divisions,Nirmal&Adilabad.
Copy Submitted to the Chief Engineer-I,RWS&S ,Hyderabad for favour of information
Copy Submitted to the Chief Engineer-VII,RWS&S ,Hyderabad for favour of information
Copy submitted to the Engineer-in-Chief ,RWS&S,Hyderabad for favour of information
MOST URGENT
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
Memo No.04/AEE3/DEE-II/Nirmal&Laxmanchanda/Grid/2018,Dated:18.09.2018
In view of the above Executive Engineer, MB Grid Division,Nirmal is hereby requested to submit the
detailed report on Physical and Financial Feasibility of above proposal under SRSP Adilabad Segment in
coordination with Executive Engineer,MB Intra Division,Nirmal.
Superintending Engineer(FAC)
RWS&S Circle-Adilabad
To,
The Executive Engineers,RWS&S,MB Grid Division,Nirmal.
Copy Submitted to the Chief Engineer-IV,RWS&S ,Hyderabad for favour of information
Copy submitted to the Engineer-in-Chief ,RWS&S,Hyderabad for favour of information
MOST URGENT
BySpeed Post
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
****
All the Executive Engineers&Dy.Executive Engineers,MB Grid&Intra of Adilabad District are hereby
requested to submit the authenticated copies of list of depopulated, deserted or Submerged habs along with
the list of newly formed habs in their respective jurisdiction immediately to this office for finalizing the
habitation count in Adilabad District.
Sd/-
Superintending Engineer(FAC)
RWS&S Circle-Adilabad
To,
The Executive Engineer,RWS&S,MB Grid/Intra Division,Adilabad.
The Dy.Executive Engineer,MB Grid Sub Division Adilabad/Ichoda.
The Dy.Executive Engineer,MB Intra Sub Division Adilabad/Boath/Utnoor.
Copy Submitted to
Chief Engineer-I,RWS&S,Hyderabad for favour of kind information
//t.c.f.b.o//
Dy.EE PA to SE
RWS&S Circle-Adilabad
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad
RWS& S-Circle,Adilabad,
Adilabad Dist.
Sir,
Wherein EOAT-I , EOAT-II&EOAT-III which were accorded vide References 3rd,4th&5th cited for
the above work were expired on 30th April 2018.Accordingly vide reference 6th cited M/s.MEIL,Hyderabad
submitted the proposals for EOAT and requested for further EOAT upto 31st December 2018.
And also the Executive Engineer MB Grid,Division, Nirmal has submitted the EOAT Proposals duly
recommending EOAT upto 31st December2018 without imposing any penalty based on the reasons explained
by the agency, and further enclosed Check slip.
Contd…..Page No.2
:::2:::
Hence,I am herewith submitting the Extension of Agreement Time(EOAT) proposals for the above said
work under SRSP-Adilabad Segment for your kind perusal and further necessary action.
Yours faithfully,
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.
Copy to Executive Engineer,MB Grid Division,Nirmal for information.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad
RWS& S-Circle,Adilabad,
Adilabad Dist.
Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-Nirmal District-Damages to BSNL
underground cables-Demand Notes -Submitted– Reg.
Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No 04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP
Circle,Nirmal.
3) Lr.No.GMTD/ADB/Plg/Way Leave Permissions/2010-19/Vol.I/67,Dated:02.07.2018 of
the General Manager,BSNL,Adilabad
4) T/o.Memo No.01/AEE3/DEE-II/BSNL/Cable Damages/2018,Dated:12.07.2018
5) Lr.No. MB GRID NIRMAL/SRSP Adilabad/BSNL/Demand Note/2018,Dated:26.09.2018
Of Executive Engineer,MB Grid Division,Nirmal.
*****
It is to submit that vide reference 3rd cited General Manager,BSNL,Adilabad has informed that at certain
locations BSNL underground cables(Both Copper&OFC) were damaged due to Mission Bhagiratha works and
accordingly demand notes were raised and payment for the same is pending.
Wherein vide reference 4th cited Executive Engineer,MB Grid Division,Nirmal was requested to go
through points raised by BSNL on the above damages and submit a detailed report for taking further necessary
action.
Accordingly vide reference 5th cited Excecutive Engineer,MB Grid Division informed that joint
inspection was conducted with BSNL officials and submitted the demand notes for the same.
In this regard I am herewith submitting the demand notes for an amount of Rs.22,73,665/- against the
damages done to underground BSNL Cables for kind perusal and further necessary action.
Yours faithfully,
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
Reminder-II
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
Superintending Engineer(FAC)
RWS&S Circle-Adilabad
To,
The Executive Engineer, MB Grid Division,Adilabad.
Copy Submitted to the Chief Engineer-I,RWS&S ,Hyderabad for favour of information
Copy submitted to the Engineer-in-Chief ,RWS&S,Hyderabad for favour of information
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The District Forest Officer,
SuperintendingEngineer(FAC), Nirmal District.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-FCA –Proposals for diversion of 4.945 Ha
of forest land in Kawal Tiger Reserve,Nirmal Division-for laying pipeline and construction of
structures in Segment-21/7(Madegaon) for providing safe drinking water to erstwhile Adilabad
District presently Nirmal District under Telangana Drinking Water Supply Project(TDWSP)-In-
Principle(Stage-I) approval accorded-Compliance report on conditions stipulated in Stage-I-
Submitted-Stage-II Clearance-Requested-Regarding.
*****
It is to submit that,vide reference 1st cited above the Government of Telangana, has accorded In-
Principle(Stage-I) approval for the diversion of 4.945 Ha of forest land in Kawal Tiger Reserve ,Nirmal
Division ,for laying of pipeline and construction of structures in Segment-21/7(Madegaon) for providing safe
drinking water to erstwhile Adilabad District presently Nirmal District under Telangana Drinking Water Supply
Project(TDWSP) in favour of Superintending Engineer,TDWSP(RWS&S) Circle,Nirmal stating thatgranting of
final approval will be considered on submission of compliance report on condtionals stipulated in In-
Princple(Stage-I) approval andaccordingly vide reference 2nd cited above Forest Divisional Officer,Nirmal
requested this office to submit the same for taking further necessary action.
In view of the above I am herewith submitting the Compliance report for conditions stipulated in In-
Principle(Stage-I) approval for diversion of 4.945 Ha forest land in Kawal Tiger Reserve,Nirmal Division for
taking further necessary action for granting Stage-II(Final) approval.
Yours faithfully,
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The District Forest Officer,
SuperintendingEngineer(FAC), Adilabad District.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-FCA –Proposals for diversion of 4.945 Ha
of forest land in Kawal Tiger Reserve,Nirmal Division-for laying pipeline and construction of
structures in Segment-21/7(Madegaon) for providing safe drinking water to erstwhile Adilabad
District presently Nirmal District under Telangana Drinking Water Supply Project(TDWSP)-In-
Principle(Stage-I) approval accorded-Compliance report on conditions stipulated in Stage-I-
Submitted-Stage-II Clearance-Requested-Regarding.
*****
It is to submit that,vide reference 1st cited above the Government of Telangana, has accorded In-
Principle(Stage-I) approval for the diversion of 4.945 Ha of forest land in Kawal Tiger Reserve ,Nirmal
Division ,for laying of pipeline and construction of structures in Segment-21/7(Madegaon) for providing safe
drinking water to erstwhile Adilabad District presently Nirmal District under Telangana Drinking Water Supply
Project(TDWSP) in favour of Superintending Engineer,TDWSP(RWS&S) Circle,Nirmal stating thatgranting of
final approval will be considered on submission of compliance report on condtionals stipulated in In-
Princple(Stage-I) approval andaccordingly vide reference 2nd cited above Forest Divisional Officer,Nirmal
requested this office to submit the same for taking further necessary action.
In view of the above I am herewith submitting the Compliance report for conditions stipulated in In-
Principle(Stage-I) approval for diversion of 4.945 Ha forest land in Kawal Tiger Reserve,Nirmal Division for
taking further necessary action for granting Stage-II(Final) approval.
Yours faithfully,
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's),. The Manager,
SuperintendingEngineer(FAC), Andhra Bank,
RWS& S-Circle,Adilabad, Balanagar Branch,
Adilabad Dist. Hyderabad,Telangana-5000037
GentleMen,
Sub:- RWS&S Circle-Adilabad –SRSP Adilabad Segment-Extension of Validity of Bank
Guarantee-Confirmation of genuineness-Requested-Reg.
*****
Yours faithfully,
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's),. The Manager,
SuperintendingEngineer(FAC), Andhra Bank,
RWS& S-Circle,Adilabad, Balanagar Branch,
Adilabad Dist. Hyderabad,Telangana-5000037
GentleMen,
*****
A copy of Extension of Bank Guarantee for Rs.73,72,159/- vide B.G.No.005715IGPER0082, Dated:
08.10.2018 of Andhra Bank, Balanagar Branch,Hyderabad extended from 09.10.2018 to 08.10.2013 issued
to M/s. Megha Engineering & Infrastructures Ltd., Hyderabadfor the work “Construction of Intake
Well,WTP and Raw Water Pumping Main in Adilabad Segment,Kaddam Segment,Asifabad Segment
and Mancherial Segment of Telangana Drinking Water Supply Project(TDWSP) with an estimated
cost of Rs.440.50 Crs is here with communicated with a request to confirm the genuineness of the BGs
extension at the earliest.
Yours faithfully,
Sir,
Sub: RWS&S Circle-Adilabad –SRSP Adilabad Segment- Extension of Validity of Bank Guarantee-
Submitted-Reg.
.
Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.
Copy submitted to the Chief Engineer-IV,RWS&S,Hyderabad for favour of kind information.
Copy to Executive Engineer,RWS&S,MB Grid Division,Nirmal for information.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Pay and Accounts Officer,
SuperintendingEngineer(FAC), Nirmal District.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Lr.No.18/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Bank Guarantee/2018-19, Dt:15.11.2018
Sir,
Sub: RWS&S Circle-Adilabad –SRSP Adilabad Segment- Extension of Validity of Bank Guarantee-
Submitted-Reg.
Yours faithfully
Encl;As above
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
.
Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.
Copy submitted to the Chief Engineer-III,RWS&S,Hyderabad for favour of kind information.
Copy to Executive Engineer,RWS&S,MB Grid Division,Adilabad for information.
Reminder-III
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
Superintending Engineer(FAC)
RWS&S Circle-Adilabad
To,
The Executive Engineer, MB Grid Division, Adilabad.
Copy Submitted to the Chief Engineer-I,RWS&S ,Hyderabad for favour of information
Copy submitted to the Engineer-in-Chief ,RWS&S,Hyderabad for favour of information
Sub:RWS&S Circle-Adilabad-Adilaba District –Habitations List-Remarks Called for the Draft list of
Habitations in Adilabad District-Reg.
Ref:1. Oral Instructions of Collector and District Magistrate Adilabad in the review meeting,
Dated:19.09.2018.
While enclosing the copy of draft list of Habitations in Adilabad District,All the Executive
Engineers and Deputy Executive Engineers of Adilabad District under this circle are hereby requested to verify
the draft list and submit the remarks/observations on the list of habitations mentioned in the draft by 18.11.2018
so as to finalize the habitation count of Adilabad District.
Further it is to inform that any remarks/objections after 18.11.2018 will not be considered.
Superintending Engineer(FAC)
RWS&S Circle-Adilabad
To,
The Executive Engineer, MB Grid Division, Adilabad.
The Executive Engineer, MB Intra Division, Adilabad.
The Deputy Executive Engineer,MB Grid Sub Division Adilabad/Ichoda.
The Deputy Executive Engineer,MB Intra Sub Division Adilabad/Boath/Utnoor.
Copy Submitted to the Chief Engineer-I,RWS&S ,Hyderabad for favour of information
Copy submitted to the Engineer-in-Chief ,RWS&S,Hyderabad for favour of information
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
Memo No.08/AEE3/DEE-II/GRID/PHASE-I/AGREEMENTS/2018,Dated:15.11.2018
Enclosure:Supplementary agreement-4
Superintending Engineer(FAC)
RWS&S Circle-Adilabad
To,
The Executive Engineer, MB Grid Division,Nirmal.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad
RWS& S-Circle,Adilabad,
Adilabad Dist.
It is to submit that videreferences 1st, 2nd & 3rd cited, the Government has accorded administrative
sanction for the work “Design, Supply, Erection, Testing and commissioning of Electro mechanical works
with SCADA & Instrumentation along with associated substation and switch gear including all connected
accessories for various Pumping stations located at various places in erstwhile districts Adilabad,
Nizamabad and Karimnagar. Including, defects liability period and operation and maintenance for 10
years Package-III”. Further through the reference 4th cited agreement was concluded with M/s Raghava
Constructions Khammam for the same.
Wherein the EOAT-I & EOAT-II which were accorded vide References 5th& 6th cited for the above
work are expired on 31st July 2018.Accordingly vide reference 7th cited EOAT proposal were submitted but
Vide reference 8th cited it was instructed to resubmit the proposal with certain clarifications
Hence I am herewith resubmitting EOAT proposals with clarifications and request the Chief Engineer-
IV,TDWSP,Hyderabad to take further necessary action regarding issuing of EOAT up to 30thNovember without
imposing Penality.
Yours faithfully,
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-Adilabad District-“Design, Supply, Erection,
Testing and commissioning of Electro mechanical works with SCADA & Instrumentation
along with associated substation and switch gear including all connected accessories for
various Pumping stations located at various places in erstwhile districts Adilabad,
Nizamabad and Karimnagar. Including, defects liability period and operation and
maintenance for 10 years Package-III”–Working Estimate-II -Submitted– Approval-
Requested-Reg.
*****
It is to submit that vide references 3rdcited, Executive Engineer,MB Grid Division,Adilabad has submitted
the Working Estimate-II for Electro Mechanical Works of SRSP Adilabad Segment in Adilabad District for favour
of kind approval and same is herewith submitted for further necessary action.
Encl:As above.
Yours faithfully,
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
By e-mailGOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
Ref:1. Oral Instructions of Collector and District Magistrate Adilabad in the review meeting,
Dated:19.09.2018.
2.T/o.Memo No.07/AEE3/DEE-II/ADB DISTRICT /Habitation Count/2018,Dated:15.11.2018
3.Lr.No.2/AEE1/MB Grid/Adilabad/ HAB COUNT /2018-19, Dt:17.11.2018 of Executive
Engineer, MB Grid Division,Adilabad.
With reference to the subject and vide reference 2nd cited above a draft list of habitations inAdilabad
District was communicated and all the Executive Engineers and Deputy Executive Engineers of Adilabad
District under this circle were requested to submit remarks/objections on the same if any by
18.11.2018.Wherein Vide reference 3rd cited above remarks were received only from Executive Engineer,MB
Grid Division,Adilabad office.
Superintending Engineer(FAC)
RWS&S Circle-Adilabad
To,
The Executive Engineer, MB Grid Division, Adilabad.
The Executive Engineer, MB Intra Division, Adilabad.
The Deputy Executive Engineer,MB Grid Sub Division Adilabad/Ichoda.
The Deputy Executive Engineer,MB Intra Sub Division Adilabad/Boath/Utnoor.
Copy Submitted to the Chief Engineer-I,RWS&S ,Hyderabad for favour of information
Copy submitted to the Engineer-in-Chief ,RWS&S,Hyderabad for favour of information
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The District Forest Officer,
SuperintendingEngineer(FAC), Adilabad District.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-FCA –Proposals for diversion of 4.945 Ha
of forest land in Kawal Tiger Reserve,Nirmal Division-for laying pipeline and construction of
structures in Segment-21/7(Madegaon) for providing safe drinking water to erstwhile Adilabad
District presently Nirmal District under Telangana Drinking Water Supply Project(TDWSP)-In-
Principle(Stage-I) approval accorded-Compliance report on conditions stipulated in Stage-I-
Submitted-Stage-II Clearance-Requested-Regarding.
*****
It is to submit that,vide reference 1st cited above the Government of Telangana, has accorded In-
Principle(Stage-I) approval for the diversion of 4.945 Ha of forest land in Kawal Tiger Reserve ,Nirmal
Division ,for laying of pipeline and construction of structures in Segment-21/7(Madegaon) for providing safe
drinking water to erstwhile Adilabad District presently Nirmal District under Telangana Drinking Water Supply
Project(TDWSP) in favour of Superintending Engineer,TDWSP(RWS&S) Circle,Nirmal stating thatgranting of
final approval will be considered on submission of compliance report on condtionals stipulated in In-
Princple(Stage-I) approval andaccordingly vide reference 2nd cited above Forest Divisional Officer,Nirmal
requested this office to submit the same for taking further necessary action.
In view of the above I am herewith submitting the Compliance report for conditions stipulated in In-
Principle(Stage-I) approval for diversion of 4.945 Ha forest land in Kawal Tiger Reserve,Nirmal Division for
taking further necessary action for granting Stage-II(Final) approval.
Yours faithfully,
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The District Forest Officer,
SuperintendingEngineer(FAC), Adilabad District.
RWS& S-Circle,Adilabad,
Adilabad Dist.
*****
It is to submit that,vide reference 1st cited above the Government of Telangana, has accorded In-
Principle(Stage-I) approval for the diversion of 4.945 Ha of forest land in Kawal Tiger Reserve ,Nirmal
Division ,for laying of pipeline and construction of structures in Segment-21/7(Madegaon) for providing safe
drinking water to erstwhile Adilabad District presently Nirmal District under Telangana Drinking Water Supply
Project(TDWSP) in favour of Superintending Engineer,TDWSP(RWS&S) Circle,Nirmal stating thatgranting of
final approval will be considered on submission of compliance report on condtionals stipulated in In-
Princple(Stage-I) approval andaccordingly vide reference 2nd cited above Forest Divisional Officer,Nirmal
requested this office to submit the same for taking further necessary action.
In view of the above I am herewith submitting the Compliance report for conditions stipulated in In-
Principle(Stage-I) approval for diversion of 4.945 Ha forest land in Kawal Tiger Reserve,Nirmal Division for
taking further necessary action for granting Stage-II(Final) approval.
Yours faithfully,
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The District Forest Officer,
SuperintendingEngineer(FAC), Adilabad District.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-FCA –Proposals for diversion of 4.945 Ha
of forest land in Kawal Tiger Reserve,Nirmal Division-for laying pipeline and construction of
structures in Segment-21/7(Madegaon) for providing safe drinking water to erstwhile Adilabad
District presently Nirmal District under Telangana Drinking Water Supply Project(TDWSP)-In-
Principle(Stage-I) approval accorded-Compliance report on conditions stipulated in Stage-I-
Submitted-Stage-II Clearance-Requested-Regarding.
In view of the above I am herewith submitting the Compliance report for conditions stipulated in In-
Principle(Stage-I) approval for diversion of 4.945 Ha forest land in Kawal Tiger Reserve,Nirmal Division for
taking further necessary action for granting Stage-II(Final) approval.
Yours faithfully,
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The District Forest Officer,
SuperintendingEngineer(FAC), Adilabad District.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-FCA –Proposals for diversion of 4.945 Ha
of forest land in Kawal Tiger Reserve,Nirmal Division-for laying pipeline and construction of
structures in Segment-21/7(Madegaon) for providing safe drinking water to erstwhile Adilabad
District presently Nirmal District under Telangana Drinking Water Supply Project(TDWSP)-In-
Principle(Stage-I) approval accorded-Compliance report on conditions stipulated in Stage-I-
Submitted-Stage-II Clearance-Requested-Regarding.
*****
It is to submit that,vide reference 1st cited above the Government of Telangana, has accorded In-
Principle(Stage-I) approval for the diversion of 4.945 Ha of forest land in Kawal Tiger Reserve ,Nirmal
Division ,for laying of pipeline and construction of structures in Segment-21/7(Madegaon) for providing safe
drinking water to erstwhile Adilabad District presently Nirmal District under Telangana Drinking Water Supply
Project(TDWSP) in favour of Superintending Engineer,TDWSP(RWS&S) Circle,Nirmal stating thatgranting of
final approval will be considered on submission of compliance report on condtionals stipulated in In-
Princple(Stage-I) approval andaccordingly vide reference 2nd cited above Forest Divisional Officer,Nirmal
requested this office to submit the same for taking further necessary action.
In view of the above I am herewith submitting the Compliance report for conditions stipulated in In-
Principle(Stage-I) approval for diversion of 4.945 Ha forest land in Kawal Tiger Reserve,Nirmal Division for
taking further necessary action for granting Stage-II(Final) approval.
Encl:Compliance Report(6 Sets)
Yours faithfully,
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The District Forest Officer,
SuperintendingEngineer(FAC), Adilabad District.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-FCA –Proposals for diversion of 4.945 Ha
of forest land in Kawal Tiger Reserve,Nirmal Division-for laying pipeline and construction of
structures in Segment-21/7(Madegaon) for providing safe drinking water to erstwhile Adilabad
District presently Nirmal District under Telangana Drinking Water Supply Project(TDWSP)-In-
Principle(Stage-I) approval accorded-Compliance report on conditions stipulated in Stage-I-
Submitted-Stage-II Clearance-Requested-Regarding.
*****
It is to submit that,vide reference 1st cited above the Government of Telangana, has accorded In-
Principle(Stage-I) approval for the diversion of 4.945 Ha of forest land in Kawal Tiger Reserve ,Nirmal
Division ,for laying of pipeline and construction of structures in Segment-21/7(Madegaon) for providing safe
drinking water to erstwhile Adilabad District presently Nirmal District under Telangana Drinking Water Supply
Project(TDWSP) in favour of Superintending Engineer,TDWSP(RWS&S) Circle,Nirmal stating thatgranting of
final approval will be considered on submission of compliance report on condtionals stipulated in In-
Princple(Stage-I) approval andaccordingly vide reference 2nd cited above Forest Divisional Officer,Nirmal
requested this office to submit the same for taking further necessary action.
In view of the above I am herewith submitting the Compliance report for conditions stipulated in In-
Principle(Stage-I) approval for diversion of 4.945 Ha forest land in Kawal Tiger Reserve,Nirmal Division for
taking further necessary action for granting Stage-II(Final) approval.
Yours faithfully,
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The District Forest Officer,
SuperintendingEngineer(FAC), Adilabad District.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-FCA –Proposals for diversion of 4.945 Ha
of forest land in Kawal Tiger Reserve,Nirmal Division-for laying pipeline and construction of
structures in Segment-21/7(Madegaon) for providing safe drinking water to erstwhile Adilabad
District presently Nirmal District under Telangana Drinking Water Supply Project(TDWSP)-In-
Principle(Stage-I) approval accorded-Compliance report on conditions stipulated in Stage-I-
Submitted-Stage-II Clearance-Requested-Regarding.
*****
It is to submit that,vide reference 1st cited above the Government of Telangana, has accorded In-
Principle(Stage-I) approval for the diversion of 4.945 Ha of forest land in Kawal Tiger Reserve ,Nirmal
Division ,for laying of pipeline and construction of structures in Segment-21/7(Madegaon) for providing safe
drinking water to erstwhile Adilabad District presently Nirmal District under Telangana Drinking Water Supply
Project(TDWSP) in favour of Superintending Engineer,TDWSP(RWS&S) Circle,Nirmal stating thatgranting of
final approval will be considered on submission of compliance report on condtionals stipulated in In-
Princple(Stage-I) approval andaccordingly vide reference 2nd cited above Forest Divisional Officer,Nirmal
requested this office to submit the same for taking further necessary action.
In view of the above I am herewith submitting the Compliance report for conditions stipulated in In-
Principle(Stage-I) approval for diversion of 4.945 Ha forest land in Kawal Tiger Reserve,Nirmal Division for
taking further necessary action for granting Stage-II(Final) approval.
Yours faithfully,
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Wherein Vide reference 2nd and 3rd Cited above, Executive Engineer,MB Grid Division,Nirmal has
submitted the Defect Liability Period(DLP) certificates pertaining to MB Grid Sub Division,Nirmal and
Bhainsahaving subwork wise starting date of Defect Liability Period.
In this regard I am herewith submitting the Defect Liability Certificates(DLP) for subworksof above
work under MB Grid Division,Nirmal for your kind perusal and further necessary action.
Yours faithfully,
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment – “Construction of Intakewell,WTP and Raw Water
Pumping Main in Adilabad Segment,Kaddam Segment,Asifabad Segment and Mancherial Segment of
Telangana Drinking Water Supply Project(TDWSP)”- Defect Liability Period(DLP) Certificate-
Submitted-Reg.
*****
It is to submit that , vide reference 1st cited above an agreement was concluded with M/s.Megha
Engineering & Infrstructures Limited,Hyderabad for the work “Construction of Intakewell,WTP and Raw
Water Pumping Main in Adilabad Segment,Kaddam Segment,Asifabad Segment and Mancherial
Segment of Telangana Drinking Water Supply Project(TDWSP)”
Wherein Vide reference 2nd Executive Engineer,MB Grid Division,Nirmal has submitted the Defect
Liability Period(DLP) certificate for sub works under above work pertaining toMB Grid Sub Division Nirmal
,having subwork wise starting date of Defect Liability Period.
In this regard I am herewith submitting the Defect Liability Certificate(DLP) for subworks of above
work pertaining to MB Grid Division,Nirmal for your kind perusal and further necessary action.
Yours faithfully,
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad.
RWS& S-Circle,Adilabad,
Adilabad Dist.
*****
It is to submit that , vide reference 2nd cited above Executive Engineer,MB Grid Division,Nirmal has
submitted the Working Estimate-II for the work “Providing Drinking Water to Habitations in SRSP Adilabad
Segment in Adilabad District”Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District Including Operation &
Maintenance for 10 Years for favour of kind approval .
Encl:Working Estimate-II
Yours faithfully,
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Sir,
Wherein vide reference 3rd cited EOAT-I ,which was accorded for the above work was expired on
10.12.2018 and accordingly vide reference 4th cited M/s.MEIL, Hyderabad submitted the proposals for EOAT
and requested this office for further EOAT upto 31stJuly 2019.
And also vide reference 5th and 6th cited above the Executive Engineers MB Grid,Division, Nirmal &
Adilabad has submitted the EOAT Proposals for the same based on the reasons explained by the agency, and
further enclosed Check slip.
Contd…..Page No.2
:::2:::
Hence,I am herewith submitting the Extension of Agreement Time(EOAT) proposals for the above said
work under SRSP-Adilabad Segment for your kind perusal and further necessary action.
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
Reminder-IV
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
Superintending Engineer(FAC)
RWS&S Circle-Adilabad
To,
The Executive Engineer, MB Grid Division, Adilabad.
Copy Submitted to the Chief Engineer-I,RWS&S ,Hyderabad for favour of information
Copy submitted to the Engineer-in-Chief ,RWS&S,Hyderabad for favour of information
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Enclosure:As Above
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To,
The Executive Engineer, MB Grid Division, Adilabad
Copy to Executive Engineer,I&CADD,Penganga Project Division,Adilabad for information.
Copy Submitted to the Chief Engineer-I,Mission Bhagiratha ,Hyderabad for favour of kind information.
Copy submitted to the Engineer-in-Chief ,Mission Bhagiratha,Hyderabad for favour of information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-Adverse News Published in Andhrajyothi News Paper on
Date:29.12.2018-With Caption “Manchi Neellu Maha Prabho”-Rejoinder-Submitted-Reg.
Ref: Arising
*****
It is to submit that,Adverse News was published in Andhrajyothi News Paper on Date:29.12.2018,
With caption “Manchi Neellu Maha Prabho”inKhandala Panchayath of Adilabad District.
In this regard, it is submitted that I personally visited Khandala village which was mentioned in in above paper
clipping and enquired withvillagersnamely1.PoojaBhai,2.Gopal,3.Sikindar,4.Aruna,5.Sunilwho stated that
they are receving Mission Bhagiratha Water everyday for a duration of nearly 1hour.Further they stated that
only on Date:29.12.2018 the water was slightly muddy due to which they did not utlizeMission Bhagiratha
water on Dt:29.12.2018& 30.12.2018.
And further it is to submit that on Dt:31.12.2018 there is a leakage in 1200mm Dia, MS Pumping main
in Nirmal due to which water is not supplied to Adilabad and supply will resume from Date:01.01.2019 and will
be supplied regularly.
Yours faithfully,
Superintending Engineer(FAC),
Mission BhagirathaCircle, Adilabad.
Copy submitted to the Engineer-in-Chief,Mission Bhagiratha ,Hyderabad for favour of kind information.
Copy Submitted to Collector &District Magistrate ,Adilabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) The Executive Engineer,
SuperintendingEngineer(FAC), Irrigation&CADD,
Mission Bhagiratha Circle,Adilabad, Penganga Project Division,
Adilabad Dist. Adilabad
Sir,
Wherein vide reference 2nd cited,Executive Engineer,MB Grid Division,Adilabad was requestedto
submit Action Taken Report for above damages and same was submitted to this office vide reference 3 rd cited
above.
In this regard I am herewith submitting the Action Taken Report on damages done to Lower Penganga
Project structures and Machinery due to opening of Mission Bhagiratha Scour Valve for information and
necessary action.
Enclosure:As Above
Yours faithfully,
Superintending Engineer(FAC),
Mission BhagirathaCircle, Adilabad.
Copy To:
Executive Engineer,MB Grid Division,Adilabad for information and necessary action.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) The Superintending Engineer,
SuperintendingEngineer(FAC), Godavari Valley Circle No.1,
Mission Bhagiratha Circle,Adilabad, SriramSagar Project-503219,
Adilabad Dist. Nizamabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment(No.21)-SRSP Reservior-Maintaining
Minimum Draw Down Level(MDDL)-Reg.
Further it is to inform that,during the review meeting with Hon’ble Chief Minister of Telangana ,on
Dt:30.06.2018 it was instructed that under any circumstances the water levels in reservoirs shall not go below
prescribed MDDL’s without prior consent of concerned Executive Engineer of Mission of Bhagiratha and same
instruction were again issued vide reference 3rd&4th cited above.
In this regard,it is requested sir to kindly instruct concerned officials to maintain Minimum Draw
Down Level(MDDL) in SRSP Reservior as per the Governament instructions so as to avoid any drinking water
scarcity in ensuing summer-2019 as it serves Adilabad(254 Habs),Boath(480 Habs),,Nirmal(209 Habs)
Constituencies under this circle.
Enclosure:As Above
Yours faithfully,
Superintending Engineer(FAC),
Mission BhagirathaCircle, Adilabad.
Copy To:
Executive Engineer,MB Grid Division,Nirmal for information and with request to Co-ordinate with concerned
Irrigation officials in Maintaining MDDL and report compliance.
Copy Submitted to:
Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of Kind information.
Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of Kind information.
Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
The Collector&District Magistrate,Adilabad for favour of Kind information
The Collector&District Magistrate,Nirmal for favour of Kind information
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) The Superintending Engineer,
SuperintendingEngineer(FAC), Irrigation Circle,Nirmal,
Mission Bhagiratha Circle,Adilabad, Nirmal District,
Adilabad Dist. .
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment(No.21)-Gaddenna Project-Maintaining
Minimum Draw Down Level(MDDL)-Reg.
Further it is to inform that,during the review meeting with Hon’ble Chief Minister of Telangana ,on
Dt:30.06.2018 it was instructed that under any circumstances the water levels in reservoirs shall not go below
prescribed MDDL’s without prior consent of concerned Executive Engineer of Mission of Bhagiratha and same
instruction were again issued vide reference 3rd&4th cited above.
In this regard,it is requested sir to kindly instruct concerned officials to maintain Minimum Draw
Down Level(MDDL) in Gaddenna Reservior as per the Governament instructions so as to avoid any drinking
water scarcity in ensuing summer-2019 as it serves Mudhole(248 Habs) Constituency and Bhainsa ULB under
this circle.
Enclosure:As Above
Yours faithfully,
Superintending Engineer(FAC),
Mission BhagirathaCircle, Adilabad.
Copy To:
Executive Engineer,MB Grid Division,Nirmal for information and with request to Co-ordinate with concerned
Irrigation officials in Maintaining MDDL and report compliance.
Copy Submitted to:
Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of Kind information.
Chief Engineer(Projects),I&CADD Department,Adilabad,for favour of kind information.
Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
The Collector&District Magistrate,Nirmal for favour of Kind information
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Ref: -
.
****
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To,
The Executive Engineer,MB Intra Division,Adilabad.(w.e)
The Executive Engineer,MB Grid Division,Adilabad/Asifabad.(w.e)
The Dy.Executive Engineers,MB Intra Sub Division Adilabad/Boath/Utnoor(w.e).
The Dy.Executive Engineers,MB Grid Sub Division Adilabad/Ichoda /Kerameri.(w.e)
The All the Assistant Executive Engineers/Assistant Engineers of Adilabad District through Concerned
Dy.EE’s Mission Bhagiratha.(w.e)
The Executing Agencies through concerned Executive Engineers,Mission Bhagiratha(w.e)
Copy Submitted to the Chief Engineer-I,Mission Bhagiratha ,Hyderabad for favour of kind information.
Copy submitted to the Engineer-in-Chief ,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) The Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
*****
It is to submit that , vide reference 3rd cited above Executive Engineer,MB Grid Division,Adilabad has
submitted the Working slip for Scattered(Isolated) habs for Rs.1130.00 Lakhs in Adilabad District as Hon’ble
Chief Minister of Telangana instructed to covered each and every habitation in the state under the work
“Providing Drinking Water to Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost
1530.00 Cr of SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years
Encl:Work Slip for Scatter Habs
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) The Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
It is to submit that videreferences 1st, 2nd & 3rd cited, the Government has accorded administrative
sanction for the work “Design, Supply, Erection, Testing and commissioning of Electro mechanical works
with SCADA & Instrumentation along with associated substation and switch gear including all connected
accessories for various Pumping stations located at various places in erstwhile districts Adilabad,
Nizamabad and Karimnagar. Including, defects liability period and operation and maintenance for 10
years Package-III”. Further through the reference 4th cited agreement was concluded with M/s Raghava
Constructions Khammam for the same.
Wherein the EOAT-I & EOAT-II which were accorded vide References 5th& 6th cited for the above
work are expired on 31st July 2018.Accordingly vide reference 7th cited M/s.Raghava Constructions submitted
the proposals for EOAT with for Electromechanical works of SRSP-Adilabad segment and requested for further
EOAT upto 30th March 2019.
And also the Executive Engineers MB Grid,Division, Nirmal has submitted the EOAT Proposals EOAT
upto 30th March 2019 without imposing any penalty based on the reasons explained by the agency, and further
enclosed item wise details such as Check slip.
Hence,It is requested sir to kindly accord EOAT upto 30.03.2019 without any penalty.
Encl:As Above.
Yours faithfully,
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) The Chief Engineer-I,
SuperintendingEngineer(FAC), TDWSP,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
It is to submit that videreferences 1st, 2nd & 3rd cited, the Government has accorded administrative
sanction for the work “Design, Supply, Erection, Testing and commissioning of Electro mechanical works
with SCADA & Instrumentation along with associated substation and switch gear including all connected
accessories for various Pumping stations located at various places in erstwhile districts Adilabad,
Nizamabad and Karimnagar. Including, defects liability period and operation and maintenance for 10
years Package-III”. Further through the reference 4th cited agreement was concluded with M/s Raghava
Constructions Khammam for the same.
Wherein the EOAT-I & EOAT-II which were accorded vide References 5th& 6th cited for the above
work are expired on 31st July 2018.Accordingly vide reference 7th cited M/s.Raghava Constructions submitted
the proposals for EOAT with for Electromechanical works of SRSP-Adilabad segment and requested for further
EOAT upto 30th March 2019.
And also the Executive Engineers MB Grid,Division, Adilabad has submitted the EOAT Proposals upto
th
30 March 2019 without imposing any penalty based on the reasons explained by the agency, and further
enclosed item wise details such as Check slip.
Hence,It is requested sir to kindly accord EOAT upto 30.03.2019 without any penalty.
Encl:As Above.
Yours faithfully,
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
To,
Executive Engineers,MB Grid Division Adilabad circle for necessary action.
Copy to Prinicipal(FAC),S.G. Govt.Polytechnic,Adilabads for information.
Copy submitted to Collector &District Magistrate,Adilabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) The Principal,
SuperintendingEngineer(FAC), S.G.Govt.Polytechnic College,
Mission Bhagiratha Circle,Adilabad, Adilabad.
Adilabad Dist.
Lr.No.37/AEE3/SE/MB/ SRSP Adilabad/Bulk Water Connection /2018-19, Dt: 10. 01.2019
Sir,
It is to submit that ,your request for Mission Bhagiratha Water Connection received by this office on
Dt:05.01.2019.
In this regard it is to inform that your college falls under the jurisdiction of Adilabad Municipality and
hence forth you are requested to approach Adilabad Municipality for Water Connection.
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Nirmal.
Copy Submitted to:
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) Chief Engineer-I ,
SuperintendingEngineer(FAC), Mission Bhagiratha,Hyderabad
Mission Bhagiratha Circle,Adilabad,
Adilabad Dist.
Sir
Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District-SRSP-Adilabad Segment-Isolated/Scattered
Habs-Detailed Report-Submitted-Reg.
*****
It is to submit that,vide reference 1sit cited above Hon’ble Chief Minister, Governament of Telanga
instructed to cover left over scattered habitations in the state under Mission Bhagiratha irrespective of the
cost.Accordinly a joint inspection was conducted by the undersigned along with EE,MB Grid Division,Adilabad
and Dy.EE&A.E.MB Grid SD Adilabad along with a representative from main grid agency M/s.MEIL for
identifying the isolated habs.
During the Joint inspection 8 Habs (Annexure enclosed) were identified as isolated/scattered in
Adilabad District under SRSP-Adilabad Segment . Executive Engineer stated that out these 8 Habs 4 Habs
were proposed to be covered in orginal estimate i.e. under 20 KL,30 Mts staging OHBR at Punaguda and same
structure was later deleted as Forest department denied permissions stating these are encroached/unauthorized
habitations and remaining 4 habs were identified later which are also encroached habitations as stated by forest
department .Furhter Executive Engineer stated that forest permissions are needed for proceeding for any further
work in these habitations.
Wherein vide reference 2nd cited above,Executive Engineer,MB Grid Division,Adilabad submitted the
estimate of Cost 1130.00 Lakhs for covering the above 8 isolated habs under Mission Bhagiratha as a workslip
under Main Grid works of SRSP-Adilabad segment stating that this amount can be met from savings of Main
Grid Works and same was submitted by this office vide reference 3rd cited above.
Enclosure:As above
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy submitted to The Engineer-in-Chief,Mission Bhagiratha Hyderabad for favour of kind information.
Copy submitted to The Chief Engineer-IV,Mission Bhairatha,Hyderabad for favour of Kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) Chief Engineer-IV ,
SuperintendingEngineer(FAC), Mission Bhagiratha,Hyderabad
Mission Bhagiratha Circle,Adilabad,
Adilabad Dist.
Sir
Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District-SRSP-Adilabad Segment-Isolated/Scattered
Habs-Detailed Report-Submitted-Reg.
*****
It is to submit that,vide reference 1sit cited above Hon’ble Chief Minister, Governament of Telanga
instructed to cover left over scattered habitations in the state under Mission Bhagiratha irrespective of the cost.
Accordinly a joint inspection was conducted by the undersigned along with EE,MB Grid Division,Adilabad and
Dy.EE&A.E.MB Grid SD Adilabad along with a representative from main grid agency M/s.MEIL for
identifying the isolated habs.
During the Joint inspection 8 Habs (Annexure enclosed) were identified as isolated/scattered in
Adilabad District under SRSP-Adilabad Segment . Executive Engineer stated that out these 8 Habs 4 Habs
were proposed to be covered in orginal estimate i.e. under 20 KL,30 Mts staging OHBR at Punaguda and same
structure was later deleted as Forest department denied permissions stating these are encroached/unauthorized
habitations and remaining 4 habs were identified later which are also encroached habitations as stated by forest
department .Furhter Executive Engineer stated that forest permissions are needed for proceeding for any further
work in these habitations.
Wherein vide reference 2nd cited above,Executive Engineer,MB Grid Division,Adilabad submitted the
estimate of Cost 1130.00 Lakhs for covering the above 8 isolated habs under Mission Bhagiratha as a workslip
under Main Grid works of SRSP-Adilabad segment stating that this amount can be met from savings of Main
Grid Works and same was submitted by this office vide reference 3rd cited above.
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy submitted to The Engineer-in-Chief,Mission Bhagiratha Hyderabad for favour of kind information.
Copy submitted to The Chief Engineer-IV,Mission Bhairatha,Hyderabad for favour of Kind information.
Endt.No.02/AEE3/ SE / MB(Adilabad) /Communication/2018-19, Dt:21.01.2019
*****
//A copy of the observations made by Forest Divisional Officer,Nirmal vide
Rc.No.2003/2016/S1,Dated:29.12.2018 on Compliance report for Conditions stipulated in Stage-I approval for
laying pipeline and construction of structures in segment-21/7(Madegaon), is herewith communicated to
Executive Engineer,MB Grid Division,Nirmal with a request to submit the compliance report on observation
made by the Forest Divisional officer,Nirmal at an early date for taking further necessary action please.//
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Nirmal.
Copy Submitted to:
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
Endt.No.03/AEE3/ SE / MB(Adilabad) /Communication/2018-19, Dt:19.01.2019
*****
//A copy of the letter received from Executive Engineer,I&CADD, Penganga Project Division, vide
Lr.No.EE/PGP/HD/ADB/DB/HD/PKBR/2018-19/381/m,Dated:11.01.2019 is herewith communicated to
Executive Engineer,MB Grid Division,Adilabad with a request to take further necessary action please//
Sd/- Superintending
Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Adilabad.
Copy to:
The Executive Engineer,I&CADD,Penganga Projecto Division,Adilabad for information.
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
//Authenticated//
Dy.EE PA to SE,
Mission Bhagiratha Circe,Adilabad
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) Executive Engineer,
SuperintendingEngineer(FAC), Irrigation&CADD Department,
Mission Bhagiratha Circle,Adilabad, Penganga Project Division,
Adilabad Dist. Adilabad
Sir
Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District-Lower Penganga Project-Formation of Pippalkoti
Balancing Reservior and it’s allied works near Pippalkoti(V) of Bheempur(M) of Adilabad(D)-Shifting
of Mission Bhagiratha Pipeline-Reg.
*****
Ref: 1.Your office Lr.No.EE/PGP/HD/ADB/DB/HD/PKBR/2018-19/381/,Dated:11.01.2019.
2.T/o.Endt.No.03/AEE3/ SE / MB(Adilabad) /Communication/2018-19, Dt:19.01.2019.
3.Lr.No./AEE/EE/MB Grid(Division Adilabad)/SRSP-ADB/2018-19 ,Dated:22.01.2019 of Executive
Engineer,MB Grid Division,Adilabad.
4.Agreement.No 04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP Circle,Nirmal.
5. Instructions issued by Hon’ble Chief Minister,Governament of Telangana on Dt:17.12.2018.
6.Instructions of Collector&District Magistrate,Adilabad on Dt:27.12.2018.
It is to submit that, vide reference 1st cited above it was requested by your officeto shift Mission
Bhagiratha Pipeline& Valvesat certain locations in Bheempur Mandal stating that Mission Bhagiratha
Pipelines&Valves crossing the proposed Balancing Reservior at Pippalkoti(V) of Bheempur(M) and Coming
under Submergence and Bund portion of above balancing reservoir.
Accordingly,Vide reference 2nd cited above,Executive Engineer,MB Grid Divison,Adilabad was
requested to take further necessary action on the above matter and a report on the same was submitted to this
office vide reference 3rd cited.
In this regard,I am herewith submitting the following points for your kind perusal as submitted by
Executie Engineer,MB Grid Division,Adilabad.
The above area under consideration falls under SRSP-Adilabad Segment of Mission Bhagiratha
forwhich agreement was concluded on 28.10.2015 and all works nearing completion and No
balanceamountis available to take any further work.Hence an Estimated is herewith submitted
for shifting of pipeline and you are requested kindly to incorporate the same in your estimate of
above project.
Vide reference 5th cited above, in the review meeting on Mission Bhagiratha, Hon’ble Chief
Minister,Governament of Telangana Instructed that Mission Bhagiratha Water should be supplied
every day to each household without any interruption and informed that any damages or
pilferageof water should be avoided and further reminded that not complaing to above will be
viewed seriously and same was instructed by Collector&District Magistriate,Adilabad during the
review meeting on Dt.27.12.2018.
In this regard you are kindly requested to co-ordinate with Executive Engineer,MB Grid
Division,Adilabad and complete the shifting of pipeline within stipulated time so as to avoid any water
scarcity problems and further complications.
Enclosure:As above
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
Copy submitted to
The Chief Engineer(Projects),I&CADD Department,Adilabad,for favour of kind information.
The Chief Engineer-I,Mission Bhagirath,Hyderabad for favour of kind information.
The Collector &District Magistrate Adilabad for favour of kind information
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) The Forest Divisional Officer,
SuperintendingEngineer(FAC), Nirmal.
Mission Bhagiratha Circle,Adilabad,
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment-FCA–Proposals for diversion
of 4.945Ha of forest land in Kawal Tiger Reserve,Nirmal Division-for laying pipeline and
construction of structures in Segment-21/7(Madegaon) for providing safe drinking water to
erstwhile AdilabadDistrict presently Nirmal District under Telangana Drinking Water Supply
Project(TDWSP)-In-Principle(Stage-I) approval accorded-Compliance report on conditions
stipulated in Stage-I-Regarding.
Ref: 1. GO.Rt.No.104,of EFS&T(For.I) Dept,Dt.09.06.2017.
2.Rc.No.2003/2016/S1,Dated.10.09.2018 of Forest Divisional Officer,Nirmal.
3.T/o.Lr.No.13/AEE3/SE/RWSS(Adilabad)/SRSP-ADB/FOREST/Compliance
Report,Dated:23.10.2018
44.Rc.No.2003/2016/S1,Dated:29.12.2018 of Forest Divisional Officer,Nirmal Received on
Dt:17.01.2019
L 5.Lr.No.MB GRID NIRMAL/SRSP Adilabad/Forest/Madegaom/2019,Dated:23.01.2019
*****
It is to submit that,vide reference 4th cited for two conditions it was requested to submit the compliance
report.
Accordingly, I herewith submitting the compliance report for two conditions as desired.
Enclosure:As above
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
The Executive Engineer,MB Grid Division,Nirmal for information.
Copy Submitted to:
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
The compliance report for observation made by Forest Divisional officer,Nirmal for the Segment-21/7
(Madegaom) is submitted to the District Forest Officer, Nirmal Districtis as Follows:
S.No. Description of the Condition Compliance
1 Publish the entire forest clearances granted in The Telangana Drinking Water Supply Corporation
verbatim along with the condition and safe- Ltd., Hyderabad has published the Obtained forest
guards imposed by the central Government in clearances for the segment-21/7(Madegaom) in
two widely circulated daily news paper one in Namaste Telangana Telugu(vernacular) daily news
Vernacular language and the other in English paper & Indian Express English daily news paper
granted to the project proponent for the use of on 21.09.2018 and the published copies are
forest land for the non-forest purposes. herewith enclosed for submission.
2 The copies of the forest clearance should also be The forest clearance was submitted & made
submitted to the heads of local bodies, available to display for 30 days in the offices of the
Panchayats and Municipal bodies by the project government, Panchayats and local bodies under
proponents in addition to the relevant offices of segment-21/7 (Madegaom).
the government who in turn has to display the
same for 30days from the date of receipt of this
reference.
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Through the reference 2ndcited, instructions were issued not to approve any Bulk Water
connections/Tapings on transmission pipeline without the approval by the authorized personal from TDWSCL
and to submit the all the Bulk Supply Connection proposals through the concerned Superintending Engineers to
the Concerned Chief Engineers with a feasibility report for further action.
Further through the reference 3rd cited ,Guidelines for Providing Bulk Non domestic,
Commercial and Industrial water supply connections &Tariffs to be fixed under Mission Bhagiratha were
submitted to the Government. Till further guidelines, presently this procedure may be followed.
Again vide reference 4th cited Instructions were issued not to approve any Bulk Water
connections/Tapings on transmission pipeline including gracious connections(All Government institutions such
as govt hospitals,govt educational institutions,govt hostels, police stations, religious places and old age homes
e.t.c)and and any discrepancy in this regard will be viewed seriously and the connections with in the village
premises from distribution lines may be served by the concerned Gram Panchayath only.
In addition , it was further instructed to strictly verify that the consumer shall apply for Bulk
connections through Mission Bhagiratha Portal only.
In this regard all the Executive Engineers,Dy.Executive Engineers under this circle are
hereby requested to follow the guidelines/instructions issuedthrough the references above .
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Exeuctuive Engineer,MB Intra Division Adilabad/Nirmal.
The Executive Engineer,MB Grid Division,Adilabad/Nirmal.
All the Dy.Executive Engineers,MB Grid&Intra through their concerned Executive Engineers.
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
In this regard, I am herewith submitting the followingpoints for your kind perusal.
Status as on 02.01.2019
Upon field verification by the undersigned above bulk and daily supply report was found true.
Hence,It is to submit that The News which was published in Eenadu News Paper isbaseless
with respect to Bulk/Daily Supply under this circle.
Status as on 31.01.2019
It is to submit that at present Out of 468 Bulk supplied habs about 454 habs are being supplied with MB
Water daily i.e 14 Habs are pending with daily supply(Nirmal Constituency-9,Mudhole Constituency-
5)as on 31.01.2019.
In Mudhole constituency out of 5 Habs pending,1 habitation namely Pipree of Mudhole Mandal merged
with Bhainsa ULB and for the same the work is in progress under PH Department. For another 4
habitations about 4 Kms of pipeline was damaged in R&B road extension and the repair work for the
same is in progress(Photo enclosed).
In Nirmal Constituency.For 9 Pending habs pending the source is Exisitng CPWS scheme
namely “CPWS Scheme to Nirmal and other Habitations”.The daily supply for these habs is
pending due to repair work of motors at Kankanpur sump and the same work is in progress(Photo
enclosed).
An annexure for Bulk and Daily status of Nirmal District under this circle as on 31.01.2019 is
herewith enclosed.
This is submitted for favour of kind information and further necessary action please.
Yours faithfully,
Superintending Engineer(FAC),
Mission BhagirathaCircle, Adilabad.
Reminder-V
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
****
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Nirmal.
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
*****
It is to submit that,vide reference cited above The Chief Engineer-I has instructed to submit the
observed data for construction of OHSR’s(8 No’s) in remote & hilly areas of Adilabad District.
Accordingly,I am herewith submitting the observed data for construction of OHSR’s in remote &
Hilly areas for taking further necessary action.
Enclosure:As above
Yours faithfully,
Superintending Engineer(FAC),
Mission BhagirathaCircle, Adilabad.
Copy to:
The Executive Engineer,MB Intra Division,Adilabad for information.
Copy Submitted to:
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
*****
It is to submit that,vide reference cited above The Chief Engineer-I has instructed to submit the
observed data for construction of OHSR’s(8 No’s) in remote & hilly areas of Adilabad District.
Accordingly,I am herewith submitting the observed data for construction of OHSR’s in remote &
Hilly areas for taking further necessary action.
Enclosure:As above
Yours faithfully,
Superintending Engineer(FAC),
Mission BhagirathaCircle, Adilabad.
Copy to:
The Executive Engineer,MB Intra Division,Adilabad for information.
Copy Submitted to:
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) All The District Officers/District HODs,
SuperintendingEngineer(FAC), Adilabad District.
Mission Bhagiratha Circle,Adilabad, .
Adilabad Dist.
Sir,
*****
It is to submit that, this office has been receiving many request for providing water connections under
Mission Bhagiratha from various institutions/offices/industries .`
In this regard, it is to inform that, as per the Government Orders issued vide reference 1st cited above “
The Telangana Drinking Water Supply Corporation Limited”(TDWSCL)has to supply drinking water at
entry points of rural/& urban areas and maintain drinking water projects outside GP/ULB’s and the connection
with in the village premises from distribution lines may be served by the concerned gram panchayath only..
Hence, without the approval of the authorized personel from TDWSCL ,this office can not execute any water
connection on transmission line as requested.
In this regard, all the District officers of Adilabad District are hereby requested to see that all the
offices/institution under their jurisidiction apply for the water connection under Mission Bhagiratha through
Mission Bhagiratha Portal(http://www.missionbhagiratha.telangana.gov.in) for taking further necessary action.
The detailed procedure is herewith enclosed.
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
Executive Engineer,MB Grid/Intra Division,Adilabad for information and necessary action.
Copy Submitted to:
The Collector&District Magistrate,Adilabad for favour of kind information
The Project of Officer,ITDA,Utnoor, for favour of kind information
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) All The District Officers/District HODs,
SuperintendingEngineer(FAC), Nirmal District.
Mission Bhagiratha Circle,Adilabad, .
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-Nirmal District-Water Connections under Mission
Bhagiratha-Reg.
*****
It is to submit that, this office has been receiving many request for providing water connections under
Mission Bhagiratha from various institutions/offices/industries .`
In this regard, it is to inform that, as per the Government Orders issued vide reference 1st cited above “
The Telangana Drinking Water Supply Corporation Limited”(TDWSCL)has to supply drinking water at
entry points of rural/& urban areas and maintain drinking water projects outside GP/ULB’s and the connection
with in the village premises from distribution lines may be served by the concerned gram panchayath only..
Hence, without the approval of the authorized personel from TDWSCL ,this office can not execute any water
connection on transmission line as requested.
In this regard, all the District officers of Nirmal District are hereby requested to see that all the
offices/institution under their jurisidiction apply for the water connection under Mission Bhagiratha through
Mission Bhagiratha Portal(http://www.missionbhagiratha.telangana.gov.in) for taking further necessary action.
The detailed procedure is herewith enclosed.
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
Executive Engineer,MB Grid/Intra Division,Nirmal for information and necessary action.
Copy Submitted to:
The Collector&District Magistrate,Nirmal for favour of kind information
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Memo No.12/AEE3/DEE-II/MB Portal/Daily Supply/2018-19,Dated:11.02.2019
In continuation to the reference cited,it is brought to the notice of undersigned that daily
water supply status of few mandals is not being updated in Mission Bhagiratha portal
(http://missionbhagiratha.telangana.gov.in/) even after supplying water, leading to wrong projection of status of
daily supply. In this regard all the Engineers under this circle are once again instructued to see that all the
habitations for which daily supply is made are updated in MB portal everyday and it becomes a part of their day
to day activites.Any discrepency in this regard will be viewed seriously and appropriate action will be initiated
against the concerened.
Further,all are remainded that the same report is shared with CMO dashboard for regular
review.
.
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Nirmal/Adilabad.
The Executive Engineer.MB Intra Division,Nirmal/Adilabad
All the Dy.Executive Engineers/Assistant Executive Engineers/Assistant Engineers through concerned
Executive Engineers.
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
To:
The Executive Engineer,MB Grid/Intra Divisions,Nirmal.
Copy Submitted to:
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE EXECUTIVE ENGINEER, MB GRID DIVISION, ADILABAD
From, To,
Sri P.Gopichand,B.E Executive Engineer,
Executive Engineer(FAC) MB Grid Division,Nirmal.
MB Grid Division,Adilabad, Nirmal Distrct.
Adilabad Dist.
Sir,
Sub: MB Grid Division-Adilabad-Submission of 21/8(Sirichelma) Wildlife segment forest Bills-
As per revised demand notice from FDPT Utnoor-Reg..
Ref: :1.PCCF,TS HYD,Rc.No.12136/2018/WL-1,Dt:04.12.2018
*****
With reference to the subject cited, FDPT Utnoor issued revised demand notice for 1.192 Ha of
Utnoor(FDPT) forest division under 21/8(Sirichelma) WL segment.\
Hence,I am herewith submitting the respective bills of 21/8(Sirichelma) WL segment for further
process of payment.
Encl: 1.MB.No.1072/TDWSP/Nirmal/2016.
2.Demand notice received from FDPT Utnoor.
Yours faithfully,
Executiver Engineer,
MB Grid Division,Adilabad.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Memo No.13/AEE3/DEE-II/ADB/KB-ASFBD/2018-19,Dated:11.02.2019
The immediate personal attention of Executive Engineer.MB Grid Division,Asifabad is drawn to the
reference 2nd cited and he is requested to go through instructions issued time to timess.
.
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Asifabad.
Copy To:
The Superintending Engineer,Mission Bhagiratha Circle,Adilabad for information and necessary action
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
1.In the price variation formulae for DI Pipes the factor “M” is not as per IS 8329:1994
As instructed in reference 2nd cited.
2.In DI Price variation formulae the factor “CPI2” is price of pig iron at the time of delivery i.e
Date of supply&delivery recorded in concerened Measurement Book as instructed in reference
2nd&3rd cited ,but is obereved that the month of invoice was considered.
3.for Mild steel Pipes,the rates of raw material prevailing 1 month before to the QC inspection
should be considered as instructed in reference 3rd cited ,but it is observed that the month of
invoice isconsidered.
4.Further the Embedded tax component from MS Plates estimated rates is not deducted.
In this regard Executive Engineer,MB Grid Division,Nirmal is hereby request to attend above remarks
and submit the information at the earliste to take further necessary action.Further he is requested to verify that
the above observations are followed in previous bills and report compliance.
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Nirmal.
Copy To:
The Executive Engineer,MB Grid Division,Adilabad for necessary action
Copy Submitted to:
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
PROCEEDINGS OF SUPERINTENDING ENGINEER,MISSION BHAGIRATHA CIRCLE-ADILABAD
Present:D.Venkateshwarlu,M.E,(Hon's)
Procs:No. 01/AEE3/DEE-II/Grid/Price Variations/2018-19,Dated:23.02.2019
****
ORDER:
Vide reference 3rd cited above ,Executive Engineer,MB Grid Division,Nirmal has submitted the price
variation proposals for POL under the work “-“Providing Drinking Water to Habitations in SRSP-Adilabad
segment in Adilabad district “Est.Cost 1530.00 Cr of SE TDWSP, Adilabad Dist including Operation and
maintenance for 10 years under Telangana Drinking Water Supply Project(TDWSP).
Accordingly,In view of the directions issued by Chief Engineer-IV,TDWSP,Hyderabad vide reference 4th
cited and as per clause no 44.6 of agreement conditions the overall price adjustment for usage of fuel and
lubricants for Runnig Account Bills 1 to 28 of above work is herewith approved for an amount of
Rs.15,36,10,027/-(Rupees Fifteen Crores Thirty Six Lakhs Ten Thousand Twenty Seven Rupees only) keeping the
responsbility on Executive Engineer,MB Grid Division,Nirmal.
Further Executive Engineer,MB Grid Division,Nirmal shall ensure that any deviations on above approved
amount is found the same shall be deducted from the subsequent bills of agency.
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Nirmal.
Copy Submitted To:
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri USN Murthy, M Tech, MBA, LLM. The Project Director,
SuperintendingEngineer, WAPCOS,AC Guards,
RWS& S-Circle,Adilabad, Hyderabad,Telangana-500004
Adilabad Dist.
Sir,
Hence it is requested to vet the above designs and drawings as per agreement conditions at an
early date and communicate.
Encl: As above
Yours Faithfully,
Superintending Engineer,
RWS&S,Adilabad-Circle.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) The Project Director,
SuperintendingEngineer(FAC), WAPCOS,AC Guards,
Mission Bhagiratha Circle,Adilabad, Hyderabad,Telangana-500004
Adilabad Dist.
Sir,
Sub:Mission Bhagiratha Circle–Adilabad-SRSP-Adilabad Segment-“Providing Drinking Water to
I am
Habitations in SRSP-Adilabad segment in Adilabad district “Est.Cost 1530.00 Cr of SE TDWSP,
Adilabad Dist including Operation and maintenance for 10 years-Vetting of Designs and
Drawings -Requested-Reg.
Hence it is requested sir to vet the above designs and drawings as per agreement conditions at an
early date and communicate.
Encl: As above
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
PROCEEDINGS OF SUPERINTENDING ENGINEER,MISSION BHAGIRATHA CIRCLE-ADILABAD
Present:D.Venkateshwarlu,M.E,(Hon's)
Procs:No. 02/AEE3/DEE-II/Grid/Price Variations/2018-19,Dated:22.02.2019
Accordingly,as per clause no 44.6 of agreement conditions the overall price adjustment for MS,DI&BWSC
Pipes for Runnig Account Bills 17 to 28 of above work is herewith approved for an amount of Rs.8,71,06,812/-
(Rupees Eight Crores Seveny One Lakhs Six thousand Eight Hundered Twelve Rupees Only) keeping the
responsbility on Executive Engineer,MB Grid Division,Nirmal.
Further Executive Engineer,MB Grid Division,Nirmal shall ensure that any deviations on above approved
amount is found the same shall be deducted from the subsequent bills of agency .
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Nirmal.
Copy Submitted To:
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) Executive Engineer,
SuperintendingEngineer(FAC), Irrigation&CADD Department,
Mission Bhagiratha Circle,Adilabad, Penganga Project Division,
Adilabad Dist. Adilabad
Sir
Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District-Lower Penganga Project-Formation of Pippalkoti
Balancing Reservior and it’s allied works near Pippalkoti(V) of Bheempur(M) of Adilabad(D)-Shifting
of Mission Bhagiratha Pipeline-Reg.
Ref: 1.Agreement.No 04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP Circle,Nirmal.
2.T/o.Lr.No.39/AEE3/SE/MB/Penganga Project/Pipeline/2018-19,Dt:23.01.2019.
3.Your office Lr.No.EE/PGP/DB/HD/P.K/M.B/043/2018-19/443/SE,Dated:22.02.2019
4.Lr.N0.02/AEE1/EE/Grid/ADB/I&CAD/Estimate/2019,Dated:28.02.2019 of Executive Engineer,
MB Grid Division,Adilabad
*****
In compliance to the reference 3rd cited above,it is to submit that, as informed earlier the work
“Providing Drinking Water to Habitations in SRSP-Adilabad segment in Adilabad District “Est.Cost
1530.00 Cr of SE TDWSP, Adilabad Dist including Operation and maintenance for 10 years is nearing
completion and no balance amount is available to take up any work .
Further,In continuation to reference 2nd cited I am herewith submitting the revised estimated of cost
41.80 Lakhs for taking further necessary action.
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
The Executive Engineer,MB Grid Division,Adilabad for information.
Copy submitted to
The Chief Engineer(Projects),I&CADD Department,Adilabad,for favour of kind information.
The Chief Engineer-I,Mission Bhagirath,Hyderabad for favour of kind information.
The Collector &District Magistrate Adilabad for favour of kind information
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – “Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years-O&M Estimate-
Submitted-Approval-Req-Reg.
*****
It is to submit that , vide reference 2nd& 3rd cited above Executive Engineer,MB Grid
Division,Nirmal&Adilabad have submitted the O&M Estimate for the work “Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad
District Including Operation & Maintenance for 10 Years.
Encl:O&M Estimate
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
The Executive Engineer,MB Grid Division,Adilabad&Nirmal for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
****
In continuation to the reference 1&2nd cited and as per the instructions of Chief Engineer-
I,Mission Bhagiratha,Hyderabad ,the Executive Engineer,MB Grid Division,Adilabad Division is hereby
directed to conduct a joint inspection along with the Executive Engineer,MB Grid Division Asifabad for
identifying the list of isolated habitations of SRSP-Adilabad Segment in Adilabad District which can be covered
through gravity from KB-Asifabad segment and vice versa and report to this office by 10.03.2019 postively for
taking further necessary action.
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
To:
The Executive Engineer,MB Grid Division,Adilabad
Copy to:
The Executive Engineer,MB Grid Division,Asifabad for information and necessary action.
The Superintending Engineer,Mission Bhagiratha Circle,Mancherial for information.
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
To:
The Executive Engineer,MB Grid/Intra Division,Adilabad
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Superintending Engineer,
SuperintendingEngineer(FAC), MB Circle-Mancherial
Mission Bhagiratha Circle,Adilabad,
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad- Phase-I SRSP-Adilabad Segment –“Providing Drinikng Water
Grid to Adilabad,Boath and Nirmal Assembly Constituencies in Adilabad District” Est.Cost.Rs.248 Crs-
-Working Estimate-V-Approved Copy Communicated-Reg.
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Enclosure:
1.Working Estimae-V(True Copy)
2.Working Estimate-IV(True Copy) and Its agreement(Original Copy)
Copy to:
The Executive Engineer,MB Grid Division,Nirmal for information.
Copy submitted to
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
Ref: Arising
****
All the Executive Engineers of MB Grid Divisions& Intra Divisions noted in the address entry are requested to
send the details of Newly recruited AEE’s details in the proforma enclosed for generation of User Ids in MB
Portal and for taking further necessary action.
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Enclosure:As above
To:
The Executive Engineer,MB Grid/Intra Division,Adilabad
The Executive Engineer,MB Grid/Intra Division,Nirmal
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderbad
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad- SRSP-Adilabad Segment “Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years-R&B Road widening
from Deepaiguda village to Bahadurpura X road-Pipeline Shifting-Reg.
****
It is to submit that,vide reference 1st cited above M/s.Megha Engieering and Infrastructure
Limited,Hyderabad entered in to the agreement for the work “Providing Drinking Water to Habitations in
SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District
Including Operation & Maintenance for 10 Years and work is nearing completion . Under the above work DI
pipeline of 150mm Dia,K-9,of Length 2.50 Kms was laid from from Deepaiguda village to Bahadurpura X
road, along the PR Road of Jainath Mandal in 2016.
Further it is to submit that, at the time of Execution , the above road was under the control of PRED and
later its assigned to R&B Department recently after commissioning of MB Pipeline and on Dt:12.03.2019 R&B
officials informed the Executive Engineer,MB Grid Division,Adilabad that the work widening and
strengthening of Road from Deepaiguda Village to Bahadurpura X road of Jainath Mandal for a length of 2.50
Kms is in progress.
Accordingly Executive Engineer,MB Grid Division,Adilabad conducted a joint inspection along with
Concerned R&B officials and vide reference 3rd cited informed this office that above pipeline has to be removed
and relaid and further submitted the estimate for the same .
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Enclosure:
Copy to:
The Executive Engineer,MB Grid Division,Adilabad for information.
Copy submitted to
The
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE EXECUTIVE ENGINEER, MISSION BHAGIRATHA GRID DIVISION, ADILABAD
Sub: Estt-MB Grid Division,Adilabad-Induction Training Phase-IV to Newly recruited AEE's at ESCI
Gachhibowli-Hyderabad-Certain Indivuals deputed for undergoing training-Relieving-Orders-
Issued.
Ref : Engineer-In-Chief,MB Dept,Hyderabad Memo.No.OP-I/AEs V&VI/RWS&S/Induction
Trg/2019,Dated:28.02.2019
****
Through the referene cited,certain Assistant Executive Engineers working under the control of MB Grid
Division,Adilabad has been deputed for(15 ) Days to undergoing training programme for the induction training
Phase-IV to Newly recruited AEEs from 11.03.2019 to 25.03.2019 (15) Days at ESCI,Gachibowli,Hyderabad
the details as follows.
Therefore the above individual of this office is hereby instructed to attend the above training programme and
report before the Director,ESCI,Gachibowli,Hyderabad on 11.03.2019 by 9 AM without fail.
The Director,ESCI,Gachibowli,Hyderabad is requested to intimate the joining and relieve of the above
individual.
Executive Engineer
MB Grid Division-Adilabad
To,
The Individiual,
The Director,ESCI,Gachibowli,Hyderabad for favour of kind information and necessary action.
Copy Submitted to Engineer-In-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The ,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderbad
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad- SRSP-Adilabad Segment “Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years-Adilabad ULB-
Providing Flow Meter at Tapping Point-Reg.
Ref: 1.Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal Circle.
2.Minutes of Joint Co-ordinaion meeting held on Dt:20.12.2018 at O/o ENC,RWSS,Hyderabad.
****
It is to submit that,vide reference 1st cited above M/s.Megha Engieering and Infrastructure
Limited,Hyderabad entered in to the agreement for the work “Providing Drinking Water to Habitations in
SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District
Including Operation & Maintenance for 10 Years and work is nearing completion . Under the above work DI
pipeline of 150mm Dia,K-9,of Length 2.50 Kms was laid from from Deepaiguda village to Bahadurpura X
road, along the PR Road of Jainath Mandal in 2016.
Most Urgent By E-mail
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Memo No.18/AEE3/DEE-II/GRID/WE-II/2018-19,Dated:10.04.2019
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
To:
The Executive Engineer,MB Grid Division,Adilabad.
The Dy.Executive Engineer,MB Grid Sub Division,Adilabad/Ichoda.
All the Assistant Executive Engineers/Assistant Engineers under MB Grid Division Adilabad through
Concerned Executive Engineer/Deputy Executive Engineers.
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
To:
The Executive Engineer,MB Grid Division,Adilabad.
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – “Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years-Sub Estimate for
Expansion Joints-Submitted-Approval-Req-Reg.
*****
It is to submit that , vide reference 2nd cited above Executive Engineer,MB Grid Division,Nirmal has
submitted the Sub Estimatefor Expansion Joints on MS Pipeline for the work “Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad
District Including Operation & Maintenance for 10 Years for favour of kind approval .
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
The Executive Engineer,MB Grid Division,Adilabad&Nirmal for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
To:
The Executive Engineer,MB Grid Division,Adilabad.
The Dy.Executive Engineer,MB Grid SD Ichoda/Adilabad through The Executive Engineer,MB Grid
Division,Adilabad.
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Engineer-in-Chief,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – “Construction of Intakewell,WTP
and RAW water pumping main in Adilabad segment,Kadam segment,Asifabad Segment and
Mancherial segment of Telangana Drinking Water Supply (TDWSP)”, Est.Cost Rs.440.50 Crs-130
MLD WTP at Madegaon-Readiness for Inspection-Reg.
*****
It is to submit that , As per the instructions issued vide references 3rd and 4th cited above performance
test on 130 MLD WTP at Madegaon is conducted by Executive Engineer,MB Grid Division,Nirmal on
18.04.2019 against approved parameters/specifications such as inlet/outlet discharges,clear water turbidity,back
wash system efficiency,bedwise efficiency,overall efficiency ,20% overloading etc .
Further through the reference 5th cited Executive Engineer,MB Grid Division,Nirmal informed that the
above test results found satisfactory as per approved parameters and is ready for Inspection.
In this regard,It is requested the kind authority that kindly instructions may be given to
SE,V&QC,Warangal and M/s.Wapcos to inspect to test the above parameters of 130 MLD WTP at Madegaon
which is ready for inspection.
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
The Executive Engineer,MB Grid Division,Nirmal for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind informations
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District –Inlet Connection to New OHSRs- Details-
Called for-Reg.
Ref: 1.Instructions of Engineer-in-Chief,MB,Hyderabad during video conference held on 24.04.2019.
****
During the Video conference with Engineer-in-Chief,Mission Bhagiratha,Hyderabad held on Dt:24.04.2019,it
was observed by the Engineer-in-Chief that in many Mandals there is a huge gap between No.of OHSRs
completed and No.of OHSRs came into utilization due to pending of Inlet Connection from MB Grid.
In this regard,All the AEE’s/AE’&Dy.EEs , MB Intra of Adilabad District are hereby requested to
Submit the details of New OHSRs(Proforma Enlosed) which are completed in all aspects and for which Inlet
Connectionimmediately required to this office positively by 27.04.2019 for taking further necessary
action.Further All the AEE’s/AE’s,Dy.EEs and EEs ,MB Grid of Adilabad District are also requested to attend
the next Video Conference(time slots will be intimated later) with Engineer-in-Chief,MB,Hyderabad.
Encl:As above
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
To:
All The Executive Engineers,Dy.Executive Engineers/Assistant Executive Engineers and Assistnt Engineers of
MB Intra&Grid of Adilabad District .
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) The Project Director,
SuperintendingEngineer(FAC), WAPCOS,AC Guards,
Mission Bhagiratha Circle,Adilabad, Hyderabad,Telangana-500004
Adilabad Dist.
Sir,
Hence it is requested sir to vet the above designs and drawings as per agreement conditions at an
early date and communicate.
Encl: As above
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) The Project Director,
SuperintendingEngineer(FAC), WAPCOS,AC Guards,
Mission Bhagiratha Circle,Adilabad, Hyderabad,Telangana-500004
Adilabad Dist.
Hence it is requested sir to vet the above designs and drawings as per agreement conditions at an
early date and communicate.
Encl: As above
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) The Project Director,
SuperintendingEngineer(FAC), WAPCOS,AC Guards,
Mission Bhagiratha Circle,Adilabad, Hyderabad,Telangana-500004
Adilabad Dist.
Sir,
1.Typical Designs and Drawings for for Expansion Joint on 1130 mm Dia,MS Pipeline
2. Typical Designs and Drawings for for Expansion Joint on 1030 mm Dia,MS Pipeline
3. Typical Designs and Drawings for for Expansion Joint on 930 mm Dia,MS Pipeline
Hence it is requested sir to vet the above designs and drawings as per agreement conditions at an
early date and communicate.
Encl: As above
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad
Copy Submitted To:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) The Project Director,
SuperintendingEngineer(FAC), WAPCOS,AC Guards,
Mission Bhagiratha Circle,Adilabad, Hyderabad,Telangana-500004
Adilabad Dist.
Sir,
1.Typical Designs and Drawings for for Expansion Joint on 1400 mm Dia,MS Pipeline
Hence it is requested sir to vet the above designs and drawings as per agreement conditions at an
early date and communicate.
Encl: As above
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy Submitted To:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment–“Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years-Quotations for
Expansion Joints-Approval-Req-Reg.
*****
It is to submit that , vide reference 2nd cited above this office has submitted the sub estimate for the
expansion joints on MS Pipeline for the work “Providing Drinking Water to Habitations in SRSP Adilabad
Segment in Adilabad District”Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District Including Operation &
Maintenance for 10 Years.
In continuation to the above,I am herewith submitting the quotations for the expansion joints along with
comparative statement and recommendations for favour of kind approval.
Encl:1.3 Original Quotations
2.Comparative Statement
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
The Executive Engineer,MB Grid Division,Adilabad for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) The Project Director,
SuperintendingEngineer(FAC), WAPCOS,AC Guards,
Mission Bhagiratha Circle,Adilabad, Hyderabad,Telangana-500004
Adilabad Dist.
Sir,
1.Typical Designs and Drawings for 100 KL Sump,10x5 Watchman Quarter,Compound wall at
Toyaguda.
2. Typical Designs and Drawings for 10 KL Sump,10x5 Watchman Quarter,Compound wall at
Wanwat.
3. Typical Designs and Drawings for 10 KL Sump,10x5 Watchman Quarter,Compound wall at
Laxmanguda.
4. Typical Designs and Drawings for 20 KL Sump,10x5 Watchman Quarter,Compound wall at
Kolamguda.
5. Typical Designs and Drawings for 10 KL Sump,10x5 Watchman Quarter,Compound wall at
Devjiguda.
6. Typical Designs and Drawings for 10 KL Sump,10x5 Watchman Quarter,Compound wall at
Chisdhari.
7.Longitudinal Section for Punaguda,Maruthiguda,Bhurki for Consttruction of Approach Roads.
8. Typical Designs and Drawings for Pumping Mains &Pumpsets for Punaguda and Maruthiguda,
Asoda and Boppapur,Laxmanguda,Kolamguda,,Wanwat ,Devjiguda,Chisdhari.
9.MS design for 150 mm ,100 mm,80 mm and 6mm thick pipeline for new habitations.
Hence it is requested sir to vet the above designs and drawings as per agreement conditions at
an early date and communicate.
Encl: As above
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle,
Adilabad.
Copy Submitted To:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
It is to submit that , vide reference 2nd cited above Executive Engineer,MB Grid Division
,Adilabad has submitted the work slip for covering Isolated/Scattered & New Habs of Adilabad District
in SRSP Adilabad Segment with an Estimate Cost of 10.00 Croresunder the work “Providing Drinking
Water to Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years and the same is herewith
submitted for taking further action please.
Encl:As above.
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle,Adilabad
Copy to:
The Executive Engineer,MB Grid Division,Adilabad for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Memo No.01/AEE3/DEE-II/GRID/2019-20,Dated:03.05.2019
The Dy.Executive Engineer,MB Grid SD,Adilabad attention is invited to the reference cited
and he is requested to be vigilant on maintaining the Arepally GLBR clear water level so that required pressure
is maintained at Adilabad BPT to avoid any interruptions in daily supply for the habitations under Adilabad
BPT and same message received from Hon’ble MLA,Adilabad .
In this connection the Dy.EE,MB Grid SD ,Adilabad is requested to co-ordinate with the
Dy.EE,MB Grid SD,Ichoda regarding the above matter
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Dy.Executive Engineer,MB Grid SD,Adilabad
Copy to:
The Dy.Executive Engineer,MB Grid SD,Ichoda with a request to co-ordinate with the Dy.EE,MB Grid SD
Adilabad.
The Executive Engineer,MB Grid Division,Adilabad for information and necessary action.
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
The P.S to Hon’ble MLA,Adilabad for favour of Kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Memo No.02/AEE3/DEE-II/GRID/2019-20,Dated:03.05.2019
Sd/-
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Adilabad
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
The Collector&District Magistrate,Adilabad for favour of kind information.
//T.C.F.B.O//
Dy.EE PA to SE
MB Circle-Adilabad
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
And also the Executive Engineer MB Grid,Division, Nirmal has submitted the EOAT Proposals duly
recommending EOAT upto 30thJune 2019 without imposing any penalty based on the reasons explained by the
agency, and further enclosed Check slip.
Contd…..Page No.2
:::2:::
Hence,I am herewith submitting the Extension of Agreement Time(EOAT) proposals for the above said
work under SRSP-Adilabad Segment for your kind perusal and further necessary action.
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
All the Executive Engineers,Dy.Executive Engineers and Assistant Executive Engineers/Assistant Engineers of
MB Grid &Intra of Adilabad District
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
Further,No other officer is permitted to sanction leave for their respective subordinates on
the day of VC i.e.on Dt:14.05.2019.
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
All the Executive Engineers,Dy.Executive Engineers and Assistant Executive Engineers/Assistant Engineers of
MB Grid &Intra of Adilabad District
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) M/s.MEIL,
SuperintendingEngineer(FAC), Balanagar,
Mission Bhagiratha Circle,Adilabad, Hyderabad-500037
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-Quotations for MS Expansioin Joints-Req-Reg.
Ref: Arising
*****
Anent to the subject cited above, M/s.MEIL,Balanagar,Hyderabad is invited to submit their quotations
for Manufacturing and Supply of MS Expansion joints for the 1100 mm Dia,1000 mm Dia,900 mm Dia and
with pressure rating 25 Kg/Cm2 Excluding all taxes ,Packing and Forwarding etc.
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
Executive Engineer,MB Grid Division,Adilabad for information and necessary action.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) M/s.S.K.Industries,
SuperintendingEngineer(FAC), Balanagar,
Mission Bhagiratha Circle,Adilabad, Hyderabad-500042
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-Quotations for MS Expansioin Joints-Req-Reg.
Ref: Arising
*****
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
Executive Engineer,MB Grid Division,Adilabad for information and necessary action.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) M/s.G.M.Dalui&Sons Pvt Ltd,
SuperintendingEngineer(FAC), Howrah-711113,
Mission Bhagiratha Circle,Adilabad, W.B.,India
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-Quotations for MS Expansioin Joints-Req-Reg.
Ref: Arising
*****
Anent to the subject cited above, M/s.G.M.Dalui&Sons Pvt Ltd,Howrah,W.B, is invited to submit their
quotations for Manufacturing and Supply of MS Expansion joints for the 1100 mm Dia,1000 mm Dia,900 mm
Dia and with pressure rating 25 Kg/Cm2 Excluding all taxes ,Packing and Forwarding etc.
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
Executive Engineer,MB Grid Division,Adilabad for information and necessary action.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
PROCEEDINGS OF SUPERINTENDING ENGINEER,MISSION BHAGIRATHA CIRCLE-ADILABAD
Present:D.Venkateshwarlu,M.E,(Hon's)
Procs:No. 01/AEE3/DEE-II/Grid/MS Expansion Joints/2018-19,Dated:28.04.2019
Rate quotations have been received from various willing suppliers for MS Expansion joints as per
specification indicated in the table below and lowest rate quoted by M/s.Megha Engineering and
Infrastructure Ltd is hereby approveds The approved ratesare as follows.
SL.N PN- UNIT
DESCRIPTION DIA
O RATING RATE
Manufacturing & Supply of Mild Steel (M.S)
Fabricated expansion joint Confirming to IS
A
2062E250BR etc. Complete ISI Marked and
Excluding GST.
1 Expansion Joint 1100 25 248400
2 Expansion Joint 1000 25 220000
3 Expansion Joint 900 25 184500
The Executive Engineer, Mission Bhagiratha Grid, Adilabad &Nirmal Divisions, are instructed to prepare and
submit the estimate accordingly for the respective Districts.
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Adilabad&Nirmal for necessary action.
Copy Submitted To:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – Construction of Intakewell,WTP and
Raw water pumping main in Adilabad segment,Kadam segment,Asifabad Segment and
Mancherial segment of Telangana Drinking Water Supply (TDWSP), Est.Cost Rs.440.50 Crs-Sub
Estimate for Expansion Joints-Submitted-Approval-Req-Reg.
*****
It is to submit that , Executive Engineer,MB Grid Division,Nirmal has submitted the Sub Estimates for
Surge Vessels,Zero velocity valve,Air cushion valves and Expansion joints for MS Pipeline for the work
“Construction of Intakewell,WTP and Raw water pumping main in Adilabad segment,Kadam
segment,Asifabad Segment and Mancherial segment of Telangana Drinking Water Supply (TDWSP),
Est.Cost Rs.440.50 Crs”for favour of kind approval .
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
The Executive Engineer,MB Grid Division,Nirmal for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years”, -Remarks on
Expansion Joints-Information-Submitted-Reg.
*****
It is to submit that , in continuation to the reference 3rd cited and as per instructions issued vide reference
2ndcited above I am herewith submitting the approved drawing for expansion joints on MS
Pipeline,Specification report and Main segment General Abstract for taking further necessary action.
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
The Executive Engineer,MB Grid Division,Adilabd for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad.
Mission Bhagiratha-Circle,Adilabad,
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – -“Design, Supply, Erection, Testing
and commissioning of Electro mechanical works with SCADA & Instrumentation along with
associated substation and switch gear including all connected accessories for various Pumping
stations located at various places in erstwhile districts Adilabad, Nizamabad and Karimnagar.
Including, defects liability period and operation and maintenance for 10 years Package-III” -
Working Estimate-II-Submitted-Approval-Req-Reg.
*****
It is to submit that vide references 3rd cited, Executive Engineer,MB Grid Division,Nirmal has
submitted the Working Estimate-II for Electro Mechanical Works of SRSP Adilabad Segment in Nirmal
District for favour of kind approval and same is herewith submitted for further necessary action.
Encl:Working Estimate-II
Yours faithfully,
Superintending Engineer(FAC),
MB Circle, Adilabad.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
*****
It is to submit that vide references 3rd cited, Executive Engineer,MB Grid Division,Nirmal has
submitted the O&M Estimate for Electro Mechanical Works of SRSP Adilabad Segment in Nirmal District for
favour of kind approval and same is herewith submitted for further necessary action.
Encl:O&M Estimate
Yours faithfully,
Superintending Engineer(FAC),
MB Circle, Adilabad.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – -“Design, Supply, Erection, Testing
and commissioning of Electro mechanical works with SCADA & Instrumentation along with
associated substation and switch gear including all connected accessories for various Pumping
stations located at various places in erstwhile districts Adilabad, Nizamabad and Karimnagar.
Including, defects liability period and operation and maintenance for 10 years Package-III” -O&M
Estimate–Defect Liability Certificate(DLP)-Submitted-Reg.
Ref: 1) Agreement No. AEE/01/2017-18,Dated:18.04.2017.of the Superintending
Engineer,TDWSP Circle,Nirmal
2) Supplementary Agreement No.AEE1/01/2018-19,Dated:15.05.2018 of Superintending
Engineer,RWS&S Circle,Mancherial.
3) Defect Liability Certificates received from Executive Engieer,MB Grid Division,Nirmal
*****
It is to submit that vide references 3rd cited, Executive Engineer,MB Grid Division,Nirmal has
submitted the Defect Liability Cerificates for Electro Mechanical Works of SRSP Adilabad Segment in Nirmal
District and same is herewith submitted for further necessary action.
Yours faithfully,
Superintending Engineer(FAC),
MB Circle, Adilabad.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – -“Design, Supply, Erection, Testing
and commissioning of Electro mechanical works with SCADA & Instrumentation along with
associated substation and switch gear including all connected accessories for various Pumping
stations located at various places in erstwhile districts Adilabad, Nizamabad and Karimnagar.
Including, defects liability period and operation and maintenance for 10 years Package-III” -O&M
Estimate–Defect Liability Certificate(DLP)-Submitted-Reg.
Yours faithfully,
Superintending Engineer(FAC),
MB Circle, Adilabad.
Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.
Copy to Executive Engineer,MB Grid Division,Nirmal for information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's),. The M/s Mega Engineering&Infrastructure Ltd,
SuperintendingEngineer(FAC), S-2, Technocrat Indl.Estate, Balanagar,
Mission Bhagiratha-Circle,Adilabad, Balanagar,
Adilabad Dist. Hyderabad,Telangana-500037
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years”, -Working
Estimate-II-Approval of Balance Item-Req-Reg.
*****
It is to submit that, vide reference 1st cited above , M/s Megha Engineering & Infrastructure
limited,Hyderabad has entered into the agreement for the work “Providing Drinking Water to Habitations
in SRSP-Adilabad segment in Adilabad district “Est.Cost 1530.00 Cr of SE TDWSP, Adilabad Dist
including Operation and maintenance for 10 years.
Further vide reference 3rd cited above,The Chief Engineer-IV,Mission Bhagiratha ,Hyderabad has
communicated the Approved General Abstract of Working Estimate-II along with the few Technically approved
sub estimates to this office for taking further necessary action.
Consequently vide reference 4th cited,a Supplymentary agreement was concluded for the technically
approved items.Wherein it is observed by the undersigned that,many of the item in Approved General abstract
are yet to be technically approved by the competent authority and also the EOAT of the above said is going to
expire on 30.06.2019.
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
The Executive Engineer,MB Grid Division,Adilabd&Nirmal for information and necessary action.
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha for favour of Kind information.
The Chief Engineer-IV,Mission Bhagiratha for favour of Kind information.
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Memo No.05/AEE3/DEE-II/MB/WE-III/2019-20,Dated:27.05.2019
Further,No other officer is permitted to sanction leave for their respective subordinates on
the day of VC i.e.on Dt:14.05.2019.
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
All the Executive Engineers,Dy.Executive Engineers and Assistant Executive Engineers/Assistant Engineers of
MB Grid &Intra of Adilabad District
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineers,MB Grid Division,Adilabad.
The Dy.Executive Engineer,MB Grid Sub Division ,Adilabad
Copy to
The District(R&B) Officer,Adilabad
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Memo No.07/AEE3/DEE-II/MB/PHASE-I/PV/2019-20,Dated:29.05.2019
****
Based on the recommendations of the Executive Engineer,MB Grid Division,Nirmal The Price
variation for Steel,Cement,MS Plates from RA Bill-1 to RA Bill-26 for the work “Construction of and
Intakewell , WTP and Raw water pumping main in Adilabad Segment Kadam segment,Asifabad
Segment Mancherial segment of Telangana Drinking Water Supply (TDWSP)”Est.Cost Rs.440.50
Crs,under SRSP-Adilabad segment is approved for an amount of Rs.-53321567.96/- (Steel- Rs.-
8303491.81/-,Cement-Rs.-4030335.57/-,MS Plate-Rs.-40987740.58/-) and a copy of same is herewith
communicated, keeping the responsibility on the Executive Engineer,MB Grid Division,Nirmal for
taking further necessary action .
Further Executive Engineer,MB Grid Division,Nirmal shall ensure that any deviations on above
approved amount is found the same shall be deducted from the subsequent bills of agency .
.
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Nirmal
Copy Submitted to:
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment –Adilabad District-Providing Drinking
Water to Habitations in SRSP Adilabad Segment in Adilabad District Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years”, -O&M Estimate
–Submitted-Reg.
Ref: 1)Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal Circle.
2) Estimate Copies received from Executive Engineer,MB Grid Division,Adilabad office.
*****
It is to submit that , Executive Engineer,MB Grid Division, Adilabad has submitted the O&M Estimate
of Adilabad District under SRSP-Adilabad segment for the work “Providing Drinking Water to Habitations
in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District
Including Operation & Maintenance for 10 Years.
Hence, same is herewith submitted and the Chief Engineer-I,Mission Bhagiratha,Hyderabad is requested
to kindly approve the same.
Encl:O&M Estimate
Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
The Executive Engineer,MB Grid Division,Adilabad for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Branch Manager ,
SuperintendingEngineer(FAC), Large Corporate Branch,
Mission Bhagiratha Circle,Adilabad, Oriental Bank of Commerce,
Adilabad Dist. Hyderabad,Telangana-500033
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – “Construction of Intake well, WTP
and Raw Water Pumping main in Adilabad segment, Kaddam segment, Asifabad segment and
Mancherial segment of Telangana drinking Water supply project (TDWSP)” Est.cost of Rs.440.50 -
Extension of Validity of Bank Guarantee -Confirmation of genuineness-Requested-Reg.
*****
A copy of Bank Guarantee Extension for ₹:8,00,00,000-00 vide B.G.No.11100029316, Dated: 30.11.2016 of
Oriental Bank of Commerce,Large Corporate Branch,Hyderabad-500033, extended upto 28.05.2020 issued to M/s.
Megha Engineering & Infrastructures Ltd., Hyderabad for the work “Construction of Intake well, WTP and Raw
Water Pumping main in Adilabad segment, Kaddam segment, Asifabad segment and Mancherial segment of
Telangana drinking Water supply project (TDWSP)” Est.cost of Rs.440.50 Crs is here with communicated with a
request to confirm the genuineness of the BGs extension at the earliest.
Copy to:
The Executive Engineer,MB Grid Division,Nirmal for information.
Copy submitted to
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
\\T.C.F.B.O\\
.
Dy.EE PA TO SE
MISSION BHAGIRATHA CIRCLE-ADILABAD
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Branch Manager ,
SuperintendingEngineer(FAC), Large Corporate Branch,
Mission Bhagiratha Circle,Adilabad, Oriental Bank of Commerce,
Adilabad Dist. Hyderabad,Telangana-500033
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment –“Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years”-Extension of
Validity of Bank Guarantee -Confirmation of genuineness-Requested-Reg.
*****
A copy of Bank Guarantee Extension for ₹:8,00,00,000-00 vide B.G.No.11100029216, Dated: 30.11.2016 of
Oriental Bank of Commerce,Large Corporate Branch,Hyderabad-500033, extended upto 28.05.2020 issued to M/s.
Megha Engineering & Infrastructures Ltd., Hyderabad for the work –“Providing Drinking Water to Habitations
in SRSP Adilabad Segment in Adilabad District Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District
Including Operation & Maintenance for 10 Years”s is here with communicated with a request to confirm the
genuineness of the BGs extension at the earliest.
Sd/-
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
The Executive Engineer,MB Grid Division,Nirmal for information.
Copy submitted to
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
\\T.C.F.B.O\\
.
Dy.EE PA TO SE
MISSION BHAGIRATHA CIRCLE-ADILABAD
.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Branch Manager ,
SuperintendingEngineer(FAC), Large Corporate Branch,
Mission Bhagiratha Circle,Adilabad, Oriental Bank of Commerce,
Adilabad Dist. Hyderabad,Telangana-500033
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment –“Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years”-Extension of
Validity of Bank Guarantee -Confirmation of genuineness-Requested-Reg.
*****
A copy of Bank Guarantee Extension for ₹:8,00,00,000-00 vide B.G.No.11100029216, Dated: 30.11.2016 of
Oriental Bank of Commerce,Large Corporate Branch,Hyderabad-500033, extended upto 28.05.2020 issued to M/s.
Megha Engineering & Infrastructures Ltd., Hyderabad for the work –“Providing Drinking Water to Habitations
in SRSP Adilabad Segment in Adilabad District Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District
Including Operation & Maintenance for 10 Years”s is here with communicated with a request to confirm the
genuineness of the BGs extension at the earliest.
Sd/-
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
The Executive Engineer,MB Grid Division,Nirmal for information.
Copy submitted to
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
\\T.C.F.B.O\\
.
Dy.EE PA TO SE
MISSION BHAGIRATHA CIRCLE-ADILABAD
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-–Adilabad District- SRSP-Adilabad Segment-SRSP-Reservior-
Water Level Below Minimum Draw Down Level(MDDL)-Critical Habs-Water Supply Through Trans
Poration-Request-Reg.
Ref: 1) G.O.Rt.No.885 of I&CADD(WRG-GRC) Department,Dated:30.10.2017.
2) Memo.No.AE-I/DEE-I/TDWSP-I/MDDL/2018,Dated:05.01.2019 of Chief Engineer,TDWSP-
I,Hyderabad.
3) T/o Lr.No.32/AEE3/SE/MB/SRSP-Reservior/MDDL/2018-19,Dated:05.01.2019.
4) Oral Instructions of Collector&District Magistrate,Adilabad during the Video Conference on
Mission Bhagiratha withMB Officials,Sarapanches,Panchayath Secreteris and MPDO’s of
Adilabad District on Dt:01.06.2019
5) Lr.No.01/AEE1/EE/MB INTRA/Drought Mitigation Measures/2019,Dated:18.06.2019
Of Executive Engineer,MB Intra Division,Adilabad.
*****
It is to submit that , vide reference 1st cited above Governament has instructed to maintain Minimum
Draw Down Levels(MDDLs) in certain reservoirs of Telangana for storing required quantum of water for
Government flagship programme “Mission Bhagiratha “ so as to provide protected and assured drinking water
on sustainable basisi to all houeholds of the states.
Further vide reference 2nd cited above instructions were issued to moniter the MDDLs in reservoirs and
co-ordinate with I&CAD Department officials in Maintaining the prescribed MDDLs.
Accordingly this office vide reference 3rd cited above,addressed the concerned Irrigation department
officials to Maintain the required MDDL in SRSP-Reservoir which is 320.35 Mts so as to avoid water scarcirty
as it serves Adilabad (254 Habs),Boath(480 Habs) Constituencies and Adilabad ULB in Adilabad District.
Further it is to submit that,as informed by the Irrigation officials the current water level in SRSP-
Reservoir is 319.7352 Mts, with present capacity of 5.66 TMC which is well below the prescribed MDDL due
to which water supply from SRSP is held up and also few habitations in KB-Asifabad segment of Adilabad
District are getting frequent interruptions in MB Water supply due to various reasons i.e.Power
Interuptions,Stabilization of Pipeline,Leakages,Repairs etc.
Consequently ,as per the instructions of The Collector&District Magistrate,Adilabad, The Executive
Engineer,MB Intra Division ,Adilabad taken up the Transportation of water in Certaion Critical Habitations
where MB Water is not being received an submitted list of the same in vide reference 5th cited .
In this regard,It is requested sir that kindly necessary instructions may be given the respective Main Grid
agencies to take up the Transportation of water for above critical habitations until the MB Water supply
resumed so as to avoid to avoid further problems.
Enclosure:As above
Yours faithfully,
`
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
The Executive Engineer,MB Grid Division&Intra ,Adilabad for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
.
Lr.No.10----WTP Repairs
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Executive Engineer,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, V&QC Division,Nirmal.
Adilabad Dist. Nirmal District.
Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment-–“Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years”-Agreement
Copies-Submitted-Reg.
.
Ref: 1.Your office Lr.No.AEE1/V&QC/Agreement Copies/2019,Dated:10.06.2019
*****
With reference to the subject and reference cited above I am herewith submitting the following Copies
of Agreements Concluded under the Work “Providing Drinking Water to Habitations in SRSP Adilabad
Segment in Adilabad District Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District Including Operation
& Maintenance for 10 Years” for information and necessary action.
1 04/2015-16 28.10.2015
2 4/INTRA/2016-17 03.08.2016
3 OFC/2016-17 09.09.2016
4 1AMS/2016-17 29.09.2016
5 MSGO128/2016-17 15.11.2016
6 04/A/2016-17 11.01.2017
7 4/INTRA2/2016-17 20.03.2017
8 04/B/2017 30.06.2017
S.No Original Date Remarks
Agreement/Supplementary
No
1 2 3 4
9 04/C/2016-17 03.07.2017
10 04/D/2016-17 30.09.2017
11 04/E/2016-17 24.11.2017
12 04/F/2016-17 30.11.2017
13 04/G/2019-20 18.01.2019
14 01/2018-19 18.01.2019
`
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
The Superintending Engineer,V&QC,MB Circle,Warangal for information
The Executive Engineer,MB Grid Division,Adilabad&Nirmal for information
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.