Sunteți pe pagina 1din 152

GOVERNMENT OF TELANGANA

OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri USN Murthy, M Tech, MBA, LLM. The M/s Mega Engineering&Infrastructure Ltd,
SuperintendingEngineer, S-2, Technocrat Indl.Estate, Balanagar,
RWS& S-Circle,Adilabad, Balanagar,
Adilabad Dist. Hyderabad,Telangana-500037

Lr.No.02/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Work ProgressDt:03.01.2018

Gentele Men,

Sub:- RWS&S Circle-Adilabad–SRSP Adilabad Segment-Slow Work Progress-Certain


Instructions-Reg

Ref: 1)Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2)Agreement.No 04/2016-17,Dated:04/2016-17 of Superintending
Engineer,TDWSP Circle,Nirmal.
3)Minutes of Meetings of Hon’ble Chief Minister Review meeting held on
24.01.2017&01.05.2017&23.09.2017.

*****
With reference to the subject and vide reference 2nd cited,M/s Megha Engineering&Infrastructure
limited entered into the agreement for the work “Providing Drinking Water to Habitations in SRSP-
Adilabad segment in Adilabad district“Est.Cost 1530.00 Cr of SE TDWSP,Adilabad Dist including
Operation and maintenance for 10 years.

Vide reference 3rd cited during the review meeting conducted by Hon’ble Chief Minister on
24.01.2017, M/s Megha Engineering&Infrastructure limited was instructed to speed up the work
and it was agreed to complete the project on schedule time lines but not later than December 2017
.

And also during the review meeting held on 01.05.2017& 23.09.2017 by the Hon’ble Chief
Minister it was instructed to supply water upto village OHSR’s by 31st Dec 2017.Inspite of all these
instructions progress of work in SRSP Adilabad segement is very poor & not upto the mark .The
status of work as on today as follows.

Structures

S.No Type of structure Total Completed Progress


1 Sumps 48 46 2
2 OHBR/BPT’s 16 7 9
3 GLBRs 6 3 3
4 PumpHouses 18 0 18
Total 88 56 32

Pipeline&Valves

S.No Description Total Procured Laid


1 MS Pipe 102.885 102.551 97.356
2 DI Pipe 823.499 796.491 577.113
3 HDPE Pipe 1336.417 1326.104 1066.716
4 BWSC Pipe 14.0 14.0 10.106
5 Valves 9368 8601 1450
Hence it is instructed to increase the men and machinery at work site for completing the bulk supply to
all habitations as the target date already elapsed on 31.12.2017.

Superintending Engineer,
RWS&S,Adilabad-Circle.

Copy to Executive Engineer RWS&S,Nirmal MB Grid for necessary action.


Copy to Executive Engineer RWS&S,Adilabad MB Grid for necessary action.
Copy submitted to Chief Engineer-III, TDWSP, Hyderabad for favour of Information.
Copy submitted to Engineer-in-Chief, RWSS, Hyderabad for favour of Information.

GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri USN Murthy, M Tech, MBA, LLM. The Superintending Engineer,
SuperintendingEngineer, RWS&S Circle,Mancherial.
RWS& S-Circle,Adilabad,

Lr.No.03/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /EM Works/EOAT, Dt:25.01.2018

Sir,

RWS&S Circle-Adilabad –SRSP Adilabad Segment-


Design,Supply,Erection,Testing,Comissioning of electro mechanical work with
SCADA&Instrumentation along with associated substation and switch gear including all
connected for various pumping stations under package-III”-Extension of Agreement Time
Proposals-Submitted-Reg.
Ref: 1) Original Agreement.No AEE/01/2017-18,Dated:18.04.2017 of Superintending
Engineer,TDWSP Circle,Nirmal.
2) Lr.No.MB GRID NIRMAL/AEE/SRSP ADB Segment/EM Works/EOAT,Dated:22
3) Lr.No.MB GRID NIRMAL/AEE/SRSP ADB Segment/EM Works/EOAT,Dated:22.01.2018

*****
With advert to the subject and vide reference 1st cited above ,the agreement period for the work
“Design,Supply,Erection,Testing,Comissioning of electro mechanical works with SCADA &
Instrumentation along with associated substation and switch gear including all connected for various
pumping station located at various places in erstwhile Adilabad,Nizamabad&Karimnagar,including
defect liability period and operation and maintainance for 10 years”,concluded on 17.01.2018.

Vide reference 2nd&3rd cited above ,the Executive Engineer,RWS&S,MB Grid Nirmal & the
Executive Engineer,RWS&S,MB Grid Adilabad have submitted EOAT proposals for above said work
in SRSP Adilabad segment duly recommending EOAT upto 30th April,2018 based on the reasons
explained by the agency.

Hence,I request the Superintending Engineer,RWS&S,Circle Mancherial to grant EOAT upto 30th
April 2018 for SRSP Adilabad segment,for taking further necessary action.

Your’s faithfully,
Superintending Engineer,
RWS&S Circle,Adilabad.

Copy submitted to Chief Engineer-III,TDWSP,Hyderabad for favour of information.


GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri USN Murthy, M Tech, MBA, LLM. The M/s Mega Engineering&Infrastructure Ltd,
SuperintendingEngineer, S-2, Technocrat Indl.Estate, Balanagar,
RWS& S-Circle,Adilabad, Balanagar,
Adilabad Dist. Hyderabad,Telangana-500037

Lr.No.04/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Roads Damage Dt:10.02.2018

Gentile Men,

Sub:- RWS&S Circle-Adilabad –SRSP Adilabad Segment-Damage of Roads due to laying


of water pipelines of Mission Bhagiratha Scheme -Certain Instructions-Reg

Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No 04/2016-17,Dated:04/2016-17 of Superintending
Engineer,TDWSP Circle,Nirmal.
3) Standing Committee meeting of Zilla Parishad Adilabad on 10.02.2018.

*****
With reference to the subject and vide reference 2nd cited above, M/s Megha
Engineering&Infrastructure limited entered into the agreement for the work “Providing Drinking
Water to Habitations in SRSP-Adilabad segment in Adilabad district “Est.Cost 1530.00 Cr of SE
TDWSP,Adilabad Dist including Operation and maintenance for 10 years.

Vide reference 3rd cited during the standing committee meeting of Zilla Parishad
Adilabad on 10.02.2018, Chairperson, Zilla Parishad Adilabadexpressed displeasure regarding the
damages done to roads in Erstwhile Adilabad district during excavation for pipelines and instructed
to clear the debris on roads and complete the restoration of damaged roads immediately to avoid
any accidents and discomfort to the pelple.
In view of the same ,the agency M/s Megha Engineering&Infrastructure limited instructed to
restore damaged roads immediately while executing Mission Bhagiratha works and clear the debris
on roads and requested further to intimate the same to this office for record.

Superintending Engineer,
RWS&S,Adilabad-Circle.

Copy to Executive Engineer RWS&S,Nirmal MB Grid for necessary action.


Copy to Executive Engineer RWS&S,Adilabad MB Grid for necessary action.
Copy submitted to Chief Engineer-III, TDWSP, Hyderabad for favour of Information.
Copy submitted to Engineer-in-Chief, RWSS, Hyderabad for favour of Information.

GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri USN Murthy, M Tech, MBA, LLM. The Project Director,
SuperintendingEngineer, WAPCOS,AC Guards,
RWS& S-Circle,Adilabad, Hyderabad,Telangana-500004
Adilabad Dist.

Lr.No.05/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Designs Dt:15.02.2018

Sir,

Sub:- RWS&S Circle-Adilabad –“Providing Drinking Water to Habitations in SRSP-Adilabad


Segment in Adilabad District”-Vetting of Designs and Drawings-Requested-Reg. I am

Ref:- 1. Agg.No.Lr.No.AEE1/DEE TDWSP plg2/RWS&S/2015 dt.3.7.2015.


2. G.O.Ms.No.47, PR&RD (RWS-IV) Dept., dt.01.06.2015.
3. G.O.Ms.No.50, PR&RD (RWS-IV) Dept., dt.19.06.2015.
With reference to the subject and vide reference cited above I am herewith submitting the following
designs and drawings for vetting.
1.Design report for Sluice Valve chamber for 500 mm dia DI Pipe line.
2.Design report for Sluice Valve chamber for 450 mm dia DI Pipe line.
3.Design report for Sluice Valve chamber for 400 mm dia DI Pipe line.
4.Design report for Sluice Valve chamber for 350 mm dia DI Pipe line.
5.Design report for Sluice Valve chamber for 300 mm dia DI Pipe line.
6.Design report for Sluice Valve chamber for 250 mm dia DI Pipe line.
7.Design report for Sluice Valve chamber for 200 mm dia DI Pipe line.
8.Design report for Sluice Valve chamber for 150 mm dia DI Pipe line.
9.Design report for Sluice Valve chamber for 100 mm dia DI Pipe line.
10.Design report for Butterfly Valve(600 mm Dia) Chamber for Pressure Main Of 930 mm dia.
11.Design report for pipe line steel bridge from Adilabad Gutta to Bhoraj X roads
At DI Pipe line of 500 mm dia@Ch.11.385 Km-11.570 Km.
12.Hydraulic Design for Clear water pumping mains –Jandaguda X rd sumo to GLBR at Chinchughat
13.Hydraulic Design for clear water pumping mains-Daheguda Sump to Molalgutta 40 KL OHBR.

Hence it is requested to vet the above designs and drawings as per agreement conditions at an
early date and communicate.

Encl: As above

Yours Faithfully,
Superintending Engineer,
RWS&S,Adilabad-Circle.
GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

Memo No :01/AEE3/DEE1/SRSP ADB/Inaguration of Scheme/2017-18, Dt:23.03.2018

Sub:RWS&S Circle-Adilabad-SRSP Adilabad Segment-Inaguration of Scheme -Certain


Instructions Issued-Reg.
Ref:1.Review meeting held on 20.03.2018 by Hon’ble Minister Sri.A.Indrakaran Reddy &
Sri Jogu Ramanna along with MLAs&MLC of Erstwhile Adilabad District at Aranya
Bhavan Hyderabad.
2.Mail from CE,TDWSP-III,Hyderabad on 23.03.2018,10:51 AM.

*****

The immediate personal attention of Executive Engineers and Deputy Executive


Engineers,RWS&S,MB Grid noted in the address entry is invited to the subject cited.
wherein,instructions were issued during the review meeting held on 20.03.2018 at Aranya Bhavan
,Hyderabad by Hon’ble Minister Sri.A.Indrakaran Reddy & Sri.Jogu Ramanna along with MLAs
&MLCof Erstwhile Adilabad District to give bulk supply to total habs(1176) in SRSP Adilabad
Segment by April.
Further vide reference 2nd cited ,the target dates for inaguration of scheme in respective
districts have been communicated.
Therefore,all the Executive Engineers and Deputy Executive Engineers are requested to
follow the instructions scrupulously and direct the concerned Section officers and Agencies
accordingly for ensuring timely completion of works. And also the concerned Executive Engineers
Are instructed to brief the day to day progress to the undersigned.
.

Superintending Engineer,
RWS&S Circle,Adilabad.
To,
The Executive Engineer,RWS&S,MB Grid Division, Nirmal/Adilabad for necessary action.
The Deputy Executive Engineer,RWS&S,MB Grid Sub Division Nirmal/Bhainsa/Ichoda/Adilabad
for necessary action.
Copy Submitted to Chief Engineer-III,TDWSP Hyderabad for favour of information.

GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri USN Murthy, M Tech, MBA, LLM. The Chief Engineer-III,
SuperintendingEngineer, TDWSP,
RWS& S-Circle,Adilabad, Hyderabad.
Lr.No.06/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /EM Works/2017-18, Dt:03.01.2018

Sir,

RWS&S Circle-Adilabad –SRSP Adilabad


SegmenDesign,Supply,Erection,Testing,Comissioning of electro mechanical work with
SCADA&Instrumentation along with associated substation and switch gear including all
connected for various pumping stations under package-III”-Extension of Agreement Time
Proposals-Submitted-Reg.

Ref: 1) Original Agreement.No AEE/01/2017-18,Dated:18.04.2017 of Superintending


Engineer,TDWSP Circle,Nirmal.
2) Lr.No.5/RC/RWS&S/PKG-3/EMW/ADB/EE./2017-18/83,Dated:03.01.2018 of Executive
Engineer,RWS&S,MB Grid Adilabad.

*****
With reference to the subject and vide reference 2nd cited above ,the Executive
Engineer,RWS&S,MB Grid Adilabad has submitted the revised head calculations &Pump Performance
curves for the pumps at following Pump House.
1.Addagutta Sump to Mangurla OHBR

The same is herewith submitted for taking further necessary action.

Your’s faithfully,
Superintending Engineer,
RWS&S Circle,Adilabad.

Copy submitted to Chief Engineer-III,TDWSP,Hyderabad for favour of information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY AND SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri USN Murthy, M Tech, MBA, LLM. The Chief Engineer,
SuperintendingEngineer, TDWSP-III,RWS&S,
RWS& S-Circle,Adilabad, Hyderabad.

Lr.No.05/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Designs Dt:15.02.2018

Sir,

Sub:- RWS&S Circle-Adilabad –“Providing Drinking Water to Habitations in SRSP-Adilabad


Segment in Adilabad District”-Vetting of Designs and Drawings-Requested-Reg. I am

Ref:- 1. Agg.No.Lr.No.AEE1/DEE TDWSP plg2/RWS&S/2015 dt.3.7.2015.


2. G.O.Ms.No.47, PR&RD (RWS-IV) Dept., dt.01.06.2015.
3. G.O.Ms.No.50, PR&RD (RWS-IV) Dept., dt.19.06.2015.
With reference to the subject and vide reference cited above I am herewith submitting the following
designs and drawings for vetting.
1.Design report for Sluice Valve chamber for 500 mm dia DI Pipe line.
2.Design report for Sluice Valve chamber for 450 mm dia DI Pipe line.
3.Design report for Sluice Valve chamber for 400 mm dia DI Pipe line.
4.Design report for Sluice Valve chamber for 350 mm dia DI Pipe line.
5.Design report for Sluice Valve chamber for 300 mm dia DI Pipe line.
6.Design report for Sluice Valve chamber for 250 mm dia DI Pipe line.
7.Design report for Sluice Valve chamber for 200 mm dia DI Pipe line.
8.Design report for Sluice Valve chamber for 150 mm dia DI Pipe line.
9.Design report for Sluice Valve chamber for 100 mm dia DI Pipe line.
10.Design report for Butterfly Valve(600 mm Dia) Chamber for Pressure Main Of 930 mm dia.
11.Design report for pipe line steel bridge from Adilabad Gutta to Bhoraj X roads
At DI Pipe line of 500 mm dia@Ch.11.385 Km-11.570 Km.
12.Hydraulic Design for Clear water pumping mains –Jandaguda X rd sumo to GLBR at Chinchughat
13.Hydraulic Design for clear water pumping mains-Daheguda Sump to Molalgutta 40 KL OHBR.

Hence it is requested to vet the above designs and drawings as per agreement conditions at an
early date and communicate.

Encl: As above

Yours Faithfully,
Superintending Engineer,
RWS&S,Adilabad-Circle.

GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri USN Murthy, M Tech, MBA, LLM. The M/s Mega Engineering&Infrastructure Ltd,
SuperintendingEngineer, S-2, Technocrat Indl.Estate, Balanagar,
RWS& S-Circle,Adilabad, Balanagar,
Adilabad Dist. Hyderabad,Telangana-500037

Lr.No.04/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Roads Damage Dt:10.02.2018

Gentile Men,

Sub:- RWS&S Circle-Adilabad –SRSP Adilabad Segment-Damage of Roads due to laying


of water pipelines of Mission Bhagiratha Scheme -Certain Instructions-Reg

Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No 04/2016-17,Dated:04/2016-17 of Superintending
Engineer,TDWSP Circle,Nirmal.
3) Standing Committee meeting of Zilla Parishad Adilabad on 10.02.2018.

*****
With reference to the subject and vide reference 2nd cited above, M/s Megha
Engineering&Infrastructure limited entered into the agreement for the work “Providing Drinking
Water to Habitations in SRSP-Adilabad segment in Adilabad district “Est.Cost 1530.00 Cr of SE
TDWSP,Adilabad Dist including Operation and maintenance for 10 years.
Vide reference 3rd cited during the standing committee meeting of Zilla Parishad
Adilabad on 10.02.2018, Chairperson, Zilla Parishad Adilabad expressed displeasure regarding the
damages done to roads in Erstwhile Adilabad district during excavation for pipelines and instructed
to clear the debris on roads and complete the restoration of damaged roads immediately to avoid
any accidents and discomfort to the pelple.

In view of the same ,the agency M/s Megha Engineering&Infrastructure limited instructed to
restore damaged roads immediately while executing Mission Bhagiratha works and clear the debris
on roads and requested further to intimate the same to this office for record.

Superintending Engineer,
RWS&S,Adilabad-Circle.

Copy to Executive Engineer RWS&S,Nirmal MB Grid for necessary action.


Copy to Executive Engineer RWS&S,Adilabad MB Grid for necessary action.
Copy submitted to Chief Engineer-III, TDWSP, Hyderabad for favour of Information.
Copy submitted to Engineer-in-Chief, RWSS, Hyderabad for favour of Information

GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri USN Murthy, M Tech, MBA, LLM. The M/s Raghava Constructions,
SuperintendingEngineer, Narayanapuram(V),Peruvancha(P),
RWS& S-Circle,Adilabad, Khammam-507209.
Adilabad Dist.

Lr.No.01/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /EM Progress Dt:18.04.2018

GentleMen,

Sub:- RWS&S Circle-Adilabad –SRSP Adilabad Segment-Electromechanical works-Slow


progress in Erection of Pump Sets -Certain Instructions-Reg

Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No AEE/01/2017-18,Dated:18.04.2017 of Superintending
Engineer,TDWSP Circle,Nirmal.
3) Minutes of Review meeting by Hon’ble Chief Minister,Telangana held on
24.08.2017
4) Inspection Report of Engineer-in-Chief RWS&S,Hyderabad,Dated:23.12.2017
5)Minutes of review meeting by Hon’ble Vice Chairman,TDWSCL,on 31.01.2018
6) Review and instructions of Secretary,RWS&S on 07.02.2018
7) Lr.No.Mission Bhagiratha/Pump Sets 1/2018,Dt:08.02.2018 of Chief Engineer,
TDWSP-III,Hyderabad.
8)Minutes of Meeting held on 20.03.2018 at Aranya Bhavan by Hon’ble
MLA’s,MLC’s of Erstwhile Adilabad District
9) Minutes of review meeting held on 12.04.2018 by Superintending
Engineer,RWS&S Circle,Adilabad.
*****
With reference to the subject and vide reference 2nd cited above, M/s Raghava Constructions
entered into the agreement for the work “Design, Supply, Erection, Testing and commissioning of
Electro mechanical works with SCADA & Instrumentation along with associated substation and
switch gear including all connected accessories for various Pumping stations located at various places
in erstwhile districts Adilabad,Nizamabad and Karimnagar Including, defects liability period and
operation and maintenance for 10 years (Package No.III).
Vide reference 3rd cited during the review meeting conducted by the Hon’ble Chief
Minister,Telangana on 24.08.2017,M/s.Raghava Construction was instructed to
procure,erect,commission all the pumpsets in phased manner from September to November 2017 .

Vide reference 5th&6th cited, during the review meetings with Hon’ble Vice Chairman,TDWSCL
&Secretary to Governament,RWS&S target dates for commissioning pumpsets and districts with bulk
water supply Were agreed and same were communicated through vide reference 7th cited for completing
the errection of pumpsets.
And also Hon’ble Minister For BC Welfare, Forest and Environment expressed displeasure
regarding progress of pumpsets in the review meeting held on 20.03.2018 and the agency M/s.Raghava
Constructions assured that by 05.04.2018 all the pumps will be errected
But it is regretted to inform thatInspite of all these several instructions the pace of erection of
pumpsets in SRSP-Adilabad Segment isVery poor due to which commissioning of bulk water supply
is getting delayed.Hence,M/s.Raghava Constructions Is hereby instructed to take necessary action
to increase the pace of erection of pumpsets so as to avoid any delays in commissioning bulk water
supply as it immensely benefits the public with potable water supply.

Superintending Engineer,
RWS&S,Adilabad-Circle.

Copy to Executive Engineer RWS&S,Nirmal MB Grid for necessary action.


Copy to Executive Engineer RWS&S,Adilabad MB Grid for necessary action.
Copy submitted to Chief Engineer-III, TDWSP, Hyderabad for favour of Information.
Copy submitted to Engineer-in-Chief, RWSS, Hyderabad for favour of Information.
Copy Submitted to District Collector & Magistrate,Adilabad for favour of information.
Copy Submitted to District Collector & Magistrate,Nirmal for favour of information.

GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.01/AEE3/DEE-I/MB GRID Nirmal/Road Restoration/2018,Dated:27.04.2018


Sub:Mission Bhagiratha-SRSP-Adilabad Segment-Nirmal District-NH-61-Damage to road
Boundary-Detailed report-Called for-Regarding.

Ref:1.Lr.No.DB/T2/NHP/Mission Bhageeratha /2017-18,Dated:28.02.2018 of Executive


Engineer,(R&B)NH Division,Perkit.
2.Lr.No.AEE/MB Grid Nirmal/SRSP ADB/Pipeline-NH/Demand
Note/2018,Dated:06.04.2018 of Executive Engineer,RWS&S,MB Grid Nirmal.

The personal attention of Executive Engineer,RWS&S,MB Grid Division,Nirmal is invited


The references cited wherein it was informed that NH-61 damaged from chainage Km 667/500 to Km 668/315
and from chainage Km 0/0 to Km 3/240 while laying Mission Bhagiratha pipeline and an estimate of Rs.3.60
Crs was submitted to deposit as Road restoration charges.

Under these circumstances ,the Executive Engineer,RWS&S,MB Grid Division,Nirmal is


directed to submit the detailed report on the damages done to NH-61 while laying Mission Bhagiratha pipeline
and to verify the submitted estimate and report compliance for taking further necessary action.

Encl:Road Restoration Charge Estimate

Superintending Engineer
Mission Bhagiratha Circle-Adilabad

To,
Executive Engineer,RWS&S,MB Grid Division,Nirmal
Copy to Executive Engineer,(R&B) NH Division,Perkit for information.
Copy Submitted to Chief Engineer,TDWSP-III,Hyderabad for favour of information.

NOTICE-I

GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Notice No:01/AEE3/DEE-I/MB/SRSP ADB /WORK PROGRESS/2018,Dated:30.04.2018

Sub:- Mission Bhagiratha Circle-Adilabad –“Providing Drinking Water to Habitations


in SRSP-Adilabad Segment in Adilabad District” including operation and
Maintainance for 10 years –Delay in completion of works-Notice issued-Reg.

Ref:- 1)Minutes of the review meeting by Hon’ble Vice Chairman,TDWSCL,on 31.01.2018


2) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
3) Agreement.No 04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP
Circle,Nirmal.
The personal attention of M/s.Megha Engineering &Infrastructure Limited is invited to the reference 1st
cited,wherein the authorized representative from your company who attended the review meeting with
Hon’ble Viceh Chairman,TDWSCL on 31.01.2018 was agreed to complete the total pipeline
Of SRSP Adilabad segment by 20.02.2018.

And also vide reference 3rd cited the agreement period for the above work was completed
On 27.04.2018.But still as per the ground reports the pipeline laying ,errection of valves e.t.c are still in progress
due to which most of the habitations are not getting bulk water which include fluoride affected and
critical(transportation&hiring) habs.

Under these circumstances it is inevitable to the department to initiate action against you for
Failing in executions as per the agreed dates which is of serious concern as it is the flagship programme of
Governament which is aimed at drought free future of Telangana and also it immensely benifitis the public with
potable water supply.

The reasons for delay occurred regarding the above should be submitted to the undersigned with
in 48 hours for taking further necessary action.

Treat this as most urgent.

Superintending Engineer
Mission Bhagiratha Circle-Adilabad

To,
M/s.Megha Engineering and Infrastructure Limited, S-2, Technocrat Indl.Estate,
Balanagar,Hyderabad,Telangana-500037.(emailed copy to the following email
ids:project4124@meilgroup.info,khs@meilgroup.com).
The Executive Engineers,RWS&S,MB Grid, Adilabad&Nirmal for initiating action against agency.
Copy submitted to Chief Engineer,TDWSP-III,Hyderabad for favour of information
Copy submitted to Engineer-in-Chief ,Hyderabad for favour of information
GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.02/AEE3/DEE-I/MB GRID Nirmal/Minimum Water Levels /2018,Dated:16.05.2018

Sub:Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment-Water levels to be


Maintained in the reservoirs-Certaion instructions-issued-Reg.

Ref:1.I&CAD (WRC-GRC)Dept,G.O.Rt.No.885,Dt:30.10.2017

2.MemoNo AEE1/DEE(Grid)/RWS&S/Water drawl permissions/2014,Dt:14.03.2018 of


Engineer-In-Chief,RWS,Hyderabad.
3.Minutes of Review meeting by Secretary,RWS(FAC) on 14.05.2018 at O/o ENC,RWS
Hyderabad

The immediate personal attention of the Executive Engineer,RWS&S,MB Grid


Division,Nirmal is invited to the reference 1st cited wherein Governament of Telangana issued orders to I&CAD
Dept to maintain the source wise Minimum Draw Down Level(MDDL)at Project/Reservior/River for storing
required quantum of water for uninterrupted supply of drinking water under “Mission Bhagiratha”and the same
was communicated vide reference 2nd cited.

And during the review meeting on 14.05.2018,Secretary,RWS expressed much displeasure


that in some reservoirs the water levels decreased below the MDDL fixed by the government and the same was
not brought to the notice of higher authorities. It was instructed strictly to moniter the levels at the reservoirs
w.r.t.GO.No.885 and bring to the notice of higher authorites if any deviations occur.

In this regard,The Executive Engineer,RWS&S,MB Grid Division,Nirmal is hereby instructed to


moniter the levels in SRSP &Gaddenna Vagu projects regularly in coordination with concerned I&CAD Dept
officials in maintaining the prescribed MDDLs as per G.O.NO.885 and brief the deviations to the undersigned if
any occurs so as to submit the same to higher authorities for taking further necessary actions.

Superintending Engineer
Mission Bhagiratha Circle-Adilabad

To,
Executive Engineer,RWS&S,MB Grid Division,Nirmal for taking necessary action.
Copy Submitted to Chief Engineer-III,TDWSP,Hyderabad for favour of information

GOVERNMENT OF TELANGANA
OFFICE OF THE Dy.EXECUTIVE ENGINEER, RWS&S SUB DIVISION, ADILABAD

From, To,
SriN.V.Ramana B.Tech. The Manager ,
Dy.Executive Engineer, Bharathi Airtel Limited,
RWS& S-Sub Division,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.01/AEE1/ ADB SD/DAMAGE TO SIM /2018-19 Dt:01.06.2018

Sub:- RWS&S Sub Division-Adilabad –Damage to Departmental SIM-Issue of Duplicate


SIM Card-Request-Reg

It is to inform you that ,the department AIRTEL SIM card bearing No: 7995660
696 has been damaged on Dt:31.05.2018.

Therefore it is requested to the Manager,Bharathi Airtel Limited Hyderabad


office to issue duplicate SIM Card on the same number to Sri.M.Shanthi
Kumar,Assistant Engineer,RWS&S,Sub Division Adilabad at an earliest.

Your’s faithfully,

Dy.Executive Engineer,
RWS&S SD,Adilabad
NOTICE-I

GOVERNMENT OF TELANGANA
OFFICE OF THE EXECUTIVE ENGINEER, RWS&S,MB GRID DIVISION, ADILABAD

Notice No:01/AEE1/MB/SRSP ADB /ADB/ADDAGUTTA/2018,Dated:06.06.2018

Sub:- RWS&S-MB Grid Division-Adilabad –SRSP-Adilabad Segment–Delay in errection


of Addagutta Pump sets-Notice issued-Reg.

Ref:- 1)Agreement.No AEE/01/2017-18,Dated:18.04.2017 of SuperintendingEngineer,TDWSP


Circle,Nirmal.
2)Lr.No.01/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /EM Progress,Dt:18.04.2018 of
Superintending Engineer,Mission Bhagiratha Circle,Adilabad.
3) Minutes of review meeting held on 12.04.2018 by Superintending
Engineer,RWS&S Circle,Adilabad.
4)Minutes of Meeting held on 20.03.2018 at Aranya Bhavan by Hon’ble
MLA’s,MLC’s of Erstwhile Adilabad District
5) Lr.No.Mission Bhagiratha/Pump Sets 1/2018,Dt:08.02.2018 of Chief Engineer,
TDWSP-III,Hyderabad.

The personal attention of M/s.Raghava Constructions is invited to the references cited,wherein


Instructions were issued time to time to complete the procurement,errection and commissioning of all
pumpsets in Adilabad district under SRSP-Adilabad segment so as to supply bulk water to all the habitations.

Inspite of all these instructions,based on ground report it was found that Pumpsets for Addagutta
Pumphouse are still not procured.

Under these circumstances it is inevitable to the department to initiate action against you as
even procurement of pumpsets is not completed which is of serious concern.
The reasons for delay occurred regarding the above should be submitted to the undersigned with
in 48 hours for taking further necessary action.

Treat this as most urgent.

Superintending Engineer
Mission Bhagiratha Circle-Adilabad

To,
M/s.Raghava Constructions,Narayanapuram(V),Peruvancha(P),Khammam-507209.(emailed copy to the
following email id:sanath2@eivipl.com).
Copy submitted to Superintending Engineer,Mission Bhagiratha Circle,Adilabad for favour of information.
Copy submitted to Chief Engineer-III,TDWSP,Hyderabad for favour of information

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's),. The Branch Manager,
SuperintendingEngineer(FAC), Large Corporate Branch,
RWS& S-Circle,Adilabad, Bank of Commerce,
Adilabad Dist. Hyderabad,Telangana-500033

Lr.No.02/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /BG/2018-19 Dt:26.06.2018

GentleMen,

Sub:- RWS&S Circle-Adilabad –SRSP Adilabad Segment- Extension of Validity of Bank


Guarantee -Confirmation of genuineness-Requested-Reg.

Ref: 1)Agreement No:AEE1/01/2015-16,Dated:09.04.2015 of SE,RWS&S,Adilabad.


2)Lr.No.AEE1/Extension BG(FSD)/MB Grid/2018,Dated:22.06.2018 of Executive
Engineer,RWS&S,MB Grid Division Nirmal.

*****
A copy of Bank Guarantee Extension for ₹:8,00,00,000-00 vide B.G.No.11100029316, Dated: 30.11.2016 of Oriental
Bank of Commerce,Large Corporate Branch,Hyderabad extended upto 28.05.2019issued to M/s. Megha Engineering
& Infrastructures Ltd., Hyderabadfor the work ““Construction of Intake well, WTP and Raw Water Pumping
main in Adilabad segment, Kaddam segment, Asifabad segment and Mancherial segment of
Telangana drinking Water supply project (TDWSP)”Est.cost of Rs.440.50 Crs is here with communicated
with a request to confirm the genuineness of the BGs extension at the earliest.

Yours faithfully,

Encl: BGs Extension Letter


Superintending Engineer(FAC),
RWS&S Circle, Adilabad

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's),. The Zonal Manager,
SuperintendingEngineer(FAC), Hyderabad Zone,
RWS& S-Circle,Adilabad, Bank of India,
Adilabad Dist. Hyderabad,Telangana-500004

Lr.No.01/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /BG/2018-19 Dt:26.06.2018

GentleMen,
Sub:- RWS&S Circle-Adilabad –SRSP Adilabad Segment-Extension of Validity of Bank
Guarantee-Confirmation of genuineness-Requested-Reg.

Ref: 1)Agreement No:04/2015-16,Dated:28.10.2016 of SE,TDWSP,Nirmal.


4)Lr.No.AEE1/Extension BG(FSD)/MB Grid/2018,Dated:22.06.2018 of Executive
Engineer,RWS&S,MB Grid Division Nirmal.

*****

A copy of Extension of Bank Guarantee for Rs.25,50,00,000/- vide B.G.No.5625IPEBG170124,


Dated: 27.12.2017 of Bank of India, Hyderabad Zone,Hyderabad extended from 27.06.2018 to 26.06.2019
issued to M/s. Megha Engineering & Infrastructures Ltd., Hyderabadfor the work “Adilabad District-
TDWSP-Providing Drinking Water to Habitations in SRSP-Adilabad segment in Adilabad District
“ under Telangana Drinking Water Supply Project with an estimated cost of Rs.1530.00 Crs is here
with communicated with a request to confirm the genuineness of the BGs extension at the earliest.

Yours faithfully,

Encl: BGs Extension Letter


Superintending Engineer(FAC),
RWS&S Circle, Adilabad

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's),. The Branch Manager,
SuperintendingEngineer(FAC), Large Corporate Branch,
RWS& S-Circle,Adilabad, Oriental Bank of Commerce,
Adilabad Dist. Hyderabad,Telangana-500033

Lr.No.03/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /BG/2018-19 Dt:26.06.2018

GentleMen,

Sub:- RWS&S Circle-Adilabad –SRSP Adilabad Segment- Extension of Validity of Bank


Guarantee -Confirmation of genuineness-Requested-Reg.

Ref: 1)Agreement No:04/2015-16,Dated:28.10.2016 of SE,TDWSP,Nirmal.


2)Lr.No.AEE1/Extension BG(FSD)/MB Grid/2018,Dated:22.06.2018 of Executive
Engineer,RWS&S,MB Grid Division Nirmal.

*****
A copy of Bank Guarantee Extension for ₹:8,00,00,000-00 vide B.G.No.11100029216, Dated: 30.11.2016 of Oriental
Bank of Commerce,Large Corporate Branch,Hyderabad extended upto 28.05.2019 issued to M/s. Megha
Engineering & Infrastructures Ltd., Hyderabadfor the work ““Adilabad District-TDWSP-Providing Drinking
Water to Habitations in SRSP-Adilabad segment in Adilabad District”under Telangana Drinking Water
Supply Project with an estimated cost of Rs.1530.00 Crs is here with communicated with a request to confirm
the genuineness of the BGs extension at the earliest.

Yours faithfully,

Encl: BGs Extension Letter


Superintending Engineer(FAC),
RWS&S Circle, Adilabad

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer,
SuperintendingEngineer(FAC), TDWSP-III,RWS&S,
RWS& S-Circle,Adilabad, Hyderabad.
Adilabad Dist.
Lr.No.04/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Small Pumpset/2018-19, Dt:04.07.2018

Sir,

Sub: RWS&S Circle-Adilabad –SRSP Adilabad Segment-Providing Drinking Water to Habitations


in Nirmal District-EM Works-Pumpsets other than Electromechanical Agreement-
Unwillingnness from Agencies-Permission for entrusting to third party-Request-Reg

Ref: 1) G.O.Rt.NO:394, Dated:23.06.2015 of PR &RD(RWS) department.


2) T.S.No. 8/2015-2016, Dt.05.08.2015 of the Chief Engineer, TDWSP,
Hyderabad.3)Lr.No.RC/RWS&S/PKG-3/EMW/CE/2018-19/17,Dated:05.12.2017 of Raghava
construction received through mail on 19.05.2018
4)Lr.No. MB Grid Nirmal/SRSP ADB/EM Works/Small Pumpsets/2018,Dated:20.06.2018 of
Executive Engineer,RWS&S,MB Grid Division,Nirmal.
*****
With advert to the subject and vide references 1st and 2nd cited above, the work " Providing Drinking
Water to habitations under SRSP Adilabad segment in Adilabad district Est. cost 1530. Crores of SE,
TDWSP, Adilabad district including Operation & maintenance for 10 years.” is sanctioned under Mission
Bhagiratha and a provision is made in the approved estimate for the Erection of submersible pumpsets.

Vide reference 3rd cited above, the agency M/s Raghava Constructions which is executing the
Electromechanical works under SRSP Adilabad segment intimated that they are unable to execute the
Design, supply, Erection, testing &commissioning of pumpsets other than their scope of work(pumpsets
below 15 HP).

Where as Vide reference 4th cited Executive Engineer,RWS&S,MB Grid Division informed that
M/s.Megha Engineering & Infrastructure Ltd which is executing civil works has also given its unwillingness
in executing pumpsets other than in Electromechanical Agreement in Nirmal District and requested this
office to accord permission for entrusting pumpsets other than Electromechanical agreement to the third
party.
Hence,The Chief Engineer-III,TDWSP is hereby requested to accord permission for entrusting
pumpsets other than in Electromechanical agreement to third party in order to supply bulk water to all
the habitations in Nirmal district under SRSP Adilabad Segment within the targeted date.

Thanking you sir.

Your’s faithfully,

Superintending Engineer(FAC),
RWS&S Circle,Adilabad.

Copy submitted to Engineer-in-Chief,RWS&S,Hyderabad for favour of information.


Copy to Executive Engineer,RWS&S,MB Grid Division,Nirmal for information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer,
SuperintendingEngineer(FAC), TDWSP-III,RWS&S,
RWS& S-Circle,Adilabad, Hyderabad.
Adilabad Dist.
Lr.No.05/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Small Pumpset/2018-19, Dt:04.07.2018

Sir,

Sub: RWS&S Circle-Adilabad –SRSP Adilabad Segment-Providing Drinking Water to Habitations


in Nirmal District-EM Works-Pumpsets other than Electromechanical Agreement- Pumpsets
other than electromechanical agreement –Submision of Approved Estimates –for further
scrutiny and technical approval- Reg
Ref: 1) G.O.Rt.NO:394, Dated:23.06.2015 of PR &RD(RWS) department.
2) T.S.No. 8/2015-2016, Dt.05.08.2015 of the Chief Engineer, TDWSP, Hyderabad.
3)Lr.No. MB Grid Nirmal/SRSP ADB/EM Works/Small Pumpsets/2018,Dated:20.06.2018 of
Executive Engineer,RWS&S,MB Grid Division,Nirmal.

*****
With advert to the subject and vide references 1st and 2nd cited above, the work " Providing Drinking
Water to habitations under SRSP Adilabad segment in Adilabad district Est. cost 1530. Crores of SE,
TDWSP, Adilabad district including Operation & maintenance for 10 years.” is sanctioned under Mission
Bhagiratha and a provision is made in the approved estimate for the Erection of submersible pumpsets.

Wherein Vide reference 3rdcited Executive Engineer,RWS&S,MB Grid Division,Nirmal has


scrutinized and technically approved sub estimates for Supply and Erection and commissioning of clear
water pumpsets at 7 locations as per site feasibility and submitted the same to this office for further
technical approval.

In this regard I am herewith submitting the 7 No. of approved Sub Estimates along with general
abstract for further scrutiny and technical approval.

Thanking you sir.

Your’s faithfully,
Encls: Sub Estimates(7 Nos.)

Superintending Engineer(FAC),
RWS&S Circle,Adilabad.

Copy submitted to Engineer-in-Chief,RWS&S,Hyderabad for favour of information.


Copy to Executive Engineer,RWS&S,MB Grid Division,Nirmal for information.

GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

Memo No.01/AEE3/DEE-II/BSNL/Cable Damages/2018,Dated:12.07.2018

Sub:RWS&S Circle-Adilabad-BSNL-Damages to underground cables-Recovery dues-Detailed


Report-Req-Reg.
Certaion instructions-issued-Reg.
Ref:1.Lr.No.GMTD/ADB/Plg/Way Leave Permissions/2010-19/Vol.I/67,Dated:02.07.2018 of
the General Manager,BSNL,Adilabad.

The immediate personal attention of the Executive Engineers,RWS&S,MB Grid & Intra
Divisions of Adilabad circle is invited to reference cited wherein it was informed that at certain locations BSNL
underground cables(Both Copper&OFC) were damaged due to Mission Bhagiratha works and accordingly
demand notes were raised and and payment for the same is pending.
In this regard,while enlcosing the copy of reference cited,all the Executive
Engineers,RWS&S,MB Grid & Intra Divisions of Adilabad circle hereby directed to go through the points raised
by BSNL and and submit a detailed report on the points related to their respective juirsidictions for taking
further necessary action.

Superintending Engineer(FAC)
RWS&S Circle-Adilabad

To,
The Executive Engineers,RWS&S,MB Intra Divisions,Nirmal&Adilabad.
The Executive Engineers,RWS&S,MB Grid Divisions,Nirmal&Adilabad.
Copy to the General Manager,BSNL,Adilabad for information.
Copy submitted to Collector&District Magistrate,Adilabad for favour of information
Copy submitted to Collector&District Magistrate,Nirmal for favour of information

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer,
SuperintendingEngineer(FAC), TDWSP-III,RWS&S,
RWS& S-Circle,Adilabad, Hyderabad.
Adilabad Dist.
Lr.No.06/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /EMW/2018-19, Dt:17.07.2018

Sir,

Sub: RWS&S Circle-Adilabad –SRSP Adilabad Segment-Electromechanical Works-Addagutta


Sump-Pumpsets &Motors-Quality Plan,Genral Arrangment ,Cross sectional
drawings&Performance curves-Submitted-Reg

Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No AEE/01/2017-18,Dated:18.04.2017 of Superintending
Engineer,TDWSP Circle,Nirmal.
3)Lr.No.01/AEE1/ EE / SRSP-ADB /EMW/ADDAGUTTA/2018-19,Dated:13.07.2017 of Executive
Engineer,RWS&S,MB Grid Division,Adilabad.
*****
Vide reference 3rd cited, the Executive Engineer RWS&S, MB Grid Division,Adilabad has submitted the
Quality Plan,General Arrangement,Cross sectional drawings and Performance curves for Pumpsets and Motors at
Addagutta Sumpfor the work “Design, Supply, Erection, Testing and commissioning of Electro mechanical works
with SCADA & Instrumentation along with associated substation and switch gear including all connected
accessories for various Pumping stations located at various places in erstwhile districts Adilabad,Nizamabad and
Karimnagar Including, defects liability period and operation and maintenance for 10 years (Package No.III)” for
obtaining approval.

Hence,I kindly request sir to kindly approve the above at an early date.

Yours faithfully
Encl;As above

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to Engineer-in-Chief,RWS&S,Hyderabad for favour of information.


Copy to Executive Engineer,RWS&S,MB Grid Division,Adilabad for information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Pay and Accounts Officer,
SuperintendingEngineer(FAC), Nirmal District.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Lr.No.07/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Bank Guarantee/2018-19, Dt:18.07.2018

Sir,

Sub: RWS&S Circle-Adilabad –SRSP Adilabad Segment- Extension of Validity of Bank Guarantee-
Submitted-Reg.

Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No 04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP
,Nirmal.
3) Lr.No.AEE1/TDWSP Nirmal Circle/SRSP-Adilabad Seg(Phase-II)/BG-Retention,
Dated :07.12.2016 of Superintending Engineer,TDWSP Circle,Nirmal.
4) Lr.No. AEE1/Extension BG(FSD)/MB Grid/2018,Dated:22.06.2018 of Executive
Engineer,RWS&S,MB Grid Division Nirmal.
5) CN/1110/LOANS/BG/2018-19,Dated:05.07.2018 of Oriental Bank of Commerce
.
*****
It is to submit that Vide reference 3rdcited a bank guarantee bearing No.11100029216, Dated:30.11.2016
issued on behalf of M/s.Megha Engineering and Infrastructure Limited,Hyderabad for the work “Adilabad
District-TDWSP-Providing Drinking Water to Habitations in SRSP-Adilabad Segment in Adilabad District” by
Oriental Bank commercefor an amount of Rs.8,00,00,00/- was submitted and the same was expired on
Dt:28.05.2018.
Whereas Vide reference 4th cited Executive Engineer,RWS&S,MB Grid Division,Nirmal has
submitted the Extension letter of above Bank Guarantee issued by bank upto 28.05.2019 and the Genuniess of
same was confirmed by the bank vide reference 5th cited.
Hence,I am herewith submitting the Extension letter of above Bank guarantee along with
Genuiness confirmation letter for taking further necessary action.

Yours faithfully
Encl;As above

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

.
Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of information.
Copy submitted to the Chief Engineer-III,RWS&S,Hyderabad for favour of information.
Copy to Executive Engineer,RWS&S,MB Grid Division,Adilabad for information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Pay and Accounts Officer,
SuperintendingEngineer(FAC), Nirmal District.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Lr.No.08/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Bank Guarantee/2018-19, Dt:18.07.2018

Sir,

Sub: RWS&S Circle-Adilabad –SRSP Adilabad Segment- Extension of Validity of Bank Guarantee-
Submitted-Reg.

Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No 04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP
,Nirmal.
3) Lr.No.AEE1/TDWSP Nirmal Circle/SRSP-Adilabad Segment/BG-Retention,
Dated :07.12.2016 of Superintending Engineer,TDWSP Circle,Nirmal.
4) Lr.No. AEE1/Extension BG(FSD)/MB Grid/2018,Dated:22.06.2018 of Executive
Engineer,RWS&S,MB Grid Division Nirmal.
5) CN/1110/LOANS/BG/2018-19,Dated:05.07.2018 of Oriental Bank of Commerce
.
*****
It is to submit that Vide reference 3rd cited a bank guarantee bearing No.11100029316,
Dated:30.11.2016 issued on behalf of M/s.Megha Engineering and Infrastructure Limited,Hyderabad for the
work “RWS&S Circle,Adilabad-TDWSP-Construction of Intakewell,WTP and Raw Water Pumping Main in
Adilabad Segment,Kaddam Segment,Asifabad Segment and Mancherial Segment of Telangana Drinking Water
Supply Project(TDWSP)” by Oriental Bank commerce for an amount of Rs.8,00,00,00/- was submitted and the
same was expired on Dt:28.05.2018.
Whereas Vide reference 4th cited Executive Engineer,RWS&S,MB Grid Division,Nirmal has
submitted the Extension letter of above Bank Guarantee issued by bank upto 28.05.2019 and the Genuniess of
same was confirmed by the bank vide reference 5th cited.
Hence,I am herewith submitting the Extension letter of above Bank guarantee along with
Genuiness confirmation letter for taking further necessary action.

Yours faithfully
Encl;As above
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of information.
Copy submitted to the Chief Engineer-III,RWS&S,Hyderabad for favour of information.
Copy to Executive Engineer,RWS&S,MB Grid Division,Adilabad for information.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Pay and Accounts Officer,
SuperintendingEngineer(FAC), Nirmal District.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Lr.No.09/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Bank Guarantee/2018-19, Dt:23.07.2018

Sir,

Sub: RWS&S Circle-Adilabad –SRSP Adilabad Segment- Extension of Validity of Bank Guarantee-
Submitted-Reg.

Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No 04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP
,Nirmal.
3) Lr.No.01/AEE3/SE/RWSS(Adilabad)/BG/SRSP-ADB/,Dated:02.01.2018 of Superintending
Engineer,RWS&S Circle,Adilabad.
Dated :07.12.2016 of Superintending Engineer,TDWSP Circle,Nirmal.
4) Lr.No. AEE1/Extension BG(FSD)/MB Grid/2018,Dated:22.06.2018 of Executive
Engineer,RWS&S,MB Grid Division Nirmal.
5) Ref No.TZO:CR:BGC:2018-19:93,Dated:21.07.2018 of Bank of India.
.
*****
It is to submit that Vide reference 3rd cited a bank guarantee bearing No.5625IPEBG170124,
Dated:27.12.2017 issued on behalf of M/s.Megha Engineering and Infrastructure Limited,Hyderabad for the
work “Adilabad District-TDWSP-Providing Drinking Water to Habitations in SRSP-Adilabad Segment in Adilabad
District” by Bank of India for an amount of Rs.25,50,00,00/- was submitted and the same was expired on
Dt:26.06.2018.
Whereas Vide reference 4th cited Executive Engineer,RWS&S,MB Grid Division,Nirmal has
submitted the Extension letter of above Bank Guarantee issued by bank upto 26.06.2019 and the Genuniess of
same was confirmed by the bank vide reference 5th cited.
Hence,I am herewith submitting the Extension letter of above Bank guarantee along with
Genuiness confirmation letter for taking further necessary action.

Yours faithfully
Encl;As above

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of information.
Copy submitted to the Chief Engineer-III,RWS&S,Hyderabad for favour of information.
Copy to Executive Engineer,RWS&S,MB Grid Division,Adilabad for information.

Endt.No.01/AEE3/ SE / RWSS(Adilabad) /Communication/2018-19, Dt:18.07.2018

Ref: 1) G.O.Ms.No.67,Dated:04.07.2018 of I&CAD(Reforms) department,Governament of


Telangana.
2) Endt.No.AEE(T)/DEE(T)/General Communication/Technical/2015,dated:17.07.2018 of
Engineer-in-Chief,RWS&S,Hyderabad.
*****
Copy of G.O.Ms.No.67,Dated:04.07.2018 of I&CAD (Reforms) department,Governament of Telangana is
communicated to the Executive Engineers,RWS&S,MB Grid& Intra of Adilabad Circle for information and
necessary action

Yours faithfully

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
To,
All the Executive Engineers,RWS&S,MB Grid &Intra of Adilabad circle for necessary action
Copy submitted to Chief Engineer-III,TDWSP,Hyderabad for favour of information
Copy submitted to Engineer-in-Chief,Hyderabad for favour of information

GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

Memo No.02/AEE3/DEE-II/MB Portal/Daily water Supply/2018,Dated:25.07.2018

Sub:RWS&S Circle-Adilabad-MB Portal -Updation –Daily water supply-Instructions-Issued-Reg.

The immediate personal attention of the Executive Engineers,RWS&S,MB Grid & Intra
Divisions of Adilabad circle noted in the address entry is invited to subject cited wherein a new form was
deployed &Instructions were issued to update the status of daily water supply to those habitations for which
bulk supply was already made on regular basis resembling the actual status.

Wherein it was observed by undersigned that updation is not done regularaly even after
several instructions.

Hence all the Executive Engineers,RWS&S,MB Grid&Intra of Adilabad circle are hereby
requested to issue necessary instructions to the field engineers to update the above form on daily basis as the
daily reports will be shared to the CMO dashboard for regular review.
Further it is to inform that if any deviations from the above will be viewed seriously and
necessary action will be initated against the defaulters.

Superintending Engineer(FAC)
RWS&S Circle-Adilabad

To,
The Executive Engineers,RWS&S,MB Intra Divisions,Nirmal&Adilabad.
The Executive Engineers,RWS&S,MB Grid Divisions,Nirmal&Adilabad.
Copy Submitted to the Chief Engineer-III,TDWSP,Hyderabad for favour of information
Copy submitted to the Engineer-in-Chief ,RWS&S,Hyderabad for favour of information

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad
RWS& S-Circle,Adilabad,
Adilabad Dist.

Lr.No.10/I/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /EM WORK/EOAT/2018-19, Dt:29.07.2018

Sir,

Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-Design, Supply, Erection, Testing and


commissioning of Electro mechanical works with SCADA & Instrumentation along
with associated substation and switch gear including all connected accessories for various
Pumping stations located at various places in erstwhile districts Adilabad, Nizamabad and
Karimnagar. Including, defects liability period and operation and maintenance for 10 years
Package-III –Extension of Agreement Time (EOAT) Proposals-Submitted – Reg.

Ref: :1)GO.RT.NO:82 of PR&RD (RWS IV) Dept.,Dt.07.02.2015


2)GO.RT.NO:336 of PR&RD (RWS IV) Dept.,Dt.01.06.2015
3)GO.RT.NO:394&392 of PR&RD (RWS IV) Dept.,Dt.23.06.2015
4)Agreement No. AEE/01/2017-18,Dated:18.04.2017.of the Superintending
Engineer,TDWSP Circle,Nirmal.
5)Proc.No.AEE1/DEEII/EOAT/Electromechanical Works/2018,Dated:16.01.2018 of
Superintending Engineer,RWS&S Circle,Mancherial.
6)Procs.No.AEE/DEE/TDWSP/Electro Mechanical/EOAT/Package-III/2017-18,
Dated:30.04.2018 of Chief Engineer-III,TDWSP,Hyderabad.
7)Lr.No.RC/RWS&S/PKG-3/EMW/SE/EOAT/2018-19/18,Dated:26.07.2018 of
M/s.Raghava Constructions.
8) Lr.No.03/AEE/MB Grid Adilabad/SRSP ADB/EM Works/EOAT/2018,
Dated: 28.07.2018 of Executive Engineer,RWS&S,MB Grid Division,Nirmal.
*****
It is to submit that videreferences 1st, 2nd & 3rd cited, the Government has accorded administrative
sanction for the work “Design, Supply, Erection, Testing and commissioning of Electro mechanical works
with SCADA & Instrumentation along with associated substation and switch gear including all connected
accessories for various Pumping stations located at various places in erstwhile districts Adilabad,
Nizamabad and Karimnagar. Including, defects liability period and operation and maintenance for 10
years Package-III”. Further through the reference 4th cited agreement was concluded with M/s Raghava
Constructions Khammam for the same.

Wherein the EOAT-I & EOAT-II which were accorded vide References 5th& 6th cited for the above
work are expired on 31st July 2018.Accordingly vide reference 7th cited M/s.Raghava Constructions submitted
the proposals for EOAT with for Electromechanical works of SRSP-Adilabad segment and requested for further
EOAT upto 30th November 2018.

And also the Executive Engineers MB Grid,Division, Nirmal has submitted the EOAT Proposals duly
recommending EOAT upto 30th November 2018 without imposing any penalty based on the reasons explained
by the agency, and further enclosed item wise details such as Check slip.

Hence I request the Chief Engineer-IV,TDWSP,Hyderabad to take further necessary action regarding
issuing of EOAT up to 30thNovember without imposing Penality.

Encl: EOAT Check slip, Revised Action plan.

Yours faithfully,

Encl;As above
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information..


Copy to Executive Engineer,RWS&S,MB Grid Division,Nirmal for information.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Chief Engineer-I,
SuperintendingEngineer(FAC), TDWSP,Hyderabad
RWS& S-Circle,Adilabad,
Adilabad Dist.

Lr.No.10/II/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /EM WORK/EOAT/2018-19, Dt:29.07.2018

Sir,

Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-Design, Supply, Erection, Testing and


Commissioning of Electro mechanical works with SCADA & Instrumentation along
with associated substation and switch gear including all connected accessories for various
Pumping stations located at various places in erstwhile districts Adilabad, Nizamabad and
Karimnagar. Including, defects liability period and operation and maintenance for 10 years
Package-III –Extension of Agreement Time (EOAT) Proposals-Submitted – Reg.

Ref: : 1) GO.RT.NO:82 of PR&RD (RWS IV) Dept.,Dt.07.02.2015


2) GO.RT.NO:336 of PR&RD (RWS IV) Dept.,Dt.01.06.2015
3) GO.RT.NO:394&392 of PR&RD (RWS IV) Dept.,Dt.23.06.2015
4) Agreement No. AEE/01/2017-18,Dated:18.04.2017.of the Superintending
Engineer,TDWSP Circle,Nirmal.
5) Proc.No.AEE1/DEEII/EOAT/Electromechanical Works/2018,Dated:16.01.2018 of
Superintending Engineer,RWS&S Circle,Mancherial.
6) Procs.No.AEE/DEE/TDWSP/Electro Mechanical/EOAT/Package-III/2017-18,
Dated:30.04.2018 of Chief Engineer-III,TDWSP,Hyderabad.
7) Lr.No.RC/RWS&S/PKG-3/EMW/SE/EOAT/2018-19/18,Dated:26.07.2018 of
M/s.Raghava Constructions.
8) Lr.No.01/AEE/MB Grid Adilabad/SRSP ADB/EM Works/EOAT/2018,
Dated: 28.07.2018 of Executive Engineer,RWS&S,MB Grid Division,Adilabad.
*****

It is to submit that videreferences 1st, 2nd & 3rd cited, the Government has accorded administrative
sanction for the work “Design, Supply, Erection, Testing and commissioning of Electro mechanical works
with SCADA & Instrumentation along with associated substation and switch gear including all connected
accessories for various Pumping stations located at various places in erstwhile districts Adilabad,
Nizamabad and Karimnagar. Including, defects liability period and operation and maintenance for 10
years Package-III”. Further through the reference 4th cited agreement was concluded with M/s Raghava
Constructions Khammam for the same.

Wherein the EOAT-I & EOAT-II which were accorded vide References 5th& 6th cited for the above
work are expired on 31st July 2018.Accordingly vide reference 7th cited M/s.Raghava Constructions submitted
the proposals for EOAT with for Electromechanical works of SRSP-Adilabad segment and requested for further
EOAT upto 30th November 2018.

And also the Executive Engineers MB Grid,Division, Adilabad has submitted the EOAT Proposals duly
recommending EOAT upto 30th November 2018 without imposing any penalty based on the reasons explained
by the agency, and further enclosed item wise details such as Check slip.

Hence I request the Chief Engineer-I,TDWSP,Hyderabad to take further necessary action regarding
issuing of EOAT up to 30thNovember without imposing Penality.
Encl: EOAT Check slip, Revised Action plan.

Yours faithfully,

Encl;As above
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information..


Copy to Executive Engineer,RWS&S,MB Grid Division,Adilabad for information.
Reminder-1
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

Memo No.03/AEE3/DEE-II/BSNL /Cable Damages/2018,Dated:07.09.2018

Sub:RWS&S Circle-Adilabad-BSNL-Damages to underground cables-Recovery dues–Certain Remarks.

Ref:1. Lr.No.GMTD/ADB/Plg/Way Leave Permissions/2010-19/Vol.I/67,Dated:02.07.2018 of the


General Manager,BSNL,Adilabad.
2.Memo No.01/AEE3/DEE-II/BSNL/Cable Damages/2018,Dated:12.07.2018 of Superintending
Engineer,RWS&S Circle,Adilabad.

****
Vide reference 2nd cited, all the Executive Engineers under this circle were requested to furnish
the detailed report on the damages done to BSNL underground cables due to Mission Bhagiratha works for
taking further necessary action.But the informations is still awaited by this office as on 07.09.2018.

In view of the above all the Executive Engineers under this cirlce are hereby directed to
furnish the above information immediately without further delay.

Superintending Engineer(FAC)
RWS&S Circle-Adilabad

To,
The Executive Engineers,RWS&S,MB Intra Divisions,Nirmal&Adilabad.
The Executive Engineers,RWS&S,MB Grid Divisions,Nirmal&Adilabad.
Copy Submitted to the Chief Engineer-I,RWS&S ,Hyderabad for favour of information
Copy Submitted to the Chief Engineer-VII,RWS&S ,Hyderabad for favour of information
Copy submitted to the Engineer-in-Chief ,RWS&S,Hyderabad for favour of information

MOST URGENT
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

Memo No.04/AEE3/DEE-II/Nirmal&Laxmanchanda/Grid/2018,Dated:18.09.2018

Sub:RWS&S Circle-Adilabad-Bulk water to Nirmal &Laxmanchanda Mandals from Madegaon WTP-


Detailed Report-Called for-Reg.
Ref:1.Memo.No.AEE-4/DEE-II/TDWSP-IV/Adilabad/2/2018-19,Dated:12.09.2018 of Chief
. Engineer-IV,TDWSP,Hyderabad.
****
The Immediate Personal attention of the Executive Engineer,MB Grid Division,Nirmal is invited to the
reference cited,where in it was informed that Hon’ble Minister for Housing,Law&Endowments desires to supply
bulk water for Nirmal,Laxmanchanda Mandals from Madegaon WTP in addition to Gandhinagar WTP and
instructed to submit the detailed report.

In view of the above Executive Engineer, MB Grid Division,Nirmal is hereby requested to submit the
detailed report on Physical and Financial Feasibility of above proposal under SRSP Adilabad Segment in
coordination with Executive Engineer,MB Intra Division,Nirmal.

Superintending Engineer(FAC)
RWS&S Circle-Adilabad

To,
The Executive Engineers,RWS&S,MB Grid Division,Nirmal.
Copy Submitted to the Chief Engineer-IV,RWS&S ,Hyderabad for favour of information
Copy submitted to the Engineer-in-Chief ,RWS&S,Hyderabad for favour of information

MOST URGENT
BySpeed Post
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

Memo No.05/AEE3/DEE-II/ADB/Habs Finalization/2018,Dated:22.09.2018

Sub:RWS&S Circle-Adilabad-List of Depopulated,Subm,erged&New Habs-Detailed Report-


Called for-Reg.

****
All the Executive Engineers&Dy.Executive Engineers,MB Grid&Intra of Adilabad District are hereby
requested to submit the authenticated copies of list of depopulated, deserted or Submerged habs along with
the list of newly formed habs in their respective jurisdiction immediately to this office for finalizing the
habitation count in Adilabad District.

Sd/-
Superintending Engineer(FAC)
RWS&S Circle-Adilabad
To,
The Executive Engineer,RWS&S,MB Grid/Intra Division,Adilabad.
The Dy.Executive Engineer,MB Grid Sub Division Adilabad/Ichoda.
The Dy.Executive Engineer,MB Intra Sub Division Adilabad/Boath/Utnoor.
Copy Submitted to
Chief Engineer-I,RWS&S,Hyderabad for favour of kind information

//t.c.f.b.o//

Dy.EE PA to SE
RWS&S Circle-Adilabad

LIST OF DEPOPULATED &SUBMERGED HABS-IN………………MANDAL

S.No District Mandal Panchayath Habitation Population Deserted/Submerged


Name

Assistant Executive Engineer-MB Intra Assistant Executive Engineer-MB Grid

Dy.Executive Engineer-MB Intra Dy.Executive Engineer-MB Grid

Executive Engineer-MB Intra Executive Engineer-MB Grid


LIST OF NEW HABS-IN………………MANDAL

S.No District Mandal Panchayath Habitation Population Remarks


Name

Assistant Executive Engineer-MB Intra Assistant Executive Engineer-MB Grid

Dy.Executive Engineer-MB Intra Dy.Executive Engineer-MB Grid

Executive Engineer-MB Intra Executive Engineer-MB Grid

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad
RWS& S-Circle,Adilabad,
Adilabad Dist.

Lr.No.11/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB/Phase-I/EOAT/2018-19, Dt:27.09.2018

Sir,

Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-Construction of Intakewell,WTP and


Raw water pumping main in Adilabad segment,Kadam segment,Asifabad Segment and
Mancherial segment of Telangana Drinking Water Supply (TDWSP), Est.Cost Rs.440.50
Crs–Extension of Agreement Time (EOAT) Proposals-Submitted – Reg.

Ref: : 1) GO.RT.NO:82 of PR&RD (RWS IV) Dept.,Dt.07.02.2015.


2)Agreement No:01/2015-16,Dated:09.04.2015 of SE,RWS&S ,Adilabad
3) Proc.No.AEE1/TDWSP-Nirmal/EOAT/2016,Dated:05.10.2016 of the Superintending
Engineer,TDWSP Circle,Nirmal.
4) Proc.No.AEE/DEE/TDWSP/Nirmal Circle/EOAT/Phase-I/2017,Dated:12.06.2017 of
the Chief Engineer-III,TDWSP,Hyderabad
5) Procs.No.AEE/DEE/TDWSP/Erst Adilabad/EOAT/Phase-I/2017,Dated:20.03.2018
of Chief Engineer-III,TDWSP,Hyderabad.
6) Lr.No.35/MEIL/TDWSP/SRSP-Adilabad/Phase-I/2018-19,Dated:16.07.2018 of
M/s.MEIL,Hyderabad.
7)Lr.No.MB GRID NIRMAL/SRSP Adilabad/Phase-I/EOAT/2018,Dated:26.09.2018 of
Executive Engineer,MB Grid Division,Nirmal.
*****
It is to submit that videreference 1st cited, Government has accorded administrative sanction for the
work “Construction of Intakewell,WTP and RAW water pumping main in Adilabad segment,Kadam
segment,Asifabad Segment and Mancherial segment of Telangana Drinking Water Supply (TDWSP)”,
Est.Cost Rs.440.50 Crs. Further through the reference 2nd cited an agreement was concluded with M/s Megha
Engineering &Infrastructure Limited,Hyderabad for the same.

Wherein EOAT-I , EOAT-II&EOAT-III which were accorded vide References 3rd,4th&5th cited for
the above work were expired on 30th April 2018.Accordingly vide reference 6th cited M/s.MEIL,Hyderabad
submitted the proposals for EOAT and requested for further EOAT upto 31st December 2018.

And also the Executive Engineer MB Grid,Division, Nirmal has submitted the EOAT Proposals duly
recommending EOAT upto 31st December2018 without imposing any penalty based on the reasons explained
by the agency, and further enclosed Check slip.

Contd…..Page No.2

:::2:::

Hence,I am herewith submitting the Extension of Agreement Time(EOAT) proposals for the above said
work under SRSP-Adilabad Segment for your kind perusal and further necessary action.

Encl: EOAT Check slip.

Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.
Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.
Copy to Executive Engineer,MB Grid Division,Nirmal for information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad
RWS& S-Circle,Adilabad,
Adilabad Dist.

Lr.No.12/AEE3/ SE / RWSS(Adilabad)/ SRSP-ADB/NIRMAL/BSNL CABLE DAMAGES, Dt:.10.2018

Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-Nirmal District-Damages to BSNL
underground cables-Demand Notes -Submitted– Reg.

Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No 04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP
Circle,Nirmal.
3) Lr.No.GMTD/ADB/Plg/Way Leave Permissions/2010-19/Vol.I/67,Dated:02.07.2018 of
the General Manager,BSNL,Adilabad
4) T/o.Memo No.01/AEE3/DEE-II/BSNL/Cable Damages/2018,Dated:12.07.2018
5) Lr.No. MB GRID NIRMAL/SRSP Adilabad/BSNL/Demand Note/2018,Dated:26.09.2018
Of Executive Engineer,MB Grid Division,Nirmal.
*****
It is to submit that vide reference 3rd cited General Manager,BSNL,Adilabad has informed that at certain
locations BSNL underground cables(Both Copper&OFC) were damaged due to Mission Bhagiratha works and
accordingly demand notes were raised and payment for the same is pending.
Wherein vide reference 4th cited Executive Engineer,MB Grid Division,Nirmal was requested to go
through points raised by BSNL on the above damages and submit a detailed report for taking further necessary
action.
Accordingly vide reference 5th cited Excecutive Engineer,MB Grid Division informed that joint
inspection was conducted with BSNL officials and submitted the demand notes for the same.
In this regard I am herewith submitting the demand notes for an amount of Rs.22,73,665/- against the
damages done to underground BSNL Cables for kind perusal and further necessary action.

Encl:Demand Notes(2 Nos)

Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.


Copy to Executive Engineer,MB Grid Division,Nirmal for information.

Reminder-II
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

Memo No.05/AEE3/DEE-II/BSNL /Cable Damages/2018,Dated:08.10.2018

Sub:RWS&S Circle-Adilabad-BSNL-Damages to underground cables-Recovery dues-Detailed Report-


Req-Reg.

Ref:1. Lr.No.GMTD/ADB/Plg/Way Leave Permissions/2010-19/Vol.I/67,Dated:02.07.2018 of the


General Manager,BSNL,Adilabad.
2.T/o Memo No.01/AEE3/DEE-II/BSNL/Cable Damages/2018,Dated:12.07.2018
3.T/o Memo No.03/AEE3/DEE-II/BSNL /Cable Damages/2018,Dated:07.09.2018

The immediate personal attention of the Executive Engineer,MB Grid Division,Adilabad is


invited to the subject and references cited,where in it was requested to furnish the detailed report on damages
done to BSNL underground cables(both Copper&OFC).But no information is received by this office even after a
lapse 3 months.

Therefore,the Executive Engineer,RWS&S,MB Grid Division,Adilabad is once again requested


to furnish the detailed report on damages to BSNL underground cables(Both Copper&OFC) to this office
immediately for taking further necessary action.

Superintending Engineer(FAC)
RWS&S Circle-Adilabad

To,
The Executive Engineer, MB Grid Division,Adilabad.
Copy Submitted to the Chief Engineer-I,RWS&S ,Hyderabad for favour of information
Copy submitted to the Engineer-in-Chief ,RWS&S,Hyderabad for favour of information
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The District Forest Officer,
SuperintendingEngineer(FAC), Nirmal District.
RWS& S-Circle,Adilabad,
Adilabad Dist.

Lr.No.13/AEE3/ SE / RWSS(Adilabad)/ SRSP-ADB/FOREST/COMPLIANCE REPORT, Dt:23.10.2018

Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-FCA –Proposals for diversion of 4.945 Ha
of forest land in Kawal Tiger Reserve,Nirmal Division-for laying pipeline and construction of
structures in Segment-21/7(Madegaon) for providing safe drinking water to erstwhile Adilabad
District presently Nirmal District under Telangana Drinking Water Supply Project(TDWSP)-In-
Principle(Stage-I) approval accorded-Compliance report on conditions stipulated in Stage-I-
Submitted-Stage-II Clearance-Requested-Regarding.

Ref: 1) GO.Rt.No.104,of EFS&T(For.I) Dept,Dt.09.06.2017.


2) Rc.No.2003/2016/S1,Dated.10.09.2018 of Forest Divisional Officer,Nirmal

*****
It is to submit that,vide reference 1st cited above the Government of Telangana, has accorded In-
Principle(Stage-I) approval for the diversion of 4.945 Ha of forest land in Kawal Tiger Reserve ,Nirmal
Division ,for laying of pipeline and construction of structures in Segment-21/7(Madegaon) for providing safe
drinking water to erstwhile Adilabad District presently Nirmal District under Telangana Drinking Water Supply
Project(TDWSP) in favour of Superintending Engineer,TDWSP(RWS&S) Circle,Nirmal stating thatgranting of
final approval will be considered on submission of compliance report on condtionals stipulated in In-
Princple(Stage-I) approval andaccordingly vide reference 2nd cited above Forest Divisional Officer,Nirmal
requested this office to submit the same for taking further necessary action.

In view of the above I am herewith submitting the Compliance report for conditions stipulated in In-
Principle(Stage-I) approval for diversion of 4.945 Ha forest land in Kawal Tiger Reserve,Nirmal Division for
taking further necessary action for granting Stage-II(Final) approval.

Encl:Compliance Report(6 Sets)

Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.


Copy to Executive Engineer,MB Grid Division,Nirmal for information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The District Forest Officer,
SuperintendingEngineer(FAC), Adilabad District.
RWS& S-Circle,Adilabad,
Adilabad Dist.

Lr.No.14/AEE3/ SE / RWSS(Adilabad)/ SRSP-ADB/FOREST/COMPLIANCE REPORT, Dt:27.10.2018

Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-FCA –Proposals for diversion of 4.945 Ha
of forest land in Kawal Tiger Reserve,Nirmal Division-for laying pipeline and construction of
structures in Segment-21/7(Madegaon) for providing safe drinking water to erstwhile Adilabad
District presently Nirmal District under Telangana Drinking Water Supply Project(TDWSP)-In-
Principle(Stage-I) approval accorded-Compliance report on conditions stipulated in Stage-I-
Submitted-Stage-II Clearance-Requested-Regarding.

Ref: 1) GO.Rt.No.104,of EFS&T(For.I) Dept,Dt.09.06.2017.


2) Rc.No.2003/2016/S1,Dated.10.09.2018 of Forest Divisional Officer,Nirmal

*****
It is to submit that,vide reference 1st cited above the Government of Telangana, has accorded In-
Principle(Stage-I) approval for the diversion of 4.945 Ha of forest land in Kawal Tiger Reserve ,Nirmal
Division ,for laying of pipeline and construction of structures in Segment-21/7(Madegaon) for providing safe
drinking water to erstwhile Adilabad District presently Nirmal District under Telangana Drinking Water Supply
Project(TDWSP) in favour of Superintending Engineer,TDWSP(RWS&S) Circle,Nirmal stating thatgranting of
final approval will be considered on submission of compliance report on condtionals stipulated in In-
Princple(Stage-I) approval andaccordingly vide reference 2nd cited above Forest Divisional Officer,Nirmal
requested this office to submit the same for taking further necessary action.

In view of the above I am herewith submitting the Compliance report for conditions stipulated in In-
Principle(Stage-I) approval for diversion of 4.945 Ha forest land in Kawal Tiger Reserve,Nirmal Division for
taking further necessary action for granting Stage-II(Final) approval.

Encl:Compliance Report(6 Sets)

Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.


Copy to Executive Engineer,MB Grid Division,Nirmal for information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's),. The Manager,
SuperintendingEngineer(FAC), Andhra Bank,
RWS& S-Circle,Adilabad, Balanagar Branch,
Adilabad Dist. Hyderabad,Telangana-5000037

Lr.No.15/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /BG/2018-19 Dt:31.10.2018

GentleMen,
Sub:- RWS&S Circle-Adilabad –SRSP Adilabad Segment-Extension of Validity of Bank
Guarantee-Confirmation of genuineness-Requested-Reg.

Ref: 1)Original Agreement.No AEE/01/2015-16,Dated:09.04.2015 of Superintending


Engineer,RWS&S Circle,Adilabad.
2) Lr.No.AEE1/Extension BG(FSD)/MB Grid/2018,Dated:27.10.2018 of Executive Engineer,
MB Grid Division,Nirmal.

*****

A copy of Extension of Bank Guarantee for Rs.7,37,21,590/- vide B.G.No.005715IGPER0081,


Dated: 08.10.2018 of Andhra Bank, Balanagar Branch,Hyderabad extended from 09.10.2018 to 08.10.2013
issued to M/s. Megha Engineering & Infrastructures Ltd., Hyderabadfor the work “Construction of Intake
Well,WTP and Raw Water Pumping Main in Adilabad Segment,Kaddam Segment,Asifabad Segment
and Mancherial Segment of Telangana Drinking Water Supply Project(TDWSP)with an estimated
cost of Rs.440.50 Crs is here with communicated with a request to confirm the genuineness of the BGs
extension at the earliest.

Yours faithfully,

Encl: BGs Extension Letter


Superintending Engineer(FAC),
RWS&S Circle, Adilabad

Copy to Executive Engineer,MB Grid Division,Nirmal for information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's),. The Manager,
SuperintendingEngineer(FAC), Andhra Bank,
RWS& S-Circle,Adilabad, Balanagar Branch,
Adilabad Dist. Hyderabad,Telangana-5000037

Lr.No.16/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /BG/2018-19 Dt:31.10.2018

GentleMen,

Sub:- RWS&S Circle-Adilabad –SRSP Adilabad Segment-Extension of Validity of Bank


Guarantee-Confirmation of genuineness-Requested-Reg.

Ref: 1)Original Agreement.No AEE/01/2015-16,Dated:09.04.2015 of Superintending


Engineer,RWS&S Circle,Adilabad.
2) Lr.No.AEE1/Extension BG(FSD)/MB Grid/2018,Dated:27.10.2018 of Executive Engineer,
MB Grid Division,Nirmal.

*****
A copy of Extension of Bank Guarantee for Rs.73,72,159/- vide B.G.No.005715IGPER0082, Dated:
08.10.2018 of Andhra Bank, Balanagar Branch,Hyderabad extended from 09.10.2018 to 08.10.2013 issued
to M/s. Megha Engineering & Infrastructures Ltd., Hyderabadfor the work “Construction of Intake
Well,WTP and Raw Water Pumping Main in Adilabad Segment,Kaddam Segment,Asifabad Segment
and Mancherial Segment of Telangana Drinking Water Supply Project(TDWSP) with an estimated
cost of Rs.440.50 Crs is here with communicated with a request to confirm the genuineness of the BGs
extension at the earliest.

Yours faithfully,

Encl: BGs Extension Letter


Superintending Engineer(FAC),
RWS&S Circle, Adilabad

Copy to Executive Engineer,MB Grid Division,Nirmal for information.


GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Pay and Accounts Officer,
SuperintendingEngineer(FAC), Nirmal District.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Lr.No.17/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Bank Guarantee/2018-19, Dt:15.11.2018

Sir,

Sub: RWS&S Circle-Adilabad –SRSP Adilabad Segment- Extension of Validity of Bank Guarantee-
Submitted-Reg.

Ref: 1) G.O.Rt.No.82, Dt.07 .02. 20 15 of PR&RD(RWS) Department


2) Original Agreement No.AEE1/ 01/2015-16,of Superintending Engineer, RWSS, Adilabad
Circle . Dt: 09.04.2015.
3)Lr.No.AEE1/Extension BG(FSD)/MB Grid/2018,Dated:27.10.2018 of Executive Engineer,
MB Grid Division,Nirmal.
4)Lr.No.0057/18/,Dated:12.11.2018 of Andhra Bank
.
*****
It is to submit that a bank guarantee bearing No.005715IGPER0082, Dated:09.04.2015 issued on
behalf of M/s.Megha Engineering and Infrastructure Limited,Hyderabad for the work “ Construction of Intake
Well,WTP and Raw Water Pumping Main in Adilabad Segment,Kaddam Se ment,Asifabad Segment
and Mancherial Segment of Telangana Drinking Water Supply Project(TDWSP) with an estimated
cost of Rs.440.50 Crs” by Andhra Bank for an amount of Rs.73,72,159/- was submitted and the same was
expired on Dt:08.10.2018.
Whereas Vide reference 3rd cited Executive Engineer,RWS&S,MB Grid Division,Nirmal has
submitted the Extension letter of above Bank Guarantee issued by bank upto 08.10.2023 and the Genuniess of
same was confirmed by the bank vide reference 4th cited.
Hence,I am herewith submitting the Extension letter of above Bank guarantee along with
Genuiness confirmation letter for taking further necessary action.
Yours faithfully
Encl;As above
Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

.
Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.
Copy submitted to the Chief Engineer-IV,RWS&S,Hyderabad for favour of kind information.
Copy to Executive Engineer,RWS&S,MB Grid Division,Nirmal for information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Pay and Accounts Officer,
SuperintendingEngineer(FAC), Nirmal District.
RWS& S-Circle,Adilabad,
Adilabad Dist.
Lr.No.18/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Bank Guarantee/2018-19, Dt:15.11.2018

Sir,

Sub: RWS&S Circle-Adilabad –SRSP Adilabad Segment- Extension of Validity of Bank Guarantee-
Submitted-Reg.

Ref: 1) G.O.Rt.No.82, Dt.07 .02. 20 15 of PR&RD(RWS) Department


2) Original Agreement No.AEE1/ 01/2015-16,of Superintending Engineer, RWSS, Adilabad
Circle . Dt: 09.04.2015.
3) Lr.No.AEE1/Extension BG(FSD)/MB Grid/2018,Dated:27.10.2018 of Executive Engineer,
MB Grid Division,Nirmal.
4)Lr.No.0057/18/,Dated:12.11.2018 of Andhra Bank.
*****
It is to submit that a bank guarantee bearing No.005715IGPER0081, Dated:09.04.2015 issued on
behalf of M/s.Megha Engineering and Infrastructure Limited,Hyderabad for the work “ Construction of Intake
Well,WTP and Raw Water Pumping Main in Adilabad Segment,Kaddam Segment,Asifabad Segment
and Mancherial Segment of Telangana Drinking Water Supply Project(TDWSP) with an estimated
cost of Rs.440.50 Crs” by Andhra Bank for an amount of Rs.7,37,21,590/- was submitted and the same was
expired on Dt:08.10.2018.
Whereas Vide reference 3rd cited Executive Engineer,RWS&S,MB Grid Division,Nirmal has
submitted the Extension letter of above Bank Guarantee issued by bank upto 08.10.2023 and the Genuniess of
same was confirmed by the bank vide reference 4th cited.
Hence,I am herewith submitting the Extension letter of above Bank guarantee along with
Genuiness confirmation letter for taking further necessary action.

Yours faithfully
Encl;As above

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

.
Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.
Copy submitted to the Chief Engineer-III,RWS&S,Hyderabad for favour of kind information.
Copy to Executive Engineer,RWS&S,MB Grid Division,Adilabad for information.
Reminder-III
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

Memo No.06/AEE3/DEE-II/BSNL /Cable Damages/2018,Dated:15.11.2018

Sub:RWS&S Circle-Adilabad-BSNL-Damages to underground cables-Recovery dues-Detailed Report-


Req-Reg.

Ref:1. Lr.No.GMTD/ADB/Plg/Way Leave Permissions/2010-19/Vol.I/67,Dated:02.07.2018 of the


General Manager,BSNL,Adilabad.
2.T/o Memo No.01/AEE3/DEE-II/BSNL/Cable Damages/2018,Dated:12.07.2018
3.T/o Memo No.03/AEE3/DEE-II/BSNL /Cable Damages/2018,Dated:07.09.2018
4.T/o Memo No.05/AEE3/DEE-II/BSNL /Cable Damages/2018,Dated:08.10.2018

The immediate personal attention of the Executive Engineer,MB Grid Division,Adilabad is


invited to the subject and references cited,where in it was requested to furnish the detailed report on damages
done to BSNL underground cables(both Copper&OFC).But no information is received by this office even after a
lapse 4 months.

Therefore,the Executive Engineer,RWS&S,MB Grid Division,Adilabad is once again requested


to furnish the detailed report on damages to BSNL underground cables(Both Copper&OFC) to this office
immediately for taking further necessary action.

Superintending Engineer(FAC)
RWS&S Circle-Adilabad

To,
The Executive Engineer, MB Grid Division, Adilabad.
Copy Submitted to the Chief Engineer-I,RWS&S ,Hyderabad for favour of information
Copy submitted to the Engineer-in-Chief ,RWS&S,Hyderabad for favour of information

MOST URGENTGOVERNMENT OF TELANGANA


RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

Memo No.07/AEE3/DEE-II/ADB DISTRICT /Habitation Count/2018,Dated:15.11.2018

Sub:RWS&S Circle-Adilabad-Adilaba District –Habitations List-Remarks Called for the Draft list of
Habitations in Adilabad District-Reg.

Ref:1. Oral Instructions of Collector and District Magistrate Adilabad in the review meeting,
Dated:19.09.2018.

While enclosing the copy of draft list of Habitations in Adilabad District,All the Executive
Engineers and Deputy Executive Engineers of Adilabad District under this circle are hereby requested to verify
the draft list and submit the remarks/observations on the list of habitations mentioned in the draft by 18.11.2018
so as to finalize the habitation count of Adilabad District.

Further it is to inform that any remarks/objections after 18.11.2018 will not be considered.

Superintending Engineer(FAC)
RWS&S Circle-Adilabad

To,
The Executive Engineer, MB Grid Division, Adilabad.
The Executive Engineer, MB Intra Division, Adilabad.
The Deputy Executive Engineer,MB Grid Sub Division Adilabad/Ichoda.
The Deputy Executive Engineer,MB Intra Sub Division Adilabad/Boath/Utnoor.
Copy Submitted to the Chief Engineer-I,RWS&S ,Hyderabad for favour of information
Copy submitted to the Engineer-in-Chief ,RWS&S,Hyderabad for favour of information
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

Memo No.08/AEE3/DEE-II/GRID/PHASE-I/AGREEMENTS/2018,Dated:15.11.2018

Sub:RWS&S Circle-Adilabad-“Construction of Intake Well,WTP and Raw Water Pumping Main in


Adilabad Segment,Kaddam Segment,Asifabad Segment and Mancherial Segment of Telangana
Drinking Water Supply Project(TDWSP) “with an estimated cost of Rs.440.50 Crs-Working
Estimate-IV-Technically approved-Supplementary Agreement-Concluded-Communicated-Reg.

Ref: 1) G.O.Rt.No.82, Dt.07 .02. 20 15 of PR&RD(RWS) Department.


2)T.S.No. 52/2014-15 Engineer-in-Chief, RWSS Hyderabad, Dt. 19.02.2015.
3)Original Agreement No.AEE1/ 01/2015-16,of Superintending Engineer, RWSS, Adilabad
Circle . Dt: 09.04.2015.
4) Supplymentary Agreement No. 01A/2015-16, Dt: 09.03.2016 of Superintending Engineer,
TDWSP, Nirmal Circle.
5) Supplymentary Agreement No. 01B/2015-16, Dt: 04.11.2016 of Superintending Engineer,
TDWSP, Nirmal Circle.
6) Supplymentary Agreement No. 01C/2015-16, Dt: 29.07.2017 of Superintending Engineer,
TDWSP, Nirmal Circle.
7) Memo.No.AEE-IV/DEE-II/TDWSP/GRID-WE-IV/SRSP-ADB(Ph-1)/2018,Dated:01.10.2018 of
Chief Engineer-IV,TDWSP,Hyderabad
8)Supplymentary Agreement No. 01D/2018-19, Dt: 14.11.2018 of Superintending Engineer,
RWS&S Circle,Adilabad.

The immediate Personal attention of Executive Engineer,MB Grid Division,Nirmal is drawn


to the reference 7th cited,wherein Chief Engineer-IV,TDWSP,Hyderabad has approved the working estimate-IV
for the work “Construction of Intake Well,WTP and Raw Water Pumping Main inAdilabad Segment,Kaddam
Segment,Asifabad Segment and Mancherial Segment of Telangana Drinking Water Supply Project(TDWSP)”with
an estimated cost of Rs.440.50 Crs.
Accordingly vide reference 8th cited,Supplementary agreement is concluded and herewith
communicated for taking further necessary action.

Enclosure:Supplementary agreement-4

Superintending Engineer(FAC)
RWS&S Circle-Adilabad

To,
The Executive Engineer, MB Grid Division,Nirmal.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad
RWS& S-Circle,Adilabad,
Adilabad Dist.

Lr.No.19/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /EM WORK/EOAT/2018-19, Dt:17.11.2018


Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-Design, Supply, Erection, Testing and
commissioning of Electro mechanical works with SCADA & Instrumentation along
with associated substation and switch gear including all connected accessories for various
Pumping stations located at various places in erstwhile districts Adilabad, Nizamabad and
Karimnagar. Including, defects liability period and operation and maintenance for 10 years
Package-III –Extension of Agreement Time (EOAT) Proposals-Submitted – Reg.

Ref: :1) GO.RT.NO:82 of PR&RD (RWS IV) Dept.,Dt.07.02.2015


2) GO.RT.NO:336 of PR&RD (RWS IV) Dept.,Dt.01.06.2015
3) GO.RT.NO:394&392 of PR&RD (RWS IV) Dept.,Dt.23.06.2015
4) Agreement No. AEE/01/2017-18,Dated:18.04.2017.of the Superintending
Engineer,TDWSP Circle,Nirmal.
5) Proc.No.AEE1/DEEII/EOAT/Electromechanical Works/2018,Dated:16.01.2018 of
Superintending Engineer,RWS&S Circle,Mancherial.
6) Procs.No.AEE/DEE/TDWSP/Electro Mechanical/EOAT/Package-III/2017-18,
Dated:30.04.2018 of Chief Engineer-III,TDWSP,Hyderabad.
7) Lr.No.RC/RWS&S/PKG-3/EMW/SE/EOAT/2018-19/18,Dated:26.07.2018 of
M/s.Raghava Constructions.
8) Memo No.AEE/DEE-I/TDWSP/NZB/Electro-Mechanical/EOAT-III/16-17,OF Chief
Engineer-IV,TDWSP,Hyderabad.
9) Lr.No.AEE/MB Grid Nirmal/SRSP ADB/EM Works/EOAT/2018,
Dated: 17.11.2018 of Executive Engineer,RWS&S,MB Grid Division,Nirmal.
*****

It is to submit that videreferences 1st, 2nd & 3rd cited, the Government has accorded administrative
sanction for the work “Design, Supply, Erection, Testing and commissioning of Electro mechanical works
with SCADA & Instrumentation along with associated substation and switch gear including all connected
accessories for various Pumping stations located at various places in erstwhile districts Adilabad,
Nizamabad and Karimnagar. Including, defects liability period and operation and maintenance for 10
years Package-III”. Further through the reference 4th cited agreement was concluded with M/s Raghava
Constructions Khammam for the same.

Wherein the EOAT-I & EOAT-II which were accorded vide References 5th& 6th cited for the above
work are expired on 31st July 2018.Accordingly vide reference 7th cited EOAT proposal were submitted but
Vide reference 8th cited it was instructed to resubmit the proposal with certain clarifications

Hence I am herewith resubmitting EOAT proposals with clarifications and request the Chief Engineer-
IV,TDWSP,Hyderabad to take further necessary action regarding issuing of EOAT up to 30thNovember without
imposing Penality.

Encl: EOAT Check slip, Revised Action plan&Clarifications Sheet.

Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information..


Copy to Executive Engineer,RWS&S,MB Grid Division,Nirmal for information.
GOVERNMENT OF TELANGNA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Chief Engineer-I,
SuperintendingEngineer(FAC), TDWSP,Hyderabad
RWS& S-Circle,Adilabad,
Adilabad Dist.
Lr.No.11/1/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /EM WORK/WE-II/2018-19, Dt:03.10.2018

Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-Adilabad District-“Design, Supply, Erection,
Testing and commissioning of Electro mechanical works with SCADA & Instrumentation
along with associated substation and switch gear including all connected accessories for
various Pumping stations located at various places in erstwhile districts Adilabad,
Nizamabad and Karimnagar. Including, defects liability period and operation and
maintenance for 10 years Package-III”–Working Estimate-II -Submitted– Approval-
Requested-Reg.

Ref: :1) Agreement No. AEE/01/2017-18,Dated:18.04.2017.of the Superintending


Engineer,TDWSP Circle,Nirmal
2)Supplementary Agreement No.AEE1/01/2018-19,Dated:15.05.2018 of Superintending
Engineer,RWS&S Circle,Mancherial.
3)Lr.No.1/AEE1/MB Grid/Adilabad/ SRSP-ADB /EM WORK/WE-II/2018-19, Dt:03.10.2018
of Executive Engineer MB Grid Division,Adilabad

*****
It is to submit that vide references 3rdcited, Executive Engineer,MB Grid Division,Adilabad has submitted
the Working Estimate-II for Electro Mechanical Works of SRSP Adilabad Segment in Adilabad District for favour
of kind approval and same is herewith submitted for further necessary action.

Encl:As above.
Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information..

Copy to Executive Engineer,RWS&S,MB Grid Division,Adilabad for information.

By e-mailGOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

Circular Memo No.01/AEE3/DEE-II/ADB DISTRICT /Habitation Count/2018,Dated:19.11.2018

Sub:RWS&S Circle-Adilabad-Adilabad District –Final Habitations List- Communicated-Reg

Ref:1. Oral Instructions of Collector and District Magistrate Adilabad in the review meeting,
Dated:19.09.2018.
2.T/o.Memo No.07/AEE3/DEE-II/ADB DISTRICT /Habitation Count/2018,Dated:15.11.2018
3.Lr.No.2/AEE1/MB Grid/Adilabad/ HAB COUNT /2018-19, Dt:17.11.2018 of Executive
Engineer, MB Grid Division,Adilabad.

With reference to the subject and vide reference 2nd cited above a draft list of habitations inAdilabad
District was communicated and all the Executive Engineers and Deputy Executive Engineers of Adilabad
District under this circle were requested to submit remarks/objections on the same if any by
18.11.2018.Wherein Vide reference 3rd cited above remarks were received only from Executive Engineer,MB
Grid Division,Adilabad office.

Accordinly by considering above remarks,a final list of habitations in Adilabad is prepared


and herewith communicated for taking further necessary action.

Enclosure:Final List of Habitations

Superintending Engineer(FAC)
RWS&S Circle-Adilabad

To,
The Executive Engineer, MB Grid Division, Adilabad.
The Executive Engineer, MB Intra Division, Adilabad.
The Deputy Executive Engineer,MB Grid Sub Division Adilabad/Ichoda.
The Deputy Executive Engineer,MB Intra Sub Division Adilabad/Boath/Utnoor.
Copy Submitted to the Chief Engineer-I,RWS&S ,Hyderabad for favour of information
Copy submitted to the Engineer-in-Chief ,RWS&S,Hyderabad for favour of information
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The District Forest Officer,
SuperintendingEngineer(FAC), Adilabad District.
RWS& S-Circle,Adilabad,
Adilabad Dist.

Lr.No.20/AEE3/ SE / RWSS(Adilabad)/ SRSP-ADB/FOREST/COMPLIANCE REPORT, Dt:29.11.2018

Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-FCA –Proposals for diversion of 4.945 Ha
of forest land in Kawal Tiger Reserve,Nirmal Division-for laying pipeline and construction of
structures in Segment-21/7(Madegaon) for providing safe drinking water to erstwhile Adilabad
District presently Nirmal District under Telangana Drinking Water Supply Project(TDWSP)-In-
Principle(Stage-I) approval accorded-Compliance report on conditions stipulated in Stage-I-
Submitted-Stage-II Clearance-Requested-Regarding.

Ref: 1) GO.Rt.No.104,of EFS&T(For.I) Dept,Dt.09.06.2017.


2) Rc.No.2003/2016/S1,Dated.10.09.2018 of Forest Divisional Officer,Nirmal

*****
It is to submit that,vide reference 1st cited above the Government of Telangana, has accorded In-
Principle(Stage-I) approval for the diversion of 4.945 Ha of forest land in Kawal Tiger Reserve ,Nirmal
Division ,for laying of pipeline and construction of structures in Segment-21/7(Madegaon) for providing safe
drinking water to erstwhile Adilabad District presently Nirmal District under Telangana Drinking Water Supply
Project(TDWSP) in favour of Superintending Engineer,TDWSP(RWS&S) Circle,Nirmal stating thatgranting of
final approval will be considered on submission of compliance report on condtionals stipulated in In-
Princple(Stage-I) approval andaccordingly vide reference 2nd cited above Forest Divisional Officer,Nirmal
requested this office to submit the same for taking further necessary action.

In view of the above I am herewith submitting the Compliance report for conditions stipulated in In-
Principle(Stage-I) approval for diversion of 4.945 Ha forest land in Kawal Tiger Reserve,Nirmal Division for
taking further necessary action for granting Stage-II(Final) approval.

Encl:Compliance Report(6 Sets)

Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.


Copy to Executive Engineer,MB Grid Division,Nirmal for information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The District Forest Officer,
SuperintendingEngineer(FAC), Adilabad District.
RWS& S-Circle,Adilabad,
Adilabad Dist.

Lr.No.21/AEE3/ SE / RWSS(Adilabad)/ SRSP-ADB/FOREST/COMPLIANCE REPORT, Dt:29.11.2018


Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-FCA –Proposals for diversion of 4.945 Ha
of forest land in Kawal Tiger Reserve,Nirmal Division-for laying pipeline and construction of
structures in Segment-21/7(Madegaon) for providing safe drinking water to erstwhile Adilabad
District presently Nirmal District under Telangana Drinking Water Supply Project(TDWSP)-In-
Principle(Stage-I) approval accorded-Compliance report on conditions stipulated in Stage-I-
Submitted-Stage-II Clearance-Requested-Regarding.

Ref: 1) GO.Rt.No.104,of EFS&T(For.I) Dept,Dt.09.06.2017.


2) Rc.No.2003/2016/S1,Dated.10.09.2018 of Forest Divisional Officer,Nirmal

*****
It is to submit that,vide reference 1st cited above the Government of Telangana, has accorded In-
Principle(Stage-I) approval for the diversion of 4.945 Ha of forest land in Kawal Tiger Reserve ,Nirmal
Division ,for laying of pipeline and construction of structures in Segment-21/7(Madegaon) for providing safe
drinking water to erstwhile Adilabad District presently Nirmal District under Telangana Drinking Water Supply
Project(TDWSP) in favour of Superintending Engineer,TDWSP(RWS&S) Circle,Nirmal stating thatgranting of
final approval will be considered on submission of compliance report on condtionals stipulated in In-
Princple(Stage-I) approval andaccordingly vide reference 2nd cited above Forest Divisional Officer,Nirmal
requested this office to submit the same for taking further necessary action.

In view of the above I am herewith submitting the Compliance report for conditions stipulated in In-
Principle(Stage-I) approval for diversion of 4.945 Ha forest land in Kawal Tiger Reserve,Nirmal Division for
taking further necessary action for granting Stage-II(Final) approval.

Encl:Compliance Report(6 Sets)

Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.


Copy to Executive Engineer,MB Grid Division,Nirmal for information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The District Forest Officer,
SuperintendingEngineer(FAC), Adilabad District.
RWS& S-Circle,Adilabad,
Adilabad Dist.

Lr.No.22/AEE3/ SE / RWSS(Adilabad)/ SRSP-ADB/FOREST/COMPLIANCE REPORT, Dt:29.11.2018

Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-FCA –Proposals for diversion of 4.945 Ha
of forest land in Kawal Tiger Reserve,Nirmal Division-for laying pipeline and construction of
structures in Segment-21/7(Madegaon) for providing safe drinking water to erstwhile Adilabad
District presently Nirmal District under Telangana Drinking Water Supply Project(TDWSP)-In-
Principle(Stage-I) approval accorded-Compliance report on conditions stipulated in Stage-I-
Submitted-Stage-II Clearance-Requested-Regarding.

Ref: 1) GO.Rt.No.104,of EFS&T(For.I) Dept,Dt.09.06.2017.


2) Rc.No.2003/2016/S1,Dated.10.09.2018 of Forest Divisional Officer,Nirmal
*****
It is to submit that,vide reference 1st cited above the Government of Telangana, has accorded In-
Principle(Stage-I) approval for the diversion of 4.945 Ha of forest land in Kawal Tiger Reserve ,Nirmal
Division ,for laying of pipeline and construction of structures in Segment-21/7(Madegaon) for providing safe
drinking water to erstwhile Adilabad District presently Nirmal District under Telangana Drinking Water Supply
Project(TDWSP) in favour of Superintending Engineer,TDWSP(RWS&S) Circle,Nirmal stating thatgranting of
final approval will be considered on submission of compliance report on condtionals stipulated in In-
Princple(Stage-I) approval andaccordingly vide reference 2nd cited above Forest Divisional Officer,Nirmal
requested this office to submit the same for taking further necessary action.

In view of the above I am herewith submitting the Compliance report for conditions stipulated in In-
Principle(Stage-I) approval for diversion of 4.945 Ha forest land in Kawal Tiger Reserve,Nirmal Division for
taking further necessary action for granting Stage-II(Final) approval.

Encl:Compliance Report(6 Sets)

Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.


Copy to Executive Engineer,MB Grid Division,Nirmal for information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The District Forest Officer,
SuperintendingEngineer(FAC), Adilabad District.
RWS& S-Circle,Adilabad,
Adilabad Dist.

Lr.No.23/AEE3/ SE / RWSS(Adilabad)/ SRSP-ADB/FOREST/COMPLIANCE REPORT, Dt:29.11.2018

Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-FCA –Proposals for diversion of 4.945 Ha
of forest land in Kawal Tiger Reserve,Nirmal Division-for laying pipeline and construction of
structures in Segment-21/7(Madegaon) for providing safe drinking water to erstwhile Adilabad
District presently Nirmal District under Telangana Drinking Water Supply Project(TDWSP)-In-
Principle(Stage-I) approval accorded-Compliance report on conditions stipulated in Stage-I-
Submitted-Stage-II Clearance-Requested-Regarding.

Ref: 1) GO.Rt.No.104,of EFS&T(For.I) Dept,Dt.09.06.2017.


2) Rc.No.2003/2016/S1,Dated.10.09.2018 of Forest Divisional Officer,Nirmal

*****
It is to submit that,vide reference 1st cited above the Government of Telangana, has accorded In-
Principle(Stage-I) approval for the diversion of 4.945 Ha of forest land in Kawal Tiger Reserve ,Nirmal
Division ,for laying of pipeline and construction of structures in Segment-21/7(Madegaon) for providing safe
drinking water to erstwhile Adilabad District presently Nirmal District under Telangana Drinking Water Supply
Project(TDWSP) in favour of Superintending Engineer,TDWSP(RWS&S) Circle,Nirmal stating thatgranting of
final approval will be considered on submission of compliance report on condtionals stipulated in In-
Princple(Stage-I) approval andaccordingly vide reference 2nd cited above Forest Divisional Officer,Nirmal
requested this office to submit the same for taking further necessary action.

In view of the above I am herewith submitting the Compliance report for conditions stipulated in In-
Principle(Stage-I) approval for diversion of 4.945 Ha forest land in Kawal Tiger Reserve,Nirmal Division for
taking further necessary action for granting Stage-II(Final) approval.
Encl:Compliance Report(6 Sets)

Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.


Copy to Executive Engineer,MB Grid Division,Nirmal for information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The District Forest Officer,
SuperintendingEngineer(FAC), Adilabad District.
RWS& S-Circle,Adilabad,
Adilabad Dist.

Lr.No.24/AEE3/ SE / RWSS(Adilabad)/ SRSP-ADB/FOREST/COMPLIANCE REPORT, Dt:29.11.2018

Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-FCA –Proposals for diversion of 4.945 Ha
of forest land in Kawal Tiger Reserve,Nirmal Division-for laying pipeline and construction of
structures in Segment-21/7(Madegaon) for providing safe drinking water to erstwhile Adilabad
District presently Nirmal District under Telangana Drinking Water Supply Project(TDWSP)-In-
Principle(Stage-I) approval accorded-Compliance report on conditions stipulated in Stage-I-
Submitted-Stage-II Clearance-Requested-Regarding.

Ref: 1) GO.Rt.No.104,of EFS&T(For.I) Dept,Dt.09.06.2017.


2) Rc.No.2003/2016/S1,Dated.10.09.2018 of Forest Divisional Officer,Nirmal

*****
It is to submit that,vide reference 1st cited above the Government of Telangana, has accorded In-
Principle(Stage-I) approval for the diversion of 4.945 Ha of forest land in Kawal Tiger Reserve ,Nirmal
Division ,for laying of pipeline and construction of structures in Segment-21/7(Madegaon) for providing safe
drinking water to erstwhile Adilabad District presently Nirmal District under Telangana Drinking Water Supply
Project(TDWSP) in favour of Superintending Engineer,TDWSP(RWS&S) Circle,Nirmal stating thatgranting of
final approval will be considered on submission of compliance report on condtionals stipulated in In-
Princple(Stage-I) approval andaccordingly vide reference 2nd cited above Forest Divisional Officer,Nirmal
requested this office to submit the same for taking further necessary action.

In view of the above I am herewith submitting the Compliance report for conditions stipulated in In-
Principle(Stage-I) approval for diversion of 4.945 Ha forest land in Kawal Tiger Reserve,Nirmal Division for
taking further necessary action for granting Stage-II(Final) approval.

Encl:Compliance Report(6 Sets)

Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.


Copy to Executive Engineer,MB Grid Division,Nirmal for information.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The District Forest Officer,
SuperintendingEngineer(FAC), Adilabad District.
RWS& S-Circle,Adilabad,
Adilabad Dist.

Lr.No.25/AEE3/ SE / RWSS(Adilabad)/ SRSP-ADB/FOREST/COMPLIANCE REPORT, Dt:29.11.2018

Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-FCA –Proposals for diversion of 4.945 Ha
of forest land in Kawal Tiger Reserve,Nirmal Division-for laying pipeline and construction of
structures in Segment-21/7(Madegaon) for providing safe drinking water to erstwhile Adilabad
District presently Nirmal District under Telangana Drinking Water Supply Project(TDWSP)-In-
Principle(Stage-I) approval accorded-Compliance report on conditions stipulated in Stage-I-
Submitted-Stage-II Clearance-Requested-Regarding.

Ref: 1) GO.Rt.No.104,of EFS&T(For.I) Dept,Dt.09.06.2017.


2) Rc.No.2003/2016/S1,Dated.10.09.2018 of Forest Divisional Officer,Nirmal

*****
It is to submit that,vide reference 1st cited above the Government of Telangana, has accorded In-
Principle(Stage-I) approval for the diversion of 4.945 Ha of forest land in Kawal Tiger Reserve ,Nirmal
Division ,for laying of pipeline and construction of structures in Segment-21/7(Madegaon) for providing safe
drinking water to erstwhile Adilabad District presently Nirmal District under Telangana Drinking Water Supply
Project(TDWSP) in favour of Superintending Engineer,TDWSP(RWS&S) Circle,Nirmal stating thatgranting of
final approval will be considered on submission of compliance report on condtionals stipulated in In-
Princple(Stage-I) approval andaccordingly vide reference 2nd cited above Forest Divisional Officer,Nirmal
requested this office to submit the same for taking further necessary action.

In view of the above I am herewith submitting the Compliance report for conditions stipulated in In-
Principle(Stage-I) approval for diversion of 4.945 Ha forest land in Kawal Tiger Reserve,Nirmal Division for
taking further necessary action for granting Stage-II(Final) approval.

Encl:Compliance Report(6 Sets)

Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.


Copy to Executive Engineer,MB Grid Division,Nirmal for information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad.
RWS& S-Circle,Adilabad,
Adilabad Dist.

Lr.No.26/AEE3/ SE / RWSS(Adilabad)/ SRSP-ADB/PHASE-II /DLP, Dt:29.11.2018


Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment – “Providing Drinking Water toHabitations in SRSP
Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District Including
Operation & Maintenance for 10 Years- Defect Liability Period(DLP) Certificates-Submitted-Reg.

Ref: 1)Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal Circle.


2)Lr.No.MB GRID NIRMAL/SRSP Adilabad/Phase-II/DLP/2018,Dated:29.11.2018 of Executive Engineer
MB Grid Division,Nirmal.
3)Lr.No.MB GRID NIRMAL/SRSP Adilabad/Phase-II/DLP/2018,Dated:29.11.2018 of Executive Engineer
MB Grid Division,Nirmal.
*****
It is to submit that , vide reference 1st cited above an agreement was concluded with M/s.Megha
Engineering & Infrstructures Limited,Hyderabad for the work “Providing Drinking Water toHabitations in
SRSP Adilabad Segment in Adilabad DistrictEst.Cost 1530.00 Cr of SE,TDWSP,Adilabad District
Including Operation & Maintenance for 10 Years”, under Telangana Drinking Water Supply
Project(TDWSP).

Wherein Vide reference 2nd and 3rd Cited above, Executive Engineer,MB Grid Division,Nirmal has
submitted the Defect Liability Period(DLP) certificates pertaining to MB Grid Sub Division,Nirmal and
Bhainsahaving subwork wise starting date of Defect Liability Period.

In this regard I am herewith submitting the Defect Liability Certificates(DLP) for subworksof above
work under MB Grid Division,Nirmal for your kind perusal and further necessary action.

Encl:Defect Liability Certificates(DLPs)

Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.


Copy to Executive Engineer,MB Grid Division,Nirmal for information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad.
RWS& S-Circle,Adilabad,
Adilabad Dist.

Lr.No.27/AEE3/ SE / RWSS(Adilabad)/ SRSP-ADB/PHASE-I /DLP, Dt:29.11.2018

Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment – “Construction of Intakewell,WTP and Raw Water
Pumping Main in Adilabad Segment,Kaddam Segment,Asifabad Segment and Mancherial Segment of
Telangana Drinking Water Supply Project(TDWSP)”- Defect Liability Period(DLP) Certificate-
Submitted-Reg.

Ref: 1)Agreement No:AEE1/01/2015-16,Dated:09.04.2015 of Superintending Engineer,RWS&S


Circle,Adilabad.
2)Lr.No.MB GRID NIRMAL/SRSP Adilabad/Phase-I/DLP/2018,Dated:29.11.2018 of Executive
Engineer, MB Grid Division,Nirmal.

*****
It is to submit that , vide reference 1st cited above an agreement was concluded with M/s.Megha
Engineering & Infrstructures Limited,Hyderabad for the work “Construction of Intakewell,WTP and Raw
Water Pumping Main in Adilabad Segment,Kaddam Segment,Asifabad Segment and Mancherial
Segment of Telangana Drinking Water Supply Project(TDWSP)”

Wherein Vide reference 2nd Executive Engineer,MB Grid Division,Nirmal has submitted the Defect
Liability Period(DLP) certificate for sub works under above work pertaining toMB Grid Sub Division Nirmal
,having subwork wise starting date of Defect Liability Period.

In this regard I am herewith submitting the Defect Liability Certificate(DLP) for subworks of above
work pertaining to MB Grid Division,Nirmal for your kind perusal and further necessary action.

Encl:Defect Liability Certificate(DLP)

Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.


Copy to Executive Engineer,MB Grid Division,Nirmal for information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad.
RWS& S-Circle,Adilabad,
Adilabad Dist.

Lr.No.28/AEE3/ SE / RWSS(Adilabad)/ SRSP-ADB/WE-II/2018-19, Dt: 06. 12.2018


Sir,
Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment – “Providing Drinking Water to Habitations in SRSP
Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District Including
Operation & Maintenance for 10 Years-Working Estimate-II-Submitted-Approval-Req-Reg.

Ref: 1)Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal Circle.


2) Lr.No.AEE1/MB GRID NIRMAL/SRSP ADILABAD SEGMENT/PH-II/WE-II/2018,Dt:06.12.2018
Of Executive Engineer,MB Grid Division,Nirmal.
.

*****
It is to submit that , vide reference 2nd cited above Executive Engineer,MB Grid Division,Nirmal has
submitted the Working Estimate-II for the work “Providing Drinking Water to Habitations in SRSP Adilabad
Segment in Adilabad District”Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District Including Operation &
Maintenance for 10 Years for favour of kind approval .

Hence,same is herewith submitted and the Chief Engineer,TDWSP-IV,Hyderabad is requested to kindly


approve the estimate at an early date.

Encl:Working Estimate-II

Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.


Copy to Executive Engineer,MB Grid Division,Nirmal for information.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad.
RWS& S-Circle,Adilabad,
Adilabad Dist.

Lr.No.29/AEE3/ SE / RWSS(Adilabad)/ SRSP-ADB/PH-II/EOAT/2018-19, Dt: 10. 12.2018

Sir,

Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment – “Providing Drinking Water to Habitations in SRSP


Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District Including
Operation & Maintenance for 10 Years- Extension of Agreement Time (EOAT) Proposals-Submitted –
Reg.

Ref: 1)GO.RT.NO:394&392 of PR&RD (RWS IV) Dept.,Dt.23.06.2015.


2)Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal Circle.
3)T/o.Proc.No.01/AEE1/DEE1/EOAT/SRSP ADB/PH-II/2018,Dated:11.05.2018.
4) Lr.No.MEIL/SRSP-ADILABAD Water Grid Ph2/2018-19,Dated:01.12.2018 of M/s.MEI,Hyderabad.
5) Lr.No.MB GRID NIRMAL/SRSP Adilabad/Phase-II/EOAT-II/2018,Dated:10.12.2018 of Executive
Engineer,MB Grid Division,Nirmal.
6)Lr.No.MB GRID ADILABAD/SRSP Adilabad/Phase-II/EOAT-II/2018, Dated:10.12.2018 of Executive
Engineer,MB Grid Division,Adilabad.
*****
It is to submit that vide reference 1stcited above , the Government has accorded administrative sanction
for the work “Providing Drinking Water to Habitations in SRSP-Adilabad Segment in Adilabad
District”Including Operation & Maintenance for 10 Years under Telangana Drinking Water Supply
Project(TDWSP). Further through the reference 2nd cited an agreement was concluded with M/s Megha
Engineering and Infrastructure Limited,Hyderabadfor the same.

Wherein vide reference 3rd cited EOAT-I ,which was accorded for the above work was expired on
10.12.2018 and accordingly vide reference 4th cited M/s.MEIL, Hyderabad submitted the proposals for EOAT
and requested this office for further EOAT upto 31stJuly 2019.

And also vide reference 5th and 6th cited above the Executive Engineers MB Grid,Division, Nirmal &
Adilabad has submitted the EOAT Proposals for the same based on the reasons explained by the agency, and
further enclosed Check slip.

Contd…..Page No.2

:::2:::

Hence,I am herewith submitting the Extension of Agreement Time(EOAT) proposals for the above said
work under SRSP-Adilabad Segment for your kind perusal and further necessary action.

Encl: EOAT Check slip.


Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information..


Copy to Executive Engineer,RWS&S,MB Grid Division,Nirmal for information.
Copy to Executive Engineer,RWS&S,MB Grid Division,Adilabad for information.

Reminder-IV
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

Memo No.08/AEE3/DEE-II/BSNL /Cable Damages/2018,Dated:20.12.2018

Sub:RWS&S Circle-Adilabad-BSNL-Damages to underground cables-Recovery dues-Detailed Report-


Req-Reg.

Ref:1. Lr.No.GMTD/ADB/Plg/Way Leave Permissions/2010-19/Vol.I/67,Dated:02.07.2018 of the


General Manager,BSNL,Adilabad.
2.T/o Memo No.01/AEE3/DEE-II/BSNL/Cable Damages/2018,Dated:12.07.2018
3.T/o Memo No.03/AEE3/DEE-II/BSNL /Cable Damages/2018,Dated:07.09.2018
4.T/o Memo No.05/AEE3/DEE-II/BSNL /Cable Damages/2018,Dated:08.10.2018
5.T/o.Memo No.06/AEE3/DEE-II/BSNL/Cable Damages/2018,Dated:15.11.2018

The immediate personal attention of the Executive Engineer,MB Grid Division,Adilabad is


invited to the subject and references cited,where in it was requested to furnish the detailed report on damages
done to BSNL underground cables(both Copper&OFC).But no information is received by this office even after a
lapse 5 months.

Therefore,the Executive Engineer,RWS&S,MB Grid Division,Adilabad is once again requested


to furnish the detailed report on damages to BSNL underground cables(Both Copper&OFC) to this office
immediately for taking further necessary action.

Superintending Engineer(FAC)
RWS&S Circle-Adilabad

To,
The Executive Engineer, MB Grid Division, Adilabad.
Copy Submitted to the Chief Engineer-I,RWS&S ,Hyderabad for favour of information
Copy submitted to the Engineer-in-Chief ,RWS&S,Hyderabad for favour of information
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.09/AEE3/DEE-II/Lower Pengana Project/Damages/2018-19,Dated:24.12.2018

Sub:Mission Bhagiratha Circle-Adilabad-Lower Penganga Project- Certain Damages to Machinery


and Structure-Detailed Report- Req-Reg.

Ref:1. Lr.No.EE/PGP/DB/HD/LPP MC/351/m,Dated:22.12.2018 of Executive Engineer,I&CADD,


Penganga Project Division,Adilabad.
****

The immediate Personal attention of Executive Engineer,MB Grid Division,Adilabad is drawn


to the reference cited above,wherein Executive Engineer,I&CADD,Penganga Project Division informed that
Mission Bhagiratha outlet Pipe of scour valve was laid in LPP Main canal and it was opened on
19.12.2018(Midnight) leading to heavy quantities of stagnation of water in Canal and causing certain damages
canal and some macheinary.

In this regard,Executive Engineer,MB Grid Division,Adilabad is hereby directed to submit the


action taken report on above damages to this office for further necessary action.

Enclosure:As Above

Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad

To,
The Executive Engineer, MB Grid Division, Adilabad
Copy to Executive Engineer,I&CADD,Penganga Project Division,Adilabad for information.
Copy Submitted to the Chief Engineer-I,Mission Bhagiratha ,Hyderabad for favour of kind information.
Copy submitted to the Engineer-in-Chief ,Mission Bhagiratha,Hyderabad for favour of information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.30/AEE3/SE/MB/ NEWS PAPER/ADEVERSE CLIPPINGS/2018-19, Dt: 31. 12.2018

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-Adverse News Published in Andhrajyothi News Paper on
Date:29.12.2018-With Caption “Manchi Neellu Maha Prabho”-Rejoinder-Submitted-Reg.

Ref: Arising
*****
It is to submit that,Adverse News was published in Andhrajyothi News Paper on Date:29.12.2018,
With caption “Manchi Neellu Maha Prabho”inKhandala Panchayath of Adilabad District.

In this regard, it is submitted that I personally visited Khandala village which was mentioned in in above paper
clipping and enquired withvillagersnamely1.PoojaBhai,2.Gopal,3.Sikindar,4.Aruna,5.Sunilwho stated that
they are receving Mission Bhagiratha Water everyday for a duration of nearly 1hour.Further they stated that
only on Date:29.12.2018 the water was slightly muddy due to which they did not utlizeMission Bhagiratha
water on Dt:29.12.2018& 30.12.2018.

And further it is to submit that on Dt:31.12.2018 there is a leakage in 1200mm Dia, MS Pumping main
in Nirmal due to which water is not supplied to Adilabad and supply will resume from Date:01.01.2019 and will
be supplied regularly.

The News which was published in Andhrajyothi News Paper is baseless.

Yours faithfully,

Superintending Engineer(FAC),
Mission BhagirathaCircle, Adilabad.

Copy submitted to the Engineer-in-Chief,Mission Bhagiratha ,Hyderabad for favour of kind information.
Copy Submitted to Collector &District Magistrate ,Adilabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) The Executive Engineer,
SuperintendingEngineer(FAC), Irrigation&CADD,
Mission Bhagiratha Circle,Adilabad, Penganga Project Division,
Adilabad Dist. Adilabad

Lr.No.31/AEE3/SE/MB/ Lower Penganga Project/Damages/2018-19, Dt: 05. 01.2019

Sir,

Sub: Mission Bhagiratha Circle-Adilabad-Lower Penganga Project-Certain Damages to Structures and


Machinery due to Mission Bhagiratha Works–Action Taken Report-Submitted-Reg.

Ref: 1.Your office Letter No.EE/PGP/DB/HD/LPP MC/351/m,Dated:22.12.2018.


2.T/o.Memo.No.09/AEE3/DEE-II/Lower Penganga Project/Damages/2018-19,Dated:24.12.2018.
3.Lr.No.DEE/MB Grid/Div.Adb/LPP-Certain Damages/ATR/2018-19,Dt:02.01.2019 of Executive
Engineer,MB Grid Division,Adilabad.
*****
It is to inform that,vide reference 1st cited above it was requested to make arrangements for damages done to
Lower Penganga Project Structures and Machinery due to opening of Mission Bhagiratha Scour Valve near
DLBR at Km.85.793 of LPP Main Canal.

Wherein vide reference 2nd cited,Executive Engineer,MB Grid Division,Adilabad was requestedto
submit Action Taken Report for above damages and same was submitted to this office vide reference 3 rd cited
above.

In this regard I am herewith submitting the Action Taken Report on damages done to Lower Penganga
Project structures and Machinery due to opening of Mission Bhagiratha Scour Valve for information and
necessary action.

Enclosure:As Above
Yours faithfully,

Superintending Engineer(FAC),
Mission BhagirathaCircle, Adilabad.

Copy Submitted to:-


The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha ,Hyderabad for favour of kind information.

Copy To:
Executive Engineer,MB Grid Division,Adilabad for information and necessary action.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) The Superintending Engineer,
SuperintendingEngineer(FAC), Godavari Valley Circle No.1,
Mission Bhagiratha Circle,Adilabad, SriramSagar Project-503219,
Adilabad Dist. Nizamabad Dist.

Lr.No.32/AEE3/SE/MB/ SRSP Reservior/MDDL/2018-19, Dt: 05. 01.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment(No.21)-SRSP Reservior-Maintaining
Minimum Draw Down Level(MDDL)-Reg.

Ref: 1.G.O.Rt.No.885 of I&CAD(WRG-GRC) Department,Dated:30.10.2017.


2.Minutes of Review Meeting on Mission Bhagiratha by Hon’ble Chief Minister of Telangana,
Dated:30.06.2018.
3.Govt.Memo.No.5355/WRG/2018-,Dated:03.07.2018
4.Lr.No.ENC(I)/DCE.I/OT-2/AEE20/MB/2018,Dated:02.07.2018 of Engineer-in-Chief(Irrigation),
I&CAD Department,Hyderabad.
*****
It is to submit that,Vide reference 1st cited above Governament has instructed to maintain Minimum
Draw Down Levels(MDDL’s) in certain Reserviors of Telangana for storing required quantum of water
forGovernament flagship Programme -“Mission Bhagiratha” so as to provide protected and assured drinking
water on sustainable basis to all the households of state.

Further it is to inform that,during the review meeting with Hon’ble Chief Minister of Telangana ,on
Dt:30.06.2018 it was instructed that under any circumstances the water levels in reservoirs shall not go below
prescribed MDDL’s without prior consent of concerned Executive Engineer of Mission of Bhagiratha and same
instruction were again issued vide reference 3rd&4th cited above.

In this regard,it is requested sir to kindly instruct concerned officials to maintain Minimum Draw
Down Level(MDDL) in SRSP Reservior as per the Governament instructions so as to avoid any drinking water
scarcity in ensuing summer-2019 as it serves Adilabad(254 Habs),Boath(480 Habs),,Nirmal(209 Habs)
Constituencies under this circle.
Enclosure:As Above
Yours faithfully,

Superintending Engineer(FAC),
Mission BhagirathaCircle, Adilabad.
Copy To:
Executive Engineer,MB Grid Division,Nirmal for information and with request to Co-ordinate with concerned
Irrigation officials in Maintaining MDDL and report compliance.
Copy Submitted to:
Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of Kind information.
Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of Kind information.
Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
The Collector&District Magistrate,Adilabad for favour of Kind information
The Collector&District Magistrate,Nirmal for favour of Kind information

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) The Superintending Engineer,
SuperintendingEngineer(FAC), Irrigation Circle,Nirmal,
Mission Bhagiratha Circle,Adilabad, Nirmal District,
Adilabad Dist. .

Lr.No.33/AEE3/SE/MB/ Gaddenna Reservior/MDDL/2018-19, Dt: 05. 01.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment(No.21)-Gaddenna Project-Maintaining
Minimum Draw Down Level(MDDL)-Reg.

Ref: 1.G.O.Rt.No.885 of I&CAD(WRG-GRC) Department,Dated:30.10.2017.


2.Minutes of Review Meeting on Mission Bhagiratha by Hon’ble Chief Minister of Telangana ,
Dated:30.06.2018.
3.Govt.Memo.No.5355/WRG/2018-,Dated:03.07.2018
4.Lr.No.ENC(I)/DCE.I/OT-2/AEE20/MB/2018,Dated:02.07.2018 of Engineer-in-Chief(Irrigation),
I&CAD Department,Hyderabad.
*****
It is to submit that,Vide reference 1st cited above Governament has instructed to maintain Minimum
Draw Down Levels(MDDL’s) in certain Reserviors of Telangana for storing required quantum of water
forGovernament flagship Programme -“Mission Bhagiratha” so as to provide protected and assured drinking
water on sustainable basis to all the households of state.

Further it is to inform that,during the review meeting with Hon’ble Chief Minister of Telangana ,on
Dt:30.06.2018 it was instructed that under any circumstances the water levels in reservoirs shall not go below
prescribed MDDL’s without prior consent of concerned Executive Engineer of Mission of Bhagiratha and same
instruction were again issued vide reference 3rd&4th cited above.

In this regard,it is requested sir to kindly instruct concerned officials to maintain Minimum Draw
Down Level(MDDL) in Gaddenna Reservior as per the Governament instructions so as to avoid any drinking
water scarcity in ensuing summer-2019 as it serves Mudhole(248 Habs) Constituency and Bhainsa ULB under
this circle.
Enclosure:As Above
Yours faithfully,

Superintending Engineer(FAC),
Mission BhagirathaCircle, Adilabad.
Copy To:
Executive Engineer,MB Grid Division,Nirmal for information and with request to Co-ordinate with concerned
Irrigation officials in Maintaining MDDL and report compliance.
Copy Submitted to:
Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of Kind information.
Chief Engineer(Projects),I&CADD Department,Adilabad,for favour of kind information.
Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
The Collector&District Magistrate,Nirmal for favour of Kind information
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.10/AEE3/DEE-II/MB/Minutes of Meeting/2018-19,Dated:05.01.2019

Sub: Mission Bhagiratha Circle-Adilabad-Minutes of Review Meeting on Mission Bhagiratha


(Grid&Intra) held by Collector&District Magistrate,Adilabad on 27.12.2018 at Adilabad-
Communicated-Reg.

Ref: -
.
****

A copy of the Minutes of Review Meeting on Mission Bhagiratha(Grid&Intra) held by


Collector&District Magistrate,Adilabad on 27.12.2018 at Adilabad is herewith communicated to all
The Executive Engineer,Deputy Executive Engineer,Assistant Executive Engineer/Assistant Engine
-ers and Executing agencies(Grid&Intra) of Adilabad District for information and necessary action.

Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad

To,
The Executive Engineer,MB Intra Division,Adilabad.(w.e)
The Executive Engineer,MB Grid Division,Adilabad/Asifabad.(w.e)
The Dy.Executive Engineers,MB Intra Sub Division Adilabad/Boath/Utnoor(w.e).
The Dy.Executive Engineers,MB Grid Sub Division Adilabad/Ichoda /Kerameri.(w.e)
The All the Assistant Executive Engineers/Assistant Engineers of Adilabad District through Concerned
Dy.EE’s Mission Bhagiratha.(w.e)
The Executing Agencies through concerned Executive Engineers,Mission Bhagiratha(w.e)
Copy Submitted to the Chief Engineer-I,Mission Bhagiratha ,Hyderabad for favour of kind information.
Copy submitted to the Engineer-in-Chief ,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) The Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.34/AEE3/SE/MB/ SRSP Adilabad/PH-II/WE-II/WorkSlip/2018-19, Dt: 05. 01.2019

Sir,

Sub: Mission Bhagiratha Circle-Adilabad- Adilabad-SRSP-Adilabad Segment – “Providing Drinking Water to


Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years-Working Estimate-II-
WorkSlip-Submitted -Approval-Req-Reg.

Ref: 1.Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal Circle.


2.T/o.Lr.No.28/AEE3/ SE / RWSS(Adilabad)/ SRSP-ADB/WE-II/2018-19, Dated: 06. 12.2018
3.Lr.No.AEE1/EE/Grid/Div-Adb/Scattered Habs/Estimate/2019,Dated:05.01.2019, of Executive
Engineer,MB Grid Division,Adilabad.

*****

It is to submit that , vide reference 3rd cited above Executive Engineer,MB Grid Division,Adilabad has
submitted the Working slip for Scattered(Isolated) habs for Rs.1130.00 Lakhs in Adilabad District as Hon’ble
Chief Minister of Telangana instructed to covered each and every habitation in the state under the work
“Providing Drinking Water to Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost
1530.00 Cr of SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years
Encl:Work Slip for Scatter Habs

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.


Copy to Executive Engineer,MB Grid Division,Adilabad for information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) The Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.35/AEE3/SE/MB/ SRSP Adilabad/EM Works/EOAT-3/2018-19, Dt: 20.11.2018

Sir,

Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-Design, Supply, Erection, Testing and


commissioning of Electro mechanical works with SCADA & Instrumentation along
with associated substation and switch gear including all connected accessories for various
Pumping stations located at various places in erstwhile districts Adilabad, Nizamabad and
Karimnagar. Including, defects liability period and operation and maintenance for 10 years
Package-III –Extension of Agreement Time (EOAT) Proposals-Submitted – Reg.

Ref: :1) GO.RT.NO:82 of PR&RD (RWS IV) Dept.,Dt.07.02.2015


2) GO.RT.NO:336 of PR&RD (RWS IV) Dept.,Dt.01.06.2015
3) GO.RT.NO:394&392 of PR&RD (RWS IV) Dept.,Dt.23.06.2015
4) Agreement No. AEE/01/2017-18,Dated:18.04.2017.of the Superintending
Engineer,TDWSP Circle,Nirmal.
5) Proc.No.AEE1/DEEII/EOAT/Electromechanical Works/2018,Dated:16.01.2018 of
Superintending Engineer,RWS&S Circle,Mancherial.
6) Procs.No.AEE/DEE/TDWSP/Electro Mechanical/EOAT/Package-III/2017-18,
Dated:30.04.2018 of Chief Engineer-III,TDWSP,Hyderabad.
7) Lr.No.RC/RWS&S/PKG-3/EMW/SE/EOAT/2018-19/18,Dated:26.07.2018 of
M/s.Raghava Constructions.
8) Lr.No.03/AEE/MB Grid Adilabad/SRSP ADB/EM Works/EOAT/2018,
Dated: 20.11.2018 of Executive Engineer,RWS&S,MB Grid Division,Nirmal.
*****

It is to submit that videreferences 1st, 2nd & 3rd cited, the Government has accorded administrative
sanction for the work “Design, Supply, Erection, Testing and commissioning of Electro mechanical works
with SCADA & Instrumentation along with associated substation and switch gear including all connected
accessories for various Pumping stations located at various places in erstwhile districts Adilabad,
Nizamabad and Karimnagar. Including, defects liability period and operation and maintenance for 10
years Package-III”. Further through the reference 4th cited agreement was concluded with M/s Raghava
Constructions Khammam for the same.

Wherein the EOAT-I & EOAT-II which were accorded vide References 5th& 6th cited for the above
work are expired on 31st July 2018.Accordingly vide reference 7th cited M/s.Raghava Constructions submitted
the proposals for EOAT with for Electromechanical works of SRSP-Adilabad segment and requested for further
EOAT upto 30th March 2019.

And also the Executive Engineers MB Grid,Division, Nirmal has submitted the EOAT Proposals EOAT
upto 30th March 2019 without imposing any penalty based on the reasons explained by the agency, and further
enclosed item wise details such as Check slip.

Hence,It is requested sir to kindly accord EOAT upto 30.03.2019 without any penalty.

Encl:As Above.

Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information..


Copy to Executive Engineer,RWS&S,MB Grid Division,Nirmal for information.
GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) The Chief Engineer-I,
SuperintendingEngineer(FAC), TDWSP,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.36/AEE3/SE/MB/ SRSP Adilabad/EM Works/EOAT-3/2018-19, Dt: 20.11.2018

Sir,

Sub: RWS&S Circle-Adilabad-SRSP-Adilabad Segment-Design, Supply, Erection, Testing and


commissioning of Electro mechanical works with SCADA & Instrumentation along
with associated substation and switch gear including all connected accessories for various
Pumping stations located at various places in erstwhile districts Adilabad, Nizamabad and
Karimnagar. Including, defects liability period and operation and maintenance for 10 years
Package-III –Extension of Agreement Time (EOAT) Proposals-Submitted – Reg.

Ref: :1) GO.RT.NO:82 of PR&RD (RWS IV) Dept.,Dt.07.02.2015


2) GO.RT.NO:336 of PR&RD (RWS IV) Dept.,Dt.01.06.2015
3) GO.RT.NO:394&392 of PR&RD (RWS IV) Dept.,Dt.23.06.2015
4) Agreement No. AEE/01/2017-18,Dated:18.04.2017.of the Superintending
Engineer,TDWSP Circle,Nirmal.
5) Proc.No.AEE1/DEEII/EOAT/Electromechanical Works/2018,Dated:16.01.2018 of
Superintending Engineer,RWS&S Circle,Mancherial.
6) Procs.No.AEE/DEE/TDWSP/Electro Mechanical/EOAT/Package-III/2017-18,
Dated:30.04.2018 of Chief Engineer-III,TDWSP,Hyderabad.
7) Lr.No.RC/RWS&S/PKG-3/EMW/SE/EOAT/2018-19/18,Dated:26.07.2018 of
M/s.Raghava Constructions.
8) Lr.No.01/AEE/MB Grid Adilabad/SRSP ADB/EM Works/EOAT/2018,
Dated: 20.11.2018 of Executive Engineer,RWS&S,MB Grid Division,Adilabad.
*****

It is to submit that videreferences 1st, 2nd & 3rd cited, the Government has accorded administrative
sanction for the work “Design, Supply, Erection, Testing and commissioning of Electro mechanical works
with SCADA & Instrumentation along with associated substation and switch gear including all connected
accessories for various Pumping stations located at various places in erstwhile districts Adilabad,
Nizamabad and Karimnagar. Including, defects liability period and operation and maintenance for 10
years Package-III”. Further through the reference 4th cited agreement was concluded with M/s Raghava
Constructions Khammam for the same.

Wherein the EOAT-I & EOAT-II which were accorded vide References 5th& 6th cited for the above
work are expired on 31st July 2018.Accordingly vide reference 7th cited M/s.Raghava Constructions submitted
the proposals for EOAT with for Electromechanical works of SRSP-Adilabad segment and requested for further
EOAT upto 30th March 2019.
And also the Executive Engineers MB Grid,Division, Adilabad has submitted the EOAT Proposals upto
th
30 March 2019 without imposing any penalty based on the reasons explained by the agency, and further
enclosed item wise details such as Check slip.

Hence,It is requested sir to kindly accord EOAT upto 30.03.2019 without any penalty.

Encl:As Above.

Yours faithfully,

Superintending Engineer(FAC),
RWS&S Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information..


Copy to Executive Engineer,RWS&S,MB Grid Division,Adilabad for information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Endt.No.02/AEE3/ SE / MB(Adilabad) /Communication/2018-19, Dt:09.01.2019

“Communicated Lr.No. B/Mission Bhagiratha/2018,Dated:04.01.2019 of S.G Govt Polytechnic


College,Adilabad”

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
To,
Executive Engineers,MB Grid Division Adilabad circle for necessary action.
Copy to Prinicipal(FAC),S.G. Govt.Polytechnic,Adilabads for information.
Copy submitted to Collector &District Magistrate,Adilabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) The Principal,
SuperintendingEngineer(FAC), S.G.Govt.Polytechnic College,
Mission Bhagiratha Circle,Adilabad, Adilabad.
Adilabad Dist.
Lr.No.37/AEE3/SE/MB/ SRSP Adilabad/Bulk Water Connection /2018-19, Dt: 10. 01.2019

Sir,

Sub: Mission Bhagiratha Circle-Adilabad- Adilabad-Adilabad District–S.G.Govt.Polytechnic College


,Adilabad-Bulk Water Connection-Reg.

Ref: 1.Your office Letter No.B/Mission Bagiratha/2018,Dated:04.01.2019


*****

It is to submit that ,your request for Mission Bhagiratha Water Connection received by this office on
Dt:05.01.2019.
In this regard it is to inform that your college falls under the jurisdiction of Adilabad Municipality and
hence forth you are requested to approach Adilabad Municipality for Water Connection.

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy submitted to The Collector&District Magistrate,Adilabad for favour of Kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.11/AEE3/DEE-II/MB/Forest/Compliance Report/2018-19,Dated:19.01.2019

Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment –Forest-21/7(Madegaon)-


Compliance report on conditions stipulated in Stage-I approval-Reg.

Ref:1.Rc.No.2003/2016/S1,Dated:29.12.2018 of Forest Divisional Officer,Nirmal.


.
.
****
A copy of the observations made by Forest Divisional Officer,Nirmal vide
Rc.No.2003/2016/S1,Dated:29.12.2018 on Compliance report for Conditions stipulated in Stage-I approval for
laying pipeline and construction of structures in segment-21/7(Madegaon), is herewith communicated to
Executive Engineer,MB Grid Division,Nirmal with a request to submit the compliance report on observation
made by the Forest Divisional officer,Nirmal at an early date for taking further necessary action.

Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad

To:
The Executive Engineer,MB Grid Division,Nirmal.
Copy Submitted to:
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) Chief Engineer-I ,
SuperintendingEngineer(FAC), Mission Bhagiratha,Hyderabad
Mission Bhagiratha Circle,Adilabad,
Adilabad Dist.

Lr.No.37/AEE3/SE/MB/ SRSP Adilabad/Adilabad District/2018-19, Dt: 18.01.2019

Sir
Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District-SRSP-Adilabad Segment-Isolated/Scattered
Habs-Detailed Report-Submitted-Reg.

Ref: 1.Instructions issued by Hon’ble Chief Minister,Governament of Telangana on Dt:17.12.2018


2. Lr.No.AEE1/EE/Grid/Div-Adb/Scattered Habs/Estimate/2019,Dated:05.01.2019, of Executive
Engineer,MB Grid Division,Adilabad.
3.T/o.Lr.No.34/AEE3/SE/MB/ SRSP Adilabad/PH-II/WE-II/WorkSlip/2018-19,Dated: 05. 01.2019
Addressed to Chief Engineer-IV,Mission Bhagiratha,Hyderabad.

*****

It is to submit that,vide reference 1sit cited above Hon’ble Chief Minister, Governament of Telanga
instructed to cover left over scattered habitations in the state under Mission Bhagiratha irrespective of the
cost.Accordinly a joint inspection was conducted by the undersigned along with EE,MB Grid Division,Adilabad
and Dy.EE&A.E.MB Grid SD Adilabad along with a representative from main grid agency M/s.MEIL for
identifying the isolated habs.

During the Joint inspection 8 Habs (Annexure enclosed) were identified as isolated/scattered in
Adilabad District under SRSP-Adilabad Segment . Executive Engineer stated that out these 8 Habs 4 Habs
were proposed to be covered in orginal estimate i.e. under 20 KL,30 Mts staging OHBR at Punaguda and same
structure was later deleted as Forest department denied permissions stating these are encroached/unauthorized
habitations and remaining 4 habs were identified later which are also encroached habitations as stated by forest
department .Furhter Executive Engineer stated that forest permissions are needed for proceeding for any further
work in these habitations.

Wherein vide reference 2nd cited above,Executive Engineer,MB Grid Division,Adilabad submitted the
estimate of Cost 1130.00 Lakhs for covering the above 8 isolated habs under Mission Bhagiratha as a workslip
under Main Grid works of SRSP-Adilabad segment stating that this amount can be met from savings of Main
Grid Works and same was submitted by this office vide reference 3rd cited above.

This is submitted for favour of further necessary action please.

Enclosure:As above

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy submitted to The Engineer-in-Chief,Mission Bhagiratha Hyderabad for favour of kind information.
Copy submitted to The Chief Engineer-IV,Mission Bhairatha,Hyderabad for favour of Kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) Chief Engineer-IV ,
SuperintendingEngineer(FAC), Mission Bhagiratha,Hyderabad
Mission Bhagiratha Circle,Adilabad,
Adilabad Dist.

Lr.No.38/AEE3/SE/MB/ SRSP Adilabad/Adilabad District/2018-19, Dt: 18.01.2019

Sir
Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District-SRSP-Adilabad Segment-Isolated/Scattered
Habs-Detailed Report-Submitted-Reg.

Ref: 1.Minutes of Review Meeting By Hon’ble Chief Minsiter,Governament of Telangana on Dt:17.12.2018


2. Lr.No.AEE1/EE/Grid/Div-Adb/Scattered Habs/Estimate/2019,Dated:05.01.2019, of Executive
Engineer,MB Grid Division,Adilabad.
3.T/o.Lr.No.34/AEE3/SE/MB/ SRSP Adilabad/PH-II/WE-II/WorkSlip/2018-19,Dated: 05. 01.2019
Addressed to Chief Engineer-IV,Mission Bhagiratha,Hyderabad.

*****

It is to submit that,vide reference 1sit cited above Hon’ble Chief Minister, Governament of Telanga
instructed to cover left over scattered habitations in the state under Mission Bhagiratha irrespective of the cost.
Accordinly a joint inspection was conducted by the undersigned along with EE,MB Grid Division,Adilabad and
Dy.EE&A.E.MB Grid SD Adilabad along with a representative from main grid agency M/s.MEIL for
identifying the isolated habs.

During the Joint inspection 8 Habs (Annexure enclosed) were identified as isolated/scattered in
Adilabad District under SRSP-Adilabad Segment . Executive Engineer stated that out these 8 Habs 4 Habs
were proposed to be covered in orginal estimate i.e. under 20 KL,30 Mts staging OHBR at Punaguda and same
structure was later deleted as Forest department denied permissions stating these are encroached/unauthorized
habitations and remaining 4 habs were identified later which are also encroached habitations as stated by forest
department .Furhter Executive Engineer stated that forest permissions are needed for proceeding for any further
work in these habitations.

Wherein vide reference 2nd cited above,Executive Engineer,MB Grid Division,Adilabad submitted the
estimate of Cost 1130.00 Lakhs for covering the above 8 isolated habs under Mission Bhagiratha as a workslip
under Main Grid works of SRSP-Adilabad segment stating that this amount can be met from savings of Main
Grid Works and same was submitted by this office vide reference 3rd cited above.

This is submitted for favour of further necessary action please.


Enclosure:As above

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy submitted to The Engineer-in-Chief,Mission Bhagiratha Hyderabad for favour of kind information.
Copy submitted to The Chief Engineer-IV,Mission Bhairatha,Hyderabad for favour of Kind information.
Endt.No.02/AEE3/ SE / MB(Adilabad) /Communication/2018-19, Dt:21.01.2019

*****
//A copy of the observations made by Forest Divisional Officer,Nirmal vide
Rc.No.2003/2016/S1,Dated:29.12.2018 on Compliance report for Conditions stipulated in Stage-I approval for
laying pipeline and construction of structures in segment-21/7(Madegaon), is herewith communicated to
Executive Engineer,MB Grid Division,Nirmal with a request to submit the compliance report on observation
made by the Forest Divisional officer,Nirmal at an early date for taking further necessary action please.//

Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad

To:
The Executive Engineer,MB Grid Division,Nirmal.
Copy Submitted to:
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
Endt.No.03/AEE3/ SE / MB(Adilabad) /Communication/2018-19, Dt:19.01.2019

*****
//A copy of the letter received from Executive Engineer,I&CADD, Penganga Project Division, vide
Lr.No.EE/PGP/HD/ADB/DB/HD/PKBR/2018-19/381/m,Dated:11.01.2019 is herewith communicated to
Executive Engineer,MB Grid Division,Adilabad with a request to take further necessary action please//

Sd/- Superintending
Engineer(FAC)
Mission Bhagiratha Circle-Adilabad

To:
The Executive Engineer,MB Grid Division,Adilabad.
Copy to:
The Executive Engineer,I&CADD,Penganga Projecto Division,Adilabad for information.
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.

//Authenticated//

Dy.EE PA to SE,
Mission Bhagiratha Circe,Adilabad

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) Executive Engineer,
SuperintendingEngineer(FAC), Irrigation&CADD Department,
Mission Bhagiratha Circle,Adilabad, Penganga Project Division,
Adilabad Dist. Adilabad

Lr.No.39/AEE3/SE/MB/ Penganga Project/Pipeline/2018-19, Dt: 23.01.2019

Sir
Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District-Lower Penganga Project-Formation of Pippalkoti
Balancing Reservior and it’s allied works near Pippalkoti(V) of Bheempur(M) of Adilabad(D)-Shifting
of Mission Bhagiratha Pipeline-Reg.
*****
Ref: 1.Your office Lr.No.EE/PGP/HD/ADB/DB/HD/PKBR/2018-19/381/,Dated:11.01.2019.
2.T/o.Endt.No.03/AEE3/ SE / MB(Adilabad) /Communication/2018-19, Dt:19.01.2019.
3.Lr.No./AEE/EE/MB Grid(Division Adilabad)/SRSP-ADB/2018-19 ,Dated:22.01.2019 of Executive
Engineer,MB Grid Division,Adilabad.
4.Agreement.No 04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP Circle,Nirmal.
5. Instructions issued by Hon’ble Chief Minister,Governament of Telangana on Dt:17.12.2018.
6.Instructions of Collector&District Magistrate,Adilabad on Dt:27.12.2018.

It is to submit that, vide reference 1st cited above it was requested by your officeto shift Mission
Bhagiratha Pipeline& Valvesat certain locations in Bheempur Mandal stating that Mission Bhagiratha
Pipelines&Valves crossing the proposed Balancing Reservior at Pippalkoti(V) of Bheempur(M) and Coming
under Submergence and Bund portion of above balancing reservoir.
Accordingly,Vide reference 2nd cited above,Executive Engineer,MB Grid Divison,Adilabad was
requested to take further necessary action on the above matter and a report on the same was submitted to this
office vide reference 3rd cited.
In this regard,I am herewith submitting the following points for your kind perusal as submitted by
Executie Engineer,MB Grid Division,Adilabad.

 The above area under consideration falls under SRSP-Adilabad Segment of Mission Bhagiratha
forwhich agreement was concluded on 28.10.2015 and all works nearing completion and No
balanceamountis available to take any further work.Hence an Estimated is herewith submitted

for shifting of pipeline and you are requested kindly to incorporate the same in your estimate of
above project.

 Vide reference 5th cited above, in the review meeting on Mission Bhagiratha, Hon’ble Chief
Minister,Governament of Telangana Instructed that Mission Bhagiratha Water should be supplied
every day to each household without any interruption and informed that any damages or
pilferageof water should be avoided and further reminded that not complaing to above will be
viewed seriously and same was instructed by Collector&District Magistriate,Adilabad during the
review meeting on Dt.27.12.2018.

In this regard you are kindly requested to co-ordinate with Executive Engineer,MB Grid
Division,Adilabad and complete the shifting of pipeline within stipulated time so as to avoid any water
scarcity problems and further complications.

Enclosure:As above

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:

The Executive Engineer,MB Grid Division,Adilabad for information.

Copy submitted to
The Chief Engineer(Projects),I&CADD Department,Adilabad,for favour of kind information.
The Chief Engineer-I,Mission Bhagirath,Hyderabad for favour of kind information.
The Collector &District Magistrate Adilabad for favour of kind information
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) The Forest Divisional Officer,
SuperintendingEngineer(FAC), Nirmal.
Mission Bhagiratha Circle,Adilabad,
Adilabad Dist.

Lr.No.40/AEE3/SE/MB/ /Forest/Compliance Report/2018-19, Dt: 23.01.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment-FCA–Proposals for diversion
of 4.945Ha of forest land in Kawal Tiger Reserve,Nirmal Division-for laying pipeline and
construction of structures in Segment-21/7(Madegaon) for providing safe drinking water to
erstwhile AdilabadDistrict presently Nirmal District under Telangana Drinking Water Supply
Project(TDWSP)-In-Principle(Stage-I) approval accorded-Compliance report on conditions
stipulated in Stage-I-Regarding.
Ref: 1. GO.Rt.No.104,of EFS&T(For.I) Dept,Dt.09.06.2017.
2.Rc.No.2003/2016/S1,Dated.10.09.2018 of Forest Divisional Officer,Nirmal.
3.T/o.Lr.No.13/AEE3/SE/RWSS(Adilabad)/SRSP-ADB/FOREST/Compliance
Report,Dated:23.10.2018
44.Rc.No.2003/2016/S1,Dated:29.12.2018 of Forest Divisional Officer,Nirmal Received on
Dt:17.01.2019
L 5.Lr.No.MB GRID NIRMAL/SRSP Adilabad/Forest/Madegaom/2019,Dated:23.01.2019
*****

It is to submit that,vide reference 4th cited for two conditions it was requested to submit the compliance
report.
Accordingly, I herewith submitting the compliance report for two conditions as desired.

Enclosure:As above
Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:
The Executive Engineer,MB Grid Division,Nirmal for information.
Copy Submitted to:
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

The compliance report for observation made by Forest Divisional officer,Nirmal for the Segment-21/7
(Madegaom) is submitted to the District Forest Officer, Nirmal Districtis as Follows:
S.No. Description of the Condition Compliance
1 Publish the entire forest clearances granted in The Telangana Drinking Water Supply Corporation
verbatim along with the condition and safe- Ltd., Hyderabad has published the Obtained forest
guards imposed by the central Government in clearances for the segment-21/7(Madegaom) in
two widely circulated daily news paper one in Namaste Telangana Telugu(vernacular) daily news
Vernacular language and the other in English paper & Indian Express English daily news paper
granted to the project proponent for the use of on 21.09.2018 and the published copies are
forest land for the non-forest purposes. herewith enclosed for submission.
2 The copies of the forest clearance should also be The forest clearance was submitted & made
submitted to the heads of local bodies, available to display for 30 days in the offices of the
Panchayats and Municipal bodies by the project government, Panchayats and local bodies under
proponents in addition to the relevant offices of segment-21/7 (Madegaom).
the government who in turn has to display the
same for 30days from the date of receipt of this
reference.

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Circular Memo No.02/AEE3/DEE-II/MB/Bulk Water Connections/2018-19,Dated:25.01.2019

Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment-Procedure to be adopted for


Bulk Water Connections-Reg.
Ref: 1.Lr.No.MB GRID NIRMAL/AEE/HF-Mudgal/Bulk connection/2019,Date:23.01.2019 of
Executive Engineer,MB Grid Division,Nirmal.
. 2.Circular Memo No.AEE2/DEE(Plg)/TDWSP/Water Supply Connections /Industries /9809 /
2017,Dt:26.04.2017 of Engineer-in-Chief,RWS&S,Hyderabad.
3.Lr.No.AEE/DEE(Designs)/TDWSP/O&M and Revenue/001/2017-18,Dated:15.07.2017 of
Engineer-in-Chief,RWS&S,Hyderabad.
4.Circular Memo.No.AEE2/DEE(Plg)/TDWSP/Water Supply/Connections/Industries/980/2017,
Dated:24.12.2018 of Engineer-in-Chief,RWS&S,Hyderabad.
****

Through the reference 2ndcited, instructions were issued not to approve any Bulk Water
connections/Tapings on transmission pipeline without the approval by the authorized personal from TDWSCL
and to submit the all the Bulk Supply Connection proposals through the concerned Superintending Engineers to
the Concerned Chief Engineers with a feasibility report for further action.

Further through the reference 3rd cited ,Guidelines for Providing Bulk Non domestic,
Commercial and Industrial water supply connections &Tariffs to be fixed under Mission Bhagiratha were
submitted to the Government. Till further guidelines, presently this procedure may be followed.

Again vide reference 4th cited Instructions were issued not to approve any Bulk Water
connections/Tapings on transmission pipeline including gracious connections(All Government institutions such
as govt hospitals,govt educational institutions,govt hostels, police stations, religious places and old age homes
e.t.c)and and any discrepancy in this regard will be viewed seriously and the connections with in the village
premises from distribution lines may be served by the concerned Gram Panchayath only.
In addition , it was further instructed to strictly verify that the consumer shall apply for Bulk
connections through Mission Bhagiratha Portal only.

In this regard all the Executive Engineers,Dy.Executive Engineers under this circle are
hereby requested to follow the guidelines/instructions issuedthrough the references above .

Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad

To:
The Exeuctuive Engineer,MB Intra Division Adilabad/Nirmal.
The Executive Engineer,MB Grid Division,Adilabad/Nirmal.
All the Dy.Executive Engineers,MB Grid&Intra through their concerned Executive Engineers.
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.41/AEE3/SE/MB/ NEWS PAPER/ADEVERSE CLIPPINGS/2018-19, Dt: 31.01.2018

Sir,

Sub: Mission Bhagiratha Circle-Adilabad-Adverse News Published in Eenadu News Paper on


Date:02.01.2019-With Caption “Asampurtiga Panulu..Abaddhala Lekkalu ”-
Rejoinder&Detailed Report-Submitted-Reg.

Ref: 1.Memo.No.01/AE V/DEE II/CE-IV/PAPER CLIPPINGS/2018-19,Dated:18.01.2019 of Chief


Engineer-IV,Mission Bhagiratha,Hyderabad
2. Memo.No.02/AE V/DEE II/CE-IV/PAPER CLIPPINGS/2018-19,Dated:29.01.2019 of Chief
Engineer-IV,Mission Bhagiratha,Hyderabad
*****
It is to submit that,Adverse News was published in EenaduNews Paper on Mission Bhagiratha works
of NirmalDistrict on Date:02.01.2019,With a caption “Asampurtiga Panulu..Abaddhala Lekkalu”.

In this regard, I am herewith submitting the followingpoints for your kind perusal.

A.Main Grid Works:

 Status as on 02.01.2019

 In Nirmal District, out 671 Habitations,468 Habitations (Nirmal Constituency-209,Mudhole


Consitituency-248,Khanapur Constituency-11) are under the jurisdiction of this circle with regard
to the Bulk/Daily supply.

 As of 02.01.2019, It was reported in MB Online portal


(http://missionbhagiratha.telangana.gov.in)that All 468 Habitations were Bulk Supplied and 453
Habitations were daily supplied with MB water (Mandal wise Annexure Enclosed) and same report was
submitted by this office on Dt:27.12.2018 through email (to ce-nzb-rwss@telangana.gov.in), for
Review meeting by Secretary to Government on Dt:28.12.2018.

 Upon field verification by the undersigned above bulk and daily supply report was found true.

 Hence,It is to submit that The News which was published in Eenadu News Paper isbaseless
with respect to Bulk/Daily Supply under this circle.

 Status as on 31.01.2019

 It is to submit that at present Out of 468 Bulk supplied habs about 454 habs are being supplied with MB
Water daily i.e 14 Habs are pending with daily supply(Nirmal Constituency-9,Mudhole Constituency-
5)as on 31.01.2019.

 In Mudhole constituency out of 5 Habs pending,1 habitation namely Pipree of Mudhole Mandal merged
with Bhainsa ULB and for the same the work is in progress under PH Department. For another 4
habitations about 4 Kms of pipeline was damaged in R&B road extension and the repair work for the
same is in progress(Photo enclosed).

 In Nirmal Constituency.For 9 Pending habs pending the source is Exisitng CPWS scheme
namely “CPWS Scheme to Nirmal and other Habitations”.The daily supply for these habs is
pending due to repair work of motors at Kankanpur sump and the same work is in progress(Photo
enclosed).
 An annexure for Bulk and Daily status of Nirmal District under this circle as on 31.01.2019 is
herewith enclosed.

This is submitted for favour of kind information and further necessary action please.

Yours faithfully,

Superintending Engineer(FAC),
Mission BhagirathaCircle, Adilabad.

Copy submitted to:

The Engineer-in-Chief,Mission Bhagiratha ,Hyderabad for favour of kind information.

The Collector &District Magistrate ,Nirmal for favour of kind information.

Reminder-V
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.12/AEE3/DEE-II/BSNL/Cable Damages/2018-19,Dated:01.02.2019

Sub: Mission Bhagiratha Circle-Adilabad- BSNL-Damages to underground cables-Recovery dues-


Detailed Report-Req-Reg.

Ref:1. Lr.No.GMTD/ADB/Plg/Way Leave Permissions/2010-19/Vol.I/67,Dated:02.07.2018 of the


General Manager,BSNL,Adilabad.
2.T/o Memo No.01/AEE3/DEE-II/BSNL/Cable Damages/2018,Dated:12.07.2018
3.T/o Memo No.03/AEE3/DEE-II/BSNL /Cable Damages/2018,Dated:07.09.2018
4.T/o Memo No.05/AEE3/DEE-II/BSNL /Cable Damages/2018,Dated:08.10.2018
5.T/o.Memo No.06/AEE3/DEE-II/BSNL/Cable Damages/2018,Dated:15.11.2018
6.T/o.Memo No.08/AEE3/DEE-II/BSNL /Cable Damages/2018,Dated:20.12.2018

****

The immediate personal attention of the Executive Engineer,MB Grid Division,Adilabad is


invited to the subject and references cited,where in it was requested to furnish the detailed report on damages
done to BSNL underground cables(both Copper&OFC).But no information is received by this office even after
a lapse 6 months.
Therefore,the Executive Engineer,RWS&S,MB Grid Division,Adilabad is once again
requested to furnish the detailed report on damages to BSNL underground cables(Both Copper&OFC) to this
office immediately for taking further necessary action.

Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Nirmal.
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.41/AEE1/SE/MB/ INTRA/OHSR’S/REMOTE AREAS/2018-19, Dt: 17.01.2019

Sir,

Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District-Intra Village Works-Construction of


OHSR’s-In remote&Hilly areas-Submission of observed data-Reg.

Ref: 1.Memo.No:AEE/DEE-II/MB/OHSR/Remote Hilly Area/Extra Allowance/2019,Dated:16.01.2019


Of Chief Engineer-I,Mission Bhagiratha,Hyderabad.

*****
It is to submit that,vide reference cited above The Chief Engineer-I has instructed to submit the
observed data for construction of OHSR’s(8 No’s) in remote & hilly areas of Adilabad District.

Accordingly,I am herewith submitting the observed data for construction of OHSR’s in remote &
Hilly areas for taking further necessary action.

Enclosure:As above

Yours faithfully,

Superintending Engineer(FAC),
Mission BhagirathaCircle, Adilabad.
Copy to:
The Executive Engineer,MB Intra Division,Adilabad for information.
Copy Submitted to:
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's) Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.41/AEE1/SE/MB/ INTRA/OHSR’S/REMOTE AREAS/2018-19, Dt: 17.01.2019

Sir,

Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District-Intra Village Works-Construction of


OHSR’s-In remote&Hilly areas-Submission of observed data-Reg.

Ref: 1.Memo.No:AEE/DEE-II/MB/OHSR/Remote Hilly Area/Extra Allowance/2019,Dated:16.01.2019


Of Chief Engineer-I,Mission Bhagiratha,Hyderabad.

*****
It is to submit that,vide reference cited above The Chief Engineer-I has instructed to submit the
observed data for construction of OHSR’s(8 No’s) in remote & hilly areas of Adilabad District.

Accordingly,I am herewith submitting the observed data for construction of OHSR’s in remote &
Hilly areas for taking further necessary action.

Enclosure:As above

Yours faithfully,

Superintending Engineer(FAC),
Mission BhagirathaCircle, Adilabad.

Copy to:
The Executive Engineer,MB Intra Division,Adilabad for information.
Copy Submitted to:
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) All The District Officers/District HODs,
SuperintendingEngineer(FAC), Adilabad District.
Mission Bhagiratha Circle,Adilabad, .
Adilabad Dist.

Lr.No.42/AEE3/SE/MB/WATER CONNECTIONS/2018-19, Dt: 11.02.2019

Sir,

Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District-Water Connections under Mission


Bhagiratha-Reg..

Ref: :1) GO.Ms.No. 17 of PR&RD Department ,Dated:30.01.2015.


2) Circular Memo.No.AEE2/DEE(Plg)/TDWSP/Water Supply Connections/Industries/
9809/2017,Dated:26.04.2017 of Engineer-in-Chief,RWS&S,Hyderabad.
3) Circular Memo.No.AEE2/DEE(Plg)/TDWSP/Water Supply Connection /Industries/
9809/2017,Dated:24.12.2018 of Engineer-in-Chief,RWS&S,Hyderabad.

*****

It is to submit that, this office has been receiving many request for providing water connections under
Mission Bhagiratha from various institutions/offices/industries .`

In this regard, it is to inform that, as per the Government Orders issued vide reference 1st cited above “
The Telangana Drinking Water Supply Corporation Limited”(TDWSCL)has to supply drinking water at
entry points of rural/& urban areas and maintain drinking water projects outside GP/ULB’s and the connection
with in the village premises from distribution lines may be served by the concerned gram panchayath only..
Hence, without the approval of the authorized personel from TDWSCL ,this office can not execute any water
connection on transmission line as requested.

In this regard, all the District officers of Adilabad District are hereby requested to see that all the
offices/institution under their jurisidiction apply for the water connection under Mission Bhagiratha through
Mission Bhagiratha Portal(http://www.missionbhagiratha.telangana.gov.in) for taking further necessary action.
The detailed procedure is herewith enclosed.

Encl:Bulk water request user manual.

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
Executive Engineer,MB Grid/Intra Division,Adilabad for information and necessary action.
Copy Submitted to:
The Collector&District Magistrate,Adilabad for favour of kind information
The Project of Officer,ITDA,Utnoor, for favour of kind information
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) All The District Officers/District HODs,
SuperintendingEngineer(FAC), Nirmal District.
Mission Bhagiratha Circle,Adilabad, .
Adilabad Dist.

Lr.No.43/AEE3/SE/MB/WATER CONNECTIONS/2018-19, Dt: 11.02.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-Nirmal District-Water Connections under Mission
Bhagiratha-Reg.

Ref: :1) GO.Ms.No. 17 of PR&RD Department ,Dated:30.01.2015.


2) Circular Memo.No.AEE2/DEE(Plg)/TDWSP/Water Supply Connections/Industries/
9809/2017,Dated:26.04.2017 of Engineer-in-Chief,RWS&S,Hyderabad.
3) Circular Memo.No.AEE2/DEE(Plg)/TDWSP/Water Supply Connection /Industries/
9809/2017,Dated:24.12.2018 of Engineer-in-Chief,RWS&S,Hyderabad.

*****

It is to submit that, this office has been receiving many request for providing water connections under
Mission Bhagiratha from various institutions/offices/industries .`

In this regard, it is to inform that, as per the Government Orders issued vide reference 1st cited above “
The Telangana Drinking Water Supply Corporation Limited”(TDWSCL)has to supply drinking water at
entry points of rural/& urban areas and maintain drinking water projects outside GP/ULB’s and the connection
with in the village premises from distribution lines may be served by the concerned gram panchayath only..
Hence, without the approval of the authorized personel from TDWSCL ,this office can not execute any water
connection on transmission line as requested.

In this regard, all the District officers of Nirmal District are hereby requested to see that all the
offices/institution under their jurisidiction apply for the water connection under Mission Bhagiratha through
Mission Bhagiratha Portal(http://www.missionbhagiratha.telangana.gov.in) for taking further necessary action.
The detailed procedure is herewith enclosed.

Encl:Bulk water request user manual.

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
Executive Engineer,MB Grid/Intra Division,Nirmal for information and necessary action.
Copy Submitted to:
The Collector&District Magistrate,Nirmal for favour of kind information
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Memo No.12/AEE3/DEE-II/MB Portal/Daily Supply/2018-19,Dated:11.02.2019

Sub: Mission Bhagiratha Circle-Adilabad-MB Portal-Daily Water Supply-Updation-Reg.

Ref:1. T/o.Memo No.02/AEE3/DEE-II/MB Portal/Daily water Supply/2018,Dated:25.07.2018


****

In continuation to the reference cited,it is brought to the notice of undersigned that daily
water supply status of few mandals is not being updated in Mission Bhagiratha portal
(http://missionbhagiratha.telangana.gov.in/) even after supplying water, leading to wrong projection of status of
daily supply. In this regard all the Engineers under this circle are once again instructued to see that all the
habitations for which daily supply is made are updated in MB portal everyday and it becomes a part of their day
to day activites.Any discrepency in this regard will be viewed seriously and appropriate action will be initiated
against the concerened.

Further,all are remainded that the same report is shared with CMO dashboard for regular
review.
.

Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Nirmal/Adilabad.
The Executive Engineer.MB Intra Division,Nirmal/Adilabad
All the Dy.Executive Engineers/Assistant Executive Engineers/Assistant Engineers through concerned
Executive Engineers.
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

Endt.No.04/AEE3/ SE / MB(Adilabad) /Communication/2018-19, Dt:11.02.2019

//A copy of the Memo.No.02/AE IV/DEE II/CE-IV/PAPER CLIPPING/2018-19,Dated:29.01.2019, of


Chief Engineer-IV,Mission Bhagiratha,Hyderabad is herewith communicated to Executive Engineer,MB
Grid/Intra Divisions,Nirmal with a request to submit the Rejoinder&detailed report on Bulk,Daily Supply and
present status of Intra village works in the habitations in their jurisidiction.//
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad

To:
The Executive Engineer,MB Grid/Intra Divisions,Nirmal.
Copy Submitted to:
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE EXECUTIVE ENGINEER, MB GRID DIVISION, ADILABAD

From, To,
Sri P.Gopichand,B.E Executive Engineer,
Executive Engineer(FAC) MB Grid Division,Nirmal.
MB Grid Division,Adilabad, Nirmal Distrct.
Adilabad Dist.

Lr.No.01/AEE3/EE/MB/FOREST PAYMENT/2018-19, Dt: 11.02.2018

Sir,
Sub: MB Grid Division-Adilabad-Submission of 21/8(Sirichelma) Wildlife segment forest Bills-
As per revised demand notice from FDPT Utnoor-Reg..
Ref: :1.PCCF,TS HYD,Rc.No.12136/2018/WL-1,Dt:04.12.2018

*****
With reference to the subject cited, FDPT Utnoor issued revised demand notice for 1.192 Ha of
Utnoor(FDPT) forest division under 21/8(Sirichelma) WL segment.\

Hence,I am herewith submitting the respective bills of 21/8(Sirichelma) WL segment for further
process of payment.

Encl: 1.MB.No.1072/TDWSP/Nirmal/2016.
2.Demand notice received from FDPT Utnoor.

Yours faithfully,

Executiver Engineer,
MB Grid Division,Adilabad.

Copy Submitted to:


The Superintending Engineer,Mission Bhagiratha,Adilabad Circle for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.13/AEE3/DEE-II/ADB/KB-ASFBD/2018-19,Dated:11.02.2019

Sub: Mission Bhagiratha Circle-Adilabad--Adilabad District-KB-Asifabad Segment-Bulk Supply-


Jurisidiction-Reg.

Ref:1. Lr.No.AEE1/TDWSP/Tap/Ashram,Dated:11.02.2019 of Executive Engineer,MB Grid


Division,Asifabad.
2.G.O.Ms.No.38,Dated:05.06.2017 of PR&RD Department.
3.Circular Memo.No.AEE2/DEE(Plg)/TDWSP/Water Supply Connection /Industries/
9809/2017,Dated:24.12.2018 of Engineer-in-Chief,RWS&S,Hyderabad.
****

The immediate personal attention of Executive Engineer.MB Grid Division,Asifabad is drawn to the
reference 2nd cited and he is requested to go through instructions issued time to timess.
.
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Asifabad.
Copy To:
The Superintending Engineer,Mission Bhagiratha Circle,Adilabad for information and necessary action
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.14/AEE3/DEE-II/GRID/PRICE VARIATIONS/2018-19,Dated:13.02.2019

Sub: Mission Bhagiratha Circle-Adilabad-Main Grid Works-SRSP-Adilabad Segment-Price


Variation of Pipes-Certain Remarks-Called for-Reg.

Ref:1. Lr.No.07/MB GRID NIRMAL/AEE/PV/Phase-II/2019,Dated:08.02.2019 of Executive


Engineer,MB Grid Division,Nirmal.
2.G.O.Rt.No.1771,Dated 26.11.2008 of PR&RD Department.
3.Memo.No.AEE/DEE/TDWSP(Plg)/Price Variations/2015,Dated:09.01.2016 of Engineer-in-
Chief,RWS&S Hyderabad.
4.Proc.No.ENC/IW/P&M/EE/DEE-2/AEE.5/GST/2018-19/Vol-II,Dated:28.08.2018 of
Engineer-in-Chief(AW),I&CAD Department and Chairman of Board of Chief Engineers.
5.Minutes of HODs/ENCs level meeting with all Engineering Dept held on 20.08.2018
****
The immediate personal attention of Executive Engineer.MB Grid Division,Nirmal is invited to the reference
1st cited, wherein in during the preliminary scrutiny of the Price adjustment calculation submittied for DI&MS
Pipes from RA-17 to RA-28 the following observations are made.

1.In the price variation formulae for DI Pipes the factor “M” is not as per IS 8329:1994
As instructed in reference 2nd cited.

2.In DI Price variation formulae the factor “CPI2” is price of pig iron at the time of delivery i.e
Date of supply&delivery recorded in concerened Measurement Book as instructed in reference
2nd&3rd cited ,but is obereved that the month of invoice was considered.

3.for Mild steel Pipes,the rates of raw material prevailing 1 month before to the QC inspection
should be considered as instructed in reference 3rd cited ,but it is observed that the month of
invoice isconsidered.

4.Further the Embedded tax component from MS Plates estimated rates is not deducted.

In this regard Executive Engineer,MB Grid Division,Nirmal is hereby request to attend above remarks
and submit the information at the earliste to take further necessary action.Further he is requested to verify that
the above observations are followed in previous bills and report compliance.

Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Nirmal.
Copy To:
The Executive Engineer,MB Grid Division,Adilabad for necessary action
Copy Submitted to:
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
PROCEEDINGS OF SUPERINTENDING ENGINEER,MISSION BHAGIRATHA CIRCLE-ADILABAD
Present:D.Venkateshwarlu,M.E,(Hon's)
Procs:No. 01/AEE3/DEE-II/Grid/Price Variations/2018-19,Dated:23.02.2019

Sub :Mission Bhagiratha Circle–Adilabad-SRSP-Adilabad Segment-“Providing Drinking Water to Habitations in


SRSP-Adilabad segment in Adilabad district “Est.Cost 1530.00 Cr of SE TDWSP, Adilabad Dist including
Operation and maintenance for 10 years-Price vaiation for POL-Accorded-Reg.
Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No 04/2016-17,Dated:04/2016-17 of Superintending Engineer,TDWSP Circle,Nirmal.
3) Lr.No.MB GRID NIRMAL/AEE/SRSP ADB/POL/Phase-II/2019,Dated:13.02.2019 of Executive Engineer,
MB Grid Division,Nirmal.
4) Memo.No.AE2/DEE Plg/POL/2017,Dated:10.02.2018 of Chief Engineer-IV,TDWSP,Hyderabad.
5) G.O.Ms.No.35 TR& B(RI) Department,Dated:28.02.2006
6)GO MS No.292 PR&RD(Progrs-II) Department,Dated:28.07.2006
7)GO MS No.94 TR&B(RI) Department,Dated:28.02.2006
8)GO MS No.252 ,TR&B(RI) Department,Dated:28.08.2008

****
ORDER:
Vide reference 3rd cited above ,Executive Engineer,MB Grid Division,Nirmal has submitted the price
variation proposals for POL under the work “-“Providing Drinking Water to Habitations in SRSP-Adilabad
segment in Adilabad district “Est.Cost 1530.00 Cr of SE TDWSP, Adilabad Dist including Operation and
maintenance for 10 years under Telangana Drinking Water Supply Project(TDWSP).

Accordingly,In view of the directions issued by Chief Engineer-IV,TDWSP,Hyderabad vide reference 4th
cited and as per clause no 44.6 of agreement conditions the overall price adjustment for usage of fuel and
lubricants for Runnig Account Bills 1 to 28 of above work is herewith approved for an amount of
Rs.15,36,10,027/-(Rupees Fifteen Crores Thirty Six Lakhs Ten Thousand Twenty Seven Rupees only) keeping the
responsbility on Executive Engineer,MB Grid Division,Nirmal.

Further Executive Engineer,MB Grid Division,Nirmal shall ensure that any deviations on above approved
amount is found the same shall be deducted from the subsequent bills of agency.

Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Nirmal.
Copy Submitted To:
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&SCIRCLE, ADILABAD

From, To,
Sri USN Murthy, M Tech, MBA, LLM. The Project Director,
SuperintendingEngineer, WAPCOS,AC Guards,
RWS& S-Circle,Adilabad, Hyderabad,Telangana-500004
Adilabad Dist.

Lr.No.05/AEE3/ SE / RWSS(Adilabad) / SRSP-ADB /Designs Dt:15.02.2018

Sir,

Sub:- RWS&S Circle-Adilabad –“Providing Drinking Water to Habitations in SRSP-Adilabad


Segment in Adilabad District”-Vetting of Designs and Drawings-Requested-Reg. I am

Ref:- 1. Agg.No.Lr.No.AEE1/DEE TDWSP plg2/RWS&S/2015 dt.3.7.2015.


2. G.O.Ms.No.47, PR&RD (RWS-IV) Dept., dt.01.06.2015.
3. G.O.Ms.No.50, PR&RD (RWS-IV) Dept., dt.19.06.2015.
With reference to the subject and vide reference cited above I am herewith submitting the following
designs and drawings for vetting.
1.Design report for Sluice Valve chamber for 500 mm dia DI Pipe line.
2.Design report for Sluice Valve chamber for 450 mm dia DI Pipe line.
3.Design report for Sluice Valve chamber for 400 mm dia DI Pipe line.
4.Design report for Sluice Valve chamber for 350 mm dia DI Pipe line.
5.Design report for Sluice Valve chamber for 300 mm dia DI Pipe line.
6.Design report for Sluice Valve chamber for 250 mm dia DI Pipe line.
7.Design report for Sluice Valve chamber for 200 mm dia DI Pipe line.
8.Design report for Sluice Valve chamber for 150 mm dia DI Pipe line.
9.Design report for Sluice Valve chamber for 100 mm dia DI Pipe line.
10.Design report for Butterfly Valve(600 mm Dia) Chamber for Pressure Main Of 930 mm dia.
11.Design report for pipe line steel bridge from Adilabad Gutta to Bhoraj X roads
At DI Pipe line of 500 mm dia@Ch.11.385 Km-11.570 Km.
12.Hydraulic Design for Clear water pumping mains –Jandaguda X rd sumo to GLBR at Chinchughat
13.Hydraulic Design for clear water pumping mains-Daheguda Sump to Molalgutta 40 KL OHBR.

Hence it is requested to vet the above designs and drawings as per agreement conditions at an
early date and communicate.

Encl: As above

Yours Faithfully,

Superintending Engineer,
RWS&S,Adilabad-Circle.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) The Project Director,
SuperintendingEngineer(FAC), WAPCOS,AC Guards,
Mission Bhagiratha Circle,Adilabad, Hyderabad,Telangana-500004
Adilabad Dist.

Lr.No.44/AEE3/SE/MB/DESIGNS /2018-19, Dt: 19.02.2019

Sir,
Sub:Mission Bhagiratha Circle–Adilabad-SRSP-Adilabad Segment-“Providing Drinking Water to
I am
Habitations in SRSP-Adilabad segment in Adilabad district “Est.Cost 1530.00 Cr of SE TDWSP,
Adilabad Dist including Operation and maintenance for 10 years-Vetting of Designs and
Drawings -Requested-Reg.

Ref:- 1. Agg.No.Lr.No.AEE1/DEE TDWSP plg2/RWS&S/2015 dt.3.7.2015.


2. G.O.Ms.No.47, PR&RD (RWS-IV) Dept., dt.01.06.2015.
3. G.O.Ms.No.50, PR&RD (RWS-IV) Dept., dt.19.06.2015.
It is to submit that,with reference to the subject and references cited above I am herewith
submitting the following designs and drawings for vetting.
1.Typical Design and Drawings of Security Room 4M*3M Size.
2.Typical Design and Drawings of Staff Quarters.
3.Typical Design and Drawings of Watchman Quarters .
4.Design and Drawings of Sump 40 KL at Thandra(V),Mamda(M).
5.Design and Drawings of Sump, 20 KL at Sakriyanaik Thanda(V),Neredigonda(M).
6.Design and Drawings for GLBR of 20 KL at Umarda-G(V),Bazarhatnoor(M).
7.Design and Drawings for GLBR of 40 KL at Dharmapur(V),Gudihatnoor(M).

Hence it is requested sir to vet the above designs and drawings as per agreement conditions at an
early date and communicate.

Encl: As above

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy Submitted To:


The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
PROCEEDINGS OF SUPERINTENDING ENGINEER,MISSION BHAGIRATHA CIRCLE-ADILABAD
Present:D.Venkateshwarlu,M.E,(Hon's)
Procs:No. 02/AEE3/DEE-II/Grid/Price Variations/2018-19,Dated:22.02.2019

Sub :Mission Bhagiratha Circle–Adilabad-SRSP-Adilabad Segment-“Providing Drinking Water to Habitations in


SRSP-Adilabad segment in Adilabad district “Est.Cost 1530.00 Cr of SE TDWSP, Adilabad Dist including
Operation and maintenance for 10 years-Price vaiation for MS,DI&BWSC-Accorded- Reg.
Ref: 1) Go.Rt.No.394,PR&RD((RWS-IV),Dated:23.06.2015
2) Agreement.No 04/2016-17,Dated:04/2016-17 of Superintending Engineer,TDWSP Circle,Nirmal.
3) Lr.No.07/MB GRID NIRMAL/AEE/PV/Phase-II/2019,Dated:08.02.2019 of Executive Engineer,
MB Grid Division,Nirmal.
4) Lr.No.07/MB GRID NIRMAL/AEE/SRSP ADB/POL/Phase-II/2019,Dated:13.02.2019 of Executive
Engineer,MB Grid Division,Nirmal.
5) G.O.Ms.No.35 TR& B(RI) Department,Dated:28.02.2006
6)GO MS No.292 PR&RD(Progrs-II) Department,Dated:28.07.2006
7)GO MS No.94 TR&B(RI) Department,Dated:28.02.2006
8)GO MS No.252 ,TR&B(RI) Department,Dated:28.08.2008
9) G.O.Rt.No.1771,PR&RD(RWS-I) Department,Dated:26.11.2008.
****
ORDER:
Vide reference 3rd cited above ,Executive Engineer,MB Grid Division,Nirmal has submitted the price
variation proposals for DI,MS&BWSC Pipes under the work “-“Providing Drinking Water to Habitations in
SRSP-Adilabad segment in Adilabad district “Est.Cost 1530.00 Cr of SE TDWSP, Adilabad Dist including
Operation and maintenance for 10 years under Telangana Drinking Water Supply Project(TDWSP).

Accordingly,as per clause no 44.6 of agreement conditions the overall price adjustment for MS,DI&BWSC
Pipes for Runnig Account Bills 17 to 28 of above work is herewith approved for an amount of Rs.8,71,06,812/-
(Rupees Eight Crores Seveny One Lakhs Six thousand Eight Hundered Twelve Rupees Only) keeping the
responsbility on Executive Engineer,MB Grid Division,Nirmal.

Further Executive Engineer,MB Grid Division,Nirmal shall ensure that any deviations on above approved
amount is found the same shall be deducted from the subsequent bills of agency .

Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Nirmal.
Copy Submitted To:
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) Executive Engineer,
SuperintendingEngineer(FAC), Irrigation&CADD Department,
Mission Bhagiratha Circle,Adilabad, Penganga Project Division,
Adilabad Dist. Adilabad

Lr.No.45/AEE3/SE/MB/ Penganga Project/Pipeline/2018-19, Dt: 01.03.2019

Sir
Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District-Lower Penganga Project-Formation of Pippalkoti
Balancing Reservior and it’s allied works near Pippalkoti(V) of Bheempur(M) of Adilabad(D)-Shifting
of Mission Bhagiratha Pipeline-Reg.
Ref: 1.Agreement.No 04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP Circle,Nirmal.
2.T/o.Lr.No.39/AEE3/SE/MB/Penganga Project/Pipeline/2018-19,Dt:23.01.2019.
3.Your office Lr.No.EE/PGP/DB/HD/P.K/M.B/043/2018-19/443/SE,Dated:22.02.2019
4.Lr.N0.02/AEE1/EE/Grid/ADB/I&CAD/Estimate/2019,Dated:28.02.2019 of Executive Engineer,
MB Grid Division,Adilabad
*****
In compliance to the reference 3rd cited above,it is to submit that, as informed earlier the work
“Providing Drinking Water to Habitations in SRSP-Adilabad segment in Adilabad District “Est.Cost
1530.00 Cr of SE TDWSP, Adilabad Dist including Operation and maintenance for 10 years is nearing
completion and no balance amount is available to take up any work .
Further,In continuation to reference 2nd cited I am herewith submitting the revised estimated of cost
41.80 Lakhs for taking further necessary action.

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:
The Executive Engineer,MB Grid Division,Adilabad for information.
Copy submitted to
The Chief Engineer(Projects),I&CADD Department,Adilabad,for favour of kind information.
The Chief Engineer-I,Mission Bhagirath,Hyderabad for favour of kind information.
The Collector &District Magistrate Adilabad for favour of kind information
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.46/AEE3/ SE / RWSS(Adilabad)/ SRSP-ADB/O&M ESTIMATE/2018-19, Dt: 07.03.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – “Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years-O&M Estimate-
Submitted-Approval-Req-Reg.

Ref: 1)Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal Circle.


2) Lr.No.AEE1/MB GRID NIRMAL/SRSP ADILABAD SEGMENT/PH-II/O&M Estimate/2018
,Dt:07.03.2019 of Executive Engineer,MB Grid Division,Nirmal.
3) Lr.No.AEE1/MB GRID NIRMAL/SRSP ADILABAD SEGMENT/PH-II/WE-II/2018,Dt:07.03.2019
Of Executive Engineer,MB Grid Division,Adilabad.

*****
It is to submit that , vide reference 2nd& 3rd cited above Executive Engineer,MB Grid
Division,Nirmal&Adilabad have submitted the O&M Estimate for the work “Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad
District Including Operation & Maintenance for 10 Years.

Hence, same is herewith submitted and the Chief Engineer-IV,Mission Bhagiratha,Hyderabad is


requested to kindly approve the same.

Encl:O&M Estimate

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:
The Executive Engineer,MB Grid Division,Adilabad&Nirmal for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.15/AEE3/DEE-II/GRID/ISOLATED HABITATIONS /2018-19,Dated:08.03.2019

Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District-Isolated Habitations-Certain


Instructions-Reg.

Ref:1.Minutes of Review Meeting By Hon’ble Chief Minsiter,Governament of Telangana on


Dt:17.12.2018.
2.Minutes of Review Meeting by Engineer-in-Chief ,Mission Bhagiratha on Dt:25.02.2019.
3.Oral Instructions of Chief Engineer-I,Mission Bhagiratha,Hyderabad on Dt:02.03.2019.

****

In continuation to the reference 1&2nd cited and as per the instructions of Chief Engineer-
I,Mission Bhagiratha,Hyderabad ,the Executive Engineer,MB Grid Division,Adilabad Division is hereby
directed to conduct a joint inspection along with the Executive Engineer,MB Grid Division Asifabad for
identifying the list of isolated habitations of SRSP-Adilabad Segment in Adilabad District which can be covered
through gravity from KB-Asifabad segment and vice versa and report to this office by 10.03.2019 postively for
taking further necessary action.

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

To:
The Executive Engineer,MB Grid Division,Adilabad
Copy to:
The Executive Engineer,MB Grid Division,Asifabad for information and necessary action.
The Superintending Engineer,Mission Bhagiratha Circle,Mancherial for information.
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.16/AEE3/DEE-II/GRID/DAILY SUPPLY /2018-19,Dated:11.03.2019

Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District-Daily Supply –Certain Instructions-Reg.

Ref:1.Review Meeting on Heat wave by Collector&District Magistrate,Adilabad on Dt:07.03.2019.


****
With reference to the subject and reference cited,it is to inform that during the review meeting with
Collector&District Magistrate ,Adilabad on Dt:07.03.2019, it was informed that many complaints are being
receieved from newly elected sarpanches regarding daily supply.

In this regard,The Executive Engineers,MB Grid/Intra Division,Adilabad are hereby requested to


submit an album of photos with sarpanches releasing water to their concerned habitations, for all habitations in
their jurisidiction positively by 13.03.2019 for taking further necessary action.

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

To:
The Executive Engineer,MB Grid/Intra Division,Adilabad
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Superintending Engineer,
SuperintendingEngineer(FAC), MB Circle-Mancherial
Mission Bhagiratha Circle,Adilabad,
Adilabad Dist.

Lr.No.47/AEE3/ SE / RWSS(Adilabad)/ SRSP-ADB/PHASE-I/2018-19, Dt:28.01.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad- Phase-I SRSP-Adilabad Segment –“Providing Drinikng Water
Grid to Adilabad,Boath and Nirmal Assembly Constituencies in Adilabad District” Est.Cost.Rs.248 Crs-
-Working Estimate-V-Approved Copy Communicated-Reg.

Ref: 1) GO.RT.NO:82 of PR&RD (RWS IV) Dept.,Dt.07.02.2015.


2) Agreement No:01/2015-16,Dated:09.04.2015 of SE,RWS&S ,Adilabad
3) Memo.No.AE-IV/DEE-II/MB-IV/SRSP Adbd-Ph-I/Working Estimate-V/2019,Dated:10.01.2019
Of Chief Engineer-IV,MB,Hyderabad.
*****
It is to submit that, the Working Estimate-V for the work –“Providing Drinikng Water Grid to
Adilabad,Boath and Nirmal Assembly Constituencies in Adilabad District” Est.Cost.Rs.248 Crs is approved by
Chief Engineer-IV,MB,Hyderabad. Hence a copy of the same along with Working Estimate-IV and its
agreementis herewith communicated and it is requested to take further necessary action please.

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Enclosure:
1.Working Estimae-V(True Copy)
2.Working Estimate-IV(True Copy) and Its agreement(Original Copy)

Copy to:
The Executive Engineer,MB Grid Division,Nirmal for information.
Copy submitted to
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.

Most Urgent By E-mail


GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD
Memo No.17/AEE3/DEE-II/MB PORTAL/USER ID /2018-19,Dated:14.03.2019

Sub: Mission Bhagiratha Circle-Adilabad-MB Portal-User IDs Creation-Reg.

Ref: Arising
****
All the Executive Engineers of MB Grid Divisions& Intra Divisions noted in the address entry are requested to
send the details of Newly recruited AEE’s details in the proforma enclosed for generation of User Ids in MB
Portal and for taking further necessary action.

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Enclosure:As above

To:
The Executive Engineer,MB Grid/Intra Division,Adilabad
The Executive Engineer,MB Grid/Intra Division,Nirmal
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderbad
Adilabad Dist.

Lr.No.48/AEE3/ SE / RWSS(Adilabad)/ GRID/Pipeline Shifting/2018-19, Dt: 14.03 .2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad- SRSP-Adilabad Segment “Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years-R&B Road widening
from Deepaiguda village to Bahadurpura X road-Pipeline Shifting-Reg.

Ref: 1.Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal Circle.


2.Oral Instructions of Chief Engineer-I,Mission Bhagiratha,Hyderabad on Dt:13.03.2019.
3.

****
It is to submit that,vide reference 1st cited above M/s.Megha Engieering and Infrastructure
Limited,Hyderabad entered in to the agreement for the work “Providing Drinking Water to Habitations in
SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District
Including Operation & Maintenance for 10 Years and work is nearing completion . Under the above work DI
pipeline of 150mm Dia,K-9,of Length 2.50 Kms was laid from from Deepaiguda village to Bahadurpura X
road, along the PR Road of Jainath Mandal in 2016.
Further it is to submit that, at the time of Execution , the above road was under the control of PRED and
later its assigned to R&B Department recently after commissioning of MB Pipeline and on Dt:12.03.2019 R&B
officials informed the Executive Engineer,MB Grid Division,Adilabad that the work widening and
strengthening of Road from Deepaiguda Village to Bahadurpura X road of Jainath Mandal for a length of 2.50
Kms is in progress.
Accordingly Executive Engineer,MB Grid Division,Adilabad conducted a joint inspection along with
Concerned R&B officials and vide reference 3rd cited informed this office that above pipeline has to be removed
and relaid and further submitted the estimate for the same .

Hence, same is herewith submitted to Chief Engineer-I,Mission Bhagiratha,Hyderabad for further


necessary orders.

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Enclosure:

Copy to:
The Executive Engineer,MB Grid Division,Adilabad for information.
Copy submitted to
The
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE EXECUTIVE ENGINEER, MISSION BHAGIRATHA GRID DIVISION, ADILABAD

Memo No.A1/ /2019, Dated:10.03.2019

Sub: Estt-MB Grid Division,Adilabad-Induction Training Phase-IV to Newly recruited AEE's at ESCI
Gachhibowli-Hyderabad-Certain Indivuals deputed for undergoing training-Relieving-Orders-
Issued.
Ref : Engineer-In-Chief,MB Dept,Hyderabad Memo.No.OP-I/AEs V&VI/RWS&S/Induction
Trg/2019,Dated:28.02.2019

****
Through the referene cited,certain Assistant Executive Engineers working under the control of MB Grid
Division,Adilabad has been deputed for(15 ) Days to undergoing training programme for the induction training
Phase-IV to Newly recruited AEEs from 11.03.2019 to 25.03.2019 (15) Days at ESCI,Gachibowli,Hyderabad
the details as follows.

Sl.No Name of the employee with Place of working Remarks


designation
1 2 3 4
1 Sri.Sirisetti Sankeerth,Assistant MB Grid Division-
Executive Engineer Adilabad

Therefore the above individual of this office is hereby instructed to attend the above training programme and
report before the Director,ESCI,Gachibowli,Hyderabad on 11.03.2019 by 9 AM without fail.

The Director,ESCI,Gachibowli,Hyderabad is requested to intimate the joining and relieve of the above
individual.

Executive Engineer
MB Grid Division-Adilabad

To,
The Individiual,
The Director,ESCI,Gachibowli,Hyderabad for favour of kind information and necessary action.
Copy Submitted to Engineer-In-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The ,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderbad
Adilabad Dist.

Lr.No.49/AEE3/ SE / RWSS(Adilabad)/ GRID/ULB/FLOW METER /2018-19, Dt: 30.03 .2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad- SRSP-Adilabad Segment “Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years-Adilabad ULB-
Providing Flow Meter at Tapping Point-Reg.
Ref: 1.Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal Circle.
2.Minutes of Joint Co-ordinaion meeting held on Dt:20.12.2018 at O/o ENC,RWSS,Hyderabad.
****
It is to submit that,vide reference 1st cited above M/s.Megha Engieering and Infrastructure
Limited,Hyderabad entered in to the agreement for the work “Providing Drinking Water to Habitations in
SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District
Including Operation & Maintenance for 10 Years and work is nearing completion . Under the above work DI
pipeline of 150mm Dia,K-9,of Length 2.50 Kms was laid from from Deepaiguda village to Bahadurpura X
road, along the PR Road of Jainath Mandal in 2016.
Most Urgent By E-mail
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.18/AEE3/DEE-II/GRID/WE-II/2018-19,Dated:10.04.2019

Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District -SRSP-Adilabad Segment-Main Grid


Works-Working Estimate-II-Certain Instructions Issued-Reg.

Ref:1.Oral Instructions of Chief Engineer-I,Mission Bhagiratha,Hyderabad on Dt:08.04.2019.


****
The immediate personal attention of the Executive Engineer,MB Grid Division,Adilabad and All the
Dy.Executive Engineers,Assistant Executive Engineers and Assistant Engineers under MB Grid Division
Adilabad is drawn to the reference cited above and all are requested to attend the O/o Chief Engineer-I,Mission
Bhagiratha,Hyderabad on Dt:15.04.2019 at 10:00 AM for finalization of provisions of Ichoda and Adilabad
Grid Sub Divisions under Adilabad Grid Division in the main estimate of Rs.1530.00 Crores with reference to
the Working Estimate-I.

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
To:
The Executive Engineer,MB Grid Division,Adilabad.
The Dy.Executive Engineer,MB Grid Sub Division,Adilabad/Ichoda.
All the Assistant Executive Engineers/Assistant Engineers under MB Grid Division Adilabad through
Concerned Executive Engineer/Deputy Executive Engineers.
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.

Most Urgent By E-mail


GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.19/AEE3/DEE-II/GRID/WE-II/ISOLATED HABS/2018-19,Dated:10.04.2019

Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District -SRSP-Adilabad Segment-Main Grid


Works-Working Estimate-II-Certain Instructions Issued-Reg.

Ref: 1.T/o. Memo No.18/AEE3/DEE-II/GRID/WE-II/2018-19,Dated:10.04.2019.


2.Oral Instructions of Chief Engineer-I,Mission Bhagiratha,Hyderabad on Dt:08.04.2019.
3.Memo.No.AEE/DEE-II/TDWSP/SRS ADB/PH-II/WE-II/ Workslip /Adilabad/ 2019
,Dt:18.02.2019
****
In continuation to the reference 1st cited above,The Executive Engineer,MB Grid Division,Adilabad is
requested to attend the remarks communicated through the reference 3rd cited and resubmit the
Isolated/Scattered habs estimatesfor taking further necessary action.

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

To:
The Executive Engineer,MB Grid Division,Adilabad.
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.50/AEE3/ SE / MB(Adilabad)/ SRSP-ADB/EXPANSION JOINTS/2018-19, Dt: 07.03.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – “Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years-Sub Estimate for
Expansion Joints-Submitted-Approval-Req-Reg.

Ref: 1)Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal Circle.


2) Lr.No.AEE1/MB GRID NIRMAL/SRSP ADILABAD SEGMENT/PH-II/WE-II/2018,Dt:06.12.2018
Of Executive Engineer,MB Grid Division,Nirmal.
.

*****
It is to submit that , vide reference 2nd cited above Executive Engineer,MB Grid Division,Nirmal has
submitted the Sub Estimatefor Expansion Joints on MS Pipeline for the work “Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad
District Including Operation & Maintenance for 10 Years for favour of kind approval .

Hence,same is herewith submitted and the Chief Engineer-I,Mission Bhagiratha,Hyderabad is requested


to kindly approve the same at an early date.

Encl:Sub Estimate of Expansion Joints

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:
The Executive Engineer,MB Grid Division,Adilabad&Nirmal for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.20/AEE3/DEE-II/GRID/WE-II/O&M ESTIMATE/2018-19,Dated:16.04.2019

Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District -SRSP-Adilabad Segment-Main Grid


Works-O&M Estimate-Certain Instructions Issued-Reg.

Ref: 1.T/o. Memo No.18/AEE3/DEE-II/GRID/WE-II/2018-19,Dated:10.04.2019.


2.Oral Instructions of Chief Engineer-I,Mission Bhagiratha,Hyderabad on Dt:08.04.2019.
****
The Executive Engineer,MB Grid Division,Adilabad is hereby directed to depute the following
officers to the O/o Chief Engineer-I,Mission Bhagiratha,Hyderabad from Dt:17.04.2019 to till the finalization
of O&M Estimate of Main Grid works of Adilabad District under SRSP-Adilabad Segment .

1.Sri.K.Madhusudan,Dy.Executive Engineer,MB Grid SD Adilabad.


2.Sri.A.Sandeep,Dy.Executive Engineer,MB Grid SD Ichoda
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

To:
The Executive Engineer,MB Grid Division,Adilabad.
The Dy.Executive Engineer,MB Grid SD Ichoda/Adilabad through The Executive Engineer,MB Grid
Division,Adilabad.
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Engineer-in-Chief,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.51/AEE3/ SE / MB(Adilabad)/ SRSP-ADB/MADEGAON WTP/2018-19, Dt: 20.04.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – “Construction of Intakewell,WTP
and RAW water pumping main in Adilabad segment,Kadam segment,Asifabad Segment and
Mancherial segment of Telangana Drinking Water Supply (TDWSP)”, Est.Cost Rs.440.50 Crs-130
MLD WTP at Madegaon-Readiness for Inspection-Reg.

Ref: 1) GO.RT.NO:82 of PR&RD (RWS IV) Dept.,Dt.07.02.2015.


2) Agreement No:01/2015-16,Dated:09.04.2015 of SE,RWS&S ,Adilabad
3)Memo.No.AEE/DEE(Plg)/TDWSP/Testing of WTPs/2019/Dated:16.04.2019 of Engineer-in-Chief,
Mission Bhagiratha,Hyderabad.
4)Minutes of Video Conference Held on 12.04.2019 By Engineer-in-Chief,MB,Hyderabad.
5)Lr.No.MB GRID NIRMAL/AEE/SRSP Adilabad/130 MLD WTP/2019,Dated:20.04.2019 of
Executive Engineer,MB Grid Division,Nirmal.

*****
It is to submit that , As per the instructions issued vide references 3rd and 4th cited above performance
test on 130 MLD WTP at Madegaon is conducted by Executive Engineer,MB Grid Division,Nirmal on
18.04.2019 against approved parameters/specifications such as inlet/outlet discharges,clear water turbidity,back
wash system efficiency,bedwise efficiency,overall efficiency ,20% overloading etc .

Further through the reference 5th cited Executive Engineer,MB Grid Division,Nirmal informed that the
above test results found satisfactory as per approved parameters and is ready for Inspection.

In this regard,It is requested the kind authority that kindly instructions may be given to
SE,V&QC,Warangal and M/s.Wapcos to inspect to test the above parameters of 130 MLD WTP at Madegaon
which is ready for inspection.

This is submitted for favour of kind infrmation.

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:
The Executive Engineer,MB Grid Division,Nirmal for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind informations

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.21/AEE3/DEE-II/MB /NEW OHSR CONNECTIONS/2018-19,Dated:26.04.2019

Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District –Inlet Connection to New OHSRs- Details-
Called for-Reg.
Ref: 1.Instructions of Engineer-in-Chief,MB,Hyderabad during video conference held on 24.04.2019.
****
During the Video conference with Engineer-in-Chief,Mission Bhagiratha,Hyderabad held on Dt:24.04.2019,it
was observed by the Engineer-in-Chief that in many Mandals there is a huge gap between No.of OHSRs
completed and No.of OHSRs came into utilization due to pending of Inlet Connection from MB Grid.
In this regard,All the AEE’s/AE’&Dy.EEs , MB Intra of Adilabad District are hereby requested to
Submit the details of New OHSRs(Proforma Enlosed) which are completed in all aspects and for which Inlet
Connectionimmediately required to this office positively by 27.04.2019 for taking further necessary
action.Further All the AEE’s/AE’s,Dy.EEs and EEs ,MB Grid of Adilabad District are also requested to attend
the next Video Conference(time slots will be intimated later) with Engineer-in-Chief,MB,Hyderabad.

Encl:As above

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

To:
All The Executive Engineers,Dy.Executive Engineers/Assistant Executive Engineers and Assistnt Engineers of
MB Intra&Grid of Adilabad District .
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) The Project Director,
SuperintendingEngineer(FAC), WAPCOS,AC Guards,
Mission Bhagiratha Circle,Adilabad, Hyderabad,Telangana-500004
Adilabad Dist.

Lr.No.52/AEE3/SE/MB/DESIGNS /2018-19, Dt: 20.04.2019

Sir,

Sub:Mission Bhagiratha Circle–Adilabad-SRSP-Adilabad Segment-“Providing Drinking Water to


I am
Habitations in SRSP-Adilabad segment in Adilabad district “Est.Cost 1530.00 Cr of SE TDWSP,
Adilabad Dist including Operation and maintenance for 10 years-Vetting of Designs and
Drawings -Requested-Reg.

Ref:- 1. Agg.No.Lr.No.AEE1/DEE TDWSP plg2/RWS&S/2015 dt.3.7.2015.


2. G.O.Ms.No.47, PR&RD (RWS-IV) Dept., dt.01.06.2015.
3. G.O.Ms.No.50, PR&RD (RWS-IV) Dept., dt.19.06.2015.
It is to submit that,with reference to the subject and references cited above I am herewith
submitting the following designs and drawings for vetting.
1.Typical Designs and Drawings for Pumpsets at following locations.
I.Chintakarra,II.Upparapally,III.Dhabbiidi,IV.Bondidi,V.Darba,VI.Gudem,VII.Mandabaguda-I
VIII.Peechara,IX.Sakriyanaik Thanda,X.Sonkhas,XI.Regulaguda sump pumping to Nandigao
-n.XII.Regulaguda Sump Pumping to New Nandigaon,XIII.Ratnapur,XIV.Damanguda,XV.Math
Ura Thanda,XVI.Neredigpmda,XVII.Mandabaguda-II.
2.Typical Designs and Drawings for for Expansion Joint on 1130 mm Dia,MS Pipeline
3. Typical Designs and Drawings for for Expansion Joint on 1030 mm Dia,MS Pipeline
4. Typical Designs and Drawings for for Expansion Joint on 930 mm Dia,MS Pipeline

Hence it is requested sir to vet the above designs and drawings as per agreement conditions at an
early date and communicate.

Encl: As above

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy Submitted To:


The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) The Project Director,
SuperintendingEngineer(FAC), WAPCOS,AC Guards,
Mission Bhagiratha Circle,Adilabad, Hyderabad,Telangana-500004
Adilabad Dist.

Lr.No.52/AEE3/SE/MB/DESIGNS /2018-19, Dt: 20.04.2019


Sir,

Sub:Mission Bhagiratha Circle–Adilabad-SRSP-Adilabad Segment-“Providing Drinking Water to


Habitations in SRSP-Adilabad segment in Adilabad district “Est.Cost 1530.00 Cr of SE TDWSP,
Adilabad Dist including Operation and maintenance for 10 years-Vetting of Designs and
Drawings -Requested-Reg.
Ref:- 1. Agg.No.Lr.No.AEE1/DEE TDWSP plg2/RWS&S/2015 dt.3.7.2015.
2. G.O.Ms.No.47, PR&RD (RWS-IV) Dept., dt.01.06.2015.
3. G.O.Ms.No.50, PR&RD (RWS-IV) Dept., dt.19.06.2015.
It is to submit that,with reference to the subject and references cited above I am herewith submitting
the following designs and drawings for vetting.
1.Typical Designs and Drawings for Pumpsets at following sump locations.
I.Chintakarra,II.Upparapally,III.Dhabbiidi,IV.Bondidi,V.Darba,VI.Gudem,VII.Mandabaguda-I
VIII.Peechara,IX.Sakriyanaik Thanda,X.Sonkhas,XI.Regulaguda sump pumping to Nandigao
-n.XII.Regulaguda Sump Pumping to New Nandigaon,XIII.Ratnapur,XIV.Damanguda,XV.Math
Ura Thanda,XVI.Neredigpmda,XVII.Mandabaguda-II.XVIII.Wai,XIX.Anthrni,XX.Hipnelly Thanda
XXI.Durga Nagar,XXII.Marlagonda,XXIII.Brahmeshwar,XIX.Chintalbori,XV.Abdullapur,XVI.Kollur,
XVII.Sirpally Thanda,XVIII.Raipad Thada, XIX.Owni, XXX.Ambakanti, XXXI.Gollamamda,
XXXII.Mudhole Phase-I,XXXIII.Mudhole,XXXIV.Sirpally,XXXV.Thandra

Hence it is requested sir to vet the above designs and drawings as per agreement conditions at an
early date and communicate.

Encl: As above

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad

Copy Submitted To:


The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) The Project Director,
SuperintendingEngineer(FAC), WAPCOS,AC Guards,
Mission Bhagiratha Circle,Adilabad, Hyderabad,Telangana-500004
Adilabad Dist.

Lr.No.53/AEE3/SE/MB/DESIGNS /2018-19, Dt: 21.04.2019

Sir,

Sub:Mission Bhagiratha Circle–Adilabad-SRSP-Adilabad Segment-“Providing Drinking Water to


Habitations in SRSP-Adilabad segment in Adilabad district “Est.Cost 1530.00 Cr of SE TDWSP,
Adilabad Dist including Operation and maintenance for 10 years-Vetting of Designs and
Drawings -Requested-Reg.
Ref:- 1. Agg.No.Lr.No.AEE1/DEE TDWSP plg2/RWS&S/2015 dt.3.7.2015.
2. G.O.Ms.No.47, PR&RD (RWS-IV) Dept., dt.01.06.2015.
3. G.O.Ms.No.50, PR&RD (RWS-IV) Dept., dt.19.06.2015.
It is to submit that,with reference to the subject and references cited above I am herewith
submitting the following designs and drawings for vetting.

1.Typical Designs and Drawings for for Expansion Joint on 1130 mm Dia,MS Pipeline
2. Typical Designs and Drawings for for Expansion Joint on 1030 mm Dia,MS Pipeline
3. Typical Designs and Drawings for for Expansion Joint on 930 mm Dia,MS Pipeline

Hence it is requested sir to vet the above designs and drawings as per agreement conditions at an
early date and communicate.

Encl: As above

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad
Copy Submitted To:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) The Project Director,
SuperintendingEngineer(FAC), WAPCOS,AC Guards,
Mission Bhagiratha Circle,Adilabad, Hyderabad,Telangana-500004
Adilabad Dist.

Lr.No.54/AEE3/SE/MB/DESIGNS /2018-19, Dt: 21.04.2019

Sir,

Sub:Mission Bhagiratha Circle–Adilabad-SRSP-Adilabad Segment“Construction of Intakewell,WTP


and RAW water pumping main in Adilabad segment,Kadam segment,Asifabad Segment
and Mancherial segment of Telangana Drinking Water Supply (TDWSP)”, Est.Cost
Rs.440.50 Cr -Vetting of Designs and Drawings -Requested-Reg.

Ref:- 1. Agg.No.Lr.No.AEE1/DEE TDWSP plg2/RWS&S/2015 dt.3.7.2015.


2. G.O.Ms.No.47, PR&RD (RWS-IV) Dept., dt.01.06.2015.
3. G.O.Ms.No.50, PR&RD (RWS-IV) Dept., dt.19.06.2015.
It is to submit that,with reference to the subject and references cited above I am herewith
submitting the following designs and drawings for vetting.

1.Typical Designs and Drawings for for Expansion Joint on 1400 mm Dia,MS Pipeline

Hence it is requested sir to vet the above designs and drawings as per agreement conditions at an
early date and communicate.

Encl: As above

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy Submitted To:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.01/AEE3/SE/MB(Adilabad)/ SRSP-ADB/EXPANSION JOINTS/QUOTATIONS/2019-20, Dt: 30.04.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment–“Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years-Quotations for
Expansion Joints-Approval-Req-Reg.

Ref: 1)Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal Circle.


2)T/o.Lr.No.50/AEE3/ SE / MB(Adilabad)/ SRSP-ADB/EXPANSION JOINTS/2018-19,
Dt:07.03.2019.

*****
It is to submit that , vide reference 2nd cited above this office has submitted the sub estimate for the
expansion joints on MS Pipeline for the work “Providing Drinking Water to Habitations in SRSP Adilabad
Segment in Adilabad District”Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District Including Operation &
Maintenance for 10 Years.

In continuation to the above,I am herewith submitting the quotations for the expansion joints along with
comparative statement and recommendations for favour of kind approval.
Encl:1.3 Original Quotations
2.Comparative Statement

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:
The Executive Engineer,MB Grid Division,Adilabad for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) The Project Director,
SuperintendingEngineer(FAC), WAPCOS,AC Guards,
Mission Bhagiratha Circle,Adilabad, Hyderabad,Telangana-500004
Adilabad Dist.

Lr.No.55/AEE3/SE/MB/DESIGNS /2018-19, Dt: .04.2019

Sir,

Sub:Mission Bhagiratha Circle–Adilabad-SRSP-Adilabad Segment-“Providing Drinking Water to


Habitations in SRSP-Adilabad segment in Adilabad district “Est.Cost 1530.00 Cr of SE TDWSP,
Adilabad Dist including Operation and maintenance for 10 years -Vetting of Designs and
Drawings -Requested-Reg.
Ref:- 1. Agg.No.Lr.No.AEE1/DEE TDWSP plg2/RWS&S/2015 dt.3.7.2015.
2. G.O.Ms.No.47, PR&RD (RWS-IV) Dept., dt.01.06.2015.
3. G.O.Ms.No.50, PR&RD (RWS-IV) Dept., dt.19.06.2015.
It is to submit that,with reference to the subject and references cited above I am herewith
submitting the following designs and drawings for vetting.

1.Typical Designs and Drawings for 100 KL Sump,10x5 Watchman Quarter,Compound wall at
Toyaguda.
2. Typical Designs and Drawings for 10 KL Sump,10x5 Watchman Quarter,Compound wall at
Wanwat.
3. Typical Designs and Drawings for 10 KL Sump,10x5 Watchman Quarter,Compound wall at
Laxmanguda.
4. Typical Designs and Drawings for 20 KL Sump,10x5 Watchman Quarter,Compound wall at
Kolamguda.
5. Typical Designs and Drawings for 10 KL Sump,10x5 Watchman Quarter,Compound wall at
Devjiguda.
6. Typical Designs and Drawings for 10 KL Sump,10x5 Watchman Quarter,Compound wall at
Chisdhari.
7.Longitudinal Section for Punaguda,Maruthiguda,Bhurki for Consttruction of Approach Roads.
8. Typical Designs and Drawings for Pumping Mains &Pumpsets for Punaguda and Maruthiguda,
Asoda and Boppapur,Laxmanguda,Kolamguda,,Wanwat ,Devjiguda,Chisdhari.
9.MS design for 150 mm ,100 mm,80 mm and 6mm thick pipeline for new habitations.

Hence it is requested sir to vet the above designs and drawings as per agreement conditions at
an early date and communicate.

Encl: As above

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle,
Adilabad.
Copy Submitted To:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.02/AEE3/SE/MB(Adilabad)/ SRSP-ADB/ISOLATED HABS/2019-20, Dt: 30. 04.2019


Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment–“Providing Drinking Water
to Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years-Workslip
for Isolated/Scattered&New Habs -Approval-Req-Reg.

Ref: 1)Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal


Circle.
2) T/o.Lr.No.55/AEE3/SE/MB/DESIGNS /2018-19, Dt: 30.04.2019 addressed to M/s.Wapcos
3).Lr.No.01/AEE3/ EE / MB(Adilabad)/ SRSP-ADB/ISOLATED HABS /2018-19,
Dt:30.04.2019 of Executive Engineer,MB Grid Division,Adilabad.

It is to submit that , vide reference 2nd cited above Executive Engineer,MB Grid Division
,Adilabad has submitted the work slip for covering Isolated/Scattered & New Habs of Adilabad District
in SRSP Adilabad Segment with an Estimate Cost of 10.00 Croresunder the work “Providing Drinking
Water to Habitations in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years and the same is herewith
submitted for taking further action please.

Encl:As above.

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle,Adilabad

Copy to:
The Executive Engineer,MB Grid Division,Adilabad for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.01/AEE3/DEE-II/GRID/2019-20,Dated:03.05.2019

Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District-SRSP-Adilabad Segment-Daily Supply


Certain Instructions-Issued-Reg.
Ref:1.Telephonic Instructions recieved from Hon’ble MLA,Adilabad on Dt:03.05.2019.
****

The Dy.Executive Engineer,MB Grid SD,Adilabad attention is invited to the reference cited
and he is requested to be vigilant on maintaining the Arepally GLBR clear water level so that required pressure
is maintained at Adilabad BPT to avoid any interruptions in daily supply for the habitations under Adilabad
BPT and same message received from Hon’ble MLA,Adilabad .
In this connection the Dy.EE,MB Grid SD ,Adilabad is requested to co-ordinate with the
Dy.EE,MB Grid SD,Ichoda regarding the above matter

Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Dy.Executive Engineer,MB Grid SD,Adilabad
Copy to:
The Dy.Executive Engineer,MB Grid SD,Ichoda with a request to co-ordinate with the Dy.EE,MB Grid SD
Adilabad.
The Executive Engineer,MB Grid Division,Adilabad for information and necessary action.
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
The P.S to Hon’ble MLA,Adilabad for favour of Kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.02/AEE3/DEE-II/GRID/2019-20,Dated:03.05.2019

Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District-SRSP-Adilabad Segment-Bulk water


Connection to 2nd BN.TSSP(IR),Yapalguda,Adilabad-Detailed Report-Called for-Reg.

Ref:1.Endorsement of Collector&District Magistrate ,Adilabad.


****

The immediate Personal attention of the Executive Engineer,MB Grid Division,Adilabad


is drawn to the reference 1st cited above and he is hereby requested to submit the detailed report
along with the detailed estimated on bulk water connection request(Copy Enclosed) of 2nd
Bn.TSSP(IR),Yapalguda,Adilabad at early date to this office for taking further necessary action.

Sd/-
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Adilabad
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
The Collector&District Magistrate,Adilabad for favour of kind information.

//T.C.F.B.O//

Dy.EE PA to SE
MB Circle-Adilabad
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.03/AEE3/SE/MB(Adilabad)/ SRSP-ADB/PHASE-I/EOAT/2019-20, Dt: 03.05.2019

Sir,

Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment-Construction of


Intakewell,WTP and Raw water pumping main in Adilabad segment,Kadam
segment,Asifabad Segment and Mancherial segment of Telangana Drinking Water
Supply (TDWSP), Est.Cost Rs.440.50 Crs–Extension of Agreement Time (EOAT)
Proposals-Submitted – Reg.

Ref: : 1) GO.RT.NO:82 of PR&RD (RWS IV) Dept.,Dt.07.02.2015.


2) Agreement No:01/2015-16,Dated:09.04.2015 of SE,RWS&S ,Adilabad
3) Proc.No.AEE1/TDWSP-Nirmal/EOAT/2016,Dated:05.10.2016 of the Superintending
Engineer,TDWSP Circle,Nirmal.
4) Proc.No.AEE/DEE/TDWSP/Nirmal Circle/EOAT/Phase-I/2017,Dated:12.06.2017 of
the Chief Engineer-III,TDWSP,Hyderabad
5) Procs.No.AEE/DEE/TDWSP/Erst Adilabad/EOAT/Phase-I/2017,Dated:20.03.2018
of Chief Engineer-III,TDWSP,Hyderabad.
6) Procs.No.AEE-IV/DEE-II/TDWSP/SRSP-Adilabad/EOAT-IV/Phase-I/2018,Dated:
13.11.2018 of Chief Engineer-IV,TDWSP,Hyderabad.
7) Lr.No.24A/SRSP-Adilabad/Phase-I/2019-20,Dated: . .2019 of M/s.MEIL,
Hyderabad.
8) Lr.No.MB GRID NIRMAL/SRSP Adilabad/Phase-I/EOAT-5/2019,Dated: .
.2019 of Executive Engineer,MB Grid Division,Nirmal.
*****
It is to submit that videreference 1st cited, Government has accorded administrative sanction for the
work “Construction of Intakewell,WTP and RAW water pumping main in Adilabad segment,Kadam
segment,Asifabad Segment and Mancherial segment of Telangana Drinking Water Supply (TDWSP)”,
Est.Cost Rs.440.50 Crs. Further through the reference 2nd cited an agreement was concluded with M/s Megha
Engineering &Infrastructure Limited,Hyderabad for the same.

Wherein EOAT-I , EOAT-II,EOAT-III&EOAT-IV which were accorded vide References 3rd,4th,


5th&6thcited for the above work were expired on 31-12-2018.Accordingly vide reference 7th cited M/s.MEIL,
Hyderabad submitted the proposals for EOAT and requested for further EOAT upto 30thJune 2019.

And also the Executive Engineer MB Grid,Division, Nirmal has submitted the EOAT Proposals duly
recommending EOAT upto 30thJune 2019 without imposing any penalty based on the reasons explained by the
agency, and further enclosed Check slip.

Contd…..Page No.2
:::2:::

Hence,I am herewith submitting the Extension of Agreement Time(EOAT) proposals for the above said
work under SRSP-Adilabad Segment for your kind perusal and further necessary action.

Encl: EOAT Check slip.

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,MB,Hyderabad for favour of kind information.


Copy to Executive Engineer,MB Grid Division,Nirmal for information.

Most Urgent By E-mail


GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.03/AEE3/DEE-II/MB/VC /2019-20,Dated:08.05.2019


Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District-Video Conference with Engineer-in-
Chief,Mission Bhagiratha,Hyderabad on Dt:14.05.2019-Certain Instructions-Issued-Reg.

Ref:1.T/o.Memo.No.21/AEE3/DEE-II/MB/NEW OHSR CONNECTIONS/2018-19,Dated:


26.04.2019.
2.Instructions of Engineer-in-Chief,Mission Bhagiratha,Hyderabad during the video
Conference held on Dt:24.04.2019.
3.Memo.No.AEE/DEE/BS/Meeting/2019,Dated:04.05.2019 of Engineer-in-Chief,
Mission Bhagiratha,Hyderabad.
****
While Enclosing the copies of the references cited above,All the Executive
Engineers,Dy.Executive Engineers and Assistant Executive Engineers/Assistant Engineers(Both Grid& Intra) of
Adilabad District are hereby requested to attend the Video Conference with Engineer-in-Chief,Mission
Bhagiratha,Hyderabad on Dt:14.05.2019 , at 2 PM in Circle office, Adilabad with relevant information with out
fail.

Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
All the Executive Engineers,Dy.Executive Engineers and Assistant Executive Engineers/Assistant Engineers of
MB Grid &Intra of Adilabad District
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

Most Urgent By E-mail


GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.04/AEE3/DEE-II/MB/VC /2019-20,Dated:08.05.2019

Sub: Mission Bhagiratha Circle-Adilabad-Adilabad District-Video Conference with Engineer-in-


Chief,Mission Bhagiratha,Hyderabad on Dt:14.05.2019-Certain Instructions-Issued-Reg.

Ref:1.T/o.Memo.No.21/AEE3/DEE-II/MB/NEW OHSR CONNECTIONS/2018-19,Dated:


26.04.2019.
2.Instructions of Engineer-in-Chief,Mission Bhagiratha,Hyderabad during the video
Conference held on Dt:24.04.2019.
3.Memo.No.AEE/DEE/BS/Meeting/2019,Dated:04.05.2019 of Engineer-in-Chief,
Mission Bhagiratha,Hyderabad.
4.T/o.Memo.No.03/AEE3/DEE-II/MB/VC/2019-20,Dated:08.05.2019
****
In continuation to the reference 4th cited above& As per instructions of Engineer-in-
Chief,MB,Hyderabad All the Executive Engineers ,Dy.Executive Engineers and Assistant Executive
Engineers/Assistant Engineers (Both MB Grid &Intra) of Adilabad District are hereby requested to approach
Engineer-in-Chief,MB,Hyderabad for availing any kind of leave,if required on the day of VC with ENC.

Further,No other officer is permitted to sanction leave for their respective subordinates on
the day of VC i.e.on Dt:14.05.2019.

Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
All the Executive Engineers,Dy.Executive Engineers and Assistant Executive Engineers/Assistant Engineers of
MB Grid &Intra of Adilabad District
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) M/s.MEIL,
SuperintendingEngineer(FAC), Balanagar,
Mission Bhagiratha Circle,Adilabad, Hyderabad-500037
Adilabad Dist.

Lr.No.I/AEE3/SE/MB/EXPANSION JOINTS /2018-19, Dt: 20.07.2018

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-Quotations for MS Expansioin Joints-Req-Reg.

Ref: Arising

*****

Anent to the subject cited above, M/s.MEIL,Balanagar,Hyderabad is invited to submit their quotations
for Manufacturing and Supply of MS Expansion joints for the 1100 mm Dia,1000 mm Dia,900 mm Dia and
with pressure rating 25 Kg/Cm2 Excluding all taxes ,Packing and Forwarding etc.
Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:
Executive Engineer,MB Grid Division,Adilabad for information and necessary action.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) M/s.S.K.Industries,
SuperintendingEngineer(FAC), Balanagar,
Mission Bhagiratha Circle,Adilabad, Hyderabad-500042
Adilabad Dist.

Lr.No.II/AEE3/SE/MB/EXPANSION JOINTS /2018-19, Dt: 20.07.2018

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-Quotations for MS Expansioin Joints-Req-Reg.

Ref: Arising

*****

Anent to the subject cited above, M/s.S.K.Industries,Balanagar,Hyderabad is invited to submit their


quotations for Manufacturing and Supply of MS Expansion joints for the 1100 mm Dia,1000 mm Dia,900 mm
Dia and with pressure rating 25 Kg/Cm2 Excluding all taxes ,Packing and Forwarding etc.

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.
Copy to:
Executive Engineer,MB Grid Division,Adilabad for information and necessary action.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

From: To:
Sri D.Venkateshwarlu,M.E,(Hon's) M/s.G.M.Dalui&Sons Pvt Ltd,
SuperintendingEngineer(FAC), Howrah-711113,
Mission Bhagiratha Circle,Adilabad, W.B.,India
Adilabad Dist.

Lr.No.III/AEE3/SE/MB/EXPANSION JOINTS /2018-19, Dt: 20.07.2018

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-Quotations for MS Expansioin Joints-Req-Reg.

Ref: Arising

*****

Anent to the subject cited above, M/s.G.M.Dalui&Sons Pvt Ltd,Howrah,W.B, is invited to submit their
quotations for Manufacturing and Supply of MS Expansion joints for the 1100 mm Dia,1000 mm Dia,900 mm
Dia and with pressure rating 25 Kg/Cm2 Excluding all taxes ,Packing and Forwarding etc.

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:
Executive Engineer,MB Grid Division,Adilabad for information and necessary action.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
PROCEEDINGS OF SUPERINTENDING ENGINEER,MISSION BHAGIRATHA CIRCLE-ADILABAD
Present:D.Venkateshwarlu,M.E,(Hon's)
Procs:No. 01/AEE3/DEE-II/Grid/MS Expansion Joints/2018-19,Dated:28.04.2019

Sub :Mission Bhagiratha Circle–Adilabad-SRSP-Adilabad Segment-“Providing Drinking Water to Habitations in


SRSP-Adilabad segment in Adilabad district “Est.Cost 1530.00 Cr of SE TDWSP, Adilabad Dist including
Operation and maintenance for 10 years-Rate approval Expansion joints of above ground MS Pipes-
Reg.
Ref: Rate quotations received from various suppliers
*****

Rate quotations have been received from various willing suppliers for MS Expansion joints as per
specification indicated in the table below and lowest rate quoted by M/s.Megha Engineering and
Infrastructure Ltd is hereby approveds The approved ratesare as follows.
SL.N PN- UNIT
DESCRIPTION DIA
O RATING RATE
Manufacturing & Supply of Mild Steel (M.S)
Fabricated expansion joint Confirming to IS
A
2062E250BR etc. Complete ISI Marked and
Excluding GST.
1 Expansion Joint 1100 25 248400
2 Expansion Joint 1000 25 220000
3 Expansion Joint 900 25 184500

The Executive Engineer, Mission Bhagiratha Grid, Adilabad &Nirmal Divisions, are instructed to prepare and
submit the estimate accordingly for the respective Districts.

Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Adilabad&Nirmal for necessary action.
Copy Submitted To:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.04/AEE3/ SE / MB(Adilabad)/ SRSP-ADB/EXPANSION JOINTS/2019-20, Dt: 14.05.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – Construction of Intakewell,WTP and
Raw water pumping main in Adilabad segment,Kadam segment,Asifabad Segment and
Mancherial segment of Telangana Drinking Water Supply (TDWSP), Est.Cost Rs.440.50 Crs-Sub
Estimate for Expansion Joints-Submitted-Approval-Req-Reg.

Ref: 1)Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal Circle.


2) Estimate Copies received from Executive Engineer,MB Grid Division,Nirmal office.

*****
It is to submit that , Executive Engineer,MB Grid Division,Nirmal has submitted the Sub Estimates for
Surge Vessels,Zero velocity valve,Air cushion valves and Expansion joints for MS Pipeline for the work
“Construction of Intakewell,WTP and Raw water pumping main in Adilabad segment,Kadam
segment,Asifabad Segment and Mancherial segment of Telangana Drinking Water Supply (TDWSP),
Est.Cost Rs.440.50 Crs”for favour of kind approval .

Hence,same is herewith submitted and the Chief Engineer-IV,Mission Bhagiratha,Hyderabad is


requested to kindly approve the same at an early date.

Encl:1.Sub Estimate of Surge Vessels


2.Sub Estimate for Zero Velocity Valves

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:
The Executive Engineer,MB Grid Division,Nirmal for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.05/AEE3/ SE / MB(Adilabad)/ SRSP-ADB/EXPANSION JOINTS/2019-20, Dt: 22.05.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years”, -Remarks on
Expansion Joints-Information-Submitted-Reg.

Ref: 1)Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal Circle.


2)Memo.No.AEE/DEE-II/SRSP ADB/PH II/WE II/Workslip/Expansion Joints/Remarks/2019,Dated:20.
05.2019 of Chief Engineer-I,Mission Bhagiratha,Hyderabad.
3) T/o.Lr.No.50/AEE3/ SE / MB(Adilabad)/ SRSP-ADB/EXPANSION JOINTS/2018-19,
Dt: 23.04.2019

*****
It is to submit that , in continuation to the reference 3rd cited and as per instructions issued vide reference
2ndcited above I am herewith submitting the approved drawing for expansion joints on MS
Pipeline,Specification report and Main segment General Abstract for taking further necessary action.

Encl:1.Approved drawing for Expansion Joints


On MS Pipeline
2.Specification Report
3.Main segment General Abstract

Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:
The Executive Engineer,MB Grid Division,Adilabd for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.

GOVERNMENT OF TELANGANA
RURAL WATER SUPPLY & SANITATION DEPARTMENT
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), TDWSP,Hyderabad.
Mission Bhagiratha-Circle,Adilabad,
Adilabad Dist.

Lr.No.11/1/AEE3/ SE / MB(Adilabad)/ SRSP-ADB/EM Works/WE-II/2019-20, Dt: 26.03.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – -“Design, Supply, Erection, Testing
and commissioning of Electro mechanical works with SCADA & Instrumentation along with
associated substation and switch gear including all connected accessories for various Pumping
stations located at various places in erstwhile districts Adilabad, Nizamabad and Karimnagar.
Including, defects liability period and operation and maintenance for 10 years Package-III” -
Working Estimate-II-Submitted-Approval-Req-Reg.

Ref: 1) Agreement No. AEE/01/2017-18,Dated:18.04.2017.of the Superintending


Engineer,TDWSP Circle,Nirmal
2) Supplementary Agreement No.AEE1/01/2018-19,Dated:15.05.2018 of Superintending
Engineer,RWS&S Circle,Mancherial.
3)Lr.No.AEE/MB Grid Nirmal/SRSP ADB /EM Works/WE-II/2019,Dated:26.03.2019 of Executive
EngineerMB Grid Division,Nirmal.

*****
It is to submit that vide references 3rd cited, Executive Engineer,MB Grid Division,Nirmal has
submitted the Working Estimate-II for Electro Mechanical Works of SRSP Adilabad Segment in Nirmal
District for favour of kind approval and same is herewith submitted for further necessary action.

Encl:Working Estimate-II

Yours faithfully,

Superintending Engineer(FAC),
MB Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.


Copy to Executive Engineer,MB Grid Division,Nirmal for information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.11/2/AEE3/ SE / MB(Adilabad)/ SRSP-ADB/EM Works/O&M/2019-20, Dt: 26.03.2019


Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – -“Design, Supply, Erection, Testing
and commissioning of Electro mechanical works with SCADA & Instrumentation along with
associated substation and switch gear including all connected accessories for various Pumping
stations located at various places in erstwhile districts Adilabad, Nizamabad and Karimnagar.
Including, defects liability period and operation and maintenance for 10 years Package-III” -O&M
Estimate -Submitted-Approval-Req-Reg.

Ref: 1) Agreement No. AEE/01/2017-18,Dated:18.04.2017.of the Superintending


Engineer,TDWSP Circle,Nirmal
2) Supplementary Agreement No.AEE1/01/2018-19,Dated:15.05.2018 of Superintending
Engineer,RWS&S Circle,Mancherial.
3)Lr.No.AEE/MB Grid Nirmal/SRSP ADB /EM Works/O&M/2019,Dated:26.03.2019 of Executive
EngineerMB Grid Division,Nirmal.

*****
It is to submit that vide references 3rd cited, Executive Engineer,MB Grid Division,Nirmal has
submitted the O&M Estimate for Electro Mechanical Works of SRSP Adilabad Segment in Nirmal District for
favour of kind approval and same is herewith submitted for further necessary action.

Encl:O&M Estimate

Yours faithfully,

Superintending Engineer(FAC),
MB Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.


Copy to Executive Engineer,MB Grid Division,Nirmal for information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, RWS&S CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.11/3/AEE3/ SE / MB(Adilabad)/ SRSP-ADB/EM Works/DLP/2019-20, Dt: 26.03.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – -“Design, Supply, Erection, Testing
and commissioning of Electro mechanical works with SCADA & Instrumentation along with
associated substation and switch gear including all connected accessories for various Pumping
stations located at various places in erstwhile districts Adilabad, Nizamabad and Karimnagar.
Including, defects liability period and operation and maintenance for 10 years Package-III” -O&M
Estimate–Defect Liability Certificate(DLP)-Submitted-Reg.
Ref: 1) Agreement No. AEE/01/2017-18,Dated:18.04.2017.of the Superintending
Engineer,TDWSP Circle,Nirmal
2) Supplementary Agreement No.AEE1/01/2018-19,Dated:15.05.2018 of Superintending
Engineer,RWS&S Circle,Mancherial.
3) Defect Liability Certificates received from Executive Engieer,MB Grid Division,Nirmal
*****
It is to submit that vide references 3rd cited, Executive Engineer,MB Grid Division,Nirmal has
submitted the Defect Liability Cerificates for Electro Mechanical Works of SRSP Adilabad Segment in Nirmal
District and same is herewith submitted for further necessary action.

Encl:Defect Liability Certificates(DLP)

Yours faithfully,

Superintending Engineer(FAC),
MB Circle, Adilabad.

Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.


Copy to Executive Engineer,MB Grid Division,Nirmal for information

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-IV,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.11/3/AEE3/ SE / MB(Adilabad)/ SRSP-ADB/EM Works/DLP/2019-20, Dt: 26.03.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – -“Design, Supply, Erection, Testing
and commissioning of Electro mechanical works with SCADA & Instrumentation along with
associated substation and switch gear including all connected accessories for various Pumping
stations located at various places in erstwhile districts Adilabad, Nizamabad and Karimnagar.
Including, defects liability period and operation and maintenance for 10 years Package-III” -O&M
Estimate–Defect Liability Certificate(DLP)-Submitted-Reg.

Ref: 1) Agreement No. AEE/01/2017-18,Dated:18.04.2017.of the Superintending


Engineer,TDWSP Circle,Nirmal
2) Supplementary Agreement No.AEE1/01/2018-19,Dated:15.05.2018 of Superintending
Engineer,RWS&S Circle,Mancherial.
1) Defect Liability Certificates received from Executive Engieer,MB Grid Division,Nirmal
*****
It is to submit that vide references 3rd cited, Executive Engineer,MB Grid Division,Nirmal has
submitted the Defect Liability Cerificates for Electro Mechanical Works of SRSP Adilabad Segment in Nirmal
District and same is herewith submitted for further necessary action.

Encl:Defect Liability Certificates(DLP)

Yours faithfully,

Superintending Engineer(FAC),
MB Circle, Adilabad.
Copy submitted to the Engineer-in-Chief,RWS&S,Hyderabad for favour of kind information.
Copy to Executive Engineer,MB Grid Division,Nirmal for information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's),. The M/s Mega Engineering&Infrastructure Ltd,
SuperintendingEngineer(FAC), S-2, Technocrat Indl.Estate, Balanagar,
Mission Bhagiratha-Circle,Adilabad, Balanagar,
Adilabad Dist. Hyderabad,Telangana-500037

Lr.No.06/AEE3/ SE / MB(Adilabad)/ SRSP-ADB/WE-II/2019-20, Dt: 27.05.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years”, -Working
Estimate-II-Approval of Balance Item-Req-Reg.

Ref: 1)Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal Circle.


2)Procs.No.AEE-IV/DEE-II/TDWSP/SRSP Adilabad/EOAT-II/Phase-II/2018,Dated:10.12.2018
Of Chief Engineer-IV,TDWSP,Hyderabad.
3)Memo. No. AEE/DEE/MB/Work Estimate-II/SRSP-Adilabad(Ph-2)/2018, Dt: 10-01 -2019 of
Chief Engineer-IV,MB,Hyderabad.
4)T/o.Supplymentary Agreement No.04/G/2019-20,Dated:18.01.2019.

*****
It is to submit that, vide reference 1st cited above , M/s Megha Engineering & Infrastructure
limited,Hyderabad has entered into the agreement for the work “Providing Drinking Water to Habitations
in SRSP-Adilabad segment in Adilabad district “Est.Cost 1530.00 Cr of SE TDWSP, Adilabad Dist
including Operation and maintenance for 10 years.

Further vide reference 3rd cited above,The Chief Engineer-IV,Mission Bhagiratha ,Hyderabad has
communicated the Approved General Abstract of Working Estimate-II along with the few Technically approved
sub estimates to this office for taking further necessary action.

Consequently vide reference 4th cited,a Supplymentary agreement was concluded for the technically
approved items.Wherein it is observed by the undersigned that,many of the item in Approved General abstract
are yet to be technically approved by the competent authority and also the EOAT of the above said is going to
expire on 30.06.2019.

In this regard,M/s.Megha Engineering and Infrastructure Limited,Hyderabad is hereby requested to submit


the detailed estimates and related documents such as designs and drawing etc of pending items to this office at
an early date as for taking further necessary action please.
Yours faithfully,

Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:
The Executive Engineer,MB Grid Division,Adilabd&Nirmal for information and necessary action.
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha for favour of Kind information.
The Chief Engineer-IV,Mission Bhagiratha for favour of Kind information.
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.05/AEE3/DEE-II/MB/WE-III/2019-20,Dated:27.05.2019

Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment-


.

Ref:1.T/o.Memo.No.21/AEE3/DEE-II/MB/NEW OHSR CONNECTIONS/2018-19,Dated:


26.04.2019.
2.Instructions of Engineer-in-Chief,Mission Bhagiratha,Hyderabad during the video
Conference held on Dt:24.04.2019.
3.Memo.No.AEE/DEE/BS/Meeting/2019,Dated:04.05.2019 of Engineer-in-Chief,
Mission Bhagiratha,Hyderabad.
4.T/o.Memo.No.03/AEE3/DEE-II/MB/VC/2019-20,Dated:08.05.2019
****
In continuation to the reference 4th cited above & As per instructions of Engineer-in-
Chief,MB,Hyderabad All the Executive Engineers ,Dy.Executive Engineers and Assistant Executive
Engineers/Assistant Engineers (Both MB Grid &Intra) of Adilabad District are hereby requested to approach
Engineer-in-Chief,MB,Hyderabad for availing any kind of leave,if required on the day of VC with ENC.

Further,No other officer is permitted to sanction leave for their respective subordinates on
the day of VC i.e.on Dt:14.05.2019.

Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
All the Executive Engineers,Dy.Executive Engineers and Assistant Executive Engineers/Assistant Engineers of
MB Grid &Intra of Adilabad District
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.06/AEE3/DEE-II/MB/ROAD DAMAGES/2019-20,Dated:01.06.2019

Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment-Adilabad District-R&B Road


Damages-Reg.
.

Ref:1.Lr.No.AEE/DEE/EEA/2019-20/119,Dated:28.05.2019 of District(R&B) Officer,Adilabad.


****
A copy of the reference cited is herewith communicated to the officers noted in the address
entry for information and necessary action in this matter.

Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineers,MB Grid Division,Adilabad.
The Dy.Executive Engineer,MB Grid Sub Division ,Adilabad
Copy to
The District(R&B) Officer,Adilabad
Copy Submitted to:
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MISSION BHAGIRATHA CIRCLE, ADILABAD

Memo No.07/AEE3/DEE-II/MB/PHASE-I/PV/2019-20,Dated:29.05.2019

Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment-“Construction of Intakewell


WTP and Raw water pumping main in Adilabad segment,Kadam Segment,Asifabad
Segment Mancherial segment of Telangana Drinking Water Supply (TDWSP)”Est.Cost
Rs.440.50 Crs-Price variation for Steel,Cement and MS Plate-Approved-Communicated-Reg.

Ref:1. Lr.No.AEE/MB Grid Nirmal/SRSP ADB/PH-I/PV/2019,Dated:28.05.2019 of


Executive Engineer,RWS&S,MB Grid Nirmal.

****

Based on the recommendations of the Executive Engineer,MB Grid Division,Nirmal The Price
variation for Steel,Cement,MS Plates from RA Bill-1 to RA Bill-26 for the work “Construction of and
Intakewell , WTP and Raw water pumping main in Adilabad Segment Kadam segment,Asifabad
Segment Mancherial segment of Telangana Drinking Water Supply (TDWSP)”Est.Cost Rs.440.50
Crs,under SRSP-Adilabad segment is approved for an amount of Rs.-53321567.96/- (Steel- Rs.-
8303491.81/-,Cement-Rs.-4030335.57/-,MS Plate-Rs.-40987740.58/-) and a copy of same is herewith
communicated, keeping the responsibility on the Executive Engineer,MB Grid Division,Nirmal for
taking further necessary action .

Further Executive Engineer,MB Grid Division,Nirmal shall ensure that any deviations on above
approved amount is found the same shall be deducted from the subsequent bills of agency .

Encl:Copy of the Approved Price variation statements


Sd/-

.
Superintending Engineer(FAC)
Mission Bhagiratha Circle-Adilabad
To:
The Executive Engineer,MB Grid Division,Nirmal
Copy Submitted to:
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.06/AEE3/ SE / MB(Adilabad)/ SRSP-ADB/O&M/2019-20, Dt: 22.05.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment –Adilabad District-Providing Drinking
Water to Habitations in SRSP Adilabad Segment in Adilabad District Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years”, -O&M Estimate
–Submitted-Reg.
Ref: 1)Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal Circle.
2) Estimate Copies received from Executive Engineer,MB Grid Division,Adilabad office.

*****
It is to submit that , Executive Engineer,MB Grid Division, Adilabad has submitted the O&M Estimate
of Adilabad District under SRSP-Adilabad segment for the work “Providing Drinking Water to Habitations
in SRSP Adilabad Segment in Adilabad District”Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District
Including Operation & Maintenance for 10 Years.

Hence, same is herewith submitted and the Chief Engineer-I,Mission Bhagiratha,Hyderabad is requested
to kindly approve the same.

Encl:O&M Estimate

Yours faithfully,
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:
The Executive Engineer,MB Grid Division,Adilabad for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.

.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Branch Manager ,
SuperintendingEngineer(FAC), Large Corporate Branch,
Mission Bhagiratha Circle,Adilabad, Oriental Bank of Commerce,
Adilabad Dist. Hyderabad,Telangana-500033

Lr.No.07/AEE3/ SE / MB(Adilabad)/ SRSP-ADB/BG/EXTENSION/PH-I/2019-20, Dt: 10.06.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment – “Construction of Intake well, WTP
and Raw Water Pumping main in Adilabad segment, Kaddam segment, Asifabad segment and
Mancherial segment of Telangana drinking Water supply project (TDWSP)” Est.cost of Rs.440.50 -
Extension of Validity of Bank Guarantee -Confirmation of genuineness-Requested-Reg.

Ref: 1)Original Agreement No:AEE1/01/2015-16,Dated:09.04.2015 of Superintending Engineer,RWS&S,


Circle,Adilabad.

*****
A copy of Bank Guarantee Extension for ₹:8,00,00,000-00 vide B.G.No.11100029316, Dated: 30.11.2016 of
Oriental Bank of Commerce,Large Corporate Branch,Hyderabad-500033, extended upto 28.05.2020 issued to M/s.
Megha Engineering & Infrastructures Ltd., Hyderabad for the work “Construction of Intake well, WTP and Raw
Water Pumping main in Adilabad segment, Kaddam segment, Asifabad segment and Mancherial segment of
Telangana drinking Water supply project (TDWSP)” Est.cost of Rs.440.50 Crs is here with communicated with a
request to confirm the genuineness of the BGs extension at the earliest.

Encl:Orignal Bank Guarantee Extension Letter


Sd/
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:
The Executive Engineer,MB Grid Division,Nirmal for information.
Copy submitted to
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

\\T.C.F.B.O\\

.
Dy.EE PA TO SE
MISSION BHAGIRATHA CIRCLE-ADILABAD
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Branch Manager ,
SuperintendingEngineer(FAC), Large Corporate Branch,
Mission Bhagiratha Circle,Adilabad, Oriental Bank of Commerce,
Adilabad Dist. Hyderabad,Telangana-500033

Lr.No.08/AEE3/ SE / MB(Adilabad)/ SRSP-ADB/BG/EXTENSION/PH-II/2019-20, Dt: 10.06.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment –“Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years”-Extension of
Validity of Bank Guarantee -Confirmation of genuineness-Requested-Reg.

Ref: 1) Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal Circle.

*****
A copy of Bank Guarantee Extension for ₹:8,00,00,000-00 vide B.G.No.11100029216, Dated: 30.11.2016 of
Oriental Bank of Commerce,Large Corporate Branch,Hyderabad-500033, extended upto 28.05.2020 issued to M/s.
Megha Engineering & Infrastructures Ltd., Hyderabad for the work –“Providing Drinking Water to Habitations
in SRSP Adilabad Segment in Adilabad District Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District
Including Operation & Maintenance for 10 Years”s is here with communicated with a request to confirm the
genuineness of the BGs extension at the earliest.

Encl:Original Bank Guarantee Extension Letter

Sd/-
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:
The Executive Engineer,MB Grid Division,Nirmal for information.
Copy submitted to
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

\\T.C.F.B.O\\

.
Dy.EE PA TO SE
MISSION BHAGIRATHA CIRCLE-ADILABAD

.
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Branch Manager ,
SuperintendingEngineer(FAC), Large Corporate Branch,
Mission Bhagiratha Circle,Adilabad, Oriental Bank of Commerce,
Adilabad Dist. Hyderabad,Telangana-500033

Lr.No.08/AEE3/ SE / MB(Adilabad)/ SRSP-ADB/BG/EXTENSION/PH-II/2019-20, Dt: 10.06.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment –“Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years”-Extension of
Validity of Bank Guarantee -Confirmation of genuineness-Requested-Reg.

Ref: 1) Agreement No:04/2015-16,Dated:28.10.2015 of Superintending Engineer,TDWSP,Nirmal Circle.

*****
A copy of Bank Guarantee Extension for ₹:8,00,00,000-00 vide B.G.No.11100029216, Dated: 30.11.2016 of
Oriental Bank of Commerce,Large Corporate Branch,Hyderabad-500033, extended upto 28.05.2020 issued to M/s.
Megha Engineering & Infrastructures Ltd., Hyderabad for the work –“Providing Drinking Water to Habitations
in SRSP Adilabad Segment in Adilabad District Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District
Including Operation & Maintenance for 10 Years”s is here with communicated with a request to confirm the
genuineness of the BGs extension at the earliest.

Encl:Original Bank Guarantee Extension Letter

Sd/-
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:
The Executive Engineer,MB Grid Division,Nirmal for information.
Copy submitted to
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

\\T.C.F.B.O\\

.
Dy.EE PA TO SE
MISSION BHAGIRATHA CIRCLE-ADILABAD
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), Chief Engineer-I,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, Hyderabad.
Adilabad Dist.

Lr.No.09/AEE3/ SE / MB(Adilabad)/ SRSP-ADB/TRANSPORTATION/2019-20, Dt: 18.06.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-–Adilabad District- SRSP-Adilabad Segment-SRSP-Reservior-
Water Level Below Minimum Draw Down Level(MDDL)-Critical Habs-Water Supply Through Trans
Poration-Request-Reg.
Ref: 1) G.O.Rt.No.885 of I&CADD(WRG-GRC) Department,Dated:30.10.2017.
2) Memo.No.AE-I/DEE-I/TDWSP-I/MDDL/2018,Dated:05.01.2019 of Chief Engineer,TDWSP-
I,Hyderabad.
3) T/o Lr.No.32/AEE3/SE/MB/SRSP-Reservior/MDDL/2018-19,Dated:05.01.2019.
4) Oral Instructions of Collector&District Magistrate,Adilabad during the Video Conference on
Mission Bhagiratha withMB Officials,Sarapanches,Panchayath Secreteris and MPDO’s of
Adilabad District on Dt:01.06.2019
5) Lr.No.01/AEE1/EE/MB INTRA/Drought Mitigation Measures/2019,Dated:18.06.2019
Of Executive Engineer,MB Intra Division,Adilabad.
*****
It is to submit that , vide reference 1st cited above Governament has instructed to maintain Minimum
Draw Down Levels(MDDLs) in certain reservoirs of Telangana for storing required quantum of water for
Government flagship programme “Mission Bhagiratha “ so as to provide protected and assured drinking water
on sustainable basisi to all houeholds of the states.
Further vide reference 2nd cited above instructions were issued to moniter the MDDLs in reservoirs and
co-ordinate with I&CAD Department officials in Maintaining the prescribed MDDLs.
Accordingly this office vide reference 3rd cited above,addressed the concerned Irrigation department
officials to Maintain the required MDDL in SRSP-Reservoir which is 320.35 Mts so as to avoid water scarcirty
as it serves Adilabad (254 Habs),Boath(480 Habs) Constituencies and Adilabad ULB in Adilabad District.
Further it is to submit that,as informed by the Irrigation officials the current water level in SRSP-
Reservoir is 319.7352 Mts, with present capacity of 5.66 TMC which is well below the prescribed MDDL due
to which water supply from SRSP is held up and also few habitations in KB-Asifabad segment of Adilabad
District are getting frequent interruptions in MB Water supply due to various reasons i.e.Power
Interuptions,Stabilization of Pipeline,Leakages,Repairs etc.
Consequently ,as per the instructions of The Collector&District Magistrate,Adilabad, The Executive
Engineer,MB Intra Division ,Adilabad taken up the Transportation of water in Certaion Critical Habitations
where MB Water is not being received an submitted list of the same in vide reference 5th cited .
In this regard,It is requested sir that kindly necessary instructions may be given the respective Main Grid
agencies to take up the Transportation of water for above critical habitations until the MB Water supply
resumed so as to avoid to avoid further problems.

Enclosure:As above
Yours faithfully,

`
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:
The Executive Engineer,MB Grid Division&Intra ,Adilabad for information.
Copy submitted to
The Engineer-in-Chief,Mission Bhagiratha for favour of kind information.

.
Lr.No.10----WTP Repairs
GOVERNMENT OF TELANGANA
DEPARTMENT OF MISSION BHAGIRATHA
OFFICE OF THE SUPERINTENDING ENGINEER, MB CIRCLE, ADILABAD

From, To,
Sri D.Venkateshwarlu,M.E,(Hon's), The Executive Engineer,
SuperintendingEngineer(FAC), Mission Bhagiratha,
Mission Bhagiratha Circle,Adilabad, V&QC Division,Nirmal.
Adilabad Dist. Nirmal District.

Lr.No.11/AEE3/ SE / MB(Adilabad)/ Grid/SRSP-ADB/PH-II/AGREEMENT COPIES/2019-20, Dt: 19.06.2019

Sir,
Sub: Mission Bhagiratha Circle-Adilabad-SRSP-Adilabad Segment-–“Providing Drinking Water to
Habitations in SRSP Adilabad Segment in Adilabad District Est.Cost 1530.00 Cr of
SE,TDWSP,Adilabad District Including Operation & Maintenance for 10 Years”-Agreement
Copies-Submitted-Reg.
.
Ref: 1.Your office Lr.No.AEE1/V&QC/Agreement Copies/2019,Dated:10.06.2019

*****

With reference to the subject and reference cited above I am herewith submitting the following Copies
of Agreements Concluded under the Work “Providing Drinking Water to Habitations in SRSP Adilabad
Segment in Adilabad District Est.Cost 1530.00 Cr of SE,TDWSP,Adilabad District Including Operation
& Maintenance for 10 Years” for information and necessary action.

S.No Original Date Remarks


Agreement/Supplementary
No
1 2 3 4

1 04/2015-16 28.10.2015

2 4/INTRA/2016-17 03.08.2016

3 OFC/2016-17 09.09.2016

4 1AMS/2016-17 29.09.2016

5 MSGO128/2016-17 15.11.2016

6 04/A/2016-17 11.01.2017

7 4/INTRA2/2016-17 20.03.2017

8 04/B/2017 30.06.2017
S.No Original Date Remarks
Agreement/Supplementary
No
1 2 3 4

9 04/C/2016-17 03.07.2017

10 04/D/2016-17 30.09.2017

11 04/E/2016-17 24.11.2017

12 04/F/2016-17 30.11.2017

13 04/G/2019-20 18.01.2019

14 01/2018-19 18.01.2019

Enclosure:Agreement Copies(14 No’s)


Yours faithfully,

`
Superintending Engineer(FAC),
Mission Bhagiratha Circle, Adilabad.

Copy to:
The Superintending Engineer,V&QC,MB Circle,Warangal for information
The Executive Engineer,MB Grid Division,Adilabad&Nirmal for information
Copy submitted to
The Chief Engineer-I,Mission Bhagiratha,Hyderabad for favour of kind information.
The Chief Engineer-IV,Mission Bhagiratha,Hyderabad for favour of kind information.
The Engineer-in-Chief,Mission Bhagiratha,Hyderabad for favour of kind information.

S-ar putea să vă placă și