Installation
Objectives
2
Contents
Cabinet Installation
Cable Installation
Equipment Power-On & Power-Off
Board Installation
Attached Equipment Installation
3
Cabinet Installation Modes
1. 机柜
2. 防静电地板
3. 可调底座
4. 地基
1. Cabinet 3.
Adjustable Base
2. Antistatic Floor 4.
Groundsill
© ZTE All rights reserved 8
Installation Flow – Step 1
Removing Cabinet Front/Rear Door
1. The four holes marked with1 are for installing the adjustable base.
2. The four holes marked with2 are for installing the cabinet on the cement
floor.
© ZTE All rights reserved 10
Installation Flow – Step 2
Positioning & Installing Expansion Bolts
1. Pin
2. Hinge
Top routing: Connect End A of the grounding cable with the grounding nut at
the top of the outer cabinet, and then extend to the cabling rack. Connect
End B with the PE copper bar on the DC Power Cabinet.
Bottom routing: Connect End A of the grounding cable with the grounding
nut at the bottom of the inner cabinet. Lead the cable out of the cabinet
bottom to the anti-static floor. Connect End B with the PE copper bar on the
DC Power Cabinet.
© ZTE All rights reserved 19
Installation Flow – Step 11
Connecting Adjacent Cabinets
Cabinet Installation
Cable Installation
Equipment Power-On & Power-Off
Board Installation
Attached Equipment Installation
21
Cable Installation
1. No.1/3/5/7 : -48V
2. No.2/4/6/8 : -48VRTN
Cabinet Installation
Cable Installation
Equipment Power-On & Power-Off
Board Installation
Attached Equipment Installation
41
Equipment Power-On and Power-Off
Power-on check:
Plug out all boards
Use a multimeter to measure whether the power output from the DC
distribution cabinet satisfies the voltage fluctuation range: -57 V DC ~ -40 V
DC.
Use a multimeter to measure the power input to the service subracks. The
voltage range should be -57 V DC ~ -40 V DC.
Set the air switch of the power distribution subrack as ON. Observe the PWR
IN indicator on the power distribution subrack. The indicator should be on.
Set the air switch for each service subrack on power distribution box as "ON".
The fans in the service subracks should operate normally.
Insert all boards to the correct slots.
Power-off procedure:
Turn off the -48 V power switch corresponding to the service subrack on the
panel of the power distribution subrack.
Turn off the -48 V power supply output to the cabinet on the DC power
distribution cabinet.
Cabinet Installation
Cable Installation
Equipment Power-On & Power-Off
Board Installation
Attached Equipment Installation
44
Board Installation
Plugging in Boards
Cabinet Installation
Cable Installation
Equipment Power-On & Power-Off
Board Installation
Attached Equipment Installation
47