Following set up at basic level before you perform the capacity requirement planning :

1. In OPKP-Define Production Scheduling parameter -Availability check -Confirm


Capacity and also Finite Scheduling check box ticked .
2. In OPU3/OPU5-Define Scheduling Parameters -you should mark the following
1. Automatic Scheduling check box should be marked
2. Scheduling Log check box should be marked -generate in case there is a scheduling
error due to capacity over load.
3. Scheduling and Generate Capacity should be ticked.
3. In OPJK Maintain check capacity with SAPSFCG013 overall profile and set indicator -
1 -Release Order -by user decision if capacity is insufficient
4.Work Center - Define the capacity planner group, activate checkbox Relevant for
Finite scheduling, on the capacity header define the shift timings, break timings and unit
of measure, no of individual capacity, enter formula for scheduling in capacity view.
5. Routing - enter the values for the standard values. Use control key with scheduling
and CRP activated.
6. OPD0 and have the following set up : Overall profile : SFAPSFC015 --Inside the
overall profile I have the following set up
1. Selection Profile -SAPSFCS013 SFC: Order view, standard overview
2. Control Profile: SAP___C004: Gen Capacity Availability Check for 1.5 months
3. Time Profile: SAP___Z006 : Gen Capacity Availability Check for 1.5 months
4. Evalution Profile: SAPSFCA013 : Gen Capacity Availability Cheek =3.0D
5. Strategy Profile: SAPSFCVER1-Gen Capacity availability Check
6. Period Profile: SAP___P001 -Weekly period
7. List Profile : SAPSFCI001-Production Planning
Check all of them in place .Then you can go ahead with Capacity Requirement Planning
-Evolution and Leveling -CM21/CM22/CM05/CM07 etc.