OTHER ITEM:
FIRE/BLAST WALL
TECHNICAL BUILDING ASSEMBLY (MD &MZD)
GRATINGS
HANDRAILS
STAIRWAYS
MISCELLANIOUS ( MONORAIL BEAM,ACCESS PLATFORM,PEDESTAL CRANE COLUMN WEST &
EAST,CRANE BOOM REST NO.1 & NO.2, CAISSON PIPES)
PIPING (PIPE SUPPORTS,PIPE SPOOLS, VALVES)
8m
ASSEMBLE LOW:
BOTTOM CHORD: 59T -61T
LSF LSF
BOTTOM CHORD INTERMEDIATE : 29T
ASSEMBLY ASSEMBLY 50m UPPER CHORD : 45T-47T
AREA AREA
UPPER CHORD INTERMEDIATE : 36T -38T
BRACINGS INTERMEDIATE: 2.2TMAX
BRACINGS BETWEEN UC & BC: 12.659T/PIECE
TEMPORARY SUPPORT DECK: 29T
22m HEAVY LIFT: 200T Apprx.
CRANE REQUIRED:
1 60T MOBILE [TEMPORARY SUPPORT/TIMBER FOR SKIDDING ARRANGEMENT, INTERMEDIATE BRACINGS]
2 400T [HEAVY LIFT UNLOADING LSF PARTS & ASSEMBLY HEAVY PARTS & INSTALL]
1 90T [BOOM 45.7M JIB 9.1M]
2. CELLAR DECK ASSEMBLY AREA
24m 38.5m
ASSEMBLE LOW:
PG1D main: 8T CONCRETE BLOCK : 5T
PG11 : 5T DIAGONAL BRACING : 7T
47.5M CD CD 45M HE700A: 2.5T (12m)
PORTION 1 PORTION 2 IPE500 : 1.1T (12m)
NODES: 15t-16.5t, 33t-36t
COLUMN : 15.25t
TRUSSES : 15.32t
CRANE REQUIRED:
2 60T MOBILE [TEMPORARY SUPPORT,HE700A,IPE500]
2 90T CRAWLER [SECONDARY BEAM, MISCELLANIOUS LIFTING ACTIVITY]
[BOOM 45.7M JIB 9.1M]
1 150T CRAWLER [NODES, PLATE GIRDER,COLUMN,TRUSSES, PIPINGS]
SHARING CD1&CD2 [BOOM 45.7M (57.8T@10M , 26.3T@20m, 15.1T@30m)]
24m 36m
ASSEMBLE LOW:
PG main: 9T CONCRETE BLOCK : 5T
52m MD MD PG11 : 6T DIAGONAL BRACING : 7T
PORTION 2 PORTION 1 HE700A: 2.5T (12m)
IPE500 : 1.1T (12m)
NODES:
COLUMN : 15.25t
TRUSSES : 14.5t
CRANE REQUIRED:
1 60T MOBILE [TEMPORARY SUPPORT,HE700A,IPE500]
2 90T CRAWLER [SECONDARY BEAM, MISCELLANIOUS LIFTING ACTIVITY]
CD CD [BOOM 45.7M JIB 9.1M]
PORTION 1 PORTION 2 1 150T CRAWLER [NODES, PLATE GIRDER,COLUMN,TRUSSES, PIPINGS]
SHARING CD1&CD2 [BOOM 45.7M (57.8T@10M , 26.3T@20m, 15.1T@30m)]
1 250T CRAWLER [COLUMN,TRUSSES,MECHANICAL EQUIPMENT,PIPINGS AFTER DECK
[BOOM 57.9 JIB 12.2(65.6T@12m, 42.7T@20m,29.5T@26m, 18.4@36m)
JETTY
SEA
4. MEZZ DECK
36m
ASSEMBLE LOW:
PG11 : 6T CONCRETE BLOCK : 5T
MEZZ HE700A: 2.5T (12m) DIAGONAL BRACING : 7T
46m DECK IPE500 : 1.1T (12m)
IPE400 : 0.8T (12m)
NODES:
CRANE REQUIRED:
1 60T MOBILE [TEMPORARY SUPPORT,HE700A,IPE500]
90T CRAWLER [SECONDARY BEAM, MISCELLANIOUS LIFTING ACTIVITY]
[BOOM 33.5M, (45.6T@6m, 11T@20m)]
1 150T CRAWLER [NODES, PLATE GIRDER,COLUMN,TRUSSES, PIPINGS]
SHARING CD1&CD2 [BOOM 45.7M (57.8T@10M , 26.3T@20m, 15.1T@30m)]
250T CRAWLER [COLUMN,TRUSSES,MECHANICAL EQUIPMENT,PIPINGS AFTER DECK
JETTY [BOOM 57.9 JIB 12.2(65.6T@12m, 42.7T@20m,29.5T@26m, 18.4@36m)
SEA