Documente Academic
Documente Profesional
Documente Cultură
Term of Reference
(ToR)
Contractual Work
Consultancy Service
2. General Description
Dams, besides having great benefits, also have great potential hazards. Dam
that collapses will cause severe flash floods to far downstream which will
cause a lot of casualties, property, public facilities and severe environmental
damage in the downstream area
To prevent such a disaster, every dam must be monitored and maintained
properly. With good monitoring, the dam administrator will know the problems
that are developing in the dam, so that appropriate steps can be taken to
prevent the problem from developing at the dam. Besides being monitored,
the monitored infrastructure must also be in good physical and performance
conditions including the spillway dam
Successful monitoring of dams needs to be supported by routine inspections,
periodic inspections, and extraordinary and special inspections. Periodic
inspections consist of regular periodic inspections carried out every 6 months
and large inspections must be carried out at least once in a period of 5 years.
At present the Spillway Pacal dam has suffered a collapse due to the flooding
that occurred. To improve dam safety, prime infrastructure is needed, namely
with a spillway that is in accordance with the current flood discharge plan. The
compiled design needs to be tested for physical models to test and examine
the performance of the Pacal Dam spillway designed before the construction
is actually carried out
In order to fulfill the mandate of Peraturan Menteri Pekerjaan Umum Dan
Perumahan Rakyat Republik Indonesia Nomor 27/PRT/M/2015 Tentang
Bendungan, to obtain an operating permit and for the implementation of the
Pacal Dam spillway construction, BBWS Bengawan Solo will carry out the
Preparation and Legalization of Operation Permit of Cengklik, Delingan, and
Ketro Dam, and Pacal Dam Physical Model Test. This work is done partially
because physical work will be carried out for the Pacal Dam Spillway Repair
for that the Pacal Dam Physical Model Test work is carried out and completed
first along with the dam data collection which will be carried out operating
permit
b. Delingan Dam
- Location
Desa Delingan, Kec. Karanganyar, Kab. Karanganyar, Jawa Tengah
(7035’15,47”S - 110059’17,27”T)
- Dam
Type : Homogeneous Landfill
Peak Elevation : El. +180,00 m
Peak Width : 4,50 m
Peak Length : 886,00 m
Volume : 300.000 m3
- Spillway
Type : Ogee with door and without door
Capacity : 67 m3/sec
- Outflow Structure
Type : Conduit
Shape : Circle
- Data and Activities that have been carried out
a) Dam Construction year 1920 - 1923 ;
b) Preparation of Operating and Maintenance Guidelines year 2017;
c) Preparation of Reservoir Operation Patterns year 2017;
d) Major Inspection year 2017;
e) EAP Document year 2014
c. Ketro Dam
- Location
Desa Ketro, Kec. Tanon, Kab. Sragen, Jawa Tengah
(7022’48,48”S - 110054’14,50”T)
- Dam
Type : homogeneous landfill
Peak Elevation : El. +102,00 m
Peak Width : 3,00 m
Peak Length : 1200 m
- Spillway
Type : Ogee tanpa pintu
Capacity : 22 m3/dt
Peak Elevation : El. + 99,00 m
Peak Length : 11,00 m
- Outflow Structure
Type : Conduit
Shape : Circle
Capacity : 0,612 m3/sec
Type of operating device : Pintu sorong baja
- Data and Activities that have been carried out
a) Dam Construction year 1975 - 1984;
b) Preparation of Operating and Maintenance Guidelines year 2017;
c) Preparation of Reservoir Operation Patterns year 2017;
d) Major Inspection year 2019;
e) EAP Document year 2012
d. Pacal Dam
- Location
Desa Tretes, Kec. Sugiwaras, Kab. Bojonegoro, Jawa Timur
(7021’44,92”S - 111052’14,54”T)
- Dam
Type : rock pile with upstream concrete membranes
Peak Elevation : El. +117,00 m
Peak Width : 7,00 m
Peak Length : 90 m
- Spillway
Type : Ogee without doors
Capacity : 303,75 m3/dt
Peak Elevation : El. + 115,00 m
Peak Length : 45,00 m
- Outflow Structure
Type : Conduit
Shape : Horseshoe
Outflow discharge : 5,79 m3/sec
Type of operating device : Sliding door
C. TARGET : The target of the activity is the implementation of operations that comply with
the prevailing laws and regulations and the conception of dam safety
E. SOURCES OF FUNDS AND : The Work of Preparation and Determination of Operation Permit of Cengklik,
REQUIRED VALUES Delingan, and Ketro Dam, and Pacal Dam Physical Model Test was funded
from the DOISP Phase-II with total ceiling provided is Rp. 5.000.000.000 (Five
Billion Rupiah)
F. SCOPE OF ACTIVITIES 1. Requirement for Operation Permit
Based on Pasal 91 Permen PUPR 27/PRT/M/2015 about Dam, explained that
dam operations must be carried out according to operating permits. There are
2 requirements that must be fulfilled, namely administrative requirements and
technical requirements described as follows:
a. administrative requirements
1) Request for operating permit
- Major Inspection
- EAP of Dam
- Operating and Maintenance Guidelines of Dam
- Reservoir Operation Patterns
- Dam construction document
2) Identity of Dam Administrator
3) Dam Monitoring Unit Decision Making
4) Permits or other requirements in accordance with the provisions of the
legislation
b. technical requirements
1) Technical Data of Dam
2) Report on filling the initial reservoir
3) Dam behavior analysis report
4) Guidelines for Operation and Maintenance of Dams and their
reservoirs
5) Special incident report during filling of reservoirs
6) Discussion on dam safety at the Technical Session and Plenary
Session of the Dam Safety Commission (KKB)
a.3.iii Bathymetri
(1) Bathimetry is carried out to obtain basic topographic
maps of Dam using GPS and echosounder. Bathimetry
is carried out along predetermined range lines (usually
done before the inundation of the Dam or in the studies
that have been carried out) obtaining the depth data of
the Dam. If there is no transmission line, before the
bathymetry is carried out, the lines must be set first
(2) The bathymetry path must be tried as far as possible
perpendicular to the direction of the river flow which in
the future can be used to monitor and numerical
modeling of changes in the base of the Dam. The
distance between bathymetry points can be less than 50
meters
(3) The density or distance between the paths of the cast,
are set as follows:
- At the top of the upstream slope of the dam: the
distance of the casting line ranges from 15 to 30 m,
with the number of lanes at least 3 (three) lanes.
Bathimetry in this area is primarily intended to obtain
an overview of the condition / geometry of the
upstream slope of the dam to support underwater
inspection activities
- For small dams or in the inundation area up to a
distance of 1 km from the top of the dam the distance
of the bathymetry line ranges from 30 to 60 m, with
a closer distance to the dead storage area
- In the inundation area over a distance of 1 km from
the peak of the dam, the distance of the bathymetry
route ranges from 100 to 200
a.4.iv Instrumentasi
Check the condition and function of the instrument by
conducting a direct reading and conducting an evaluation /
evaluation of the existing monitoring data series. Check and
make sure the hydrological equipment, remote monitoring
system and communication equipment are all functioning well
and evaluating the monitoring data
H. RESPONSIBILITY : The consultant must be fully responsible for the results of the work that has
been made. If in the future there is a discrepancy in the quality of the results
of this study activity, then the consultant must be willing to correct it
2. Withdrawal of Funds
Withdrawal of Fund consist of 2 types, among other :
a. Direct Cost of Personeel / honorium
1) Profesional Staff;
2) Sub. Profesional Staff;
3) Supporting Staff.
b. Cost of Non Personeel
1) Official Travel Cost;
• Professional Staff
• Sub. Professional Staff
2) Vehicle Rental Cost;
• Car
• Motorcycle
3) Cost of Basecamp/Office Rental;
4) Cost of Survey and Physical Model Test of pacal dam;
5) Cost of office needed;
• Rent of Computer
• Rent of Printer
• Rent of Plotter
• Office stationary and consumable
6) Cost of communication (Telephon, Fax, Internet);
7) Cost of making report;
8) Data Purchases;
• The cost of Secondary Data Collection includes image and
maps
9) Discussion of the Preliminary Report;
10) Discussion of Intermediary Reports
11) Discussion of Final Report
12) Technical Meeting Discussion (Balai’s Dam)
13) Plenary Session Discussion (Balai’s Dam)
14) Adjuration for Dam Operation Permit Session
ToR is made so that it can become a reference in the implementation of consultancy services for Preparation and
Determination of Operation Permit of Cengklik, Delingan, and Ketro Dam, and Pacal Dam Physical Model Test