TENTATIVE SCHEDULE PEMBANGUNAN SUTET 500 KV TL DURI KOSAMBI - MUARA KARANG BARU

ID Task Task Name Duration Start Finish Half 1, 2018 Half 2, 2018 Half 1, 2019 Half 2, 2019 Half 1, 2020
Mode N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J
1 500 KV TL DURI KOSAMBI - MUARA KARANG BARU 815 days Thu 28/12/17 Sat 21/03/20
2 ADMINISTRATION 292 days Thu 28/12/17 Mon 15/10/18
3 Contract Signing 0 days Thu 28/12/17 Thu 28/12/17 28/12
4 Contract Effective Date 0 days Mon 15/10/18Mon 15/10/18 15/10
5 KONSTRUKSI 523 days Tue 16/10/18 Sat 21/03/20
6 ENGINEERING 275 days Tue 16/10/18 Wed 17/07/19
7 Preparation Work 5 days Tue 16/10/18 Sat 20/10/18
8 Re - Check Survey & Completed Final Survey 30 days Sun 21/10/18 Mon 19/11/18
9 Completed Clearence of Strip of Land 120 days Wed Wed
Concentric 20/03/19 17/07/19
10 Soil Investigation 30 days Sun 04/11/18 Mon 03/12/18
11 Sondir 30 days Sun 04/11/18 Mon 03/12/18
12 Boring 30 days Sun 04/11/18 Mon 03/12/18
13 Approval Towe Schedule 15 days Tue 20/11/18 Tue 04/12/18
14 Approval Tower Design Including Destruction 45 days Sun 21/10/18 Tue 04/12/18
Test
15 Tower Design Type AA 45 days Sun 21/10/18 Tue 04/12/18
16 Tower Design Type BB 45 days Sun 21/10/18 Tue 04/12/18
17 Tower Design Type CC 45 days Sun 21/10/18 Tue 04/12/18
18 Tower Design Type DD 45 days Sun 21/10/18 Tue 04/12/18
19 Tower Design Type EE 45 days Sun 21/10/18 Tue 04/12/18
20 Tower Design Type FF 45 days Sun 21/10/18 Tue 04/12/18
21 Distruction Test Type AA10+0 63 days Mon 11/02/19Sun 14/04/19
22 Test Single Pile 80 days Sat 02/03/19 Mon 20/05/19
23 Approval Foundation Design Including Loading 21 days Wed Tue 25/12/18
Test 05/12/18
24 Design Pondasi T.2 FF+0 21 days Wed 05/12/18Tue 25/12/18
25 Design Pondasi T.3 BB+3 21 days Wed 05/12/18Tue 25/12/18
26 Design Pondasi T.4 AA+9 21 days Wed 05/12/18Tue 25/12/18
27 Design Pondasi T.5 AA+6 21 days Wed 05/12/18Tue 25/12/18
28 Design Pondasi T.6 AA+6 21 days Wed 05/12/18Tue 25/12/18
29 Design Pondasi T.7 CC+6 21 days Wed 05/12/18Tue 25/12/18
30 Design Pondasi T.8 CC+6 21 days Wed 05/12/18Tue 25/12/18
31 Design Pondasi T.9 AA+3 21 days Wed 05/12/18Tue 25/12/18
32 Design Pondasi T.10 AA+3 21 days Wed 05/12/18Tue 25/12/18
33 Design Pondasi T.11 AA+3 21 days Wed 05/12/18Tue 25/12/18
34 Design Pondasi T.12 AA+3 21 days Wed 05/12/18Tue 25/12/18
35 Design Pondasi T.13 AA+6 21 days Wed 05/12/18Tue 25/12/18
36 Design Pondasi T.14 EE+6 21 days Wed 05/12/18Tue 25/12/18
37 Design Pondasi T.15 AA+3 21 days Wed 05/12/18Tue 25/12/18
38 Design Pondasi T.16 AA+6 21 days Wed 05/12/18Tue 25/12/18
39 Design Pondasi T.17 AA+6 21 days Wed 05/12/18Tue 25/12/18
40 Design Pondasi T.18 AA+6 21 days Wed 05/12/18Tue 25/12/18
41 Design Pondasi T.19 AA+3 21 days Wed 05/12/18Tue 25/12/18
42 Design Pondasi T.20 CC+9 21 days Wed 05/12/18Tue 25/12/18
43 Design Pondasi T.21 CC+9 21 days Wed 05/12/18Tue 25/12/18
44 Design Pondasi T.22 AA+12 21 days Wed 05/12/18Tue 25/12/18
45 Design Pondasi T.23 AA+9 21 days Wed 05/12/18Tue 25/12/18
46 Design Pondasi T.24 AA+9 21 days Wed 05/12/18Tue 25/12/18
47 Design Pondasi T.25 AA+9 21 days Wed 05/12/18Tue 25/12/18
48 Design Pondasi T.26 AA+9 21 days Wed 05/12/18Tue 25/12/18
49 Design Pondasi T.27 AA+9 21 days Wed 05/12/18Tue 25/12/18
50 Design Pondasi T.28 AA+6 21 days Wed 05/12/18Tue 25/12/18
51 Design Pondasi T.29 BB+9 21 days Wed 05/12/18Tue 25/12/18
52 Design Pondasi T.29A BB+15 21 days Wed 05/12/18Tue 25/12/18
53 Design Pondasi T.30 BB+15 21 days Wed 05/12/18Tue 25/12/18
54 Design Pondasi T.31 BB+6 21 days Wed 05/12/18Tue 25/12/18
55 Design Pondasi T.32 AA+6 21 days Wed 05/12/18Tue 25/12/18
56 Design Pondasi T.33 AA+9 21 days Wed 05/12/18Tue 25/12/18
57 Design Pondasi T.34 AA+6 21 days Wed 05/12/18Tue 25/12/18
58 Design Pondasi T.35 AA+6 21 days Wed 05/12/18Tue 25/12/18
59 Design Pondasi T.36 DD+6 21 days Wed 05/12/18Tue 25/12/18
60 Design Pondasi T.37 CC+6 21 days Wed 05/12/18Tue 25/12/18
61 Design Pondasi T.38 CC+12 21 days Wed 05/12/18Tue 25/12/18
62 Design Pondasi T.40 FF+9 21 days Wed 05/12/18Tue 25/12/18
63 Approval Insulator 60 days Tue 06/11/18 Fri 04/01/19
64 Approval Fitting & Accessories 60 days Tue 06/11/18 Fri 04/01/19
65 Approval OPGW 60 days Tue 06/11/18 Fri 04/01/19
66 PROCUREMENT 255 days Wed 05/12/18Fri 16/08/19
67 PO MATERIAL 45 days Wed 05/12/18Fri 18/01/19
68 Steel Stub Angle 14 days Wed 26/12/18Tue 08/01/19
69 Steel Lattice Tower 14 days Wed 05/12/18Tue 18/12/18
70 Insulator 14 days Sat 05/01/19 Fri 18/01/19
71 Fitting & Accessories 14 days Sat 05/01/19 Fri 18/01/19
72 OPGW 14 days Sat 05/01/19 Fri 18/01/19
73 MANUFACTURING AND DELIVERY MATERIAL 220 days Wed 09/01/19Fri 16/08/19
74 Steel Stub Angle 14 days Wed 09/01/19Tue 22/01/19
75 Stub T.2 FF+0 14 days Wed 09/01/19Tue 22/01/19
76 Stub T.3 BB+3 14 days Wed 09/01/19Tue 22/01/19
77 Stub T.4 AA+9 14 days Wed 09/01/19Tue 22/01/19
78 Stub T.5 AA+6 14 days Wed 09/01/19Tue 22/01/19
79 Stub T.6 AA+6 14 days Wed 09/01/19Tue 22/01/19
80 Stub T.7 CC+6 14 days Wed 09/01/19Tue 22/01/19
81 Stub T.8 CC+6 14 days Wed 09/01/19Tue 22/01/19
82 Stub T.9 AA+3 14 days Wed 09/01/19Tue 22/01/19
83 Stub T.10 AA+3 14 days Wed 09/01/19Tue 22/01/19
84 Stub T.11 AA+3 14 days Wed 09/01/19Tue 22/01/19
85 Stub T.12 AA+3 14 days Wed 09/01/19Tue 22/01/19
86 Stub T.13 AA+6 14 days Wed 09/01/19Tue 22/01/19
87 Stub T.14 EE+6 14 days Wed 09/01/19Tue 22/01/19
88 Stub T.15 AA+3 14 days Wed 09/01/19Tue 22/01/19
89 Stub T.16 AA+6 14 days Wed 09/01/19Tue 22/01/19
90 Stub T.17 AA+6 14 days Wed 09/01/19Tue 22/01/19
91 Stub T.18 AA+6 14 days Wed 09/01/19Tue 22/01/19
92 Stub T.19 AA+3 14 days Wed 09/01/19Tue 22/01/19
93 Stub T.20 CC+9 14 days Wed 09/01/19Tue 22/01/19
94 Stub T.21 CC+9 14 days Wed 09/01/19Tue 22/01/19
95 Stub T.22 AA+12 14 days Wed 09/01/19Tue 22/01/19
96 Stub T.23 AA+9 14 days Wed 09/01/19Tue 22/01/19
97 Stub T.24 AA+9 14 days Wed 09/01/19Tue 22/01/19
98 Stub T.25 AA+9 14 days Wed 09/01/19Tue 22/01/19
99 Stub T.26 AA+9 14 days Wed 09/01/19Tue 22/01/19
100 Stub T.27 AA+9 14 days Wed 09/01/19Tue 22/01/19
101 Stub T.28 AA+6 14 days Wed 09/01/19Tue 22/01/19
102 Stub T.29 BB+9 14 days Wed 09/01/19Tue 22/01/19
103 Stub T.29A BB+15 14 days Wed 09/01/19Tue 22/01/19
104 Stub T.30 BB+15 14 days Wed 09/01/19Tue 22/01/19
105 Stub T.31 BB+6 14 days Wed 09/01/19Tue 22/01/19
106 Stub T.32 AA+6 14 days Wed 09/01/19Tue 22/01/19
107 Stub T.33 AA+9 14 days Wed 09/01/19Tue 22/01/19
108 Stub T.34 AA+6 14 days Wed 09/01/19Tue 22/01/19
109 Stub T.35 AA+6 14 days Wed 09/01/19Tue 22/01/19
110 Stub T.36 DD+6 14 days Wed 09/01/19Tue 22/01/19
111 Stub T.37 CC+6 14 days Wed 09/01/19Tue 22/01/19
112 Stub T.38 CC+12 14 days Wed 09/01/19Tue 22/01/19
113 Stub T.40 FF+9 14 days Wed 09/01/19Tue 22/01/19
114 Steel Lattice Tower 60 days Mon 15/04/19Thu 13/06/19
115 Lattice Tower T.2 FF+0 60 days Mon 15/04/19Thu 13/06/19
116 Lattice Tower T.3 BB+3 60 days Mon 15/04/19Thu 13/06/19
117 Lattice Tower T.4 AA+9 60 days Mon 15/04/19Thu 13/06/19
118 Lattice Tower T.5 AA+6 60 days Mon 15/04/19Thu 13/06/19
119 Lattice Tower T.6 AA+6 60 days Mon 15/04/19Thu 13/06/19
120 Lattice Tower T.7 CC+6 60 days Mon 15/04/19Thu 13/06/19
121 Lattice Tower T.8 CC+6 60 days Mon 15/04/19Thu 13/06/19
122 Lattice Tower T.9 AA+3 60 days Mon 15/04/19Thu 13/06/19
123 Lattice Tower T.10 AA+3 60 days Mon 15/04/19Thu 13/06/19
124 Lattice Tower T.11 AA+3 60 days Mon 15/04/19Thu 13/06/19
125 Lattice Tower T.12 AA+3 60 days Mon 15/04/19Thu 13/06/19
126 Lattice Tower T.13 AA+6 60 days Mon 15/04/19Thu 13/06/19
127 Lattice Tower T.14 EE+6 60 days Mon 15/04/19Thu 13/06/19
128 Lattice Tower T.15 AA+3 60 days Mon 15/04/19Thu 13/06/19
129 Lattice Tower T.16 AA+6 60 days Mon 15/04/19Thu 13/06/19
130 Lattice Tower T.17 AA+6 60 days Mon 15/04/19Thu 13/06/19
131 Lattice Tower T.18 AA+6 60 days Mon 15/04/19Thu 13/06/19
132 Lattice Tower T.19 AA+3 60 days Mon 15/04/19Thu 13/06/19
133 Lattice Tower T.20 CC+9 60 days Mon 15/04/19Thu 13/06/19
134 Lattice Tower T.21 CC+9 60 days Mon 15/04/19Thu 13/06/19
135 Lattice Tower T.22 AA+12 60 days Mon 15/04/19Thu 13/06/19
136 Lattice Tower T.23 AA+9 60 days Mon 15/04/19Thu 13/06/19
137 Lattice Tower T.24 AA+9 60 days Mon 15/04/19Thu 13/06/19
138 Lattice Tower T.25 AA+9 60 days Mon 15/04/19Thu 13/06/19
139 Lattice Tower T.26 AA+9 60 days Mon 15/04/19Thu 13/06/19
140 Lattice Tower T.27 AA+9 60 days Mon 15/04/19Thu 13/06/19
141 Lattice Tower T.28 AA+6 60 days Mon 15/04/19Thu 13/06/19
142 Lattice Tower T.29 BB+9 60 days Mon 15/04/19Thu 13/06/19
143 Lattice Tower T.29A BB+15 60 days Mon 15/04/19Thu 13/06/19
144 Lattice Tower T.30 BB+15 60 days Mon 15/04/19Thu 13/06/19
145 Lattice Tower T.31 BB+6 60 days Mon 15/04/19Thu 13/06/19
146 Lattice Tower T.32 AA+6 60 days Mon 15/04/19Thu 13/06/19
147 Lattice Tower T.33 AA+9 60 days Mon 15/04/19Thu 13/06/19
148 Lattice Tower T.34 AA+6 60 days Mon 15/04/19Thu 13/06/19
149 Lattice Tower T.35 AA+6 60 days Mon 15/04/19Thu 13/06/19
150 Lattice Tower T.36 DD+6 60 days Mon 15/04/19Thu 13/06/19
151 Lattice Tower T.37 CC+6 60 days Mon 15/04/19Thu 13/06/19
152 Lattice Tower T.38 CC+12 60 days Mon 15/04/19Thu 13/06/19
153 Lattice Tower T.40 FF+9 60 days Mon 15/04/19Thu 13/06/19
154 Insulator 210 days Sat 19/01/19 Fri 16/08/19
155 Fitting & Accessories 210 days Sat 19/01/19 Fri 16/08/19
156 OPGW 90 days Sat 19/01/19 Thu 18/04/19
157 DISMANTLING EXISTING TRANSMISSION LINE 123 days Tue 30/04/19 Sat 31/08/19
158 Permit to Shutdown the Line 0 days Tue 30/04/19 Tue 30/04/19 30/04
159 Dismantling & Rewinding Conductor Section 1 30 days Wed 01/05/19Thu 30/05/19
160 Dismantling & Rewinding Conductor Section 2 30 days Wed 01/05/19Thu 30/05/19
161 Dismantling Insulator Section 1 15 days Fri 31/05/19 Fri 14/06/19
162 Dismantling Insulator Section 2 15 days Fri 31/05/19 Fri 14/06/19
163 Dismantling & Rewinding Earthwire 30 days Wed 01/05/19Thu 30/05/19
164 Dismantling Tower 24 days Sat 15/06/19 Mon 08/07/19
165 Dismantling Tower Existing T.3 6 days Sat 15/06/19 Thu 20/06/19
166 Dismantling Tower Existing T.4 6 days Fri 21/06/19 Wed 26/06/19
167 Dismantling Tower Existing T.5 6 days Thu 27/06/19 Tue 02/07/19
168 Dismantling Tower Existing T.6 6 days Sat 15/06/19 Thu 20/06/19
169 Dismantling Tower Existing T.7 6 days Fri 21/06/19 Wed 26/06/19
170 Dismantling Tower Existing T.8 6 days Thu 27/06/19 Tue 02/07/19
171 Dismantling Tower Existing T.9 6 days Sat 15/06/19 Thu 20/06/19
172 Dismantling Tower Existing T.10 6 days Fri 21/06/19 Wed 26/06/19
173 Dismantling Tower Existing T.11 6 days Thu 27/06/19 Tue 02/07/19
174 Dismantling Tower Existing T.12 6 days Sat 15/06/19 Thu 20/06/19
175 Dismantling Tower Existing T.13 6 days Fri 21/06/19 Wed 26/06/19
176 Dismantling Tower Existing T.14 6 days Thu 27/06/19 Tue 02/07/19
177 Dismantling Tower Existing T.15 6 days Sat 15/06/19 Thu 20/06/19
178 Dismantling Tower Existing T.16 6 days Fri 21/06/19 Wed 26/06/19
179 Dismantling Tower Existing T.17 6 days Thu 27/06/19 Tue 02/07/19
180 Dismantling Tower Existing T.18 6 days Sat 15/06/19 Thu 20/06/19
181 Dismantling Tower Existing T.19 6 days Fri 21/06/19 Wed 26/06/19
182 Dismantling Tower Existing T.20 6 days Sat 15/06/19 Thu 20/06/19
183 Dismantling Tower Existing T.21 6 days Fri 21/06/19 Wed 26/06/19
184 Dismantling Tower Existing T.22 6 days Thu 27/06/19 Tue 02/07/19
185 Dismantling Tower Existing T.23 6 days Sat 15/06/19 Thu 20/06/19
186 Dismantling Tower Existing T.24 6 days Fri 21/06/19 Wed 26/06/19
187 Dismantling Tower Existing T.25 6 days Thu 27/06/19 Tue 02/07/19
188 Dismantling Tower Existing T.26 6 days Sat 15/06/19 Thu 20/06/19
189 Dismantling Tower Existing T.27 6 days Fri 21/06/19 Wed 26/06/19
190 Dismantling Tower Existing T.28 6 days Thu 27/06/19 Tue 02/07/19
191 Dismantling Tower Existing T.29 6 days Sat 15/06/19 Thu 20/06/19
192 Dismantling Tower Existing T.29A 6 days Fri 21/06/19 Wed 26/06/19
193 Dismantling Tower Existing T.30 6 days Thu 27/06/19 Tue 02/07/19
194 Dismantling Tower Existing T.31 6 days Sat 15/06/19 Thu 20/06/19
195 Dismantling Tower Existing T.32 6 days Fri 21/06/19 Wed 26/06/19
196 Dismantling Tower Existing T.33 6 days Thu 27/06/19 Tue 02/07/19
197 Dismantling Tower Existing T.34 6 days Sat 15/06/19 Thu 20/06/19
198 Dismantling Tower Existing T.35 6 days Thu 27/06/19 Tue 02/07/19
199 Dismantling Tower Existing T.36 6 days Wed 03/07/19Mon 08/07/19
200 Dismantling Tower Existing T.37 6 days Sat 15/06/19 Thu 20/06/19
201 Dismantling Tower Existing T.38 6 days Thu 27/06/19 Tue 02/07/19
202 Dismantling Pondasi 72 days Fri 21/06/19 Sat 31/08/19
203 Dismantling Pondasi Existing T.3 30 days Sun 21/07/19 Mon 19/08/19
204 Dismantling Pondasi Existing T.4 30 days Sat 27/07/19 Sun 25/08/19
205 Dismantling Pondasi Existing T.5 30 days Fri 02/08/19 Sat 31/08/19
206 Dismantling Pondasi Existing T.6 30 days Sun 21/07/19 Mon 19/08/19
207 Dismantling Pondasi Existing T.7 30 days Sat 27/07/19 Sun 25/08/19
208 Dismantling Pondasi Existing T.8 30 days Fri 02/08/19 Sat 31/08/19
209 Dismantling Pondasi Existing T.9 30 days Sun 21/07/19 Mon 19/08/19
210 Dismantling Pondasi Existing T.10 30 days Sat 27/07/19 Sun 25/08/19
211 Dismantling Pondasi Existing T.11 30 days Fri 02/08/19 Sat 31/08/19
212 Dismantling Pondasi Existing T.12 30 days Sun 21/07/19 Mon 19/08/19
213 Dismantling Pondasi Existing T.13 30 days Sat 27/07/19 Sun 25/08/19
214 Dismantling Pondasi Existing T.14 30 days Fri 02/08/19 Sat 31/08/19
215 Dismantling Pondasi Existing T.15 30 days Sun 21/07/19 Mon 19/08/19
216 Dismantling Pondasi Existing T.16 30 days Sat 27/07/19 Sun 25/08/19
217 Dismantling Pondasi Existing T.17 30 days Fri 02/08/19 Sat 31/08/19
218 Dismantling Pondasi Existing T.18 30 days Sun 21/07/19 Mon 19/08/19
219 Dismantling Pondasi Existing T.19 30 days Fri 02/08/19 Sat 31/08/19
220 Dismantling Pondasi Existing T.20 30 days Fri 21/06/19 Sat 20/07/19
221 Dismantling Pondasi Existing T.21 30 days Thu 27/06/19 Fri 26/07/19
222 Dismantling Pondasi Existing T.22 30 days Wed 03/07/19Thu 01/08/19
223 Dismantling Pondasi Existing T.23 30 days Fri 21/06/19 Sat 20/07/19
224 Dismantling Pondasi Existing T.24 30 days Thu 27/06/19 Fri 26/07/19
225 Dismantling Pondasi Existing T.25 30 days Wed 03/07/19Thu 01/08/19
226 Dismantling Pondasi Existing T.26 30 days Fri 21/06/19 Sat 20/07/19
227 Dismantling Pondasi Existing T.27 30 days Thu 27/06/19 Fri 26/07/19
228 Dismantling Pondasi Existing T.28 30 days Wed 03/07/19Thu 01/08/19
229 Dismantling Pondasi Existing T.29 30 days Fri 21/06/19 Sat 20/07/19
230 Dismantling Pondasi Existing T.29A 30 days Thu 27/06/19 Fri 26/07/19
231 Dismantling Pondasi Existing T.30 30 days Wed 03/07/19Thu 01/08/19
232 Dismantling Pondasi Existing T.31 30 days Fri 21/06/19 Sat 20/07/19
233 Dismantling Pondasi Existing T.32 30 days Thu 27/06/19 Fri 26/07/19
234 Dismantling Pondasi Existing T.33 30 days Wed 03/07/19Thu 01/08/19
235 Dismantling Pondasi Existing T.34 30 days Fri 21/06/19 Sat 20/07/19
236 Dismantling Pondasi Existing T.35 30 days Wed 03/07/19Thu 01/08/19
237 Dismantling Pondasi Existing T.36 30 days Tue 09/07/19 Wed 07/08/19
238 Dismantling Pondasi Existing T.37 30 days Fri 21/06/19 Sat 20/07/19
239 Dismantling Pondasi Existing T.38 30 days Wed 03/07/19Thu 01/08/19
240 CONSTRUCTION 296 days Tue 21/05/19 Wed 11/03/20
241 Foundation Work 193 days Tue 21/05/19 Fri 29/11/19
242 Pondasi T.2 FF+0 60 days Tue 21/05/19 Fri 19/07/19
243 Borepile 30 days Tue 21/05/19 Wed 19/06/19
244 Pad Chimny 30 days Thu 20/06/19 Fri 19/07/19
245 Pondasi T.3 BB+3 60 days Tue 20/08/19 Fri 18/10/19
246 Borepile 30 days Tue 20/08/19 Wed 18/09/19
247 Pad Chimny 30 days Thu 19/09/19 Fri 18/10/19
248 Pondasi T.4 AA+9 60 days Mon 26/08/19Thu 24/10/19
249 Borepile 30 days Mon 26/08/19Tue 24/09/19
250 Pad Chimny 30 days Wed 25/09/19Thu 24/10/19
251 Pondasi T.5 AA+6 60 days Sun 01/09/19 Wed 30/10/19
252 Borepile 30 days Sun 01/09/19 Mon 30/09/19
253 Pad Chimny 30 days Tue 01/10/19 Wed 30/10/19
254 Pondasi T.6 AA+6 90 days Tue 20/08/19 Sun 17/11/19
255 Kisdam 30 days Tue 20/08/19 Wed 18/09/19
256 Borepile 30 days Thu 19/09/19 Fri 18/10/19
257 Pad Chimny 30 days Sat 19/10/19 Sun 17/11/19
258 Pondasi T.7 CC+6 60 days Mon 26/08/19Thu 24/10/19
259 Borepile 30 days Mon 26/08/19Tue 24/09/19
260 Pad Chimny 30 days Wed 25/09/19Thu 24/10/19
261 Pondasi T.8 CC+6 90 days Sun 01/09/19 Fri 29/11/19
262 Kisdam 30 days Sun 01/09/19 Mon 30/09/19
263 Borepile 30 days Tue 01/10/19 Wed 30/10/19
264 Pad Chimny 30 days Thu 31/10/19 Fri 29/11/19
265 Pondasi T.9 AA+3 60 days Tue 20/08/19 Fri 18/10/19
266 Borepile 30 days Tue 20/08/19 Wed 18/09/19
267 Pad Chimny 30 days Thu 19/09/19 Fri 18/10/19
268 Pondasi T.10 AA+3 60 days Mon 26/08/19Thu 24/10/19
269 Borepile 30 days Mon 26/08/19Tue 24/09/19
270 Pad Chimny 30 days Wed 25/09/19Thu 24/10/19
271 Pondasi T.11 AA+3 60 days Sun 01/09/19 Wed 30/10/19
272 Borepile 30 days Sun 01/09/19 Mon 30/09/19
273 Pad Chimny 30 days Tue 01/10/19 Wed 30/10/19
274 Pondasi T.12 AA+3 60 days Tue 20/08/19 Fri 18/10/19
275 Borepile 30 days Tue 20/08/19 Wed 18/09/19
276 Pad Chimny 30 days Thu 19/09/19 Fri 18/10/19
277 Pondasi T.13 AA+6 60 days Mon 26/08/19Thu 24/10/19
278 Borepile 30 days Mon 26/08/19Tue 24/09/19
279 Pad Chimny 30 days Wed 25/09/19Thu 24/10/19
280 Pondasi T.14 EE+6 60 days Sun 01/09/19 Wed 30/10/19
281 Borepile 30 days Sun 01/09/19 Mon 30/09/19
282 Pad Chimny 30 days Tue 01/10/19 Wed 30/10/19
283 Pondasi T.15 AA+3 60 days Tue 20/08/19 Fri 18/10/19
284 Borepile 30 days Tue 20/08/19 Wed 18/09/19
285 Pad Chimny 30 days Thu 19/09/19 Fri 18/10/19
286 Pondasi T.16 AA+6 60 days Mon 26/08/19Thu 24/10/19
287 Borepile 30 days Mon 26/08/19Tue 24/09/19
288 Pad Chimny 30 days Wed 25/09/19Thu 24/10/19
289 Pondasi T.17 AA+6 60 days Sun 01/09/19 Wed 30/10/19
290 Borepile 30 days Sun 01/09/19 Mon 30/09/19
291 Pad Chimny 30 days Tue 01/10/19 Wed 30/10/19
292 Pondasi T.18 AA+6 60 days Tue 20/08/19 Fri 18/10/19
293 Borepile 30 days Tue 20/08/19 Wed 18/09/19
294 Pad Chimny 30 days Thu 19/09/19 Fri 18/10/19
295 Pondasi T.19 AA+3 60 days Sun 01/09/19 Wed 30/10/19
296 Borepile 30 days Sun 01/09/19 Mon 30/09/19
297 Pad Chimny 30 days Tue 01/10/19 Wed 30/10/19
298 Pondasi T.20 CC+6 90 days Sun 21/07/19 Fri 18/10/19
299 Kisdam 30 days Sun 21/07/19 Mon 19/08/19
300 Borepile 30 days Tue 20/08/19 Wed 18/09/19
301 Pad Chimny 30 days Thu 19/09/19 Fri 18/10/19
302 Pondasi T.21 CC+6 60 days Sat 27/07/19 Tue 24/09/19
303 Borepile 30 days Sat 27/07/19 Sun 25/08/19
304 Pad Chimny 30 days Mon 26/08/19Tue 24/09/19
305 Pondasi T.22 AA+12 60 days Fri 02/08/19 Mon 30/09/19
306 Borepile 30 days Fri 02/08/19 Sat 31/08/19
307 Pad Chimny 30 days Sun 01/09/19 Mon 30/09/19
308 Pondasi T.23 AA+9 60 days Sun 21/07/19 Wed 18/09/19
309 Borepile 30 days Sun 21/07/19 Mon 19/08/19
310 Pad Chimny 30 days Tue 20/08/19 Wed 18/09/19
311 Pondasi T.24 AA+9 60 days Sat 27/07/19 Tue 24/09/19
312 Borepile 30 days Sat 27/07/19 Sun 25/08/19
313 Pad Chimny 30 days Mon 26/08/19Tue 24/09/19
314 Pondasi T.25 AA+9 60 days Fri 02/08/19 Mon 30/09/19
315 Borepile 30 days Fri 02/08/19 Sat 31/08/19
316 Pad Chimny 30 days Sun 01/09/19 Mon 30/09/19
317 Pondasi T.26 AA+9 60 days Sun 21/07/19 Wed 18/09/19
318 Borepile 30 days Sun 21/07/19 Mon 19/08/19
319 Pad Chimny 30 days Tue 20/08/19 Wed 18/09/19
320 Pondasi T.27 AA+9 60 days Sat 27/07/19 Tue 24/09/19
321 Borepile 30 days Sat 27/07/19 Sun 25/08/19
322 Pad Chimny 30 days Mon 26/08/19Tue 24/09/19
323 Pondasi T.28 AA+6 60 days Fri 02/08/19 Mon 30/09/19
324 Borepile 30 days Fri 02/08/19 Sat 31/08/19
325 Pad Chimny 30 days Sun 01/09/19 Mon 30/09/19
326 Pondasi T.29 BB+9 60 days Sun 21/07/19 Wed 18/09/19
327 Borepile 30 days Sun 21/07/19 Mon 19/08/19
328 Pad Chimny 30 days Tue 20/08/19 Wed 18/09/19
329 Pondasi T.29 ABB+15 60 days Sat 27/07/19 Tue 24/09/19
330 Borepile 30 days Sat 27/07/19 Sun 25/08/19
331 Pad Chimny 30 days Mon 26/08/19Tue 24/09/19
332 Pondasi T.30 BB+15 60 days Fri 02/08/19 Mon 30/09/19
333 Borepile 30 days Fri 02/08/19 Sat 31/08/19
334 Pad Chimny 30 days Sun 01/09/19 Mon 30/09/19
335 Pondasi T.31 BB+9 60 days Sun 21/07/19 Wed 18/09/19
336 Borepile 30 days Sun 21/07/19 Mon 19/08/19
337 Pad Chimny 30 days Tue 20/08/19 Wed 18/09/19
338 Pondasi T.32 AA+6 60 days Sat 27/07/19 Tue 24/09/19
339 Borepile 30 days Sat 27/07/19 Sun 25/08/19
340 Pad Chimny 30 days Mon 26/08/19Tue 24/09/19
341 Pondasi T.33 AA+9 60 days Fri 02/08/19 Mon 30/09/19
342 Borepile 30 days Fri 02/08/19 Sat 31/08/19
343 Pad Chimny 30 days Sun 01/09/19 Mon 30/09/19
344 Pondasi T.34 AA+6 60 days Sun 21/07/19 Wed 18/09/19
345 Borepile 30 days Sun 21/07/19 Mon 19/08/19
346 Pad Chimny 30 days Tue 20/08/19 Wed 18/09/19
347 Pondasi T.35 AA+6 60 days Fri 02/08/19 Mon 30/09/19
348 Borepile 30 days Fri 02/08/19 Sat 31/08/19
349 Pad Chimny 30 days Sun 01/09/19 Mon 30/09/19
350 Pondasi T.36 DD+6 60 days Thu 08/08/19 Sun 06/10/19
351 Borepile 30 days Thu 08/08/19 Fri 06/09/19
352 Pad Chimny 30 days Sat 07/09/19 Sun 06/10/19
353 Pondasi T.37 CC+6 60 days Sun 21/07/19 Wed 18/09/19
354 Borepile 30 days Sun 21/07/19 Mon 19/08/19
355 Pad Chimny 30 days Tue 20/08/19 Wed 18/09/19
356 Pondasi T.38 CC+6 60 days Fri 02/08/19 Mon 30/09/19
357 Borepile 30 days Fri 02/08/19 Sat 31/08/19
358 Pad Chimny 30 days Sun 01/09/19 Mon 30/09/19
359 Pondasi T.40 FF+6 60 days Tue 21/05/19 Fri 19/07/19
360 Borepile 30 days Tue 21/05/19 Wed 19/06/19
361 Pad Chimny 30 days Thu 20/06/19 Fri 19/07/19
362 Erection Work 163 days Sat 20/07/19 Sun 29/12/19
363 Erection Tower T.2 FF+0 30 days Sat 20/07/19 Sun 18/08/19
364 Erection Tower T.3 BB+3 30 days Sat 19/10/19 Sun 17/11/19
365 Erection Tower T.4 AA+9 30 days Fri 25/10/19 Sat 23/11/19
366 Erection Tower T.5 AA+6 30 days Thu 31/10/19 Fri 29/11/19
367 Erection Tower T.6 AA+6 30 days Mon 18/11/19Tue 17/12/19
368 Erection Tower T.7 CC+6 30 days Fri 25/10/19 Sat 23/11/19
369 Erection Tower T.8 CC+6 30 days Sat 30/11/19 Sun 29/12/19
370 Erection Tower T.9 AA+3 30 days Sat 19/10/19 Sun 17/11/19
371 Erection Tower T.10 AA+3 30 days Fri 25/10/19 Sat 23/11/19
372 Erection Tower T.11 AA+3 30 days Thu 31/10/19 Fri 29/11/19
373 Erection Tower T.12 AA+3 30 days Sat 19/10/19 Sun 17/11/19
374 Erection Tower T.13 AA+6 30 days Fri 25/10/19 Sat 23/11/19
375 Erection Tower T.14 EE+6 30 days Thu 31/10/19 Fri 29/11/19
376 Erection Tower T.15 AA+3 30 days Sat 19/10/19 Sun 17/11/19
377 Erection Tower T.16 AA+6 30 days Fri 25/10/19 Sat 23/11/19
378 Erection Tower T.17 AA+6 30 days Thu 31/10/19 Fri 29/11/19
379 Erection Tower T.18 AA+6 30 days Sat 19/10/19 Sun 17/11/19
380 Erection Tower T.19 AA+3 30 days Thu 31/10/19 Fri 29/11/19
381 Erection Tower T.20 CC+9 30 days Sat 19/10/19 Sun 17/11/19
382 Erection Tower T.21 CC+9 30 days Wed 25/09/19Thu 24/10/19
383 Erection Tower T.22 AA+12 30 days Tue 01/10/19 Wed 30/10/19
384 Erection Tower T.23 AA+9 30 days Thu 19/09/19 Fri 18/10/19
385 Erection Tower T.24 AA+9 30 days Wed 25/09/19Thu 24/10/19
386 Erection Tower T.25 AA+9 30 days Tue 01/10/19 Wed 30/10/19
387 Erection Tower T.26 AA+9 30 days Thu 19/09/19 Fri 18/10/19
388 Erection Tower T.27 AA+9 30 days Wed 25/09/19Thu 24/10/19
389 Erection Tower T.28 AA+6 30 days Tue 01/10/19 Wed 30/10/19
390 Erection Tower T.29 BB+9 30 days Thu 19/09/19 Fri 18/10/19
391 Erection Tower T.29A BB+15 30 days Wed 25/09/19Thu 24/10/19
392 Erection Tower T.30 BB+15 30 days Tue 01/10/19 Wed 30/10/19
393 Erection Tower T.31 BB+6 30 days Thu 19/09/19 Fri 18/10/19
394 Erection Tower T.32 AA+6 30 days Wed 25/09/19Thu 24/10/19
395 Erection Tower T.33 AA+9 30 days Tue 01/10/19 Wed 30/10/19
396 Erection Tower T.34 AA+6 30 days Thu 19/09/19 Fri 18/10/19
397 Erection Tower T.35 AA+6 30 days Tue 01/10/19 Wed 30/10/19
398 Erection Tower T.36 DD+6 30 days Mon 07/10/19Tue 05/11/19
399 Erection Tower T.37 CC+6 30 days Thu 19/09/19 Fri 18/10/19
400 Erection Tower T.38 CC+12 30 days Tue 01/10/19 Wed 30/10/19
401 Erection Tower T.40 FF+9 30 days Sat 20/07/19 Sun 18/08/19
402 Stringing Works 120 days Wed 06/11/19Wed 04/03/20
403 Stringing Section 1 60 days Sun 05/01/20 Wed 04/03/20
404 Stringing Section 2 60 days Wed 06/11/19Sat 04/01/20
405 Finishing Work 7 days Thu 05/03/20 Wed 11/03/20
406 PROJECT COMPLETION 10 days Thu 12/03/20 Sat 21/03/20
407 Final Inspection 7 days Thu 12/03/20 Wed 18/03/20
408 Test & Commissioning 3 days Thu 19/03/20 Sat 21/03/20
409 Hand Over to PLN 0 days Sat 21/03/20 Sat 21/03/20 21/03