Sunteți pe pagina 1din 28

3M™ Fire Barrier Duct Wrap 615

Product Data and Installation Instructions

Thinking
Outside
Product
Foil Encapsulated Blanket
Blanket
Flame Spread
0
0
The
Surface Burning Characteristics (ASTM E 84 for 15A, 20A, 5A)
Smoke Developed
0
0 Box
Duct Wrap Fire Protection
Systems for Ventilation
Air Ducts
1. Product Description Other types of duct assemblies that often require fire-resistive
3M™ Fire Barrier Duct Wrap 615 is a fire resistant wrap consisting enclosure are:
of a bio-soluble ceramic fiber blanket encapsulated with a • Dryer Exhaust Vents
scrim-reinforced foil. As a single layer fire resistant wrap, it has • Toilet Exhaust Vents
passed ISO 6944 ‘Fire Resistance Tests – Ventilation Ducts’. This
3M™ Fire Barrier 1000 N/S, 1003 S/L, and 2000+ Silicone Sealant is
non-asbestos wrap contains a safer fiber construction and installs
used in combination with 3M™ Fire Barrier Duct Wrap 615 to firestop
easily because of its high flexibility and strength. With its excellent
the duct when the duct penetrates fire rated floors and walls.
insulating capabilities, low weight and thin profile, it is an ideal
choice for a duct enclosure system.
3. Availability
Features Product Unit Size Units/ ctn. Wt./ ctn.
• One layer wrap for ventilation ducts 98-0400-5551-3
3M™ Fire Barrier 1.5" x 24" x 25' 39.3 lbs.
• High flexibility for installation ease Duct Wrap 615
Roll
(38mm x 61cm x 762cm)
1
17.8 kg
• Thin and lightweight 98-0400-5552-1
• Nominal 6pcf density 3M™ Fire Barrier 1.5" x 48" x 25' 78.6 lbs.
Roll 1
Duct Wrap 615 (38mm x 122cm x 762cm) 35.7 kg
• Foil encapsulated for blanket protection, less dust
and high wrap strength 4. Typical Physical Properties
• Center stitched for ease of handling and banding location
Blanket Color Weight Per Area
• Safer fiber construction* White .75 lb/ft 2 (3.66 kg/m2)

2. Applications 5. Performance
3M™ Fire Barrier Duct Wrap 615 is an ideal fire resistive enclosure 3M™ Fire Barrier Duct Wrap 615 has been tested in accordance
for life safety system ducts. These duct systems are in place to with the following:
allow occupants to safely leave a building in fire scenario. Dampers
ISO 6944, ASTM E 84, ULC/CAN S 102, ASTM E 814, UL 1479,
are frequently omitted from life safety ducts. 3M™ Fire Barrier
ASTM C 1338, ASTM C 411, ASTM C 518
Duct Wrap 615 installed around the duct creates a fire-resistive
enclosure that maintains the integrity of the duct and prevents
Surface Burning Characteristics
the passage of fire from one compartment to the next. Compared
Test Method Flame Spread Smoke Developed
to conventional gypsum enclosures, 3M™ Fire Barrier Duct Wrap Foil Encapsulated Blanket
615 is lighter weight, requires less space and typically has lower ASTM E84 < 25 < 50
installation costs. It is a proven alternative to a 1- or 2-hour fire CAN/ULC S102-03 < 25 < 50
resistant rated shaft enclosure in protecting ventilation ducts as
tested per ISO 6944-85 ‘Fire Resistance Tests – Ventilation Ducts’. Thermal Conductivity
Some smoke-control methods commonly used to achieve life safety Temperature btu•in./(hr.•ft2•F) W/m2•K
500˚F (260˚C) 0.48 0.07
objectives are:
1000˚F (537˚C) 0.97 0.14
• Mechanical Smoke Exhaust 1500˚F (815˚C) 1.57 0.23
• Stairwell Pressurization 1800˚F (982˚C) 1.98 0.29
2000˚F (1093˚C) 2.23 0.33
• Ventilated Vestibules
• Zoned Smoke Control Linear Shrinkage
• Elevator Smoke Control 24 Hr @ 2012°F (1100°C)
• Smokeproof Enclosures with Mechanical Ventilation 1.2%

• Engineered Ventilation Systems

* Has been demonstrated to be soluble in the lungs according to EU guidelines 97/69/EC, for biopersistence.
2
Ventilation Air Duct Listings 6. Installation Techniques
Fire Through-
Resistive Enclosure Penetration Listing 3M™ Fire Barrier Duct Wrap 615 system should be installed in
Rating System Duct System System Agency accordance with the following installation instructions.
1 or 2 1 layer of V-27 W-L-7180, UL
Hours 3M™ Fire W-J-7104
Barrier Duct Material and Equipment
Wrap 615,
3" (76mm).
• 3M™ Fire Barrier Duct Wrap 615 Blanket, 1-1/2" (38mm) thick,
perimeter and 3MU/FRD-120-15 3MU/PH 60-03 Intertek / 24" (61cm) or 48" (122cm) wide, 25' (762cm) standard length.
longitudinal 3MU/PV 120-23 (OPL)
overlaps 3MU/PV 120-25 The 48" (122cm) wide blanket helps to minimize waste.
• Aluminum foil tape.
This is only a partial list of design listings that utilized 3M Fire

• Minimum 1/2" (12.7mm) wide filament tape.
Barrier Duct Wrap 615. Please visit www.3M.com/firestop for a • Carbon steel or stainless steel banding material, minimum
current list of third-party design listings. 1/2" (12.7mm) wide, minimum 0.015" (0.38mm) thick, with steel
banding clips.
For technical data and properties of 3M™ Fire Barrier 1000 N/S
and 1000 N/S, 1003 S/L and 2000+ Silicone Sealants see separate • Hand banding tensioner, crimping tool, and banding cutter.
product data sheets available from your 3M representative or go • Minimum 12 gauge copper-coated steel insulation pins;
to www.3M.com/firestop. galvanized steel speed clips, minimum 1-1/2" (38mm) square
or 1-1/2" (38mm) diameter round, or equivalent sized insulated
Code Compliance cup-head pins; capacitor discharge stud gun.
3M™ Fire Barrier Duct Wrap 615 can be used to comply with • Scrap pieces of 3M™ Fire Barrier Duct Wrap 615 Blanket.
requirements of the following codes: • 3M™ Fire Barrier 1000 N/S, 1003 S/L and 2000+ Silicone Sealant.
• NFPA 92A Standard for Smoke-Control System
Utilizing Barriers and Pressure Differences, Storage
2006 Edition – Section 6.6.2 The 3M™ Fire Barrier Duct Wrap 615 and 3M™ Fire Barrier
• NFPA 92B Standard for Smoke Management 1000 N/S, 1003 S/L and 2000+ Silicone Sealants must be stored
Systems in Malls, Atria, and Large Spaces, in a dry warehouse environment. Pallets should not be stacked.
2005 Edition – Section 7.5.2
Preparatory Work
• NFPA 101® Life Safety Code®, 2006 Edition –
Section(s) 8.6.7, 18.7.7 3M™ Fire Barrier Duct Wrap 615 is installed with common tools,
such as knives, banders and capacitor discharge guns for applying
• International Mechanical Code®, 2006 Edition –
insulation pins. In order to install the duct firestop system, the
Section 513.10.2
surfaces of all the openings and penetrating items need to be clean,
• International Building Code®, 2006 Edition –
dry, frost free and free of dust.
Section 909.10.2
Method
This is only a partial list of code compliance. For the latest
To minimize waste, 3M™ Fire Barrier Duct Wrap 615 material should
code and approval information go to www.3M.com/firestop or
be rolled out tautly before measuring. General instructions for
speak to your authorized 3M distributor or sales representative
installing the 3M™ Fire Barrier Duct Wrap 615 include a one-layer
at (800) 328-1687.
wrap construction applied directly to the duct. The 3M™ Fire Barrier
Duct Wrap 615 Blanket is wrapped around the perimeter of the duct
and is cut to a length to overlap itself not less than 3" (76mm). The
overlap made by adjacent blankets forms the “longitudinal” overlap.
Aluminum foil tape is used to seal all cut edges of the blanket and
any tears in the foil scrim.

3
There are three (3) approved installation techniques For Mechanical Fastening with Pins Only
for installing the 3M™ Fire Barrier Duct Wrap 615 (See Figure 2A–2E)
(See Figures 1A–1D and Figures 2A–2E): Insulation pins are welded to the duct in the centers of the overlaps
a minimum of 1-1/2" (38mm) from each edge of the blanket, and
1. Telescoping 3" (76mm) Overlap Wrap spaced a maximum of 10-1/2" (26.7cm) on center along perimeter
With the telescoping overlap wrap method, each blanket overlaps overlap, and a maximum of 10-1/2" (26.7mm) on center along
one adjacent blanket and each blanket has one edge exposed longitudinal overlaps. The blanket is impaled over the pins and
and one edge covered by the next blanket as shown in Figure 1A held in place by galvanized speed clips. Insulation pins that extend
and 1B. The visible edges of the perimeter overlaps all point in beyond the blanket wrap shall be turned down to eliminate sharp
the same direction. points. Insulated cup-head pins can be used at the same spacing
requirements of the insulation pins.
2. Checkerboard 3" (76mm) Overlap Wrap
With the 3" (76mm) checkerboard overlap wrap method, NOTE: Support hangar systems do not need to be wrapped provided
blankets with both edges exposed alternate with blankets with the hangar rods are at least a minimum of 3/8" (9.53mm) diameter
covered edges, as shown in Figure 1C. The visible edges of the and spaced a maximum of 60" (152cm) on center along the length
perimeter overlaps alternate their directions and appear on every of the duct. Use a minimum 1-1/2" x 1-1/2" x 1/4" (38mm x 38mm
other blanket. x 6.35mm) steel angle steel support channel or SMACNA equivalent
support system. For ducts greater than 1440 in2 and less than
3. Butt Joint With Collar 2040 in2, the trapeze requirements increase to a minimum of
With the butt joint and collar method, adjacent blankets are 2" x 2" x 1/4".
butted tightly together and a 6" (152mm) wide collar of 3M™ Fire
Barrier Duct Wrap is centered over the joint, overlapping each Penetrations (See Figures 3A–3F)
blanket by 3" (76mm) minimum as shown in Figure 1D. When the duct penetrates a fire rated wall, ceiling or floor, an
approved firestop system must be employed. Figures 3A–3F
In all three overlap techniques, the perimeter overlap can occur at illustrate typical conditions.
any location on the duct. The blanket is mechanically attached to
the duct by steel banding or by welded insulation pins and clips for To firestop the duct where it passes through rated assemblies,
all three installation methods listed above. follow the installation parameters detailed in the Intertek Testing
Services (ITS) or Underwriter’s Laboratories (UL) design listings.
For Banding Only (See Figures 1A–1D)
Filament tape can be used to temporarily hold the blanket in place Other Applications
until the banding is applied. The steel banding is applied around Refer to Figures 5–11 for additional typical conditions.
the duct 1-1/2" (38mm) from each edge of the blanket, and
maximum 10-1/2" (26.7cm) centers. The banding is placed around
the material and tightened so as to sufficiently hold the 3M™ Fire
Barrier Duct Wrap 615 in place against the duct, compressing the
foil but not cutting the foil.

Additional Pinning to Prevent Sagging of the Wrap


For ducts 24" (60cm) and larger in width, additional pins are needed
to support the blanket on the bottom horizontal surface and on the
outside face of a vertical duct run. Space pins a maximum of 10-1/2"
(26.7cm) apart in the direction of the blanket width, and a maximum
of 12" (30cm) apart in the direction of the blanket length. Refer to the
following paragraph for more information on Mechanical Fastening
with Pins.

4
7. Maintenance
No maintenance is required when installed in accordance with the
3M Installation Instructions. Once installed, if any section of the
3M™ Fire Barrier Duct Wrap 615 is damaged so that the blanket is
damaged, the following procedures will apply:

• The damaged section should be removed by cutting the steel


banding or removing the clips holding it in place.
• A new section of the same dimension should be cut from a roll
of 3M™ Fire Barrier Duct Wrap 615, either 24" (60.9cm) or
48" (121cm) wide.
• The new section should be placed and fitted, ensuring the same
overlap that existed previously.
• The steel banding should be placed around the material and
tensioned so as to sufficiently hold the 3M™ Fire Barrier Duct
Wrap 615 in place.
• If the blanket has not been damaged but the foil has ripped,
seal the rips with aluminum foil tape.

8. Purchase Information
3M Fire Barrier products are available through a network
of nationwide distributors. For information on where to buy,
go to www.3M.com/firestop.

9. Safe Handling Information


Consult Material Safety Data Sheet prior to handling and disposing
of 3M™ Fire Barrier Duct Wrap 615.

5
Figure 1A—3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
1 or 2 Hour Telescoping Technique with Banding

NOTES
Ducts >24" wide require pinning on the bottom
1. One Layer 3M™ Fire Barrier Duct Wrap 615 side. Pinning may be omitted by banding max.
2. Steel Banding 1/2" (13mm) Wide Minimum Typical 5-1/4" O.C. Ensure that material is held tightly to
3. 3" (76mm) Minimum Longitudinal Overlap the duct.
4. 3" (76mm) Minimum Perimeter Overlap Consult current independent testing laboratories
System integrity is limited by quality of installation. (UL, Intertek) for systems or design details.

6
Figure 1B—Telescoping Overlap Wrap Option
Cross Sectional View

Figure 1C—Checkerboard Overlap Wrap Option


Cross Sectional View

Figure 1D—Butt Joint With Collar Option


Cross Sectional View

1. One Layer 3M™ Fire Barrier Duct Wrap 615


2. Steel Banding 1/2" (13mm) Wide Minimum Typical
3. 3" (76mm) Minimum Longitudinal Overlap
4. 3" (76mm) Minimum Perimeter Overlap
6" (152mm) Wide Collar Made From
5.
3M™ Fire Barrier Duct Wrap 615
6. Firmly Butted Joint Consult current independent testing laboratories
System integrity is limited by quality of installation. (UL, Intertek) for systems or design details.

7
Figure 2A­— 3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
1 or 2 Hour Telescoping Wrap Technique With Weld Pins

1. One Layer 3M™ Fire Barrier Duct Wrap 615


1-1/2" Square (38mm) or 1-1/2" Diameter (38mm)
2.
Galvanized Speed Clips Over 12 Gauge Steel Impaling Pins
3. 3" (76mm) Minimum Longitudinal Overlap
4. 3" (76mm) Minimum Perimeter Overlap Consult current independent testing laboratories
System integrity is limited by quality of installation. (UL, Intertek) for systems or design details.

8
Figure 2B—Telescoping Overlap Wrap Option
Cross Sectional View

Figure 2C—Checkerboard Overlap Wrap Option


Cross Sectional View

Figure 2D—Butt Joint With Collar Option


Cross Sectional View

1. One Layer 3M™ Fire Barrier Duct Wrap 615


1-1/2" Square (38mm) or 1-1/2" Diameter (38mm)
2.
Galvanized Speed Clips Over 12 Gauge Steel Impaling Pins
3. 3" (76mm) Minimum Longitudinal Overlap
4. 3" (76mm) Minimum Perimeter Overlap
6" (152mm) Wide Collar Made From
5.
3M™ Fire Barrier Duct Wrap 615
6. Firmly Butted Joint Consult current independent testing laboratories
System integrity is limited by quality of installation. (UL, Intertek) for systems or design details.

9
Figure 2E—Pinning Techniques
Isometric View

NOTES
After speed clips are installed over impaling pin,
cut off excess pin length or bend pins flush.
Impaling pins shall be 12 gauge copper-coated
steel.
Typical Impaling Pin Length:
Min. 4-1/2"
Typical Impaling Pin Spacing:
Max. 10-1/2" O.C. along duct length.
1. Duct
Max. 12" O.C. across duct width.
2. 3M™ Fire Barrier Duct Wrap 615
A cup head pin length shall be chosen that
3. Impaling Pin ensures the 3M™ Fire Barrier Duct Wrap 615
4. Speed Clip material is held tightly to the duct.
5. Insulated Cup Head Pin Consult current independent testing laboratories
System integrity is limited by quality of installation. (UL, Intertek) for systems or design details.

10
Figure 3A—3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
1 or 2 Hour Through-Penetration Systems
Concrete Floor or Wall Assembly
Firestopped to Bare Duct

NOTES
Individual Intertek (OPL) Fire Penetration Seal
1. Concrete Floor/Ceiling or Wall Assembly
Design Listing are available from the Intertek
2. Duct Directory of Listed Products
3A. One Layer 3M™ Fire Barrier Duct Wrap 615
Underwriters Laboratories Inc. (UL) Through-
3B. Banding or Pinning Penetration Firestop Systems are available from
3C. Packing Material the UL Online Certifications Directory
3M™ Fire Barrier 1000 N/S, 1003 S/L or 2000+ Silicone Systems are also available at 3M.com/firestop
Sealant For Wall Assembly Apply Sealant at Both Faces of
3D. For duct sizes ≥ 1440 in2 the through-penetration
Wall. For Floor Assembly, Sealant Required at Top of Floor Only.
3M™ Fire Barrier 1003 S/L Not Suitable For Wall Applications. designs include retaining angles.
3E. 24" Wide Collar (1 layer of 3M™ Fire Barrier Duct Wrap 615) For duct sizes ≤ 1440 in2 the through-penetration
System integrity is limited by quality of installation. designs do not require collars.

11
Figure 3B—3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
1 or 2 Hour Through-Penetration Systems
Concrete Floor or Wall Assembly
Firestopped to Duct Wrap Envelope

NOTES
Individual Intertek (OPL) Fire Penetration Seal
1. Concrete Floor/Ceiling or Wall Assembly
Design Listing are available from the Intertek
2. Duct Directory of Listed Products
3A. One Layer 3M™ Fire Barrier Duct Wrap 615
Underwriters Laboratories Inc. (UL) Through-
3B. Banding or Pinning Penetration Firestop Systems are available from
3C. Packing Material the UL Online Certifications Directory
3M™ Fire Barrier 1000 N/S, 1003 S/L or 2000+ Silicone Systems are also available at 3M.com/firestop
Sealant For Wall Assembly Apply Sealant at Both Faces of
3D. For duct sizes ≥ 1440 in2 the through-penetration
Wall. For Floor Assembly, Sealant Required at Top of Floor Only.
3M™ Fire Barrier 1003 S/L Not Suitable For Wall Applications. designs include retaining angles.
3E. 24" Wide Collar (1 layer of 3M™ Fire Barrier Duct Wrap 615) For duct sizes ≤ 1440 in2 the through-penetration
System integrity is limited by quality of installation. designs do not require collars.

12
Figure 3C—3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
1 or 2 Hour Through-Penetration Systems
Gypsum Wallboard Assembly

NOTES
Individual Intertek (OPL) Fire Penetration Seal
Design Listing are available from the Intertek
Directory of Listed Products
1. Gypsum Wall Assembly Underwriters Laboratories Inc. (UL) Through-
2. Duct Penetration Firestop Systems are available from
3A. One Layer 3M™ Fire Barrier Duct Wrap 615 the UL Online Certifications Directory
3B. Banding or Pinning Systems are also available at 3M.com/firestop
3C. Packing Material For duct sizes ≥ 1440 in2 the through-penetration
3D. 3M Fire Barrier 1000 N/S or 2000+ Silicone Sealant

designs include retaining angles.
3E. 24" Wide Collar (1 layer of 3M™ Fire Barrier Duct Wrap 615) For duct sizes ≤ 1440 in2 the through-penetration
System integrity is limited by quality of installation. designs do not require collars.

13
Figure 3D—3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
1 or 2 Hour Through-Penetration Systems
Shaftwall Assembly

NOTES
Individual Intertek (OPL) Fire Penetration Seal
Design Listing are available from the Intertek
Directory of Listed Products
1. Gypsum Wall Assembly Underwriters Laboratories Inc. (UL) Through-
2. Duct Penetration Firestop Systems are available from
3A. One Layer 3M™ Fire Barrier Duct Wrap 615 the UL Online Certifications Directory
3B. Banding or Pinning Systems are also available at 3M.com/firestop
3C. Packing Material For duct sizes ≥ 1440 in2 the through-penetration
3D. 3M Fire Barrier 1000 N/S or 2000+ Silicone Sealant

designs include retaining angles.
3E. 24" Wide Collar (1 layer of 3M™ Fire Barrier Duct Wrap 615) For duct sizes ≤ 1440 in2 the through-penetration
System integrity is limited by quality of installation. designs do not require collars.

14
Figure 3E—3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
1 or 2 Hour Through-Penetration Systems
Fire Rated Wood/Gypsum—Floor/Ceiling Assembly

NOTES
Individual Intertek (OPL) Fire Penetration Seal
Design Listing are available from the Intertek
Directory of Listed Products
1. Floor—Ceiling Assembly Underwriters Laboratories Inc. (UL) Through-
2. Duct Penetration Firestop Systems are available from
3A. One Layer 3M™ Fire Barrier Duct Wrap 615 the UL Online Certifications Directory
3B. Banding or Pinning Systems are also available at 3M.com/firestop
3C. Packing Material For duct sizes ≥ 1440 in2 the through-penetration
3D. 3M Fire Barrier 1000 N/S, 1003 S/L or 2000+ Silicone Sealant

designs include retaining angles.
3E. 24" Wide Collar (1 layer of 3M™ Fire Barrier Duct Wrap 615) For duct sizes ≤ 1440 in2 the through-penetration
System integrity is limited by quality of installation. designs do not require collars.

15
Figure 3F—3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
1 or 2 Hour Through-Penetration Systems
Fire Rated Concrete Roof Assembly

NOTES
Individual Intertek (OPL) Fire Penetration Seal
1. Roof Assembly Design Listing are available from the Intertek
2. Duct Directory of Listed Products
3A. One Layer 3M™ Fire Barrier Duct Wrap 615 Underwriters Laboratories Inc. (UL) Through-
3B. Banding or Pinning Penetration Firestop Systems are available from
3C. Packing Material the UL Online Certifications Directory
3D. 3M™ Fire Barrier 1000 N/S, 1003 S/L or 2000+ Silicone Sealant Systems are also available at 3M.com/firestop
3E. 24" Wide Collar (1 Layer of 3M Fire Barrier Duct Wrap 615)

For duct sizes ≥ 1440 in2 the through-penetration
4. Roof Flashing designs include retaining angles.
5. Vent Flashing For duct sizes ≤ 1440 in2 the through-penetration
System integrity is limited by quality of installation. designs do not require collars.

16
Figure 4—3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
1 or 2 Hour Suggested Three Sided Wrap

1. Concrete Slab
2. One Layer 3M™ Fire Barrier Duct Wrap 615
Concrete Fasteners — Minimum 1/4" (6mm)
3.
Diameter Steel Concrete Anchors
1/8" (3mm) Thick x 2"–3" (50mm–76mm) Wide
4.
Bar Stock Perforated 12" (30cm) O.C.
5. Duct
6. Banding
7. Banding Clips
System integrity is limited by quality of installation.

17
Figure 5—3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
1 or 2 Hour Suggested Two Sided Wrap

1. Concrete Slab
2. One Layer 3M™ Fire Barrier Duct Wrap 615
Concrete Fasteners — Minimum 1/4" (6mm)
3.
Diameter Steel Concrete Anchors
1/8" (3mm) Thick x 2"–3" (50mm–76mm) Wide
4.
Bar Stock Perforated 12" (30cm) O.C.
5. Duct
6. Banding
7. Banding Clips
System integrity is limited by quality of installation.

18
Figure 6—3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
1 or 2 Hour Suggested 90° Shaft Wall Transition

1. Gypsum Shaft Enclosure


2. One Layer 3M™ Fire Barrier Duct Wrap 615
3. 3" (76mm) Minimum Overlap
NOTES
4. Steel Bands and Clips
5. 1/4" Steel Toggle Bolts This scenario depicts penetration into a rated shaft
enclosure and the firestop system is asymmetric.
6. Bar Stock 2" Wide 1/8" Thick Perforated 12" O.C.
For this reason, the fire protective characteristic
7. Packing Material of this system is relevant only to fires existing
8. 3M™ Fire Barrier 1000 N/S or 2000+ Silicone Sealant external to the shaft construction. It does not apply
System integrity is limited by quality of installation. to fires internal to the shaft enclosure.

19
Figure 7—3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
1 or 2 Hour Suggested Horizontal Shaft Wall Transition

1. Shaft Enclosure
2. Shaft Clearance, per Building Code (If Required)
3. Duct
4. One Layer 3M™ Fire Barrier Duct Wrap 615
5. Steel Bands and Clips
6. 2" x 1/8" Thick Bar Stock Perforated 12" O.C.
7. Toggle Bolts
8. Concrete Floor/Ceiling
9. Concrete Anchor with Washer
System integrity is limited by quality of installation.

20
Figure 8—3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
Rectangular/Square Duct
1 or 2 Hour Suggested Shaft Wall Termination

NOTES
This scenario depicts penetration into a rated shaft
enclosure and the firestop system is asymmetric.
For this reason, the fire protective characteristic
of this system is relevant only to fires existing
external to the shaft construction. It does not apply
to fires internal to the shaft enclosure.
Individual Intertek (OPL) Fire Penetration Seal
1. Gypsum Shaftwall Assembly Design Listing are available from the Intertek
2. Duct— Rectangular/Spiral Wound Round Directory of Listed Products
3A. One Layer 3M™ Fire Barrier Duct Wrap 615 Underwriters Laboratories Inc. (UL) Through-
3B. Banding or Pinning Penetration Firestop Systems are available from
the UL Online Certifications Directory
3C. Packing Material
3D. 3M™ Fire Barrier 1000 N/S or 2000+ Silicone Sealant Systems are also available at 3M.com/firestop
24" Wide Collar (1 Layer 3M™ Fire Barrier Duct Wrap For duct sizes ≥ 1440 in2 the through-penetration
3E.
615) (If Applicable) designs include retaining angles.
4. Retaining Angles (If Applicable) For duct sizes ≤ 720 in2 the through-penetration
System integrity is limited by quality of installation. designs do not require collars.

21
Figure 9A—3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
1 or 2 Hour Round Duct Elbow Configuration
Installation Recommendation

1. One Layer 3M™ Fire Barrier Duct Wrap 615


2. Round Duct
3. 3" (76mm) Minimum Overlap
4. 1/2" Steel Bands Consult current independent testing laboratories
System integrity is limited by quality of installation. (UL, Intertek) for systems or design details.

22
Figure 9B—3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
1 or 2 Hour Rectangle Duct Elbow Installation Recommendation

1. Perimeter NOTES
2. 3" Overlap Place overlap on opposite side of horizontal pattern.
3. Hole Cut Off—Center Consult current independent testing laboratories
System integrity is limited by quality of installation. (UL, Intertek) for systems or design details.

23
Figure 9C—3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
1 or 2 Hour Banding Pattern Suggested Installation

1. Duct
2. One Layer 3M™ Fire Barrier Duct Wrap 615
3. 3" (76mm) Minimum Overlap
4. 1/2" Steel Bands
Chalker bands added on all sides to secure wrap when
5.
10-1/2" spacing cannot be maintained Consult current independent testing laboratories
System integrity is limited by quality of installation. (UL, Intertek) for systems or design details.

24
Figure 9D—3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
1 or 2 Hour Vertical Duct Runs Installation Recommendation

1. One Layer 3M™ Fire Barrier Duct Wrap 615


1-1/2" Square or 1-1/2" Round Galvanized Speed Clips Over
2.
12 Gauge Galvanized Steel Impaling Pins
3. 3" (76mm) Minimum Longitudinal Overlap (Not Shown)
4. 3" (76mm) Minimum Perimeter Overlap
5. 1/2" Steel Bands Consult current independent testing laboratories
System integrity is limited by quality of installation. (UL, Intertek) for systems or design details.

25
Figure 10—3M™ Fire Barrier Duct Wrap 615
Fire Rated Ductwork
Hanging Support Details

THIS INFORMATION SHOULD BE PROVIDED TO THE MECHANICAL


CONTRACTOR FOR USE IN LAYING OUT THEIR DUCT HANGER LOCATIONS.

NOTES
In order to facilitate the application of
3M™ Fire Barrier Duct Wrap 615 to the installed
ductwork, so the rods trapeze hangers are
outside the wrap envelope, the carbon steel
thread hanging support rods shall be:
1. Installed to provide a 3-1/2" to 4-1/2"
clearance between the rod and the side
of the duct.

2. The rods should be cut 2-1/2" longer than


normally required in order to permit the cradles
to be reinstalled onto the threaded rods after
the duct has been wrapped.

Consult current independent testing laboratories


(UL, Intertek) for systems or design details.

26
Figure 11—3M™ Fire Barrier Duct Wrap 615
Ventilation Air Duct Systems
Suggested Wrap Around Trapeze Hanger & Rod

NOTE: CREATE OPENING IN WRAP SO IT CLOSELY


FOLLOWS THE CONTOUR OF THE PENETRATING TRAPEZE

1. All Thread Rod


2. Trapeze Hanger
3. 3M™ Fire Barrier Duct Wrap 615
4. 1/2" Crown of CP 25WB+ Caulk Consult current independent testing laboratories
System integrity is limited by quality of installation. (UL, Intertek) for systems or design details.

27
Warranty and Limited Remedy
This product will be free from defects in material and manufacture for a period of ninety (90) days from date of purchase. 3M MAKES NO OTHER
WARRANTIES INCLUDING, BUT NOT LIMITED TO, ANY IMPLIED WARRANTY OR MERCHANTABILITY OR FITNESS FOR A PARTICULAR
PURPOSE. User is responsible for determining whether the 3M product is fit for a particular purpose and suitable for user's method of application.
If this 3M product is proved to be defective within the warranty period stated above, your exclusive remedy and 3M's sole obligations shall be, at
3M's option, to replace or repair the 3M product or refund the purchase price of the product.

Limitation of Liability
Except where prohibited by law, 3M will not be liable for any loss or damages arising from the use of this 3M product, whether direct, indirect,
special, incidental or consequential, regardless of the legal theory asserted, including warranty, contract, negligence or strict liability.

ERTEK A PO
INT EG IN
M
O

T
CM

C W US C AB E US
L

S
ar
nock Herse OR A ORI
y

T
BATTS AND BLANKETS FOR USE DUCT WRAP MATERIALS FOR USE
IN FIRE RESISTIVE DUCT ASSEMBLIES IN THROUGH-PENETRATION
SEE UL DIRECTORY OF PRODUCTS FIRESTOP SYSTEMS
CERTIFIED FOR CANADA AND SEE SEE UL DIRECTORY OF PRODUCTS
UL FIRE RESISTANCE DIRECTORY CERTIFIED FOR CANADA AND
90G9 UL FIRE RESISTANCE DIRECTORY
90G9

Building and Commercial Services Division


3M Center 223-2S-24
St. Paul, MN 55144-1000
Phone 800-328-1687 Please recycle. Printed in U.S.A 3M is a trademark of 3M Company.
Fax 888-362-2737 © 3M 2008. All rights reserved. All other trademarks are the property
www.3M.com/firestop 98-0213-4371-4 of their respective owners.

S-ar putea să vă placă și