ACTUAL RATES OF BITUMEN VG-10 AT PANIPAT INCLUDING TAXES as on 01/07/2014

Bulk Packed
Bitumen 80/100 (VG-10) 41460.00 Bitumen 80/100 (VG-10) 44460.00
Add 14.42 % excise duty 5979.00 Add 14.42 % excise duty 6411.00
Add 3% educational tax on excise 179.00 Add 3% educational tax on excise 192.00
duty duty
47618.00 51063.00
Add 5.25% VAT 2500.00 Add 5.25% VAT 2681.00
Total 50118.00 Total 53744.00
Add. 5 % Entry tax 2506 Add. 5 % Entry tax 2687
Total 52624.00 Total 56431.00
ACTUAL RATES OF BITUMEN EMULSION AT PANIPAT INCLUDING TAXES as on 1/02/2014

Bitumen Emulsion (Medium) 34640.00 Bitumen Emulsion (Medium) 38490.00


Add 14.42 % excise duty 4995.00 Add 14.42 % excise duty 5550.00
Add 3% educational tax on excise 150.00 Add 3% educational tax on excise 167.00
duty duty
39785.00 44207.00
Add 5.25% VAT 2089.00 Add 5.25% VAT 2321.00
Total 41874.00 Total 46528.00
Add. 5 % Entry tax 2094 Add. 5 % Entry tax 2326
Total 43968.00 Total 48854.00
Bitumen Emulsion Rapid 34440.00 Bitumen Emulsion Rapid 38290.00
Add 14.42 % excise duty 4966.00 Add 14.42 % excise duty 5521.00
Add 3% educational tax on excise 149.00 Add 3% educational tax on excise 166.00
duty duty
39555.00 43977.00
Add 5.25% VAT 2077.00 Add 5.25% VAT 2309.00
Total 41632.00 Total 46286.00
Add. 5 % Entry tax 2082 Add. 5 % Entry tax 2314
Total 43714.00 Total 48600.00
Bitumen Emulsion Slow 32820.00 Bitumen Emulsion Slow 36670.00
Add 14.42 % excise duty 4733.00 Add 14.42 % excise duty 5288.00
Add 3% educational tax on excise 142.00 Add 3% educational tax on excise 159.00
duty duty
37695.00 42117.00
Add 5.25% VAT 1979.00 Add 5.25% VAT 2211.00
Total 39674.00 Total 44328.00
Add. 5 % Entry tax 1984 Add. 5 % Entry tax 2216
Total 41658.00 Total 46544.00

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.
ACTUAL RATES OF BITUMEN AT PANIPAT INCLUDING TAXES as on 16/09/2017
Bulk Packed
Bitumen 80/100 (VG-10) Panipat 23140.00 Bitumen 80/100 (VG-10) Panipat 26240.00

Add 18 % GST 4165.00 Add 18 % GST 4723.00

27305.00 30963.00

Add. 5 % Entry tax 1365.00 Add. 5 % Entry tax 1548.00

Total 28670.00 Total 32511.00

Bitumen 60/70 (VG-30) 23940.00 Bitumen 60/70 (VG-30) 27040.00

Add 18 % GST 4309.00 Add 18 % GST 4867.00

28249.00 31907.00

Add. 5 % Entry tax 1412.00 Add. 5 % Entry tax 1595.00

Total 29661.00 Total 33502.00

Bitumen Emulsion (Medium) 19790.00 Bitumen Emulsion (Medium) 0.00


Haldia (Haldia)
Add 18 % GST 3562.00 Add 18 % GST 0.00

23352.00 0.00

Add. 5 % Entry tax 1168.00 Add. 5 % Entry tax 0.00

Total 24520.00 Total 0.00

Bitumen Emulsion Rapid 19920.00 Bitumen Emulsion Rapid 23870.00


(chennai) (Chennai)
Add 18 % GST 3586.00 Add 18 % GST 4297.00

23506.00 28167.00

Add. 5 % Entry tax 1175.00 Add. 5 % Entry tax 1408.00

Total 24681.00 Total 29575.00

Bitumen Emulsion Slow (Chennai) 32080.00 Bitumen Emulsion Slow (Chennai) 36030.00
Add 18 % GST 5774.00 Add 18 % GST 6485.00

37854.00 42515.00

Add. 5 % Entry tax 1893.00 Add. 5 % Entry tax 2126.00

Total 39747.00 Total 44641.00

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.
Abstract of Carriage

Name of Work :-

Sr. No. Description of Item Amount Unit

1 Cement 245.85 Tonne

2 Sand 682.60 Cum

3 Aggregate 40mm and above 784.60 Cum

4 Aggregate 40mm and below 784.60 Cum

5 Cut Stone 427.05 Cum

6 Boulder 427.05 Cum

7 Bitumen 1522.95 Tonne

Bitumen Emulsion 6131.40 Tonne

CRRI Bitchem Cold Mix binder 0.00 Tonne

8 Hume Pipe 1448.24 Rmt.

9 Steel 262.25 Tonne

10 Well graded gravel / soil aggregate base material for 427.05 Cum
grading-I as per table 400.1 of specification
CHAPTER A
Basic Rates of Labour

Item Code Sl. No. Description of Labour Unit Rate Excluding Rate including
paid Holiday 1/6th paid Holiday
(Rs.) (Rs.)

0102 L-01 Bhisti day 210.00 245.00

0148 L-02 Bitumen Sprayer day 210.00 245.00

0103 L-03 Blacksmith day 252.00 294.00

0145 L-04 Blaster day 252.00 294.00

0111 L-05 Carpenter 1st class day 331.00 386.17

0156 L-06 Chips spreader day 210.00 245.00

0144 L-07 Chiseller day 265.00 309.17

0133 L-08 Dresser (Skilled) day 210.00 245.00

0143 L-09 Driller day 210.00 245.00

0157 L-10 Electrican day 252.00 294.00

0122 L-11 Fitter day 252.00 294.00

0128 L-12 Mason (1st Class) day 331.00 386.17

0129 L-13 Mason (2nd Class) day 252.00 294.00

0134 L-14 Mate day 210.00 245.00

0116 L-15 Mazdoor (Unskilled) day 210.00 245.00

0'115 L-16 Mazdoor (Semi skilled) day 210.00 245.00

0149 L-17 Mazdoor (Skilled) day 210.00 245.00

0137 L-18 Painter (1st class) day 252.00 294.00

0153 L-19 Plumber day 252.00 294.00

0150 L-20 Surveyor day 331.00 386.17

0158 L-21 White Washer day 225.00 262.50

Certified that the labour rates are as per notification issued vide Principal Secretary (Finance) Government Himachal
Pradesh Letter No. Fin.(PR)B(7)-33/2010 dated 07/04/2017 and being paid to the casual labour employed by the deptt. on
M/Roll basis.

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.
Material Rate

Sr. Description Unit Present Remarks


No. Market
Rate
1 Cement Tonne 7400.00 Market rate
2 Tor Steel Tonne 49000.00 Market rate
3 Detonaters 100Nos. 1600.00 Market rate
4 Special Gelatine 80% Kg. 98.00 Market rate
5 Safety fuse coil Coil 24.00 Market rate
6 RCC Hume Pipe 900mm NP2 Meter 3016.00 Factory site
7 Collar Nos. 0.00 Factory site
RCC Hume Pipe 900mm NP3 with collar Meter 4119.00 Factory site
8 Stone aggregate 90mm size Cum. 933.00 Crusher site
9 Stone aggregate 75mm size Cum. 933.00 Crusher site
10 Stone aggregate 63mm size Cum. 933.00 Crusher site
11 Stone aggregate 50mm size Cum. 933.00 Crusher site
12 Stone aggregate 40mm size Cum. 1069.00 Crusher site
13 Stone aggregate 25mm size Cum. 1042.00 Crusher site
14 Stone aggregate 20mm size Cum. 1276.00 Crusher site
15 Stone aggregate 12/12.5mm size Cum. 929.00 Crusher site
16 Stone aggregate 10mm size Cum. 1281.00 Crusher site
17 Stone aggregate 6mm size Cum. 983.00 Crusher site
18 Sand Cum. 1101.00 Quarry site
19 Quarried stone in block Cum. 1061.00 Quarry site
Stone for coursed rubble masonry 1st. Sort. Cum. 1368.00 Quarry site
Stone for coursed rubble masonry 2nd. Sort. Cum. 1303.00 Quarry site
20 Oridinary quarried stone Cum. 1170.00 Quarry site
21 Through, bond stone Nos. 30.00 Quarry site
22 Stone for soling, filling crate Cum. 766.00 Quarry site
23 Stone for pitching Cum. 766.00 Quarry site
Stone spalls Cum. 751.00 Quarry site
Loose stone for filling Cum. 760.00 Quarry site
24 53 to 9.5mm Cum. 947.00 Crusher site
25 9.5 to 2.36mm Cum. 981.00 Crusher site
26 13.2 to 5.6mm Cum. 1220.00 Crusher site
27 2.36 and below Cum. 1093.00 Crusher site
28 Well graded gravel / soil aggregate base material of Cum. 817.00 Quarry site
nominal maximum size 40mm
Well graded gravel / soil aggregate base material for Cum. 938.00 Quarry site
grading-I as per table 400.1 of specification
29 90 to 45mm Cum. 952.00 Crusher site
30 63 to 45mm Cum. 999.00 Crusher site
31 50 to 20mm Cum. 1067.00 Crusher site
32 Bitumen 80/100 (VG-10) Tonne 34992.53 Sunder Nagar
depot
33 Bitumen Emulsion (SS-I) Tonne 45198.00 Sunder Nagar
depot
34 Bitumen Emulsion (RS-I) Tonne 42793.00 Sunder Nagar
depot
35 Bitumen Emulsion (MS) Tonne 47091.00 Sunder Nagar
depot
36 Bitchem Regular Emulsion (RS-1) Tonne ----do------
37 Bitchem Regular Emulsion (SS-1) Tonne ----do------
38 Bitchem Regular Emulsion (SS-2) Tonne ----do------
39 CRRI- Bitchem Cold mix binder (All in one) Tonne 0.00 ----do------
40 Stone Chipps 13.2mm to 5.6mm 0.27Cum/10Sqm. Cum. 1103.00 Crusher site
41 Crushed Stone Chipping 13.2mm nominal size Cum. 1220.00 Crusher site
42 Stone screening Type B 11.2 mm Cum. 1213.00 Crusher site
43 Cement primer as per specification ltr. 149.00 Market rate
44 Epoxy primer/red oxide ltr. 206.00 Market rate
45 Epoxy paint ltr. 374.00 Market rate
46 Paint ltr. 312.00 Market rate
47 Water Kl. 102.00 Market rate
48 Binding material Cum. 82.00 Market rate
49 Binding material for road Cum. 539.00 Market rate
50 Binding wire Kg. 70.00 Market rate
51 G.I. Pipe 100mm dia. Meter 625.00 Market rate
52 PVC pipe 100 mm dia Metre 260.00 Market rate
53 Corrison resistant structural steel Kg. 110.00 Market rate
54 GI Wire 4mm dia Kg. 82.00 Market rate
55 Filter Media Cum. 751.00 Market rate
56 Cast steel rocker bearing assembly of 250 tonne Each 75000.00 Market rate
57 Forged steel roller bearing assembly of 250 tonne Each 80000.00 Market rate
58 Granular material Cum. 376.00 Quarry site
59 MS Tube Kg. 91.00 Market rate
60 Angle iron Kg. 45.00 Market rate
61 1.6 mm thick MS sheet duly painted per sqm. 1451.00 Market rate
62 1.5 mm and 1.6 mm thick MS sheet duly painted per sqm. 1554.00 Market rate

Certified that the rate taken above for material are the
lowest prevailing market rates in the area.

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar
Usage Rates of Plant and Machinery
Sr. No. Machinery Unit Rate as per Enhancement Present Rate
HPSR 2016 of machinery
rate
1 Dozer D-50-A15 @ 43.28 cum per hour Per Hour 3160.00 0.00 3160.00
2 Motor Grader 3.35Mtr Grade Per Hour 3513.00 0.00 3513.00
3 Hudraulic Excavator of 0.09 cum Bucket Per Hour 1843.00 0.00 1843.00
4 Front end loader 1cum bucket capacity Per Hour 1321.00 0.00 1321.00
loading soil
Front end loader 1cum bucket capacity Per Hour 1281.00 0.00 1281.00
loading Agreegate
5 Tipper 5.50Cum/10t . Per Hour 513.00 0.00 513.00
6 Water Tanker 6kl capacity Per Hour 500.00 0.00 500.00
7 Tractor with trolley Per Hour 581.00 0.00 581.00
8 Tractor with Rotavator Per Hour 688.00 0.00 688.00
9 Tractor with Ripper Per Hour 687.00 0.00 687.00
10 Tractor mount grader 110 @ 25 cum/hour Per Hour 1192.00 0.00 1192.00
Tractor with disc Harrows Per Hour 801.00 0.00 801.00
11 Air Compressor 210 cfm Per Hour 465.00 0.00 465.00
12 Mechanical Broom Hydraulic with tractor Per Hour 528.00 0.00 528.00
13 Bitumen emulsion pressure distributor Per Hour 1569.00 0.00 1569.00
14 Bitumen boiler oil fired 1000 ltr Per Hour 1408.00 0.00 1408.00
15 Hotmix plant 30-40TPH Capacity Per Hour 13798.00 0.00 13798.00
16 Paver finisher Mechnical 75.00 TPH Per Hour 4300.00 0.00 4300.00
17 Three wheeled 80-100KN static roller for Per Hour 791.00 0.00 791.00
Earth Embankment or sub grade 80/70
cum/hr.
18 Three wheeled 80-100KN static roller for Per Hour 745.00 0.00 745.00
Sub Base Grade-I. 10 cum./hr.
19 Three wheeled 80-100KN static roller for Per Hour 741.00 0.00 741.00
Sub Base Gr-II/Gr-III. 8 cum/hr.
20 Three wheeled 80-100KN static roller for Per Hour 741.00 0.00 741.00
WMM. 16.00 cum./hr.
21 Three wheeled 80-100KN static roller for Per Hour 741.00 0.00 741.00
BUSG. 10.00 cum./hr.
22 Three wheeled 80-100KN static roller for Per Hour 741.00 0.00 741.00
BM 50/75 mm. 12.00 cum./hr.
23 Three wheeled 80-100KN static roller for Per Hour 741.00 0.00 741.00
premix 20 mm 250 sqm./hr.
24 Three wheeled 80-100KN static roller for Per Hour 741.00 0.00 741.00
seal coat 500.00sqm./hr.
25 Three wheeled 80-100KN static roller for Per Hour 741.00 0.00 741.00
surface dressing Ist. coat. 400.00 sqm../hr.

26 Three wheeled 80-100KN static roller for Per Hour 741.00 0.00 741.00
surface dressing 2nd.. coat. 500.00
sqm../hr.
Smooth wheeled 80-100kn tandem roller Per Hour 1319.00 0.00 1319.00
27 Crane 8 Tonne Per Hour 916.00 0.00 916.00
28 Concrete Mixer 0.4/0.28Cum Per Hour 350.00 0.00 350.00
Plate vibrator Per hour 98.00 0.00 98.00
29 Electric Generator set, 125 KVA Per Hour 1125.00 0.00 1125.00
30 Truck 5.5Cum/10Tonne Per Hour 589.00 0.00 589.00
31 Dozer D-50 for spreading @ 200 cum. Per Per Hour 6285.00 0.00 6285.00
hr.
32 Hotmix plant 40-60TPH Capacity Per Hour 16896.00 0.00 16896.00
33 Vibratory rollar 80-100 Kn. Per Hour 2417.00 0.00 2417.00
Certified that rates taken for usage of machinery are the present lowest prevailing rate.
Sr. No. Machinery Unit Rate as per Enhancement Present Rate
HPSR 2016 of machinery
rate

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.
Material Rate

Sr. Description Unit Present Remarks


No. Market
Rate
1 Cement Tonne 7400.00 Market rate
2 Tor Steel Tonne 49000.00 Market rate
3 Detonaters 100Nos. 1600.00 Market rate
4 Special Gelatine 80% Kg. 98.00 Market rate
5 RCC Hume Pipe 900mm NP2 Meter 3016.00 Factory site
6 RCC Hume Pipe 900mm NP3 with collar Meter 4119.00 Factory site
7 Stone aggregate 40mm size Cum. 1069.00 Crusher site
8 Stone aggregate 20mm size Cum. 1276.00 Crusher site
9 Stone aggregate 10mm size Cum. 1281.00 Crusher site
10 Sand Cum. 1101.00 Quarry site
11 Quarried stone in block Cum. 1061.00 Quarry site
12 Stone for coursed rubble masonry 1st. Sort. Cum. 1368.00 Quarry site
13 Stone for coursed rubble masonry 2nd. Sort. Cum. 1303.00 Quarry site
14 Oridinary quarried stone Cum. 1170.00 Quarry site
15 Through, bond stone Nos. 30.00 Quarry site
16 Stone for soling, filling crate Cum. 766.00 Quarry site
17 Stone for pitching Cum. 766.00 Quarry site
18 Stone spalls Cum. 751.00 Quarry site
19 Loose stone for filling Cum. 760.00 Quarry site
20 13.2 to 5.6mm Cum. 1220.00 Crusher site
21 90 to 45mm Cum. 952.00 Crusher site
22 63 to 45mm Cum. 999.00 Crusher site
23 Bitumen 80/100 (VG-10) Tonne 36691.73 Dhanotu depot
24 Bitumen Emulsion (SS-I) Tonne 45479.00 Dhanotu depot
25 Bitumen Emulsion (RS-I) Tonne 43084.00 Dhanotu depot
26 Bitumen Emulsion (MS) Tonne 47440.00 Dhanotu depot
27 Stone Chipps 13.2mm to 5.6mm 0.27Cum/10Sqm. Cum. 1103.00 Crusher site
28 Crushed Stone Chipping 13.2mm nominal size Cum. 1220.00 Crusher site
29 Stone screening Type B 11.2 mm Cum. 1213.00 Crusher site
30 Cement primer as per specification ltr. 149.00 Market rate
31 Epoxy primer/red oxide ltr. 206.00 Market rate
32 Epoxy paint ltr. 374.00 Market rate
33 Paint ltr. 312.00 Market rate
34 Water Kl. 102.00 Market rate
35 Binding material for road Cum. 663.00 Market rate
36 Binding wire Kg. 70.00 Market rate
37 G.I. Pipe 100mm dia. Meter 837.00 Market rate
38 PVC pipe 100 mm dia Metre 260.00 Market rate
39 Corrison resistant structural steel Kg. 151.00 Market rate
40 GI Wire 4mm dia Kg. 82.00 Market rate
41 Filter Media Cum. 751.00 Market rate
42 Cast steel rocker bearing assembly of 250 tonne Each 73472.00 Market rate
43 Forged steel roller bearing assembly of 250 tonne Each 111803.00 Market rate
44 Granular material Cum. 376.00 Quarry site
45 MS Tube Kg. 91.00 Market rate
46 Angle iron Kg. 45.00 Market rate
47 1.6 mm thick MS sheet duly painted per sqm. 1451.00 Market rate
48 1.5 mm and 1.6 mm thick MS sheet duly painted per sqm. 1554.00 Market rate

Certified that the rate taken above for material are the lowest prevailing market rates in the area.

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar
Analysis of Rate Chapter-1
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (RS.)
No. MORD
Specification
1.1 Loading & Unloading of lime, aggregate, stone
boulder, brick aggregate, Kankar, Building Rubish,
Crusher slag stone for masonry work by Manual
means including a lead upto 30 m
I) Loading
Unit = Cum.
Taking Output = 5.5 cum.
a) Labour
Mate Day 0.02 245.00 4.90
Majdoor (Unskilled) Day 0.50 245.00 122.50
Total 127.40
b)_Machinery
Truck Hour 0.50 589.00 294.50
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over 52.74
head Charges @ 2.5% )
474.64
d) Add Labour cess @ 1.00 % 4.75
Cost for 5.5 Cum. = a+b+c+d 479.39
Rate per Cum 87.16
Say 87.16
iii) Unloading
Unit=Cum.
Taking Output = 5.5 cum.
a) Labour
Mate Day 0.01 245.00 2.45
Majdoor (Unskilled) Day 0.25 245.00 61.25
Total 63.70
b) Machinery
Truck Hour 0.25 589.00 147.25
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over 26.37
head Charges @ 2.5% )
237.32
d) Add Labour cess @ 1.00 % 2.37
Cost for 5.5 Cum. = a+b+c+d 239.69
Rate per Cum 43.58
Say 42.95
Rate per cum for loading & unloading 130.11

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 10
Analysis of Rate Chapter-1
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (RS.)
No. MORD
Specification
1.1 Loading & unloading of earth, sand, stone chips,
moorum, manure flyash by manual means including a
lead upto 30 mtr.
ii) Loading
Unit = Cum.
Taking Output = 5.5 cum.
a) Labour
Mate Day 0.01 245.00 2.45
Majdoor (Unskilled) Day 0.25 245.00 61.25
Total 63.70
b) Machinery
Truck Hour 0.25 589.00 147.25
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over 26.37
head Charges @ 2.5% )
237.32
d) Add Labour cess @ 1.00 % 2.37
Cost for 5.5 Cum. = a+b+c+d 239.69
Rate per Cum 43.58
Say 43.58
iv) Unloading
Unit=Cum.
Taking Output = 5.5 cum.
a) Labour
Mate Day 0.005 245.00 1.23
Majdoor (Unskilled) Day 0.125 245.00 30.63
Total 31.85
b) Machinery
Truck Hour 0.166 589.00 97.77
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over 16.20
head Charges @ 2.5% )
145.83
d) Add Labour cess @ 1.00 % 1.46
Cost for 5.5 Cum. = a+b+c+d 147.29
Rate per Cum 26.78
Rate per cum for loading & unloading 70.36

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 11
Analysis of Rate Chapter-1
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (RS.)
No. MORD
Specification

1.4 Loading and unloading of cement by manual means


including a lead upto 30 mtr.
I) Loading
Unit = Tonne
Taking Output = 10 Tonne
a) Labour
Mate Day 0.06 245.00 14.70
Majdoor (Unskilled) Day 1.50 245.00 367.50
Total 382.20
b) Machinery
Truck Hour 1.00 589.00 589.00
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over 121.40
head Charges @ 2.5% )
1092.60
d) Add Labour cess @ 1.00 %) 10.93
Cost for 10Tonne = a+b+c+d 1103.53
Rate per Tonne 110.35
Say 110.35
ii) Unloading
Unit = Tonne
Taking Output = 10 Tonne
a) Labour
Mate Day 0.06 245.00 14.70
Majdoor (Unskilled) Day 1.50 245.00 367.50
Total 382.20
b) Machinery
Truck Hour 1.00 589.00 589.00
c) Add 12.50% on a+b(Contractor's profit @ 10% + 121.40
Over head Charges @ 2.5% )
1092.60
d) Add Labour cess @ 1.00 % 10.93
Cost for 10Tonne = a+b+c+d 1103.53
Rate per Tonne 110.35
Say 110.35
Rate per tonne for loading & unloading 220.70

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 12
Analysis of Rate Chapter-1
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (RS.)
No. MORD
Specification

1.5 Loading and unloading of structural steel and steel


bars by manual means
I) Loading
Unit=Tonne
Taking Output = 10 Tonne
a) Labour
Mate Day 0.07 245.00 17.15
Majdoor (Unskilled) Day 1.80 245.00 441.00
Total 458.15
b) Machinery
Truck Hour 1.00 589.00 589.00
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over 130.89
head Charges @ 2.5% )
1178.04
d) Labour cess @ 1.00 % 11.78
Cost for 10Tonne = a+b+c 1189.82
Rate per Tonne 118.98
Say 118.98
ii) Unloading
Unit=Tonne
Taking Output = 10 Tonne
a) Labour
Mate Day 0.07 245.00 17.15
Majdoor (Unskilled) Day 1.80 245.00 441.00
Total 458.15
b) Machinery
Truck Hour 1.00 589.00 589.00
c) Add 12.50% on a+b (Contractor's profit @ 10% + 130.89
Over head Charges @ 2.5% )
Total 1178.04
d) Add on a+b+c Labour cess @ 1.00 % 11.78
Cost for 10Tonne = a+b+c+d Total 1189.82
Rate per Tonne 118.98
Say 118.98
Rate per tonne for loading & unloading 237.96

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 13
Analysis of Rate Chapter-1
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (RS.)
No. MORD
Specification

1.8 Loading and unloading with care C.C. blocks, Km.


stone, 200 mtr. stone, boundary pillar, curb, channel,
bond stone, etc. by manual means including a lead
upto 30 mtr.
I) Loading
Unit = Cum.
Taking Output = 5.5 cum.
a) Labour
Mate Day 0.08 245.00 19.60
Majdoor (Unskilled) Day 2.00 245.00 490.00
Total 509.60
b) Machinery
Truck Hour 1.50 589.00 883.50
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over 174.14
head Charges @ 2.5% )
Total 1567.24
d) Add on a+b+c Labour cess @ 1.00 % 15.67
Cost for 5.5 Cum. = a+b+c+d 1582.91
Rate per Cum 287.80
Say 287.80
ii) Unloading
Unit=Cum.
Taking Output = 5.5 cum.
a) Labour
Mate Day 0.08 245.00 19.60
Majdoor (Unskilled) Day 2.00 245.00 490.00
Total 509.60
b) Machinery
Truck Hour 1.50 589.00 883.50
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over 174.14
head Charges @ 2.5% )
Total 1567.24
d) Add on a+b+c Labour cess @ 1.00 % 15.67
Cost for 5.5 Cum. = a+b+c+d 1582.91
Rate per Cum 287.80
Say 287.80
Rate per cum. For loading and unloading 575.60

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 14
Analysis of Rate Chapter-1
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (RS.)
No. MORD
Specification

1.6 Loading and unloading of bitumen, drums by manual


means including a lead upto 30mtr.
I) Loading
Unit=Tonne
Taking Output = 10 tonne
a) Labour
Mate Day 0.06 245.00 14.70
Majdoor (Unskilled) Day 1.60 245.00 392.00
Total 406.70
b) Machinery
Truck Hour 1.25 589.00 736.25
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over 142.87
head Charges @ 2.5% )
Total 1285.82
d) Add on a+b+c Labour cess @ 1.00 % 12.86
Cost for 10Tonne = a+b+c+d 1298.68
Rate per Tonne 129.87
Say 129.87
ii) Unloading
Unit=Tonne
Taking Output = 10 tonne
a) Labour
Mate Day 0.05 245.00 12.25
Majdoor (Unskilled) Day 1.20 245.00 294.00
Total 306.25
b) Machinery
Truck Hour 1.25 589.00 736.25
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over 130.31
head Charges @ 2.5% )
Total 1172.81
d) Add on a+b+c Labour cess @ 1.00 % 11.73
Cost for 10Tonne = a+b+c+d 1184.54
Rate per Tonne 118.45
Say 118.45
Rate per tonne for loading & unloading 248.32

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 15
Analysis of Rate Chapter-1
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (RS.)
No. MORD
Specification

1.9 Loading and unloading of RCC hume pipes by


mechanical means including a lead upto 30 m.
1000/1200 mm dia RCC hume pipe
I) Loading
Unit = Pipe
Taking output = 9pipe
a) Labour
Mate Day 0.02 245.00 4.90
Majdoor (Unskilled) Day 0.50 245.00 122.50
Total 127.40
b) Machinery
Truck Hour 0.33 589.00 194.37
Crane Hour 0.33 916.00 302.28
Total 496.65
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over 78.01
head Charges @ 2.5% )
Total 702.06
d) Add on a+b+c Labour cess @ 1.00 % 7.02
Cost for 9 pipes a+b+c+d 709.08
Cost per pipe 78.79
Say 78.79
ii) Unloading
Unit = Pipe
Taking output = 9pipe
a) Labour
Mate Day 0.02 245.00 4.90
Majdoor (Unskilled) Day 0.50 245.00 122.50
Total 127.40
b) Machinery
Truck Hour 0.20 589.00 117.80
Crane Hour 0.20 916.00 183.20
Total 301.00
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over 53.55
head Charges @ 2.5% )
Total 481.95
d) Add on a+b+c Labour cess @ 1.00 % 4.82
Cost for 9 pipes a+b+c+d 486.77
Cost per pipe 54.09
Say 54.09
Rate per pipe for loading & unloading 132.88

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 16
Analysis of Rate Chapter-1
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (RS.)
No. MORD
Specification

1.10 Haulage of material by tiper excluding loading & unloading and stacking
Unit = Tonne Km.
Taking output 10 tonne load and lead 10 km = 100 tonne
km.
1) Surface road
Speed with load : 25 km per hour
speed while returning empty : 35 km per hour
a) Machinery
Tipper 10 tonne capacity
Haulage with load Hour 0.40 513.00 205.20
Empty return trip Hour 0.29 513.00 148.77
Total 353.97
b) Add 12.50% on a (Contractor's profit @ 10% + Over 44.25
head Charges @ 2.5% ) Total 398.22
C) Add Labour cess @ 1.00 % 3.98
Cost for 100 tonne Km. 402.20
Rate per tonne km. 4.02
Say 4.02
2) Un Surfaced Gravelled road
Speed with load : 20 km per hour
Speed for empty return trip= 30Km./H
a) Machinery
Tipper 10 tonne capacity
Haulage with load Hour 0.50 513.00 256.50
Empty return trip Hour 0.33 513.00 169.29
Total 425.79
b) Add 12.50% on a (Contractor's profit @ 10% + Over 53.22
head Charges @ 2.5% ) 479.01
C) Add Labour cess @ 1.00 % 4.79
Cost for 100 tonne Km. 483.80
Rate per tonne km. 4.84
Say 4.84
Haulage of hume pipe by tiper excluding loading & unloading and stacking
Unit = Tonne Km.
Taking output 8 t load and lead 10
km = 9 pipes
1) Surface road
Speed with load : 25 km per hour
speed while returning empty : 35 km per hour
a) Machinery
Tipper 10 tonne capacity
Haulage with load Hour 0.40 513.00 205.20
Empty return trip Hour 0.29 513.00 148.77
Total 353.97
b) Add 12.50% on a (Contractor's profit @ 10% + Over 44.25
head Charges @ 2.5% ) Total 398.22
C) Add Labour cess @ 1.00 % 3.98

Page 17
Analysis of Rate Chapter-1
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (RS.)
No. MORD
Specification
Cost for 9 pipe (a+b+c) 402.20
Rate per pipe for 10 Km. 44.69
Rate per pipe per Km. 4.47

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.
1.2 Loading & unloading of lime affregate, stone boulder, brick aggregate, kankar, building rubbish,
crushed slag stone for masonry work by mechnical means
ii) Loading of earth, sand, stone chips, moorum, manure, flyash by mechnical means including a
lead upto 30m
Placing tipper at loading point, loading with front end loader excluding time for haulage and retrun
trip.
Unit = Cum.
Taking Output = 5.5 cum.
Time requirement for
i) Positioning of tipper at loading point Min 1.00
ii) Loading by front end loader 1 cum bucket capacity @ Min 3.30
100 cum per hour
iii) Waiting time, unforeseen contingencies etc. Min 2.00
Total Min 6.30
a) Machinery
Tipper 10t capacity Hour 0.105 513.00 53.87
Front end loader 1 cum bucket capacity @ 100 cum per Hour 0.055 1321.00 72.66
hour
b) Add 12.50% on a (Contractor's profit @ 10% + Over 15.82
head Charges @ 2.5% )
142.34
c) Add on a+b Labour cess @ 1.00 % 1.42
Cost for 5.5 Cum. = a+b+c 143.76
Rate per Cum 26.14
Say 26.14
iii) Unloading of earth, sand, stone chips, moorum aggregate stone boulder, brick aggregate, kankar,
building rubbish, maanure, crushed slag, flyash, stone for masonry work by mechanical means.

Unit = cum
Taking output = 5.5 cum
Placing tipper at unloading point excluding time for haulage
and tipper return trip
Time required for
i) Positioning of tipper at unloading point min 1.00
ii) Maneeuvering, reversing, dumping and truning for retrun min 2.00

iii) Waiting time unforeseen contingencies etc. min 2.00


Total Min 5.00
a) Machinery
Tipper 10t capacity Hour 0.080 513.00 41.04
b) Add 12.50% on a (Contractor's profit @ 10% + Over 5.13
head Charges @ 2.5% )
46.17
c) Add on a+b Labour cess @ 1.00 % 0.46
Cost for 5.5 Cum. = a+b+c 46.63
Rate per Cum 8.48

Page 18
Analysis of Rate Chapter-1
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (RS.)
No. MORD
Specification
Say 8.48
Rate per cum for loading & unloading 34.62

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.
1.2 Loading & unloading of lime aggregate, stone boulder,
brick aggregate, kankar, building rubbish, crushed
slag stone for masonry work by mechnical means

i) Loading of lime, aggregate stone boulder, brick aggregate, kankar, building rubbish, maanure,
crushed slag, flyash, stone for masonry work by mechanical means including a lead upto 30m
Placing tipper at loading point, loading with front end
loader excluding time for haulage and retrun trip.

Unit = Cum.
Taking Output = 5.5 cum.
Time requirement for
i) Positioning of tipper at loading point Min 1.00
ii) Loading by front end loader 1 cum bucket capacity @ 45 Min 7.33
cum per hour
iii) Waiting time, unforeseen contingencies etc. Min 2.00
Total Min 10.33
a) Machinery
Tipper 10t capacity Hour 0.172 513.00 88.24
Front end loader 1 cum bucket capacity @ 45 cum per Hour 0.122 1321.00 161.16
hour
b) Add 12.50% on a (Contractor's profit @ 10% + Over 31.17
head Charges @ 2.5% )
Cost for 5.5 Cum. = a+b 280.57
Add labour less on (a+b) @ 1 % 2.81
283.38
Rate per Cum 51.52
iii) Unloading of earth, sand, stone chips, moorum,
aggregate, stone boulder, brick aggregate, kankar,
building rubbish, maanure, crushed slag, flyash, stone
for masonry work by mechanical means.
Unit = cum
Taking output = 5.5 cum
Placing tipper at unloading point excluding time for haulage
and tipper return trip
Time required for
i) Positioning of tipper at unloading point min 1.00
ii) Maneeuvering, reversing, dumping and truning for retrun min 2.00

iii) Waiting time unforeseen contingencies etc. min 2.00


Total Min 5.00
a) Machinery
Tipper 10t capacity Hour 0.080 513.00 41.04
b) Add 12.50% on a (Contractor's profit @ 10% + Over 5.13
head Charges @ 2.5% )
Cost for 5.5 Cum. = a+b 46.17
Add labour less on (a+b) @ 1 % 0.46

Page 19
Analysis of Rate Chapter-1
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (RS.)
No. MORD
Specification
46.63
Rate per Cum 8.48
Rate per pipe for loading & unloading 60.00

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 20
Chapter-2
Reference of
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
2.2 201.1 Clearing and grubbing road land
Cleaning and grubbing road land including uprooting wild
vegetation, grass, bushes, shrubs, saplings and trees of girth
upto 300mm, removal of tumps of such trees cut earlier and
disposal of unserviceable materials and stacking of serceable
material to be used or auctioned, upto a lead of 1000m
including removal and disposal of top organic soil not
exceeding 150mm in thickness as per technical specification
clause 201.1

Unit = hectare
Taking output = 1 hectare
(II) By Mechnical Means
(A) In area of non thorny jungle
a) Labour
Mate day 0.16 245.00 39.20
Mazdoor (unskilled) day 4.00 245.00 980.00
b) Machinery
Dozer D 50 with attachment or suitable machinery for remvoal hour 10.00 6285.00 62850.00
of trees & stumps
Tractor with trolley hour 1.00 581.00 581.00
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over 8056.28
head Charges @ 2.5% )
72506.48
d) Add 1 % labour cess 725.06
Cost per Hectare = a+b+c+d 73231.54
Say 73231.50
Rate per sqm = (a+b+c+d)/10000 7.32
Say 7.30

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 21
Chapter-3
Reference of
Sr. Rate
MORD Description Unit Quantity
No. (Rs.)
Specifications
3.14 303.1 Construction of Subgrade and Earthen Shoulders
Construction of subgrade and earthen shoulders with
approved material obtained from borrow pits with all lefts and
leads, transporting to site, spreading, grading to required slope
and compacted to meet requirement of Table 300.2 with lead
upto 1000m as per Technical Specification Clause 303.1.

Unit = Cum.
Taking output = 100Cum.
a) Labour
Mate day 0.04 245.00
Mazdoor (unskilled) day 1.00 245.00
Total
b) Machinery
Hydraulic excavator 0.9Cum bucket capacity @ 100cum/hour hour 1.00 1843.00
Tipper 5.5Cum capacity 4 trip per hour hour 4.50 513.00
Add rate for Loading as per item 1.1 (ii) cum 100.00 38.35
Add rate for Unloading as per item 1.1 (iv) cum 100.00 23.57
Dozer D-50 for spreading @ 200 cum/hour hour 0.50 6285.00
Motor grader for grading @ 200 cum/hour hour 0.50 3513.00
Water tanker with 6kl capacity hour 2.00 500.00
Three wheel 80-100 kN Static Roller @ 70 cum/hour hour 1.43 791.00
Total
c) Material
Water kl 12.00 102.00
Compensation for earth taken from private land cum 100.00 63.00
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 %
Cost for 100Cum = a+b+c+d+e
Rate per Cum = (a+b+c+d+e)/100
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 22
Chapter-3
Reference of
Sr. Rate
MORD Description Unit Quantity
No. (Rs.)
Specifications

3.15 303 (ii) Compacting original ground supporting subgrade


Loosening of ground upto a level of 300mm below the
subgrade level, watered graded and compacted in layers to
meet requirement of Table 300.1 and 300.2 for subgrade
construction as per technical Specifiaction clause 303.5.2.
Unit = Cum.
Taking output = 600Cum.
a) Labour
Mate day 0.24 245.00
Mazdoor (Unskilled) day 6.00 245.00
Total
b) Machinery
Trator with ripper attachment hour 10.00 687.00
Motor grader for grading hour 6.00 3513.00
Water tanker 6kl capacity hour 4.00 500.00
Three wheel 80-100 KN Static Roller @ 70Cum/Hour hour 8.60 791.00
Total
c) Material
Water kl 24.00 102.00
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 %
Cost for 600Cum = a+b+c+d
Rate per Cum = (a+b+c+d+e)/600
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 23
Chapter-3
Reference of
Sr. Rate
MORD Description Unit Quantity
No. (Rs.)
Specifications

(I) Excavation in cutting in soil by mannual means with


3.5 302
lead upto 50mtrs.
Excavation for road way in soil using mannual means for
carrying of cut to embeckment site with lift upto 1.5mtrs.
And lead upto 50mtrs. As per technical specificcaion
clause 302.3.
Unit: Cum
Taking output 120Cum.
a) Labour
Mate day 1.80 245.00
Mazdoor (Unskilled) day 45.00 245.00
Total
b) Add 13.50% on a (Contractor's profit @ 10% + Over
head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost of 120Cum.
Cost per Cum.

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 24
Chapter-3
Reference of
Sr. Rate
MORD Description Unit Quantity
No. (Rs.)
Specifications

Construction of Embankment with material obtained from


3.4 301.5
Borrow Pits.
Construction of embankment with approved material
obtained from borrow pits with a lift upto 1.5m
transporting to site spreading, grading to recumed slope
and compacting to meet requirement of Table 300.1 and
300.2 with a lead upto 1000m as per technical
specification clause 301.5

Unit: Cum
Taking output 100Cum.
a) Labour
Mate day 0.04 245.00
Mazdoor (Unskilled) day 1.00 245.00
Total
b) Machinery
Hydraulic excavator 0.29Cum backet capacity @ 60Cum hour 1.67 1843.00
Tipper 5.5Cum hour 4.50 513.00
Loading of earth as per item 1.1 (ii) cum 100.00 42.95
Unloading of earth as per item 1.1 (iv) cum 100.00 26.47
Dozer D-50 for spreading @ 200Cum/Hour hour 0.50 6285.00
Motor grader for grading @ 200Cum/Hour hour 0.50 3513.00
Water tanker 6kl capacity hour 2.00 500.00
Three wheeled 80-100kN static roller @ 80cum hour 1.25 791.00
Total
c) Material
Water Kl 12.00 102.00
Compenstion for earth taken from pricate land cum 100.00 1.00
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
E) Add 1 % labour cess
Cost for 100Cum.
Cost per Cum.
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 25
Chapter-3
Reference of
Sr. Rate
MORD Description Unit Quantity
No. (Rs.)
Specifications

3.19 307 (i) Surface drains in soil


Construction of unlined suface drains of average cross-
sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions. Excavated material to be used in
embankment with a lift upto 3m and lead of 50m (average lead
25m) as per Technical specification clause 307.
Unit = m
Taking output = 10 m
(b) Mechnical means
a) Labour
Mate day 0.01 245.00
Mazdoor (Unskilled) day 0.25 245.00
b) Machinery
Hydraulic excavator 0.9cum bucket capacity @ 100 cum per hour 0.04 1843.00
hour
c) Add 13.50% on a +b (Contractor's profit @ 10% + Over
head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost for 10 m.
Cost per m.

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 26
Chapter-3
Reference of
Sr. Rate
MORD Description Unit Quantity
No. (Rs.)
Specifications

3.19 307 (ii) Surface drains in ordinary rock


Construction of unlined suface drains of average cross-
sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions. Excavated material to be used in
embankment with a lift upto 3m and lead of 50m (average lead
25m) as per Technical specification clause 307. Excavated
material to be used in embankment at site.

Unit = m
Taking output = 10 m
(b) Mechnical means
a) Labour
Mate day 0.02 245.00
Mazdoor (Unskilled) day 0.50 245.00
b) Machinery
Hydraulic excavator 0.9cum bucket capacity @ 100 cum per hour 0.10 1843.00
hour
d) Add 13.50% on a (Contractor's profit @ 10% + Over
head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost for 10 m.
Cost per m.

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 27
Chapter-3
Reference of
Sr. Rate
MORD Description Unit Quantity
No. (Rs.)
Specifications

2.2 201 Clearing and grubbing road land including uprooting


wild vegetation, grass, bushes, shrubs, saplings and
trees of girth upto 300 mm, removal of stumps of such
trees cut earlier and disposal of unserviceable
materials and stacking of serviceable material to be
used or auctioned, upto a lead of 1000 m including
removal and disposal of top organic soil not exceeding
150 mm in thickness as per Technical Specification
Clause 201.

By Mechanical Means
Unit = hectare
Taking output = 1 hectare
(A) In area of non-thorny jungle
a) Labour
Mate day 0.16 245.00
Mazdoor (Unskilled) day 4.00 245.00
b) Machinery
Dozer D 50 with attachment or suitable machinery for hour 10.00 6,285.00
removal of trees & stumps
Tractor with Trolley hour 1.00 581.00

c) Contractor’s profit & Overheads @ 12.50 % on (a+b)

d) Labour Cess @ 1 % on (a+b+c)


Rate per hectare = a+b+c+d

Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 28
Chapter-3
Reference of
Sr. Rate
MORD Description Unit Quantity
No. (Rs.)
Specifications

Construction of Embankment with material obtained from


3.3 301.5
road way cutting
Construction of embankment with approved material
deposited at site from road way cutting and excavation
from drain and foundation of other structure grading and
compacted to meet requirement of Table 300.1 and 300.2
with a lead upto 1000m as per technical specification
clause 301.5

Unit: Cum
Taking output 100Cum.
a) Labour
Mate day 0.02 245.00
Mazdoor (Unskilled) day 0.50 245.00
Total
b) Machinery
Dozer D-50 for spreading @ 200Cum/Hour hour 0.50 6285.00
Motor grader for grading @ 200Cum/Hour hour 0.50 3513.00
Water tanker 6kl capacity hour 2.00 500.00
Three wheeled 80-100kN static roller @ 80cum hour 1.25 791.00
Total
c) Material
Water Kl 12.00 102.00
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5%
e) Add 1 % labour cess
Cost for 100Cum.
Cost per Cum.
Say

Executive Engineer,
B&R Division,HPPWD.,
Joginder Nagar.

Page 29
Amount
(Rs.)

9.80
245.00
254.80

1843.00
2308.50
3835.00
2357.00
3142.50
1756.50
1000.00
1131.13
17373.63

1224.00
6300.00
7524.00
3144.05

282.96
28579.45
285.79
285.80

ngineer,
n HP.PWD.,
agar

Page 30
Amount
(Rs.)

58.80
1470.00
1528.80

6870.00
21078.00
2000.00
6802.60
36750.60

2448.00
5090.93

458.18
46276.51
77.13
77.10

ngineer,
n HP.PWD.,
agar

Page 31
Amount
(Rs.)

441.00
11025.00
11466.00
1547.91

13013.91
108.40

ngineer,
n HP.PWD.,
agar

Page 32
Amount
(Rs.)

9.80
245.00
254.80

3077.81
2308.50
4295.00
2647.00
3142.50
1756.50
1000.00
988.75
19216.06

1224.00
100.00
1324.00
2599.36

233.94
23628.16
236.28
236.30

ngineer,
n HP.PWD.,
agar

Page 33
Amount
(Rs.)

2.45
61.25

73.72

18.55

155.97
15.60

ngineer,
n HP.PWD.,
agar

Page 34
Amount
(Rs.)

4.90
122.50

184.30

42.08

353.78
35.40

ngineer,
n HP.PWD.,
agar

Page 35
Amount
(Rs.)

39.20
980.00

62,850.00

581.00
64,450.20
8,056.28

72,506.48
725.06
73,231.54

73231.50

ngineer,
n HP.PWD.,
agar

Page 36
Amount
(Rs.)

4.90
122.50
127.40

3142.50
1756.50
1000.00
988.75
6887.75

1224.00
1224.00
1029.89

92.69
9361.73
93.62
93.60

ngineer,
n,HPPWD.,
agar.

Page 37
Chaper-4
Reference of
Sr. MORD
Description Unit Quantity Rate (Rs.)
No. Specification
s
Granular Sub Base with well graded Matarial (Table 400.1)
4.1 401

(A) By Mix in Place Method


Construction of granular sub-base by providing well graded
material spreading in uniform layers with motor grader on
prepared surface mixing by mix in place methof with rotavator
at CM and compating with smooth wheel roller to achieve the
desired density, complete as per technical specification Clause
401.

(I) For Grading I Material


Unit = Cum
Taking Output = 300Cum.
a) Labour
Mate Day 0.48 245.00
Mazdoor (Skilled) Day 2.00 245.00
Mazdoor (Unskilled) Day 10.00 245.00
Total
b) Machinery
Tractor Motor grader 110Hp @ 25Cum/Hour Hour 12.00 1192.00
Three Wheel 80-100kN static roller @ 10Cum/Hour Hour 30.00 745.00
Tractor with Ratavator 25Cum/Hour Hour 12.00 688.00
Water tanker 6Kl capacity Hour 5.00 500.00
Total
c) Material

Well graded granular sub-base material as per Table 400.1 Cum 360.00 938.00
Water Kl 30.00 102.00
Total
d) Add 12.50% on a +b+c(Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add 1% labour cess on a +b+c+d
Cost for 300cum = a+b+c+d
Rate per Cum = (a+b+c+d)/300 (Excluding
carriage)
Carriage
Well graded granular sub-base material as per Table 400.1 Cum 360.00 561.88
Cost for 300cum
Rate per Cum (Including carriage)
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 38
Chaper-4
Reference of
Sr. MORD
Description Unit Quantity Rate (Rs.)
No. Specification
s

4.7 405 Water Bound Macadam Sub-Base/Base


1) WBM Grading-I
Providing, laying, spreading and compating stone aggregates
of specific sizes to water bound macadam spefication
including spreading in uniform thickness, hand packing rolling
with three wheel roller 80-100 kN static roller in stages to
proper grade and camber, applying and broomingm, stone
screeing/bending materials to fill-up the interstrices of coarse
aggregate watering and compacting to the required density
grading 1 as per Technical Specification Clause 404.

(A) By Manual Means


Unit = Cum
Taking output = 360Cum
a) Labour
Mate Day 10.08 245.00
Mazdoor (Skilled) Day 2.00 245.00
Mazdoor (Unskilled) Day 250.00 245.00
Total
b) Machinery
Three Wheel 80-100kN static roller @ 8Cum/Hour Hour 36.00 741.00
Water Tanker 5kl capacity Day 24.00 500.00
Total
c) Material (From Table 400.7, 8, 9 and 10)
Aggregate
Grading 1 90mm to 45mm @ 1.21Cum/10Sqm. For Cum 435.60 952.00
compacted thickness of 100mm
Stone Screenings
Type A 13.2mm for grading-1 @ 0.27cum per 10sqm Cum 97.20 1220.00
Binding Materterial
Binding Material @ 0.08Cum per 10sqm for Grading 1 Material Cum 28.80 82.00

Water kl 144.00 102.00


Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
e) Add on a+b+c+d Labour cess @ 1.00 %
Cost for 360cum = a+b+c+d+e
Rate per Cum = a+b+c+d+e/360 (Excluding
carriage)
Carriage
Stone aggregate Cum 561.60 784.00
Cost for 360cum = a+b+c+d+e
Rate per Cum = a+b+c+d+e/360 (Including
carriage)
say

Executive Engineer,
B&R Division,HPPWD.,
Joginder Nagar.

Page 39
Chaper-4
Reference of
Sr. MORD
Description Unit Quantity Rate (Rs.)
No. Specification
s

4.7 405 2) WBM Grading-2


Providing, laying, spreading and compating stone aggregates
of specific sizes to water bound macadam spefication loading
spreasing in uniform thickness, hand packing rolling with
smooth wheel roller 80-100 kN in stages to proper grade and
camber, applying and broomingm, stone screeing/bending
materials to fill-up the interstrices of coarse aggregate
watering and compacting to the required density grading 2 as
per Technical Specification Clause 405

(A) By Manual Means


Unit = Cum
Taking output = 360Cum
a) Labour
Mate day 10.08 245.00
Mazdoor (Skilled) day 2.00 245.00
Mazdoor (Unskilled) day 250.00 245.00
Total
b) Machinery
Three Wheel 80-100kN static roller @ 8Cum/Hour Hour 45.00 741.00
Water Tanker 5kl capacity day 24.00 500.00
Total
c) Material (From Table 400.7, 8, 9 and 10)
Aggregate
Grading 2 63mm to 45mm @ 0.91Cum/10Sqm. For Cum 435.60 999.00
compacted thickness of 75mm
Stone Screenings
Type B 11.2mm for grading-2 @ 0.20cum per 10sqm Cum 96.01 1213.00
Binding Materterial
Binding Materterial @ 0.06Cum per 10sqm for Grading 2 Cum 28.80 82.00
Material
Water kl 144.00 102.00
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c +d Labour cess @ 1.00 %
Cost for 360cum = a+b+c+d+e
Rate per Cum = a+b+c+d+e/360 (excluding
carriage)
Carriage
Stone aggregate Cum 560.41 1088.08
Cost for 360cum = a+b+c+d+e
Rate per Cum = a+b+c+d+e/360 (Including
carriage)
Say

Executive Engineer,
B&R Division,HPPWD.,
Joginder Nagar.

Page 40
Chaper-4
Reference of
Sr. MORD
Description Unit Quantity Rate (Rs.)
No. Specification
s

4.7 405 3) WBM Grading 3


Providing, laying, spresding and compacting stone aggregate
of specific sizes to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling
with smooth wheel roller 80-100 kN in stages to proper grade
and camber, applying and brooming, stone screening to fill-up
the interstices of coarse aggregate, watering and compacting
to the required density as per technical Specification Cluase
405.

(A) By Manual Means


Unit = Cum
Taking Output = 360Cum
a) Labour
Mater Day 10.08 245.00
Mazdoor (Skilled) Day 2.00 245.00
Mazdoor (Unskilled) Day 250.00 245.00
Total
b) Machinery
Three wheel 80-100 kN static roller @ 8Cum per Hour Hour 45.00 741.00
wtaer tanker 6kl capacity Day 24.00 500.00
Total
c) Material (Refer Tables 400.7, 8, 9 and 10)
Aggregate
Grading 3 53mm to 22.4mm @ 0.91 cum per 10Sqm. For Cum 435.60 1067.00
comapcted thickness of 75mm
Stone Screenings
Type B 11.2 mm for grading 3 @ 0.18 Cum per 10 Sqm. Cum 86.40 1213.00
Water kl 144.00 102.00
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c +d Labour cess @ 1.00 %
Cost for 360cum = a+b+c+d+e
Rate per Cum = a+b+c+d+e/360 (Excluding
carriage)
Carriage
Stone aggregate Cum 522.00 1088.08
Cost for 360cum = a+b+c+d+e
Rate per Cum = a+b+c+d+e/360 (Including
carriage)
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 41
Chaper-4
Reference of
Sr. MORD
Description Unit Quantity Rate (Rs.)
No. Specification
s

v) Gravel/soil Aggregate base/sub-base Nominal


Maximum size Grading 40mm (Table 2.3 of IRC SP 77-
2008)
Construction of Gravel/soil aggregate sub-base/base by
providing well graded material of nominal maximum size
grading 40mm as per table 2.3 of IRC SP 77-2008, spreading
in uniform layers with tractor mount appropriate grading
arrangements on prepared surface, mixing by mix in place
method at OMC with tractor mount appropriate rotavator
attachment and cmpaction with three wheel 80-100 kN Static
Roller capacity to achieve the desired density complete as per
specifications contained in Para 2.2, 3.6 and 3.7 of IRC SP 77-
2008. Reference of MORD specificaions: NRRDA letter No. P-
17012/7/2005/P-III dated 20th April, 2009 and IRC SP 77-
2008.

Unit = cum
Taking output = 300 cum
a) labour
Mate day 0.40 245.00
Mazdoor (skilled) day 2.00 245.00
Mazdoor (unskilled) day 8.00 245.00
b) Machinery
Tractor mount grader @ 25cum per hour hour 12.00 1192.00
Three wheel 80-100 kN static roller @ 10cum per hour hour 30.00 741.00
Water tanker 6kl capacity hour 5.00 500.00
Tractor with rotavator 25cum per hour hour 12.00 688.00
c) Material
Well graded gravel/soil aggregate base material of nominal cum 360.00 817.00
maximum size 40mm as per table 2.3 of IRC SP 77-2008
Water kl 30.00 102.00
d) Add 13.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost for 300cum = a+b+c+d
Rate per Cum = a+b+c+d/300 (Excluding
carriage)
Carriage
Well graded gravel/soil aggregate base material of nominal Cum 360.00 427.05
maximum size 40mm
Cost for 300cum = a+b+c+d
Rate per Cum = a+b+c+d+e/300 (Including
carriage)

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 42
Chaper-4
Reference of
Sr. MORD
Description Unit Quantity Rate (Rs.)
No. Specification
s

Granular Sub Base with well graded Matarial (Table 400.1)


4.1 401

(A) By Mix in Place Method


Construction of granular sub-base by providing well graded
material spreading in uniform layers with tractor mount grader
on prepared surface mixing by mix in place methof with
rotavator at CM and compating with smooth wheel roller to
achieve the desired density, complete as per technical
specification Clause 401.

(I) For Grading I Material


Unit = Cum
Taking Output = 300Cum.
a) Labour
Mate Day 0.48 245.00
Mazdoor (Skilled) Day 2.00 245.00
Mazdoor (Unskilled) Day 10.00 245.00
Total
b) Machinery
Tractor Mount grader @ 25Cum/Hour Hour 12.00 1192.00
Three Wheel 80-100kN static roller @ 10Cum/Hour Hour 30.00 745.00
Tractor mount with Ratavator/grader 25Cum/Hour Hour 12.00 688.00
Water tanker 6Kl capacity Hour 5.00 500.00
Total
c) Material
Well graded granular sub-base material Cum 360.00 938.00
Water kl 30.00 102.00
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add 1 % labour cess on (a+b+c+d)
Cost for 300cum = a+b+c+d+e
Rate per Cum = (a+b+c+d+e)/300 (Excluding
carriage)
Carriage
Well graded granular sub-base material Cum 360.00 420.42
Cost for 300cum
Rate per Cum (Including carriage)
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 43
Chaper-4
Reference of
Sr. MORD
Description Unit Quantity Rate (Rs.)
No. Specification
s

Non Construction of pavement base/sub base/subgrade layer using RBI-81 an inorganic pavement material and
Schedule soil stabilizer by pulverization, spreading, mixing and compaction at OMC in 75/200mm thick layers all as
specified in construction manual provided by alchemist touchnology ltd. Construction of stabilizer soil layer
by providing soil and using 2.0 % RBI Grade- 81 (by weight), spreading in uniform layers of 100-150 mm with
motor/tractor grader on prepared surface, spreading, mixing by mix in place method with rotavater at OMC,
and compacting with vibratory soil compactor of 10-12 tonne to achieve the desired density, complete as per
technical specification all as specifications and Engineer-in-Charge direction.

Layer composition (%)

Soil 10 mm aggregate 20m Stone RBI


100 0 m
0 dust 0.00 Grade-81
2.00
Design of mix (g/cc) agg. 1.90
Unit= Cum
Taking Output = 200Cum.
a) Labour
Mate Day 2.00 245.00
Mazdoor (Skilled) for checking line and level Day 3.00 245.00
Mazdoor (Unskilled) Day 16.00 245.00
Total
b) Machinery
Backhoe Loader (JCB) Hour 3.50 1321.00
Earth vibratory compactor Hour 7.00 1319.00
Tractor with Ratavator Hour 3.50 688.00
Taractor trolley/Dumper 8.00 581.00
Water tanker 6Kl capacity Hour 8.00 500.00
Tractor grader Hour 8.00 801.00
Total
c) Material
Soil Cum 250.00 200.00
RBI Grade-81 tonne 6.00 34000.00
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add 1 % labour cess on (a+b+c+d)
Cost for 200cum = a+b+c+d+e
Rate per Cum = (a+b+c+d+e)/300 (Excluding
carriage)
Carriage
Soil tonne 250.00 98.92
RBI-81 Cum 6.00 357.38
Cost for 200cum
Rate per Cum (Including carriage)
Say

Executive Engineer,
B&R Division HP.PWD.,

Page 44
Chaper-4
Reference of
Sr. MORD
Description Unit Quantity Rate (Rs.)
No. Specification
s
Joginder Nagar

RBI Grade-81 Treated Soil Base Unit Quantity Rate Rs

Providing, Laying, spreading and compacting available soil (excluding clay soils) in base course including in situ mixing 50%- 20
mm down Aggregate, 50% soil and 3.50% of RBI 81 product by Alchemist touchnology ltd, spreading in uniform layers with
motor/tractor grader on a prepared base including watering and compacting with 8 to 10 tonne Vibratory power roller to achieve
the desired density including all materials, labour, HOM of machinery, etc complete as per specifications.

Unit = cum
Density = 2.00 g/cc
Taking output = 300.00 cum
600.00 MT
a) Labour
Mate day 0.48 245.00
Mazdoor (Skilled) day 2.00 245.00
Mazdoor (Unskilled) day 10.00 245.00
Total of (a)
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity hour 5.00 1843.00
Tipper 5.5 cum, 4 trips per hour hour 14.00 513.00
Tractor mounted grader hour 6.00 1192.00
Vibratory roller 8 - 10 tonne hour 4.30 2417.00
Tractor with Rotavator and blade @25 cum per hour hour 12.00 688.00
Water tanker 6 KL capacity hour 5.00 500.00
Total of (b)
c) Material
Soil @ 50% cum 187.50 63.00
20 mm @ 50% cum 172.50 1276.00
Quantity of RBI Grade-81 by weight @ 3.5% MT 21.00 34000.00
Cost of water @ 10% KL 60.00 102.00
Total of (c)
d) Add 12.50% on a+b+c (Contractor's profit @ 10% + Over
head Charges @ 2.5% )
e) Add 1 % labour cess on (a+b+c+d)
Cost for 300cum = a+b+c+d+e
Rate per Cum = (a+b+c+d+e)/300 (Excluding carriage)
Carriage
Soil cum 187.50 98.92
Agg. cum 172.50 921.56
RBI-81 tonne 21.00 260.90
Cost for 300cum
Rate per Cum (Including carriage)
Say

Executive Engineer,
B&R Division, HPPWD.,

Page 45
Chaper-4
Reference of
Sr. MORD
Description Unit Quantity Rate (Rs.)
No. Specification
s
Joginder Nagar.

Page 46
Amount (Rs.)

117.60
490.00
2450.00
3057.60

14304.00
22350.00
8256.00
2500.00
47410.00

337680.00
3060.00
340740.00
48900.95

4401.09
444509.64
1481.70

202276.80
646786.44
2155.95
2155.95

gineer,
HP.PWD.,
ar

Page 47
Amount (Rs.)

2469.60
490.00
61250.00
64209.60

26676.00
12000.00
38676.00

414691.20

118584.00

2361.60

14688.00
550324.80
81651.30

7348.62
742210.32
2061.70

440294.40
1182504.70
3284.74

3284.70

gineer,
,HPPWD.,
ar.

Page 48
Amount (Rs.)

2469.60
490.00
61250.00
64209.60

33345.00
12000.00
45345.00

435164.40

116460.13

2361.60

14688.00
568674.13
84778.59

7630.07
770637.39
2140.66

609770.91
1380408.31
3834.47

3834.45

gineer,
,HPPWD.,
ar.

Page 49
Amount (Rs.)

2469.60
490.00
61250.00
64209.60

33345.00
12000.00
45345.00

464785.20

104803.20
14688.00
584276.40
86728.88

7805.60
788365.47
2189.90

567977.76
1356343.20
3767.62

3767.60

gineer,
HP.PWD.,
ar

Page 50
Amount (Rs.)

98.00
490.00
1960.00

14304.00
22230.00
2500.00
8256.00

294120.00

3060.00
46847.43

393865.43
1312.88

153738.00

547603.40
1825.30

gineer,
HP.PWD.,
ar

Page 51
Amount (Rs.)

117.60
490.00
2450.00
3057.60

14304.00
22350.00
8256.00
2500.00
47410.00

337680.00
3060.00
340740.00
48900.95

4401.09
444509.64
1481.70

151351.20
595860.84
1986.20
1986.20

gineer,
HP.PWD.,
ar

Page 52
Amount (Rs.)

c pavement material and


00mm thick layers all as
on of stabilizer soil layer
yers of 100-150 mm with
d with rotavater at OMC,
density, complete as per

layer code

490.00
735.00
3920.00
5145.00

4623.50
9233.00
2408.00
4648.00
4000.00
6408.00
31320.50

50000.00
204000.00
254000.00
36308.19

3267.74
330041.43
1650.21

24730.00
2144.28
356915.71
1784.58
1784.60

gineer,
HP.PWD.,

Page 53
Amount (Rs.)

ar

Cost Rs

g in situ mixing 50%- 20


g in uniform layers with
y power roller to achieve

117.60
490.00
2450.00
3057.60

9215.00
7182.00
7152.00
10393.10
8256.00
2500.00
44698.10

11812.50
220110.00
714000.00
6120.00
952042.50
124974.78

11247.73
1136020.71
3786.74

18547.50
158969.10
5478.90
1319016.21
4396.72
4396.70

xecutive Engineer,
&R Division, HPPWD.,

Page 54
Amount (Rs.)

oginder Nagar.

Page 55
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications
5.1 502 Prime Coat
(i) Low Porosity
Providing and applying primer coat with bitumen emulsion
(SS-1) as perpared surface of granular base including
cleaning the road suface and spraying primer at the rate of
0.70-1.00 kg/Sqm. Using mechanical means as per
Techincal Specification clause 502.
Unit = Sqm.
Taking output = 1750 sqm.
a) Labour
Mate Day 0.04 245.00
Mazdoor (Unskilled) Day 1.00 245.00
Total
b) Machinery
Hydrostatic broom @ 1250 sqm per hour Hour 1.40 528.00
Air compressor 210 cfm Hour 1.40 465.00
Bitumen emulsion pressure distrubutor @ 1750 sqm per Hour 1.00 1569.00
hour
Water tanker 6 kl capacity 1 trip per hour Hour 0.50 500.00
Total
c) Material
Bitumen emulsion (SS-1) @ 0.85 kg per sqm t 1.48 45198.00
Water kl 3.00 102.00
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 %
Cost for 1750 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d+e/1750 (Excluding carriage)
Carriage
Bitumen emulsion (SS-1 t 1.48 702.58
Cost for 1750 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d+e/1750 (Including carriage)
Add 1 % labour cess Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 56
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

5.9 508 20mm thick open graded premix carpet using


bitumenous (penetration grade/modified bitumen)
binder
Providing, laying and rolling of open graded premix carpet of
20mm thickness composed of 13.2mm to 5.6mm aggregates
either using penetration grade bitumen or emulsion to
required line, grade and level to serve as wearing course on
a previously prepared base, including mixing in a suitable
plant, laying and rolling with a three wheel 80-100kN static
roller capacity, finished to required level and grades to be
followed by seal coat of either Type A or Type B or Type C as
per Technical Specification Clause 508.

Case-II By Mechnical Means


(I) Bituem (VG-10)
Unit = Sqm.
Taking output = 4000Sqm. (80Cum.)
a) Labour
Mate Day 0.52 245.00
Mazdoor (Unskilled) Day 10.00 245.00
Mazdoor (Skilled) Day 3.00 245.00
Total
b) Machinery
HMP 30/40Tonne/Hour Hour 6.00 13798.00
Electric Generator Set 125KVA Hour 6.00 1125.00
Front End loader 1Cum. Bucket Capacity Hour 6.00 1281.00
Tipper 5.5 10 Tonne Capacity Hour 3.64 513.00
Paver Finisher Hour 6.00 4300.00
Three wheeled 80-100 kN Static Roller Hour 16.00 741.00
Total
c) Material
Bitumen (VG-10) @ 14.60Kg./10Sqm. t 5.84 34992.53
Crushed stone chipping 13.2mm to 5.6mm @ cum. 108.00 1220.00
0.27Cum./10Sqm.
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 %)
Cost for 4000Sqm. = a+b+c+d+e
Rate per Sqm. = a+b+c+d+e/4000 (Excluding
carriage)
Carriage
Bitumen t 5.84 702.58
Stone Aggregate cum 108.00 1088.08
Cost for 4000Sqm. = a+b+c+d+e
Rate per Sqm. = a+b+c+d+e/4000 (Including
carriage)
Say

Page 57
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications
Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

5.9 508 20mm thick open graded premix carpet using


bitumenous (penetration grade/modified bitumen)
binder
Providing, laying and rolling of open graded premix carpet of
20mm thickness composed of 13.2mm to 5.6mm aggregates
either using penetration grade bitumen or emulsion to
required line, grade and level to serve as wearing course on
a previously prepared base, including mixing in a suitable
plant, laying and rolling with a three wheel 80-100kN static
roller capacity, finished to required level and grades to be
followed by seal coat of either Type A or Type B or Type C as
per Technical Specification Clause 508.

Case-I By Mannual Means


(I) Bituem (S-90)
Unit = Sqm.
Taking output = 500Sqm. (10Cum.)
a) Labour
Mate Day 1.08 245.00
Mazdoor (Unskilled) Day 21.00 245.00
Mazdoor (Skilled) Day 6.00 245.00
Total
b) Machinery
Mixall 6/10 t capacity Hour 4.00 #REF!
Bitumen boiler oil fired 1000 ltr. Capacity fitted with spray Hour 4.00 #REF!
capacity
Three wheeled 80-100 kN Static Roller Hour 2.00 741.00
Total
c) Material
Bitumen (S-90) @ 14.60Kg./10Sqm. t 0.73 34992.53
Crushed stone chipping 13.2mm to 5.6mm @ cum. 13.50 983.00
0.27Cum./10Sqm.
Total
d) Add 13.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost for 4000Sqm. = a+b+c+d+e
Rate per Sqm. = a+b+c+d+e/500 (Excluding
carriage)
Carriage
Bitumen t 0.73 1522.95
Stone Aggregate cum 13.50 784.60
Cost for 4000Sqm. = a+b+c+d+e
Rate per Sqm. = a+b+c+d+e/500 (Including
carriage)

Not Corrected

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 58
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

5.12 510 Seal Coat


Providing and applying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade and
cross fall using Type A, Type B and Type C as per Technical
Specification Clause 510
A) By Manual Means
Case - 1 Type A
(I) Bitumen (S-90)
Unit = Sqm
Taking output = 1100Sqm
a) Labour
Mate day 1.15 210.00
Bitumen Sprayer day 1.00 252.00
Mazdoor (Skilled) day 22.00 331.00
Mazdoor (Semi-Skilled) day 6.00 331.00
Total
b) Machinery
Bitumen boiler oil fired, capacity 1000 liter fitted with sapray hour 2.20 1408.00
set
Three wheel 80-100 kN roller hour 2.20 741.00
Total
c) Material
Bitumen (S-90) @ @ 9.80 kg per 10 sqm t 1.078 34992.53
Crushed stone chipping of 6.7mm size 100 per cent crossing cum 9.90 1103.00
11.2mm sieve and retained on 2.36mm sieve accoed @
0.09cum per 10 sqm.
Total
d) Add 13.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost for 1100 sqm = a+b+c+d
Rate per Sqm = a+b+c+d/1100 (Excluding
carriage)
Carriage
Bitumen t 1.078 1522.95
Aggregate cum 9.90 784.60
Cost for 1100 sqm
Rate per Sqm (Including carriage)

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 59
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

5.1 502 (iii) Providing and applying tack coat with bitumen S-90
@ 0.25 to 0.30 per Kg./Sqm. On the prepared granular
surfaces treated with primer and cleaned with Hydraulic
broom as per technical specification Clause503.

Unit = Sqm.
Taking output 1750Sqm.
a) Labour
Mate day 0.04 210.00
Mazdoor (Unskilled) day 1.00 331.00
Total
b) Machinery
Hydraulic broom @ 1250sqm per hour hour 1.50 528.00
Air compressor 210 cfm hour 1.40 465.00
Bitumen pressure distributer @ 1750sqm per hor hour 1.00 1569.00
Total
c) Material
Bitumen (S-90) @ 0.275Kg per sqm t 0.48 34992.53
d) Add 13.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost of 1750Sqm. (a+b+c+d)
Rate per Sqm. (Excluding carriage)
Carriage
Bitumen t 0.48 1522.95
Cost for 1750 sqm
Rate per Sqm (Including carriage)

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 60
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

5.12 510 Seal Coat


Providing and applying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade and
cross fall using Type A, Type B and Type C as per Technical
Specification Clause 510
Case - II Type B
(I) Bitumen (S-90)
Unit = Sqm
Taking output = 1100Sqm
a) Labour
Mate day 0.85 210.00
Mazdoor (unskilled) day 15.00 331.00
Mazdoor (Semi-Skilled) day 2.00 331.00
Total
b) Machinery
Mixall 6/10t capacity hour 2.50 741.00
Three wheel 80-100 kN roller hour 2.50 741.00
Bitumen boiler oil fired, capacity 1000 liter fitted with sapray hour 2.50 1408.00
set
Total
c) Material
Bitumen (S-90) @ 6.80 kg per 10 sqm t 0.850 34992.53
Crushed sand or grit as passing 2.36mm sieve and retained cum 7.50 1093.00
on 180micron sieve applied @ 0.06cum per 10sqm.

Total
d) Add 13.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost for 1100 sqm = a+b+c+d
Rate per Sqm = a+b+c+d/1100 (Excluding
carriage)
Carriage
Bitumen t 0.850 1522.95
Aggregate cum 7.500 784.60
Cost for 1100 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d+e/1100 (Including
carriage)

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 61
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

5.1 502 Prime Coat


(ii) Medium Porosity
Providing and applying primer coat with bitumen emulsion
(SS-1) as perpared surface of granular base including
cleaning and road suface and spraying primer at the rate of
0.90-1.4agg/Sqm. Using mechanical means as per Techincal
Specification clause 502.
Unit = Sqm.
Taking output = 1750 sqm.
a) Labour
Mate Day 0.10 210.00
Mazdoor (Unskilled) Day 2.00 331.00
Total
b) Machinery
Hydrostatic broom @ 1250 sqm per hour Hour 1.40 528.00
Air compressor 210 cfm Hour 1.40 465.00
Bitumen emulsion pressure distrubutor @ 1750 sqm per Hour 1.00 1569.00
hour
Water tanker 6 kl capacity 1 trip per hour Hour 0.50 500.00
Total
c) Material
Bitumen emulsion (SS-1) @ 1.05 kg per sqm t 1.83 34992.53
Water kl 3.00 102.00
Total
d) Add 13.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost for 1750 sqm = a+b+c+d
Rate per Sqm = a+b+c+d/1750 (Excluding
carriage)
Carriage
Bitumen t 1.83 1522.95
Cost for 1750 sqm
Rate per Sqm (Including carriage)

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 62
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

5.12 510 Seal Coat


Providing and laying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade and
cross fall using Type B as per Technical Specification Clause
510 (By mechanical means)
Case - II Type B
(I) Bitumen (VG-10)
Unit = Sqm
Taking output = 5000Sqm (30Cum)
a) Labour
Mate day 0.16 245.00
Mazdoor (unskilled) day 4.00 245.00
Total
b) Machinery
HMP of 30/40 tonne/Hour hour 2.00 13798.00
Electric generator set 125KVA hour 2.00 1125.00
Front end loader cum bucket capacity hour 2.00 1281.00
Tipper 5.5Tonne capacity hour 1.36 513.00
Paver finisher hour 2.00 4300.00
Three wheel 80-100 kN static roller hour 10.00 741.00
Total
c) Material
Bitumen (VG-10) @ 6.80 kg per 10 sqm t 3.40 34992.53
Crushed sand defined as passing 2.36mm sieve and cum 30.00 1093.00
retained on 180micron sieve applied @ 0.06 cum per
10sqm.
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 %
Cost for 5000 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d/5000 (Excluding
carriage)
Carriage
Bitumen t 3.40 702.58
Crushed sand cum 30.00 947.68
Cost for 5000 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d/5000 (Including
carriage)
F Say

Page 63
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

5.2 503 (ii) Providing and applying tack coat with bitumen emulsion
(RS-1) using emulsion distributor @ 0.25 to 0.30Kg/sqm. On
the prepared dry and hungry bituminous/ granular surface
cleaned with hydroulic as per the technical specification
clause-503.
Unit = Sqm.
Taking output = 1750 sqm.
a) Labour
Mate Day 0.04 245.00
Mazdoor (Unskilled) Day 1.00 245.00
Total
b) Machinery
Hydrostatic broom @ 1250 sqm per hour Hour 1.40 528.00
Air compressor 210 cfm Hour 1.40 465.00
Bitumen emulsion pressure distrubutor @ 1750 sqm per Hour 1.00 1569.00
hour
Total
c) Material
Bitumen emulsion (RS-1) @ 0.275 kg per sqm t 0.48 42793.00
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 %
Cost for 1750 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d+e/1750 (Excluding carriage)
Carriage
Bitumen emulsion (RS-1) t 0.48 702.58
Cost for 1750 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d+e/1750 (Including carriage)
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 64
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

5.1 502 Prime Coat


(i) Low Porosity
Providing and applying primer coat with bitumen emulsion
(SS-1) on prepared surface of granular base including
cleaning of road surface and spraying primer at the rate of
0.70-1.00 kg/sqm using mechnical means as per technical
specification Cluase502.
Unit = Sqm.
Taking output = 1750 sqm.
a) Labour
Mate Day 0.04 210.00
Mazdoor (Unskilled) Day 1.00 331.00
Total
b) Machinery
Hydrostatic broom @ 1250 sqm per hour Hour 1.40 528.00
Air compressor 210 cfm Hour 1.40 465.00
Bitumen emulsion pressure distrubutor @ 1750 sqm per Hour 1.00 1569.00
hour
Water tank 6 kg capacity 1 trip/hour Hour 0.50 500.00
Total
c) Material
Bitumen @ 1.0 Kg./Sqm t 1.48 45198.00
Water kl 3.00 102.00
Total
d) Add 13.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost for 1750 sqm = a+b+c+d
Rate per Sqm = a+b+c+d/1750 (Excluding carriage)
Carriage
Bitumen t 1.75 1522.95
Cost for 1750 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d+e/1750 (Including carriage)

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 65
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

5.1 502 Prime Coat


(i) Low Porosity
Providing and applying tack coat with bitumen emulsion
distributor at the rate of 0.5 Kg. Per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom

Unit = Sqm.
Taking output = 1750 sqm.
a) Labour
Mate Day 0.04 210.00
Mazdoor (Unskilled) Day 1.00 331.00
Total
b) Machinery
Hydrostatic broom @ 1250 sqm per hour Hour 1.40 528.00
Air compressor 210 cfm Hour 1.40 465.00
Bitumen emulsion pressure distrubutor @ 1750 sqm per Hour 1.00 1569.00
hour
Total
c) Material
Bitumen @ 0.5 Kg./Sqm t 0.88 45198.00
Total
d) Add 13.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost for 1750 sqm = a+b+c+d
Rate per Sqm = a+b+c+d+e/1750 (Excluding carriage)
Carriage
Bitumen t 0.88 1522.95
Cost for 1750 sqm = a+b+c+d
Rate per Sqm = a+b+c+d+e/1750 (Including carriage)

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 66
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

5.1 502 Prime Coat


(i) Low Porosity
Providing and applying tack coat with bitumen emulsion
distributor at the rate of 1.0 Kg. Per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom

Unit = Sqm.
Taking output = 1750 sqm.
a) Labour
Mate Day 0.04 210.00
Mazdoor (Unskilled) Day 1.00 331.00
Total
b) Machinery
Hydrostatic broom @ 1250 sqm per hour Hour 1.40 528.00
Air compressor 210 cfm Hour 1.40 465.00
Bitumen emulsion pressure distrubutor @ 1750 sqm per Hour 1.00 1569.00
hour
Total
c) Material
Bitumen @ 0.5 Kg./Sqm t 1.75 34992.53
Total
d) Add 13.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost for 1750 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d/1750 (Excluding carriage)
Carriage
Bitumen t 1.75 1522.95
Cost for 1750 sqm = a+b+c+d
Rate per Sqm = a+b+c+d+e/1750 (Including carriage)

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 67
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

Providing and applying priming/tack coat with bituminous


primer (VG-10) at the rate of 1.00 kg per sqm on existing
WBM surface cleaned with mechnical brooms as per
HPPWD/MORD specification.
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate day 0.04 210.00
Mazdoor (unskilled) day 1.00 331.00
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 1.40 528.00
Air Compressor 210 cfm hour 1.40 465.00
Bitumen boier oil fired with spray set @ 1000 litre sqm per hour 4.38 1408.00
hour
c) Material
Bitumen (VG-10) @ 1 kg per sqm t 1.75 34992.53
d) Add 13.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost for 1750 sqm = a+b+c+d
Rate per Sqm = a+b+c+d/1750 (Excluding carriage)
Carriage
Bitumen t 1.75 1522.95
Cost for 1750 sqm = a+b+c+d
Rate per Sqm = a+b+c+d+e/1750 (Including carriage)

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 68
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

5.10 508.2 20mm thick open graded premix carpet using bitumen
emulsion as per Technical Specification Clause 508.2

Providing, laying and rolling of open graded premix carpet of


20mm thickness composed of 13.2mm to 5.6mm aggregates
either using penetration grade bitumen emulsion (MS) to
required line, grade and level to serve as wearing course on
a previously prepared base, including mixing in a concrete
mixer, laying and rolling with a three wheel 80-100kN static
roller capacity, finished to required level and grades to be
followed by seal coat of Type C as per Technical
Specification Clause 508.2

(I) Bituem Emulsion (MS)


Unit = Sqm.
Taking output = 900 Sqm. (24.30 Cum.)
a) Labour
Mate Day 0.80 210.00
Mazdoor (Unskilled) Day 18.00 331.00
Mazdoor (Skilled) Day 2.00 331.00
Total
b) Machinery
Concrete mixer 0.40/0.28 cum capacity Hour 6.00 350.00
Three wheeled 80-100 kN Static Roller Hour 3.60 741.00
Total
c) Material
Bitumen emulsion (MS) @ 21.50 Kg./10Sqm. t 1.94 47091.00
Crushed stone chipping 13.2mm to 5.6mm @ cum. 24.30 1220.00
0.27Cum./10Sqm.
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 %
Cost for 900 Sqm. = a+b+c+d+e
Rate per Sqm. = a+b+c+d+e/900 (Excluding
carriage)
Carriage
Bitumen emulsion (MS) t 1.94 783.15
Stone Aggregate cum 24.30 943.28

Page 69
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications
Cost for 900Sqm. = a+b+c+d+e
Rate per Sqm. = a+b+c+d+e/900 (Including
carriage)
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

5.12 510 Seal Coat by using bitumen emulsion SS2


Providing and laying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade and
cross fall using Type C as per Technical Specification Clause
510 (By mechanical means)
Case - II Type C
(I) Bitumen (SS2)
Unit = Sqm
Taking output = 5000Sqm (30 Cum)
a) Labour
Mate day 0.16 210.00
Mazdoor (unskilled) day 4.00 331.00
Total
b) Machinery
Concrete mixer hour 8.00 350.00
Three wheel 80-100 kN static roller hour 10.00 741.00
Total
c) Material
Bitumen (SS2) @ 6.80 kg per 10 sqm t 3.40 45198.00
Crushed sand defined as passing 2.36mm sieve and cum 30.00 1093.00
retained on 180micron sieve applied @ 0.06 cum per
10sqm.
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 %
Cost for 5000 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d/5000 (Excluding
carriage)
Carriage
Bitumen emulsion (SS2) t 3.40 6131.40
Crushed sand cum 30.00 682.60
Cost for 5000 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d/5000 (Including
carriage)
Say

Page 70
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

5.12 510 Seal Coat by using CRRI Bitchem cold mix


binder
Providing and laying seal coat using CRRI- Bitchem cold
mix, sealing the voids in a bituminous surface laid to the
specified levels, grade and cross fall using Type C as per
Technical Specification Clause 510 (By mechanical means)

Case - II Type B
(I) CRRI Bitchem cold mix binder
Unit = Sqm
Taking output = 1250 Sqm (11.25 Cum)
a) Labour
Mate day 0.80 210.00
Mazdoor (unskilled) day 14.00 331.00
Total
b) Machinery
Concrete mixer hour 2.00 350.00
Three wheel 80-100 kN static roller hour 2.00 741.00
Total
c) Material
CRRI Bitchem cold mix binder( All in 1) @ 10 kg per 10 sqm t 1.25 47104.00
Crushed stone chipping of 6.7 mm size 100 % passing cum 11.25 983.00
9.5mm sieve and retained on 2.36 mm sieve applied @ 0.09
cum per 10sqm.
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 %
Cost for 1250 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d/1250 (Excluding
carriage)
Carriage
CRRI Bitchem cold mix binder( All in 1) t 1.25 1000.05
Crushed stone chipping of 6.7 mm size cum 11.25 722.23
Cost for 1250 sqm = a+b+c+d+e

Page 71
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications
Rate per Sqm = a+b+c+d/1250 (Including
carriage)
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

5.1 502 Prime Coat with Bitchem Regular Emulsion


(i) Low Porosity
Providing and applying primer coat with bitumen Bitchem
regular emulsion as perpared surface of granular base
including cleaning the road suface and spraying primer at
the rate of 0.70-1.00 kg/Sqm. Using mechanical means as
per Techincal Specification clause 502.
Unit = Sqm.
Taking output = 1750 sqm.
a) Labour
Mate Day 0.04 210.00
Mazdoor (Unskilled) Day 1.00 331.00
Total
b) Machinery
Hydrostatic broom @ 1250 sqm per hour Hour 1.40 528.00
Air compressor 210 cfm Hour 1.40 465.00
Emulsion pressure distrubutor @ 1750 sqm per hour Hour 1.00 1569.00
Water tanker 6 kl capacity 1 trip per hour Hour 0.50 500.00
Total
c) Material
Bitchem Regular Emulsion (CSS-I) @ 0.85 kg per sqm t 1.48 42204.00
Water kl 3.00 102.00
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 %
Cost for 1750 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d+e/1750 (Excluding carriage)
Carriage
Bitchem Regular Emulsion (CSS-I) t 1.48 1000.05
Cost for 1750 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d+e/1750 (Including carriage)
Say

Page 72
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

5.10 508.2 20mm thick open graded premix carpet using Bitumen
Emulsion as per Technical Specification Clause 508.2

Providing, laying and rolling of open graded premix carpet of


20mm thickness composed of 13.2mm to 5.6mm nominal
size aggregates with 2:1 ratio by using Bitumen emulsion
(MS) to required line, grade and level to serve as wearing
course on a previously prepared base, including mixing to a
suitable plan, laying and rolling with a three wheel 80-100kN
static roller capacity, finished to required level and grades to
be followed by seal coat of Type A or Typ[e B or Type C as
per Technical Specification

(I) CRRI Bitchem Cold Mix Binder


Unit = Sqm.
Taking output = 900 Sqm. (24.30 Cum.)
a) Labour
Mate Day 0.80 210.00
Mazdoor (Unskilled) Day 18.00 331.00
Mazdoor (Skilled) Day 2.00 331.00
Total
b) Machinery
Concrete mixer 0.40/0.28 cum capacity Hour 6.00 350.00
Three wheeled 80-100 kN Static Roller Hour 3.60 741.00
Total
c) Material
Bitumen emulsion (MS) @ 21.50 Kg./10Sqm. t 1.94 47091.00
Crushed stone chipping 13.2mm to 5.6mm @ cum. 24.30 1220.00
0.27Cum./10Sqm.
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 %

Page 73
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications
Cost for 900 Sqm. = a+b+c+d+e
Rate per Sqm. = a+b+c+d+e/900 (Excluding
carriage)
Carriage
Bitumen emulsion (MS) t 1.94 8758.83
Crushed stone chipping 13.2mm to 5.6mm cum 24.30 943.28
Cost for 900Sqm. = a+b+c+d+e
Rate per Sqm. = a+b+c+d+e/900 (Including
carriage)
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 74
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications
5.2 503 (ii) Providing and applying tack coat with CRRI Bitchem
cold mix binder using emulsion distributor @ 0.25 to
0.30Kg/sqm. On the prepared granular surface treated with
primer & cleaned with Hydraulic broom as per the technical
specification clause-503.
Unit = Sqm.
Taking output = 1750 sqm.
a) Labour
Mate Day 0.04 210.00
Mazdoor (Unskilled) Day 1.00 331.00
Total
b) Machinery
Hydrostatic broom @ 1250 sqm per hour Hour 1.40 528.00
Air compressor 210 cfm Hour 1.40 465.00
Bitumen emulsion pressure distrubutor @ 1750 sqm per Hour 1.00 1569.00
hour
Total
c) Material
CRRI Bitchem cold mix binder @ 0.275 kg per sqm t 0.48 38702.00
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 %
Cost for 1750 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d+e/1750 (Excluding carriage)
Carriage
Bitumen t 0.48 0.00
Cost for 1750 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d+e/1750 (Including carriage)
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 75
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

5.12 510 Seal Coat by using Emulsion cold mix binder


Providing and laying seal coat using CRRI- Bitchem cold
mix, sealing the voids in a bituminous surface laid to the
specified levels, grade and cross fall using Type C as per
Technical Specification Clause 510 (By mechanical means)

Case - II Type B
(I) Emulsion cold mix binder
Unit = Sqm
Taking output = 1250 Sqm (11.25 Cum)
a) Labour
Mate day 0.80 116.67
Mazdoor (unskilled) day 14.00 116.67
Total
b) Machinery
Concrete mixer hour 2.00 0.00
Three wheel 80-100 kN static roller hour 2.00 0.00
Total
c) Material
CRRI Bitchem cold mix binder @ 10 kg per 10 sqm t 1.25 0.00
Crushed stone chipping of 6.7 mm size 100 % passing cum 11.25 0.00
9.5mm sieve and retained on 2.36 mm sieve applied @ 0.09
cum per 10sqm.
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 %
Cost for 1250 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d/1250 (Excluding
carriage)
Carriage
CRRI Bitchem cold mix binder t 1.25 0.00
Crushed stone chipping of 6.7 mm size cum 11.25 0.00
Cost for 1250 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d/1250 (Including
carriage)
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 76
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications
5.2 503 (ii) Providing and applying tack coat with bitumen emulsion
(RS-1) using emulsion distributor @ 0.20 to 0.25Kg/sqm. On
the prepared bituminous surface cleaned with hydroulic as
per the technical specification clause-503.
Unit = Sqm.
Taking output = 1750 sqm.
a) Labour
Mate Day 0.04 210.00
Mazdoor (Unskilled) Day 1.00 331.00
Total
b) Machinery
Hydrostatic broom @ 1250 sqm per hour Hour 1.40 528.00
Air compressor 210 cfm Hour 1.40 465.00
Bitumen emulsion pressure distrubutor @ 1750 sqm per Hour 1.00 1569.00
hour
Total
c) Material
Bitumen emulsion (RS-1) @ 0.225 kg per sqm t 0.39 42793.00
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 %
Cost for 1750 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d+e/1750 (Excluding carriage)
Carriage
Bitumen t 0.39 586.00
Cost for 1750 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d+e/1750 (Including carriage)
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 77
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

5.7 508 Semi-Dense Bituminous Concrete


Providing and laying semi dense bituminous concrete
with 100-120 TPH batch type HMP producing an
average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with
bituminous binder @ 4.5 to 5 per cent of mix and
filler, transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the
required grade, level and alignment, rolling with
smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MoRTH
specification clause No. 508 complete in all respects

Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 331.00
Mazdoor working with HMP, mechanical broom, paver, day 16.000 331.00
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 331.00
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 16896.00
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 4300.00
cum per hour
Generator 250 KVA hour 6.000 1125.00
Front end loader 1 cum bucket capacity hour 6.000 1281.00
Tipper 10 tonne capacity tonn 450 x 10 4.02
e.km
Add 10 per cent of cost of carriage to cover cost of
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00 x
down rolling. 0.65*
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00 x 741.00
0.65*
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00 x 741.00
roller 0.65*
c) Material
Grading II: 10 mm (Nominal Size)
Bitumen @ 5 per cent of weight of mix tonn 22.500 34992.53
e
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm @ 57 per cent cum 162.45 1103.00
4.75 and below @ 41 per cent cum 116.85 1103.00
Filler @ 2 per cent of weight of aggregates. tonn 8.620 7400.00
e

Page 78
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications
*Any one of the alternative may be adopted as per
approved design
for Grading I ( 13 mm nominal size )
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 %
Cost for 195 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/195 (For Grading I)

Carriage by Mech. Tpt.


Bitumen cum 22.50 618.33
Agg. cum 279.30 950.52
Filler tonn 8.620 272.84
e
Cost for 195 cum
Rate per cum
Rate per Cum including carriage
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 79
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

5.3 504 Bituminous Macadam


Providing and laying bituminous macadam with 40-60
TPH hot mix plant producing an average output of 40
tonnes per hour using crushed aggregates of specified
grading premixed with bituminous binder, transported
to site, laid over a previously prepared surface with
paver finisher to the required grade, level and
alignment and rolled as per clauses 501.6 and 501.7
to achieve the desired compaction

Unit = cum
Taking output = 102.50 cum (225 tonnes)
a) Labour
Mate day 0.520 210.00
Mazdoor working with HMP, mechanical broom, paver, day 10.000 331.00
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 3.000 331.00
b) Machinery
Batch mix HMP 40-60 TPH @ 40 tonne per hour hour 6.000 16896.00
actual output
Mechanical broom hydraulic @ 1250 sqm per hour hour 1.100 528.00

Air compressor 250 cfm hour 1.100 465.00


Paver finisher hydrostatic with sensor control @ 75 hour 6.000 4300.00
cum per hour
Generator 125 KVA hour 6.000 1125.00
Front end loader 1 cum bucket capacity hour 6.000 1281.00
Tipper 10 tonne capacity hour 6.210 513.00
Smooth wheeled roller 80-100 kn tandem rollar for hour 12.000 1319.00
initial break down rolling, final and finishing rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.000 2417.00
c) Material
i) Bitumen @ 3.3 per cent of mix VG-10 T 7.425 34992.53
weight of mix = 205 x 2.2 = 450 tonne
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes
Weight of aggregate = 450 -14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
GradingII(19 mm nominal size)
25 - 10 mm 40 per cent cum 58.020 1276.00
10 - 5 mm 40 per cent cum 58.020 1276.00
5 mm and below 20 per cent cum 29.010 1276.00
* Any one of the alternative may be adopted as per
approved design
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )

Page 80
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications
e) Add on a+b+c+d Labour cess @ 1.00 %
Cost for 102.50 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/102.50 excluding
carriage
Carriage by Mech Tpt.
Bitumen T 7.43 618.33
Agg. Cum 145.05 950.52

Cost for 102.50 cum


Rate per cum = (a+b+c+d+e)/102.50 including
carriage
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 81
Chapter-5
Sr. Reference of Description Unit Quantity Rate (Rs.)
No. MORD
Specifications

5.2 503 (iii) Providing and applying tack coat with bitumen emulsion
(RS-1) using emulsion distributor @ 0.25 to 0.30Kg/sqm on
the prepared granular surface treated with primer and
cleaned with hydroulic broom as per the technical
specification clause-503.
Unit = Sqm.
Taking output = 1750 sqm.
a) Labour
Mate Day 0.04 245.00
Mazdoor (Unskilled) Day 1.00 245.00
Total
b) Machinery
Hydrostatic broom @ 1250 sqm per hour Hour 1.40 528.00
Air compressor 210 cfm Hour 1.40 465.00
Bitumen emulsion pressure distrubutor @ 1750 sqm per Hour 1.00 1569.00
hour
Total
c) Material
Bitumen emulsion (RS-1) @ 0.275 kg per sqm t 0.48 42793.00
Total
d) Add 12.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 %
Cost for 1750 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d+e/1750 (Excluding carriage)
Carriage
Bitumen emulsion (RS-1) t 0.48 557.86
Cost for 1750 sqm = a+b+c+d+e
Rate per Sqm = a+b+c+d+e/1750 (Including carriage)
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 82
Amount (Rs.)

9.80
245.00
254.80

739.20
651.00
1569.00

250.00
3209.20

66893.04
306.00
67199.04
8832.88

794.96
80290.88
45.88

1039.82
81330.70
46.47
46.45

e Engineer,
sion HP.PWD.,
Nagar

Page 83
Amount (Rs.)

127.40
2450.00
735.00
3312.40

82788.00
6750.00
7686.00
1867.32
25800.00
11856.00
136747.32

204356.38
131760.00

336116.38
59522.01

5356.98
535698.11
133.92

4103.07
117512.64
657313.80
164.33

164.30

Page 84
Amount (Rs.)

e Engineer,
sion HP.PWD.,
Nagar

264.60
5145.00
1470.00
6879.60

#REF!
#REF!

1482.00
#REF!

25544.55
13270.50

38815.05
8681.98

#REF!
#REF!

1111.75
10592.10
#REF!
#REF!

e Engineer,
sion HP.PWD.,
Nagar

Page 85
Amount (Rs.)

241.50
252.00
7282.00
1986.00
9761.50

3097.60

1630.20
4727.80

37721.95
10919.70

48641.65
8522.68

71653.63
65.10

1641.74
7767.54
81062.91
73.70

e Engineer,
sion HP.PWD.,
Nagar

Page 86
Amount (Rs.)

8.40
331.00
339.40

792.00
651.00
1569.00
3012.00

16796.41
2719.95

22867.77
13.10

731.02
23598.79
13.50

e Engineer,
sion HP.PWD.,
Nagar

Page 87
Amount (Rs.)

178.50
4965.00
662.00
5805.50

1852.50
1852.50
3520.00

7225.00

29743.65
8197.50

37941.15
6881.17

57852.82
52.60

1294.51
5884.50
65031.83
59.10

e Engineer,
sion HP.PWD.,
Nagar

Page 88
Amount (Rs.)

21.00
662.00
683.00

739.20
651.00
1569.00

250.00
3209.20

64036.33
306.00
64342.33
9211.66

77446.19
44.30

2787.00
80233.19
45.80

e Engineer,
sion HP.PWD.,
Nagar

Page 89
Amount (Rs.)

39.20
980.00
1019.20

27596.00
2250.00
2562.00
697.68
8600.00
7410.00
49115.68

118974.60
32790.00

151764.60
25237.44

2271.37
229408.29
45.88

2388.77
28430.40
260227.50
52.05

52.05

Page 90
Amount (Rs.)

e Engineer,
sion HP.PWD.,
Nagar

9.80
245.00
254.80

739.20
651.00
1569.00

2959.20

20540.64
20540.64
2969.33

267.24
26991.21
15.42

337.24
27328.45
15.62
15.60

e Engineer,
sion HP.PWD.,
Nagar

Page 91
Amount (Rs.)

8.40
331.00
339.40

739.20
651.00
1569.00

250.00
3209.20

66893.04
306.00
67199.04
9550.93

80298.57
45.90

2665.16
82963.73
47.41

e Engineer,
sion HP.PWD.,
Nagar

Page 92
Amount (Rs.)

8.40
331.00
339.40

739.20
651.00
1569.00

2959.20

39774.24
39774.24
5814.83

48887.67
27.90

1340.20
50227.87
28.70

e Engineer,
sion HP.PWD.,
Nagar

Page 93
Amount (Rs.)

8.40
331.00
339.40

739.20
651.00
1569.00

2959.20

61236.93
61236.93
8712.30

73247.82
41.90

2665.16
75912.99
43.40

e Engineer,
sion HP.PWD.,
Nagar

Page 94
Amount (Rs.)

8.40
331.00

739.20
651.00
6167.04

61236.93
9333.03

78466.60
44.84

2665.16
81131.76
46.36

e Engineer,
sion HP.PWD.,
Nagar

Page 95
Amount (Rs.)

168.00
5958.00
662.00
6788.00

2100.00
2667.60
4767.60

91356.54
29646.00

121002.54
16569.77

1491.28
150619.19
167.40

1519.31
22921.70

Page 96
Amount (Rs.)

175060.20
194.51

194.50

e Engineer,
sion HP.PWD.,
Nagar

33.60
1324.00
1357.60

2800.00
7410.00
10210.00

153673.20
32790.00

186463.20
24753.85

2227.85
225012.50
45.00

6131.40
20478.00
251621.90
50.32

51.00

Page 97
Amount (Rs.)

e Engineer,
sion HP.PWD.,
Nagar

168.00
4634.00
4802.00

700.00
1482.00
2182.00

58880.00
11058.75

69938.75
9615.34

865.38
87403.47
69.92

1250.06
8125.09
96778.60

Page 98
Amount (Rs.)

77.42

75.80

e Engineer,
sion HP.PWD.,
Nagar

8.40
331.00
339.40

739.20
651.00
1569.00
250.00
3209.20

62461.92
306.00
62767.92
8289.57

746.06
75352.15
43.06

1480.07
76832.22
43.90
43.40

Page 99
Amount (Rs.)

e Engineer,
sion HP.PWD.,
Nagar

168.00
5958.00
662.00
6788.00

2100.00
2667.60
4767.60

91356.54
29646.00

121002.54
16569.77

1491.28

Page 100
Amount (Rs.)

150619.19
167.40

16992.13
22921.70
190533.02
211.70

211.70

e Engineer,
sion HP.PWD.,
Nagar

Page 101
Amount (Rs.)

8.40
331.00
339.40

739.20
651.00
1569.00

2959.20

18576.96
18576.96
2734.45

246.10
24856.11
14.20

0.00
24856.11
14.20
17.20

e Engineer,
sion HP.PWD.,
Nagar

Page 102
Amount (Rs.)

93.34
1633.38
1726.72

0.00
0.00
0.00

0.00
0.00

0.00
215.84

19.43
1961.98
1.57

0.00
0.00
1962.00
1.57

78.00

e Engineer,
sion HP.PWD.,
Nagar

Page 103
Amount (Rs.)

8.40
331.00
339.40

739.20
651.00
1569.00

2959.20

16689.27
16689.27
2498.48

224.86
22711.22
12.98

228.54
22939.76
13.11
13.10

e Engineer,
sion HP.PWD.,
Nagar

Page 104
Amount (Rs.)

278.04
5296.00

1655.00

101376.00
25800.00

6750.00
7686.00
18090.00

1809.00

0.00

2889.90

2889.90

787331.93

179182.35
128885.55
63788.00

Page 105
Amount (Rs.)

166713.46

15004.21
1515425.33
7771.41

13912.43
265480.24
2351.88

281744.54
1444.84
9216.25
9216.30

ve Engineer,
ision HP.PWD.,
r Nagar.

Page 106
Amount (Rs.)

109.20
3310.00

993.00

101376.00

580.80

511.50
25800.00

6750.00
7686.00
3185.73
15828.00

14502.00

259819.54

74033.52
74033.52
37016.76

78191.95

Page 107
Amount (Rs.)

7037.28
710764.79
6934.29

4591.10
137872.93
142464.03
1389.89
8324.18

8324.20

ve Engineer,
ision HP.PWD.,
r Nagar.

Page 108
Amount (Rs.)

9.80
245.00
254.80

739.20
651.00
1569.00

2959.20

20540.64
20540.64
2969.33

267.24
26991.21
15.42

267.77
27258.98
15.58
15.60

e Engineer,
sion HP.PWD.,
Nagar

Page 109
HPSR Chapter-6
Granular Sub-Bases, Bases (Non-Bituminous) and Shoulders
Sr. No. Reference Description Unit Qty. Rate Amount
of MORD
Specificati
on
6.4 1500 (A) Cement Concrete Pavement.
Construction of un-reinforced, plain cement concrete pavement, thickness as per design, over a
prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade),
coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding
25mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher
using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125
micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing),
spreading the concrete with shovles, rakes, compacted using needle, screed and plate vibrators and
finished in continuous operation including provision of contraction and expansion, construction joints,
applying debonding strips, primer, sealant, dowel bars, near approaches to bridge/culvert and
construction joints, admixtures as approved, curing of concrete slabs for 14-days, using curing
compound (where specified) and water finishing to lines and grade as per drawing and technical
specification clause 1501.

Unit = cum
Taking output = 75 cum (172.50 t) (100 x
3.75 x 0.200)
a) Labour
Mate day 7.000 245.00 1715.00
Mason (1st class) day 5.000 386.17 1930.85
Mason (2nd class) day 5.000 294.00 1470.00
Mazdoor (unskilled) day 129.000 245.00 31605.00
Mazdoor (skilled) day 6.000 245.00 1470.00
Surveyor day 2.000 386.17 772.34
Mazdoor (Semi-skilled) day 6.000 245.00 1470.00
Bhisti day 14.000 245.00 3430.00
43863.19
b) Machinery
Concrete mixer 0.28/0.4 cum capacity (6 hour 36.000 350.00 12600.00
mixers) with weight batcher and suitable
capacity calibrated water tank
Needle vibrator hour 9.000 113.00 1017.00
Screed vibrator hour 9.000 98.00 882.00
Plate vibrator hour 9.000 98.00 882.00
Concrete joint cutting machine for intial hour 4.000 1191.00 4764.00
& final cuts
Water tanker 6 kl capacity hour 5.000 500.00 2500.00
Air compressor (1 hour initial + 1 hour hour 2.000 465.00 930.00
final)
23575.00
c) Material
(i) Crushed stone coarse aggregates, cum 67.500 1103.00 74452.50
grading will be as per clause 1501.2.4.1
(table 1500.1) of specifications @ 0.90
cum/cum of concrete
(ii) Sand as per IS:383 and conforming cum 33.750 1101.00 37158.75
to clause 1500.2.4.2 @ 0.45 cum/cum of
concrete
(iii) Cement @ 310 kg/cum of concrete t 26.250 7400.00 194250.00
(iv) Polythene sheet 125 micron sqm 412.500 30.00 12375.00
Bitumen primer @ 200 ml per joint for 23 t 0.005 34992.53 174.96
joints
Bituminous sealant 800 ml per joint for litre 19.000 230.00 4370.00
23 joints
Jute rope 12mm dia including 5 percent m 90.000 12.00 1080.00
wastage

Page 110
HPSR Chapter-6
Granular Sub-Bases, Bases (Non-Bituminous) and Shoulders
Sr. No. Reference Description Unit Qty. Rate Amount
of MORD
Specificati
on
Debonding strips 3.75 m (length) x 10 m 90.000 13.00 1170.00
mm (width) x 5mm (thick) cut-out of
rubber filler board or similar material
including 5 percent wastage
Plasticizer 0.5 per cent by weight of litre 122.000 160.00 19520.00
cement
Curing compound (if used) @ 0.33 liter litre 131.250 65.00 8531.25
per sqm
Water for curing kl 18.000 102.00 1836.00
Joint filler board 20 mm thick as per sqm 3.000 625.00 1875.00
IS:1838 (4 x 3.75 x 0.200 = 3 sqm)
356793.46
d) Formwork @ 3% of (a+b+c) 12726.95
e) Add 12.50% on a+b+c+d 54619.83
(Contractor's profit @ 10% + Over
head Charges @ 2.5%
f) Add on a+b+c+d+e Labour cess @ 4915.78
1.00 %
Cost for 75 Cum = a+b+c+d+e+f 496494.21
Rate per Cum. = a+b+c+d+e/75 6619.92
(Excluding carriage)
Carriage
Crushed stone coarse aggregates Cum 67.50 1088.08 73445.40
Sand cum 33.75 947.68 31984.20
Cement Tonne 26.25 357.38 9381.23
Cost for 75 Cum. = a+b+c+d+e 611305.03
Rate per Sqm = a+b+c+d+e/75 8150.73
(Including carriage)
Say 8150.70

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 111
HPSR Chapter-6
Granular Sub-Bases, Bases (Non-Bituminous) and Shoulders
Sr. No. Reference Description Unit Qty. Rate Amount
of MORD
Specificati
on

6.6 1500 (A) Rectangular Concrete Block Pavement


Manufacturing, laying of cement concrete blocks of size 0.450 m x 0.300 m x 0.15 m of Cement
Concrete (C.C.) M30 garde and spreading 25 mm thick sand under neath and filling joints with sand on
existing W.B.M. base as per Technical Specification Clause 1503.

Unit = sqm
Taking output = 112.5 sqm.
Concrete M30 grade for block, 400 x (0.450 x 0.300 x 0.150) 8.10 cum
Concrete M30 for edge block, 2 x 50 x (0.300 x 0.300 x 0.150) 1.35 cum
9.45 cum
a) Labour for manufacturing the cement concrete block
Mate day 1.70 245.00 416.50
Mazdoor (unskilled) day 41.00 245.00 10045.00
Mason (2nd. class) day 6.00 294.00 1764.00
Bhisti day 1.40 245.00 343.00
12568.50
b) Machinery
Concrete mixer 0.28/0.4 cum capacity (6 hour 6.000 350.00 2100.00
mixers) with weight batcher and suitable
capacity calibrated water tank
Plate vibrator hour 12.000 98.00 1176.00
Water tanker 6 kl capacity hour 2.000 500.00 1000.00
4276.00
c) Material
(i) coarse aggregates, (9.450x0.84) cum 7.940 1276.00 10131.44
(ii) Sand (9.450x0.42) cum 3.970 1101.00 4370.97
(iii) Cement t 3.800 7400.00 28120.00
(iv) Sand as per table 1500.5 cum 1.725 1101.00 1899.23
bed = 60x0.025 = 1.50 cum.
Joints = 1.50x0.15 = 0.225
cum
Cost of water kl 6.000 102.00 612.00
45133.64
d) Formwork @ 3% of (a+b+c) 1859.34
e) Add 12.50% on a+b+c+d (Contractor's profit @ 10% + Over head 7979.69
Charges @ 2.5%
f) Add on a+b+c+d+e Labour cess @ 1.00 % 718.17
Cost for 112.5 sqm = a+b+c+d+e+f 72535.34
Rate per Cum. = a+b+c+d+e/112.5 (Excluding carriage) 644.76
Carriage
coarse aggregates Cum 7.94 936.04 7432.16
Sand cum 5.70 812.65 4628.04
Cement Tonne 3.80 268.94 1021.97
Cost for 112.5 sqm. = a+b+c+d+e 85617.51
Rate per Sqm = a+b+c+d+e/112.5 (Including carriage) 761.04
Say 761.00

Executive Engineer,
B&R Division, HPPWD.,
Joginder Nagar.

Page 112
Chaper-8
Sr. Reference of Description Unit Quantity Rate
No. MORD (Rs.)
Specifications
8.3 1600 & 300 Excavation in soil in hilly Area by mechanical means
including cutting and trimming of side slopes and
disposing of excavated earth with a lift upto 1.50 mtr. and
a lead upto 20 m as per techncial speficiation clauses
1603.1 ( 8.3 (ii) A)

Unit = Cum.
Taking output =260 cum
a) Labour
Mate Day 0.80 245.00
Majdoor (Unskilled) for triming slopes and helping in Day 20.00 245.00
excavation etc.
Total
b) Machinery
Dozer D-50@ 43.28 cum. per hour Hour 6.00 3160.00
Front end loader Hour 6.00 1321.00
Total
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over
head Charges @ 2.5% )
d) Add on a+b+c Labour cess @ 1.00 %
Cost for 260 cum. (a+b+c+d)
Rate per cum
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 113
Chaper-8
Sr. Reference of Description Unit Quantity Rate
No. MORD (Rs.)
Specifications
8.3 1600 & 300 Excavation in hilly Area in ordinary rock not requiring
blasting by mechanical means including cutting and
trimming of side slopes and disposing of cut materials
with a lift upto 1.5mtr. and lead upto 20 m as per techncial
speficiation clauses 1603.2 ( 8.3 (ii)

Unit = Cum.
Taking output =170 cum
a) Labour
Mate Day 0.68 245.00
Majdoor (Unskilled) Day 17.00 245.00
Majdoor for disposing of earth upto 20m Day 9.00 245.00
Total
b) Machinery
Dozer D-50@ 28.32 cum. per hour Hour 6.00 3160.00
Hydrolic Excavator 0.09Cum. Bucket capacity @ 40Cum. Hour 4.25 1843.00
Total
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over
head Charges @ 2.5% )
d) Add on a+b+c Labour cess @ 1.00 %
Cost for 170 cum. (a+b+c+d)
Rate per cum
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 114
Chaper-8
Sr. Reference of Description Unit Quantity Rate
No. MORD (Rs.)
Specifications
8.3 1600 Excavation in hilly area in hard rock requiring blasting by
mechanical means, lift upto 1.5 m and disposal off
excavated rock upto a lead of 20 mtr. as per clause 1603.2
(8.3(iii)A)

Unit = Cum.
Taking output =170 cum
a) Labour
Mate Day 1.36 245.00
Majdoor (Unskilled Day 22.00 245.00
Driller Day 2.00 245.00
Blaster Day 10.00 294.00
Total
b) Machinery
Dozer D-50@ 43.28 cum. per hour (blasting rock) Hour 3.00 3160.00
Hydrolic excator 0.9 cum bucket capacity @ 34 cum per hour Hour 5.00 1843.00
Air compressor 210 cum with two jack hammer @ 6 cum per Hour 28.00 465.00
hour
Total
c) Material
Gelatine 80 per cent Kg 67.00 98.00
Electric detameters @ 1 detometer for 1 gelatine stick of 285 Nos. 235.00 16.00
gm each
Total
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over
head Charges @ 2.5% )
d) Add on a+b+c Labour cess @ 1.00 %
Cost for 170 cum. ( a+b+c+d)
Rate per cum
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 115
Chaper-8
Sr. Reference of Description Unit Quantity Rate
No. MORD (Rs.)
Specifications

8.7 1600, 300 &700 ii) Random rubble dry stone masonry
Construction of random rubble dry stone masonry as per
drawing and technical specification.
Quantity or 6 m formation width = 38 cum
a) Labour
Mate Day 3.80 245.00
Mason (Ist class) Day 38.00 386.17
Majdoor (Unskilled) Day 57.00 245.00
Total
b) Material
Stone for RR masonry Cum 38.00 1170.00
Bond stone Nos. 266.00 30.00
Total
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over
head Charges @ 2.5% )
d) Labour cess @ 1.00 % on (a+b+c)
Cost for 6 m = a+b+c+d
Rate per m = (a+b+c)/6

Cost per Cum. (without carriage)


Carriage
Stone Cum 38.00 631.71
Bond Stone Nos. 6.08 631.71
Cost for 6 m
Rate per m
Cost per Cum. Including carriage
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 116
Chaper-8
Sr. Reference of Description Unit Quantity Rate
No. MORD (Rs.)
Specifications

8.3 1600 & 300 Earth work in Hill road


(i) Excavation in hilly areas in soil by manual means
A) Excavation in soil in hilly area by manual means including
cutting and trimming of side slopes and disposing of
excavated earth with a lift upto 1.50 metres and a lead upto
20.00 metres as per drawing and technical specification
clause 1603.1.
Unit
Taking output = 120cum
a) Labour
Mate day 2.40 245.00
Mazdoor (unskilled) day 60.00 245.00
b) Add 12.50% on a (Contractor's profit @ 10% + Over
head Charges @ 2.5% )
b) Add on a+b Labour cess @ 1.00 %
Cost for 120cum (a+b)
Rate per cum (a+b+c)/120

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 117
Chaper-8
Sr. Reference of Description Unit Quantity Rate
No. MORD (Rs.)
Specifications

8.2 1600 Setting out


Unit = 1Km
The analysis of rate per Km shall account for the following
(1) Construction of reference pillars (burjee) @ 20m on both
sides as per Fig. 1600.1 (b) and @ 8.33 m interval on curves.

(2) Construction of back pillars in front of each reference pillar


as per Fig. 1600.1 (c)
(3) Construction of job pillars as per Fig. 1600.1 (d)
(1) Construction of reference pillar as per Fig. 1600.1 to as
per drawing and technical specification clause 1602.1

(a) Earth work in excavation for foundation as per drawing and cum 1.20 231.60
technical specifications. Rate as per item No. 11.1 of chapter
11
(b) Stone Masonry work in Cement mortar 1:4 in foundation cum 1.20 5615.50
complete asper drawing and technical specifications. Rate as
per item No. 11.6 of chapter 11
(c) Plater with cement mortar 1:4 as per technical sqm 4.00 196.60
specifications. Rate as per item No.12.3 of chaper 12
Add 5% cost of item (a+b+c)
Rate per Km.
Say Rs.

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 118
Chaper-8
Sr. Reference of Description Unit Quantity Rate
No. MORD (Rs.)
Specifications

8.2 1600 Setting out


Unit = 1Km
The analysis of rate per Km shall account for the following
(1) Construction of reference pillars (burjee) @ 20m on both
sides as per Fig. 1600.1 (b) and @ 8.33 m interval on curves.

(2) Construction of back pillars in front of each reference pillar


as per Fig. 1600.1 (c)
(3) Construction of job pillars as per Fig. 1600.1 (d)
(2) Construction of back pillar as per Fig. 1600.1(c) as per
drawing and technical specification cluase 1602.3
(a) Earth work in excavation for foundation as per drawing and cum 3.60 231.60
technical specifications. Rate as per item No. 11.1 of chapter
11
(b) Stone Masonry work in Cement mortar 1:4 in foundation cum 3.60 5615.50
complete asper drawing and technical specifications. Rate as
per item No. 11.6 of chapter 11
(c) Plaster with cement mortar 1:4 as per technical sqm 45.00 196.60
specifications. Rate as per item No.12.4 of chaper 12
Add 5% cost of item (a+b+c)
Rate per Km.
Say Rs.

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 119
Chaper-8
Sr. Reference of Description Unit Quantity Rate
No. MORD (Rs.)
Specifications

8.2 1600 Setting out


Unit = 1Km
The analysis of rate per Km shall account for the following
(1) Construction of reference pillars (burjee) @ 20m on both
sides as per Fig. 1600.1 (b) and @ 8.33 m interval on curves.

(2) Construction of back pillars in front of each reference pillar


as per Fig. 1600.1 (c)
(3) Construction of job pillars as per Fig. 1600.1 (d)
(3) Construction of job Piller as per Fig. 1600.1 (d) and
technical specifation clause 1602.4
(a) Earth work in excavation for foundation as per drawing and cum 0.096 231.60
technical specifications. Rate as per item No. 11.1 of chapter
11
(b) Stone Masonry work in Cement mortar 1:4 in foundation cum 0.096 5615.50
complete asper drawing and technical specifications. Rate as
per item No. 11.6 of chapter 11
(c) Plater with cement mortar 1:4 as per technical sqm 0.96 196.60
specifications. Rate as per item No.12.4 of chaper 12
Add 5% cost of item (a+b+c)
Rate per Km.
Say Rs.

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 120
Amount
(Rs.)

196.00
4900.00

5096.00

18960.00
7926.00
26886.00
3997.75

359.80
36339.55
139.77
139.75

ngineer,
n HP.PWD.,
agar

Page 121
Amount
(Rs.)

166.60
4165.00
2205.00
6536.60

18960.00
7832.75
26792.75
4166.17

374.96
37870.47
222.77
222.75

ngineer,
n HP.PWD.,
agar

Page 122
Amount
(Rs.)

333.20
5390.00
490.00
2940.00
9153.20

9480.00
9215.00
13020.00

31715.00

6566.00
3760.00

10326.00
6399.28

575.93
58169.41
342.17
342.15

ngineer,
n HP.PWD.,
agar

Page 123
Amount
(Rs.)

931.00
14674.46
13965.00
29570.46

44460.00
7980.00
52440.00
10251.31

922.62
93184.39
15530.70
or
2452.22

24004.98
3840.80
121030.16
20171.70
3185.00
3185.00

ngineer,
n HP.PWD.,
agar

Page 124
Amount
(Rs.)

588.00
14700.00
1911.00

171.99
17370.99
144.76

ngineer,
n HP.PWD.,
agar

Page 125
Amount
(Rs.)

277.92

6738.60

786.40

390.15
8193.07
8193.10

ngineer,
n HP.PWD.,
agar

Page 126
Amount
(Rs.)

833.76

20215.80

8847.00

1494.83
31391.39
31391.40

ngineer,
n HP.PWD.,
agar

Page 127
Amount
(Rs.)

22.23

539.09

188.74

37.50
787.56
787.55

ngineer,
n HP.PWD.,
agar

Page 128
Chaper-9
Reference of
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Providing and laying reinforced cement concrete pipe
9.5 1100
NP2 as per design in single row
Providing and laying reinforced cement concrete pipe
NP2 for culvert on 1st class bedding of granular material
in single row including fixing collar with cement mortar
1:2 but excluding excavation protection work back filling
concrete and masonry work in head walls and parapets
clause 1106.
Unit = m
Taking output = 7.5m (3 pipes of 2.5 m length each)
B) 900mm dia
a) Labour
Mate day 0.07 210.00 14.70
Mason 1st class day 0.20 210.00 42.00
Mazdoor (unskilled) day 1.60 331.00 529.60
b) Material
Sand cum 0.04 1101.00 44.04
Cement t 0.03 7400.00 222.00
RCC Pipe NP2 including collar m 7.50 3016.00 22620.00
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over 2934.04
head Charges @ 2.5% )
d) Add on a+b+c Labour cess @ 1.00 % 264.06
Cost for 7.5 m a+b+c 26670.45
Cost per m a+b+c+d/7.5 (Excluding carriage) 3556.06
Carriage
Sand cum 0.04 682.60 27.30
Cement t 0.03 245.85 7.38
RCC Pipe NP2 including collar m 7.50 1448.24 10861.80
Cost for 7.5 m a+b+c+d 37566.93
Cost per m a+b+c/7.5 (Including carriage) 5008.92

Say 4557.75

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 129
Chaper-9
Reference of
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Specifications
Providing and laying reinforced cement concrete pipe
9.5 1100
NP3 as per design in single row
Providing and laying reinforced cement concrete pipe
NP3 for culvert on 1st class bedding of granular material
in single row including fixing collar with cement mortar
1:2 but excluding excavation protection work back filling
concrete and masonry work in head walls and parapets
clause 1106.
Unit = m
Taking output = 7.5m (3 pipes of 2.5 m length each)
C) 900mm dia
a) Labour
Mate day 0.07 245.00 17.15
Mason 1st class day 0.20 386.17 77.23
Mazdoor (unskilled) day 1.60 245.00 392.00
b) Material
Sand cum 0.04 1101.00 44.04
Cement t 0.03 7400.00 222.00
RCC Pipe NP3 including collar m 7.50 4119.00 30892.50
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over 3955.62
head Charges @ 2.5% )
d) Add on a+b+c Labour cess @ 1.00 % 356.01
Cost for 7.5 m a+b+c 35956.54
Cost per m a+b+c+d/7.5 (Excluding carriage) 4794.21
Carriage
Sand cum 0.04 947.68 37.91
Cement t 0.03 357.38 10.72
RCC Pipe NP3 including collar m 7.50 174.74 1310.55
Cost for 7.5 m a+b+c+d 37315.72
Cost per m a+b+c/7.5 (Including carriage) 4975.43

Say 4975.40

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 130
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications
10.5 1700 Painting two coats on New concrete surface
Painting two coats including primer coat, after
filling the surface with synthetic enemal paint in all
shades on new, plastered/concrete surfaces as per
drawing and technical specification clause 1701

Unit - Sqm
taking output = 40 sqm..
a) Labour
Mate Day 0.20 245.00 49.00
Painter (Ist Class) Day 3.00 294.00 882.00
Majdoor (Unskilled) Day 2.00 245.00 490.00
Total 1421.00
b) Material
Cement Primer as per specification litre 3.00 149.00 447.00
Paint conforming to requirement of clause 1701.3.8 litre 6.00 312.00 1872.00
Total 2319.00
c) Add for scaffolding @ 1 percent of labour cost 14.21
where required
d) Add 12.50% on a+b+c (Contractor's profit @ 10% 467.50
+ Over head Charges @ 2.5% )
Add 1 % labour cess 37.54
Cost for 40 sqm = (a+b+c+d) 4221.71
Rate per sqm = (a+b+c+d)/40 105.54
Say 105.50

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 131
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications

10.7 1700 Painting two coats including primer coat with


epoxy paint of approved brand on concrete/steel
surfaces after through cleaning of surface to give
an even shade as per drawing and technical
specification clause-1700

Unit - Sqm.
Taking output = 10 sqm..
a) Labour
Mate Day 0.25 245.00 61.25
Painter (Ist Class) Day 0.60 294.00 176.40
Majdoor (Unskilled) Day 0.40 245.00 98.00
Total 335.65
b) Material
Epoxy primer/red oxide litre 0.60 206.00 123.60
Epoxy paint litre 1.25 374.00 467.50
Total 591.10
c) Add for scaffolding @ 1 percent of labour cost 3.36
where required
d) Add 12.50% on a+b+c (Contractor's profit @ 10% 116.26
+ Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 % 10.46
Cost for 10 sqm = (a+b+c+d) 1056.83
Rate per sqm = (a+b+c+d)/10 105.68
Say 105.70

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 132
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications

10.7 1700 Painting on concrete/Steel surface with epoxy


Providing and applying two coats of apoxy paint
including primer coat of approved brand on steel
surface after through cleaning of surface throughly
to give an even shade as per drawing and technical
specification clause 1701.

Unit - Sqm
taking output = 10 sqm..
a) Labour
Mate Day 0.25 245.00 61.25
Painter (Ist Class) Day 0.60 294.00 176.40
Majdoor (Unskilled) Day 0.40 245.00 98.00
Total 335.65
b) Material
Epoxy primer/Redoxide primer as epr specification litre 0.60 206.00 123.60
Apoxy Paint approved brand litre 1.25 374.00 467.50
Total 591.10
c) Add for scaffolding @ 1 percent of labour cost 3.36
where required
d) Add 12.50% on a+b+c (Contractor's profit @ 10% 116.26
+ Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 % 10.46
Cost for 10 sqm = (a+b+c+d) 1056.83
Rate per sqm = (a+b+c+d)/10 105.70

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 133
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications

1.66mm thick MS sheet strengthen by 25x5MS flat


iron on Logo and middle plate angle iron
25x25x5mm on bottom plate paint with stove
enemelled paint on both side as per MORD
specification.

1 MS Sheet = 1.66mm thick I.e. 1.44Sqm. @ Kg. 18.07 50.00 903.50


12.55Kg/Sqm. = 18.07Kg.
2 25x5mm flat 0.90mtr. Length @ 1Kg/Mtr. = 0.90Kg Kg. 0.90 50.00 45.00
3 Angle iron 25x25x5mm = 1.50Mtr. @ 1.80Kg/Mtr. = Kg. 2.70 50.00 135.00
2.70Kg.
1083.50
Add for welding charges, labour and painting etc. L.S 200.00
Cost for 1.44Sqm. 1283.50
Cost per Sqm 891.30

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 134
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications

10.1 1700 Printing New Leters and Figures of any shade


Printing new letter and figures of any shade with
synthetic enamel paint black or any other approved
colour to give an even shade as per drawings and
technical specification clause 1701
I) Hindi (Matras commas and the like not to be
measured and paid for (Half letters shall be
counted as half only)
Details for 100 letters of 160 mm height, i.e. 1600 cm
Unit=per cm height per letter

a) Labour
Mate Day 0.12 245.00 29.40
Painter (Ist Class) Day 2.00 294.00 588.00
Majdoor (Unskilled) Day 1.00 245.00 245.00
Total 862.40
b) Material
Paint litre 0.70 312.00 218.40
c) Add 12.50% on a+b (Contractor's profit @ 10% + 135.10
Over head Charges @ 2.5% )
d) Add on a+b+c Labour cess @ 1.00 %) 12.16
Cost for 1600 cm = (a+b+c+d) 1228.06
Rate per sqm = (a+b+c+d)/1600 0.77

ii) English and Romani (Hyphens commas and the


like not to be measured and paid for 100 letters of
160mm height I.e. 1600Cm.
Details for 100 letters of 160 mm height, i.e. 1600 cm
Unit=per cm height per letter

a) Labour
Mate Day 0.07 245.00 17.15
Painter (Ist Class) Day 1.25 294.00 367.50
Majdoor (Unskilled) Day 0.50 245.00 122.50
Total 507.15
b) Material
Paint litre 0.50 312.00 156.00
c) Add 12.50% on a+b (Contractor's profit @ 10% + 82.89
Over head Charges @ 2.5% )
d) Add on a+b+c Labour cess @ 1.00 % 7.46
Cost for 1600 cm = (a+b+c+d) 753.50
Rate per sqm = (a+b+c+d)/1600 0.47

Page 135
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar
### 1700.00 Providing and fixing Logo on PMGSY Project (Rate
including Carriage)
Providing and fixing of typical PMGSY informatory
sign board with Logo as per MORD specifications
and drawing. Three MS plates of 1.6 mm thick, top
and middle plate duly welded with MS flat iron 25
mm , 5 mm size on back on edges. The lower plate
will be welded with MS angles iron frame of 25 mm
x 25 mm x 5 mm. The angle iron frame of the lower
most plate and flat iron frame of middle plate will
be welded to 2 No.s 75 mm x 75 mm x of 12 SWG
sheet tubes posts duly embedded in cement
concrete M-15 grade blocks of 450 mm x 450 mm x
600 mmm, 600 mm below ground level. The top
most diamond plate will be welded to middle plate
by 47 mm x 47 mm of 12 SWG steel plate tube . All
MS will be stove enameled on both sides lettering
and printing arrows, borders etc. will be painted
with ready mixed sythetic enamel paint of superior
quality in required shade and colour. All sections of
framed posts and steel tube will be painted with
primer and two coats of epoxy paint as per drawing
clauses 1701 and Annexure 1700.1

Unit = each
Taking output = one typical board
I) Excavation for foundations
As per item No. 11.1 of chapter 11 Cum 0.252 231.60 58.36
ii) Cement concrete M-15 Grade as per item no. 11.4 Cum 0.252 6326.55 1594.29
of chapter 11
iii) Painting on MS steel tubes with primer and two
coats of epoxy paint
2x2.05x0.30=1.23
1x1.10x188=0.21 Sqm. 1.80 105.70 190.26
Total = 1.44 sqm @ 1.25 = 1.80 sqm.
iv) Printing new letters and figures of any shade
with synthetic enamel paint black or any other
approved colour to give an even shade.
Logo border 60x4x5= 1200 per cm height per letter
Figure 60x10=600 per cm height per letter
Middle plate words 28x5=140 per cm height per letter
Bottom plate border 150x2x5=1500 per cm height per
letter
Bottom plate border 60x2x5=600 per cm height per
letter
words 101x2.5=252.5
Words 80x3x240.00

Page 136
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications
Total 4532.5 per cm height per letter as per item No. Per 4532.50 0.77 3490.03
10.1 of chapter 10 cm
a) Labour ( for fixing at site)
Mate Day 0.03 245.00 7.35
Majdoor (Unskilled) Day 0.75 245.00 183.75
Total 191.10
b) Material
2 Nos. MS tubes 75 mm x 75 mm of 12 SWG sheet Kg 63.15 91.00 5746.65
2650 mm long
1 Nos. MS tubes 47 mm x 47 mm of 12 SWG sheet Kg 4.47 91.00 406.77
1100 mm long
Angle iron 50 mm x 50 mm x 5 mm for lugs Kg 2.12 45.00 95.40
1.6 mm thick MS sheet strenghtened by 25 mm x 5 ms Sqm. 1.44 1554.00 2237.76
flat iron on logo and middle plate angle iron 25 mmm x
25 mm x 5 mm on botom plate painting with stove
enameled paint on both side as per MORD
specification
Add 3% cost of MS tube and angle iron towards the 187.46
cost of fabrications, drilling holes, nuts, bolts, etc.
Total 8674.04
c) Machinery
Tractor with trolly Hour 0.24 581.00 139.44
d) Add 12.50% on a+b+c (Contractor's profit @ 10% 1125.57
+ Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 % 101.30
15564.40
Rate for one board = Say 15564.40

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 137
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications

### 1700.00 Providing and fixing Citizen Information Board "A"


on PMGSY Project (Rate Including carriage)
Providing and fixing of typical PMGSY Citizen
informatory board as per MORD specifications and
drawing. two MS sheets of 16SWG of size 900 mm x
750 mm duly welded with M.S. flat iron steel plate
with 75 mm diametre steel tube. All MS will be
stove enameled on both sides lettering and printing
arrows, borders etc. will be painted with ready
mixed sythetic enamel paint of superior quality in
required shade and colour. All sections of framed
posts and steel tube will be painted with primer and
two coats of epoxy paint as per drawing clauses
1701 and annexure. 75 mm diametre steel tube
posts duly embded in cement concrete M-15 grade
blocks of 600mm x 600mm x 750 mm, 750 mm
below ground level.

Unit = each
Taking output = one Citizen Information Board
board
I) Excavation for foundations
As per item No. 11.1 of chapter 11 Cum 0.27 231.60 62.53
ii) Cement concrete M-15 Grade as per item no. 11.4 Cum 0.27 6125.80 1653.97
of chapter 11
iii) Painting on MS steel tubes and MS sheets with
primer and two coats of epoxy paint
M.S. Sheet (Both side) = 1x2x0.45x0.05 = 0.045
Sqm.
= 2x2x0.90x0.75 =2.700
Sqm.
M.S. flat = 14x2x0.05x0.05 = 0.070
Sqm.
M.S. Tube (vertical)= x2x3.14x0.0375x3.20 =1.51
Sqm.
Horizontal =2x2x3.14x0.0375x1.00= 0.47
Sqm.
Total = 4.795 Sqm. 4.795 105.70 506.83
Sqm.
iv) Printing new letters and figures of any shade
with synthetic enamel paint black or any other
approved colour to give an even shade.
Information border 120x4x5= 2400 per cm height per
letter
Figure 120x2 x10=2400 per cm height per letter

Page 138
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications
words 1000x2.5=2500
Words 150x3= 450.00
Total 7750 per cm height per letter as per item No. 10.1 Per 7750.00 0.00 0.00
of chapter 10 cm
a) Labour ( for fixing at site)
Mate Day 0.03 210.00 6.30
Majdoor (Unskilled) Day 0.75 331.00 248.25
Total 254.55
b) Material
2 Nos. MS tubes 75 mm dia (Medium steel pipe) Kg 52.39 91.00 4767.49
Vertical = 2x3.20 = 6.40 Rmt.
Horizontal = 2x1.00 = 2.00 Rmt.
Total = 8.40 Rmt.
Wastage
@ 5% = 0.42 Rmt.
Total = 8.82 Rmt. @ 5.94 Kg./Rmt. = 52.39 Kg.
MS sheet 16 SWG Sqm. 1.44 1451.00 2089.44
Top portion = 1x0.45x0.05 = 0.02 Sqm.
' =
2x0.90x0.75 = 1.35 Sqm. '
Total = 1.37 Sqm.
Wastage @ 5% = 0.07 Sqm.
' Total = 1.44
Angle iron 40 mm x 40 mm x 6 mm for lugs= 2x0.40 = Kg 4.28 45.00 192.60
0.80 Rmt. @ 3.50 Kg/Rmt = 2.80 Kg.
50x 5 mm thick Steel flat for joints=
14x0.05 = 0.70 Rmt. Wastage @ 5 % = 0.04 rmt.
Total flat = 0.74
Rmt. @ 2.00 Kg/Rmt = 1.48 Kg Total =
(2.80+1.48) = 4.28 Kg.
Add 3% cost of MS tube and angle iron towards the 211.49
cost of fabrications, drilling holes, nuts, bolts, etc.
Total 7261.02
c) Machinery
Tractor with trolly Hour 0.24 581.00 139.44
d) Add 12.50% on a+b+c (Contractor's profit @ 10% 956.88
+ Over head Charges @ 2.5% )
e) Add on a+b+c Labour cess @ 1.00 % 86.12
10921.33

Rate for one board = (i+ii+iii+a+b+c+d+e) Say 14341.50

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 139
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications

### 1700.00 Providing and fixing Logo on PMGSY Project (Rate


Including carriage)
Providing and fixing of typical PMGSY informatory
sign board with Logo as per MORD specifications
and drawing. Three MS plates of 1.6 mm thick, top
and middle plate duly welded with MS flat iron 25
mm , 5 mm size on back on edges. The lower plate
will be welded with MS angles iron frame of 25 mm
x 25 mm x 5 mm. The angle iron frame of the lower
most plate and flat iron frame of middle plate will
be welded to 2 No.s 75 mm x 75 mm x of 12 SWG
sheet tubes posts duly embedded in cement
concrete M-15 grade blocks of 450 mm x 450 mm x
600 mmm, 600 mm below ground level. The top
most diamond plate will be welded to middle plate
by 47 mm x 47 mm of 12 SWG steel plate tube . All
MS will be stove enameled on both sides lettering
and printing arrows, borders etc. will be painted
with ready mixed sythetic enamel paint of superior
quality in required shade and colour. All sections of
framed posts and steel tube will be painted with
primer and two coats of epoxy paint as per drawing
clauses 1701 and annexure

Unit = each
Taking output = one typical board
I) Excavation for foundations
As per item No. 11.1 of chapter 11 Cum 0.252 231.60 58.36
ii) Cement concrete M-15 Grade as per item no. 11.4 Cum 0.252 6326.55 1594.29
of chapter 11
iii) Painting on MS steel tubes with primer and two
coats of epoxy paint
2x2.05x0.30=1.23
1x1.10x188=0.21 Sqm. 1.80 105.70 190.26
Total 1.44 @ 1.25 = 1.80 sqm.
iv) Printing new letters and figures of any shade
with synthetic enamel paint black or any other
approved colour to give an even shade.
Logo border 60x4x5= 1200 per cm height per letter
Figure 60x10=600 per cm height per letter
Middle plate words 28x5=140 per cm height per letter
Bottom plate border 150x2x5=1500 per cm height per
letter

Page 140
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications
Bottom plate border 60x2x5=600 per cm height per
letter
words 101x2.5=252.5
Words 80x3x240.00
Total 4532.5 per cm height per letter as per item No. Per 4532.50 0.77 3490.03
10.1 of chapter 10 cm
a) Labour ( for fixing at site)
Mate Day 0.03 245.00 7.35
Majdoor (Unskilled) Day 0.75 245.00 183.75
Total 191.10
b) Material
2 Nos. MS tubes 75 mm x 75 mm of 12 SWG sheet Kg 63.15 91.00 5746.65
2650 mm long
1 Nos. MS tubes 47 mm x 47 mm of 12 SWG sheet Kg 4.47 91.00 406.77
1100 mm long
Angle iron 50 mm x 50 mm x 5 mm for lugs Kg 2.12 45.00 95.40
1.6 mm thick MS sheet strenghtened by 25 mm x 5 ms Sqm. 1.44 1451.00 2089.44
flat iron on logo and middle plate angle iron 25 mmm x
25 mm x 5 mm on botom plate painting with stove
enameled paint on both side as per MORD
specification
Add 3% cost of MS tube and angle iron towards the 250.15
cost of fabrications, drilling holes, nuts, bolts, etc.
Total 8588.41
c) Machinery
Tractor with trolly Hour 0.24 581.00 139.44
d) Add 12.50% on a+b+c (Contractor's profit @ 10% 1114.87
+ Over head Charges @ 2.5% & Labour cess @
1.00 %)
e) Add Labour cess @ 1.00 %) 100.34
Rate for one board = (i+ii+iii+iv+a+b+c+d+e) 15366.76

Say 15366.75

Not Corrected

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 141
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications

### 1700 Kilometer stone (Excluding carriage)


Rain forced cement concrete M - 15 grade kilometer
stone/local stone of standard design as per IRC : 8
fixing in position including painting and printing
etc. as per drawing and technical specification
clauses 1703.

i I) Ordinary kilometer stone


Unit - each
taking output = 14 Nos.
a) M-15 grade of concrete as per item No. 12.8 of Cum 3.77 6609.40 24917.44
chapter 12
b) Steel reinforcement @ 5 kg per sqm. as per item No. Kg 26.32 61.90 1629.21
12.9 of chapter 12
c) Excavation in soil for foundation as per item No. 11.1 Cum 2.77 231.60 641.53
of chapter 11
d) Painting two coats on concrete surface as per item Sqm 11.41 105.54 1204.21
No. 10.5 of chapter 10
e) Lettering on Km/post (average 12 letters of 10 cm per 1680.00 0.77 1293.60
height each) as per item No. 10.1 of chapter 10 cm
high
per
letter
29685.99
Transportation and Fixing
f) Labour
Mate Day 0.32 210.00 67.20
Mason (Ist class) Day 1.00 210.00 210.00
Mazdoor (Unskilled) Day 7.00 331.00 2317.00
2594.20
g) Machinery
50 HP tractor with trolly Hour 6.00 581.00 3486.00
h) Add 12.50% on f+g (Contractor's profit @ 10% + 760.03
Over head Charges @ 2.5% )
i) Add 1 % labour cess 68.40
Cost for 14 Nos. ordinary km stone = 36594.62
a+b+c+d+e+f+g+h+i)
Rate for each = (a+b+c+d+e+f+h)/14 2613.90
say 2613.90

Page 142
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

### 1700 Kilometer stone (Excluding carriage)


Rain forced cement concrete M - 15 grade kilometer
stone/local stone of standard design as per IRC : 8
fixing in position including painting and printing
etc. as per drawing and technical specification
clauses 1703.

iii) 200 m stone (precast)


Unit - each
taking output = 33 Nos.
a) M-15 grade of concrete as per item No. 12.8 of Cum 1.58 6609.40 10442.85
chapter 12
b) Steel reinforcement @ 5 kg per sqm. as per item No. Kg 66.00 61.90 4085.40
12.6 of chapter 12
c) Excavation in soil for foundation as per item No. 11.1 Cum 1.39 231.60 321.92
of chapter 11
d) Painting two coats on concrete surface as per item Sqm 6.27 105.54 661.74
No. 10.5 of chapter 10
e) Lettering on Km/post (average 12 letters of 10 cm per 330.00 0.77 254.10
height each) as per item No. 10.1 of chapter 10 cm
high
per
letter
15766.01
Transportation and Fixing
f) Labour
Mate Day 0.34 210.00 71.40
Mason (Ist class) Day 1.50 210.00 315.00
Mazdoor (Unskilled) Day 7.00 331.00 2317.00
2703.40
g) Machinery
50 HP tractor with trolly Hour 6.00 581.00 3486.00
h) Add 12.50% on f+g (Contractor's profit @ 10% + 773.68
Over head Charges @ 2.5% )
i) Add 1 % labour cess 69.63
Cost for 33 Nos. ordinary km stone = 22729.09
a+b+c+d+e+f+g+h+i)
Rate for each = (a+b+c+d+e+f+h)/33 688.76
Say 688.76

Page 143
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

### 1700 Kilometer stone (Rate including carriage)


Rain forced cement concrete M - 15 grade kilometer
stone/local stone of standard design as per IRC : 8
fixing in position including painting and printing
etc. as per drawing and technical specification
clauses 1703.

i I) Ordinary kilometer stone


Unit - each
taking output = 14 Nos.
a) M-15 grade of concrete as per item No. 12.5 of Cum 3.77 6609.40 24917.44
chapter 12
b) Steel reinforcement @ 5 kg per sqm. as per item No. Kg 26.32 61.90 1629.21
12.6 of chapter 11
c) Excavation in soil for foundation as per item No. 11.1 Cum 2.77 231.60 641.53
of chapter 11
d) Painting two coats on concrete surface as per item Sqm 11.41 105.50 1203.76
No. 10.5 of chapter 10
e) Lettering on Km/post (average 12 letters of 10 cm per 1680.00 0.77 1293.60
height each) as per item No. 10.1 of chapter 10 cm
high
per
letter
29685.53
Transportation and Fixing
f) Labour
Mate Day 0.32 245.00 78.40
Mason (Ist class) Day 1.00 386.17 386.17
Mazdoor (Unskilled) Day 7.00 245.00 1715.00
2179.57
g) Machinery
50 HP tractor with trolly Hour 6.00 581.00 3486.00
h) Add 12.50% on f+g (Contractor's profit @ 10% + 708.20
Over head Charges @ 2.5% )
i) Add Labour cess @ 1.00 %) on f+g+h 63.74
Cost for 14 Nos. ordinary km stone = 36123.04
a+b+c+d+e+f+g+h+i)
Rate for each = (a+b+c+d+e+f+h)/14 2580.22
Say 2580.20
Page 144
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

### 1700 Kilometer stone (Rate including carriage)


Rain forced cement concrete M - 15 grade kilometer
stone/local stone of standard design as per IRC : 8
fixing in position including painting and printing
etc. as per drawing and technical specification
clauses 1703.

iii) 200 m stone (precast)


Unit - each
taking output = 33 Nos.
a) M-15 grade of concrete as per item No. 12.5 of Cum 1.58 6609.40 10442.85
chapter 12
b) Steel reinforcement @ 5 kg per sqm. as per item No. Kg 66.00 61.90 4085.40
12.9 of chapter 12
c) Excavation in soil for foundation as per item No. 11.1 Cum 1.39 231.60 321.92
of chapter 11
d) Painting two coats on concrete surface as per item Sqm 6.27 105.50 661.49
No. 10.5 of chapter 10
e) Lettering on Km/post (average 12 letters of 10 cm per 330.00 0.77 254.10
height each) as per item No. 10.1 of chapter 10 cm
high
per
letter
15765.76
Transportation and Fixing
f) Labour
Mate Day 0.34 245.00 83.30
Mason (Ist class) Day 1.50 386.17 579.26
Mazdoor (Unskilled) Day 7.00 245.00 1715.00
2377.56
g) Machinery
50 HP tractor with trolly Hour 6.00 581.00 3486.00
h) Add 12.50% on f+g (Contractor's profit @ 10% + 732.94
Over head Charges @ 2.5% )
i) Add Labour cess @ 1.00 %) on f+g+h 5870.88
Cost for 33 Nos. ordinary km stone = 28233.14
a+b+c+d+e+f+g+h+i)
Rate for each = (a+b+c+d+e+f+h)/33 855.55

Page 145
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications
Say 855.55

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

10.2 1700, 300, 800 Traffic Signs.


Semi Reflective Traffic Signs.
(III) Providing and fixing semi reflective cautionary, mandatory and informatory sign board as per
IRC:67 made of 1.5 mm thick MS sheet duly stove white colour in front and gray colour on
back with red reflective border of 65 mm width and required letters and figures with reflective
tape engineering grade as per clause 1701.3.9 of MORD for Rural Roads of required shade
and colour supported and welded on 47 mmx47 mm x 12 SWG sheet tube firmly fixed to the
ground by mean of properly designed foundations with M-15 grade cement concrete
450x450x600 mm, 600 mm below ground level as per approved drawing clause 1701.2.2.

Unit = each
Taking output = one traffic sign.
I) Excavation for foundations
As per item No. 11.1 of chapter 11 Cum 0.126 231.60 29.18
ii) Cement concrete M-15 Grade as per item no. 11.4 Cum 0.126 6326.55 797.15
of chapter 11
iii) Painting steel tube posts with primer and two
coats of epoxy paint as per vspecifications.

As per item No. 10.7 of chapter 10 Sqm. 0.46 105.70 48.62


a) Labour ( for fixing at site)
Mate Day 0.01 245.00 2.45
Majdoor (Unskilled) Day 0.25 245.00 61.25
Support of MS sheet tube Total 63.70
b) Material

(i) 47 mm x 47 mm of 12 SWG sheet 3050 mm long Kg 12.40 91.00 1128.40


(ii) Angle iron 50 mm x 50 mm x 6 mm for hold fast Kg 1.06 45.00 47.70
including 5 % wastage
(III)1.5 mm thick MS sheet duly painted with stove
enamelled paint including lettering, sign, border,
message with reflective tape of engineering grade
required size, shade and colour as per Technical
Specifications.
(iii) 600 mm Circular Sqm. 0.283 1554.00 439.78

Page 146
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications
Add 3% cost of MS sheet tube tube 12 SWG and angle 35.28
iron towards the cost of fabrications, drilling holes, nuts,
bolts, etc.
Total 1651.16
c) Machinery
Tractor with trolly Hour 0.08 581.00 46.48

d) Add 12.50% on a+b+c (Contractor's profit @ 10% 220.17


+ Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 % 19.82
Rate for one board = (i+ii+iii+a+b+c+d+e) 2876.28
Say 2876.30

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

10.2 1700, 300, 800 Traffic Signs.


Semi Reflective Traffic Signs.
(II) Providing and fixing semi reflective cautionary, mandatory and informatory sign board as per
IRC:67 made of 1.5 mm thick MS sheet duly stove white colour in front and gray colour on
back with red reflective border of 65 mm width and required letters and figures with reflective
tape engineering grade as per clause 1701.3.9 of MORD for Rural Roads of required shade
and colour supported and welded on 47 mmx47 mm x 12 SWG sheet tube firmly fixed to the
ground by mean of properly designed foundations with M-15 grade cement concrete
450x450x600 mm, 600 mm below ground level as per approved drawing clause 1701.2.2.

Unit = each
Taking output = one traffic sign.
I) Excavation for foundations
As per item No. 11.1 of chapter 11 Cum 0.126 231.60 29.18
ii) Cement concrete M-15 Grade as per item no. 11.4 Cum 0.126 6326.55 797.15
of chapter 11
iii) Painting steel tube posts with primer and two
coats of epoxy paint as per vspecifications.

As per item No. 10.7 of chapter 10 Sqm. 0.46 105.70 48.62


a) Labour ( for fixing at site)
Mate Day 0.01 245.00 2.45
Majdoor (Unskilled) Day 0.25 245.00 61.25
Total 63.70
b) Material
Support of MS sheet tube
(i) 47 mm x 47 mm of 12 SWG sheet 3050 mm long Kg 12.40 91.00 1128.40
(ii) Angle iron 50 mm x 50 mm x 6 mm for hold fast Kg 1.06 45.00 47.70
including 5 % wastage
(III)1.5 mm thick MS sheet duly painted with stove
enamelled paint including lettering, sign, border,
message with reflective tape of engineering grade
required size, shade and colour as per Technical
Specifications.

Page 147
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications
(iii) 900 mm octagon Sqm. 0.672 1554.00 1044.29
Add 3% cost of MS sheet tube tube 12 SWG and angle 35.28
iron towards the cost of fabrications, drilling holes, nuts,
bolts, etc.
Total 2255.67
c) Machinery
Tractor with trolly Hour 0.08 581.00 46.48

d) Add 12.50% on a+b+c (Contractor's profit @ 10% 295.73


+ Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 % 26.62
Rate for one board = (i+ii+iii+a+b+c+d+e) 3563.15
Say 3536.60

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

10.3 1700, 300, 800 Direction and place identification signs up to 0.90 sqm. Size board.
(B) Semi Reflective Traffic Signs. Direction and place
identification signs up to 0.90 sqm. Size board.
Providing and erecting direction and place indentifications of semi reflective sign board as
per IRC:67 made of 2 mm thick MS sheet duly stove enameled paint in white colour in front
and gray colour on back with red reflective border of 70 mm width and required letters and
figures with reflective tape engineering grade as per MORD specification of required shade
and colour. supported and welded on 47 mmx47 mm x 12 SWG square tube of 3050 mm
height duly strengthened by 25 mm x 5 mm MS flat iron on edges on back firmly fixed to the
ground by mean of properly designed foundations with M-15 grade cement concrete
450x450x600 mm, 600 mm below ground level as per approved drawing clause 1701

Unit = each
Taking output = 0.90 Sqm.
I) Excavation for foundations
As per item No. 11.1 of chapter 11 Cum 0.126 231.60 29.18
ii) Cement concrete M-15 Grade as per item no. 11.4 Cum 0.126 6326.55 797.15
of chapter 11
iii) Painting steel tube posts with primer and two
coats of epoxy paint as per vspecifications.

As per item No. 10.7 of chapter 10 Sqm. 0.59 105.70 62.36


a) Labour ( for fixing at site)
Mate Day 0.01 245.00 2.45
Majdoor (Unskilled) Day 0.25 245.00 61.25
Total 63.70
b) Material
Support of MS sheet tube
(i) 47 mm x 47 mm of 12 SWG sheet 3050 mm long Kg 12.40 91.00 1128.40
(ii) Angle iron 50 mm x 50 mm x 6 mm for hold fast Kg 1.06 45.00 47.70
including 5 % wastage

Page 148
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications
(III)1.5 mm thick MS sheet duly painted with stove
enamelled paint including lettering, sign, border,
message with reflective tape of engineering grade
required size, shade and colour as per Technical
Specifications.
(iii) 0.90 sqm size board Sqm. 0.900 1554.00 1398.60
Add 3% cost of MS sheet tube tube 12 SWG and angle 35.28
iron towards the cost of fabrications, drilling holes, nuts,
bolts, etc.
Total 2609.98
c) Machinery
Tractor with trolly Hour 0.08 581.00 46.48

d) Add 12.50% on a+b+c (Contractor's profit @ 10% 340.02


+ Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 % 30.60
Rate for one 0.90 Sqm. = (i+ii+iii+a+b+c+d+e) 3979.47
Rate per square metre 4421.63
Say 4421.60

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar
10.2 1700, 300, 800 Traffic Signs.
Semi Reflective Traffic Signs.
(III) Providing and fixing semi reflective cautionary, mandatory and informatory sign board as per
IRC:67 made of 1.5 mm thick MS sheet duly stove white colour in front and gray colour on
back with red reflective border of 65 mm width and required letters and figures with reflective
tape engineering grade as per clause 1701.3.9 of MORD for Rural Roads of required shade
and colour supported and welded on 47 mmx47 mm x 12 SWG sheet tube firmly fixed to the
ground by mean of properly designed foundations with M-15 grade cement concrete
450x450x600 mm, 600 mm below ground level as per approved drawing clause 1701.2.2.

Unit = each
Taking output = one traffic sign.
I) Excavation for foundations
As per item No. 11.1 of chapter 11 Cum 0.126 231.60 29.18
ii) Cement concrete M-15 Grade as per item no. 11.4 Cum 0.126 6326.55 797.15
of chapter 11
iii) Painting steel tube posts with primer and two
coats of epoxy paint as per vspecifications.

As per item No. 10.7 of chapter 10 Sqm. 0.46 105.70 48.62


a) Labour ( for fixing at site)
Mate Day 0.01 245.00 2.45
Majdoor (Unskilled) Day 0.25 245.00 61.25
Support of MS sheet tube Total 63.70
b) Material

(i) 47 mm x 47 mm of 12 SWG sheet 3050 mm long Kg 12.40 91.00 1128.40


(ii) Angle iron 50 mm x 50 mm x 6 mm for hold fast Kg 1.06 45.00 47.70
including 5 % wastage

Page 149
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications
(III)1.5 mm thick MS sheet duly painted with stove
enamelled paint including lettering, sign, border,
message with reflective tape of engineering grade
required size, shade and colour as per Technical
Specifications.
(iii) 600 mm equilateral & Trangle Sqm. 0.156 1554.00 242.42
Add 3% cost of MS sheet tube tube 12 SWG and angle 35.28
iron towards the cost of fabrications, drilling holes, nuts,
bolts, etc.
Total 1453.81
c) Machinery
Tractor with trolly Hour 0.08 581.00 46.48

d) Add 12.50% on a+b+c (Contractor's profit @ 10% 195.50


+ Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 % 17.59
Rate for one board = (i+ii+iii+a+b+c+d+e) 2652.03
Say 2652.00

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

10.2 1700, 300, 800 Traffic Signs.


Semi Reflective Traffic Signs.
(III) Providing and fixing semi reflective cautionary, mandatory and informatory sign board as per
IRC:67 made of 1.5 mm thick MS sheet duly stove white colour in front and gray colour on
back with red reflective border of 65 mm width and required letters and figures with reflective
tape engineering grade as per clause 1701.3.9 of MORD for Rural Roads of required shade
and colour supported and welded on 47 mmx47 mm x 12 SWG sheet tube firmly fixed to the
ground by mean of properly designed foundations with M-15 grade cement concrete
450x450x600 mm, 600 mm below ground level as per approved drawing clause 1701.2.2.

Unit = each
Taking output = one traffic sign.
I) Excavation for foundations
As per item No. 11.1 of chapter 11 Cum 0.126 231.60 29.18
ii) Cement concrete M-15 Grade as per item no. 11.4 Cum 0.126 6326.55 797.15
of chapter 11
iii) Painting steel tube posts with primer and two
coats of epoxy paint as per vspecifications.

As per item No. 10.7 of chapter 10 Sqm. 0.46 105.70 48.62


a) Labour ( for fixing at site)
Mate Day 0.01 245.00 2.45
Majdoor (Unskilled) Day 0.25 245.00 61.25
Support of MS sheet tube Total 63.70
b) Material

(i) 47 mm x 47 mm of 12 SWG sheet 3050 mm long Kg 12.40 91.00 1128.40

Page 150
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications
(ii) Angle iron 50 mm x 50 mm x 6 mm for hold fast Kg 1.06 45.00 47.70
including 5 % wastage
(III)1.5 mm thick MS sheet duly painted with stove
enamelled paint including lettering, sign, border,
message with reflective tape of engineering grade
required size, shade and colour as per Technical
Specifications.
(iii) 600x450 mm rectangular Sqm. 0.270 1554.00 419.58
Add 3% cost of MS sheet tube tube 12 SWG and angle 35.28
iron towards the cost of fabrications, drilling holes, nuts,
bolts, etc.
Total 1630.96
c) Machinery
Tractor with trolly Hour 0.08 581.00 46.48

d) Add 12.50% on a+b+c (Contractor's profit @ 10% 217.64


+ Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 % 19.59
Rate for one board = (i+ii+iii+a+b+c+d+e) 2853.32
Say 2826.75

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

10.2 1700, 300, 800 Traffic Signs.


Semi Reflective Traffic Signs.
(III) Providing and fixing semi reflective cautionary, mandatory and informatory sign board as per
IRC:67 made of 1.5 mm thick MS sheet duly stove white colour in front and gray colour on
back with red reflective border of 65 mm width and required letters and figures with reflective
tape engineering grade as per clause 1701.3.9 of MORD for Rural Roads of required shade
and colour supported and welded on 47 mmx47 mm x 12 SWG sheet tube firmly fixed to the
ground by mean of properly designed foundations with M-15 grade cement concrete
450x450x600 mm, 600 mm below ground level as per approved drawing clause 1701.2.2.

Unit = each
Taking output = one traffic sign.
I) Excavation for foundations
As per item No. 11.1 of chapter 11 Cum 0.126 220.60 27.80
ii) Cement concrete M-15 Grade as per item no. 11.4 Cum 0.126 5268.70 663.86
of chapter 11
iii) Painting steel tube posts with primer and two
coats of epoxy paint as per vspecifications.

As per item No. 10.7 of chapter 10 Sqm. 0.46 105.68 48.61


a) Labour ( for fixing at site)
Mate Day 0.01 233.33 2.33
Majdoor (Unskilled) Day 0.25 233.33 58.33
Support of MS sheet tube Total 60.67
b) Material

Page 151
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications
(i) 47 mm x 47 mm of 12 SWG sheet 3050 mm long Kg 12.40 91.00 1128.40
(ii) Angle iron 50 mm x 50 mm x 6 mm for hold fast Kg 1.06 45.00 47.70
including 5 % wastage
(III)1.5 mm thick MS sheet duly painted with stove
enamelled paint including lettering, sign, border,
message with reflective tape of engineering grade
required size, shade and colour as per Technical
Specifications.
(iii) 900 mm side octagon Sqm. 0.672 1554.00 1044.29
Add 3% cost of MS sheet tube tube 12 SWG and angle 35.28
iron towards the cost of fabrications, drilling holes, nuts,
bolts, etc.
Total 2255.67
c) Machinery
Tractor with trolly Hour 0.24 581.00 139.44

d) Add 12.50% on a+b+c (Contractor's profit @ 10% 306.97


+ Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 % 27.63
Rate for one board = (i+ii+iii+a+b+c+d+e) 3530.64
Say 3530.60

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

### 1700 Kilometer stone (Including carriage)


Rain forced cement concrete M - 15 grade kilometer
stone/local stone of standard design as per IRC : 8
fixing in position including painting and printing
etc. as per drawing and technical specification
clauses 1703.

i I) 5th. kilometer stone


Unit - each
taking output = 6 Nos.
a) M-15 grade of concrete as per item No. 12.8 of Cum 2.35 6609.40 15532.09
chapter 12
b) Steel reinforcement @ 5 kg per sqm. as per item No. Kg 22.08 61.90 1366.75
12.9 of chapter 12
c) Excavation in soil for foundation as per item No. 11.1 Cum 1.68 231.60 389.09
of chapter 11
d) Painting two coats on concrete surface as per item Sqm 9.85 105.50 1039.18
No. 10.5 of chapter 10
e) Lettering on Km/post (average 12 letters of 10 cm per 1800.00 0.77 1386.00
height each) as per item No. 10.1 of chapter 10 cm
high
per
letter
19713.11
Transportation and Fixing

Page 152
Chapter-10
Sr. Reference of Description Unit Quantit Rate Amount
No. MORD y (Rs.) (Rs.)
Specifications
f) Labour
Mate Day 0.26 245.00 63.70
Mason (Ist class) Day 0.60 386.17 231.70
Mazdoor (Unskilled) Day 6.00 245.00 1470.00
1765.40
g) Machinery
50 HP tractor with trolly Hour 6.00 581.00 3486.00
h) Add 12.50% on f+g (Contractor's profit @ 10% + 656.43
Over head Charges @ 2.5% )
i) Add 1 % labour cess on f+g+h 59.08
Cost for 14 Nos. ordinary km stone = 25680.01
a+b+c+d+e+f+g+h+i)
Rate for each = (a+b+c+d+e+f+h)/6 4280.00
say 4280.00

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 153
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications
11.4 800 & 1200 Providing concrete for plain / reinforced concrete in (For Parapets, & craddle beding,
open foundation complete as per drawing and technical sign board etc)
specifications clauses 802, 803, 1202, 1203.
i) PCC grade M - 15
Nominal mix 1:2½:5 (Hand Mixing)
Unit = cum
a) Material
Cement t 0.275 7400.00
Sand cum 0.48 1101.00
40 mm aggregate cum 0.48 1069.00
20 mm aggregate cum 0.24 1276.00
10 mm aggregate cum 0.08 1281.00
Total
b) Labour
Mate day 0.08 245.00
Mason ( Ist class) day 0.10 386.17
Majdoor (Unskilled) day 1.63 245.00
Bhisti day 0.27 245.00
Total
c) Machinery
Mechanical concrete mixer 0.4/0.28 cum capacity fitted with Hour 0.40 350.00
water measuring device and preferably also with load cell.
d) Form work @ 4% on cost of material labur and
machinery (a+b)
e) Add 12.50% on a +b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
f) Add Labour cess @ 1.00 % on a+b+c+d+e)
Rate per cum = a+b+c+d
Cost Per Cum. Excluding carriage
Carriage
Cement t 0.275 357.38
Sand cum 0.48 947.68
Aggregate cum 0.80 1088.08
Cost Per Cum. including carriage
say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 154
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications
11.4 800 & 1200 Providing concrete for plain / reinforced concrete in
open foundation complete as per drawing and technical
specifications clauses 802, 803, 1202, 1203.
Nominal mix 1:6:12 (Hand Mixing) (Based on item
No.11.4)
Unit = cum
a) Material
Cement t 0.11 7400.00
Sand cum 0.47 1101.00
40 mm aggregate cum 0.65 1069.00
20 mm aggregate cum 0.20 1276.00
Total
b) Labour
Mate day 0.08 210.00
Mason ( Ist class) day 0.10 210.00
Majdoor (Unskilled) day 1.63 331.00
Bhisti day 0.27 252.00
Total
c) Form work @ 4% on cost of material labur and
material (a+b)
d) Add 13.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Rate per cum = a+b+c+d
Cost Per Cum. Excluding carriage
Carriage
Cement t 0.11 245.85
Sand cum 0.47 682.60
Aggregate cum 0.85 784.60
Cost Per Cum. including carriage

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 155
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications
11.4 800 & 1200 Providing concrete for plain / reinforced concrete in
open foundation complete as per drawing and technical
specifications clauses 802, 803, 1202, 1203.
Nominal mix 1:5:10 (Hand Mixing) (Based on item
No.11.4)
Unit = cum
a) Material
Cement t 0.13 7400.00
Sand cum 0.47 1101.00
40 mm aggregate cum 0.65 1069.00
20 mm aggregate cum 0.24 1276.00
Total
b) Labour
Mate day 0.08 210.00
Mason ( Ist class) day 0.10 210.00
Majdoor (Unskilled) day 1.63 331.00
Bhisti day 0.27 252.00
Total
c) Form work @ 4% on cost of material labur and
Material (a+b)
d) Add 13.50% on a+b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Rate per cum = a+b+c+d
Cost Per Cum. Excluding carriage
Carriage
Cement t 0.13 245.85
Sand cum 0.47 682.60
Aggregate cum 0.89 784.60
Cost Per Cum. Including carriage

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 156
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications
11.4 800 & 1200 Providing concrete for plain/reinforced concrete in open,
foundation complete as per drawings and technical
specification clause 802, 803, 1202 & 1203

P.C.C. grade M-10


Nominal mix 1:3:6
a) Material
Cement T 0.250 7400.00
Coarse sand Cum 0.480 1101.00
40 mm aggregate Cum 0.576 1069.00
20 mm aggregate Cum 0.288 1276.00
10 mm aggregate Cum 0.096 1281.00
Total
b) Labour
Mate Day 0.080 210.00
Meson ( Ist class) Day 0.10 210.00
Majdoor (Unskilled) Day 1.63 331.00
Bhisti Day 0.27 252.00
Total
c) Machinery
Mechanical concrete mixer 0.4/0.28 cum capacity fitted with Hour 0.40 350.00
water measuring device and preferably also with load cell.
d) Formwork @ 4% on cost of material, labour and
machinery (a+b+c)
e) Add 12.50% on a+b+c+d (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
f) Add on a+b+c+d+e Labour cess @ 1.00 %
Cost per cum = a+b+c+d+e (Excluding
carriage)
Carriage
Cement T 0.250 272.84
Coarse sand Cum 0.480 825.51
Aggregate Cum 0.960 950.52
Cost per cum including carriage

Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 157
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications

11.1 300 Excavation for Structure


Earthwork in excavation for structures as per drawing
and technical speficiations clause 305.1 including
setting out, construction of shorting the bracing,
removal of stumps and other deleterious material and
disposal upto a lead of 50 mtr dressing of sides and
bottom and back filling in trenches with excavated
suitable material.

I) Ordinary Soil
Upto 3 m depth
Unit = cum
Taking outpur = 10 cum

a) Labour
Mate Day 0.32 245.00
Majdoor (Unskilled Day 8.00 245.00
Total:-

b) Add 12.50% on a (Contractor's profit @ 10% + Over


head Charges @ 2.5% )
b) Add on a+b Labour cess @ 1.00 %
Cost for 10 cum = (a+b)
Rate per cum = (a+b)/10
Say
Upto 3 m to 6 m depth
Unit = cum
Taking outpur = 10 cum

a) Labour
Mate Day 0.32 245.00
Majdoor (Unskilled Day 9.50 245.00
Total:-

b) Add 12.50% on a (Contractor's profit @ 10% + Over


head Charges @ 2.5% )
b) Add on a+b Labour cess @ 1.00 %
Cost for 10 cum = (a+b)
Rate per cum = (a+b)/10
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 158
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications

11.4 800 & 1200 Providing concrete for plain/reinforced concrete in open,
foundation complete as per drawings and technical
specification clause 802, 803, 1202 & 1203
P.C.C. grade M-10
Nominal mix 1:3:6
a) Material
Cement T 0.250 7400.00
Coarse sand Cum 0.480 1101.00
40 mm aggregate Cum 0.576 1069.00
20 mm aggregate Cum 0.288 1276.00
10 mm aggregate Cum 0.096 1281.00
Total
b) Labour
Mate Day 0.080 245.00
Meson ( Ist class) Day 0.10 386.17
Majdoor (Unskilled) Day 1.63 245.00
Bhisti Day 0.27 245.00
Total
c) Machinery
Mechanical concrete mixer 0.4/0.28 cum capacity fitted with Hour 0.40 350.00
water measuring device and preferably also with load cell.
d) Formwork @ 4% on cost of material, labour and
machinery (a+b+c)
e) Add 12.50% on a+b+c+d (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
f) Add on a+b+c+d+e Labour cess @ 1.00 %
Cost per cum = a+b+c+d+e (Excluding
carriage)
Carriage
Cement T 0.250 357.38
Coarse sand Cum 0.480 947.68
Aggregate Cum 0.960 1088.08
Cost per cum including carriage
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 159
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications

11.6 Stone masonry work in cement mortar in foundation


complete as per drawing and technical specifications
clauses 702, 704, 1202 & 1203
I) Coarsed rubble masonry (2nd sort) in 1:3 cement
mortar
a) Material
Stone for C.R. masonry 2nd sort Cum 1.10 1061.00
Through bond stone ( 7 nos x 0.24x0.24x0.39=0.16 cum) Nos. 7.00 30.00
Cement mortar (Rate as in item 11.51) Cum 0.30 5179.95
Total
b) Labour
Mate Day 0.14 210.00
Mason (Ist class) Day 1.50 210.00
Majdoor (Unskilled) Day 2.10 331.00
Bhisti Day 0.08 252.00
Total
c) Add for scafolding @ 5% of cost (a+b)
d) Add 13.50% on a+b+c(Contractor's profit @ 10% +
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost per cum = a+b+c+d (excluding carriage)
Carriage
Stone Cum 1.10 427.05
Bond stone Cum 0.16 427.05
Cement Mortar
Cement Cum 0.15 245.85
Sand Cum 0.31 682.60
Cost per cum = a+b+c+d (Including carriage)

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 160
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications

11.6 700 & 1200 Stone masonry work in cement mortar in foundation
complete as per drawing and technical specifications
clauses 702, 704, 1202, & 1203.
In 1:4 cement mortar
Unit = cum
a) Materials
Stone for C.R. masonry 2nd sort Cum 0.60 1061.00
Through bond stone (7 nos x0.24 x 0.24 x 0.39 = 0.16 cum) Nos. 7.00 30.00
Spalls/blasted rubble Cum 0.50 766.00
Cement mortar (rate as in item 11.51) Cum 0.33 4217.95

b) Labour
Mate Day 0.14 210.00
Mason (Ist class) Day 1.30 210.00
Majdoor (Unskilled) Day 2.00 331.00
Bhisti Day 0.08 252.00

c) Add 13.50% on a+b (Contractor's profit @ 10% + Over


head Charges @ 2.5% & Labour cess @ 1.00 %)
Rate per cum = (a+b+c) excluding carriage
Carriage
Stone for C.R. masonry 2nd sort Cum 0.60 427.05
Through bond stone (7 nos x0.24 x 0.24 x 0.39 = 0.16 cum) Cum 0.16 427.05
Spalls/blasted rubble Cum 0.50 427.05
Cement mortar
Cement 0.125 245.85
Sand 0.35 682.60
Rate per cum including carriage

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 161
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications

11.6 Stone masonry work in cement mortar in foundation


complete as per drawing and technical specifications
clauses 702, 704, 1202, & 1203.
I) Coarsed rubble masonry (2nd Sort) in 1:3 cement
mortar
Unit = cum
a) Materials
Stone for C.R. masonry 2nd sort Cum 0.60 1061.00
Through bond stone (7 nos x0.24 x 0.24 x 0.39 = 0.16 cum) Nos. 7.00 30.00
Spalls/blasted rubble Cum 0.50 766.00
Cement mortar (rate as in item 11.51) Cum 0.33 5179.95

b) Labour
Mate Day 0.14 210.00
Mason (Ist class) Day 1.30 210.00
Majdoor (Unskilled) Day 2.00 331.00
Bhisti Day 0.08 252.00

c) Add 13.50% on a+b (Contractor's profit @ 10% + Over


head Charges @ 2.5% & Labour cess @ 1.00 %)
Rate per cum = a+b+c (Excluding carriage)
Carriage
Stone Cum 0.60 427.05
Bond stone Cum 0.16 427.05
Spalls Cum 0.50 427.05
Cement t 0.17 245.85
Sand Cum 0.35 682.60
Rate per cum including carriage

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 162
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications

11.4 800 & 1200 Providing concrete for plain/reinforced concrete in open, (For Parapets, Toe wall, ctachpits
foundation complete as per drawings and technical & craddle beding)
specification clause 802, 803, 1202 & 1203
(II) P.C.C. grade M-15
Nominal mix 1:2.5:5
a) Material
Cement T 0.275 7400.00
Coarse sand Cum 0.480 1101.00
40 mm aggregate Cum 0.480 1069.00
20 mm aggregate Cum 0.240 1276.00
10 mm aggregate Cum 0.080 1281.00
Total
b) Labour
Mate Day 0.080 245.00
Meson ( Ist class) Day 0.10 386.17
Majdoor (Unskilled) Day 1.63 245.00
Bhisti Day 0.27 245.00
Total
c) Machinery
Concrete mixer 0.4/0.28 cum capacity Hour 0.40 350.00
d) Formwork @ 4% on cost of material, labour and
machinery (a+b+c)
e) Add 12.50% on a +b+c+d (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a +b+c+d+e Labour cess @ 1.00 %
Cost per cum = a+b+c+d+e (Excluding
carriage)
Carriage
Cement T 0.275 272.96
Coarse sand Cum 0.480 819.08
Aggregate Cum 0.800 943.28
Cost per cum including carriage

Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 163
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications

11.4 800 & 1200 Providing concrete for plain/reinforced concrete in open,
foundation complete as per drawings and technical
specification clause 802, 803, 1202 & 1203

(III) P.C.C. grade M-20


(I) Nominal mix 1:2:4 (Hand Mix)
a) Material
Cement T 0.330 3700.00
Coarse sand Cum 0.450 250.00
40 mm aggregate Cum 0.360 300.00
20 mm aggregate Cum 0.360 380.00
10 mm aggregate Cum 0.180 380.00
Total
b) Labour
Mate Day 0.090 81.67
Meson ( Ist class) Day 0.10 130.67
Majdoor (Unskilled) Day 2.00 81.67
Bhisti Day 0.27 81.67
Total
c) Formwork @ 4% on cost of material, labour and
machinery (a+b+c)
d) Add 13.50% on a+b+c(Contractor's profit @ 10% +
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost per cum = a+b+c+d (Excluding carriage)
Add 28.92% contractor premium for similar item No. 28 (rate
as per DNIT = 1939.20, rate as per aggrement No. 2500,
hence percentage above 28.92%)
Total

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 164
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications

11.4 800 & 1200 Providing concrete for plain/reinforced concrete in open,
foundation complete as per drawings and technical
specification clause 802, 803, 1202 & 1203

(III) P.C.C. grade M-20


(I) Nominal mix 1:2:4
a) Material
Cement T 0.330 3700.00
Coarse sand Cum 0.450 250.00
40 mm aggregate Cum 0.360 300.00
20 mm aggregate Cum 0.360 380.00
10 mm aggregate Cum 0.180 380.00
Total
b) Labour
Mate Day 0.080 81.67
Meson ( Ist class) Day 0.10 130.67
Majdoor (Unskilled) Day 1.63 81.67
Bhisti Day 0.27 81.67
Total
c) Machinery
Concrete mixer 0.4/0.28 cum capacity Hour 0.40 150.00
d) Formwork @ 4% on cost of material, labour and
machinery (a+b+c)
e) Add 13.50% on a +b+c(Contractor's profit @ 10% +
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost per cum = a+b+c+d+e (Excluding
carriage)
Carriage
Cement T 0.330 117.93
Coarse sand Cum 0.450 150.99
Aggregate cum 0.900 143.98
Cost Per Cum. including carriage

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 165
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications

11.11 800 & 1200 Providing concrete for plain / reinforced concrete in
open foundation complete as per drawing and technical
specifications clauses 802, 803, 1202, 1203.
Nominal mix 1:4:8 40 mm aggregate (Based on item
No.11.11, 800 & 1200)
Unit = cum
a) Material
Cement t 0.17 7400.00
Sand cum 0.47 1101.00
40 mm aggregate cum 0.65 1069.00
20 mm aggregate cum 0.24 1276.00
Total
b) Labour
Mate day 0.08 245.00
Mason ( Ist class) day 0.10 386.17
Majdoor (Unskilled) day 1.63 245.00
Bhisti day 0.27 245.00
Total
c) Mechanical concrete mixer 0.4/0.28 cum capacity fitted Hour 0.40 350.00
with water measuring device and preferably also with load
cell.
d) Form work @ 4% on cost of material labur and
machinery (a+b+c)
e) Add 12.50% on a +b+c (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
f) Add Labour cess @ 1.00 % on a+b+c+d+e)
Rate per cum = a+b+c+d
Cost Per Cum. Excluding carriage
Carriage
Cement t 0.17 357.38
Sand cum 0.47 947.68
Aggregate cum 0.89 1088.08
Cost Per Cum. including carriage
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 166
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications

11.16 800 & 1200 Construction of parapets with cement concrete 1:5:10 ( 1
Non Schedule cement :5 Sand : 10 graded stone aggregate 40mm nominal
size ) and curing complete including the cost of form work
with steel plates in dressiest as per drawing and HP.PWD
technical specifications.
Detail of cost for one parapet(based on item No. 11.16)
Excluding carriage
a) Excavation in earth work (1x1.85x0.45x0.15 = 0.12) rate cum 0.12 144.76
as per item No. 8.3 (i) (A)
b) Providing laying CC 1:5:10 (1x1.85x0.45x0.60 = 0.50cum)

Less for tapped portion (1x1.85x0.15x0.15 = 0.02)


Total 0.48cum (as per item 11.12) cum 0.48 3715.59
Cost of parapets

Detail of cost for one parapet


Including carriage
a) Excavation in earth work (1x1.85x0.45x0.15 = 0.12) rate cum 0.12 144.76
as per item No. 8.3 (i) (A)
b) Providing laying CC 1:5:10 (1x1.85x0.45x0.60 = 0.50cum)

Less for tapped portion (1x1.85x0.15x0.15 = 0.02)


Total 0.48cum (as per item 11.12) cum 0.48 5175.85
Cost of parapets
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 167
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications

11.12 800 & 1200 Providing and laying concrete for plain / reinforced concrete
in open foundations complete as per drawing and technical
specification clauses 802,803,1202 & 1203. P.C.C. nominal
mix 1:5:10 ( 40mm aggregates)
Unit = cum
a) Material
Aggregate 40mm cum 0.65 1069.00
Aggregate 20mm cum 0.24 1276.00
Course sand cum 0.47 1101.00
Cement t 0.13 7400.00
b) Labour
Mate day 0.08 210.00
Mason 1st class day 0.10 210.00
Mazdoor (Unkilled) day 1.63 331.00
Bhisti day 0.27 252.00
c) Machinery
Mechanical concrete mixer 0.4/0.28cum capacity fitted with hour 0.40 350.00
water measuring device and preferably also with load cell
d) Form work @ 4% on (a+b+c)
e) Add 12.50% on a+b+c+d (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
f) Add Labour cess @ 1.00 % on a+b+c+d+e)
Cost per cum (Excluding carriage)
Carriage
Aggregate 40mm cum 0.65 1059.12
Aggregate 20mm cum 0.24 1059.12
Course sand cum 0.47 921.96
Cement t 0.13 357.26
Cost for per cum including carrriage

Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 168
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications

11.13 800 & 1200 Providing concrete for plain / reinforced concrete in
open foundation complete as per drawing and technical
specifications clauses 802, 803, 1202, 1203.
PCC 1:6:12
Unit = cum
a) Material
Cement t 0.11 7400.00
Sand cum 0.47 1101.00
40 mm aggregate cum 0.65 1069.00
20 mm aggregate cum 0.24 1276.00
Total
b) Labour
Mate day 0.08 245.00
Mason ( Ist class) day 0.10 386.17
Majdoor (Unskilled) day 1.63 245.00
Bhisti day 0.27 245.00
Total
c) Machinery
Concrete mixer hour 0.40 350.00
d) Form work @ 4% on cost of material labur and
material (a+b+c)
e) Add 12.50% on a+b+c+d (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
f) Add on a+b+c+d+e Labour cess @ 1.00 %
Rate per cum = a+b+c+d+e+f
Cost Per Cum. Excluding carriage
Carriage
Cement t 0.11 357.38
Sand cum 0.47 947.68
Aggregate cum 0.89 1088.08
Cost Per Cum. including carriage

Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 169
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications

Base 800 & 1200 Providing concrete for plain / reinforced concrete in
on open foundation complete as per drawing and technical
11.13 specifications clauses 802, 803, 1202, 1203.
PCC 1:5:10 (Based on item No.11.13)
Unit = cum
a) Material
Cement t 0.13 7400.00
Sand cum 0.47 1101.00
40 mm aggregate cum 0.65 1069.00
20 mm aggregate cum 0.24 1276.00
Total
b) Labour
Mate day 0.08 245.00
Mason ( Ist class) day 0.10 386.17
Majdoor (Unskilled) day 1.63 245.00
Bhisti day 0.27 245.00
Total
c) Machinery
Mechanical Concrete mixer 0.4/0.28 cum capacity. hour 0.40 350.00
d) Form work @ 4% on cost of material labur and
material (a+b+c)
e) Add 12.50% on a +b+c+d (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
f) Add on a +b+c+d +e Labour cess @ 1.00 %)
Rate per cum = a+b+c+d+e+f
Cost Per Cum. Excluding carriage
Carriage
Cement t 0.13 357.38
Sand cum 0.47 947.68
Aggregate cum 0.89 1088.08
Cost Per Cum. including carriage

Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 170
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications

11.11 800 & 1200 Providing concrete for plain / reinforced concrete in
open foundation complete as per drawing and technical
specifications clauses 802, 803, 1202, 1203.
PCC 1:4:8 (40 mm Aggregates) (Based on 11.11, 800 &
1200)
Unit = cum
a) Material
Cement t 0.17 7400.00
Sand cum 0.47 1101.00
40 mm aggregate cum 0.65 1069.00
20 mm aggregate cum 0.24 1276.00
Total
b) Labour
Mate day 0.08 210.00
Mason ( Ist class) day 0.10 210.00
Majdoor (Unskilled) day 1.63 331.00
Bhisti day 0.27 252.00
Total
c) Machinery
Concrete mixer hour 0.40 350.00
d) Form work @ 4% on cost of material labur and
material (a+b+c)
e) Add 12.50% on a+b+c+d (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
f) Add on a+b+c+d+e Labour cess @ 1.00 %
Rate per cum = a+b+c+d+e+f
Cost Per Cum. Excluding carriage
Carriage
Cement t 0.17 198.60
Sand cum 0.47 511.24
Aggregate cum 0.89 591.82
Cost Per Cum. including carriage

Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 171
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications
11.16 800 & 1200 Construction of parapets with cement concrete 1:5:10 (one
Non Schedule cement : five sand : ten graded stone aggregate 40mm (forty
millimeter) nominal size) and curing complete including cost
of form work with steel plates as per HP.PWD specification
including carriage of material within all leads and lifts and
other incidental charges as per direction of Engineer-In-
Charge.

Detail of cost for one parapet (based on 11.16 , 800 &


1200
Excluding carriage
a) Excavation in earth work (1x1.85x0.45x0.15 = 0.12) rate cum 0.12 144.76
as per item No. 8.3 (i) (A)
b) Providing laying CC 1:5:10 with 15 % plum
(1x1.85x0.45x0.60 = 0.50cum)
Less for tapped portion (1x1.85x0.15x0.15 = 0.02)
Total 0.48cum (as per item 11.14) cum 0.48 3715.59
Cost of parapets

Detail of cost for one parapet


Including carriage
a) Excavation in earth work (1x1.85x0.45x0.15 = 0.12) rate cum 0.12 144.76
as per item No. 8.3 (i) (A)
b) Providing laying CC 1:5:10 with 15 % plum
(1x1.85x0.45x0.60 = 0.50cum)
Less for tapped portion (1x1.85x0.15x0.15 = 0.02)
Total 0.48cum (as per item 11.14) cum 0.48 5175.85
Cost of parapets
Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 172
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications
11.14 800 & 1200 Providing and laying cement concrete 1:5:10 (one
cement : five sand : ten graded stone aggregate 40mm
nominal size) with 15% plum and curing complete
including cost of form work in retaining walls/breast
walls the size of plums shall be 150mm to 300mm (one
hundred fifty to three hundred millimetre) as per HP.PWD
specifications

Unit = cum
a) Material
Aggregate 40mm cum 0.60 1069.00
Aggregate 20mm cum 0.22 1276.00
Course sand cum 0.47 1101.00
Cement t 0.13 7400.00
Plum cum 0.15 760.00
b) Labour
Mate day 0.08 245.00
Mason 1st class day 0.10 386.17
Mazdoor (Unkilled) day 1.63 245.00
Bhisti day 0.27 245.00
c) Machinery
Mechanical concrete mixer 0.4/0.28cum capacity fitted with hour 0.40 350.00
water measuring device and preferably also with load cell
d) Form work @ 4% on (a+b+c)
e) Add 12.50% on a+b+c+d (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
f) Add on a+b+c+d+e Labour cess @ 1.00 %
Cost per cum (Excluding carriage)
Carriage
Aggregate 40mm cum 0.60 936.04
Aggregate 20mm cum 0.22 936.04
Course sand cum 0.47 812.65
Cement t 0.13 268.94
Plum cum 0.15 499.11
Cost for per cum including carrriage

Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 173
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications
11.4 800 & 1200 Providing concrete for plain/reinforced concrete in open,
foundation complete as per drawings and technical
specification clause 802, 803, 1202 & 1203

(IV) R.C.C. grade M-20


(I) Nominal mix 1:2:4
a) Material
Cement T 0.350 7400.00
Coarse sand Cum 0.450 1101.00
20 mm aggregate Cum 0.540 1276.00
10 mm aggregate Cum 0.360 1281.00
Total
b) Labour
Mate Day 0.080 210.00
Meson ( Ist class) Day 0.12 210.00
Majdoor (Unskilled) Day 1.73 331.00
Bhisti Day 0.27 252.00
Total
c) Machinery
Concrete mixer 0.4/0.28 cum capacity Hour 0.40 350.00
d) Formwork @ 4% on cost of material, labour and
machinery (a+b+c)
e) Add 12.50% on a +b+c +d (Contractor's profit @ 10% +
Over head Charges @ 2.5% )
e) Add on a+b+c+d+eLabour cess @ 1.00 %)
Cost per cum = a+b+c+d+e (Excluding
carriage)
Carriage
Cement T 0.350 245.85
Coarse sand Cum 0.450 682.60
Aggregate cum 0.900 784.60
Cost Per Cum. including carriage

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 174
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications
11.7 1000 & 1200 Supplying, fitting and placing HYSD bar
reinforcement in foundation complete as per
drawings and technical specifications Clauses
1000 and 1202
Unit = t
a) Material
HYSD bars including 5 per cent for overlaps and t 1.05 49,000.0
wastage
Binding wire kg 6.00 70.00
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.40 210.00
Blacksmith day 2.00 331.00
Mazdoor (Unskilled) day 6.00 331.00

c) Contractor’s profit & Overheads @ 12.50% on


(a+b)
d) Labour Cess @ 1% on (a+b+c)
Rate per t = a+b+c+d

Carriage by Mech Tpt.


Steel t 1.05 262.25

Rate per tonne

Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 175
Chaper-11
Sr. Reference of Description Unit Quantit Rate (Rs.)
No. MORD y
Specifications
11.6 700 & 1200 Stone masonry work in cement mortar in foundation
complete as per drawing and technical specifications
clauses 702, 704, 1202, & 1203.
In 1:4 cement mortar
Unit = cum
a) Materials
Stone for C.R. masonry 1st sort Cum 1.10 1368.00
Through bond stone (7 nos x0.24 x 0.24 x 0.39 = 0.16 cum) Nos. 7.00 30.00
Cement mortar (rate as in item 11.5 (ii)) Cum 0.30 4217.95

b) Labour
Mate Day 0.14 245.00
Mason (Ist class) Day 1.50 386.17
Majdoor (Unskilled) Day 2.10 245.00
Bhisti Day 0.08 245.00

c) Add 12.50% on a+b (Contractor's profit @ 10% + Over


head Charges @ 2.5% )
c) Add Labour cess @ 1.00 % on a+b+c
Rate per cum = (a+b+c) excluding carriage
Carriage
Stone for C.R. masonry 2nd sort Cum 1.10 508.11
Through bond stone (7 nos x0.24 x 0.24 x 0.39 = 0.16 cum) Cum 0.16 508.11
Cement mortar
Cement 0.114 272.96
Sand 0.31 819.08
Rate per cum including carriage

Say

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 176
Amount
(Rs.)

ts, & craddle beding,


n board etc)

2035.00
528.48
513.12
306.24
102.48
3485.32

19.60
38.62
399.35
66.15
523.72

140.00

165.96

539.37

48.54
4902.92
4902.90

98.28
454.89
870.46
6326.55
6326.55

gineer,
HP.PWD.,
ar

Page 177
Amount
(Rs.)

814.00
517.47
694.85
255.20
2281.52

16.80
21.00
539.53
68.04
645.37
117.08

410.94

3454.90
3454.90

27.04
320.82
666.91
4469.70

gineer,
HP.PWD.,
ar

Page 178
Amount
(Rs.)

962.00
517.47
694.85
306.24
2480.56

16.80
21.00
539.53
68.04
645.37
125.04

438.88

3689.85
3689.80

31.96
320.82
698.29
4740.90

gineer,
HP.PWD.,
ar

Page 179
Amount
(Rs.)

1850.00
528.48
615.74
367.49
122.98
3484.69

16.80
21.00
539.53
68.04
645.37

140.00

170.80

555.11

49.96
5045.93

68.21
396.24
912.50
6422.88

6422.90

gineer,
HP.PWD.,
ar

Page 180
Amount
(Rs.)

78.40
1960.00
2038.40

254.80

22.93
2316.13
231.61
231.60

78.40
2327.50
2405.90

300.74

27.07
2733.70
273.37
273.40

gineer,
HP.PWD.,
ar

Page 181
Amount
(Rs.)

1850.00
528.48
615.74
367.49
122.98
3484.69

19.60
38.62
399.35
66.15
523.72

140.00

165.94

539.29

48.54
4902.17

89.35
454.89
1044.56
6490.96
6490.95

gineer,
HP.PWD.,
ar

Page 182
Amount
(Rs.)

1167.10
210.00
1553.99
2931.09

29.40
315.00
695.10
20.16
1059.66
199.54
565.69

4756.00

469.76
68.33

36.88
211.61
5542.60

gineer,
HP.PWD.,
ar.

Page 183
Amount
(Rs.)

636.60
210.00
383.00
1391.92
2621.52

29.40
273.00
662.00
20.16
984.56
486.82

4092.90

256.23
68.33
213.53

30.73
238.91
4900.60

gineer,
HP.PWD.,
ar.

Page 184
Amount
(Rs.)

636.60
210.00
383.00
1709.38
2938.98

29.40
273.00
662.00
20.16
984.56
529.68

4453.20

256.23
68.33
213.53
41.79
238.91
5272.00

gineer,
HP.PWD.,
ar.

Page 185
Amount
(Rs.)

s, Toe wall, ctachpits


addle beding)

2035.00
528.48
513.12
306.24
102.48
3485.32

19.60
38.62
399.35
66.15
523.72

140.00
165.96

539.37

48.54
4902.92

75.06
393.16
754.62
6125.77

6125.80

gineer,
HP.PWD.,
ar

Page 186
Amount
(Rs.)

1221.00
112.50
108.00
136.80
68.40
1646.70

7.35
13.07
163.34
22.05
205.81
74.10

260.09

2186.70
632.39

2819.10

gineer,
HP.PWD.,
ar

Page 187
Amount
(Rs.)

1221.00
112.50
108.00
136.80
68.40
1646.70

6.53
13.07
133.12
22.05
174.77

60.00
75.26

264.16

2220.90

38.92
67.95
129.58
2457.30

gineer,
HP.PWD.,
ar

Page 188
Amount
(Rs.)

1258.00
517.47
694.85
306.24
2776.56

19.60
38.62
399.35
66.15
523.72
140.00

137.61

447.24

40.25
4065.38
4065.40

60.75
445.41
968.39
5539.93
5539.90

gineer,
HP.PWD.,
ar

Page 189
Amount
(Rs.)

17.37

1783.48
1800.85

17.37

2484.41
2501.78
2501.80

gineer,
HP.PWD.,
ar

Page 190
Amount
(Rs.)

694.85
306.24
517.47
962.00

16.80
21.00
539.53
68.04

140.00

130.64
424.57

38.21
3859.35

688.43
254.19
433.32
46.44
5281.73

5281.70

gineer,
HP.PWD.,
ar

Page 191
Amount
(Rs.)

814.00
517.47
694.85
306.24
2332.56

19.60
38.62
399.35
66.15
523.72

140.00
119.85

389.52

35.06
3540.70
3540.70

39.31
445.41
968.39
4993.81
.
4993.80

gineer,
HP.PWD.,
ar

Page 192
Amount
(Rs.)

962.00
517.47
694.85
306.24
2480.56

19.60
38.62
399.35
66.15
523.72

140.00
125.77

408.76

36.79
3715.59
3715.59

46.46
445.41
968.39
5175.85

5175.85

gineer,
HP.PWD.,
ar

Page 193
Amount
(Rs.)

1258.00
517.47
694.85
306.24
2776.56

16.80
21.00
539.53
68.04
645.37

140.00
142.48

463.05

41.67
4209.13
4209.13

33.76
240.28
526.72
5009.89

4312.80

gineer,
HP.PWD.,
ar

Page 194
Amount
(Rs.)

17.37

1783.48
1800.85

17.37

2484.41
2501.78
2501.80

gineer,
HP.PWD.,
ar

Page 195
Amount
(Rs.)

641.40
280.72
517.47
962.00
114.00

19.60
38.62
399.35
66.15

140.00

127.17
413.31

37.20
3756.99

561.62
205.93
381.95
34.96
74.87
5016.32

5016.30

gineer,
HP.PWD.,
ar

Page 196
Amount
(Rs.)

2590.00
495.45
689.04
461.16
4235.65

16.80
25.20
572.63
68.04
682.67

140.00
202.33

657.58

59.18
5977.42

86.05
307.17
706.14
7076.80

gineer,
HP.PWD.,
ar

Page 197
Amount
(Rs.)

50,400.0

420.00

84.00
518.00
1,260.00
52,682.00
6585.25

592.67
59859.92

275.36

60135.28

60135.30

gineer,
HP.PWD.,
ar

Page 198
Amount
(Rs.)

1504.80
210.00
1265.39
2980.19

34.30
579.26
514.50
19.60
1147.66
515.98

46.44
4690.26

558.92
81.30

31.12
253.91
5615.51

5615.50

gineer,
HP.PWD.,
ar.

Page 199
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.4 700 Stone masonry in cement mortar for substructure


complete as per drawing and technical specification
clause 702, 704, 1202 & 1204.
1. Coursed rubble masonry (1st sort)
(III) In cement mortar 1:5
Unit: Cum
a) Material
Stone for CR Masonry 1st sort cum. 0.60 1061.00 636.60
Through and bond stone Nos. 7.00 30.00 210.00
(7Nos. X 0.24m X 0.24m X 0.39m = 0.16Cum.
Spalls/blasted rubbles cum. 0.50 766.00 383.00
Cement mortar (Rate same as in item 12.1 (III) cum. 0.33 3699.95 1220.98
Total 2450.58
b) Labour
Mate day 0.14 210.00 29.40
Mason 1st Class day 1.30 210.00 273.00
Mazdoor (Unskilled) day 2.00 331.00 662.00
Bhisti day 0.08 252.00 20.16
Total 984.56
c) Add for scaffolding @ 5% on (a+b) 171.76
d) Add 13.50% on a (Contractor's profit @ 10% + Over 486.93
head Charges @ 2.5% & Labour cess @ 1.00 %)

Rate per Cum excluding carriage 4093.80


Carriage
Stone for CR Masonry 1st sort cum. 0.60 427.05 256.23
Through and bond stone cum. 0.16 427.05 68.33
(7Nos. X 0.24m X 0.24m X 0.39m = 0.16Cum.
Spalls/blasted rubbles cum. 0.50 427.05 213.53
Cement Mortar
Cement cum. 0.10 245.85 24.59
Sand cum. 0.35 682.60 238.91
Rate per Cum including carriage 4895.40

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 200
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.1 600 Sub Analysis


Cement mortar 1:5
a) Material
Cement t 0.31 7400.00 2294.00
Sand cum. 1.05 1101.00 1156.05
b) Labour
Mate day 0.04 245.00 9.80
Mazdoor (Unskilled) day 0.90 245.00 220.50
Bhisti day 0.08 245.00 19.60
Total Material and Labour (a+b) 3699.95

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 201
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.14 1200 Back filling behind abutment, wing wall and return
wall complete as per drawing and techinical
sepcification clause 1204.3.8
Unit = Cum.
Taking output = 10 Cum.
a) Mterial
Granular Material cum 12.00 376.00 4512.00
b) Labour
Mate day 0.28 245.00 68.60
Mazdoor (Unskilled) day 10.00 245.00 2450.00
Bhishti day 0.40 245.00 98.00
Total 2616.60
c) Add 12.50% on a+b (Contractor's profit @ 10% + 891.08
Over head Charges @ 2.5% )
d) Add on a+b+c Labour cess @ 1.00 % 80.20
Cost of 10 Cum (a+b+c+d) 8099.87
Rate per Cum. Excluding carriage 809.99
Carriage
Granular Material cum 12.00 98.92 1187.04
Cost of 10 Cum 1187.04
Cost per cum 118.70
Cost per cum including carriage 928.69
Say 928.70

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 202
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.4 700 Stone masonry work in cement mortar in foundation


complete as per drawing and technical specifications
clauses 702, 704, 1202, & 1204.
In 1:4 cement mortar
Unit = cum
a) Materials
Stone for C.R. masonry 1st sort Cum 1.10 1061.00 1167.10
Through bond stone (7 nos x0.24 x 0.24 x 0.39 = 0.16 Nos. 7.00 30.00 210.00
cum)
Cement mortar (rate as in item 11.5(ii) Cum 0.30 4217.95 1265.39
Total 2642.49
b) Labour
Mate Day 0.14 210.00 29.40
Mason (Ist class) Day 1.50 210.00 315.00
Majdoor (Unskilled) Day 2.10 331.00 695.10
Bhisti Day 0.08 252.00 20.16
Total 1059.66
c) Add 13.50% on a+b (Contractor's profit @ 10% + 499.79
Over head Charges @ 2.5% & Labour cess @ 1.00 %)

Rate per cum = (a+b+c) 4201.93


Cost per Cum excluding carriage 4201.90
Carriage
Stone Cum 1.10 427.05 469.76
Bond stone Cum 0.16 427.05 68.33
Cement Mortar
Cement Cum 0.11 245.85 27.04
Sand Cum 0.31 682.60 211.61
Cost per Cum including carriage 4978.60

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 203
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

Cement mortar 1:3 ( 1 cement : sand)


a) Material
Cement T 0.51 7400.00 3774.00
Sand cum Cum 1.05 1101.00 1156.05
4930.05
b) Labour
Mate Day 0.04 245.00 9.80
Majdoor (Unskilled) Day 0.90 245.00 220.50
Bhisti Day 0.08 245.00 19.60
249.90
Cost Per Cum 5179.95

Cement mortar 1:4 ( 1 cement : 4 sand)


a) Material
Cement T 0.38 7400.00 2812.00
Sand cum Cum 1.05 1101.00 1156.05
3968.05
b) Labour
Mate Day 0.04 245.00 9.80
Majdoor (Unskilled) Day 0.90 245.00 220.50
Bhisti Day 0.08 245.00 19.60
249.90
Cost Per Cum 4217.95

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 204
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.7 700 Stone masonry in cement mortar for substructure


(III) (iv) complete as per drawing and techinical specification
clause 702, 704, 1202 & 1204.
(iii) Random Rubble Masonry in cement mortar 1:6
Unit = Cum
a) Material
Stone for RR Masonry cum 1.00 1170.00 1170.00
Through and bound stone Nos. 7.00 30.00 210.00
Cement mortar 1:6 (as per AR) cum 0.33 3255.95 1074.46
Total 2454.46
b) Labour
Mate day 0.12 245.00 29.40
Mason 1st class day 1.20 386.17 463.40
Mazdoor (Unskilled) day 1.80 245.00 441.00
Bhisti day 0.08 245.00 19.60
Total 953.40
c) Add for saffolding @ 5% of cost of material and 170.39
labour
d) Add 12.50% on a+b+c (Contractor's profit @ 10% + 447.28
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 % 40.26
Rate per cum = a+b+c+d+e 4065.80
Cost Per Cum. Excluding carriage 4065.80
Carriage
Stone for RR Masonry cum 1.00 697.11 697.11
Through and bond stone cum 0.16 697.11 111.54
Cement Mortar
Cement T 0.08 357.38 28.59
Sand cum 0.35 947.68 331.69
Cost Per Cum. including carriage 5234.73

Say 5234.70

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 205
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

Sub Analysis Cement Mortar 1:6


Unit = Cum.
a) Material
Cement t 0.25 7400.00 1850.00
Sand. cum. 1.05 1101.00 1156.05
b) Labour
Mate day 0.04 245.00 9.80
Mazdoor (Unskilled) day 0.90 245.00 220.50
Bhisti day 0.08 245.00 19.60
Total of Material and Labour (a+b) 3255.95

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 206
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.6 700 Construction of dry rubble masonry for retaining


walls, breast wals, revetment walls and parapets etc.
for sub structure and super structure complete as per
drawing and technical specification clauses 704.6 and
1302.5.
Unit = Cum
a) Material
Stone for RR Masonry cum 1.00 1170.00 1170.00
Through and bound stone Nos. 7.00 30.00 210.00
Total 1380.00
b) Labour
Mate day 0.12 245.00 29.40
Mason 1st class day 1.20 386.17 463.40
Mazdoor (Unskilled) day 1.80 245.00 441.00
Bhisti day 0.08 245.00 19.60
Total 953.40
c) Add for saffolding @ 5% of cost of material and 116.67
labour (a+b)
d) Add 12.50% on a+b+c (Contractor's profit @ 10% + 306.26
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 % 27.56
Rate per cum = a+b+c+d+e 2783.89
Cost Per Cum. Excluding carriage 2783.89
Carriage
Stone for RR Masonry cum 1.00 697.11 697.11
Through and bond stone cum 0.16 697.11 111.54
Cost Per Cum. including carriage 3592.54

Say 3592.50

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 207
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.4 700 Stone masonry work in cement mortar in foundation


complete as per drawing and technical specifications
clauses 702, 704, 1202, & 1204.
In 1:3 cement mortar
Unit = cum
a) Materials
Stone for C.R. masonry 1st sort Cum 1.10 1061.00 1167.10
Through bond stone (7 nos x0.24 x 0.24 x 0.39 = 0.16 Nos. 7.00 30.00 210.00
cum)
Cement mortar (rate as in item 11.5(ii) Cum 0.30 5179.95 1553.99
Total 2931.09
b) Labour
Mate Day 0.14 210.00 29.40
Mason (Ist class) Day 1.50 210.00 315.00
Majdoor (Unskilled) Day 2.10 331.00 695.10
Bhisti Day 0.08 252.00 20.16
Total 1059.66
d) Add 13.50% on a+b (Contractor's profit @ 10% + 538.75
Over head Charges @ 2.5% & Labour cess @ 1.00 %)

Rate per cum = (a+b+c) 4529.50


Cost per Cum excluding carriage 4529.50
Carriage
Cement Mortar
Cement t 0.15 245.85 36.88
Sand cum 0.31 682.60 211.61
Stone cum 1.10 427.05 469.76
Bond stone cum 0.16 427.05 68.33
Cost per Cum including carriage 5316.10

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 208
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.13 600 Providing weep holes in brick masonry/stone


masorny, plain/reinficed concrete abutment, wing
walls, return walls with 100mm dia PVC Pipe
extending through the full width of structures with
slope of 1(V):20 (H) towards drawing face complete as
per drawing and technical specifications clauses 614,
709, 1204, 3.7.

Unit : Nos.
Taking output 30 Nos.
a) Materials
PVC Pipe 100mm dia including wastate @ 5% average m 31.50 260.00 8190.00
length of weep holes is taken as 1mtr. For the purpose of
estimating
Cement morat 1:3 (For rate refer to item No.11.51) cum. 0.05 5179.95 259.00
Total 8449.00
b) Labour
Mate day 0.03 245.00 7.35
Mason 1st Class day 0.50 386.17 193.09
Mazdoor (Unskilled) day 0.25 245.00 61.25
Total 261.69
c) Add 12.50% on a+b (Contractor's profit @ 10% + 1088.84
Over head Charges @ 2.5% )
d) Add on a+b +c Labour cess @ 1.00 % 98.00
Cost for 30Nos. (a+b+c+d) 9897.51
Cost per Nos. 329.92

Say 329.90

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 209
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.5 800 Plain / reinforced cement concrete in sub structure


complete as per drawing and technical specifications
clauses 802, 804, 805, 806, 807, 1202, 1204

P.C.C. grade M-20


Nominal mix (1:2:4)
a) Material
Cement T 0.33 7400.00 2442.00
Sand Cum 0.45 1101.00 495.45
40 mm aggregate Cum 0.36 1069.00 384.84
20 mm aggregate Cum 0.36 1276.00 459.36
10 mm aggregate Cum 0.18 1281.00 230.58
4012.23
b) Labour
Mate Day 0.08 210.00 16.80
Mason ( Ist class) Day 0.10 210.00 21.00
Majdoor (Unskilled) Day 1.63 331.00 539.53
Bhisti Day 0.27 252.00 68.04
645.37
c) Machinery
Concrete mixture 0.4/0.28 cum capacity Hour 0.40 350.00 140.00
d) Form work @ 10% on (a+b+c) 479.76
e) Add 12.50% on a +b+c+d (Contractor's profit @ 10% 659.67
+ Over head Charges @ 2.5% )
e) Add Labour cess @ 1.00 %) 59.37
Rate per cum = a+b+c+d+e+f (excluding 5996.40
carriage)
Carriage
Cement T 0.33 245.85 81.13
Sand Cum 0.45 682.60 307.17
Aggregate Cum 0.90 784.60 706.14
Rate per cum = a+b+c+d+e+f (Including 7090.84
carriage)
Say 6152.60

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 210
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.12 1200 Supplying, fitting and fixing in position to line and


level elastromric bearing confirming to IRC:83 (Part-II
section-IX) complete including all accessories as per
drawing and technical specificaion clause 1207.1.

Unit:- Cubic Centimetre


Considering an elastromric bearing of size
500X400X96mm for this analysis
Overall volume = 19200Cu. Cm.
Volume of 6Nos. 488X388X4mm size rainforcing steel
plants = 4545Cu. Cm.
Hence volume of elastomer = 14655Cu. Cm.
a) Labour
Mate day 0.06 210.00 12.60
Mazdoor (Unskilled) day 1.00 331.00 331.00
Mazdoor (Skilled) day 0.50 331.00 165.50
Total 509.10
b) Material
Elastromeric Bearing assembly consisting of 7intral Nos 1.00 6000.00 6000.00
rainorcing steel laminates by the process of vulcanisation ,
complete with all components as drawing and techanical
specification.
Add for anchorage bolts if required and consumables @ 60.00
1%
d) Add 13.50% on a (Contractor's profit @ 10% + Over 886.83
head Charges @ 2.5% & Labour cess @ 1.00 %)

Cost of 19200Cu. Cm. 7455.93


Rate per Cu. Cm. 0.39

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 211
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.11 1200 Providing and laying filter media with granular


crushed aggregate as per specification to a thickness
of not less than 600mm with smaller size towards the
soil and bigger size towards the wall and providing
over the entire surface behind abutment, wing walls,
return wall to the full height, compacted to firm
condition complete as per drawing and technical
specification clause 1204.3.8

Unit:- Cum
Taking output:- 10 Cum.
a) Material
Filter media as per specification cum 12.00 751.00 9012.00
b) Labour
Mate day 0.40 245.00 98.00
Mazdoor (unskilled) day 9.00 245.00 2205.00
Mazdoor (skilled) day 1.00 245.00 245.00
Bhisti day 0.50 245.00 122.50
c) Add 12.50% on a+b (Contractor's profit @ 10% + 1460.31
Over head Charges @ 2.5% )
d) Add on a+b+c Labour cess @ 1.00 % 131.43
Cost of 10 Cum. 13274.24
Rate per Cum. (excluding carriage) 1327.40
Carriage
Filter media as per specification cum 12.00 499.11 5989.32
Cost of 10 Cum. 19263.56
Rate per Cum. (including carriage) 1926.36

Say 1926.35

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 212
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.4 700 Stone masonry work in cement mortar in foundation


complete as per drawing and technical specifications
clauses 702, 704, 1202, & 1204.
In 1:6 cement mortar
Unit = cum
a) Materials
Stone for C.R. masonry 1st sort Cum 1.10 1061.00 1167.10
Through bond stone (7 nos x0.24 x 0.24 x 0.39 = 0.16 Nos. 7.00 30.00 210.00
cum)
Cement mortar (rate as in item 11.5(ii) Cum 0.30 3255.95 976.79
Total 2353.89
b) Labour
Mate Day 0.14 210.00 29.40
Mason (Ist class) Day 1.50 210.00 315.00
Majdoor (Unskilled) Day 2.10 331.00 695.10
Bhisti Day 0.08 252.00 20.16
Total 1059.66
c) Add 13.50% on a+b (Contractor's profit @ 10% + 460.83
Over head Charges @ 2.5% & Labour cess @ 1.00 %)

Rate per cum = (a+b+c) 3874.37


Cost per Cum excluding carriage 3874.40
Carriage
Cement Mortar
Cement t 0.075 245.85 18.44
Sand cum 0.31 682.60 211.61
Stone cum 1.10 427.05 469.76
Bond stone cum 0.16 427.05 68.33
Cost per Cum including carriage 4642.53

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 213
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.4 700 Stone masonry work in cement mortar in foundation


complete as per drawing and technical specifications
clauses 702, 704, 1202, & 1204.
In 1:4 cement mortar
Unit = cum
a) Materials
Stone for C.R. masonry 2nd sort Cum 0.60 1061.00 636.60
Through bond stone (7 nos x0.24 x 0.24 x 0.39 = 0.16 Nos. 7.00 30.00 210.00
cum)
Spalls/blaster rubble Cum 0.50 766.00 383.00
Cement mortar (rate as in item 11.5(ii) Cum 0.33 4217.95 1391.92
Total 2621.52
b) Labour
Mate Day 0.14 210.00 29.40
Mason (Ist class) Day 1.30 210.00 273.00
Majdoor (Unskilled) Day 2.00 331.00 662.00
Bhisti Day 0.08 252.00 20.16
Total 984.56
c) Add 13.50% on a+b (Contractor's profit @ 10% + 486.82
Over head Charges @ 2.5% & Labour cess @ 1.00 %)

Rate per cum = (a+b+c) 4092.90


Cost per Cum excluding carriage 4092.90
Carriage
Stone Cum 0.60 427.05 256.23
Bond stone Cum 0.16 427.05 68.33
Spalls/blaster rubble Cum 0.50 427.05 213.53
Cement Mortar
Cement Cum 0.125 245.85 30.73
Sand Cum 0.35 682.60 238.91
Cost per Cum including carriage 4900.60

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 214
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.7 700 Stone masonry work in cement mortar for Sub


Structure complete as per drawing and technical
specifications clauses 702, 704, 1202, & 1204.
Course rubble masonry (2nd sort)
In 1:3 cement mortar
Unit = cum
a) Materials
Stone for C.R. masonry 2nd sort Cum 0.60 1061.00 636.60
Through bond stone (7 nos x0.24 x 0.24 x 0.39 = 0.16 Nos. 7.00 30.00 210.00
cum)
Spalls/blaster rubble Cum 0.50 766.00 383.00
Cement mortar (rate as in item 11.5(ii) Cum 0.33 5179.95 1709.38
Total 2938.98
b) Labour
Mate Day 0.14 210.00 29.40
Mason (Ist class) Day 1.30 210.00 273.00
Majdoor (Unskilled) Day 2.00 331.00 662.00
Bhisti Day 0.08 252.00 20.16
Total 984.56
c) Add 13.50% on a +b (Contractor's profit @ 10% + 529.68
Over head Charges @ 2.5% & Labour cess @ 1.00 %)

Rate per cum = (a+b+c) 4453.22


Cost per Cum excluding carriage 4453.20
Carriage
Cement Mortar
Cement t 0.168 245.85 41.30
Sand cum 0.35 682.60 238.91
Stone cum 0.60 427.05 256.23
Spalls/blaster rubble Cum 0.50 427.05 213.53
Bond stone cum 0.16 427.05 68.33
Cost per Cum including carriage 5271.50

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 215
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.7 700 Stone masonry in cement mortar for substructure


complete as per drawing and technical specification
clause 702, 704, 1202 & 1204.
II. Coursed rubble masonry (2nd sort)
(III) In cement mortar 1:5
Unit: Cum
a) Material
Stone for CR Masonry 2nd sort cum. 0.60 1303.00 781.80
Through and bond stone Nos. 7.00 30.00 210.00
(7Nos. X 0.24m X 0.24m X 0.39m = 0.16Cum.
Spalls/blasted rubbles cum. 0.50 751.00 375.50
Cement mortar (Rate same as in item 12.1 (III) cum. 0.33 3699.95 1220.98
Total 2588.28
b) Labour
Mate day 0.14 245.00 34.30
Mason 1st Class day 1.30 386.17 502.02
Mazdoor (Unskilled) day 2.00 245.00 490.00
Bhisti day 0.08 245.00 19.60
Total 1045.92
c) Add for scaffolding @ 5% on (a+b) 181.71
d) Add 12.50% on a+b+c (Contractor's profit @ 10% + 476.99
Over head Charges @ 2.5% )
e) Add on a+b+c+d Labour cess @ 1.00 % 42.93
Rate per Cum excluding carriage 4335.80
Carriage
Stone for CR Masonry 2nd sort cum. 0.60 697.11 418.27
Through and bond stone cum. 0.16 697.11 111.54
(7Nos. X 0.24m X 0.24m X 0.39m = 0.16Cum.
Spalls/blasted rubbles cum. 0.50 697.11 348.56
Cement Mortar
Cement Tonne 0.10 357.38 35.74
Sand cum. 0.35 947.68 331.69
Rate per Cum including carriage 5581.58

Say 5581.60

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 216
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.4 600 Plastering with cement mortar (1:4), 15mm thick on brick
work in super strucutre as per technical specification
clauses 613.4 & 1204
Unit = 10 sqm
Taking output = 1 sqm
a) Material
Cement mortar 1:4 (rate as per item 11.5 II) cum 0.24 4217.95 1012.31
b) Labour
Mate day 0.06 245.00 14.70
Mason 1st class day 0.60 386.17 231.70
Mazdoor (unskilled) day 0.60 245.00 147.00
Bhisti day 0.30 245.00 73.50
c) Add 12.50% on a+b (Contractor's profit @ 10% + 184.90
Over head Charges @ 2.5% )
d) Add Labour cess @ 1.00 % on a+b+c 16.64
Cost for 10 sqm = (a+b+c+d) 1680.75
Rate per sqm = (a+b+c+d)/10 168.08
Cost per sqm excluding carriage 168.08
Carriage
Cement Mortar
Cement Cum 0.114 272.96 31.12
Sand Cum 0.31 819.08 253.91
285.03
Rate of carriage per sqm = (a+b+c+d)/10 28.50
Cost per sqm including carriage 196.58
Say 196.60

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 217
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.4 700 Stone masonry work in cement mortar in foundation


complete as per drawing and technical specifications
clauses 702, 704, 1202, & 1204.
In 1:6 cement mortar
Unit = cum
a) Materials
Stone for C.R. masonry 2nd sort Cum 0.60 1061.00 636.60
Through bond stone (7 nos x0.24 x 0.24 x 0.39 = 0.16 Nos. 7.00 30.00 210.00
cum)
Spalls/blaster rubble Cum 0.50 766.00 383.00
Cement mortar (rate as in item 11.5(ii) Cum 0.33 3255.95 1074.46
Total 2304.06
b) Labour
Mate Day 0.14 210.00 29.40
Mason (Ist class) Day 1.30 210.00 273.00
Majdoor (Unskilled) Day 2.00 331.00 662.00
Bhisti Day 0.08 252.00 20.16
Total 984.56
c) Add 12.50% on a +b+c+d (Contractor's profit @ 10% 411.08
+ Over head Charges @ 2.5% )
d) Add Labour cess @ 1.00 %) 37.00
Cost per Cum excluding carriage 3736.70
Carriage
Stone Cum 0.60 427.05 256.23
Bond stone Cum 0.16 427.05 68.33
Spalls/blaster rubble Cum 0.50 427.05 213.53
Cement Mortar
Cement Cum 0.0825 245.85 20.28
Sand Cum 0.3465 682.60 236.52
Cost per Cum including carriage 4531.60

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 218
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.5 800 Plain / reinforced cement concrete in substructure


complete as per drawing and technical specifications
clauses 802, 804, 805, 806, 807, 1202, 1204

I) R.C.C. grade M-20


Nominal mix (1:2:4)
a) Material
Cement T 0.35 7400.00 2590.00
Sand Cum 0.45 1101.00 495.45
20 mm aggregate Cum 0.54 1276.00 689.04
10 mm aggregate Cum 0.36 1281.00 461.16
4235.65
b) Labour
Mate Day 0.08 245.00 19.60
Mason ( Ist class) Day 0.12 386.17 46.34
Majdoor (Unskilled) Day 1.73 245.00 423.85
Bhisti Day 0.27 245.00 66.15
555.94
c) Machinery
Concrete mixture 0.4/0.28 cum capacity Hour 0.40 350.00 140.00
d) Form work @ 10% on (a+b+c) 493.16
c) Add 12.50% on a +b+c+d (Contractor's profit @ 10% 678.09
+ Over head Charges @ 2.5% )
d) Add Labour cess @ 1.00 %) 61.03
Rate per cum = a+b+c+d+e (excluding 6163.87
carriage)
Carriage
Cement T 0.35 268.94 94.13
Sand Cum 0.45 812.65 365.69
Aggregate Cum 0.90 736.04 662.44
Rate per cum = a+b+c+d+e (Including 7286.13
carriage)
Say 7286.10

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 219
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.5 800 Plain / reinforced cement concrete in substructure


complete as per drawing and technical specifications
clauses 802, 804, 805, 806, 807, 1202, 1204

VI R.C.C. grade M-25


a) Material
Cement T 0.404 7400.00 2989.60
Sand Cum 0.45 1101.00 495.45
20 mm aggregate Cum 0.54 1276.00 689.04
10 mm aggregate Cum 0.36 1281.00 461.16
4635.25
b) Labour
Mate Day 0.08 245.00 19.60
Mason ( Ist class) Day 0.12 386.17 46.34
Majdoor (Unskilled) Day 1.73 245.00 423.85
Bhisti Day 0.27 245.00 66.15
555.94
c) Machinery
Concrete mixture 0.4/0.28 cum capacity Hour 0.40 350.00 140.00
d) Form work @ 10% on (a+b+c) 533.12
e) Add 12.50% on a+b+c +d (Contractor's profit @ 10% 733.04
+ Over head Charges @ 2.5% )
f) Add Labour cess @ 1.00 % on a+b+c+d+e 65.97
Rate per cum = a+b+c+d+e+f (excluding 6663.32
carriage)
Carriage
Cement T 0.404 272.96 110.28
Sand Cum 0.45 819.08 368.59
Aggregate Cum 0.90 943.28 848.95
Rate per cum = a+b+c+d+e (Including 7991.14
carriage)
Say 7991.10

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 220
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.9 1000 Supplying, fitting, and placing HYSD bar


reinforcement (Fe-415) in sub structure complete as
per drawing and technical specifications caluses
1002, 1005, 1010 and 1202.
Unit =T
a) Material
HYSD bars including 5 per cent over laps and wastage t 1.05 49000.00 51450.00
Binding wire Kg 6.00 70.00 420.00
51870.00
b) Labour
Mate Day 0.34 245.00 83.30
Blacksmith Day 2.00 294.00 588.00
Mazdoor (Unskilled) Day 6.50 245.00 1592.50
2263.80
c) Add 12.50% on a+b (Contractor's profit @ 10% + 6766.73
Over head Charges @ 2.5% )
d) Add on a+b+c Labour cess @ 1.00 %) 609.01
Rate per Tonne = a+b+c+d 61509.53
Cost per Kg. Excluding carriage 61.51
Carriage
HYSD bars including 5 per cent for laps and wastage t 1.05 374.64 393.37
Rate per Tonne = a+b+c 61902.90
Cost per Kg. including carriage 61.90
Say 61.90

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 221
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

3.11 2000, 1000 & Supplying, fitting and fixing in position true to line and level
2200 (Based cast steel rocker bearing conforming to IRC:83 (Pt.-1)
on HPSR- section IX and clause 2003 of MORTH specification
2009) complete including all accessories as per drawing and
technical specifications.
Unit : 1 tonne capacity
Considering a 250 tonne capacity bearing for this analysis

a) Labour
Mate day 0.06 210.00 12.60
Mazdoor (skilled) day 0.50 331.00 165.50
Mazdoor day 1.00 331.00 331.00
b) Material
Cast steel rocker bearing assembly of 250 tonne design each 1.00 75000.00 75000.00
laod capacity duly painted complete with all its
components as per drawing and specifications
Add 1% of cost of bearing assembly for foundation 750.00
anchorage bolts, lifting arrangements, grease and other
consumeable
d) Add 13.50% on a+b (Contractor's profit @ 10% + 10294.98
Over head Charges @ 2.5% & Labour cess @ 1.00 %)

Cost for 250 tonne capacity bearing = a+b+c+d 86554.08


Cost per tonne capacity 346.20

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 222
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

3.12 2000, 1000 & Supplying, fitting and fixing in position true to line and level
2200 (Based cast steel roller bearing conforming to IRC:83 (Pt.-1)
on HPSR- section IX and clause 2003 of MORTH specification
2009) complete including all accessories as per drawing and
technical specifications.
Unit : 1 tonne capacity
Considering a 250 tonne capacity bearing for this analysis

a) Labour
Mate day 0.06 210.00 12.60
Mazdoor (skilled) day 0.50 331.00 165.50
Mazdoor day 1.00 331.00 331.00
b) Material
Forged steel roller bearing assembly of 250 tonne design each 1.00 80000.00 80000.00
laod capacity duly painted complete with all its
components as per drawing and specifications
Add 1% of cost of bearing assembly for foundation 800.00
anchorage bolts, lifting arrangements, grease and other
consumeable
d) Add 13.50% on a+b (Contractor's profit @ 10% + 10976.73
Over head Charges @ 2.5% & Labour cess @ 1.00 %)

Cost for 250 tonne capacity bearing = a+b+c+d 92285.83


Cost per tonne capacity 369.10

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 223
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.8 800 Plain / reinforced cement concrete in substructure For Kms. Stones, toe walls &
complete as per drawing and technical specifications catchpits etc.
clauses 802, 804, 805, 806, 807, 1202, 1204

I) P.C.C. grade M-15


Nominal mix (1:2.5:5)
a) Material
Cement T 0.275 7400.00 2035.00
Sand Cum 0.48 1101.00 528.48
40 mm aggregate Cum 0.48 1069.00 513.12
20 mm aggregate Cum 0.24 1276.00 306.24
10 mm aggregate Cum 0.08 1281.00 102.48
3485.32
b) Labour
Mate Day 0.08 245.00 19.60
Mason ( Ist class) Day 0.10 386.17 38.62
Majdoor (Unskilled) Day 1.63 245.00 399.35
Bhisti Day 0.27 245.00 66.15
523.72
c) Machinery
Concrete mixture 0.4/0.28 cum capacity Hour 0.40 350.00 140.00
d) Form work @ 10% on (a+b+c) 414.90
e) Add 12.50% on a+b+c+d (Contractor's profit @ 10% 570.49
+ Over head Charges @ 2.5% )
f) Add on a+b+c+d+eLabour cess @ 1.00 % 51.34
Rate per cum = a+b+c+d+e+f (excluding 5185.78
carriage)
Carriage
Cement T 0.275 357.38 98.28
Sand Cum 0.48 947.68 454.89
Aggregate Cum 0.80 1088.08 870.46
Rate per cum = a+b+c+d+e (Including 6609.41
carriage)
Say 6609.40

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 224
Chapter-12
Sr. No. Reference of Description Unit Quantity Rate (Rs.) Amount
MORD (Rs.)
Specifications

12.5 800 Plain / reinforced cement concrete in substructure


complete as per drawing and technical specifications
clauses 802, 804, 805, 806, 807, 1202, 1204

II) R.C.C. grade M-20 (5mtr. to 10 mtr. Height)


Nominal mix (1:2:4)
a) Material
Cement T 0.35 7400.00 2590.00
Sand Cum 0.45 1101.00 495.45
20 mm aggregate Cum 0.54 1276.00 689.04
10 mm aggregate Cum 0.36 1281.00 461.16
4235.65
b) Labour
Mate Day 0.08 245.00 19.60
Mason ( Ist class) Day 0.12 386.17 46.34
Majdoor (Unskilled) Day 1.73 245.00 423.85
Bhisti Day 0.27 245.00 66.15
555.94
c) Machinery
Concrete mixture 0.4/0.28 cum capacity Hour 0.40 350.00 140.00
d) Form work @ 12% on (a+b+c) 591.79
d) Add 12.50% on a +b+c+d (Contractor's profit @ 10% 690.42
+ Over head Charges @ 2.5% )
e) Add Labour cess @ 1.00 %) 62.14
Rate per cum = a+b+c+d+e (excluding
carriage)
Carriage
Cement T 0.35 245.85 86.05
Sand Cum 0.45 682.60 307.17
Aggregate Cum 0.90 784.60 706.14
Rate per cum = a+b+c+d+e (Including 7375.30
carriage)

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 225
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns
13.11 800 PCC M-15 Ordinary grade (1:2.5:5) leveling course below
approach slab as per drawing and technical specifications
clauses 800 & 1211
Nominal Mix 1:2 1/2 : 5)
Unit Cum.
a) Material
Cement T 0.275 7400.00 2035.00
Coarse sand Cum 0.48 1101.00 528.48
40mm aggregate Cum 0.48 1069.00 513.12
20 mm aggregate Cum 0.24 1276.00 306.24
10 mm aggregate Cum 0.08 1281.00 102.48
Total 3485.32
b) Labour
Mate Day 0.08 210.00 16.80
Mason ( Ist class) Day 0.10 210.00 21.00
Majdoor (Unskilled) Day 1.63 331.00 539.53
Bhisti Day 0.27 252.00 68.04
Total 645.37
c) Machinery .
Concrete mixture 0.4/0.28 cum capacity Hour 0.40 350.00 140.00
d) Add 13.50% on a +b+c(Contractor's profit @ 10% + 576.54
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Rate per cum = a+b+c+d 4847.23
Rate per cum excluding carriage 4847.20
Carriage
Cement T 0.275 245.85 67.61
Coarse sand Cum 0.48 682.60 327.65
Aggregate Cum 0.80 784.60 627.68
Rate per cum including carriage 5870.14

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 226
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns

900 & 1200 Providing concrerte for plain/reinforced concrete in open


foundation complete as per drawing and technical
specification clause 802, 803, 1202 & 1203.
II. PCC Grade M-15
Nominal Mix 1:2 1/2 : 5
Unit Cum.
a) Material
Cement t 0.275 7400.00 2035.00
Coarse sand cum 0.48 1101.00 528.48
40mm aggregate cum 0.48 1069.00 513.12
20 mm aggregate cum 0.24 1276.00 306.24
10mm aggregate cum 0.08 1281.00 102.48
Total 3485.32
b) Labour
Mate Day 0.08 245.00 19.60
Mason ( Ist class) Day 0.10 386.17 38.62
Majdoor (Unskilled) Day 1.63 245.00 399.35
Bhisti Day 0.27 245.00 66.15
Total 523.72
c) Machinery
Concrete mixture 0.4/0.28 cum capacity Hour 0.40 350.00 140.00
d) Add form work @ 4% on a+b+c 165.96
e) Add 12.50% on a +b+c+d (Contractor's profit @ 10% + 539.37
Over head Charges @ 2.5% )
Add 1 % labour cess 48.54
Rate per cum = a+b+c+d+e+f (excluding 4902.92
carriage)
Say 4902.90
Carriage
Cement t 0.275 297.08 81.70
Coarse sand cum 0.48 857.66 411.68
Aggregate cum 0.80 986.72 789.38
Rate per cum inlcuding carriage 6185.67

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 227
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns
13.2 1000 Supplying, fitting, and placing HYSD bar reinforcement in
super structure complete as per drawing and technical
specifications caluses 1002, 1010 and 1202.
Unit =T
a) Material
HYSD bars including 5 per cent for laps and wastage t 1.05 49000.00 51450.00
Binding wire Kg 8.00 70.00 560.00
52010.00
b) Labour
Mate Day 0.44 245.00 107.80
Blacksmith Day 3.00 294.00 882.00
Majdoor (Unskilled) Day 8.00 245.00 1960.00
2949.80
c) Add 12.50% on a +b (Contractor's profit @ 10% + Over 6869.98
head Charges @ 2.5% )
Add 1 % labour cess 618.30
Rate per Tonne = a+b+c 62448.07
Cost per Kg. Excluding carriage 62.40
Carriage
HYSD bars including 5 per cent for laps and wastage t 1.05 286.20 300.51
Rate per Tonne = a+b+c 62748.58
Cost per Kg. Including carriage 62.75
Say 62.75

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 228
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns

13.1 800 Providing and laying reinforced cement concrete in super


structure complete as per drawing and technical
specifications clauses, 800, 1205.4 and 1205.5
II R.C.C. grade M - 25 (5mtr. to 10 mtr. Height)
a) Material
Cement T 0.40 7400.00 2960.00
Coarse sand Cum 0.45 1101.00 495.45
20 mm aggregate Cum 0.54 1276.00 689.04
10 mm aggregate Cum 0.36 1281.00 461.16
Total 4605.65
b) Labour
Mate Day 0.08 245.00 19.60
Mason ( Ist class) Day 0.12 386.17 46.34
Majdoor (Unskilled) Day 1.73 245.00 423.85
Bhisti Day 0.27 245.00 66.15
Total 555.94
c) Machinery
Concrete mixture 0.4/0.28 cum capacity Hour 0.40 350.00 140.00
d) Form work and stagging refere to sub-item (c) of i (ii) 1325.40
above 25%
e) Add 12.50% on a +b+c+d (Contractor's profit @ 10% + 828.37
Over head Charges @ 2.5% )
f) Add Labour cess @ 1.00 %) 74.55
Cost per cum = a+b+c+d+e (excluding carriage) 7529.90
Carriage
Cement T 0.40 260.90 104.36
Coarse sand Cum 0.45 799.79 359.91
Aggregate Cum 0.90 921.56 829.40
Cost per cum = a+b+c+d+e (including carriage) 8823.57
Say 8823.60

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 229
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns

13.1 800 Providing and laying reinforced cement concrete in super


structure complete as per drawing and technical
specifications clauses, 800, 1205.4 and 1205.5
R.C.C. grade M-25 (Wearing coat)
a) Material
Cement T 0.40 7400.00 2960.00
Coarse sand Cum 0.45 1101.00 495.45
20 mm aggregate Cum 0.54 1276.00 689.04
10 mm aggregate Cum 0.36 1281.00 461.16
Total 4605.65
b) Labour
Mate Day 0.08 210.00 16.80
Mason ( Ist class) Day 0.12 210.00 25.20
Majdoor (Unskilled) Day 1.73 331.00 572.63
Bhisti Day 0.27 252.00 68.04
Total 682.67
c) Machinery
Concrete mixture 0.4/0.28 cum capacity Hour 0.40 350.00 140.00
d) Add 13.50% on a +b+c (Contractor's profit @ 10% + 732.82
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost per cum = a+b+c+d (excluding carriage) 6161.10
Carriage
Cement T 0.40 245.85 98.34
Coarse sand Cum 0.45 682.60 307.17
Aggregate Cum 0.90 784.60 706.14
Cost per cum = a+b+c+d(including carriage) 7272.80

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 230
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns

13.6 800 Construction of R.C.C. railing of M-25 grade in cast -in-


situ with 20 mm nominal size aggregate, true to line and
grade, tolerance of vertical railing post not to exceed 1 in
500, centre - to -centre spacing between vertical posts not
to exceed 2000 mm as per drawing and technical
specifications clauses 800, 900 and 1208.3

Unit = each
Taking output = 4x12
Span = 48 m
a) M- 25 grade R.C.C. Excluding carriage
No. of vertical posts = (6+1) 4= 28 Nos.
Cross-sectional area of vetical post = 0.25x0.275=0.069 sqm
Concrete in vertical posts = 0.069x28x1=1.932 cum
Hand rail in 3 liters =3x48=144 m
Cross -sectional area =0.17x0.175= 0.03 sqm
Concrete in hand rails =0.03x144=4.32 cum
Total concrete =1.932+4.32=6.252 cum Cum 6.25 6746.80 42167.52
b) HYSD bar renforcement T 1.36 62448.07 84929.38
Cost for 48 m = (a+b) 127096.90
Rate per M 2647.90

a) M- 25 grade R.C.C. Including carriage


No. of vertical posts = (6+1) 4= 28 Nos.
Cross-sectional area of vetical post = 0.25x0.275=0.069 sqm
Concrete in vertical posts = 0.069x28x1=1.932 cum
Hand rail in 3 liters =3x48=144 m
Cross -sectional area =0.17x0.175= 0.03 sqm
Concrete in hand rails =0.03x144=4.32 cum
Total concrete =1.932+4.32=6.252 cum Cum 6.25 8128.61 50803.81
b) HYSD bar renforcement T 1.36 62748.58 85338.07
Cost for 48 m = (a+b) 136141.89
Rate per M 2836.29
say 2836.30

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 231
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns

Sub analysis for rate of concrete


a) Material
Cement T 0.40 7400.00 2960.00
Coarse sand Cum 0.45 1101.00 495.45
20 mm aggregate Cum 0.54 1276.00 689.04
10 mm aggregate Cum 0.36 1281.00 461.16
Total 4605.65
b) Labour
Mate Day 0.08 245.00 19.60
Mason ( Ist class) Day 0.12 386.17 46.34
Majdoor (Unskilled) Day 1.73 245.00 423.85
Bhisti Day 0.27 245.00 66.15
Total 555.94
c) Machinery
Concrete mixture 0.4/0.28 cum capacity Hour 0.40 350.00 140.00
d) Forwork @ 12% 636.19
e) Add 13.50% on a +b +c+d (Contractor's profit @ 10% + 742.22
Over head Charges @ 2.5% )
f) Add Labour cess @ 1.00 % on a+b+c+d+e 66.80
Cost per Cum excluding carriage 6746.80
Carriage
Cement T 0.40 293.06 117.22
Coarse sand Cum 0.45 851.23 383.05
Aggregate Cum 0.90 979.48 881.53
Cost per Cum including carriage 8128.61

Say 8128.60

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 232
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns

13.10 1200 Drainage spouts complete as per drawing and technical


specifications clauses 1209
Unit = 1 No.
a) Material
Corrison resistant structural steel grating including 5 per cent Kg 4.00 110.00 440.00
wastage
G.I. pipe 100 M dia m 1.00 625.00 625.00
Total 1065.00
b) Labour
For fabrication
Mate Day 0.02 245.00 4.90
Blacksmith, welder etc. (skilled) Day 0.02 294.00 5.88
Majdoor (Unskilled) Day 0.20 245.00 49.00
For fixing position
Mate Day 0.01 245.00 2.45
Mason ( Ist class) Day 0.01 386.17 3.86
Majdoor (Unskilled) Day 0.20 245.00 49.00
Total 115.09
c) Add @ 5 per cent of ocst of material and labour (a+b) 59.00
for electrodes, gas cutting, sealent, anti-corrosive
bituminous paint, mild steel grating etc.
d) Add 13.50% on a +b +c (Contractor's profit @ 10% + 154.89
Over head Charges @ 2.5% )
e) Add Labour cess @ 1.00 % on a+b+c+d 13.94
Rate per No. = (a+b+c+d+e) 1407.92

Say 1407.90

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 233
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns

13.1 800 Providing and laying reinforced cement concrete in


substructure complete as per drawing and technical
specifications clauses, 800, 1205.4 and 1205.5
III R.C.C. grade M-30 (5mtr. to 10 mtr. Height)
a) Material
Cement T 0.43 7400.00 3182.00
Coarse sand Cum 0.45 1101.00 495.45
20 mm aggregate Cum 0.54 1276.00 689.04
10 mm aggregate Cum 0.36 1281.00 461.16
4827.65
b) Labour
Mate Day 0.08 210.00 16.80
Mason ( Ist class) Day 0.12 210.00 25.20
Majdoor (Unskilled) Day 1.73 331.00 572.63
Bhisti Day 0.27 252.00 68.04
682.67
c) Machinery
Concrete mixture 0.4/0.28 cum capacity Hour 0.40 350.00 140.00
d) Form work and stagging refere to sub-item (c) of i (ii) 1412.58
above 25%
e) Add 13.50% on a +b+c+d (Contractor's profit @ 10% + 953.49
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Rate per cum = a+b+c+d+e (Excluding carriage) 8016.40
Carriage
Cement T 0.43 245.85 105.72
Coarse sand Cum 0.45 682.60 307.17
Aggregate Cum 0.90 784.60 706.14
Rate per cum including carriage 9135.40

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 234
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns

13.12 800 Reinforced cement concrete M-25 grade in aproach slab


including reinforcement and form work complete as per
drawing and technical speicifications clauses 800 & 1211

Unit : Cum.

Material Excluding carriage


Reinforcement cement concrete M-25grade rate as per item Cum. 1.00 7529.90 7529.90
No.13.11
HYSD Reinfcement (rate as per item No. 13.2 t 0.05 62448.07 3122.40

Rate per Cum. 10652.30


Material Including carriage
Reinforcement cement concrete M-25grade rate as per item Cum. 1.00 8823.57 8823.57
No.13.11
HYSD Reinfcement (rate as per item No. 13.2 t 0.05 62748.58 3137.43

Rate per Cum. 11961.00

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 235
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns

13.13 1200 Providing and laying of elestromeric slab seal expension


joint complete as per approved drawing and approved
specification to be installed by manufacturer/supplier or
their othorized representative ensuring compliance to the
manufacturer instructions for installations and as per
technical specification clause 1207.2.5

Unit: Rmt.
Taking output 7.5m
a) Material
Supply of elestromeric slab seal expension joint m 7.50 350.00 2625.00
b) Labour
Mate Day 0.04 210.00 8.40
Mazdoor (Skilled) Day 0.70 331.00 231.70
Mazdoor (Un-Skilled) Day 0.40 331.00 132.40
Total 372.50
c) Add 13.50% on a +b (Contractor's profit @ 10% + Over 404.66
head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost of 7.5M (a+b+c) 3402.16
Rate per Mtr. 453.62

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 236
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns

13.5 800 Providing and laying cement concrete in wearing course


M-30 grade including reinforcement complete as per
drawing and technical specifications clauses, 800 &
1206.3.

Unit Cum.
a) Material
Cement T 0.43 7400.00 3182.00
Coarse sand Cum 0.45 1101.00 495.45
20 mm aggregate Cum 0.54 1276.00 689.04
10 mm aggregate Cum 0.36 1281.00 461.16
HYSD bar reinfocement (Rate as per item no.13.2) t 0.075 62448.00 4683.60
Binding wire Kg. 0.010 70.00 0.70
9511.95
b) Labour
Mate Day 0.08 210.00 16.80
Mason ( Ist class) Day 0.12 210.00 25.20
Majdoor (Unskilled) Day 1.73 331.00 572.63
Bhisti Day 0.27 252.00 68.04
682.67
c) Machinery
Concrete mixture 0.4/0.28 cum capacity Hour 0.40 350.00 140.00
d) Form work@ 3% of cost of concrete 144.85
Mazdoor (Unskilled) for cleaning deck slab concrete Day 0.15 331.00 49.65
surface
e) Add 12.50% on a +b+c+d (Contractor's profit @ 10% + 730.69
Over head Charges @ 2.5% )
f) Add Labour cess @ 1.00 %) 65.76
Rate per cum = a+b+c+d+e (Excluding carriage) 11325.60
Carriage
Cement T 0.43 245.85 105.72
Coarse sand Cum 0.45 682.60 307.17
Aggregate Cum 0.90 784.60 706.14
Steel t 0.075 262.25 19.67
Rate per cum including carriage 12464.30

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 237
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns
13.12 800 Reinforced cement concrete M-25 grade in aproach slab
including reinforcement and form work complete as per
drawing and technical speicifications clauses 800 & 1211

Unit : Cum.

Material (excluding carraige)


Reinforcement cement concrete M-25grade rate as per item Cum. 1.00 7529.90 7529.90
No.13.11
HYSD Reinfcement (rate as per item No. 13.2 t 0.05 62448.07 3122.40

Rate per Cum. 10652.30

Material (including carriage)


Reinforcement cement concrete M-25grade rate as per item Cum. 1.00 8823.57 8823.57
No.13.11
HYSD Reinfcement (rate as per item No. 13.2 t 0.05 62748.58 3137.43

Rate per Cum. 11961.00

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 238
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns
800 Providing and laying reinforced cement concrete in super
structure as per drawing and technical specifications
clause 800, 1205 and 1205.5
III RCC Grade M-30
Unit Cum.
a) Material
Cement T 0.43 7400.00 3182.00
Coarse sand Cum 0.45 1101.00 495.45
20 mm aggregate Cum 0.54 1276.00 689.04
10 mm aggregate Cum 0.36 1281.00 461.16
4827.65
b) Labour
Mate Day 0.08 210.00 16.80
Mason ( Ist class) Day 0.12 210.00 25.20
Majdoor (Unskilled) Day 1.73 331.00 572.63
Bhisti Day 0.27 252.00 68.04
682.67
c) Machinery
Concrete mixture 0.4/0.28 cum capacity Hour 0.40 350.00 140.00
d) Form work@ 3% of cost of concrete 144.83
e) Add 13.50% on a +b+c+d (Contractor's profit @ 10% + 782.35
Over head Charges @ 2.5% & Labour cess @ 1.00 %)
Rate per cum = a+b+c+d+e (Excluding carriage) 6577.50
Carriage
Cement T 0.43 245.85 105.72
Coarse sand Cum 0.45 682.60 307.17
Aggregate Cum 0.90 784.60 706.14
Rate per cum including carriage 7696.50

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 239
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns
13.1 800 Providing and laying reinforced cement concrete in super
structure complete as per drawing and technical
specifications clauses, 800, 1205.4 and 1205.5
RCC Grade M-20
Unit Cum.
a) Material
Cement T 0.35 7400.00 2590.00
Coarse sand Cum 0.45 1101.00 495.45
20 mm aggregate Cum 0.54 1276.00 689.04
10 mm aggregate Cum 0.36 1281.00 461.16
4235.65
b) Labour
Mate Day 0.08 210.00 16.80
Mason ( Ist class) Day 0.12 210.00 25.20
Majdoor (Unskilled) Day 1.73 331.00 572.63
Bhisti Day 0.27 252.00 68.04
682.67
c) Machinery
Concrete mixture 0.4/0.28 cum capacity Hour 0.40 350.00 140.00
d) Form work @ 20% of cost of concrete on a+b+c 1011.66
e) Add 12.50% on a +b (Contractor's profit @ 10% + Over 758.75
head Charges @ 2.5% )
f) Add Labour cess @ 1.00 %) 68.29
Rate per cum = a+b+c+d+e+f (Excluding 6897.02
carriage)
Carriage
Cement T 0.43 245.85 105.72
Coarse sand Cum 0.45 682.60 307.17
Aggregate Cum 0.90 784.60 706.14
Rate per cum including carriage 8016.05
Say 6916.10

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 240
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns

13.16 1200 Providing and filling joint sealing compound as per drawings
and technical specifications with course sand and 6 percent
bitumen by weight.
Unit : Running metre
Taking output 7.50 mtr
7.5m long x 100mm wide x 10mm deep recess
a) Material
Sand
Volume = 7.5x0.1x0.01 = 0.008cum cum 0.008 1101.00 8.81
Weight = 0.008 x 1400 = 11.2 kg
Bitumen = 11.2 x 0.06 = 0.672 kg t 0.0007 34992.53 24.49
b) Labour
Mate day 0.02 210.00 4.20
Mazdoor (Skilled) day 0.50 331.00 165.50
Mazdoor (Unskilled) day 0.10 331.00 33.10
c) Add 13.50% on a +b (Contractor's profit @ 10% + Over 31.87
head Charges @ 2.5% & Labour cess @ 1.00 %)
d) Cost for 7.50 rmt with 10mm deepth 267.97
Rate per rmt with 10mm depth = (a+b+c+d)/7.5 35.70
(Excluding carriage)
Carriage
Sand Cum 0.008 682.60 5.46
Bitumen t 0.0007 1522.95 1.07
Rate per cum including carriage 42.20

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 241
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns
3.11 2000,1000& Supplying, fitting and fixing in position true to line
2200 and level cast steel rocker bearing conforming to
IRC:83 (Pt.-1) section IX and clause 2003 of MORTH
specification complete including all accessories as
per drawing and technical specifications.

(Based on Unit = One Tonne Capacity


HPRS-2009)
Considering a 250 tonne capacity bearing for this
analysis.
a) Labour
Mate day 0.06 210.00 12.60
Mazdoor (Skilled) day 0.50 331.00 165.50
Mazdoor (Unskilled) day 1.00 331.00 331.00
b) Material
Cast steel rocker bearing assembly of 250 tonne design load Each 1.00 75000.00 75000.00
capacity duly painted complete with all its components as per
drawing and technical specification.
Add 1% of cost of bearing assembly for foundation anchorage 750.00
bolts, lifting arrangements, grease and other consumables.

Total 76259.10
c) Add 13.50% on a +b (Contractor's profit @ 10% + Over 10294.98
head Charges @ 2.5% & Labour cess @ 1.00 %)
Rate for 250 tonne capacity. = (a+b+c) 86554.10
Rate per tonne capacity. = (a+b+c) 346.22

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 242
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns

3.12 2000,1000& Supplying, fitting and fixing in position true to line


2200 and level cast steel roller bearing conforming to
IRC:83 (Pt.-1) section IX and clause 2003 of MORTH
specification complete including all accessories as
per drawing and technical specifications.

(Based on Unit = One Tonne Capacity


HPRS-2009)
Considering a 250 tonne capacity bearing for this
analysis.
a) Labour
Mate day 0.06 210.00 12.60
Mazdoor (Skilled) day 1.00 331.00 331.00
Mazdoor (Unskilled) day 0.50 331.00 165.50
b) Material
Cast steel rocker bearing assembly of 250 tonne design load Each 1.00 80000.00 80000.00
capacity duly painted complete with all its components as per
drawing and technical specification.
Add 1% of cost of bearing assembly for foundation anchorage 800.00
bolts, lifting arrangements, grease and other consumables.

Total 81309.10
c) Add 13.50% on a +b (Contractor's profit @ 10% + Over 10976.73
head Charges @ 2.5% & Labour cess @ 1.00 %)
Rate for 250 tonne capacity. = (a+b+c) 92285.80
Rate per tonne capacity. = (a+b+c) 369.14

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 243
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns

Providing and fixing 50mm dia G.I. vent pipe in


soffits of slab as per design and specification and
as per direction of Engineer-in-Charge.
Detail of cost of one number
a) Material
M.S. grating 260mm X 260mm i/c carriage Each 1.00 200.00 200.00
50mm diametre GI pipe i/c carriage Mtr. 1.00 250.00 250.00
Bituminous paint LS 50.00
a) Labour
Mason 2nd class day 0.10 252.00 25.20
Mazdoor (Skilled) day 0.20 331.00 66.20
Total 591.40
c) Add 13.50% on a +b (Contractor's profit @ 10% + Over 79.84
head Charges @ 2.5% & Labour cess @ 1.00 %)
Rate for one number = (a+b+c) 671.20

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 244
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns

Based 800 Reinforced cement concrete M-30 grade in aproach slab


on including reinforcement and form work complete as per
13.12 drawing and technical speicifications clauses 800 & 1211

Unit : Cum.

Material (excluding carraige)


Reinforcement cement concrete M-30 grade rate as per item Cum. 1.00 7695.70 7695.70
No.13.1 III
HYSD Reinfcement (rate as per item No. 13.2 t 0.05 62448.07 3122.40

Rate per Cum. 10818.10

Material (including carriage)


Reinforcement cement concrete M-30 grade rate as per item Cum. 1.00 8814.73 8814.73
No.13.1 III
HYSD Reinfcement (rate as per item No. 13.2 t 0.05 62748.58 3137.43

Rate per Cum. 11952.16

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 245
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns
13.1 800 Providing and laying reinforced cement concrete in
substructure complete as per drawing and technical
specifications clauses, 800, 1205.4 and 1205.5
III R.C.C. grade M-30 (Up to 5mtr. Height)
a) Material
Cement T 0.43 7400.00 3182.00
Coarse sand Cum 0.45 1101.00 495.45
20 mm aggregate Cum 0.54 1276.00 689.04
10 mm aggregate Cum 0.36 1281.00 461.16
4827.65
b) Labour
Mate Day 0.08 210.00 16.80
Mason ( Ist class) Day 0.12 210.00 25.20
Majdoor (Unskilled) Day 1.73 331.00 572.63
Bhisti Day 0.27 252.00 68.04
682.67
c) Machinery
Concrete mixture 0.4/0.28 cum capacity Hour 0.40 350.00 140.00
d) Form work and stagging refere to sub-item (c) of i (ii) 1130.06
above 20%
e) Add 13.50% on a +b (Contractor's profit @ 10% + Over 915.35
head Charges @ 2.5% & Labour cess @ 1.00 %)
Rate per cum = a+b+c+d+e (Excluding carriage) 7695.70
Carriage
Cement T 0.43 245.85 105.72
Coarse sand Cum 0.45 682.60 307.17
Aggregate Cum 0.90 784.60 706.14
Rate per cum including carriage 8814.73

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 246
Chapter-13
Sr. Reference Description Unit Quantity Rate (Rs.) Amount
No. of MORD (Rs.)
Specificatio
ns

13.1 800 Providing and laying reinforced cement concrete in super


structure complete as per drawing and technical
specifications clauses, 800, 1205.4 and 1205.5
II (i) R.C.C. grade M - 25 ( up to 5mtr Height)
a) Material
Cement T 0.40 7400.00 2960.00
Coarse sand Cum 0.45 1101.00 495.45
20 mm aggregate Cum 0.54 1276.00 689.04
10 mm aggregate Cum 0.36 1281.00 461.16
Total 4605.65
b) Labour
Mate Day 0.08 210.00 16.80
Mason ( Ist class) Day 0.12 210.00 25.20
Majdoor (Unskilled) Day 1.73 331.00 572.63
Bhisti Day 0.27 252.00 68.04
Total 682.67
c) Machinery
Concrete mixture 0.4/0.28 cum capacity Hour 0.40 350.00 140.00
d) Form work and stagging refere to sub-item (c) of i (ii) 1085.66
above 20%
e) Add 12.50% on a +b+c+d (Contractor's profit @ 10% + 814.25
Over head Charges @ 2.5% )
f) Add on a +b+c+d+e Labour cess @ 1.00 % 73.28
Cost per cum = a+b+c+d+e+f (excluding 7401.50
carriage)
Carriage
Cement T 0.40 268.94 107.58
Coarse sand Cum 0.45 812.65 365.69
Aggregate Cum 0.90 936.04 842.44
Cost per cum = a+b+c+d+e (including carriage) 8717.20
Say 8717.20

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 247
Chaper-14
Sr. Reference of Description Unit Quantity Rate Amount
No. MORD (Rs.) (Rs.)
Specifications
14.2 1300 Providing and laying boulder apron laid in wire crates
with 4mm dia GI wire conforming to IS:280 and IS:4826 in
100mm x 100mm mesh (woven diagonally) including 10%
extra for laps and joints laid with stones boulder weighing
not less then 25Kg. Each as per drawing and technical
specification clause 1301.

Unit: Cum
Taking output 3m x 1.5m x 1.25m = 5.63Cum.
a) Material
Stone boulder (25Kg. Minimum) cum 5.63 766.00 4312.58
Stone spalls cum 1.13 766.00 865.58
GI Wire 4mm dia @ 32Kg./10Sqm. Kg 64.00 82.00 5248.00
Total 10426.16
b) Labour
Mate day 0.18 245.00 44.10
Mazdoor (Skilled) day 1.50 245.00 367.50
Mazdoor (Unskilled) day 3.00 245.00 735.00
Total 1146.60
c) Add for labour for weaving the wire crates @ 2% of cost of 104.96
GI wire
d) Add 12.50% on a+b (Contractor's profit @ 10% + Over 1459.72
head Charges @ 2.5% )
e) Add Labour cess @ 1.00 % on a+b+c+d 131.37
Cost of 5.63Cum. 13268.81
Cost per Cum. Excluding carriage 2356.80
Carriage
Stone boulder (25Kg. Minimum) cum 5.63 697.11 3924.73
Stone spalls cum 1.13 697.11 787.73
Cost of 5.63Cum. 17981.27
Cost per Cum. Including carriage 3193.83
say 3193.80

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 248
Chaper-14
Sr. Reference of Description Unit Quantity Rate Amount
No. MORD (Rs.) (Rs.)
Specifications
14.8 1303 Providing and laying flooring laid over cement concrete
bedding complete as per drawing and technical
specification clause 1303.3 Rubble stone laid in cement
mortar 1:5.
Unit = Cum
a) Material
Cement mortar 1:5 (For rate Raffer to item No.11.6) (1) cum 0.33 3699.95 1220.98
Add for Cement concrete bedding
Stone for rubble flooring 150mm thick cum 1.00 1303.00 1303.00
Stone spalls cum 0.20 766.00 153.20
Total 2677.18
b) Labour
Mate Day 0.10 245.00 24.50
Mason 1st Class Day 0.50 386.17 193.09
Mazdoor (Unskilled) Day 1.50 245.00 367.50
Total 585.09
c) Add 12.50% on a+b (Contractor's profit @ 10% + Over 407.78
head Charges @ 2.5% )
d) Add on a+b+c Labour cess @ 1.00 % 36.70
Cost per Cum. Excluding carriage 3706.75
Carriage
Cement mortar 1:5
Cement T 0.10 357.38 35.74
Sand cum 0.35 947.68 331.69
Stone for rubble flooring 150mm thick cum 1.00 697.11 697.11
Stone spalls cum 0.20 697.11 139.42
Cost per Cum. Including carriage 4910.71
Say 4910.70

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 249
Chaper-14
Sr. Reference of Description Unit Quantity Rate Amount
No. MORD (Rs.) (Rs.)
Specifications
14.7 1300 Providing and laying flooring laid over cement concrete
bedding complete as per drawing and technical
specification. Rubble stone laid in cement mortar 1:3.
Unit = Cum
a) Material
Cement mortar 1:3 (For rate Raffer to item No.11.6) (1) cum 0.33 5179.95 1709.38
Add for Cement concrete bedding
Stone for rubble flooring 150mm thick cum 1.00 1170.00 1170.00
Stone spalls cum 0.20 766.00 153.20
Total 3032.58
b) Labour
Mate Day 0.08 210.00 16.80
Mason 1st Class Day 0.50 210.00 105.00
Mazdoor (Unskilled) Day 1.50 331.00 496.50
Total 618.30
c) Add 13.50% on a+b (Contractor's profit @ 10% + Over 492.87
head Charges @ 2.5% & Labour cess @ 1.00 %)
Cost per Cum. Excluding carriage 4143.80
Carriage
Cement mortar 1:3
Cement cum 0.17 245.85 41.79
Sand cum 0.35 682.60 238.91
Add for Cement concrete bedding
Stone for rubble flooring 150mm thick cum 1.00 784.60 784.60
Stone spalls cum 0.20 784.60 156.92
Cost per Cum. Including carriage 5366.00

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 250
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (Rs.)
No. MORD
Specifications
Based On Providing and laying cement concrete 1:5:10 (one
HPSR-1999 cement : five sand : ten graded stone aggregate 40mm
nominal size) with 15% plum and curing complete
including cost of form work in retaining walls/breast
walls the size of plums shall be 150mm to 300mm (one
hundred fifty to three hundred millimetre) as per
HP.PWD specification is based on HPSR 1999

a) Material
Stone aggregate 40mm nominal size (0.65x0.92 = cum 0.60 1069.00 641.40
0.60cum)
Stone aggregate 20mm nominal size (0.24x0.92 = cum 0.22 1276.00 280.72
0.22cum)
Sand (0.47x0.92 = 0.43cum) cum 0.43 1101.00 473.43
Cement (0.13x0.92 = 0.1196Tonne) tonne 0.1196 7400.00 885.04
Selcected Hard stone cum 0.15 766.00 114.90
Total 2395.49
b) Labour
Beldar day 1.070 331.00 354.17
Beldar (Extra for ramming) day 0.980 331.00 324.38
Bhisti for extra ramming day 0.250 252.00 63.00
Mason 1st class day 0.170 210.00 35.70
Total 777.25
c) Add 13.50% on a+b (Contractor's profit @ 10% + 428.32
Over head Charges @ 2.5% & Labour cess @ 1.00 %)

Cost for per cum excluding carriage 3601.10


Carriage
Stone aggregate cum 0.82 784.60 643.37
Sand cum 0.43 682.60 293.52
Cement tonne 0.1196 245.85 29.40
Selcected Hard stone cum 0.15 427.05 64.06
Cost for per cum including carrriage 4631.50

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 251
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (Rs.)
No. MORD
Specifications
Based On C/o parapets with cement concrete 1:5:10 (one
HPSR-1999 cement : five sand : ten graded stone aggregate 40mm
nominal size) with 15% plum and curing complete
including cost of form work in retaining walls/breast
walls the size of plums shall be 150mm to 300mm (one
hundred fifty to three hundred millimetre) as per
HP.PWD specification is based on HPSR 1999

Detail of cost for each parapets excluding carriage


1 Excavation in earth work (1x1.85x0.45x0.15 = 0.12) cum 0.12 231.61 27.79
2 Providing form work steel plate
Front side = 1x1.85x0.30 = 0.55
Back side = 1x1.85x0.45 = 0.85
Toped portion = 1x1.50x0.15 = 0.28
Sides = 2x0.45x0.30
2x(0.45+0.30)/2x0.15 = 0.11
Total 2.04Sqm. Sqm 2.04 179.80 366.79
3 Providing laying CC 1:5:10 with 15% plum
(1x1.85x0.45x0.60 = 0.50cum)
Less for tapped portion (1x1.85x0.15x0.15 = 0.02)
Total 0.48cum cum 0.48 3601.10 1728.53

Cost for each parapet 2123.11


Say Rs. 2123.10

Detail of cost for each parapets including carriage


1 Excavation in earth work (1x1.85x0.45x0.15 = 0.12) cum 0.12 231.61 27.79
2 Providing form work steel plate
Front side = 1x1.85x0.30 = 0.55
Back side = 1x1.85x0.45 = 0.85
Toped portion = 1x1.50x0.15 = 0.28
Sides = 2x0.45x0.30
2x(0.45+0.30)/2x0.15 = 0.11
Total 2.04Sqm. Sqm 2.04 179.80 366.79
3 Providing laying CC 1:5:10 with 15% plum
(1x1.85x0.45x0.60 = 0.50cum)
Less for tapped portion (1x1.85x0.15x0.15 = 0.02)
Total 0.48cum cum 0.48 4631.50 2223.12

Cost for each parapet 2617.71


Say Rs. 2617.70

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Based On Foundation footing base column etc. and and mass


HPSR-1999 concrete

Page 252
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (Rs.)
No. MORD
Specifications
Detail of cost for 30Sqm.
Material
Rate as per item No.0805000000D sqm. 30.000 1261.60 37848.00
Battens 2nd calss kail wood cum 0.102 17513.40 1786.37
Ballies 125mm dia (kail wood)
10x1.5 = 15.00Rmt.
10x4.5 = 45.00Rmt.
Total = 60.00Rmt.
Add 5% for wastate 3.00Rmt.
Total 63.00Cum. Mtr. 63.00 70.00 4410.00
Carriage
Carriage of timber
Ballies 63x22/7x1/4(0.125)2 = 0.773cum
Battens = 0.102
Total = 0.875
1Km. By Mech. Tpt. cum 0.875 61.87 54.14
100mtr. By head load cum 0.875 25.46 22.28
44120.78
Assuming that Steel plates will becomes unserviceable each 0.01 37848.00 378.48
after being used 100times hence cost for using once
Add 1% for using repeatedly including repairs removal of 378.48
concrete deposits and applying oiling and greasing.
Assuming that timber shall become unserviceable after each 0.06 6272.78 392.05
being used 16times hece cost for using once
Add 5% wastage for usage repeatedly 313.64
1462.65
For assembling errection and dismentalling carpenter
taken item no.0801000000 has been reduced 60%
Carpenter 2nd calss each 3.00 210.00 630.00
Beldar each 6.00 331.00 1986.00
4078.65
Add CP & OH charges @ 15% 611.80
Cost for 30Sqm. 4690.44
Cost per sqm 156.35
Say Rs. 156.30

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Providing and laying (To level for slopes) and jointing


reinforced concrete light duty non pressure pipe 1st
class NP2 internal dia metre with collers and butt ends
prepared for coller joints including testing of joints
complete (900mm dia NP2) 2.50Mtr.

Page 253
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (Rs.)
No. MORD
Specifications
Detail of cost for 10Metre
a) Material
900mm dia pipe (2.50mtr length) 4Nos.
10metre Metre 10.00 3016.00 30160.00
Collar Each 4.00 0.00 0.00
Cement for 4joints (4x0.0082cum = 0.0238 cum or 0.049 tonne 0.04900 7400.00 362.60
tonne)
Sand for 4joints (4x0.0164cum = 0.066cum) cum 0.06600 1101.00 72.67
Total 30595.27
b) Labour
Mason 1st class day 1.50 210.00 315.00
Mason 2nd class day 1.50 252.00 378.00
Beldar day 3.60 331.00 1191.60
Bhisti day 0.60 252.00 151.20
Total 2035.80
c) Add 13.50% on a+b (Contractor's profit @ 10% + 4405.19
Over head Charges @ 2.5% & Labour cess @ 1.00 %)

Cost for 10mtr. 37036.26


cost for per mtr. (Rate excluding carriage) 3703.60
Carriage
Hume pipe by mech tpt Metre 10.00 1448.24 14482.40
Cement by mech tpt tonne 0.04900 245.85 12.05
Sand by mech tpt cum 0.06600 682.60 45.05
cost for per mtr. (Rate including carriage) 18243.10

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Based on HPSR 1999 (2110020000)


Stone soling properly hand packed filling interstices
with Kharanja sotne and consolidating with powe road
roller the required gradient and camber inlcuing
spreading, watering and rolling of hiding materils
moorum or earth etc.
Detail of cost for one cubic metre 100mm spread thickness
(finished work including materials and labour)
a) Material
Oridinary quarried stone Cum 1.00 766.00 766.00

Page 254
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (Rs.)
No. MORD
Specifications
Moorum/Earth L.S. 10.00
Total 776.00
b) Labour
Mate day 0.08 210.00 16.80
Beldar day 0.80 331.00 264.80
Bhishti day 0.21 252.00 52.92
Chowkidar day 0.009 331.00 2.98
Total 337.50
c) Machinery
Road roller chargres 8-10tonne day 0.009 2964.00 26.68
d) Add 13.50% on a+b+c (Contractor's profit @ 10% + 153.92
Over head Charges @ 2.5% & Labour cess @ 1.00 %)

Cost per cum. Excluding carriage 1294.10


Carriage
Oridinary quarried stone Cum 1.00 427.05 427.05
Cost per cum. including carriage 1721.20

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

805030000 Vertical surfaces such as walls (any thickness)


partions and the like including attached pillasters
butterss, plinth and string courses and the linke
Detail of cost for a parapets wall 15mtr. Long and 1mtr.
Height for surface area 2x15x1 = 30sqm.

a) Material
Rate as per item no. 80500000D sqm. 30.00 1834.60 55038.00
2nd class Kail wood battens cum. 0.102 28000.00 2856.00
Ballies 125mm dia Kail wood mtr. 63.00 100.00 6300.00

Assuming that Steel plates will becomes unserviceable each 0.01 55038.00 550.38
after being used 100times hence cost for using once

Page 255
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (Rs.)
No. MORD
Specifications
Add 1% for using repeatedly including repairs removal of 550.38
concrete deposits and applying oiling and greasing.
Assuming that timber shall become unserviceable after each 0.063 9156.00 576.83
being used 16times hece cost for using once
Add 5% wastage for usage repeatedly 457.80

For assembling errection and dismentalling carpenter


taken item no.0801000000 has been reduced 60%
Carpenter 2nd calss each 3.00 210.00 630.00
Beldar each 6.00 331.00 1986.00
Total 4751.39
b) Add 13.50% on a (Contractor's profit @ 10% + Over 641.44
head Charges @ 2.5% & Labour cess @ 1.00 %)

Cost for 30Sqm. 5392.83


Cost per Sqm 179.80

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Construction of parapets with CC 1:2.5:5 graded stone


aggregate 40mm and down including curing complete
as per direction of Engineer-In-Charge.

Detail for cost of each parapets excluding carriage


I) Pick Jumper work cum 0.12 231.61 27.79
ii) Providing and laying 1:2.5:5 in parapets including form cum 0.48 4902.90 2353.39
work

Total 2381.20
Detail for cost of each parapets including carriage
I) Pick Jumper work cum 0.12 231.61 27.79
ii) Providing and laying 1:2.5:5 in parapets including form cum 0.48 6326.55 3036.74
work

Total 3064.50

Page 256
Sr. Reference of Description Unit Quantity Rate (Rs.) Amount (Rs.)
No. MORD
Specifications

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar.

Page 257
Analysis of Rate

Construction of hill side (V-shaped) drain in accordance with the requirement of specifications true to line and
grade diamentions and other particulars as per drawing and technical specifications Clause 1606.1 in cement
concrete 1:3 :6 (1 cement:3 sand:6gradedcrushedstone aggregate 20 mm nominal size,with thickness of
concrete10cm of size 45cm X 25cm including cost of earthwork in all kinds of soil and cost of form work with
steel plates as per M O R D specifications including carriage of materials in allleads and lifts as per the
directions of Engineer-in-Charge.

Cost for 10Rmt.

Sr. Description of Item No. Length Breadth Height/


No. Depth

1 Earth work in excavation of structure as per drawing 1 10.00 1/2x0.474 0.35


and technical specification
Amount 0.83 231.60

2 Providing and laying cement concrete 1:3:6 (20mm)


I) 1 10.00 0.25 0.10
ii) 1 10.00 0.47 0.10
iii) 1 10.00 1/2x0.10 0.10

Amount 0.774 4902.17

Cost for 10Rmt.


Cost per Rmt excluding carriage
1 Earth work in excavation of structure as per drawing 1 10.00 1/2x0.474 0.35
and technical specification
Amount 0.83 231.60

2 Providing and laying cement concrete 1:3:6 (20mm)


I) 1 10.00 0.25 0.10
ii) 1 10.00 0.47 0.10
iii) 1 10.00 1/2x0.10 0.10

Amount 0.774 6490.96

Cost for 10Rmt.


Cost per Rmt including carriage
Say
Hill Side
Beam
45Cm

25Cm
37.40
Cm
10 Cement Concrete 1:3:6
10 Cm
Cm

Executive Engineer,
B&R Division HP.PWD.,

Page 258
Joginder Nagar

Page 259
tions true to line and
use 1606.1 in cement
ze,with thickness of
ost of form work with
and lifts as per the

Qty.

0.83

192.23

0.250
0.474
0.050
0.774
3794.28

3986.51
398.65
0.83

192.23

0.250
0.474
0.050
0.774
5024.00

5216.23
521.62
521.60

ncrete 1:3:6

Engineer,
on HP.PWD.,

Page 260
agar

Page 261
Analysis of Rate
Construction of hill side (U-shaped) drain in accordance with the requirement of specifications true to line and
grade diamentions and other particulars as per drawing and technical specifications Clause 1606.1 in cement
concrete 1:3 :6 (1 cement:3 sand:6gradedcrushedstone aggregate 20 mm nominal size,with thickness of
concrete10cm of size 45x50cm.
Cost for 10Rmt.
Sr. Description of Item No. Length Breadth Height/ Qty.
No. Depth
1 Earth work in excavation of structure as per 1 10.00 (0.80 + 0.60 3.90
drawing and technical specification 0.50)/2
Amount 3.90 231.60 903.24
2 Providing and laying cement concrete 1:3:6
i) 1 10.00 0.50 0.15 0.750
ii) 2 10.00 0.47 0.10 0.940
1.690
Amount 1.690 4902.17 8284.67

Cost for 10Rmt. 9187.91

1 Earth work in excavation of structure as per 1 10.00 (0.80+0.50)/ 0.60 3.90


drawing and technical specification 2
Amount 3.90 231.60 903.24

2 Providing and laying cement concrete 1:3:6


i) 1 10.00 0.50 0.15 0.750
ii) 2 10.00 0.47 0.10 0.940
1.690
Amount 1.690 6490.96 10969.72

Cost for 10Rmt. 11872.96

Cost per Rmt including carriage 1187.30


say 1187.30
0.60mtr

0.45mtr

0.30mtr.

0.15mtr. CC 1:3:6

0.50mtr

Executive Engineer,
B&R Division HP.PWD.,

Page 262
Joginder Nagar

Page 263
Item
Description Unit Qty. Rate Cost Remarks
Code
80500000D Sub analysis for manufacturing steel paltes for shuttering
steel work welded in builtup section including cutting fixing in
position in angles, plates etc. complete (Rate as per item
15040100 detail of cost for 90cmx60cm size of plate = 0.54
Sqm.

Material
3.15mm thick M.S. plate
0.90mx0.60m = 0.54 Sqm.
@ 24.72kgs per sqm. = 13.35Kgs
Add wastate @ 5% = 0.67Kgs
Total = 14.01Kgs
or 0.14Qtl.
Qtl 0.140 3200.00 448.00
Angle iron in frame 30x30x5mm size
2(0.90m+0.60m) = 3.00Rmt.
@ 2.20kgs. Per Rmt. = 6.60Kgs.
Add wastate @ 5% = 0.33Kgs.
Total = 6.93Kgs
or 0.0693Qtl.
Qtl 0.0693 3000.00 207.90
Carriage
Carriage of M.S. Plate and angles
M.S. Plate : 0.140Qtl.
Angel iron : 0.0683Qtl.
Total : 0.2093Qtl.
or 0.02093Tonne
By Mech. Transport Tonne 0.020 0.00 0.00 0.00
By Head Load Tonne 0.020 0.00 0.00
Total 0.00
Labour
Black Smith 1st Class Each 0.066 252.00 16.63
Bandhani Each 0.066 252.00 16.63
Beldar Each 0.154 331.00 50.97
Sundries L.S. 0.50
Welding charges by electric plant Cm 300.000 1.00 300.00
Total 384.74
Add for water charges @ 1.5% 15.61
Total 1056.25
Less credit for Scrap value after full use of plate when
65.59
become unserviceable @ 10% as reserve price
Total 990.66
Cost for 0.540Sqm 990.66
Cost per Sqm. 1834.60

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 264
Item
Description Unit Qty. Rate Cost Remarks
Code
805030000 Vertical surfaces such as walls (any thickness) partitions and
the like I/c attached pillasters buttress, plinth and string
courses and the like.
Detail of cost for a Parapet wall 15mtr. Long and 1mtr. High
for surface ares 2x15x1 = 30Sqm.
Material
Rate as per item no. 080500000D Sqm. 30.000 1834.60 55038.00
2nd class kail wood bettens Cum 0.102 28000.00 2856.00
Ballies 125mm dia (Kail wood) Mtr. 63.000 100.00 6300.00
Carriage
Carriage of timber
By Mech Tpt. Cum 0.875 0.00 0.00 0.00
By head load Cum 0.875 0.00 0.00
Total 64194.00
Assuming that steel plates will become unserviceable after
Each 0.010 55038.00 550.38
being used 100 times. Hence cost for using once
Add 1% for using repeatedy I/c repairs, removal of dents
550.38
cleaning concrete deposits & applying oiling & greasings
Assuming that timber shall become unserviceable after being
Each 0.063 9156.00 572.25
used 16times. Hence cost for using once
Add 5% wastate for usage repetedly 457.80
Total 2130.81
Labour
For assembling errection & dismentling carpenter taken of
item no. 0801000000 has been reducted to 60%
Carpenter 2nd class Each 3.000 210.00 630.00
Beldar Each 6.000 331.00 1986.00
Sundries (Taking 10% of cost of labour) 261.60
Total 5008.41
Add for contrctor's profit @ 10% except on 1/16th carriage 500.84
Add for Over head charges @ 5% except on 1/16th carriage 250.42
Cost for 30Sqm. 5759.67
Cost per Sqm. 191.99

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

9130000 Providing and laying cement concrete 1:4:8 (1 Cement : 4


sand : 8 graded stone aggregate 40mm nominal size) and
curing complete excluding the cost of form work in:-
9130100 Foundation and plinth

Page 265
Item
Description Unit Qty. Rate Cost Remarks
Code
Detail for cost of 1Cum.

a) Material
Stone aggregate 40mm nominal size (0.70-7.5% for voides Cum 0.650 1069.00 694.85
I.e. 0.05 = 0.65)
Stone aggregate 20mm nominal size Cum 0.240 1276.00 306.24
Sand Cum 0.470 1101.00 517.47
Cement (0.1175Cum) or 0.17Tonne Tonne 0.170 7400.00 1258.00
Total 2776.56
b) Labour
Beldar Each 2.090 331.00 691.79
Bhishti Each 0.270 252.00 68.04
Masnon 1st class Each 0.050 210.00 10.50
Mason 2nd class Each 0.050 252.00 12.60
Mate Each 0.040 210.00 8.40
Beldar (For extra ramming) Each 0.250 331.00 82.75
Total 874.08
c) Add 19% on a+b+c (Contractor's profit @ 10% + Over 693.62
head Charges @ 5% + water charges @ 1.5% + PMGSY
Practice @ 2.5%)
Cost per cum excluding carriage 4344.30
Carriage
Stone aggregate Cum 0.890 784.60 698.29
Sand Cum 0.470 682.60 320.82
Cement Tonne 0.170 245.85 41.79
Cost per cum excluding carriage 5405.20

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Providing and applying evenly a priming/tack coat with the


2118010000
stright run bitumenous primer @ 10Kg./10Sqm.
Detail of cost for 10Sqm.
a) Material
Bitumen straight run tonne 0.010 34992.53 349.93
Fuel wood for heating bitumen (Height 1500-2500 feets)
Page 266
Item
Description Unit Qty. Rate Cost Remarks
Code
@ 8Qtl./Mt = 0.01 x 8 = 0.08Qtl. Qtl 0.080 200.00 16.00
Total 365.93
b) Labour for aplying heating and spraying
Mate each 0.024 210.00 5.04
Beldar each 0.370 331.00 122.47
Mason 2nd class each 0.006 252.00 1.51
Spray man each 0.007 252.00 1.76
Total 130.79
c) Machinery
Bitumen Boiler with sparyer day 0.007 #VALUE! #VALUE!
d) Add 19% on a+b (Contractor's profit @ 10% + Over
head Charges @ 5% + water charges @ 1.5% + PMGSY 94.38
Practice @ 2.5%)
e) Add PMGSY Practice @ 2.5% on c ###
Cost per 10Sqm. ###
Cost per Sqm. Excluding carriage ###
Carriage
Bitumen tonne 0.010 1522.95 15.23
Cost per 10Sqm. ###
Cost per Sqm. Excluding carriage ###

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Preparing surfaces by brushing with wire brushes for


removing caked mud etc. sweeping with brooms and finally
211700000
fanning the cleaned surface with gunny bags to remove all
loose dirt etc.
2117010000 Water Bound macadam surface (new)
Detail of cost for 10Sqm.
Labour
Mate day 0.060 210.00 12.60

Page 267
Item
Description Unit Qty. Rate Cost Remarks
Code
Beldar day 0.600 331.00 198.60
Total 211.20
Add 1.5% for water charges 3.17
Total 214.37
Add for CP & OH Charges @ 15% 32.16
Cost for 10Sqm. 246.52
Cost per Sqm. 24.65
Say Rs. 24.70

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar

Page 268
Sr. Reference of Description Unit Quantity Rate
No. MORD (Rs.)
Specifications
Maintenance and repair per Kilometre plain area, Hill
area for single lane road.
Norms taken as per Yard Stick Rate of A/R & M/O letter No.
11659-70 dated 28/01/1997.
Ordinary Repair of plain area for one Year.
1) Labour
Beldar @ 0.30 No. per Km. @ '` 3600/- per month(For Month 6.000 3600.00
six months due to new metalled road)
Mistri @ 0.04No. per Km. @ '` 5760/- per month(For six Month 6.000 5760.00
months due to new metalled road)
2) Patch/ repair and pot holes @ 6%
Surface area 1000x3.05x6%= 183.00 sqm.
Stone aggregate @ 0.27cum/10sqm.= 4.94 cum. Cum 4.940 975.00
Bitumen @ 14.6 kg/ 10sqm. = 14.60x183.00/10=0.27 Tonne Tonne 0.270 34992.53

Fuel wood for heating Bitumen @ 6.00qtl/Tonne=1.92 Qtl


Fuel wood for grit 4.94cum.@ 0.50qtl/cum= 2.47qtl
Total:-4.39qtl. Qtl 4.390 475.00
3) Periodicity of routeen maintenance activity
i) Filling up edges metalled surface of excavating borrow pit. L.S.

ii) Dressing of berms. L.S.


iii) White washing/guard stones. L.S.
iv) Fixing disturbed caution boards / village board, speed L.S.
limit board etc.
v) Fixing displaced guard stones. L.S.
vi) White washing and gero painting of trunks of trees. L.S.
vii) Cutting ofbranches of trees. L.S.
viii) Topping of WBM blindage operation including picking of L.S.
loose metal.
ix) Maintenance of catch water drain. L.S.
x) Clearanceof CD work. L.S.
xi) Clearance of wild seasoned growth on berms. L.S.
xii) White washing of parapets & CD work. L.S.
xiii) Earth work in berms,de-silting of drain etc. L.S.
Total:-
To repair hill/ ordinary area= '` 26613/- @ 25%

1. For 1st Year


2. For 2nd year '` 35406/- + 8%
3. For 3rd year ` 38238/- + 8%
4. For 4rth year '` 41297/- +8%
5. For 5th year '` 44601/- +8%

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar
Amount
(Rs.)

6480.00

1382.00

4817.00
9448.00

2085.00

200.00

200.00
200.00
50.00

50.00
25.00
25.00
500.00

25.00
100.00
50.00
100.00
100.00
25837.00
6459.00
32296.00
32296.00
34880.00
37670.00
40684.00
43939.00

ngineer,
n HP.PWD.,
gar
Chaper-11
Reference of
Sr. Rate
MORD Discription Unit Quantity
No. (Rs.)
Specifications
11.4 800 & 1200 Providing concrete for plain/reinforced concrete in open,
foundation complete as per drawings and technical
specification clause 802, 803, 1202 & 1203
P.C.C. grade M-15
Nominal mix 1:2.5:5
a) Material
Cement T 0.250 3700.00
Coarse sand Cum 0.480 250.00
40 mm aggregate Cum 0.576 1069.00
20 mm aggregate Cum 0.288 380.00
10 mm aggregate Cum 0.096 380.00
Total
b) Labour
Mate Day 0.080 81.67
Meson ( Ist class) Day 0.10 130.67
Majdoor (Unskilled) Day 1.63 81.67
Bhisti Day 0.27 81.67
Total
c) Machinery
Concrete mixer 0.4/0.28 cum capacity Hour 0.40 150.00
d) Formwork @ 4% on cost of material, labour and
machinery (a+b+c)
e) Add 19% on a+b (Contractor's profit @ 10% + Over
head Charges @ 5% + water charges @ 1.5% + PMGSY
Practice @ 2.5%)
f) Add PMGSY Practice @ 2.5% on c
Cost per cum = a+b+c+d+e+f (Excluding
carriage)
Add 28.92% contractor premium for similar item i.e. item
No.28 (Rate as per DNIT = 1939.20, Rate as per agreement =
2500.00, Percent above 28.92%)

Say Rs.

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar
Amount
(Rs.)

925.00
120.00
615.74
109.44
36.48
1806.66

6.53
13.07
133.12
22.05
174.77

60.00

81.66

376.47
1.50

2501.10

723.32

3224.42
2521.95

ngineer,
n HP.PWD.,
gar
Analysis of Carriage of Material

Name of Work:- Construction of Ghatta Bag road KM. 0/0 to 4/5555 under PMGSY-I for the year 2016-17
Batch-I Package No. HP- 08-245.

Sr. Description of Item Length Rate Unit Amount


No.
1 Cement Lead = 8.000 Km.
Carriage by Mech. Tpt. 8.00 4.02 Tonne 32.16
Add for loading and unloading Tonne 220.70
Tonne 252.86
2 Sand Lead = 96.00Km.
Carriage by Mech. Tpt. Rs.3.15 per Tonne per Km. 96.00 6.43 Cum. 617.28
or Rs 5.04 per cum. Per Km.
Add for loading and unloading Cum. 27.40
Cum. 644.68
3 Aggregate 40mm and above Lead 96.00Km.
Carriage by Mech. Tpt. Rs.3.15 per Tonne per Km. 96.00 7.24 Cum. 695.04
or Rs.5.67 per cum. Per Km.
Add for loading and unloading Cum. 47.50
Cum. 742.54
4 Aggregate below 40mm Lead 96.00 Km.
Carriage by Mech. Tpt. Rs.3.15 per Tonne per Km. 96.00 7.24 Cum. 695.04
or Rs.5.67 per cum. Per Km.
Add for loading and unloading Cum. 47.50
Cum. 742.54
5 Cut Stone Lead 16.00 Km.
Carriage by Mech. Tpt. Rs.3.15 per Tonne per Km. 16.00 10.45 Cum. 167.20
or Rs.8.19 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 297.31
6 Boulder Lead 16.00 Km.
Carriage by Mech. Tpt. Rs.3.15 per Tonne per Km. 16.00 10.45 Cum. 167.20
or Rs.8.19 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 297.31
7 Steel Lead 8.00 Km.
Carriage by Mech. Tpt. 8.00 4.02 Tonne 32.16
Add for loading and unloading Tonne 237.96
Tonne 270.12
8 Hume Pipe Lead 105.00 Km.
Carriage by Mech. Tpt. 105.00 35.10 pipe 3685.50
Add for loading and unloading pipe 132.88
Pipe 3818.38
Rmt. 1527.35
9 Bitumen Lead 418.00Km.
Carriage by Mech. Tpt. 418.00 4.02 Tonne 1680.36
Add for loading and unloading Tonne 248.32
Tonne 1928.68
10 Bitumen Emulsion Lead 1881.00Km.
Carriage by Mech. Tpt. 1881.00 3.15 Tonne 5925.15
Add for loading and unloading Tonne 248.32
Tonne 6173.47

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar
Analysis of Carriage of Material

Name of Work:- Upgradation of Nauhli Uperli to Andralu Uperla (km. 0/00 to 4/500 km) Under PMGSY-I
Batch-I Package No. HP-08-247.

Sr. Description of Item Length Rate Unit Amount


No.
1 Cement Lead = 23.000 Km.
Carriage by Mech. Tpt. 23.00 4.02 Tonne 92.46
Add for loading and unloading Tonne 220.70
Tonne 313.16
2 Sand Lead = 130.00Km.
Carriage by Mech. Tpt. Rs.3.15 per Tonne per Km. 130.00 6.43 Cum. 835.90
or Rs 5.04 per cum. Per Km.
Add for loading and unloading Cum. 34.62
Cum. 870.52
3 Aggregate 40mm and above Lead 130.00Km.
Carriage by Mech. Tpt. Rs.3.15 per Tonne per Km. 130.00 7.24 Cum. 941.20
or Rs.5.67 per cum. Per Km.
Add for loading and unloading Cum. 47.50
Cum. 988.70
4 Aggregate below 40mm Lead 130.00 Km.
Carriage by Mech. Tpt. Rs.3.15 per Tonne per Km. 130.00 7.24 Cum. 941.20
or Rs.5.67 per cum. Per Km.
Add for loading and unloading Cum. 47.50
Cum. 988.70
5 Cut Stone Lead 40.00 Km.
Carriage by Mech. Tpt. Rs.3.15 per Tonne per Km. 40.00 10.45 Cum. 418.00
or Rs.8.19 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 548.11
6 Boulder & Filter media Lead 40.00 Km.
Carriage by Mech. Tpt. Rs.3.15 per Tonne per Km. 40.00 10.45 Cum. 418.00
or Rs.8.19 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 548.11
7 Steel Lead 23.00 Km.
Carriage by Mech. Tpt. 23.00 4.02 Tonne 92.46
Add for loading and unloading Tonne 237.96
Tonne 330.42
8 Hume Pipe Lead 100.00 Km.
Carriage by Mech. Tpt. 100.00 35.10 pipe 3510.00
Add for loading and unloading pipe 132.88
Pipe 3642.88
Rmt. 1457.15
9 Bitumen Lead 423.00Km.
Carriage by Mech. Tpt. 423.00 4.02 Tonne 1700.46
Add for loading and unloading Tonne 248.32
Tonne 1948.78
10 Bitumen Emulsion Lead 1886.00Km.
Carriage by Mech. Tpt. 1886.00 4.02 Tonne 7581.72
Add for loading and unloading Tonne 248.32
Tonne 7830.04

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar
Analysis of Carriage of Material

Name of Work:- Construction of Sandha to Makan road Km. 0/0 to 5/600 under PMGSY for the year 2014-
15 Batch-II Package No. HP-08-246.

Sr. Description of Item Length Rate Unit Amount


No.
1 Cement Lead = 33.000 Km.
Carriage by Mech. Tpt. 33.00 3.00 Tonne 99.00
Add for loading and unloading Tonne 160.00
Tonne 259.00
2 Sand Lead = 121.00Km.
Carriage by Mech. Tpt. Rs.3.00 per Tonne per Km. 121.00 4.80 Cum. 580.80
or Rs4.80 per cum. Per Km.
Add for loading and unloading Cum. 28.00
Cum. 608.80
3 Aggregate 40mm and above Lead 121.00Km.
Carriage by Mech. Tpt. Rs.3.00 per Tonne per Km. 121.00 5.40 Cum. 653.40
or Rs.5.40 per cum. Per Km.
Add for loading and unloading Cum. 48.00
Cum. 701.40
4 Aggregate below 40mm Lead 121.00 Km.
Carriage by Mech. Tpt. Rs.3.00 per Tonne per Km. 121.00 5.40 Cum. 653.40
or Rs.5.40 per cum. Per Km.
Add for loading and unloading Cum. 48.00
Cum. 701.40
5 Cut Stone Lead 41.00 Km.
Carriage by Mech. Tpt. Rs.3.00 per Tonne per Km. 41.00 7.80 Cum. 319.80
or Rs.7.80 per cum. Per Km.
Add for loading and unloading Cum. 94.00
Cum. 413.80
6 Boulder Lead 41.00 Km.
Carriage by Mech. Tpt. Rs.3.00 per Tonne per Km. 41.00 7.80 Cum. 319.80
or Rs.7.80 per cum. Per Km.
Add for loading and unloading Cum. 94.00
Cum. 413.80
7 Steel Lead 33.00 Km.
Carriage by Mech. Tpt. 33.00 3.00 Tonne 99.00
Add for loading and unloading Tonne 174.00
Tonne 273.00
8 Hume Pipe Lead 92.00 Km.
Carriage by Mech. Tpt. 92.00 35.00 pipe 3220.00
Add for loading and unloading pipe 106.00
Pipe 3326.00
Rmt. 1330.40
11 CRRI Bitchem Cold Mix binder Lead 54.00 Km.
Carriage by Mech. Tpt. 54.00 3.00 Tonne 162.00
Add for loading and unloading Tonne 179.00
Tonne 341.00

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar
Analysis of Carriage of Material

Name of Work:- Construction of Guini to Prain road Km. 0/0 to 5/120 under PMGSY for the year 2014-15
Batch-II Package No. HP-08-248.

Sr. Description of Item Length Rate Unit Amount


No.
1 Cement Lead = 35.000 Km.
Carriage by Mech. Tpt. 35.00 3.00 Tonne 105.00
Add for loading and unloading Tonne 160.00
Tonne 265.00
2 Sand Lead = 138.00Km.
Carriage by Mech. Tpt. Rs.3.00 per Tonne per Km. 138.00 4.80 Cum. 662.40
or Rs4.80 per cum. Per Km.
Add for loading and unloading Cum. 28.00
Cum. 690.40
3 Aggregate 40mm and above Lead 138.00Km.
Carriage by Mech. Tpt. Rs.3.00 per Tonne per Km. 138.00 5.40 Cum. 745.20
or Rs.5.40 per cum. Per Km.
Add for loading and unloading Cum. 48.00
Cum. 793.20
4 Aggregate below 40mm Lead 138.00 Km.
Carriage by Mech. Tpt. Rs.3.00 per Tonne per Km. 138.00 5.40 Cum. 745.20
or Rs.5.40 per cum. Per Km.
Add for loading and unloading Cum. 48.00
Cum. 793.20
5 Cut Stone Lead 58.00 Km.
Carriage by Mech. Tpt. Rs.3.00 per Tonne per Km. 58.00 7.80 Cum. 452.40
or Rs.7.80 per cum. Per Km.
Add for loading and unloading Cum. 94.00
Cum. 546.40
6 Boulder Lead 58.00 Km.
Carriage by Mech. Tpt. Rs.3.00 per Tonne per Km. 58.00 7.80 Cum. 452.40
or Rs.7.80 per cum. Per Km.
Add for loading and unloading Cum. 94.00
Cum. 546.40
7 Steel Lead 35.00 Km.
Carriage by Mech. Tpt. 35.00 3.00 Tonne 105.00
Add for loading and unloading Tonne 174.00
Tonne 279.00
8 Hume Pipe Lead 58.00 Km.
Carriage by Mech. Tpt. 58.00 35.00 pipe 2030.00
Add for loading and unloading pipe 106.00
Pipe 2136.00
Rmt. 854.40
11 CRRI Bitchem Cold Mix binder Lead 35.00 Km.
Carriage by Mech. Tpt. 35.00 3.00 Tonne 105.00
Add for loading and unloading Tonne 179.00
Tonne 284.00

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar
Analysis of Carriage of Material

Name of Work:- Construction of Kundani Kass road Km. 0/0 to 6/795 under PMGSYRRP-II Stage-II for the
year 2012-13 Package No. HP-08-15.

Sr. Description of Item Length Rate Unit Amount


No.
1 Aggregate 40mm and above Lead 119.00Km.
Carriage by Mech. Tpt. Rs.3.15 per Tonne per Km. 119.00 5.67 Cum. 674.73
or 3.15 x 1.80 = Rs.5.67 per cum. Per Km.
Add for loading and unloading Cum. 47.50
Cum. 722.23
2 Aggregate below 40mm Lead 119.00 Km.
Carriage by Mech. Tpt. Rs.3.15 per Tonne per Km. 119.00 5.67 Cum. 674.73
or 3.15 x 1.80 = Rs.5.67 per cum. Per Km.
Add for loading and unloading Cum. 47.50
Cum. 722.23
3 Sand Lead 119.00 Kms.
Carriage by Mech. Tpt. Rs.3.15 per Tonne per Km. 119.00 5.04 Cum. 599.76
or 3.15 x 1.60 = Rs.5.04 per cum. Per Km.
Add for loading and unloading Cum. 27.40
Cum. 627.16
4 Bitchem Regular emulsion & CRRI- Bitchem
Cold Mix Binder Lead 257.00 Kms.
Carriage by Mech. Tpt. Rs.3.15 per Tonne per Km. 257.00 3.15 Cum. 809.55

Add for loading and unloading Cum. 190.50


Cum. 1000.05

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar
Material Rate

Sr. Description Unit Present Remarks


No. Market
Rate
1 90 to 45mm Cum. 500.00 Crusher site
2 63 to 45mm Cum. 500.00 Crusher site
3 Crushed Stone Chipping 13.2mm nominal size Cum. 636.00 Crusher site
4 Stone screening Type B 11.2 mm Cum. 636.00 Crusher site
5 Binding material Cum. 73.00 Market rate

Certified that the rate taken above for material are the
lowest prevailing market rates in the area.

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar
Analysis of Carriage of Material
Name of Work:- Construction of Bhardoan Gagoti road PMGSY-I Batch-II for the year 2016-17 Package No. HP-08-
08A
Sr. No. Description of Item Length Rate Unit Amount
1 Cement Lead = 25.000 Km.
Carriage by Mech. Tpt. 25.00 4.02 Tonne 100.50
Add for loading and unloading Tonne 216.56
Tonne 317.06
2 Sand Lead = 113.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 113.00 6.43 Cum. 726.59
6.43 per cum. Per Km.
Add for loading and unloading Cum. 34.62
Cum. 761.21
3 Aggregate 40mm and above Lead 113.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 113.00 7.24 Cum. 818.12
7.24 per cum. Per Km.
Add for loading and unloading Cum. 60.00
Cum. 878.12
4 Aggregate below 40mm Lead 113.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 113.00 7.24 Cum. 818.12
7.24 per cum. Per Km.
Add for loading and unloading Cum. 60.00
Cum. 878.12
5 Cut Stone Lead 33.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or 33.00 10.45 Cum. 344.85
Rs.10.45 per cum. Per Km.
Add for loading and unloading Cum. 128.86
Cum. 473.71
6 Boulder Lead 33.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or 33.00 10.45 Cum. 344.85
Rs.10.45 per cum. Per Km.
Add for loading and unloading Cum. 128.86
Cum. 473.71
7 Steel Lead 25.00 Km.
Carriage by Mech. Tpt. 25.00 4.02 Tonne 100.50
Add for loading and unloading Tonne 233.00
Tonne 333.50
8 Hume Pipe Lead 79.00 Km.
Carriage by Mech. Tpt. 79.00 44.69 pipe 3530.51
Add for loading and unloading pipe 131.34
Pipe 3661.85
Rmt. 1464.74
9 Bitumen Lead 446.00Km.
Carriage by Mech. Tpt. 446.00 4.02 Tonne 1792.92
Add for loading and unloading Tonne 244.47
Tonne 2037.39
10 Bitumen Emulsion Lead 2700.00Km.
Carriage by Mech. Tpt. 2700.00 4.02 Tonne 10854.00
Add for loading and unloading Tonne 244.47
Tonne 11098.47
11 Soil Lead 10.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 10.00 6.43 Cum. 64.30
6.43 per cum. Per Km.
Carriage by Mech. Tpt. Cum. 34.62
Cum. 98.92
12 GSB Average Lead 70.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 70.00 6.43 Cum. 450.10
6.43 per cum. Per Km.
Carriage by Mech. Tpt. Cum. 34.62
Cum. 484.72

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar
ACTUAL RATES OF BITUMEN AT PANIPAT INCLUDING TAXES as on 01/05/2016
HDPE (NEW) Drums Packed
Bitchem Regular Emulsion( RS-I) 40983.00
Add 14.42 % excise duty 5910.00
Add 3% educational tax on excise duty 177.00
47070.00
Add 5.25% VAT 2471.00
Total 49541.00
Add. 5 % Entry tax 2477
Total 52018.00
Bitumen Emulsion Rapid 34240.00
Add 14.42 % excise duty 4937.00
Add 3% educational tax on excise duty 148.00
39325.00
Add 5.25% VAT 2065.00
Total 41390.00
Add. 5 % Entry tax 2070
Total 43460.00
Bitumen Emulsion Slow 32640.00
Add 14.42 % excise duty 4707.00
Add 3% educational tax on excise duty 141.00
37488.00
Add 5.25% VAT 1968.00
Total 39456.00
Add. 5 % Entry tax 1973
Total 41429.00
ACTUAL RATES OF BITUMEN & EMULSION AT PANIPAT, HALDIA, CHENNAI INCLUDING
TAXES APPLICABLE FROM 01/03/2017

Bulk
Bitumen 80/100 (VG-10) 27916.00
Add 14.42 % excise duty 4025.00
31941.00
Add 5.25% VAT 1677.00
Total 33618.00
Add. 5 % Entry tax 1681
Total 35299.00
Bitumen 60/70 (VG-30) 28716.00
Add 14.42 % excise duty 4141.00
32857.00
Add 5.25% VAT 1725.00
Total 34582.00
Add. 5 % Entry tax 1729
Total 36311.00
Bitumen Emulsion (Medium) (Haldia) 22346.00
Add 14.42 % excise duty 3222.00
25568.00
Add 5.25% VAT 1342.00
Total 26910.00
Add. 5 % Entry tax 1346
Total 28256.00
Bitumen Emulsion Rapid (Chennai) 22356.00
Add 14.42 % excise duty 3224.00
25580.00
Add 5.25% VAT 1343.00
Total 26923.00
Add. 5 % Entry tax 1346
Total 28269.00
Bitumen Emulsion Slow(SS1) (Chennai) 35616.00
Add 14.42 % excise duty 5136.00
40752.00
Add 5.25% VAT 2139.00
Total 42891.00
Add. 5 % Entry tax 2145
Total 45036.00
Bitumen Emulsion Slow (SS2) (Chennai) 23746.00
Add 14.42 % excise duty 3424.00
27170.00
Add 5.25% VAT 1426.00
Total 28596.00
Add. 5 % Entry tax 1430
Total 30026.00

Executive Engineer,
B&R Division,HPPWD.,
Joginder Nagar.
ACTUAL RATES OF BITUMEN & EMULSION AT DHANOTU (SUNDER NAGAR) INCLUDING
TAXES APPLICABLE FROM 16/03/2017

Packed/Bulk
Bitumen 80/100 (VG-10) (including all taxes) 36299.72

Total 36299.72

Bitumen Emulsion (Medium) (Dhanotu) 43449.00

Add 5 % VAT 2172.45

45621.45

Bitumen Emulsion Rapid (RS-I) (Dhanotu) 39715.00

Add 5 % VAT 1985.75

41700.75

Bitumen Emulsion Slow(SS1) (Dhanotu) 42048.00

Add 5 % VAT 2102.40

44150.40

Bitumen Emulsion Slow (SS2) (Dhanotu) 41468.00

Add 5 % VAT 2073.40

43541.40

Bitumen Emulsion Medium (MS) (Dhanotu) 43449.00


Add 5 % VAT 2172.45
45621.45

Executive Engineer,
Dharampur Division,.,
HPPWD Dharampur.
Analysis of Carriage of Material
Name of Work:- Up-gradation of Gadiyara to Thara road Km. 0/0 to 3/0 under Regular PMGSY, batch-I, 2017-18
Package No. HP-08-310.
Sr. No. Description of Item Length Rate Unit Amount
1 Cement Lead = 38.000 Km.
Carriage by Mech. Tpt. 38.00 4.02 Tonne 152.76
Add for loading and unloading Tonne 220.70
Tonne 373.46
2 Sand Lead = 130.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 130.00 6.43 Cum. 835.90
6.43 per cum. Per Km.
Add for loading and unloading Cum. 34.62
Cum. 870.52
3 Aggregate 40mm and above Lead 130.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 130.00 7.24 Cum. 941.20
7.24 per cum. Per Km.
Add for loading and unloading Cum. 60.00
Cum. 1001.20
4 Aggregate below 40mm Lead 130.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 130.00 7.24 Cum. 941.20
7.24 per cum. Per Km.
Add for loading and unloading Cum. 60.00
Cum. 1001.20
5 Cut Stone Lead 50.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or 50.00 9.00 Cum. 450.00
Rs.10.45 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 580.11
6 Boulder Lead 50.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or 50.00 9.00 Cum. 450.00
Rs.10.45 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 580.11
7 Steel Lead 38.00 Km.
Carriage by Mech. Tpt. 38.00 4.02 Tonne 152.76
Add for loading and unloading Tonne 237.96
Tonne 390.72
8 Hume Pipe Lead 53.00 Km.
Carriage by Mech. Tpt. 53.00 44.69 pipe 2368.57
Add for loading and unloading pipe 132.88
Pipe 2501.45
Rmt. 1000.58
9 Bitumen Lead 117.00Km. VG-10, RS-I, SS-I & MS.
(Dhanotu)
Carriage by Mech. Tpt. 117.00 4.02 Tonne 470.34
Add for loading and unloading Tonne 248.32
Tonne 718.66
10 Soil Lead 10.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 10.00 6.43 Cum. 64.30
6.43 per cum. Per Km.
Add for loading and unloading Cum. 34.62
Cum. 98.92
11 GSB Average Lead 70.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 70.00 6.43 Cum. 450.10
6.43 per cum. Per Km.
Add for loading and unloading Cum. 34.62
Cum. 484.72

Executive Engineer,
B&R Division HP.PWD.,
Sr. No. Description of Item Length Rate Unit Amount
Joginder Nagar
Analysis of Carriage of Material
Name of Work:- Construction of Bhararoo to Banaru Dom road Km.0/0 to 15/600 under Regular PMGSY , Batch-I,
2017-18 Package No. HP-08-307.
Sr. No. Description of Item Length Rate Unit Amount
1 Cement Lead = 19.000 Km.
Carriage by Mech. Tpt. 19.00 4.02 Tonne 76.38
Add for loading and unloading Tonne 220.70
Tonne 297.08
2 Sand Lead = 128.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 128.00 6.43 Cum. 823.04
6.43 per cum. Per Km.
Add for loading and unloading Cum. 34.62
Cum. 857.66
3 Aggregate 40mm and above Lead 128.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 128.00 7.24 Cum. 926.72
7.24 per cum. Per Km.
Add for loading and unloading Cum. 60.00
Cum. 986.72
4 Aggregate below 40mm Lead 128.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 128.00 7.24 Cum. 926.72
7.24 per cum. Per Km.
Add for loading and unloading Cum. 60.00
Cum. 986.72
5 Cut Stone Lead 48.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or 48.00 9.00 Cum. 432.00
Rs.10.45 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 562.11
6 Boulder Lead 48.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or 48.00 9.00 Cum. 432.00
Rs.10.45 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 562.11
7 Steel Lead 19.00 Km.
Carriage by Mech. Tpt. 19.00 4.02 Tonne 76.38
Add for loading and unloading Tonne 237.96
Tonne 314.34
8 Hume Pipe Lead 80.00 Km.
Carriage by Mech. Tpt. 80.00 44.69 pipe 3575.20
Add for loading and unloading pipe 132.88
Pipe 3708.08
Rmt. 1483.23
9 Bitumen Lead 98.00Km. VG-10, RS-I, SS-I & MS.
(Dhanotu)
Carriage by Mech. Tpt. 98.00 4.02 Tonne 393.96
Add for loading and unloading Tonne 248.32
Tonne 642.28
10 Soil Lead 10.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 10.00 6.43 Cum. 64.30
6.43 per cum. Per Km.
Carriage by Mech. Tpt. Cum. 34.62
Cum. 98.92
11 GSB Average Lead 70.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 70.00 6.43 Cum. 450.10
6.43 per cum. Per Km.
Add for loading and unloading Cum. 34.62
Cum. 484.72

Executive Engineer,
B&R Division HP.PWD.,
Sr. No. Description of Item Length Rate Unit Amount
Joginder Nagar
Analysis of Carriage of Material
Name of Work:- Construction of Kas Patohlu road Km.0/0 to 5/0 under Regular PMGSY , Batch-I, 2017-18 Package
No. HP-08-173A.
Sr. No. Description of Item Length Rate Unit Amount
1 Cement Lead = 13.000 Km.
Carriage by Mech. Tpt. 13.00 4.02 Tonne 52.26
Add for loading and unloading Tonne 220.70
Tonne 272.96
2 Sand Lead = 122.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 122.00 6.43 Cum. 784.46
6.43 per cum. Per Km.
Add for loading and unloading Cum. 34.62
Cum. 819.08
3 Aggregate 40mm and above Lead 122.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 122.00 7.24 Cum. 883.28
7.24 per cum. Per Km.
Add for loading and unloading Cum. 60.00
Cum. 943.28
4 Aggregate below 40mm Lead 122.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 122.00 7.24 Cum. 883.28
7.24 per cum. Per Km.
Add for loading and unloading Cum. 60.00
Cum. 943.28
5 Cut Stone Lead 42.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or 42.00 10.45 Cum. 438.90
Rs.10.45 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 569.01
6 Boulder Lead 42.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or 42.00 10.45 Cum. 438.90
Rs.10.45 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 569.01
7 Steel Lead 13.00 Km.
Carriage by Mech. Tpt. 13.00 4.02 Tonne 52.26
Add for loading and unloading Tonne 237.96
Tonne 290.22
8 Hume Pipe Lead 74.00 Km.
Carriage by Mech. Tpt. 74.00 4.47 pipe 330.78
Carriage by Mech. Tpt. pipe 132.88
Pipe 463.66
Rmt. 185.46
9 Soil Lead 10.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 10.00 6.43 Cum. 64.30
6.43 per cum. Per Km.
Add for loading and unloading Cum. 34.62
Cum. 98.92
10 GSB Average Lead 70.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 70.00 6.43 Cum. 450.10
6.43 per cum. Per Km.
Add for loading and unloading Cum. 34.62
Cum. 484.72

Executive Engineer,
Sr. No. Description of Item Length Rate Unit Amount
B&R Division HP.PWD.,
Joginder Nagar
Analysis of Carriage of Material
Name of Work:- Construction of Gumma to Kharsa road Km.0/0 to 6/0 under PMGSY , Batch-II, 2017-18 Package
No. HP-08-308.
Sr. No. Description of Item Length Rate Unit Amount
1 Cement Lead = 13.000 Km.
Carriage by Mech. Tpt. 13.00 4.02 Tonne 52.26
Add for loading and unloading Tonne 220.70
Tonne 272.96
2 Sand Lead = 122.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 122.00 6.43 Cum. 784.46
6.43 per cum. Per Km.
Add for loading and unloading Cum. 34.62
Cum. 819.08
3 Aggregate 40mm and above Lead 122.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 122.00 7.24 Cum. 883.28
7.24 per cum. Per Km.
Add for loading and unloading Cum. 60.00
Cum. 943.28
4 Aggregate below 40mm Lead 122.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 122.00 7.24 Cum. 883.28
7.24 per cum. Per Km.
Add for loading and unloading Cum. 60.00
Cum. 943.28
5 Cut Stone Lead 42.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or 42.00 9.00 Cum. 378.00
Rs.9.00 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 508.11
6 Boulder Lead 42.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or 42.00 9.00 Cum. 378.00
Rs.9.00 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 508.11
7 Steel Lead 13.00 Km.
Carriage by Mech. Tpt. 13.00 4.02 Tonne 52.26
Add for loading and unloading Tonne 237.96
Tonne 290.22
8 Hume Pipe Lead 90.00 Km.
Carriage by Mech. Tpt. 90.00 4.47 pipe 402.30
Add for loading and unloading pipe 132.88
Pipe 535.18
Rmt. 214.07
9 Soil Lead 10.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 10.00 6.43 Cum. 64.30
6.43 per cum. Per Km.
Carriage by Mech. Tpt. Cum. 34.62
Cum. 98.92
10 GSB Average Lead 61.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 61.00 6.43 Cum. 392.23
6.43 per cum. Per Km.
Carriage by Mech. Tpt. Cum. 34.62
Cum. 426.85

Executive Engineer,
Sr. No. Description of Item Length Rate Unit Amount
B&R Division HP.PWD.,
Joginder Nagar
Analysis of Carriage of Material
Name of Work:- Up-gradation of Chauntra to Tikri Mushera road Km.0/0 to 1/770 under PMGSY , Batch-II, 2017-18
Package No. HP-08-229.
Sr. No. Description of Item Length Rate Unit Amount
1 Cement Lead = 10.000 Km.
Carriage by Mech. Tpt. 10.00 4.02 Tonne 40.20
Add for loading and unloading Tonne 220.70
Tonne 260.90
2 Sand Lead = 100.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 100.00 6.43 Cum. 643.00
6.43 per cum. Per Km.
Add for loading and unloading Cum. 34.62
Cum. 677.62
3 Aggregate 40mm and above Lead 100.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 100.00 7.24 Cum. 724.00
7.24 per cum. Per Km.
Add for loading and unloading Cum. 60.00
Cum. 784.00
4 Aggregate below 40mm Lead 100.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 100.00 7.24 Cum. 724.00
7.24 per cum. Per Km.
Add for loading and unloading Cum. 60.00
Cum. 784.00
5 Cut Stone Lead 20.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or 20.00 9.00 Cum. 180.00
Rs.9.00 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 310.11
6 Boulder Lead 20.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or 20.00 9.00 Cum. 180.00
Rs.9.00 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 310.11
7 Steel Lead 10.00 Km.
Carriage by Mech. Tpt. 10.00 4.02 Tonne 40.20
Add for loading and unloading Tonne 237.96
Tonne 278.16
8 Hume Pipe Lead 87.00 Km.
Carriage by Mech. Tpt. 87.00 4.47 pipe 388.89
Add for loading and unloading pipe 132.88
Pipe 521.77
Rmt. 208.71
9 Soil Lead 10.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 10.00 6.43 Cum. 64.30
6.43 per cum. Per Km.
Carriage by Mech. Tpt. Cum. 34.62
Cum. 98.92
9 Bitumen Lead 89.00Km. VG-10, RS-I, SS-I & MS.
(Dhanotu)
Carriage by Mech. Tpt. 89.00 4.02 Tonne 357.78
Add for loading and unloading Tonne 248.32
Tonne 606.10

Executive Engineer,
B&R Division HP.PWD.,
Sr. No. Description of Item Length Rate Unit Amount
Joginder Nagar
Analysis of Carriage of Material
Name of Work:- Upgradation of Balakrupi to Darat Bagla road Km. 0/0 to 5/0 under PMGSY Batch-II for the year
2017-18 Package No. HP – 08- 371.
Sr. No. Description of Item Length Rate Unit Amount
1 Cement Lead = 5.000 Km.
Carriage by Mech. Tpt. 5.00 4.02 Tonne 20.10
Add for loading and unloading Tonne 220.70
Tonne 240.80
2 Sand Lead = 113.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 113.00 6.43 Cum. 726.59
6.43 per cum. Per Km.
Add for loading and unloading Cum. 34.62
Cum. 761.21
3 Aggregate 40mm and above Lead 113.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 113.00 7.24 Cum. 818.12
7.24 per cum. Per Km.
Add for loading and unloading Cum. 60.00
Cum. 878.12
4 Aggregate below 40mm Lead 113.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 113.00 7.24 Cum. 818.12
7.24 per cum. Per Km.
Add for loading and unloading Cum. 60.00
Cum. 878.12
5 Cut Stone Lead 34.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or 34.00 9.00 Cum. 306.00
Rs.9.00 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 436.11
6 Boulder Lead 34.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or 34.00 9.00 Cum. 306.00
Rs.9.00 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 436.11
7 Steel Lead 5.00 Km.
Carriage by Mech. Tpt. 5.00 4.02 Tonne 20.10
Add for loading and unloading Tonne 237.96
Tonne 258.06
8 Hume Pipe Lead 78.00 Km.
Carriage by Mech. Tpt. 78.00 4.47 pipe 348.66
Add for loading and unloading pipe 132.88
Pipe 481.54
Rmt. 192.62
9 GSB Lead 53.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 53.00 6.43 Cum. 340.79
6.43 per cum. Per Km.
Carriage by Mech. Tpt. Cum. 34.62
Cum. 375.41
9 Bitumen Lead 89.00Km. VG-10, RS-I, SS-I & MS.
(Dhanotu) Lead 84.00 Km.
Carriage by Mech. Tpt. 84.00 4.02 Tonne 337.68
Add for loading and unloading Tonne 248.32
Tonne 586.00

Executive Engineer,
B&R Division HP.PWD.,
Sr. No. Description of Item Length Rate Unit Amount
Joginder Nagar
Analysis of Carriage of Material
Name of Work:- Upgradation of Drubbal to Banwar road Km. 0/0 to 8/600 under PMGSY Batch-II for the year 2017-
18 Package No. HP – 08- 312.
Sr. No. Description of Item Length Rate Unit Amount
1 Cement Lead = 34.000 Km.
Carriage by Mech. Tpt. 34.00 4.02 Tonne 136.68
Add for loading and unloading Tonne 220.70
Tonne 357.38
2 Sand Lead = 142.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 142.00 6.43 Cum. 913.06
6.43 per cum. Per Km.
Add for loading and unloading Cum. 34.62
Cum. 947.68
3 Aggregate 40mm and above Lead 142.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 142.00 7.24 Cum. 1028.08
7.24 per cum. Per Km.
Add for loading and unloading Cum. 60.00
Cum. 1088.08
4 Aggregate below 40mm Lead 142.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 142.00 7.24 Cum. 1028.08
7.24 per cum. Per Km.
Add for loading and unloading Cum. 60.00
Cum. 1088.08
5 Cut Stone Lead 63.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or 63.00 9.00 Cum. 567.00
Rs.9.00 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 697.11
6 Boulder Lead 63.00 Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or 63.00 9.00 Cum. 567.00
Rs.9.00 per cum. Per Km.
Add for loading and unloading Cum. 130.11
Cum. 697.11
7 Steel Lead 34.00 Km.
Carriage by Mech. Tpt. 34.00 4.02 Tonne 136.68
Add for loading and unloading Tonne 237.96
Tonne 374.64
8 Hume Pipe Lead 68.00 Km.
Carriage by Mech. Tpt. 68.00 4.47 pipe 303.96
Add for loading and unloading pipe 132.88
Pipe 436.84
Rmt. 174.74
9 GSB Lead 82.00Km.
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 82.00 6.43 Cum. 527.26
6.43 per cum. Per Km.
Carriage by Mech. Tpt. Cum. 34.62
Cum. 561.88
10 Bitumen Lead 113.00Km. VG-10, RS-I, SS-I & MS.
(Dhanotu) Lead 84.00 Km.
Carriage by Mech. Tpt. 113.00 4.02 Tonne 454.26
Add for loading and unloading Tonne 248.32
Tonne 702.58
11 Earth/Granular material Lead 10.00Km. (Av.)
Carriage by Mech. Tpt. Rs.4.02 per Tonne per Km. or Rs 10.00 6.43 Cum. 64.30
6.43 per cum. Per Km.
Carriage by Mech. Tpt. Cum. 34.62
Cum. 98.92

Executive Engineer,
B&R Division HP.PWD.,
Joginder Nagar