GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
PC-1 FORM
(PRODUCTION SECTORS)
0
3. Authorities Responsible for
i. Sponsoring Government of Sindh through Provincial ADP.
ii. Execution i. Secretary to Government of Sindh, livestock
and Fisheries Department, Karachi.
ii. Director General, livestock Sindh,
Hyderabad.
iii. Director Animal Husbandry Sindh
Hyderabad.
iv. Works and Services Department, Government
of Sindh.
iii. Operation and maintenance i. Director Animal Husbandry Sindh
Hyderabad.
1
ii. Provincial Buildings Department,
Government of Sindh, Tharparkar.
iv. Concerned federal ministry Ministry of Food Security and Research,
Islamabad.
In case of more than one agency, Capital Component by Works and Services
give their component0-wise Department, for construction of buildings.
responsibility. For provincial Revenue Component by Livestock and Fisheries
projects, name of the concerned Department, for registration of land and other
Federal Ministry be provided. items.
4 (a) Plan Provision
If the project is included in the
-
medium term / five year Plan,
specify actual allocation.
If not included in the current Plan, The Scheme included in ADP 2017-2018 with
what warrants its inclusion and allocation of Rs: 31.86 million
how is it now proposed to be
accommodated.
If the project is proposed to be
financed out of block provision, Not applicable
indicate:
5 Project objectives and its relationship Objective 1
with Sect-oral objectives Construction of Goat Bank in District Tharparkar
Activities.
Works and Services Department, Government of
Sindh.
Objective 2
Provision of livelihood facilities to 400 families of
4 taluka of district Tharparkar through livestock on
cost sharing basis.
Activities:
Advertisement for appointment of project staff.
Invitation tender for animal purchase.
Selection of staff.
Training of staff.
Survey conducted Taluka wise for selection of
poor peoples in each taluka through score card.
Meeting with selected poor peoples to brief
about project policies.
Objective 3
Provision of green grass, concentrate and health
services to the animals for intial 18 months to
reduce nutritional as well as medical burdon upon
400 families of 4 talukas of District tharparkar.
Activities:
2
Training of veterinary doctors and para vets.
Tender for medicine and instruments.
To distribute the above medicine and
instrument to the following staff.
Invitation tender for feed and green grass in
news paper.
Selection of firm.
Distribution of ration among peoples on
weekly basis.
3
the commodities which are being used in all the
group of age. Low quality of food item will affect
the population so with the help of improving social
status and general social conditions of the people of
District Tharparkar, we can also overcome the
health issues of our population.
Project Implementation:
The period of scheme is three years. During 1st year
of this period Goat Bank will be established. In this
regard land will be provided by the Livestock
farmers as free of cost and will be registered in
favor of Livestock Department.
Staff will be appointed through Contract Basis not
going to permanent.
Treatment and vaccination coverage in area of
Tharparkar will be increased and drenching to
control the parasitic diseases. Will also be
increased.
7 Capital cost estimates Civil cost estimate are based on approved schedule
Basis of determining the capital cost be of rates and estimates for other items based on
provided. It includes market survey, prevailing market rates.
schedule rates.
Provide year-wise estimation of physical Year-wise / component wise physical activities are
activities as per following. as under:
8 Annual operating Cost based on The items-wise annual operating cost will be as
proposed capacity utilization for 3 under:
years Sr.# Item Rupees in million
4
1 Purchase of Medicine 5.80
2 Purchase of Vaccine 3.40
3 Payment of utility
0.30
bills
4 Other Miscellaneous /
unforeseen 0.28
expenditure
Total 9.78
ii. Social benefits with indicators Project will improve the per animal productivity &
profitability resulting in improvement in the income
resources of livestock farmers and creating Job
opportunities, thereby improving the social status and
general social conditions.
iii. Environmental impact Project will result in increase in per animal
productivity & help in curtailing the number of
animals thus in controlling the stocking rates
resulting in land degradation.
12 Implementation schedule Starting date July 2017 and completion date 30th June
Indicate starting and completion date of 2020.
the project. During the 1st year of the project Goat Bank will be
established at a convenient location for keeping of
50% animals returned back from each beneficiaries.
For the construction land will be provided by the
farmers free of cost only registration fees will be paid
by the livestock department.
13 Management structure and manpower Project work will be administered / executed by the
requirements. livestock Department, Government of Sindh. The
Administrative arrangements for civil works will be administered / carried out by the
implementation of project. Building Department.
The manpower requirements by skills / Temporary staff will be appointed through Contract
profession during execution and basis.
operation of the project.
14 Additional projects/decisions required No Any
to maximize socio-economic
benefits from the proposed project
5
SUMMARY COST FOR THE SCHEME POVERTY ELIMINATION OF PEOPLE OF
THARPARKAR THROUGH LIVESTOCK
Sr. Total
Particulars 2017-18 2018-19 2019-20
No.
A. PAY OF OFFICERS
20.52
1. Pay of the Officers 3 6.84 6.84 6.84
20.52
6.84 6.84 6.84
6
C. RECURRING CONTINGENCIES
Recurring
3. - 2.15 6.3 6.3 14.75
Contingencies
Total Recurring
- 2.15 6.3 6.3 14.75
Contingencies
Non-Recurring
4. - 15.25 10.75 10 36
Contingencies
Total Non-Recurring
- 15.25 10.75 10 36
Contingencies
7
APPOINTMENT OF STAFF FOR THE SCHEME POVERTY ELIMINATION OF PEOPLE OF THARPARKAR
THROUGH LIVESTOCK
Sr.
Particulars 2017-18 2018-19 2019-20 Total
No.
PAY OF OFFICERS
Project
Director
(BPS-19) 1.2 1.2 1.2
(On Contract
1 Basis) 1 3.6
Deputy
Project
Director
0.84 0.84 0.84
(BPS-18)(On
Contract
2 Basis) 1 2.52
Veterinary
Officers
(BPS-17)(On 4.8 4.8 4.8
Contract
3 Basis) 8 14.4
A.
Total Pay of Officers 10 6.84 6.84 6.84 20.52
PAY OF OTHER STAFF
Stock
5.76 5.76 5.76
4 Assistant 16 17.28
5 Accountant 1 0.36 0.36 0.36 1.08
6 Clerk 1 0.24 0.24 0.24 0.72
7 Peon 2 0.36 0.36 0.36 1.08
8 Chowkidar 1 0.18 0.18 0.18 0.54
9 Driver 4 0.72 0.72 0.72 2.16
B. Total Pay of
7.62 7.62 7.62 22.86
Other Staf 25
Total Pay (A+B) 35 14.46 14.46 14.46 43.38
RECURRING AND NON RECURRING CONTINGENCIES FOR THE SCHEME POVERTY ELIMINATION OF
PEOPLE OF THARPARKAR THROUGH LIVESTOCK.
8
Sr.
Particulars Nos. 2017-18 2018-19 2019-20 Total
No.
1 Purchase of Vehicle 2 4 0 0 4
Purchase of Veterinary
5 Instruments 0.25 0 0 0.25
Purchase of
6 Refrigerators 2 0.15 0 0 0.15
Purchase of Water
7 Dispenser 2 0.08 0 0 0.08
Purchase of Photostat
8 Machine 1 0.2 0 0 0.2
Travelling / Daily
8 Allowances (TA/DA) 0.25 0.5 0.5 1.25
Printing and
9 Publication 0.35 0.6 0.6 1.55
10 Office Stationary 0.05 0.15 0.15 0.35
11 POL Charges 0.3 0.65 0.65 1.6
9
JUSTIFICATION FOR THE REQUIREMENTS
Cost
Sr.
Particulars (Million Justification
#
s)
Travelling / Daily Travelling & Daily Allowance charges will be required for disease
5. 2.250
Allowances (TA/DA) surveillance, control and vaccination & monitoring activities.
Printing and Printing and publication charges will be required for literature to create
6. 2.750
Publication awareness of farmers.
Stationary will be required for reporting and record keeping by the field
7. Office Stationary 0.650
staff, for which is the minimum requirement.
POL charges will be essentially required for vehicle for disease
8. POL Charges 2.900 surveillance, control and monitoring activities in the district for the
smooth working of the project.
10.80
9. Purchase of Medicines Medicine will be required for disease control and treatment.
0
10. Purchase of Vaccines 6.400 Vaccine will be required for preventive disease control.
Repair and
Repair and Maintenance of vehicles will be required during their use in
11. Maintenance of the 1.000
disease surveillance, control and vaccination activities.
Vehicles
Repair and
12. Maintenance of 0.600 Repair and maintenance of the furniture will be required for project office.
Furniture
Vehicle will be required for disease surveillance, monitoring and control
13. Purchase of Vehicle 4.000
in Sindh for Project Director and Deputy Project Director.
Computer along with laser printer will be required for word processing,
Purchase of Computer
14. 0.17 data analysis, statistical analysis and epidemiological survey required for
and Laser Printer
disease control and surveillance activities.
Purchase of Veterinary
16. 0.250 Veterinary instrument will be required for disease control and treatment.
Instruments
Purchase of Refrigerators will be required for safety of efficacy for Vaccines and
17. 0.150
Refrigerators Medicine.
Purchase of Water Water Dispenser will be required in the office of Project Direct and
18. 0.080
Dispenser Deputy Project Director.
Purchase of Photostat
19. 0.200 Photostat Machine will be required for office work.
Machine
20. Purchase of Generator 0.200 Generator will required for alternative energy in the office of the Project.
21. Purchase of Furniture 1.000 Furniture will be required for the office of the Project staff.
10
TENTATIVE LIST OF VACCINE
11
Office table and Chair of Accounts
6 13 Steel Cup Board
Assistant
7 Steel Almahari 14 Computer table
4 BD syringe 10 ml 14 Cotton
13
Activities under objective Reporting and pictorial Role of media will
I: presentation. be positive and it
Works and Services will be helpful in the
sense of spreading
Department, Government knowledge amongst
of Sindh. the communities
Activities Under Objective through news papers,
II: television programs
Advertisement for etc.
appointment of Elected member will
also play important
project staff.
role for the success
Invitation tender of project as they
for animal could donate money
purchase. and other resources.
Timely release of
Selection of staff.
funds.
Training of staff. The project is
Survey conducted smoothly executed.
Taluka wise for Budget disbursed as
selection of poor planned.
peoples in each
taluka through
score card.
Meeting with
selected poor
peoples to brief
about project
policies.
14
firm.
Distribution of
ration among
peoples on
weekly basis
15
15. Certificate
Certified that the project proposal has been prepared on the basis of
instructions issued by the Planning Commission for the preparation of
PC-I for Production Sector projects.
16