BILL OF MATERIALS

MATERIALS UNIT QUANTITY UNIT PRICE


Portland Cement 40kg Bags 954 220 209880
Sand m³ 53 650 34450
Gravel m³ 39 650 25350
Soil Poisoning Gal. 6 1000 6000
16mmØ x 6m RSB Pcs. 169 522 88218
12mmØ x 6m RSB Pcs. 67 372 24924
10mmØ x 6m RSB Pcs. 840 222 186480
#16 G.I. Tie wire Kg. 70 100 7000
5”x8”x16” CHB Pcs. 5090 10 50900
Prepainted long span m² 97 500 48500
Ridge rolls Pcs. 3 160 480
CW nail 2” Kg. 15 55 825
CW nail 3” Kg. 15 55 825
CW nail 4” Kg. 15 55 825
¼ x 2 x 2 angular bars Pcs. 12 1360 16320
¼ x 2 x 4 channel bars Pcs. 12 1620 19440
2 x 4 C-purlins Pcs. 32 1995 63840
Electrical works l.s. - 120000 120000
Plumbing works l.s. - 100000 100000
¼ x 4 x 8 plywood Pcs. 34 500 17000
Coco lumber Bdft. 710 22 15620
Painting works l.s. - 100000 100000
Wooden doors l.s. - 70000 70000
Roll-up doors Pcs. 2 50000 100000
Sliding doors l.s. - 40000 40000

MANPOWER NO. OF DAYS RATE


1 engineer 100 800/day 80000
1 foreman 100 500/day 50000
3 mason/carpenter 100 450/day 45000
5 labor 100 300/day 30000
TOTAL 1,551,877.00

Prepared by: Engr. Paul Cedrick M. Rea