Sunteți pe pagina 1din 12

Testing & Modeling of Generator Controls

G.R. Bérubé, L.M. Hajagos


Kestrel Power Engineering
Toronto, Ontario, Canada

INTRODUCTION Benefits

NERC planning standards approved in September 1997 Some of the benefits of modelling tests are listed below
have reiterated the need for accurate and timely model data
for the transmission system and connected equipment. The • To accurately determine the reliability of the system
data requirement includes steady-state and dynamic models, through operating security limit studies
and covers control system small-signal performance and • To plan equipment outages and required enhancements
limits. through accurate estimates of active and reactive
margins
GENERATION EQUIPMENT MODELLING DATA • To identify and correct control instability problems
REQUIREMENTS • To identify and correct equipment problems

The subject of this paper is the generating unit and its TESTING EXPERIENCE
controls. The applicable NERC requirements from Sections
IIA and IIB of the Planning Standards are summarized Kestrel Power Engineering has routinely performed all of
below. the recommended tests on units ranging in size from 2 to
1200 MVA. We perform acceptance and tuning tests and
Steady-State Data modelling of exciters, power system stabilizers and limiters.
Generators are tested to derive model parameters and to
• Generator minimum and maximum ratings (net real and establish their reactive capability. We have also performed
reactive power), regulated bus and voltage set-point tests and coordinated tuning of multiple governors in
• Station service and auxiliary loads islanded conditions.

Dynamic Data Much of our testing and modelling effort takes place during
the commissioning phase of new or retrofit equipment.
• Unit-specific dynamic data for generators, excitation Control performance and validation is routinely specified as
systems, voltage regulators, turbine-governor systems and part of any equipment modification. Regular re-verification
power system stabilizers has not been a priority in the past, although routine tests
have been incorporated into regular scheduled outages.
Testing Requirements
A number of problems in recent years have forced us to re-
• Generator reactive limits shall be periodically reviewed visit generator control performance and settings. In cases
and field tested to ensure that reported var limits are where we have tested controls to analyze and avoid system
attainable disturbances we have found numerous changes to the model
• Dynamic modelling data shall be field verified through parameters: equipment parameters have been altered from
testing their reported settings, latent uncorrected defects have been
• Dynamic field testing shall include voltage regulators, discovered, and system changes have occurred without
speed/load governor controls, excitation systems, power corresponding alteration of tunable controls.
system stabilizers and other devices if applicable
• Test shall ensure coordination of generator controls The attached paper describes some of the issues and our
(minimum and maximum excitation limiters) with experiences in performing testing and modelling on the
generator short-term capability and protective relays North American bulk electricity system. An attachment
• Tests are required at least every 5 years provides some examples of actual results obtained using the
• Unit-specific data is required for all generators greater described test procedures. These tests were performed on
than 50 MVA or installed after 1990 behalf of utility clients wishing to meet the recent WSCC
modelling requirements.

1
Testing & Modeling of Generator Controls
G.R. Bérubé, L.M. Hajagos
Kestrel Power Engineering
Toronto, Ontario, Canada

INTRODUCTION
Power System Generation Dispatch includes automatic
The testing and modeling of generators, and their associated generation control systems (AGC) for the maintenance of
controls, is a complex topic. This is in part because of the overall system frequency and tie-line interchanges and
variety of different generators and controls found on a manual operator controls such as economic dispatch.
practical power system, and the manner in which they
interact during normal and abnormal power system Prime Mover Energy Supply System for fossil-fired units
operating conditions. There is a consensus within the (shown) includes fuel supply and boiler control loops, while
industry that the development of accurate models for for hydroelectric machines, penstock and conduit systems
generator control systems is a key step in establishing will participate in the dynamic behaviour.
operating-security limits and in simulating and
understanding the operation of the system during Turbine Controls include the governor (speed control
disturbances. loop) as well as supplementary controls which are active
during full or partial load rejections.
The most common objectives of utilities embarking on
systematic test programs, to establish models of their Excitation System includes the amplification stage(s),
facilities, include: automatic voltage regulator (AVR) function, excitation
limiters and supplementary controls such as power system
• Simulate system or local disturbances, to compare with stabilizers (PSS), and outer control loops (e.g. power factor
measured data or reconstruction of actual events and or reactive power regulators).
derive remedial actions
• Simulate system disturbances in the planning or operating Included within these control loops are the turbine and
time frame to establish secure operating limits and assess synchronous generator. Clearly, the modelling of these
alternative plans components can have a significant impact on the accuracy
• Coordinate existing or new protection and control systems of the representation of each of the major control loops.
• Study the addition of new facilities
While not explicitly shown in Figure 1, plant auxiliaries and
Regardless of the reason for testing, the first step should be large system loads may require detailed modeling,
a thorough needs analysis. The needs analysis identifies the especially for conditions involving large variations in
utility’s requirements and translates them into specific system frequency and voltage /2/.
criteria: location of critical stations, list of critical units, list
of critical components (e.g. generator, excitation system, The need to represent each of these components and control
governor…), type of models and data to be collected, and loops, and the type of model required, is established by
finally, types of tests to be performed. determining the type of simulations which are to be
performed, and the types of operating conditions to be
This paper describes some of the issues in performing a represented.
needs analysis, and our experience in performing testing and
modelling in North America and worldwide. MATCHING MODELS TO REQUIREMENTS

GENERATING UNIT CONTROLS A critical stage, which is often overlooked, is a Needs


Analysis. The needs analysis identifies the utility’s
Figure 1 provides an overview of the turbine-generator requirements and translates them into the information
control loops for a typical fossil-fired unit. These controls required to proceed with testing and modelling. The various
allow the power system to meet the continually changing stages are described below.
customer load requirements by adjusting the active and
reactive outputs of the generators. Briefly, the major
control loops are:

2
Figure 1: Turbine-Generator Control Loops

Define the Need


A prioritized list of stations and units can usually be
The first step is to define why the tests and models are compiled from a quick review of a past system event or a
required. Some questions that must be answered are: forecast operating condition.

• Is the sole purpose of performing the tests to develop Define the Equipment Modelling Requirements
simulation models?
• Are the tests intended to reproduce disturbance conditions In order to determine which pieces of equipment must be
in order to identify deficiencies and improper modelled in detail, the type of simulations that will be
coordination of limiters and controls? performed must be defined. This involves establishing the
• Will the models be used to produce recommendations for time frame and the system conditions that are to be
changes to equipment settings? simulated (e.g. interconnected and/or islanded operation).
The latter is often specified as a range of voltages and
Once these questions have been answered, the modeling frequencies for which the models must be valid.
requirements may be identified.
Table 1 provides example guidelines for equipment to be
Select Location(s) modelled for different purposes. These are only guidelines;
location-specific details should be combined with the study
This is often the simplest stage, and involves considering objectives to arrive at a final decision. The entries can be
the following factors: interpreted as follows: “Y” indicates dynamic model
normally included, “N” normally not included, “?” may be
• Was a station or specific unit a critical participant in a included depending on the specific conditions and
system event? simulation goals.
• Did the station, or specific equipment, exhibit unexpected
behaviour during the system event?
• Is existing dynamic data available at a station?
• Is the available data supported by previous tests and
measurements or well-documented manufacturer’s data
sheets?

3
The following are definitions of the study types used in significant nonlinearities, such as saturation and limits.
Table 1 (typical bounds on study time scales for each Linearized representations may be derived from the large-
phenomenon are indicated in parentheses): signal models, often within the simulation software used in
the studies without intervention by the user.
SSR subsynchronous resonant interaction between
synchronous machines and transmission system elements Normally, the models are developed to match industry-
and controls. (< 1s) accepted standards /5,6,7/. In some cases more complex
Transient large disturbance, first-swing rotor-angle models are developed; these are usually used for unusual
stability(< 10 s) equipment or when a direct correspondence is required
Small-Signal linearized analysis of oscillatory modes between the model parameters and the settings of the
associated with rotor electromechanical oscillations and physical system. Figure 2 provides a portion of an overview
control system modes(<20 s or eigenvalue) block diagram of an excitation system in which external
Islanded Operation operation of isolated portions of the components are identified for each module. One of the
system; large frequency and voltage excursions (10 s to a blocks, the damping feedback circuit shows the relationship
few minutes) between the external settings and transfer function
Long-Term Dynamics slow dynamics associated with constants. The transfer functions and defining equations for
operation following widespread disturbances (minutes) /3/ each of the blocks is developed in a similar manner to
Voltage analysis of voltage stability for large and small include gains, time constants and limits in terms of the
disturbances (all time frames are possible, depending on physical components and available settings (e.g.
type of phenomenon) potentiometer settings, resistor values, jumper positions).

Table 1: Equipment Modelling Requirements The advantage of this type of


STUDY TYPE model is that it allows the results
EQUIPMENT SSR Transient Small- Islanded Long-Term Voltage of studies to be translated into
Signal Operation Dynamics recommended changes which can
Generator Y Y Y Y Y Y be implemented in the field to
Shaft System Y N ? N N N obtain performance
Excitation Systems improvements, and the variables
AVR ? Y Y Y Y Y are represented in engineering
Stabilizer ? Y Y ? ? Y
units (e.g. V, A,…) which can be
Limiters N ? N ? Y Y
compared directly with measured
PF/VAR N N N ? Y Y
results /8/.
Turbine Controls
Speed Governor N N ? Y Y N
Overspeed N N N Y Y N
The disadvantage of this structure
Controls is that the models are complex,
AGC N N N N ? N manufacturer-specific and are not
Prime Mover N N N ? Y N in a standard format that can be
Loads N N ? Y Y Y used in commercial simulation
software. Therefore, the detailed
models are often used as a starting point for developing
There is obviously overlap in these selected study types, as standard non-linear or linear models. Figure 3 is an
certain simulations will address multiple categories example of one such model, IEEE Standard AC1A /5/,
simultaneously. One row has been added for loads; representing an alternator-rectifier excitation system with
although they are not part of the generator control systems, non-controlled rectifiers.
inclusion of accurate load models is often critical to the
success of detailed simulations /4/. For many studies this kind of representation, the exciter
power stage and AVR control, will be adequate, while for
Select Model Structures other studies the excitation limiters or supplementary
controls must be added to reproduce the unit’s behaviour
The types of models and tests required are a function of the /9/. While industry standards also provide guidance for
intended application. For small-signal studies, linearized modeling these features, there tends to be a higher level of
representations are adequate. For transient or other large customization, often requiring user-defined representations.
disturbance studies, the models must explicitly include all

4
Figure 2: Overview of Block Diagram of Exciter Including External Settings

Vs VAMAX
limiters VRMAX
+
- 1 + s TC KA VR 1 VE Efd
Vc GATE +
X
+ 1 + s TB 1 + s TA s TE
- -
FEX
0
Vref VAMIN VRMIN
FEX=f[IN]
VX = VE SE[VE]

+
+
KE KCIFD
IN =
VE

s KF +
+
KD Ifd
1 + s TF VFE

Figure 3: Excitation System Model Type AC1A

TESTING METHODOLOGY validation. The following is a brief description of the steps


which can be included in this process /10/. Not all of these
Once the locations and level of modeling detail have been steps are required for each location and each piece of
selected, the model parameters must be determined. Field equipment.
testing is normally part of the model development and

5
Step 1 - Review available data: Collect data from the In order to perform tests on a wide variety of equipment
station and from the manufacturer of the equipment. This designs, specialized test instrumentation is required. Over
includes operating manuals, diagrams, capability and rating the years custom transducers have been developed for
data, previous test results, and, where available, block measuring all of the quantities associated with generators,
diagrams. This stage often provides a significant amount of excitation systems and governors (e.g. active/reactive
information reducing the amount of site testing required. powers, field voltages and currents, shaft speed, frequency,
valve positions…). These transducers and associated
Step 2 - Select model structures: Based on the available instrumentation differ from multi-purpose hardware in that
data, develop a block diagram of the equipment to be they have been specifically designed for the bandwidth,
modeled. This often involves selecting the standard model isolation and accuracy requirements of these dynamic tests.
that is the best fit to the equipment.
In order to support different client requirements, we utilize
Step 3 -Develop test plan: The test plan should include most of the common commercially-available power system
measurements to identify all of the key parameters, and and control simulation packages, along with several custom-
provide additional data for validating the final product - the designed tools. This allows us to develop and test models
completed model. The plan should clearly identify any on different target platforms.
special equipment requirements, the station/unit operating
state during each phase, and the safety/reliability issues. EXAMPLE RESULTS AND CASE STUDIES

Step 4 - Perform site tests: Included in the actual testing Generator Testing
should be a review of nameplate data and any equipment
modifications and a comparison to the manufacturer’s data In many cases, utilities rely on manufacturer-supplied data
gathered earlier. In our experience, it is not uncommon to in impedance and time-constant form. Depending on the
find differences between field wiring, installed component manufacturer, this data may be measured through enhanced
values, equipment settings and documentation. The short-circuit and stator decrement tests, or derived from
functional and dynamic tests also frequently identify latent numerical analysis of design data /12/. Our experience has
deficiencies, such as defective components or incorrect been that there can be significant differences between the
settings. These may not be apparent during typical day-to- parameters provided by manufacturers and those obtained
day operation. through direct measurement. The tests we have performed
range from simple static and open-circuit measurements to
Step 5 - Validate data: Compare measured and modeled sophisticated standstill and on-line frequency response tests
responses for modules and/or complete system. In order to /13/.
expedite this stage we have developed data acquisition
systems which format the data for use with our simulation Figure 4 provides a comparison of the quadrature-axis
software. Whenever possible parameters are calculated on- operational inductance of a round-rotor generator obtained
site and compared with test results. This provides an through standstill frequency response tests and data
opportunity to identify inconsistencies or missing data, provided by the manufacturer. Detailed impedance and time
which can then be rectified prior to removing the test constant values may be derived from SSFR data.
equipment.

Step 6 - Produce reduced-order model: Eliminate


feedback loops, time constants and limits not relevant to the
target model. Convert all parameters to per-unit values for
use within simulation software.

Step 7 - Train station staff: This step is not always


included as part of the process, but it is actually critical to
ensuring that the relationship between the derived model
and equipment settings is maintained. Ideally, station staff
should be provided with enough training to periodically test
the unit and confirm that its dynamic performance has not
changed significantly. Regular courses are offered, and test
facilities have been added to most excitation systems and
stabilizers to permit verification of the closed-loop voltage
regulator and PSS response /11/. Figure 4: Comparison of SSFR and Manufacturer Data
for Thermal Generator

6
Although the models derived through detailed tests can be valid for a variety of operating conditions. Regardless of
significantly different, one of the conclusions of /13/ is that, the technique applied, the final step should include
for modern generators, there is not always a significant validating the model, by comparing simulated time-domain
improvement in the accuracy of simulations when compared results against measured field data.
with those conducted using manufacturer’s data. In fact,
our experience has been that the accuracy of the excitation
system models is often far more significant in determining
the outcome of most simulations. Once accurate exciter and
governor models are available, then improving the generator
representation can provide incremental improvement, where
special controls are being simulated or tuned.

Excitation System Modelling

It has been our experience that generator excitation system


settings and performance can have a dramatic effect on the
overall behaviour of individual units and the power system
as a whole. Some form of excitation system model is
required in virtually every type of power system simulation.
Our approach has been to maximize transmission capability
through the use of high-initial-response (HIR) excitation
systems and supplementary controls such as power system
stabilizers (PSS) and transient excitation controls (TSEC).
Consequently, we test all excitation systems and derive Figure 5: Comparison of Measured and Simulated
detailed large-signal models for inclusion in the system Response for Alternator-Rectifier Excitation System
dynamic database.
Figure 5 provides an example comparison between
Excitation system tests are normally performed in one, or simulated and measured data for a generator equipped with
more, of the following operating conditions: an alternator-rectifier excitation system.

• excitation system energized via test supplies and isolated Thermal Governor Modelling
from the generator field winding. These tests are often
scheduled during routine maintenance outages, and Detailed thermal governor models are normally only
provide an opportunity to obtain detailed measurements of developed when simulation of partial/full load rejections are
the transfer functions of the various sub-assemblies (e.g. required. Reference /2/ describes simulations performed to
AVR, UEL, PSS, …) understand the nature of a failed load rejection test on a
• generator on open circuit at rated speed. The excitation nuclear unit. The failure was a result of large induction
system is operated in its normal configuration and motors stalling, causing protective relays to operate. Potential
generator excitation and field voltage are adjusted to remedial measures were simulated and a final solution, using
various levels. This provides an opportunity to measure a temporary voltage boost on the AVR, adopted and
closed-loop response and test the various power stages implemented to prevent further failures.
under normal and forcing conditions.
• generator synchronized to the grid, operating at a variety Simulations were conducted to answer the following
of active and reactive power loads. These tests provide an questions:
opportunity to test excitation limiters, and supplementary
controls (e.g. PSS, VAR regulator) under realistic • Under the conditions of the test, do the pump motors stall?
operating conditions. • Are the initial generator conditions important?
• Is the sustained overspeed important?
A wide variety of testing techniques have been developed • Is the distribution of the motors loads significant?
for determining the model parameters. In general, they all • Does the performance of the AVR play a significant role?
involve performing measurements of the time or frequency
response of the system, and comparing the result against The simulations also allowed different remedial measures to
simulated responses calculated using different model be studied, thereby eliminating costly re-testing on the unit. In
parameters. Various system identification techniques are order to simulate the generator speed and motor stalling,
available for extracting the model parameters directly from detailed generator, governor and load models were required.
overall test results /14/. Some caution must be used when
interpreting results from overall tests to ensure that they are

7
The generator was represented with the usual power system from bus C/D (feeding 7 motors) are shown at the top of the
stability model having two damper windings on the graph with generator speed. The simulation shows that the
quadrature axis and one on the direct axis, using accurate PHT pump motors on the more heavily-loaded transformer
reactances and time-constants parameters. secondary are unable to track the generator speed. The high
motor current lowers the motors' terminal voltage sufficiently
The excitation system consists of a main rotating exciter and to cause their speed to start to reduce after 1 s, i.e. the motors
twin digital AVRs, each with a power system stabilizer (PSS). stall. The duration of the high inrush current eventually causes
It was represented by a continuous equivalent IEEE standard the operation of the bus protective relays.
model /5/.
Simulation results, and past experience, demonstrated that if
A governor model which represented the control and the generator terminal voltage could rapidly be increased to
intercept valve action and the overspeed controls was used. In over 1.05 per unit for several seconds following a full load
particular, the shaft acceleration detector controls were rejection, the motor stalling problem could be overcome. The
modelled as shown in /2/. This control acts to close the necessary logic to activate a terminal voltage boost signal was
intercept valves for 5 seconds following detection of shaft obtained from the very flexible logic already present in the
acceleration greater than 4.5%/s /15/. The governor load set- digital excitation system. This solution was subsequently
point runback at 10%/s following detection of full load implemented without exhaustive testing because of the
rejection was also explicitly modelled. Governor parameters fidelity of the computer models.
were adjusted to produce a speed signal that closely matched
the measured results. This non-standard model was Hydro Governor Modeling
implemented within the user-defined capabilities of the time-
domain simulation program. Detailed hydro governor models are normally only included
in simulations intended to reproduce long-term dynamics
The station auxiliary service load consists of large induction and system operation during which large frequency
motors driving pumps, the generator excitation system, lights, deviations occur, such as islanded operation. The structure
and other smaller loads. The most important motors are those of the local bulk electricity system includes numerous
driving the Primary Heat Transport (PHT) pumps. pockets of hydroelectric generation, which are connected to
the remainder of the system via limited transmission
Each type of motor was modelled as a detailed induction connections. As a result, we have performed measurements
motor having a deep bar rotor, and with saturation of the and simulations of islanded operation on several occasions,
stator and rotor leakage reactances represented /1/. The model and have developed standard procedures for tuning for
parameters were obtained by converting from the standard optimal damping /16/.
specifications supplied by the motor manufacturer using
commercial software. The approach taken for hydro governor testing is similar to
that used for excitation system testing, although additional
specialized test equipment is required to introduce test
inputs and measure the intermediate and output quantities.
With the advent of electro-hydraulic governors, which
employ analog and digital regulators, the need for
specialized hardware has been reduced, as all critical
quantities are converted to electrical form.

Figure 7 shows a comparison of the measured and simulated


response of a hydro-governor during islanded operation.
Clearly, the model developed for the PI governor, provides
an excellent tool for studying the performance of the unit
during isolated operation.

Figure 6. Simulation of Failed Load Rejection Test

The simulation of the unsuccessful load rejection test is


shown in Fig. 6. The shaft speed of one of the Primary Heat
Transport pumps from bus A/B (feeding 5 motors) and one

8
3. Long-Term Power System Dynamics, EPRI Report EL-6627,
Final Report of Project 2473-22, Ontario Hydro, December, 1989.
4. L. Hajagos, B. Danai, Laboratory Measurement of Modern
Loads Subjected to Large Voltage Changes for Use in Voltage
Stability Studies, CEA project 113T1040, final report, May 1996.
5. IEEE Recommended Practice for Excitation System Models
for Power System Stability Studies, IEEE Standard 421.5-1992.
6. Hydraulic Turbine and Turbine Control Models for System
Dynamic Studies, IEEE Working Group Report, IEEE Trans., Vol.
PWRS-7, No. 1, pp. 167-179, Feb 1992.
7. Dynamic Models for Steam and Hydro Turbines in Power
System Studies, IEEE Trans., Vol. PAS-92, Nov/Dec 1973.
8. K. Shah, G.R. Bérubé, R.E. Beaulieu, Testing and Modelling of
the Union Electric Generator Excitation Systems, presented at the
1995 Missouri Valley Electrical Association meeting in Kansas City,
MO, April, 1995.
Figure 7. Governor Response - Islanded Operation 9. G.R. Bérubé, L.M. Hajagos, R.E. Beaulieu, A Utility
Perspective on Underexcitation Limiters, IEEE Transactions on
Energy Conversion, Vol 10, No 3, September 1995.
10. IEEE Guide for Identification, Testing and Evaluation of the
CONCLUSIONS & RECOMMENDATIONS Dynamic Performance of Excitation Control Systems, IEEE
Standard 421.2-1990.
Our experience has been that the most critical models for 11. G.R. Bérubé, L.M. Hajagos, Utility Experience with Digital
system stability limit studies are those of the exciter and Excitation Systems, IEEE PES Winter Meeting, Feb 1997, NY.
associated controls, such as power system stabilizers. Up- 12. IEEE Guide: Test Procedures for Synchronous Machines,
to-date manufacturer’s data, confirmed with spot IEEE Standard 115-1995.
measurements usually provides adequate representation of 13. J. Service, L.M. Hajagos, Practical Aspects of On-Load
Generator Testing, EPRI TR-102351, Project 2328-02, Final
generators. Governor models are required for islanded
Report, May 1993.
operation studies or for simulation of plant dynamics, such 14. T. Guo et al, Identification of Model Parameters of Excitation
as load rejections. Induction motor and nonlinear load System and Power System Stabilizer of Mingtan #6 via Finalization
models may be required for specific event reconstruction. Field Tests, paper 94-SM-566-0-PWRS presented at IEEE/PES
Representation of over- and under-excitation limiters, 1994 Meeting.
voltage and volts/Hertz limiters and power factor/var 15. P. Kundur, D.C. Lee, J.P. Bayne and P.L. Dandeno, Impact
controllers may be required for detailed simulations; in of Turbine Generator Overspeed Controls on Unit Performance
addition, site tests provide an opportunity to confirm Under System Disturbance Conditions, IEEE Trans. on PAS, June
settings for adherence to contractual agreements for 1985, Vol PAS_104, No. 6.
16. P.L. Dandeno, P. Kundur, J.P. Bayne, Hydraulic Unit Dynamic
available reactive support
Performance under Normal and Islanding Conditions - Analysis
and Validation, IEEE Trans., Vol. PAS-97, Nov/Dec 1978.
Prior to embarking on a test program, the utility should 17. Rowen, W.I Simplified Mathematical Representations of
complete a “needs analysis” to define exactly what the Heavy-Duty Gas Turbines, Journal of Engineering for Power,
results will be used for or describe the problem which has October 1983, Vol 105, p865.
initiated the requirement for testing and modelling. Once
this has been done, determine what pieces of equipment G. Roger Bérubé graduated from McGill University in Montréal,
should be tested at what locations. Select the types of tests Canada, with a B.Eng. and M.Eng. in electrical engineering in 1981
based on the types of models required. Produce a test plan and 1982 respectively. Since 1986, he has worked mainly on the
for the location based on combining the standard tests and modeling, testing and development of excitation and governor
location-specific details. As much as possible, validate the controls for synchronous generators. He is a registered Professional
Engineer in the Province of Ontario and a member of the IEEE PES.
models on-site, and train staff to collect appropriate data for
E-mail: roger@kestrelpower.com ph:(416)767-7704
future performance review. Finally, the testing methodology
should conform to the utility’s normal operating and Les M. Hajagos received his B.A.Sc. in 1985 and his M.A.Sc. in
maintenance practices. 1987 from the University of Toronto. Since 1988 he has worked
mainly in the analysis, design, testing and modelling of generator,
REFERENCES turbine and power system control equipment and power system
loads. He is a registered Professional Engineer in the Province of
1. Extended Transient Midterm Stability Program: Version 3.0, Ontario and an active member of the IEEE PES. E-mail:
EPRI TR-102004, Ontario Hydro, Project 1208-9, April 1993. les@kestrelpower.com ph:(905) 272-2191
2. G. Rogers, R.E. Beaulieu, L.M. Hajagos Performance of
Station Service Induction Motors Following Full Load Rejection of
a Nuclear Generating Unit, IEEE Transactions on Power Systems,
Vol 10, No 3, August 1995.

9
APPENDIX A: WSCC TESTING EXPERIENCE
40

Out Overexcited
The following examples are drawn from our recent testing
experience in the WSCC system and elsewhere.

Generator Testing 30

Generator parameters may be confirmed with some straight-


forward static and dynamic tests. The open-circuit 20
saturation curve should be measured and compared with the ROTOR LIMIT 1140 A
manufacturer’s measurements as shown in Figure 8.

Reactive Power (MVAr)


10
16
Active Power(MW)
14 0
0 10 20 30 40 50
12
-10
Terminal (kV)

10

8
In Underexcited -20
6
Air gap field current UEL LIMITER
@ 13.8 kV = 560 Adc
4 -30
measured points
fitted curve
2 LOE RELAY
-40
0
0 200 400 600 800 1000
Figure 9. Capability Curve
Field Current (Adc) 1.00
simulated
Terminal V

Figure 8. Open Circuit Saturation Curve 0.95


measured
(pu)

0.90
Static measurements of field current, terminal voltage,
active and reactive power, and rotor angle allow the 0.85
calculation of d- and q-axis and leakage reactances. During 0.80
these tests, the capability curve may be verified, and limits
such as field current, bus voltage, under-excitation limiter or 140
loss of field relay identified (Figure 9). 135
(Vdc)
Field

Two load rejection tests have been used to verify transient 130
parameters. A zero power factor test with excitation on 125
manual, shown in Figure 10, allows d-axis parameters to be
120
fitted to terminal voltage and field current response.
465
A partial load rejection test, as in Figure 11, allows
450
confirmation of generator inertia, and is also useful in
(Adc)

435
Field

analyzing off-line governor performance.


420
405
390
0 5 10 15

Time (seconds)
Figure 10. 0 pf Load Rejection Test

10
filters, gain, and phase lead-lag stages are measured with the
60
Power (%) stabilizer off-line. The stabilizer tuning requirement may be
determined using an on-line frequency response test, shown
40
in Figure 12.
20
The desired stabilizer gain and phase lead were
0 implemented and on-line step responses with the stabilizer
on and off, shown in Figure 13, were used to demonstrate
140 the results.
130
Speed (%)

1.00

Active Power
120

(pu)
0.95
110
100 0.90
90
initial slope with inertia 2.55 MW-s/MVA 1.04
60
Gate Pos'n (%)

Terminal V
(pu)
cushioning rate = -0.8 %/s 1.03
40
closing rate -6%/s PSS ON
PSS OFF
20 1.02

0 0.0010
0 10 20 30 40
delta speed
(pu) 0.0005
0
Time (seconds)
-0.0005
Figure11. Partial Load Rejection Test
-0.0010

0.005
150
PSS Output

stabilizer phase compensation 0


Tw = 10 s, Tlead = 0.18 s, Tlag = 0.05 s
(pu)

measured phase lead requirement


-0.005

-0.010
0 1 2 3 4 5
100
Phase (degrees)

Time (seconds)

Figure 13. Power System Stabilizer Test

Electro-Hydraulic Governor Testing

50 Electronic governors may be tested in the same way as


analog electronic exciters, with a combination of time- and
frequency-response tests. Static measurements are used to
establish the permanent droop and turbine operating curve
(gate or fuel flow versus power output). Step tests, shown in
Figure 14, may be used to confirm PID gain parameters.
0
0.1 0.2 0.5 1 2 5 Gas Turbine Governor Modeling
Frequency (Hz)
The advent of gas turbines and co-generation has created a
Figure 12. Stabilizer Phase Lead Requirement new class of facility, which is becoming widespread as the
choice for new construction. A simplified simulation model
Power System Stabilizer Tuning and Testing of a single-shaft gas turbine is presented in /17/.

Power system stabilizer testing and tuning is performed The controls are typically analog-electronic or digital
using a combination of off-line and on-line time- and electronic. In both cases, step-response tests and steady-
frequency-domain tests. Transfer functions of the input state measurements have been successfully used to

11
characterize both the turbine and governor (Figure 16). Gas Turbine Governor
Instrumenting and performing dynamic tests on digital Off-Line Reference Step Response
versions presents more of a challenge. However, even if the 1.5
manufacturer has not provided built-in test facilities, 1.0

speed
dynamic response tests can usually be performed with some

(%)
0.5 measured
guidance from the manufacturer. The testing environment simulated
0
(typically the plant control room) is decidedly more
-0.5
attractive.
1.0
2
0

Pos'n (pu)
Prop

simulated
(V)

Valve
-2 0.5
-4 measured
-6
8 0
6
(V)
Int

4 600
2

(deg F)
0

Temp
575
2
1
Deriv
(V)

0 550
-1
-2 0.2

Demand (pu)
3
Power

Valve
(MW)

2 0
1
0 -0.2
0.5 0 10 20 30 40
0.4
Gate

Time (seconds)
(pu)

0.3
0.2 Figure 16. Gas Turbine Governor Response
0.1
0
0.8
0.6 CONCLUSIONS
Lvdt
(pu)

0.4
0.2
0 The preceding paper and case studies are intended to
0 5 10 15 illustrate that models, test techniques, and control guidelines
are available to meet the NERC testing and modelling
Time (seconds) recommendations. The equipment models shown have been
Figure 14. PID PID Governor On-Line Response drawn from IEEE standards and are widely available in
power system simulation programs.
Standards for control tuning for such equipment have not
yet evolved, so reporting a model, rather than tuning is the G. Roger Bérubé
primary test objective. It should be noted that the model Senior Engineer
shown includes several control modes: droop control (the Kestrel Power Engineering
familiar mode for partial load conditions), acceleration Ph: (416) 767-7704
control (for startup and maneuvering), and temperature E-mail: roger@kestrelpower.com
control. For economic reasons, these units are invariably
loaded to near full output, and are controlled to respect Les M. Hajagos
temperature, pressure and emission constraints. In this Senior Engineer
mode, the speed/load droop control is not active. As these Kestrel Power Engineering
facilities may represent a significant portion of the total Ph: (905) 272-2191
generation in an area, control guidelines will need to be E-mail: les@kestrelpower.com
developed to correctly model their governor performance.

12

S-ar putea să vă placă și