Documente Academic
Documente Profesional
Documente Cultură
Design and Building of St. Sebastian North Lock Gates and Pumping Station
Contract No: MCUDP/SLLRDC/W/12
Feb-19 MCUDP/NLGPS/D/DOC/S/003 – A1
Item Employer’s Comments Contractor’s Reply Note to the Revisions
No. (Ref. No. DH-KOR-MCUDP-LKA-
170904-790 dated 31st Jan. 2019)
c Considering above issues, Please The relevant recommendations with the Clarified. The supplier was
provide combigrid manufacture properties of the material have already informed to provide if there
confirmation with backup analysis to are any additional details.
Page 1 of 3
verify the sufficiency of proposed been submitted with the proposal of
treatment method for bearing capacity reinforced earthwork.
and settlement of the walls in order to
keep them in allowable range.
d We are aware that the bearing pressure Clarified.
It is recommended to use a wall toe can be brought down to the allowable
with 0.75m length in RW06 in order to range by doing this but it is not allowed
reduce the foundation bottom pressure to extend the foundation to a land which
around 75KPa. is not possessive. However, it can be
considered case wise during the
construction as we are very much aware
the benefit of that.
2 The suitable joint type has already been Refer the revised note at the
Water tight method for the wall joints agreed at the site and it will be 20mm connection detail.
with PVC water stops should be noted thick expandable polystyrene sheet with
in drawing for RW06, RW06a and suitable sealing. The relevant note will be
others. updated for all the retaining walls
accordingly.
9 Agreed and the relevant coating has been Refer the revised note in the
As you are going to use sheet pile specified in the final drawing. sheet pile detail.
members (class FSP IIIA) for
permanent application in upstream
side and considering their marginal
calculated bending moment capacity
comparing with applied loads, you are
requested to propose suitable coating
method in order to provide enough
corrosion resistance for whole life
cycle of the project.
Page 3 of 3
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
This report is an addendum to the original design report MCUDP/NLGPS/D/DOC/S/003 - R2. The
report provides additional design claculations for the revised proposals to fulfill the client's instructions
received via PMU/MCUDP/NLPS/2018/W/12/04-b and 04-b II. As shown in section 3 of the report the
additional calculations includes here for sheet pile retaining wall in the right bank of upstream canal,
reinforced concrete retaining wall for eastern side of the site boundary and re-design of part of the
reinforced concrete retaining walls in left bank without struts considering the decision for keeping the
bank level as it is.
- FHWA-HIF-12-003 (FHWA)
Evaluating Scour at Bridges- 5th Edition
- ENVIROMESH (ENSH)
Designing with Gabions & Mattresses - Volume 3
- HEC 11
Design of Riprap Revetment
- EN 1992 (EC2)
Design of concrete structures
- EN 206-1:2000
Concrete - Part 1: Specification, performance, production and conformity
- EN 197-1
Cement - Part 1: Composition, specifications and conformity criteria for common cements
- G/5056 - Geotechnical Investigations for proposed St. Sebastian North Lock Gates and Pumping Station
(July 2017)
- ELS SI 4003 - Report 2, Soil investigation for lock gate, left canal bank and canal bed (ELS4003-2)
- Software
- PROKON 3.0
- Auto Cad 2016 - MS Excel 2013
- PLAXIS
Page 1 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
2 Design Data and Parameters
2.1 Material Properties
3
EC1-Table A.1 Density of Concrete (ϒc) = 25 kN/m
3
ERQ-VI-3-16 Density of Water (ϒw) = 10 kN/m
3
Density of soil fill (ϒs) = 18 kN/m
(Type I or II soil. Gravel-Sand mix as per ICTAD SCA/5) =
FAD, Table 2-6
0
ELS4003-2 Angle of shearing resistance (φk) = 30
** Geotechnical parameters for existing soil will be obtained from the ELS 4003-2 as relevant.
2
ERQ Vertical surcharge = 20 kN/m
Page 2 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
3 Identified components for design
Page 3 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
4 Design of Concrete Retaining Walls
The design calculations has been done using 'Retaining Wall Design Module' in PROKON.
Input
According to the W.P.M Black, The calculation of laboratory and in-sity values of
California bearing capacity data, Geotechnique, 11, 1969, pp. 14-21,
qu = 70*CBR kPa
= 875 kPa
with F.O.S of 3 qa = 291.67 kPa
According to Portland cement association (PCA), Design of concrete airport pavement, 1955
qu = 26.16*CBR0.664 psi
= 964.95 kPa
with F.O.S of 3 qa = 321.65 kPa
According to the paper by Zumrawi M.E of "Predicting bearing strength characteristics from soil index properties
2016"
qu = 65*(CBR-1.5) kPa
= 715 kPa
with F.O.S of 3 qa = 238.33 kPa
Adopting the minimum value
Allowable bearing capacity after soil improvement = 200 kPa (conservatively assume
with additional safety
msrgin)
Maximum characteristic load on the retained side = surcharge from the
vehicles
2
= 20 kN/m
0
ELS4003-2 Angle of shearing resistance for existing soil = 26
Page 4 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
0
Angle of shearing resistance of backfill soil = 30
0
Angle of shearing resistance of crushed stone base = 40
material
Output Results
Page 5 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
OK
Page 6 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
4.1.2 Design of RW06a
Input
Output
Page 7 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
OK
Page 8 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
Input
Output
Page 9 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
OK
Maximum characteristic load on the retained side = surcharge from the vehicles
2
= 20 kN/m
Maximum possible water level at the back of wall = 4.12 m MSL
**analysis with water pressure is critical than the analysis with vehicle surcharge
Note: It has been conservatively neglected the canal side water pressure in this calculation.
0
ELS4003-2 Angle of shearing resistance for backfill soil = 40
(Average)
0
Angle of shearing resistance for base soil = 40
2
Allowable bearing capacity at foundation level = 75 kN/m
Page 10 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
Note-: In the above calaculations, the program has checked the shear based on the required reinforcements and the
value of shear force has been taken at the wall-slab joint.
To correct this, the shear check has separately carried out based on the proposed reinforcement and the value of
shear force at a distance 'd (effective depth)' from the top face of base slab and the calculation is presented below.
In addition to that deflection check has also presented.
Page 11 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
Check For Shear
OK
OK
Page 12 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
5 Design of Sheet pile Retaining Walls
10kN/m2
Organic clay
-10
Page 13 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
Analysis phases
Phase 1 - Driving sheet piles with canal water level at +1.0 m MSL
Phase 2 - Load apply due to the backfill and surcharge with canal water level at +1.00 m MSL
Page 14 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
Phase 3 - F.O.S calculations for Phase 2 (applying phi c reduction)
Phase 4 - Load apply due to backfill and surcharge with canal dry condition (i.e at -2.00m MSL)
A conservative assumption
Output Results
Page 15 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
Phase 1
a) Horizontal displacements
Page 16 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
Phase 2
a) Horizontal displacements
Phase 3
Page 17 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
Phase 4
a) Horizontal displacements
Phase 5
Page 18 of 19
Project Design and Building of St. Sebastian North Lock Gates and
CHINA GEO ENGINEERING CORPORATION Pumping Station Calc by CDM
Contract.No: MCUDP/SLLRDC/W/12 Che by DAJ
Component Canal Lining 11.01.2019 A1
Reference Calculations Output
Design Checks
2
Yield strength of sheet pile (fy) = 295 N/mm
(test results shows higher values
3
Elastic section modulus per 1m width of sheet pile = 1.52E+06 mm
2
Shear area per 1m width of sheet pile wall (Av) = 2880 mm
(Av = A-hwtw)
Page 19 of 19