Grafic esalonare GANTT

,,Proiectare, asisten?a tehnica din partea proiectantului ?i execu?ie lucrari de construc?ii"


Reabilitare Drumul Nordului - Maramures, LOT1
Rev. 04
Puncte de referinta

ID Task Name UM Cantitati Durata zile Start Finish Resource Names 2019 2020
calendaristice N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M
0 825 1/15/19 4/19/21
580 MM Drumul Nordului Lot1
1 Semnarea Acordului Contractual 0 1/15/19 1/15/19 1/15
3 Data de incepere 0 3/1/19 3/1/19 3/1
4 Acces pe santier 0 3/2/19 3/2/19 3/2
5 Primire documentatie de executie de la beneficiar 0 3/1/19 3/1/19 3/1
6 Durata de Executie 780 3/1/19 4/19/21
7 Proiectare 180 3/1/19 8/28/19
11 Acces la santier pentru executia lucrarilor 0 8/28/19 8/28/19 8/28
14 Durata Lucrarilor 600 8/28/19 4/19/21
15 Start lucrari 0 8/28/19 8/28/19 8/28
170 Terminare Lucrari Sector 1 0 2/24/20 2/24/20 2/24
311 Terminare Lucrari Sector 2 0 9/21/20 9/21/20 9/21
438 Terminare Lucrari Sector 3 0 4/19/21 4/19/21 4/19
496 Terminare Lucrari Pod Km97+421 0 5/26/20 5/26/20 5/26
569 Terminare Lucrari Pod Km102+101 0 7/7/20 7/7/20 7/7
636 Terminare Lucrari Pod Km28+777.5 0 8/10/20 8/10/20 8/10
701 Terminare Lucrari Pod Km35+650 0 8/18/20 8/18/20 8/18
770 Terminare Lucrari Pod Km37+806 0 7/7/20 7/7/20 7/7
838 Terminare Lucrari Pod Km40+266 0 9/15/20 9/15/20 9/15
892 Terminare Lucrari Pod Km43+767 0 9/15/20 9/15/20 9/15
957 Terminare Lucrari Pod Km45+554 0 4/8/21 4/8/21 4/8
1009 Terminare Lucrari Pod Km45+975 0 3/5/21 3/5/21 3/5
1061 Terminare Lucrari Pod Km46+249 0 4/16/21 4/16/21 4/16
1062 Notificare pentru Receptie la Terminarea Lucrarilor 0 3/30/21 3/30/21 3/30
1063 Receptie la Terminarea Lucrarilor LOT1 0 4/19/21 4/19/21 4/19