Documente Academic
Documente Profesional
Documente Cultură
Sub-Total
5 Approach Tunnel
1
5 Desander
1 Hard Rock Excavation Including Payline m³ 6017.47 375.84
2 Pattern Rock Bolts 3m length , 25 mm dia. nos 759.29 69.28
3 Spot Bolts 3m length , 25mm dia. nos 156.00 12,634.72
4 Steel Ribs: ISMB 200 including plates and bolts Tons 25.04
Rib Reinforcements:Tie bars,
5 Tons 12.80
Connecting bars,Anchor Bars
6 Wire mesh 4.75mm dia 100*100 mm mesh m² 875.05
7 Safety Shotcrete 30mm thickness m³ 55.80
8 FINAL SHOTCRETE:
Sub-Total
B Underground Structures
1 Inlet Portal
1 Boulder mix soil Excavation m³ 6497.76 375.84
2 Rock excavation-Open Cut m³ 324.89 1,097.92
3 30 mm thick plain shotcrete (M25) m³ 70.22 23,364.32
4 Rockbolts (25mm dia, 3m long)
a. with plain cement grout no 421.20 2,892.80
b. with resin capsules no 97.20 4,196.96
c. with cement capsules no 129.60 5,040.00
5 50 mm dia HDPE perforated pipe (3m long) no 15.00 6,314.40
6 Perforated cement grouting kg 2250.00 127.04
7 Weep holes (50 mm dia/10 kgf HDP, 3 m long) no 30.23 2,116.32
8 4.75mm dia wiremesh @ 100mm c/c m² 2340.79 704.80
9 Backfill and compaction m³ 83.57 376.32
10 Stone masonary(1:4) m³ 66.88 6,504.48
11 Steel lagging (ISMC 100) kg 34.42 239.52
12 16 mm dia connecting bar kg 127.82 239.52
13 Steel rib ISMB 150 (incl. base, steel plates & nut bolts) kg 1014.72 239.52
14 Anchoring rod (25 mm dia, 2.5 m long) no 40.00 2,169.60
Rate (NRs)
Amount (NRs) Remarks
In words
28,800,000.00
23,718,400.00
20,574,656.00
6,160,000.00
24,307,200.00
53,152,960.00
672,000.00
6,720,000.00
16,000,000.00
4,009,280.00
1,200,000.00 Provisional
4,800,000.00 Provisional
28,159,129.60
17,600,000.00
Sub-Total 235,873,625.60
149,727.06
13,365.50
966,664.40
332,455.18
5,190,266.88
Rate (NRs)
Amount (NRs) Remarks
In words
Sub-Total 6,652,479.02
1,591,457.01
57,500.65
1,048,649.92
51,763,958.78
3,668,626.62
685,813,599.10
-
1,630,711.68
14,633,859.77
96,944.64
Sub-Total 760,305,308.16
74,467.06
166.36
1,297,913.74
204,088.42
9,180,521.59
-
667,101.66
18,067.21
680,000.00
Sub-Total 12,122,326.04
770,512.03
Rate (NRs)
Amount (NRs) Remarks
In words
17,458.56
682,274.88
199,299.99
922,419.75
-
17,669.26
175,631.78
382,913.91
69,543.94
2,861.60
16,960.32
21,837.07
52,373.43
5,049,086.21
86,674.22
257,835.60
305,280.00
-
Sub-Total 9,030,632.54
Rate (NRs)
Amount (NRs) Remarks
In words
2,261,604.80
52,603.61
1,971,016.32
Rate (NRs)
Amount (NRs) Remarks
In words
715,087.08
120,274.13
1,244,431.36
2,042.56
1,836,554.46
Sub-Total 8,203,614.32
6,331,833.80
6,817,930.30
53,716.66
1,601,848.28
489,820.30
47,217,733.00
6,629,635.19
5,025,931.37
1,690,645.45
Sub-Total 75,859,094.34
Rate (NRs)
Amount (NRs) Remarks
In words
52,376,495.33
17,000,497.18
91,657.44
2,733,254.50
-
3,494,502.40
1,691,374.88
4,537,697.75
4,512,779.04
294,090.74
1,640,635.90
56,555,530.69
47,132,321.53
-
192,334.05
9,053,275.33
706,135.03
983,208.01
1,655,722.88
309,727.09
263,144.76
1,801,459.13
1,678,294.79
3,840.00
732,960.00
Rate (NRs)
Amount (NRs) Remarks
In words
35,045.00
82,885.50
37,619.71
462,560.00
3,200,000.00
4,000,000.00
278,190.88
Sub-Total 217,537,239.55
5,361,384.66
57,717.79
1,721,163.20
167,369.11
488,706.54
21,020,007.18
21,021,217.02
-
1,524,618.35
1,787,905.63
258,116.32
169,052.93
251,996.35
Sub-Total 53,829,255.09
328,464.06
235,307.97
Rate (NRs)
Amount (NRs) Remarks
In words
17,118.59
150,411.79
3,910,108.55
2,528,242.22
2,207,355.76
-
Sub-Total 9,377,008.95
2,442,118.12
356,701.03
1,640,731.67
-
1,218,447.36
407,944.51
653,184.00
94,716.00
285,840.00
63,965.77
1,649,791.47
31,449.11
435,019.62
8,243.32
30,614.97
243,044.54
86,784.00
Rate (NRs)
Amount (NRs) Remarks
In words
Sub-Total 9,648,595.49
9,343,479.20
1,680,378.14
7,887,847.79
6,282,168.64
-
2,888,096.72
189,057.92
-
518,280.00
684,047.52
1,312,440.50
97,087.99
5,263,877.54
323,336.64
330,641.65
385,370.88
Sub-Total 37,186,111.14
182,583,665.96
10,581,536.84
252,046.38
1,239,963.08
2,309,913.37
119,776.69
Rate (NRs)
Amount (NRs) Remarks
In words
76,830,485.03
74,739,700.73
-
34,282,787.10
4,541,990.57
3,779,100.80
-
5,182,800.00
1,718,121.92
2,701,110.72
36,408,113.05
183,184.90
489,839.48
16,573,624.92
10,939,409.41
4,324,024.32
330,145.92
6,517,516.61
1,940,352.00
-
1,164,841.33
243,016.99
-
- Provisional
Sub-Total 479,977,068.12
Rate (NRs)
Amount (NRs) Remarks
In words
5,517,779.76
701,081.56
-
829,248.00
537,883.52
5,174,826.32
4,121,419.74
90,296.32
388,871.26
7,327.40
143,474.59
309,948.94
185,743.36
2,196,176.79
148,201.92
111,919.84
58,738.40
12,273.11
18,610.00
12,628.64
7,054.40
Sub-Total 20,573,503.87
800,496.35
158,531.67
Rate (NRs)
Amount (NRs) Remarks
In words
172,588.88
-
165,840.00
80,640.00
400,176.00
33,861.12
150,620.33
13,199,937.30
6,483,348.46
776,036.68
-
1,181,678.40
760,052.80
7,352,867.03
3,294,388.31
97,350.72
1,118,004.87
447,527.75
199,603.20
54,955.47
102,049.89
1,305,879.73
251,242.56
107,399.04
113,657.76
Rate (NRs)
Amount (NRs) Remarks
In words
63,489.60
-
5,123,019.10
132,602.40
400,176.00
Sub-Total 44,528,021.42
1,283,951.66
381,413.99
656,466.91
-
943,269.60
458,640.00
177,856.00
48,675.36
42,795.38
25,670,314.80
3,340,587.46
2,560,983.24
-
3,856,003.20
2,478,941.44
2,004,205.45
1,637,936.43
Rate (NRs)
Amount (NRs) Remarks
In words
131,211.84
3,645,668.05
1,476,877.45
650,880.00
137,388.67
1,581,773.31
4,309,507.80
781,643.52
354,425.44
353,601.92
197,523.20
195,734.00
590,736.00
Sub-Total 59,949,012.13
789,619.17
586,415.77
407,854.32
-
210,767.20
105,840.00
57,168.00
44,442.72
205,053.21
Rate (NRs)
Amount (NRs) Remarks
In words
9,007,128.00
1,172,135.95
898,590.61
-
1,347,528.00
876,984.00
34,578.46
28,259.23
183,414.40
1,263,831.59
518,202.61
225,638.40
47,628.07
552,770.24
1,512,108.00
279,158.40
124,359.80
126,286.40
70,544.00
44,198.00
133,392.00
Sub-Total 20,853,896.57
333,400,893.01
171,318,106.08
43,584,640.12
Rate (NRs)
Amount (NRs) Remarks
In words
132,605,902.96
-
101,460,760.33
27,246,801.60
26,976,348.19
8,128,225.10
-
3,641,114.88
3,335,130.24
3,641,114.88
-
5,783,865.12
5,633,653.12
5,783,865.12
-
27,613,958.40
20,726,392.96
26,695,392.96
1,151,278.08
64,747,064.60
2,135,019.96
8,500,439.05
34,532,141.20
5,750,663.04
2,428,678.08
3,870,685.44
Rate (NRs)
Amount (NRs) Remarks
In words
1,145,532.48
601,204.80
2,265,062.40
2,377,313.28
20,082,579.98
13,939,293.91
371,832.00
372,813.44
214,973.63
685,687.68
11,548,562.40
1,045,545.20
4,369,793.11
884,016.00
889,280.00
Sub-Total 1,131,485,624.83
502,332.71
15,551,814.43
2,429,349.85
10,706,115.77
8,680,335.09
-
4,796,281.55
-
601,204.80
Rate (NRs)
Amount (NRs) Remarks
In words
339,100.48
507,916.80
323,824.00
208,310.69
206,007.83
143,691.99
Sub-Total 44,996,285.99
537,879.36
392,819.09
94,716.00
285,840.00
399,984.48
158,152.46
3,538,504.73
3,207,351.81
291,653.44
32,973.28
131,670.40
32,597.00
19,843.03
-
130,176.00
75,600.00
Sub-Total 9,329,761.09
Rate (NRs)
Amount (NRs) Remarks
In words
400,000,000.00
120,000,000.00
Sub-Total 520,000,000.00
d Total for Civil Works 3,767,318,464.26
Vat (13%) 489,751,400.35 263,733,780
Total 4,257,069,864.61
480,000,000.00
Sub-Total 480,000,000.00
for Transmission Line 480,000,000.00
1,185,533.34
1,185,533.34
1,155,992.66
1,155,992.66
158,430.24
158,430.24
581,143.79
1,007,315.91
125,179.45
125,179.45
2,691,297.64
1,748,926.95
Rate (NRs)
Amount (NRs) Remarks
In words
2,352,879.76
1,922,638.89
127,367,226.16
14,720,814.48
3,715,793.52
1,955,680.80
3,200,000.00
6,425,675.84
4,345,675.84
6,928,707.84
10,672,480.00
1,842,911.36
5,336,240.00
921,455.68
921,455.68
21,344,960.00
18,906,154.56
6,302,051.52
Rate (NRs)
Amount (NRs) Remarks
In words
Sub Total 250,461,757.59
for Mechanical Works 276,103,686.38
2 Preparation of foundation
Foundation of Type 1 at U/s upto weir 1.00 50.86 2.00
Foundation of Type 2 at U/s upto divide wall 1.00 45.60 2.00
3 Filling works
Soil Mixed Boulders filling for Type 1 at U/s upto weir
Top Portion 1.00 50.86 AREA=
Bottom Portion 1.00 50.86 AREA=
Soil Mixed Boulders filling for Type 2 at U/s upto divide wall
Top Portion 1.00 45.60 AREA=
Bottom Portion 1.00 45.60 AREA=
4 10 mm thick Geomembrane
Geomembrane of Type 1 at U/s upto weir 1.00 50.86
Geomembrane of Type 2 a U/s upto divide wall 1.00 45.60
4.13 210.05
4.13 188.33
Sub Total 398.38 m3
101.72
91.20
Sub Total 192.92 m2
22.50 1144.35
4.13 210.05
22.50 1026.00
4.13 188.33
Sub Total 2568.73 m3
6.50 330.59
6.50 296.40
Sub Total 626.99 m2
22.50 1793.48
22.50 1547.33
Sub Total 3340.80 m3
5.00 1963.07
5.00 1528.56
Sub Total 3491.63 m3
ITEMS
1 BOULDER MIXED SOIL EXCAVATION
2 SURFACE PREPARATION
3 100mm THICK M15 BLINDING CONCRETE
4 M25 PLAIN CONCRETE
5 REINFORCEMENT
6 FORMWORK
7 RIP-RAP WORKS
8 GEOTEXTILE
9 BACKFILLING WORKS & COMPACTION
10 HANDRAILS
2 SURFACE PREPARATION
a Weir cut-off wall 1.00 31.60 2.50
b Cutoff wall at U/s 1.00 31.60 2.50
c Cutoff wall at D/s 1.00 52.50 2.50
d Undersluice 1.00 45.42 2.50
e Guide wall at left bank 1.00 81.86 2.78
f Guide wall at right bank 1.00 71.80 2.78
j Beam
Longer Span 4.00 3.00 0.30
Shorter Span 3.00 3.00 0.30
5 REINFORCEMENT
1% of Concrete works
6 FORMWORK
Type F3
a Weir cut-off side face 2.00 31.60
b Cut-off wall at U/s side face 2.00 36.39
c Cut-off wall at D/s side face 2.00 52.50
d Divide Wall 2.00 45.45
e Guide Wall at left bank side faces 2.00 81.86
Guide Wall at left bank front and back 2.00 0.50
f Guide Wall at right bank side faces 2.00 71.80
Guide Wall at right bank front and back 2.00 0.50
g Platform Slab
Platform slab above undersluice 4.00 4.50
Platform slab above undersluice base 1.00 4.50 4.50
Deduct Gate opening longer side -4.00 1.50
Deduct gate opening for slab -1.00 1.00 1.50
Platform slab with supporting gate mechanism 4.00 4.30
Platform slab with supporting gate mechanism base 1.00 4.30 4.30
Deduct Gate opening longer side -4.00 1.50
Deduct gate opening for slab -1.00 1.00 1.50
j Beam
Longer Span side faces 8.00 3.00
Shorter Span side faces 6.00 3.00
7 RIP-RAP WORKS
At U/s launching apron 1.00 Area= 257.76
At D/s launching apron 1.00 Area= 324.46
8 GEOTEXTILE
At U/s of weir 1.00 30.00 31.60
SUMMARY
6.82 215.51
14.84 468.94
42.89 2251.90
2.44 110.78
7.82 639.87
7.82 547.40
Sub Total 4234.40 m3
79.00
79.00
131.25
113.55
227.57
199.60
Sub Total 829.97 m2
0.1 7.90
0.1 7.90
0.1 13.13
0.1 11.36
0.1 22.76
0.1 19.96
Sub Total 83.00 m3
9.92 313.47
3.50 110.60
6.50 341.25
7.57 619.43
7.57 543.31
3.96 3.98
6.26 144.73
5.50 69.52
5.50 5.53
0.20 4.05
0.20 -0.15
0.20 3.70
0.20 -0.15
6.20 6.20
0.50 1.80
0.50 1.35
2.50 1.13
0.30 34.07
0.30 34.07
14.67 440.10
16.74 602.64
1.50 247.62
1.50 170.63
Sub Total 3698.86 m3
36.99
Sub Total 290.36 ton
9.00 568.80
3.00 218.34
6.00 630.00
5.50 499.95
7.80 1277.02
7.80 7.80
7.80 1120.08
7.80 7.80
0.20 3.60
20.25
0.20 -1.20
-1.50
0.20 3.44
18.49
0.20 -1.20
-1.50
6.20 49.60
2.50 1.50
2.50 7.50
0.50 12.00
0.50 9.00
Sub Total 4449.77 m2
1.00 257.76
1.00 324.46
Sub Total 582.22 m3
948.00
Sub Total 948.00 m2
64.00 2022.40
61.16 3210.90
7.11 224.68
4.10 129.56
25.54 1340.85
Sub Total 6928.39 m3
16.80
16.80
0.90 28.80
Sub Total 62.40 m
ITEMS
1 Hard Rock Excavation
2 50mm blinding concrete
3 Plain concrete work (M25)
4 M15 plum concrete
5 Abrasion resistant concrete M50
6 Reinforcement
7 Formwork F1
8 Formwork F2
9) 2" MS steel Hand Rail
58.00
58.00 m2
260.00
260.00 nos.
12458.70
807.11
82.51
13.35 Tons
3460.75
224.20
22.92
3.71 Tons
972.22
205.43
379.26
1.56 Tons
114.00
260.00
374.00 m2
7.80
7.80 m3
39.00
39.00 m3
125.00
125.00 m3
0.29
0.29
1.82
2.40 m3
23.20
2.03
7.54
14.62
-0.21
-2.45
6.48
1.68
0.32
6.82
2.14
1.87
2.30
0.94
2.31
7.44
1.73
3.01
4.13
0.57
6.24
11.42
-1.41
102.73 m3
14.06
14.06 m3
59.57
59.57 m3
8.06 Tons
8.06 Tons
2.32
20.88
5.80
9.48
13.56
60.56
50.16
36.96
10.35
38.02
15.24
43.36
2.56
6.60
315.84 m2
10.27
37.74
48.01 m2
59.06
25.60
85.00 m
ITEMS:
1 Hard Rock Excavation Including Payline
2 Pattern Rock Bolts 3m length , 25 mm dia.
3 Spot Bolts 3m length , 25mm dia.
4 Steel Ribs: ISMB 200 including
Rib Reinforcements:Tie bars, plates and bolts
5 Connecting bars,Anchor Bars
6 Wire mesh 4.75mm dia 100*100 mm mesh
7 Safety Shotcrete 30mm thickness
8 Plain Shotcrete 200mm thickness
9 Stone Backfill
10 Forepolling Bars: 25mm dia 3m length
11 Dewatering:
12 HDPE perferated pipes 50mm dia. 3m length
13 50 mm M15 Blinding Concrete
14 M25 Plain Concrete
15 Formwork
16 Quantity of reinforcement
17 M15 Plum Concrete
18 2" MS steel Hand Rail
9 Stone Backfill
Upto 350mm thickness 1.00 18.20 28.46
11 Dewatering: 1.00
iv) Column
a) Rectangular column 2.00 4.25 0.40
16) Formwork
i) Blinding Concrete
a) Inclined Portion: 2.00 11.10 0.05
b) Settling Zone: 2.00 5.80 0.05
c) Transition Zone: 1.00 11.10 0.05
d) At Flushing Channel transition: 2.00 2.56 0.05
111.00 2020.20
23.01 29.91
SUB TOTAL 2050.11 m3
202.02
3.33
SUB TOTAL 205.35 m2
18.00 252.00
SUB TOTAL 252.00 nos.
18.00 54.00
SUB TOTAL 54.00 nos.
25.40 12458.70
0.012 807.11
82.51
SUB TOTAL 13.35 Tons
3.86 3500.00
2.47 873.09
2.47 1611.85
SUB TOTAL 5.98 Tons
28.50 484.50
SUB TOTAL 484.50 m2
0.03 15.51
SUB TOTAL 15.51 m3
0.20 102.10
SUB TOTAL 102.10 m3
0.35 181.29
SUB TOTAL 181.29 m3
5.00 184.80
SUB TOTAL 184.80 nos.
1.00
SUB TOTAL 1.00 LS
1.00 18.00
SUB TOTAL 18.00 nos
0.05 0.73
0.05 2.69
0.05 0.60
0.05 5.56
0.05 1.11
SUB TOTAL 10.69 m3
0.30 3.36
0.30 0.30
0.30 1.55
0.30 8.28
0.30 -1.75
0.50 7.25
0.50 26.88
0.50 5.40
0.30 3.78
0.30 1.02
0.30 4.15
0.60 0.49
0.30 -0.24
0.30 4.39
0.30 0.34
2.50 52.85
2.16 -31.55
0.30 2.35
0.30 3.02
0.30 15.30
0.30 6.93
1.15 25.44
0.60 -7.58
1.15 8.28
0.60 -2.47
0.30 -0.36
0.20 0.90
0.20 1.00
0.25 0.66
0.30 0.30
0.30 0.23
0.30 22.19
0.30 -1.79
0.30 155.39
SUB TOTAL 260.20 m3
1.11
0.58
0.56
0.26
3.38
12.20
7.65
4.21
5.08
11.44
14.50
53.76
8.96
3.20
1.70
7.84
2.19
10.07
9.24
46.18
110.60
35.98
-4.60
11.90
18.75
32.43
75.34
33.00
2.86
3.12
73.96
1035.94
30.97
SUB TOTAL 1633.37 m2
1.87 14.71
2.76 18.84
1.87 95.37
SUB TOTAL 128.92 m3
84.00
75.00
159.00 m
0.01 3.47
0.01 1.13
SUB TOTAL 4.60 Tons
ITEMS:
1 Hard Rock Excavation Including Payline
2 Pattern Rock Bolts 3m length , 25 mm dia.
3 Spot Bolts 3m length , 25mm dia.
4 Steel Ribs: ISMB 200 including
Rib Reinforcements:Tie bars, plates and bolts
5 Connecting bars,Anchor Bars
6 Wire mesh 4.75mm dia 100*100 mm mesh
7 Safety Shotcrete 30mm thickness
8 Plain Shotcrete 200mm thickness
9 Stone Backfill
10 Forepolling Bars: 25mm dia 3m length
11 Dewatering:
12 HDPE perferated pipes 50mm dia. 3m length
13 50 mm M15 Blinding Concrete
14 M25 Plain Concrete
15 Formwork
16 Quantity of reinforcement
17 M15 Plum Concrete
18 2" MS steel Hand Rail
9 Stone Backfill
Upto 300mm thickness 0.50 21.60 9.40
11 Dewatering: 1.00
16) Formwork
Concrete Lining:
a) Peripheral perimeter at concrete lining 2.00 21.60 7.25
b) Invert lining at the sides 250.00 2.56 0.30
7.96 429.84
7.96 0.00
SUB TOTAL 429.84 m3
10.80 17.50
10.80 31.50
10.80 49.50
21.60 71.50
SUB TOTAL 170.00 nos.
5.00 5.00
SUB TOTAL 5.00 nos.
15.40 2496.14
0.012 239.50
55.32
SUB TOTAL 2.79 Tons
1.58 321.42
1.58 334.51
1.58 778.24
SUB TOTAL 1.43 Tons
7.53 162.65
SUB TOTAL 162.65 m2
0.03 6.39
SUB TOTAL 6.39 m3
0.05 4.19
SUB TOTAL 4.19 m3
0.08 6.19
SUB TOTAL 6.19 m3
0.10 8.18
SUB TOTAL 8.18 m3
0.18 14.08
SUB TOTAL 14.08 m3
7.00 25.92
SUB TOTAL 25.92 m3
5.00 13.50
SUB TOTAL 13.50 nos.
1.00
SUB TOTAL 1.00 LS
1.00 54.00
SUB TOTAL 54.00 nos
0.25 19.56
0.30 41.47
SUB TOTAL 61.03 m3
7850.00 4.79 Tons
SUB TOTAL 4.79 Tons
312.98
192.00
SUB TOTAL 504.98 m2
ITEMS:
1 Hard Rock Excavation Including Payline
2 Pattern Rock Bolts 3m length , 25 mm dia.
3 Spot Bolts 3m length , 25mm dia.
4 Steel Ribs: ISMB 200 including
Rib Reinforcements:Tie bars, plates and bolts
5 Connecting bars,Anchor Bars
6 Wire mesh 4.75mm dia 100*100 mm mesh
7 Safety Shotcrete 30mm thickness
8 Plain Shotcrete 200mm thickness
9 Stone Backfill
10 Forepolling Bars: 25mm dia 3m length
11 Dewatering:
12 HDPE perferated pipes 50mm dia. 3m length
13 50 mm M15 Blinding Concrete
14 M25 Plain Concrete
15 Formwork
16 Quantity of reinforcement
17 M15 Plum Concrete
18 2" MS steel Hand Rail
8) FINAL SHOTCRETE:
8.1 Fibre Reinforced Shotcrete 100mm thickness 1.00 15.19 24.29
9 Stone Backfill
Upto 350mm thickness 1.00 37.00 24.68
11 Dewatering: 1.00
16) Formwork
i) Blinding Concrete
a) Inclined Portion: 1.00 40.84 0.05
b) Settling Zone along the length: 1.00 11.20 0.05
b) Settling Zone at side portion: 2.00 0.56
c) Transition Zone: 4.00 8.35 0.05
d) At Flushing Channel transition: 2.00 3.20 0.05
44.65 607.24
81.34 4652.65
81.34 679.19
21.78 78.39
SUB TOTAL 6017.47 m3
131.60
616.17
11.52
SUB TOTAL 759.29 m2
15.19 243.00
22.79 456.00
37.98 911.00
SUB TOTAL 1610.00 nos.
2.00 156.00
SUB TOTAL 156.00 nos.
25.40 23164.80
0.012 1703.89
174.19
SUB TOTAL 25.04 Tons
3.86 7388.89
2.47 1900.25
2.47 3508.15
SUB TOTAL 12.80 Tons
23.65 875.05
SUB TOTAL 875.05 m2
0.03 55.80
SUB TOTAL 55.80 m3
0.10 36.89
SUB TOTAL 36.89 m3
0.20 109.94
SUB TOTAL 109.94 m3
0.35 319.61
SUB TOTAL 319.61 m3
296.00
SUB TOTAL 296.00 nos.
1.00
SUB TOTAL 1.00 LS
1.00 75.95
SUB TOTAL 76.00 nos
0.05 4.20
0.05 25.74
0.05 6.29
0.05 5.72
0.05 3.92
0.05 0.56
SUB TOTAL 46.44 m3
0.20 1.20
0.20 5.10
0.20 -1.68
0.30 25.20
0.30 6.77
0.30 154.44
0.30 37.75
0.30 30.47
0.30 34.32
0.60 28.94
0.85 4.25
0.25 -0.06
0.20 2.16
0.30 0.31
0.15 0.02
2.63 56.39
1.00 -31.22
10.90 28.34
7.06 -18.36
10.90 32.70
7.06 -21.18
0.60 2.11
0.30 6.93
1.10 15.90
0.50 -3.28
1.10 7.46
0.50 -1.54
0.30 -1.49
0.20 1.22
0.20 1.12
0.25 0.85
0.30 0.39
0.30 0.19
0.30 10.71
0.30 -0.47
0.30 269.49
SUB TOTAL 685.45 m3
2.04
0.56
1.12
1.67
0.32
8.53
23.10
12.25
168.00
514.80
9.00
1.20
114.40
0.60
188.76
91.96
43.17
-9.90
112.05
11.94
167.77
39.00
3.04
2.59
15.36
100.52
1874.45
SUB TOTAL 3498.30 m2
39.54
SUB TOTAL 39.54 m3
40.00
20.00
60.00 m
0.01 2.06
0.01 0.97
SUB TOTAL 3.03 Tons
ITEMS:
1 Hard Rock Excavation Including Payline
2 Pattern Rock Bolts 3m length , 25 mm dia.
3 Spot Bolts 3m length , 25mm dia.
4 Steel Ribs: ISMB 200 including
Rib Reinforcements:Tie bars, plates and bolts
5 Connecting bars,Anchor Bars
6 Wire mesh 4.75mm dia 100*100 mm mesh
7 Safety Shotcrete 30mm thickness
8 Plain Shotcrete 200mm thickness
9 Stone Backfill
10 Forepolling Bars: 25mm dia 3m length
11 Dewatering:
12 HDPE perferated pipes 50mm dia. 3m length
13 50 mm M15 Blinding Concrete
14 M25 Plain Concrete
15 Formwork
16 Quantity of reinforcement
17 M15 Plum Concrete
18 2" MS steel Hand Rail
9 Stone Backfill
Upto 300mm thickness 0.50 1448.00 9.40
11 Dewatering: 1.00
16) Formwork
Concrete Lining:
a) Peripheral perimeter at concrete lining 2.00 1455.20 7.25
b) Invert lining at the sides 250.00 2.56 0.30
7.96 28815.20
7.96 47.76
SUB TOTAL 28862.96 m3
727.60 1274.00
727.60 2182.50
727.60 3333.00
1455.20 4732.00
SUB TOTAL 11522.00 nos.
364.00 364.00
SUB TOTAL 364.00 nos.
15.40 160040.31
0.012 15355.78
3547.15
SUB TOTAL 178.94 Tons
1.58 20608.00
1.58 22424.34
1.58 52170.90
SUB TOTAL 95.20 Tons
7.53 10903.44
SUB TOTAL 10903.44 m2
0.03 428.56
SUB TOTAL 428.56 m3
0.05 282.58
SUB TOTAL 282.58 m3
0.08 417.32
SUB TOTAL 417.32 m3
0.10 550.79
SUB TOTAL 550.79 m3
0.18 948.86
SUB TOTAL 948.86 m3
7.00 1737.60
SUB TOTAL 1737.60 m3
5.00 905.00
SUB TOTAL 905.00 nos.
1.00
SUB TOTAL 1.00 LS
1.00 3638.00
SUB TOTAL 3638.00 nos
0.25 1317.87
0.30 2780.16
SUB TOTAL 4098.03 m3
21085.85
192.00
SUB TOTAL 21277.85 m2
DETAILED ESTIMATE OF ADIT 1 & SPILLWAY
S.N. ITEM NO LENGTH IN M BREADTH IN M
AUDIT PORTAL
A Boulder mix soil Excavation for Adit 2 portal
Portal Excavation 1.00 14.80 Area=
I Backfill
(a) Access Road 1.00 10.00 Area(m2)=
J Catch Drain
Reinforced Cement Concrete 1.00 14.80 Area(m2)=
M REINFORCEMENT
AUDIT TUNNEL
1 Rock Excavation
Adit 1 Tunnel 1.00 49.33 Area=
2 30 mm Thick Plain Shotcrete
(a) At Wall & Arch 1.00 49.33 10.69
6 Reinforcement
I Backfill
(a) Access Road 1.00 10.00 Area(m2)=
(b) Below Box Culvert 1.00 2.80 Area(m2)=
J Catch Drain
Reinforced Cement Concrete 1.00 14.80 Area(m2)=
AUDIT TUNNEL
1 Rock Excavation
Adit 2 Tunnel 1.00 46.36 Area=
6 Reinforcement
ADIT TUNNEL
1 Rock Excavation
2 30 mm Thick Plain Shotcrete
3 100mm Thick Plain Shotcerte
4 1.8 m Long , 20 mm Dia Grouted Rockbolts
At Wall and Crown 1.5m c/c with plain cement grout
5 Reinforced cement concrete M25
6 Reinforcement
7 Weepholes of 50mm Dia , 2 m Long
8 Steel ribs 150mm @1.5m c\c
9 Wire mesh (4.75mm diameter)
10 Anchoring 2.0m long 20mm dia.
11 Steel lagging ISMC 100
12 16 mm dia connecting bar
13 Forepoling (3m Length, MS 2")
14 Stone Backfilling
15 MS PIPE 2"
16 Drain pipe perforated 6m long
17 Drain hole 76mm Ø
18 Formwork(Type F2)
19 Stone Pitching
20 Tie Bars (16mm Diameter, 1.65m Long)
I Stone Masonary(1:4)
(a) Paraphet Wall 1.00 3.16 Area(m2)=
(b) Maonary Wall 1.00 2.50 Area(m2)=
J Catch Drain
Plain Concrete 1.00 12.00 Area(m2)=
AUDIT TUNNEL
1 Rock Excavation
Adit 3 Tunnel 1.00 217.75 Area=
6 Reinforcement
SUMMARY ADIT 3
ADIT PORTAL
A Boulder mix soil Excavation for Adit 3 portal
B Rock excavation
C 50mm Thick Shotcrete Adit 3 portal
D Rockbolt (20mm dia, 1.8m length)
E Perforated Grouting
F Weep holes(6m Long, diameter 56mm)
G Wire mess (4.75mm dia)
H Stone Masonary
I Plain concrete
J Soil Cushion
ADIT TUNNEL
1 Rock Excavation
2 30 mm thick initial plain shotcrete (M25)
3 100 mm thick plain shotcrete (M25)
4 1.8 m Long , 20 mm Dia Grouted Rockbolts
1m c/c with plain cement grout(Type 1)
2m c/c with plain cement grout(Type2)
5 Reinforced cement concrete M25
6 Reinforcement
7 Weepholes of 50mm Dia , 2 m Long
8 Steel ribs 150mm @1.5m c\c
9 Wire mesh (4.75mm diameter)
10 Anchoring 2.0m long 20mm dia.
11 Steeling Lagging ISMC
12 16 mm dia connecting bar
13 FOREPOLLING (3M LONG, MS2")
14 Stone Backfilling
15 MS PIPE 2"
16 Drain pipe perforated 6m long
17 Drain hole 76mm Ø
18 Dewatering
19 Tie Bars(16mm Diameter, 1.65m Long)
I Stone Masonary(1:4)
(a) Paraphet Wall 1.00 3.16 Area(m2)=
(b) Maonary Wall 1.00 2.50 Area(m2)=
J Catch Drain
Plain Concrete 1.00 12.00 Area(m2)=
1 Rock Excavation
ADIT 4 TUNNEL 1.00 53.16 AREA(M2)=
6 Reinforcement
7 Weepholes of 50mm Dia , 2 m Long , 2m c/c
(a) At Wall & Arch 5.00 14.00
SUMMARY ADIT 4
ADIT PORTAL
A Boulder mix soil Excavation for Adit 3 portal
B Rock excavation
C 50mm Thick Shotcrete Adit 3 portal
D Rockbolt (20mm dia, 1.8m length)
E Perforated Grouting
F Weep holes(6m Long, diameter 56mm)
G Wire mess (4.75mm dia)
H Stone Masonary
I Plain concrete
J Soil Cushion
ADIT TUNNEL
1 Rock Excavation
2 30 mm thick initial plain shotcrete (M25)
3 100 mm thick plain shotcrete (M25)
4 1.8 m Long , 20 mm Dia Grouted Rockbolts
TYPE 1: (AT WALL AND CROWN)
TYPE 2: (AT WALL AND CROWN)
5 Reinforced cement concrete M25
6 Reinforcement
7 Weepholes of 50mm Dia , 2 m Long
8 Steel ribs 150mm @1.5m c\c
9 Wire mesh (4.75mm diameter)
10 Anchoring 2.5m long 25mm dia.
11 Steeling Lagging ISMC
12 16 mm dia connecting bar
13 FOREPOLLING (3M LONG, MS2")
14 Stone Backfilling
15 MS PIPE 2"
16 Drain pipe perforated 6m long
17 Drain hole 76mm Ø
18 Dewatering 1.00
19 Tie Bars
I Stone Masonary(1:4)
(a) Paraphet Wall 1.00 3.16 Area(m2)=
(b) Maonary Wall 1.00 2.50 Area(m2)=
J Catch Drain
Plain Concrete 1.00 12.00 Area(m2)=
AUDIT TUNNEL
1 Rock Excavation
Adit 5 Tunnel 1.00 77.53 Area=
6 Reinforcement
SUMMARY ADIT 5
ADIT PORTAL
A Boulder mix soil Excavation for Adit 3 portal
B Rock excavation
C 50mm Thick Shotcrete Adit 3 portal
D Rockbolt (20mm dia, 1.8m length)
E Perforated Grouting
F Weep holes(6m Long, diameter 56mm)
G Wire mess (4.75mm dia)
H Stone Masonary
I Plain concrete
J Soil Cushion
ADIT TUNNEL
1 Rock Excavation
2 30 mm thick initial plain shotcrete (M25)
3 100 mm thick plain shotcrete (M25)
4 1.8 m Long , 20 mm Dia Grouted Rockbolts
1m c/c with plain cement grout(Type 1)
2m c/c with plain cement grout(Type2)
5 Reinforced cement concrete M25
6 Reinforcement
7 Weepholes of 50mm Dia , 2 m Long
8 Steel ribs 150mm @1m c\c
9 Wire mesh (4.75mm diameter)
10 Anchoring 2.5m long 25mm dia.
11 Steeling Lagging ISMC
12 16 mm dia connecting bar
13 FOREPOLLING (3M LONG, MS2")
14 Stone Backfilling
15 Forepolling (6m length, MS 2")
16 Drain pipe perforated 6m long
17 Drain hole 76mm Ø
18 Dewatering 1.00
19 Tie Bars(16mm Diameter, 1.65m Long)
I Stone Masonary(1:4)
(a) Paraphet Wall 1.00 3.16 Area(m2)=
(b) Maonary Wall 1.00 2.50 Area(m2)=
J Catch Drain
Plain Concrete 1.00 12.00 Area(m2)=
AUDIT TUNNEL
1 Rock Excavation
Adit 6 Tunnel 1.00 30.98 Area=
6 Reinforcement
SUMMARY ADIT 6
ADIT PORTAL
A Boulder mix soil Excavation for Adit 3 portal
B Rock excavation
C 50mm Thick Shotcrete Adit 3 portal
D Rockbolt (20mm dia, 1.8m length)
E Perforated Grouting
F Weep holes(6m Long, diameter 56mm)
HEIGHT IN M QUANTITY UNIT REMARK
9.66 7.15
SUB TOTAL 7.15 m3
0.00 #VALUE! kg
- 18.00 no
1.22 12.17 m³
0.57 1.60 m³
5.29 10.58 m³
0.50 1.58 m³
TOTAL 25.93 m³
6.24 62.43 m³
0.21 1.82 m³
1.00 14.80 m³
0.30 0.95 m³
0.14 ton
10.74 529.56 m³
Total 529.56 m³
0.03 15.82 m³
187.00 no
Total 187.00 no
0.80 m³ 1% of concrete
Total 6.32 tons
- 65.00 no
Total 65.00 no
- 103.59 m2
- 98.66 m2
- 0.65 m2
- 11.00 m2
- 16.00 m2
- 10.00 m2
- 4.56 m2
Total 244.46 m2
0.10 1.50 m³
Total 1.50 m³
336.00 no 24 Tie Bars Between two Ribs
128.67 m³
14.30 m³
7.15 m³
35.00 no
#VALUE! no
18.00 no
71.48 m2
25.93 m³
62.43 m³
1.82 m³
14.80 m2
0.95 m³
0.14 tons
529.56 m³
15.82 m³
7.27 m³
187.00 no
80.46 m³
6.32 tons
65.00 no
427.01 kg
63.10 kg
2471.03 Kg
203.77 m2
60.00 no
18.00 no
20.69 m³
54.00 m
12.00 no
120.00 m
244.46 m2
1.50 m³
336.00 no
9.50 7.03
SUB TOTAL 7.03 m3
0.00 #VALUE! kg
- 18.00 no
3.25 32.51 m³
2.46 6.89 m³
5.29 10.58 m³
0.50 1.58 m³
TOTAL 51.55 m³
0.40 4.03 m³
2.77 7.76 m³
TOTAL 11.79 m³
0.21 3.03 m³
1.00 14.80 m2
0.30 0.95 m³
11.55 535.43 m³
Total 535.43 m³
0.03 14.59 m³
176.00 no
Total 176.00 no
1.50 69.54 m³
2.28 11.40 m³ Type 2
Total 40.47 m³
0.40 m³ 1% of concrete
Total 3.18 tons
- 12.00 no
Total 12.00 no
- 97.35 m2
- 92.72 m2
- 0.65 m2
- 11.00 m2
- 16.00 m2
- 10.00 m2
- 4.56 m2
Total 232.28 m2
0.10 1.50 m³
Total 1.50 m³
312.00 no 24 Tie Bars Between two Ribs
126.54 m³
14.06 m³
7.03 m³
35.00 no
#VALUE! no
18.00 no
70.30 m2
51.55 m³
11.79 m³
3.03 m³
14.80 m2
0.95 m³
535.43 m³
14.59 m³
6.83 m³
176.00 no
69.54 m³
3.18 tons
12.00 no
2306.30 Kg
187.79 m2
70.00 no
63.10 kg
398.54 kg
20.00 no
18.78 m³
60.00 m
12.00 no
120.00 m
232.28 m2
1.50 m³
312.00 no
20.71 248.53 m3
SUB TOTAL 223.68 m3
24.85 m3
6.3 3.42 m3
SUB TOTAL 3.42 m3
- 14.00 no
6.30 37.80 m2
0.50 1.58 m3
6.11 15.27 m3
TOTAL 16.85 m3
0.205 2.46 m3
0.30 2.37 m3
7.96 1733.29 m³
Total 1733.29 m³
0.03 51.87 m³
485.00 no AT 1m C/C
461.00 no At 2m C/C
Total 946.00 no
7.73 27.06 m³
0.03 2.34 Type 2
Total 27.06 m³
0.27 m³ 1% of concrete
Total 2.12 tons
15.40 7468.69 Kg
655.86 m2
240.00 no
9.56 252.38 kg 20% of Length of Type 1
1.58 1133.50 kg
60.00 no 25% of Length of Type I Category
0.78 67.59 m³
180.00 m
53.00 no
530.00 m 10m c/c
1.00
- 1121.00 no 19 Tie Bars connecting two ribs
223.68 m³
24.85 m³
3.42 m³
27.00 no
0.00 kg
14.00 no
37.80 m2
16.85 m³
2.46 m³
2.37 m³
1733.29 m³
51.87 m³
32.10 m³
485.00 no
461.00 no
27.06 m³
2.12 tons
69.00 no
7468.69 Kg
655.86 m2
240.00 no
252.38 kg
1133.50 kg
60.00 no
67.59 m³
180.00 m
53.00 no
530.00 m
1.00
1121.00 no
4.142 2.13 m3
SUB TOTAL 2.13 m3
0.00 #VALUE! kg
- 9.00 no
4.14 24.85 m2
0.50 1.58 m3
6.11 15.27 m3
TOTAL 16.85 m3
0.205 2.46 m3
0.30 2.37 m3
Total 2.37 m³
7.96 423.10 m³
0.03 12.66 m³
123.00 no AT 1m C/C
116.00 no At 2m C/C
Total 239.00 no
7.73 27.06 m³
0.03 2.34 Type 2
Total 27.06 m³
0.27 m³ 1% of concrete
Total 2.12 tons
- 18.00 no 50% OF Length of Adit Tunnel
Total 18.00 no
15.40 1995.13 Kg
9.52 m2
64.00 no
9.56 84.13 kg 20% of Length of Type 1
1.58 288.18 kg
5.00 no 25% of Length of Type I Category
0.78 0.98 m³
180.00 m
1.00 no
10.00 m 10m c/c
1.00
- 285.00 no 19 Tie Bars connecting two ribs
144.22 m³
16.02 m³
2.13 m³
18.00 no
#VALUE! kg
9.00 no
24.85 m2
16.85 m³
2.46 m³
2.37 m³
423.10 m³
12.66 m³
7.84 m³
123.00 no
116.00 no
27.06 m³
2.12 tons
18.00 no
1995.13 Kg
9.52 m2
64.00 no
84.13 kg
288.18 kg
5.00 no
0.98 m³
180.00 m
1.00 no
10.00 m
1.00
285.00 no
5.217 2.77 m3
SUB TOTAL 2.77 m3
0.00 #VALUE! kg
- 12.00 no
5.22 31.30 m2
0.50 1.58 m3
6.11 15.27 m3
TOTAL 16.85 m3
0.205 2.46 m3
0.30 2.37 m3
Total 2.37 m³
7.96 617.14 m³
Total 617.14 m³
0.03 18.47 m³
7.73 27.06 m³
0.03 2.34 Type 2
Total 27.06 m³
0.27 m³ 1% of concrete
Total 2.12 tons
15.40 2743.30 Kg
233.52 m2
88.00 no
9.56 105.16 kg 20% of Length of Type 1
1.58 403.45 kg
25.00 no 25% of Length of Type I Category
0.78 24.07 m³
180.00 m
19.00 no
190.00 m 10m c/c
1.00
399.00 no 19 Connecting Bars two ribs
157.13 m³
17.46 m³
2.77 m³
22.50 no
#VALUE! kg
12.00 no
31.30 m2
16.85 m³
2.46 m³
2.37 m³
617.14 m³
18.47 m³
11.43 m³
177.00 no
167.00 no
27.06 m³
2.12 tons
25.00 no
2743.30 Kg
233.52 m2
88.00 no
105.16 kg
403.45 kg
25.00 no
24.07 m³
180.00 m
19.00 no
190.00 m
1.00
399.00 no
8.207 4.57 m3
SUB TOTAL 4.57 m3
0.00 #VALUE! kg
- 16.00 no
8.21 49.24 m2
0.50 1.58 m3
6.11 15.27 m3
TOTAL 16.85 m3
0.205 2.46 m3
0.30 2.37 m3
Total 2.37 m³
7.96 246.60 m³
Total 246.60 m³
0.03 7.38 m³
74.00 no AT 1m C/C
69.00 no At 2m C/C
Total 143.00 no
7.73 27.06 m³
0.03 2.34 Type 2
Total 27.06 m³
0.27 m³ 1% of concrete
Total 2.12 tons
15.40 1246.96 Kg
93.31 m2
40.00 no
9.56 42.06 kg 20% of Length of Type 1
1.58 172.91 kg
15.00 no 25% of Length of Type I Category
0.78 9.62 m³
180.00 m
8.00 no
80.00 m 10m c/c
1.00
171.00 no 19 Tie Bars Between Two Ribs
203.91 m³
22.66 m³
4.57 m³
31.50 no
#VALUE! kg
16.00 no
1 Boulder Mixed Soil Excavation
2 Rock Excavation
3 50 mm Thick Shotcrete
4 M25 Concrete
5 Reinforcement in Concrete
6 Formwork
Pattern Bolting 2m Long ,20mm Dia Grouted Rockbolts at
7 1.5m*1.5m Centers.
Weepholes of 50 mm Dia,1.5m Long, 2 m C/C or Less As
8 Required.
9 Cover With wire mesh
10 CGI sheet in roofing (24 gauge)
2 Rock Excavation
Cyclindrical portion(Upto bottom of tunnel) 1.00 Area=
3 30 mm Thick Shotcrete
Cylindrical portion(Upto top of tunnel) 1.00 28.20
4 M25 Concrete
6 Formwork
Type F2
Cylindrical portion interior( from bottom upto 12.5m) 1.00 16.00
Cylindrical portion interior(above 12.5m) 1.00 16.70
Rock trap 6.00 0.60
SUMMARY
S.N. ITEM Unit Quantity
1 Boulder mixed soil excavation m ³
97.09
2 Rock excavation m ³
761.90
3 30mm thick plain shotcrete (M25) m³ 22.77
4 Plain concrete (M25) m³ 271.06
5 Reinforcement ton 21.28
6 Formwork
a. Type F2 m² 466.94
7 Rockbolts (25mm dia, 3m long)
a. with plain cement grout no 176.00
b. with cement capsules no 59.00
8 Weep holes (50mm dia, 2m long) no 132.00
9 4.75mm dia wiremesh @ 100mm c/c m² 304.76
10 Metal sheet( Cover) m ²
32.45
BREADTH IN m HEIGHT IN m QUANTITY UNIT REMARK
2.71
21.28 Ton
10.00 160.00 m2
18.25 304.78
0.60 2.16 678
234.00
176.00 No.s 75%
59.00 No.s 25%
84.75
132.00
32.45 32.45 m2
Remarks
List of quantities listed below
1 Excavation
1.1 Boulder mixed soil Excavation
1.2 Rock Excavation
2 Preparation of foundation
3 350mm thick stone soling
4 M25 Concrete
5 Reinforcements
6 Formworks
7 Concrete block masonry works
8 Backfilling and compaction
9 Screening and Punning
10 Iron works in Truss
11 Iron works for staircase
12 CGI sheet on walls (24 gauge)
13 CGI sheet for roofing (24 gauge)
14 12mm plaster work (1:4) in cement sand mortar
15 Distemper painting
16 2" MS pipe handrails
17 Woodworks in doors and fittings
18 Aluminium works in walls, doors, windows and ventilation
19 Grill fittings in windows and ventilations
20 Door shutter 4cm thick panelled including fittings, door locker and handle
21 Rolling shutter
22 Water supply and Sanitation works
23 Electrification
Detailed Estimate of
S.N. Item Description No
1 Excavation
Upto bottom level of machine foundation 1
For isolated footing of powerhouse 19
2 Preparation of foundation
Below isolated footing of powerhouse 19
Below isolated footing of control room and switchgear room 5
5
Base of powerhouse 1
Base of control room and switchgear room 1
3 350 mm thick stone soiling
Isolated footing of powerhouse 19
Isolated footing of control room and switchgear room 5
5
4 M25 concrete
Isolated footing
Powerhouse area
Rectangular portion 19
Trapezoidal portion 19
Control room and switchgear room
Rectangular portion of full isolated footing 5
Trapezoidal portion of full isolated footing 5
Rectangular portion of half isolated footing 5
Trapezoidal portion of half isolated footing 5
Tie beams
Across long walls of powerhouse 12
2
Across short walls of powerhouse 6
Beams
At powerhouse
At TG floor level
Across long walls of powerhouse 12
2
Across short walls of powerhouse 6
At intermediate level
Along long walls 8
Along short walls 2
Columns
At powerhouse
From above isolated footing upto gantry level 18
From gantry level upto roof truss level 18
Below slab of service bay 1
Shear wall
Along long walls 12
2
Along short walls 4
Slab
At service bay level 1
At TG floor below service bay 1
At control room and service bay 1
Mat foundation
Below staircase 1
Between two units 1
Below units 2
Deduct
Opening for canal 2
Deduct for turbine (Consider 5% of total concrete for units) 1
6 Formworks
For isolated footing
At powerhouse
Rectangular portion 76
Trapezoidal portion 76
Beams
Tie beams
At the powerhouse 12
24
2
4
6
12
At the control room and switchyard room 2
16
Beams
At powerhouse
Along long walls 48
96
8
16
Along short walls 20
40
Shear wall
Along long walls 24
4
Along short walls 8
Slab
At service bay level 1
2
2
At TG Floor 2
2
At control room and switchgear room 2
2
Mat foundation
Below stairs 2
2
Between units 2
2
Below units 4
4
For canal 2
1
1
5% of total formworks below units is added for turbine openings and accessories
At toilet/washroom 1
Deduct
Window openings 12
2
Ventilations 1
Doors 1
1
In landing
Angle (50*50*5) 9
Angle (50*50*5) 3
Flat MS sheet 1 (25*5) 12
4
Flat MS sheet 2 (25*5) 21
3
8mm chequered plate 3
1
15 Distemper painting
20 Door shutter 4cm thick panelled including fittings, door locker and handle
At door D1 1
21 Rolling shutter
At entrance 1
23 Electrification
Summary
10489.92 m3
Sub total 10489.92 m3
4495.68 m3
Sub total 4495.68 m3
3 3 0.3 51.30 m3
A= 5 0.35 33.25 m3
230.88 ton
Sub total 230.88 ton
3 0.3 68.40 m2
A= 0.7 53.20 m2
A= 116.337 116.34 m2
20.7 0.15 6.21 m2
6.91 0.15 2.07 m2
20.7 0.3 12.42 m2
6.91 0.3 4.15 m2
20.7 0.15 6.21 m2
7.2 0.15 2.16 m2
20 0.7 28.00 m2
6.8 0.7 9.52 m2
20 0.7 28.00 m2
4.35 0.7 6.09 m2
13.865 3.65 202.43 m2
20 3.65 292.00 m2
9.4 1.45 27.26 m2
9.4 2 18.80 m2
2 1.45 2.90 m2
24.72 m2
Sub total 6246.36 m2
1622.71 m2
Sub total 1622.71 m2
2.795 25.20 m
2.82 67.70 m
1 24.00 m
0.9 86.40 m
15.8 47.40 m
0.9 15.30 m
Sub total 266.00 m
2.1 1 -4.20 m2
Sub total 146.89 m2
7.8 0.02 0.005 0.07 ton
6 0.02 0.005 0.01 ton
5.61 6 33.66 m2
Sub total 33.66 m2
1.00 LS
Sub total 1.00 LS
1.00 LS
Sub total 1.00 LS
Quantity Remarks
14985.60
10489.92
4495.68
1426.95
113.84
2941.10
230.88
6246.36
146.86
8393.08
292.08
15.19
3.39
685.03
1270.68
1622.71
1622.71
266.00
0.004
146.89
0.48
1.78
33.66
1.00
1.00
Remarks
2 Preparation of foundation
From Column of powerhouse upto confluence point excluding gate 2 15.91
From confluence point to the end of tailrace 1 120.07
Below gate 2 3.2
4 M25 Concrete
From confluence point to end of tailrace 1 120.07
Along end of wall of powerhouse upto 0.9m distance 2 0.9
From confluence point upto 15m upto gate section 2 15
For gate portion
Bottom slab along canal 4 3.2
Bottom slab at walls 4 0.4
Below gate 2 3.2
Top slab above canal 4 3.2
Top slab at walls 4 0.4
Side walls at canal 4 1
Above canal section upto broadening point 2 7.2
From broadening point to bottom of slab 2 8
Top slab 2 3.2
Deduct
Gate opening at slab 2 2.6
6 Formworks
For canal works
From end of tailrace upto confluence point of tailrace
Bottom slab 2 120.07
2 2.6
For side walls
Inside face 2 120.07
Outside face 2 120.07
End face 4 0.3
Top slab 2 15
4 2.6
4 15
From outside wall of powerhouse upto 0.9m upto gate section L= 0.9
Bottom slab 4 0.9
4 2.6
For side walls
Inside face 4 0.9
Outside face 4 0.9
End face 8 0.3
9 Bitumen Sealant
Base 9 5.2
Side walls 18 2.9
Top Slab 9 5.2
Summary
A= 62.56 1057.90 m3
A= 51.10 6135.82 m3
Sub total 7193.72 m3
5035.60 m3
Sub total 5035.60 m3
2158.11 m3
Sub total 2158.11 m3
2.6 82.73 m2
2.6 312.18 m2
1 6.40 m2
Sub total 401.31 m2
A= 2.43 291.77 m3
A= 2.43 4.37 m3
A= 2.43 72.94 m3
32.21 ton
Sub-total 32.21 ton
0.3 72.04 m2
0.3 1.56 m2
1.45 348.20 m2
1.45 348.20 m2
1.45 1.74 m2
2 240.14 m2
0.3 1.56 m2
0.3 72.04 m2
0.3 18.01 m2
0.3 3.12 m2
1.45 87.05 m2
1.45 87.05 m2
1.45 3.48 m2
2 60.03 m2
0.3 3.12 m2
0.3 18.01 m2
0.3 1.08 m2
0.3 3.12 m2
1.45 5.22 m2
1.45 5.22 m2
1.45 3.48 m2
2 3.60 m2
0.3 3.12 m2
0.3 1.08 m2
0.6 7.68 m2
0.6 2.40 m2
0.3 3.12 m2
0.3 0.36 m2
1.45 5.80 m2
1.45 2.32 m2
1.45 6.96 m2
1.45 3.48 m2
3.2 3.84 m2
0.3 1.20 m2
0.3 3.84 m2
1.755 22.46 m2
1.755 2.11 m2
5.124 65.59 m2
5.124 6.15 m2
0.3 3.84 m2
0.3 0.78 m2
Sub total 1533.20 m2
A= 73.20 1112.59 m3
A= 126.42 884.94 m3
A= 139.02 2350.83 m3
A= 43.214 5188.70 m3
Sub total 4768.53 m3
23.4 m
26.1 m
23.4 m
Sub total 72.90 m
46.80 m
52.20 m
46.80 m
Sub total 145.80 m
0.3 7.02 m2
0.3 7.83 m2
0.3 7.02 m2
Sub total 21.87 m2
Remarks
Data considered
Section of canal
Inside Width 2m Same for the canal section after turbi
Inside Depth 1.45 m and after combination of two canals
Concrete thickness 0.3 m Across all faces
Total Length of canal 136.98 m 1:500 slope from end of wall of powerho
Length of canal upto confluence point from outside wall of powerhouse 16.91 m
Remaining canal length 120.07 m