Documente Academic
Documente Profesional
Documente Cultură
Absent:
Ken-Pal (KP) : Mr. Sng K.Y. 93829138
: Mr. Sai Ywet Hark 92761841
: Mr. Lin Chen Qing 96809411
: Ms. Debby Zheng 85064538
Page 1 of 1
6
3U Construction (3U) : Mr. Zhou Jun Qing 96850989
Page 2 of 2
6
dormitories).
e. KP informed all sub-cons that 15 demerit points were issued to KP as a result of an All to note, especially
incident on site involving TH’s worker injuring himself from a falling piece of TH
formwork while striking formwork. TH to step up on safety efforts.
f. TH is required to submit an incident report to KP WSHO pertaining to an incident TH
involving 2 TH workers injuring themselves while using the makita tool. The incident
happened on Monday, 23 Jun 14.
g. KP WSHO reminded TH to install temporary metal staircase at MSCP. TH
h. KP WSHO reminded TH of any unused internal scaffolding to be cleared. TH should TH
not be using any loose platform for working without proper securing.
i. KP WSHO caught TH’s worker not wearing safety glasses while performing cleaning TH
duties.
j. KP WSHO reminded Shin to cover all plumbing openings at Blk 871C. Shin
Block Progress
870A Excavation: 100%
Pilecaps and stumps: 100%
Backfill : 100%
P&S IC and U/G pipes : 100%
1st sty slab : 100%
2nd sty slab: 100%
Page 3 of 3
6
3rd sty slab: 100%
4th sty slab: 100%
5th sty slab: 100% C&S/KPS/TH to note
6th sty slab: 100%
7th sty slab: 100%
8th sty slab: 100%
9th sty slab: 100%
10th sty slab: 100%
11th sty slab: 100%
12th sty slab: 100%
13th sty slab: 100%
14th sty slab: 100%
15th sty slab: 66%
Block 870B (MSCP & ESS) Pilecaps and stumps: 100%
Backfill: 100%
P&S IC and U/G pipes: 70%
1A slab: 100%
1B slab: 100%
2A slab: 100%
2B slab: 100%
3A slab: 100%
3B slab: 100%
4A slab: 100%
4B slab: 100%
Block 871C Excavation: 100%
Pilecaps and stumps : 100%
Backfill : 100%
P&S IC and U/G pipes : 100%
1st sty slab : 100%
2nd sty slab: 100%
3rd sty slab: 100%
4th sty slab: 100%
5th sty slab: 100%
6th sty slab: 100%
7th sty slab: 100%
8th sty slab: 100%
9th sty slab: 100%
10th sty slab: 100%
11th sty slab: 100%
12th sty slab: 100%
13th sty slab: 100%
14th sty slab: 100%
15th sty slab: 100%
Block 871B Excavation: 100%
Pilecaps & stumps: 100%
Backfill : 100%
P&S IC and U/G pipes : 100%
1st sty slab : 100%
2nd sty slab: 100%
3rd sty slab: 100%
4th sty slab: 100%
5th sty slab: 100%
6th sty slab: 100%
7th sty slab: 100%
8th sty slab: 100%
9th sty slab: 100%
10th sty slab: 100%
11th sty slab: 100%
12th sty slab: 100%
Page 4 of 4
6
13th sty slab: 66%
14th sty slab: 33%
c. Structural clearance:
Page 5 of 5
6
c. Shin to follow up with comments given by HDB Fire Safet Audit and to finish up the
outstanding works by 26 July 2014. Shin
d. (Afternote) Shin informed that all the pumpsets/piping material/ control panels, etcl Shin
for transfer tanks will be delivered on site by July 2014 and target finishing in early
Aug 2014.
e. (Afternote) Shin informed that the ordering of sanitary wares will be based on latest Shin
OCS schedule and completion of tiles laying works in toilets.
f. (Afternote) Shin to follow up with the tapping point of water supply to planters’ Shin
irrigation system as per given via email.
16.0 The next meeting will be scheduled at 10.30 am, 1 Jul 2014 at Project Site office Meeting
Room.
A.O.B: NIL
Page 6 of 6
6