duagon
This User's Guide is written for the application
engineer dealing with MVB in railway vehicle
applications.
Page 2/109 d000656-003145 duagon

Duagon Data Sheet Preamble

On having purchased products described in this data sheet, the customer acquires the right
to use the products according to its specified purpose and in accordance with all operation,
service and maintenance instructions. All other rights to the product, Duagon's intangible as-
sets rights in particular, belong solely to Duagon and may not be deemed to have been as-
signed along with the sale of the products.

All product properties are fully described in the data sheet under express exclusion of any
warranty for other properties. Of decisive relevance is the data sheet valid at the time of the
order being placed. Duagon provides a warranty that the product properties are retained
during the period of warranty. Evidence that the properties of the product have been re-
tained will be brought, always and exclusively, on Duagon premises by means of a test con-
struction pursuant to the type test.

The customer is obliged to inspect whether the products themselves are suitable for the ap-
plication intended. In particular, that inspection must include the integration of the products
into the intended system configuration and a check on whether the properties as per data
sheet can be fulfilled once integrated into the system configuration as planned by the cus-
tomer. Since the products are not certificated for operation with security applications, the
customer must take appropriate measures to ensure that any malfunctions that may occur in
a system configuration with other products will be absorbed by supplementary security mea-
sures.

The period of warranty for the products is 24 months and it begins on the date the products
are shipped from the factory.

The warranty that Duagon assumes for the products will, at Duagon's discretion, be limited
either to the repair of or the replacement of the products at the Duagon factory. The warran-
ty solely covers the products or parts thereof which, despite professional handling, have be-
come defective or unusable and which arrive at the Duagon factories for repair or replace-
ment during the period of warranty. The extent of Duagon's warranty is fully set out in this
data sheet. Duagon cannot be held liable for consequential damage caused by a defect or
for indirect damage or for consequential damage of any kind. Therefore the customer bears
all and any costs that occur due to production downtime, for example, or due to the installa-
tion or dismantling of products or due to their transportation to Duagon and back.
Duagon's liability and warranty do not obtain if evidence cannot be brought that the prod-
ucts were being operated according to its specified purpose and in accordance with all oper-
ation, service and maintenance instructions as issued by Duagon.

These provisions form an integrated part of the product properties. Duagon products cannot
be acquired with other or more extensive degrees of warranty and liability on the part of Du-
agon.

This data sheet is to be evaluated in accordance with Swiss law. The court of jurisdiction is
the seat of the vendor. The applicability of the UN agreement as to international sales of
goods (also known as "Viennese Purchasing Convention") is herewith expressly excluded.

duagon GmbH, Badenerstrasse 21, CH-8953 Dietikon, Switzerland


Phone: +41 1 7434012, Fax +41 1 7434015, www.duagon.com

Document history

Rev. Date Author Comments Ident-Number


1 August,14th 2004 Schlage First release d000656-002181
2 May, 27th 2005 Schlage d000656-003145
3
4
5
6
7
8

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 3/109

Table of contents

Introduction........................................................................................5

General Network Architecture...........................................................6


MVB Bus Traffic........................................................................................8
Process Variables...................................................................................10
Process Data Ports........................................................................................11
Process Data: Bus Broadcasting.....................................................................12
Data Consistency..........................................................................................14
Invalid Variables, received ...........................................................................15
...or transmitted............................................................................................16

Message Data MD.................................................................................17


Traffic Store Interface............................................................................22
Timing Structure....................................................................................25
Frames.........................................................................................................25
Basic Period..................................................................................................27
MF&SF Time Requirements............................................................................28
Basic period time requirements.....................................................................29
PD Periodic Polling.......................................................................................30
MD Event Arbitration....................................................................................31
Macro Period................................................................................................32
Turn - BA Mastership Transfer.......................................................................32

MVB System Engineering.................................................................33


Selection of Classes...............................................................................33
Porting Software into Host Systems........................................................35
How to put a new node into operation...................................................36
Real world performance.........................................................................39
Failures, Failures, Failures.....................................................................40
Applying Redundancy in general............................................................42
Applying Redundancy in MVB Based Control Systems.............................44
Safety...........................................................................................................44
Redundancy of Bus Nodes.............................................................................45
Network Topology.................................................................................49

Physical Layers.................................................................................53
Termination...........................................................................................53
Insulation Concepts...............................................................................54
Shielding Concept.................................................................................55
Wires & Redundancy..............................................................................57
How to find cable faults by wire redundancy information...............................64
How to find cable faults by other checks........................................................72

Comparison EMD – ESD+......................................................................74

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 4/109 d000656-003145 duagon

Electrical Short Distance Bus ESD, ESD+................................................76


Typical Node Structure ESD+........................................................................76
Terminators ESD+........................................................................................77
Pin definition ESD+ .....................................................................................77
Terminator Supply ESD+...............................................................................78
MVB Cable Attachment ESD+.......................................................................78
Electrical Middle Distance Bus EMD........................................................79
Terminators EMD..........................................................................................80
Pin definition EMD........................................................................................80
MVB Cable Attachment for EMD....................................................................81
Cables...................................................................................................82
Cable Structure............................................................................................82
Technical data..............................................................................................83
Wire allocation.............................................................................................84
SUB-D- connectors................................................................................85
Cable hood examples...................................................................................86

Reflections.............................................................................................88
What are reflections?....................................................................................89
Open end....................................................................................................90
Short circuit..................................................................................................90
Capacitive Mismatch.....................................................................................91
TDR measurement conclusions......................................................................92
Interference by reflections.............................................................................92

ESD end delimiter..................................................................................93


Oscilloscope Checks..............................................................................95
Everything OK..............................................................................................96
Everything OK..............................................................................................97
Terminator missing.......................................................................................98
Full Bus Load ESD+......................................................................................99
Full Bus Load EMD......................................................................................100
ESD+ Power equalisation line.....................................................................101
ESD+ Loss of Bias.......................................................................................102

Mixed pickles.................................................................................103

Appendix A: Error counters for duagon products..........................105

Index..............................................................................................108

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 5/109

Introduction
This User's Guide is written for the application engineer dealing with MVB in rail-
way vehicle applications.
Three main areas are covered:
• Understanding
The basics of the MVB world are presented in a condensed way.

Implementation
Build your own network: start from network topologies, optimise your
own decisions about e.g. engineering effort, bandwidth performance,
redundancy, cost, time to complete.

Practical work
Take measurements to verify the network performance; analyse and
interpret failures in a correct way. Special attention was put on inter-
operability issues.
This document reflects the personal experience of the author, based on daily busi-
ness within the company “duagon GmbH”. This is not an advertisement or a com-
mitment for technical data, though – it is much more a collection of issues beyond
the scope of usual product documentation.
This user's guide shall be a general help for the application engineer, and hope-
fully this “knowledge snapshot” will be enhanced in future by feedback arriving
from the field: It is understood to be a living document; i.e. comments and contri-
butions are invited: contact the author thomas.schlage@duagon.com.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 6/109 d000656-003145 duagon

General Network Architecture


TCN – Train communication network
The “TCN” Train Communication Network is a network with two hierarchical lay-
ers:

The WTB connects the vehicles within a train


The MVB connects the devices within one vehicle

WTB WTB node (Gateway)

MVB MVB Devices

WTB - Wire Train Bus


The technical key specifications of the WTB are:

Main application: open trains with variable composition such as UIC


trains

Covered distance: 860m


Number of nodes: 32 max.


Data rate: 1 Mbits/second over shielded, twisted wires


Response time: 25ms


Inauguration: assigns to each node its sequential address and orien-


tation
The key issue is the interoperability between different vehicles:

vehicles of different type: with and without traction, specific types like
sleeping or dining coach

vehicles from different manufacturers


vehicles passing the border from one railway operator to the next one
If all these facettes of interoperability shall be fulfilled, a standardisation beyond
the communication network takes place:

The TCN network with WTB and MVB defines how information is ex-
changed

Other standards define, what information content is exchanged.


For example, various UIC leaflets define the meaning of exchanged information.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 7/109

MVB Multifunction Vehicle Bus


The technical key specifications of the MVB are:

Data rate 1.5 Mbit/s , data frame size 16-256 bits


Cyclic transmission of process data (broadcast)


Event driven message data transfer (point-to-point)


Full support of redundancy


Three physical layers:


OGF optical fibres 2000m


EMD twisted pair 200m, 32 nodes


ESD twisted pair 20m, 32 nodes


with galvanic insulation 200m
The key issue is the cost versus performance optimisation within a vehicle:

Integrate communication to various subsupplier´s devices into one ve-


hicle; e.g. traction equipment, door controllers, displays, driver´s cab
control equipment.

The focus of optimisation follows the type of vehicle. The network may
be more or less complex; the requirements about availability are dif-
ferent.

The cost optimisation of the network nodes takes place on complete


units. The network equipment is a small part within the subsuppliers
scope of delivery; the competition works on complete units like power
converters, doors, passenger information systems, vehicle control sys-
tems.

For the vehicle supplier, the cost of integration, i.e. application engi-
neering, is dominant. The MVB matches railway specific requirements,
and the standardisation ensures reusability of engineering work.

The support cost during years of operation drives the use of standard-
ised communication equipment: one tool set for the whole vehicle;
support of later retrofit options from an open supplier market.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 8/109 d000656-003145 duagon

MVB Bus Traffic


State Variables

Control switches
Temperature

Open door button

Motor power throttle Door is locked

Speed

The Variables reflect the state of the plant.


The information content is “small”: From a single bit up to a several


bytes

Their typical response time is in the range of 16 to 256 ms.


Examples are driver commands, speed or temperature information.


The variables are periodically transmitted.


Spurious data losses will be compensated at the next periodic cycle.


The use of the variables may be at multiply points wide spread over
the vehicle

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 9/109

Messages

From “black box” event recorder to


position detection system:
Tell me time and location.

From brake to diagnostic display:


“Get brake service after 5000 cycles”

Messages contain the events of the plant.


On-demand transmission from one point to another point.


The size of a single message may be “big”: practical size of up to sev-


eral 100kBytes.

Response is at human speed: >0.5s.


There is a flow control & error recovery protocol for catching all
events.

Examples during normal operation are on-line diagnostics, passenger


information, event recorder.

During commissioning or field service, messages are used for soft-


ware download and collection of debugging data.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 10/109 d000656-003145 duagon

Process Variables

Distribution of Process Variables over the bus


One “publisher application” generates the process variable and places it in the
traffic store of the generating device.
From the traffic store of the generating device, the process variable is distributed
over the MVB. After transmission over MVB, the process variable is available in all
traffic stores.
A “subscriber application” reads the process variable from its local traffic store.

subscriber publisher
application application
instance instance

traffic store
instance
device
bus
instance MVB

traffic store traffic store


instance instance

subscriber subscriber
application application
instances instances
device device

There exist a number of instances of the same process variable.


These instances are inconsistent to each other. The distribution from


the publisher application to the subscriber application takes time,
even if both are located on the same device.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 11/109

Process Data Ports


Several process variables, which are intended to be distributed from the same de-
vice, are collected together to form a “dataset”. A dataset is transmitted within
one “process data port”.

Process variable 3
Process variable 2
Process variable 1

Process data port

The process data port as a whole is actually sent over the MVB, not
the single variables.

The definition, how the variables are collected together, is done by


the application engineer. This definition will follow practical consider-
ations like source device, repetition frequency over the bus, size of
variables, clustering of variables with a functional relationship.

Obviously, the definition of the variables must be the same for all de-
vices on the bus:

Preferably the variable definition should be done with the fo-


cus on the overall MVB traffic, together with the MVB bus ad-
ministrator configuration. A tool then generates different
configuration files for all involved devices.

Sometimes, the import of such a variable definition is not


possible; e.g. due to not matching engineering tools. Then,
the definition must be maintained separately: Be sure to
keep track of changes!

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 12/109 d000656-003145 duagon

Process Data: Bus Broadcasting


Step 1: The bus administrator sends out a request for a PD port, which is located
on node 34. On the bus, this is represented by a “master frame”.

Bus node node node node node node


admin 33 34 35 36 37 38

Sends
master frame

Step 2: Reading the master frame from the bus most devices realise, that they are
not involved so far. However, node 34 is alarmed to send out the requested PD
port.

Bus node node node node node node


admin 33 34 35 36 37 38

match!

Step 3: Node 34 sends out the PD port, and everybody else listens to it (= broad-
casting). On the bus, this is represented by a “slave frame”.

Bus node node node node node node


admin 33 34 35 36 37 38

sends
PD port

Step 4: Some of the listening nodes are interested in the PD port sent over the
bus. They will store this PD port in their local traffic store; for later use by their ap-
plication.

Bus node node node node node node


admin 33 34 35 36 37 38

stores stores stores


PD port PD port PD port

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 13/109

This way of PD port distribution has some consequences:


The bus administrator initiates the PD transfer, but it does not need to
understand any data. Data is received on PD- nodes, only. However,
the administrator function can be integrated within a normal node;
then all activities are executed transparent to each other.

The bus administrator addresses “logical ports”, not the device ad-
dresses of the involved nodes. By this way, each node may have more
than one source port.

For one “logical port address” there is exactly one node having this
port defined as a “source”.

The time, when PD data is received or transmitted, is not influenced


by the slave nodes; the have simply to react. By this way, there is no
need to configure the nodes with any timing related parameters. All
timing configuration is to be done on the administrator.

The slave nodes have to be configured with the following information:


The “source” ports (the ports to be transmitted).


The size of the ports: Even though this information could be


derived from the master frame, it is used for an additional
plausibility check during reception or transmission of ports.

For simple applications, an individual node may need only a


few PD ports. Thus it may make sense to identify a reduced
set of PD “sink” ports (ports to be received). By this way, a
cost effective small traffic store may be applied.
More complex nodes will typically implement the whole PD
port address space: The theoritical maximum for PD is: 4096
ports * 32 bytes = 128 kBytes. Such nodes will not need “sink
port configuration”, since they will store all possible logical
ports, anyway.

The bus administrator has to be configured with the following infor-


mation:

All used logical port addresses.


The size of all used ports.


The repetition rate of all used ports.


This information is sufficient for a fully functional bus administra-
tor. However, some administrator implementations require some
more data (which is separated from the PD traffic):

A list of device addresses (existing nodes) together with their


MD and BA capabilities. Note: This information can also be
dynamically derived from watching the bus traffic.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 14/109 d000656-003145 duagon

Data Consistency
In some cases, different variables, being defined at a common point in time, must
be kept together.
The feature “consistency” is mandatory for variables within one PD port
(“dataset”). Note: Any additional “clustering” of variables does not extend the
consistency beyond the port/ dataset.
Example:
The source distributes the variables DAY, MONTH, YEAR at the same time, within
one source port, representing a “date”:

DAY MONTH YEAR


31 12 2004

A certain time later, the source distributes the variable DAY, MONTH, YEAR
again; but now with changed contents:

DAY MONTH YEAR


01 01 2005

Since the distribution of variables over the MVB takes some time, any subscriber
of these variables will get the new data somehow later.
However, there is a strong requirement of “data consistency”: Any subscriber of
these variables will receive either the first or the second set of variables, but never
a mix of both: This means “consistent data contents”.

Imagine, a wrong working subsriber node would receive the first variables DAY
and MONTH from the first transmitted set; then it is interrupted by the MVB trans-
mission of the second variable set and gets YEAR from the new set:

DAY MONTH YEAR


31 12 2005
Obviously, the result is completely wrong. It does not reflect neither the first nor
the second set of variables, but something different.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 15/109

Invalid Variables, received ...


There may be several reasons, why variables could be invalid. Of course, any de-
vice receiving variables should be aware of this and act in a reasonable way. This
could be for example to switch off all outputs and enter a safe state or to use data
from a redundant source:

The source device worked fine, but now Freshness


fails completely (like power off) or the
communication to the source device is The freshness information
interrupted (e.g. broken cable): comes with every received
Every variable includes information variable.
about the “freshness”. This “age of the
variable” can be used to decide, An UNSIGNED16 represents
whether it is still to be considered OK the time being elapsed from
or not. A reasonable level is for exam- the last valid reception up to
ple twice the repitition time for PD; or now: 0 is “just born”; 2000 is
2seconds at most. 2 seconds, which is fairly old;
By this way, a single loss of a data and 65535 is the outmost
frame is still not detected as an error;
value, which does not “age”
an error requires two or more consecu-
tive losses. any more.
Please note, that this limit as well as When you get a 65535, the
the reasonable reaction upon data loss port has most probably never
is defined by the application engineer. been received.
The MVB driver software just delivers
the freshness information, nothing more.

The source device is still working, but


some specific variables are not valid Check_Variable
any more: The validity of a variable is
This could be one defective sensor
confirmed by a Check_Vari-
among others in normal operation. Or
a gateway collects variables from dif-
able. It is defined in the
ferent sources and one of these is miss- same dataset, type ANTIVA-
ing. LENT2:
For this purpose, the application engi-
0b00: the protected vari-
neer should introduce “check
variables”. These declare variables to
ables are erroneous
be either valid or erroneous. One or suspicious;
check variable may be used for several 0b01: the protected vari-
variables.
ables are assumed to
The MVB driver software does not
recognise invalid variables in between
be correct;
valid ones: the MVB communication by 0b10: the protected vari-
itself was successful. ables have been
The application engineer has to take
forced to an imposed
care about the introduction, configura-
tion and use of check variables.
value (set to a certain
value on purpose e.g.

The source device has sent correct for debugging; to be


data, but the sink receivers get single understood as correct)
or multiple bit errors.
This case is checked by the MVB con- 0b11: the protected vari-
troller according to several methods. ables are undefined
This includes a plausibility check of the
Manchester coding, start and end delimiters, cyclic redundancy checking, pari-
ty bit, check of the timing between master and slave frame. The result of this
check is very reliable; and the result from finding an error is always the same:
the data is not presented to the upper software layers. As a result, the user will
face missing data, and may react as described before.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 16/109 d000656-003145 duagon

...or transmitted
Transmission of invalid variables is absolutely forbidden! It is up to the user to ac-
tively avoid some critical cases:

The application software must make use of a watchdog. In case, the


software is locked in an eternal loop, the PD is still actively distributed
over the MVB, taking data from the traffic store. This keeps “old” data
perfectly fresh on the receiver´s side.
After a while, the watchdog fires and the complete CPU system dives
through a reset. Be sure, that the watchdog reset really arrives at the
MVB interface: When reset, the interface has to definitively shut off
any MVB activity.
Afterwards, the software may come back to life again and configure
the MVB interface another time.

If an application is able to detect an invalid state of a variable, it must


pass this information with the variable. This could be by the use of
check variables, but also by stopping the transmission of source ports,
or by stopping MVB traffic at all (software reset).

Life Sign Reception


Quite often, a different method for vari-
able verification is used: “Life_Sign” or “ Life_Sign
heart beat”. This method has been proven A single bit is toggled from 0
by experience, but please note some basic to 1 and vice versa; with a
drawbacks:
rate of e.g. once per second.

The life sign does not prove


On sink side, the toggling bit
the valid transmission of pro-
cess variables in the sense of gives confidence about the
MVB transmission. There is no health of the source device;
particular rule, that “unde- this applies also to the re-
fined” PD data in the traffic ceived process variables.
memory must be “constant”.
For this purpose, use in any
case the freshness information.

The life sign may prove valid execution of the source device´s internal
task structure. Of course, this is an important information. However,
have a look into using a watchdog on the source side: It would serve
the same purpose, too and has the benefit of restarting the complete
device.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 17/109

Message Data MD
Functions and Devices
Each vehicle supports a number of standardised functions.
The Train Bus accesses vehicles without knowing their internal structure.
The train bus accesses functions rather than devices.
These functions are implemented by one or several vehicle bus devices, or even
by the gateway itself.
The gateway deduces the device from the function and routes messages.

WTB WTB-MVB Gateway

MVB MVB devices

Sensors and
Actors

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 18/109 d000656-003145 duagon

Client- Server Service


The application interface for messages provides a “call with reply” service.
Applications communicate among themselves on a Client- Server basis.
Tasks use the same communication scheme:

within the same processor


within the same vehicle bus


within the Train Communication Network.

Caller Replier
Transport Network Transport
layer layer layer Receive request
Call request
CAL
L

Receive confirm
Replier
time F
out LY
REP Reply request

Receive request
Call confirm
time
Example: The Caller issues a Call request. To a high extent, this looks like “in-
voking a function” as it is used in usual software source code. According to the
kind of function, parameters are attached to the “call” as well as to the “reply”.
In contrast to usual software, where the calling and the replying code is executed
on the same processor, the function is executed on a remote node, the “server”.
The server may not be available or the communication may be somehow dis-
turbed. This requires the use of some administrative effort: Timers will mark a
function as being “unavailable”, which unblocks the Caller´s software execution.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 19/109

Transport: Frame Exchange in one Direction (Call or Reply)


A transport exchange consists of three phases: connection, transfer and discon-
nection.

Session Session
layer Transport Network Transport layer
Producer layer layer layer Consumer
tm_message.req Connection
conne
c t r eq
uest

connect sm_connect.ind
time sm_connect.cnf
out

nfirm
ct co
c onne

alive
time
Transfer out
ack data(0
time
)
out ack(1)
alive
time
data(1 out
ack
)
time
out ack(2)

data(
last)
ack sm_message.ind
time
out ack(last)
late
sm_message.cnf Disconnection acks

In this example, the transfer takes place with window size = 1. In case, there was
a higher window size negotiated, the producer´s transport layer will send a high-
er number of data frames before waiting for an acknowledge.
Various time-outs ensure, that any spurious losses of frames will lead to a repeat-
ed transmission. In this sense, the execution flow in the drawing is simplified: the
retry paths are not shown.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 20/109 d000656-003145 duagon

End- to- End Transport Protocol

(router) (router)
Application Application Application Application

Presentation Presentation Presentation Presentation

Message Session Session Session Session


Transport
Protocol Transport Transport Transport Transport

Network Network Network Network

Link Link Link Link Link Link

Physical Phys Phys Phys Phys Physical

MVB segment WTB segment MVB segment

The “Message Transport Protocol” is able to route between different links. The ex-
ample above demonstrates the routing from one vehicle via the WTB train bus to
another vehicle.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 21/109

Foreign Devices & Bus Systems


It is possible to link other bus systems to the MVB bus.
This is done by the use of gateways:

Since the Network Layers are not compatible to each other, the routing of
message data has to be done via the application layer.

The PD marshal picks out data from one side and copies it to the other side;
and vice versa.
In order to ensure successful operation:

The protocol conversion requires a common object address space.


Common data representation and semantics is important.


Therefore, a standard object description is needed.

Gateway

MD conversion

PD
Application Application
marshalling

Presentation Presentation Presentation Presentation

Session Session Session Session

Transport Transport Transport Transport

Network Network Network Network

Link Link Link Link

Physical Phys Phys Physical

MVB segment Other bus system

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 22/109 d000656-003145 duagon

Traffic Store Interface


The interface between the bus and the application is the “traffic store”. This is a
shared memory, which is accessed by the application and the bus traffic.

up to 4095
PD ports

MD FIFO buffers
Rx and Tx

Bus supervision
& administration

Traffic store

Application MVB

MVB controller
Device

The MVB- controller handles the interface of the application and the MVB bus
into the traffic store. This function is implemented in a highly integrated logic
chip.
The accesses from the application and the bus into the traffic memory are not syn-
chronised to each other: usually, both sides will follow their own timing, indepen-
dent from each other.
If the accesses occur by coincidence at the same time, an arbitration logic within
the controller chip has to decide, which access is to be processed first. During this
time, the other side is delayed.
Note: There is no direct interaction from the application to the MVB. All commu-
nication has to pass the traffic store, and the timing of bus traffic is determined
from the bus administrator on the outside.

How to access the traffic store


For full complexity nodes, the market is divided into two major controller families:
• The “MVBC01” was the first available ASIC chip; originally devel-
opped by ABB (now Bombardier) and Siemens. In the meantime,
some proprietary new family members appeared.
• The “UART emulation” based MVB controller from duagon. Several
versions with application specific optimisation are available.
The traffic store interface has to handle the full set of MVB functionality from Class
1 to 4: PD, MD, BA. This requires memory space of at least 256kByte. Since this
amount of memory is usually not included within a logic chip, a separate SRAM
chip is used.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 23/109

In both cases, the controller arbitrates the accesses from the application and the
MVB side. However, there is a difference about the organisation of data, which is
transferred between application and traffic store.

Dual Port RAM Traffic Store Access


The software addresses each single word in the traffic memory. In order to per-
form a complete Link Layer function like a PD port read, the software will perform
a sequence of several memory accesses.
The MVB- controller- internal arbitration works in a word- by- word- manner; and
a single access may be delayed (dynamic wait states, up to several 10 µs).

Software
addresses
memory cells
Traffic store
within e.g.
256kBytes
of SRAM
MVB
ARB
MVBC01 controller
Device

In order to keep data consistency, the MVB controller has implemented a special
protocol to avoid write actions during a read sequence of the same port (called “
two page protocol”). While a read of a port takes place in one page, a simultane-
ous write to the same port takes place on the second page. By this way, data con-
sistency is perfectly kept, as long as the read of a port is completed within the PD
repetition time on MVB.
This real time requirement is usually kept by “real time operating systems”, for ex-
ample for PD port repetition rates of 128ms and higher. If faster repetition rates
have to be supported, a software expert may introduce an “interrupt disable” dur-
ing the PD port read. Then, any other interrupt (like the OS tick timer) is delayed
until the end of PD port read. This delays the overall interrupt latency figure in the
range of several 10 to 100 microseconds.
A problem occurs, when a non- real-time- OS is to be used. A good example is
Microsoft Windows in its various derivatives. Several tools are on the market, in-
tended to enhance the RT- behaviour, but these are not very comfortable, since
they rely on a specific Windows version; an update may be expensive, uncomfort-
able or not possible.
To avoid this difficulty between Windows and the MVBC01, a wide spread com-
promise is to prohibit any use of data consistency beyond one word.
The first representative of this architecture is the MVBC01. Newer derivatives im-
plement “semaphores” in the traffic memory. They temporarily disable accesses
from the MVB- side. By this way, data consistency is kept without real time re-

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 24/109 d000656-003145 duagon

quirements; however newer data is lost during the disable time, which yields ad-
ditional latency.

Encapsulated Traffic Store Access


The software issues “commands and parameters” into a “serial line” and waits for
“results” being sent back. The command packets are defined close to what is de-
fined in the link layer; e.g. they include the handling of complete PD ports.
The transferred data packets contain complete sets for the required action and
are stored in FIFOs of the controller chip.
The arbitration to the traffic store is done “packet by packet”. The single access to
the UART emulation is of a fixed timing, i.e. dynamic wait states are not required.

Software
deals with
LL commands/
Traffic store
results:
“UART
emulation”
MVB
FIFO
buffers ARB
Duagon MVB controller
Device

No real time requirements are left for the traffic store handling; even the use of
Microsoft Windows is no problem any more: Data consistency is always kept.
Note: There are still real time requirements; for example application imposed re-
quirements or for the message data protocol stack. However, the involved timings
are much more relaxed in terms of absolute numbers: several 100 milliseconds to
several seconds.

Note: The expressions “UART” or “serial line” may sound like being slow. This is
not true: The UART emulation just uses the simple register model of a UART; the
data transmission itself is very fast. The worst case delay from issuing a command
to the reply is below 10µs; reading the whole FIFO in single bytes takes approx.
25µs (widely depending on host CPU and local bus speed).

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 25/109

Timing Structure

Frames
All transmission of data is organised within a “master frame – slave frame” se-
quence. The master frame is always issued by the bus administrator; the slave
frame is issued by various devices, depending on which device was addressed by
the master frame.

Master frame Slave frame

22µs t_ms 22µs - 198µs t_sm


t_mm

The picture shows the most important timing relationships:


• The length of the master frame (MF) is fixed to 22µs; this represents
16 bits of transmitted data (net data, without start & end delimiter).
• The time between a master frame and its related slave frame (t_ms) is
from 2µs to 42.7µs. Any slave node has to reply within 6µs; the rest is
delay for the frames travelling along the line and crossing repeaters.
• The length of the slave frame depends on the type of data being
transferred; with a data contents of 16 to 256 bits.
• The time from the end of a slave frame to the beginning of the next
master frame (t_sm) is at least 3µs.

The master frame is structured in two bit fields:

Master Frame Structure


0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

F-Code Address

Note: The numbering of the individual bits within a frame reflects the sequence
how the data is transmitted over the MVB lines. In usual microprocessors, the
numbering of data bits within a word is in the opposite direction.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 26/109 d000656-003145 duagon

The table lists all possible MF- SF combinations:

Master frame Slave frame


Size
(bits Destina-
F-code Address Request Source ) Response tion
0 16
1 32 All de-
Single device
Process Process vices sub-
2 Logical subscribed as 64
data data scribed as
source
3 128 sink
4 256
5
6 reserved reserved
7
Mastership Proposed Mastership
8 Device 16 Master
transfer master transfer
General
One or more Event
9 All devices event (pa- 16 Master
devices identifier
rameters)
10
reserved reserved
11
Message Message Selected
12 Device Single device 256
data data device(s)
Device Group_ One or more Event
13 16 Master
group event devices identifier
Single Event
14 Device Single device 16 Master
event identifier
Master or
Device Device
15 Device Single device 16 monitor
status status
device

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 27/109

Basic Period
The basic period is divided into three major sections: periodic phase, supervisory
phase and event phase.

periodic supervisory &


phase event phase

base period 1.0ms next base period

• During the periodic phase, process data is transferred. The se-


quence of several MF+SF- frame pairs per base period is defined by
the bus administrator list: it may contain a mix of all PD frame
lengths, with 16 to 256 net data bits.
The contents of the periodic phase is determined during the engineer-
ing phase and can not be changed dynamically during operation.
• Supervisory data is the “device status scan” and the “bus mastership
transfer”.
The contents of this phase is automatically generated by the bus ad-
ministrator and will follow certain deterministic rules. But, there are
some aspects being decided dynamically during operation: e.g. the is-
sue of a “bus mastership transfer” depends on the availablity of other
BAs.
• The event phase basically performs the transfer of message data
from one slave node to another. This includes -
• the identification of devices being ready to send out MD. The
bus administrator will perform a search for such devices in an
endless loop. Since more than one device may have message
data to be sent, the BA must also handle the concurrent reply
of several nodes, which is a “collision” of frames on the bus.
Following a certain strategy, the “event arbitration”, the BA
takes care that all devices will be able to send out data after
a while, and that the transfer of MD is performed within a
certain time (real time behaviour).
• the MD transfer itself. The BA invokes any identified nodes,
and these will send out an MD data frame. The destination
address of the MD frame is included within the transferred
data bits; each listening node will compare the frame con-
tents with respect to its own device address.
Events, or the transmission of message data, occur with a random in-
tensity: absence of events leads the BA to unsuccesfully scan for MD;
during high activity bursts, MD transfer may take place “from every-
body to everybody”.
A fourth phase, the “guard phase”, simply fills up the time until the fixed end of
the basic period. Since it does not transmit data, it is neglected here.
From the standard, the base period may also have another length, e.g. 2ms;
however this is almost never used in practice.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 28/109 d000656-003145 duagon

MF&SF Time Requirements


In order to estimate the amount of MF- SF- combinations which fit into one basic
period, the following table shows the worst case time being required for the indi-
vidual combinations:

Master frame F-Code Max. time required


“periodic phase”
PD 1 word 0 93 µs
PD 2 word 1 103 µs
PD 4 word 2 125 µs
PD 4 word 3 173 µs
PD 16 word 4 269 µs

The timings shown here assume the worst case delay between the master and
slave frame. On a normal working bus, the required amount will be smaller, since
the majority of slave frames will have significantly shorter reply times; e.g. for a
single cable segment 8.4µs instead of 42.7µs, which is 34.3µs faster.

Master frame F-Code Time required


“supervisory and event phase”
Bus mastership offer 8
General Event 9
Group Event 13 93 µs
Single Event 14
Device Status 15
MD 16 word 12 269 µs

Usually, these frames are automatically generated by the bus administrator.


Therefore, the application engineer does not have to organise them (this is done
by the MVB controller chip). However, he must leave sufficient time for these
frames when allocating time for PD.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 29/109

Basic period time requirements


The application engineer may influence the available bandwidth for PD and MD
within certain limits. Since the overall bandwidth is fixed, this is basically done by
moving a trade-off between PD and MD bandwidth.
• Event phase: The recommended minimum time, being reserved for
the event phase, is one “MD transfer” (269µs). The same allocated
time can also be used by “general event requests”, “group event re-
quests” and “single event requests”.
• More bandwidth for MD: For the “classic MVB controller
implementations”, e.g. MVBC01, the event arbitration will
proceed step by step in 1ms- base period increments, with
the MD transfer at the end. It did not make sense to allocate
more bandwidth for an MVBC01- based bus administrator,
since this chip required software interaction for the execution
of the event arbitration strategy.
New MVB- controller implementations (duagon) have the
event arbitration completely working in hardware. For them,
it is possible to perform even several event requests and MD-
transfers within one basic period. This way, additional band-
width for MD is not wasted. Note: this is also true for saved
time due to fast PD- transfers (see previous paragraph).
• Less bandwidth for MD: Of course, it could be possible to
allocate the “MD transfer” (268µs) e.g. every fourth base pe-
riod, only. However, the real time requirements for the mes-
senger software have to be calculated accordingly. Be sure,
that the worst case requirements for your application can still
be met.
• Supervisory phase: The “device status” scan rate is recommended
by the standard to be 64 devices per 512ms, which means one “de-
vice status request” within eight base periods. This leads to an overall
amount of approximately 33 seconds for a complete scan of all 4095
devices. A personal recommendation from the author is to double this
rate (16 seconds is still a long time, and one device status request
within four base periods does not hurt, yet).
The “bus mastership transfer” occurs fairly seldom and does not play
a role for bandwidth considerations.
• Periodic phase: The number, the size and the repetition frequency of
PD ports is defined by the application engineer. Any available time for
MD is indirectly defined from this, i.e. the application engineer does
not have to define the bandwidth for MD, instead he has to allocate
PD in a cautious way.
The typical situation will be, that the allocation of the periodic phase is done by a
tool, i.e. the application engineer does not have to take care of the individual
frames.
For practical reasons, the bandwidth calculation is very often handled in a “statis-
tical” way. Be aware, that the granularity of the required amounts of time may
void a statistical calculation: 20% bandwidth for MD sounds nice, but if this mar-
gin is equally allocated to the base periods, the remaining 20% of 1ms = 200µs
may not allow a single MD transfer!

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 30/109 d000656-003145 duagon

PD Periodic Polling
The repetition frequency of an individual PD port can be selected from the steps of
1, 2, 4, 8, 16, 32, 64,128, 256, 512 and 1024ms. Due to the fact, that the fast
rates will occupy a lot of bandwidth, the repetition rates below 16ms are rarely
used.

base periods

1 2 2 1
2ms
4ms

Example: the PD port 1 has a repetition time of 4ms, and port 2 has 2ms.
The situation for a typical application is, that there will be several hundreds of
ports to be served:
• Some “fast” ports, with a repetition rate of 32ms or less, will handle
the jobs with critical reaction times.
• “Slow” ports, with 512ms or 1024ms will handle slow moving signals
(temperature...), configuration data for remote IO-modules, etc.
• The majority of ports will be somewhere in between, mainly allocated
according to general bandwidth considerations.
The application engineer will select a repetition rate for each port. The allocation
to particular base periods and the phase relationship between several PD ports is
done by a tool.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 31/109

MD Event Arbitration
“Event arbitration” is an algorithm executed by the bus administrator, which
searches for devices having MD data ready for transmission.
The classic event arbitration, as it is described in the TCN- standard and as it is
implemented e.g. in the MVBC01 chip, can be described in a simplified way like
this:
• The BA starts a new event poll by issuing a “general event request”.
Three possible reactions can happen now:
• If there is a clearly readable frame from one device, this device will be
served, then another “general event request” is issued, this time “not
a new poll”.
• If there is no reply at all, the “poll” is terminated and everything starts
from the very beginning: Obviously, there is no device left, which ap-
plies for event service.
• If there is a reply from more than one device, a collision occurs on the
bus lines. This situation can be detected by the decoder. The BA will
now issue a subsequent “group event request”, which invokes half of
the devices from before. With repetitive “group event requests” and
“single event requests” at the very end, all involved nodes can be
found out and served after a while.
As a rule for all participating devices, devices will not start to apply for events dur-
ing a “poll”, a running event round. They will wait until there is a “new round”
started. Therefore it is ensured, that every event seeking device will be served be-
fore the new round is started. This method leads to a deterministic maximum
time, until a random node is served (real time behaviour).
The event arbitration, as it is described in the TCN standard, is “recommended”,
but not “specified”. As written in paragraph 3.6.3.2.4.of the IEC61375, “other al-
gorithms are permitted. ... they may take advantage of the fact, that the identity
of participating devices is known, and that events tend to occur in bursts for mes-
sage data transfers”. Newer MVB controller implementations (duagon UART emu-
lation) take up these ideas and implement a new event arbitration strategy. In ad-
dition, the new strategy is implemented in hardware (does not need software in-
teraction). Both points together lead to the fact, that the net bandwidth for the ap-
plication engineer is increased by a factor of 5 to 10.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 32/109 d000656-003145 duagon

Macro Period
After 1024 base periods, the PD polling list is completely executed and will start
from the begin afterwards. This is called a “macro period”.

Turn - BA Mastership Transfer


The medium access is controlled by one of the bus administrators, the master,
which remains in control of the bus for the duration of a “turn”.
At the end of the turn, the master tries to pass mastership to another bus adminis-
trator (or remain itself master if no other valid BA is found).

mastership transfer sequence

BA BA BA
1 2 3

controlled slave devices


The time for a turn is always a multiple of the macro period, i.e. a multiple of
1.024s. A reasonable turn time will allow the device status scan to work at least
once through the complete address space: With one device status scan per four
base periods, this ends up at a turn time of 16s. This is sufficiently far away from
the maximum turn time of 256s.
The “BA mastership” circulates preferably in ascending order of the device ad-
dresses. The list of available BAs can be defined in the BA configuration, or it can
dynamically be derived online from the device status scan. The latter principle
helps to insert new devices into an existing application, e.g. for a diagnostic de-
vice.
During power up, a bus administrator waits for a predefined time before starting
bus activity. This time is influenced by the device address. Since the device ad-
dress is unique for all devices on the bus, one of several redundant bus adminis-
trators starts first, when all are switched on at the same time.
Note: due to this behaviour, it makes sense to allocate “small device adresses” to
the BAs. If the highest possible address is given to a BA, it will wait several sec-
onds before becoming an active master on the bus – try to avoid this unnecces-
sary idle time.
For availability and reliability reasons, the application must monitor the regular
BA mastership transfers. Otherwise, a non- operating BA may not be found, lead-
ing to a complete bus breakdown if the single remaining BA becomes defective.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 33/109

MVB System Engineering

Selection of Classes
When planning a new MVB- based control system, it makes sense to review the
capabilities of the involved MVB- nodes.
• Some capabilities may be skipped for simple nodes
• It is commercially reasonable to select the required capabilities, only.
In order to simplify the discussion about this issue, some “Classes” have been de-
fined in the IEC standard. Please note, that sometimes there is a more detailed
classification used in the market (which is not standardised):

MVB Device Classes


The devices participating at the MVB- traffic, are divided into several classes of
“communication capabilities”:
Class 0: Repeaters and bus converters; working on physical layer with no
data interaction.
Class 1: Process data IO, very simple, often as pure hardware solutions,
sometimes without any communication software.
Class 2: Process + message data, local processing of data, communica-
tion software with LinkLayer and real time protocols (RTP).
Class 3: Same as Class 2, additional application specific software varia-
tions, downloadable software configurations.
Class 4: Most complex bus stations including functions like MVB bus ad-
ministrator
Class 5: WTB gateway (nodes with several link layers)

Class 0 and Class 5 devices are usually defined by their function, i.e. there is no
headroom left for the application engineer to decide about capabilities.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 34/109 d000656-003145 duagon

Class selection
When thinking about your application, try to specify the requirements in the fol-
lowing sequence:

Class 1
Class 1 devices are the cheapest in terms of hardware as well as software and
software integration cost. Use Class 1 for as many as possible nodes.

Class 2
The step from Class 1 to 2 is usually reflected in a certain cost increase for the
MVB interface implementation. The reason for this is mainly the additional RTP
package for Message Data transfer, which contains quite a high complexity.
• For low volume (less than 1000 MVB nodes), it pays off to use MVB in-
terface boards, which have a local microprocessor on board (called
the “MVB server”). This one will run the RTP software, and the host
CPU has reduced requirements about software integration cost (soft-
ware integration is the dominating cost factor).
• For high volume (more than 10´000 MVB nodes), it may pay off to
port the RTP protocol stack to the application CPU. Now the hardware
cost becomes the dominating factor; the high amount of software in-
tegration cost is justified by hardware cost reduction.

Class 3
Class 2 and 3 are almost the same for up-to-date control systems. Today, the
download of configuration data and software updates is standard; which achieves
“Class 3”, already.

Class 4
The former cost for the additional bus administrator (the step from Class 3 to 4),
is now decreased to an almost invisible level. The reason for this is, that newer BA
implementations do not need high speed real time software any more. This
makes the BA a “friendly guest” on application CPUs running under tough load.
Following this, the BA functionality will be preferably moved to an existing Class 3
node, and not be on own node.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 35/109

Porting Software into Host Systems


Class 1 and the PD part of Class 2,3
The integration of process data driver software is very simple and cheap: the ef-
fort is in the range of 1 to 2 days. Usually, the driver software can be taken (or
derived) from an open software; available in source code.
Put some emphasis on clarification of the following issues:
• Does the type of MVB controller require real time behaviour in order
to achieve data consistency? If yes: implement e.g. interrupt blocking
mechanisms or skip “data consistency” at all. See page 14 for data
consistency in general and page 22 for the implications from the traf-
fic memory interface.
• Are application accesses required to happen from several tasks? If
yes: The use of semaphores has some impact on bandwidth and/or
latency of PD reception. For the practical impact, see page 39.
• Does the application use the Layer 2 or Layer 7 interface?
In simple cases, it may make sense to use the Layer 2 interface (PD
ports): the application reads or writes complete PD ports; the PD port
contents is resolved by the application software into several variables.
Sometimes it is helpful, to distribute the allocation of variables cen-
tralised for the whole MVB traffic. Then, the particular node software
tool has to import the variable definition, which delivers the variable
name, the variable type, and the location of the variable within the
PD port. In this case, you will work preferably on Layer 7 interface (PV
variables).
Sometimes, the lower hardware cost of pure Class 1 nodes generates the idea to
implement functionalities of the higher Classes via PD and some user written soft-
ware. Be aware, that this approach may turn out to be very tricky: You will have to
imlement an own protocol for it. In particular, we do not recommend the follow-
ing issues for pure Class 1 devices:
• Download of data into a local flash memory.
• Communication with data structures with a size far beyond 32 bytes;
for example long text, diagnostic data sets, complex configuration
data sets.

Class 2,3 Message data


The RTP real time protocols package is a very complex software. Today, there is
still significant software license cost and an NDA contract attached to it. The com-
plexity of the software itself as well as the integration effort into products usually
requires at least one engineer, working on this topic all year round.
These questions are in the foreground:
• The operating system must support real time behaviour. If the MVB in-
terface is an “MVB server”, this requirement is restricted to this unit,
only. If the RTP are ported to the main application CPU, then this one
has to support real time.
• The RTP require support of semaphores, which are preferably to be
used from the OS.
• The RTP require a number of (software) timers.
All together, skilled engineers will require in the range of some man months for a
complete porting of the RTP on another platform.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 36/109 d000656-003145 duagon

For the MVB server approach, the effort is reduced to a two day work: only a slim
client software has to be ported, with simple requirements related to the OS: no
real time, no timers, maybe just semaphores (in case of multitasking
applications).

Class 4 Bus Administrator


Previous controllers required a BA software with very fast interrupt service rou-
tines. This is of course a clear interference with demanding applications.
Newer designs include the BA completely in hardware. The remaining require-
ments upon software are quite trivial: The BA must be started by software, requir-
ing some memory space for the configuration file. After the BA has started, abso-
lutely no software interaction is required.

How to put a new node into operation


After having the software ported, the whole device has to be tested first time with
MVB. The proposed sequence shown below is just a recommendation, to be
adapted according to the particular project requirements.

Hardware Integration of MVB controller


Try to initialise some PD ports, read and write the same port. This activity takes up
the contact with the MVB controller. When yo can read a PD port with a value
(which should be the same you have written previously), then the hardware inte-
gration is obviously correct (at least the most important parts). For this test, you do
not need any communication over the MVB cable.

RTP software porting


The same you can do with message data, too. Call a function, which is imple-
mented on the same node. This does not need MVB interaction, too. It is just a
test of the successful software porting.

Hardware of MVB attachment


Now connect the new node with a BA bus administrator and a diagnostic device
(most diagnostic tools already contain a BA). The new node must be recognised
with its “Device Status” on the preconfigured address.
Check the contents of the device status word:
The RLD- bit must reflect your physical layer choice:
• If you use Line_A only, RLD will be 1 (and LAT=1, too).
• With redundant lines, RLD must be 0.
Now make a short circuit on MVB Line_A (it is the one between pin 1
and 2 of the Sub-D- connector): The result must be RLD=1 and
LAT=0.
Then make a short circuit on Line_B (between pin 4 and 5), the result
must be RLD=1 and LAT=1.
Be sure, to really get a new DSW from the bus – do not use old values
(use freshness information!).

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 37/109

Typical DSW structure:

Bit positions
15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0
Capabilities specific common flags

DNR
MAS

SDD
RLD
ACT
AX0

SSD

ERD
LAT

FRC
GW

Ax1

SER
MD
PD

BA
0 0 0 1 0 0 0 0 x x 0 0 0 0 0 0

This test sequence demonstrates, that the MVB connection is working


in general, and your device is able to communicate on both Lines, in
receiving as well as in transmitting direction.

BA attachment
Now use the bus administrator with a configuration close to what is required in
your application project.
Check the ports, that are defined as “source” on your device. You may again use
a diagnostic tool to receive these ports via the MVB cable. Be sure to have the BA
switched off on the diagnostic tool; otherwise the regular BA may be out of ser-
vice.
Add a device, that generates with an active source the PD ports, which are “sink”
on your device. You may use the diagnostic tool for this, or the finally intended
MVB devices of your application project.
Now the PD sink ports on your device must show low freshness values, indicating
the successful reception of new data.
The test demonstrates so far, that the configuration of the BA and your PD ad-
dresses match to each other. If they do not, communication will not take place
(freshness indicates antique data).

Check list for missing frames


When you enter the fact, that PD frames do not arrive at the intended device, sev-
eral potential reasons should be checked:
• No BA: The BA is not existing, not configured, not active.

• Wrong configuration: The configuration of the BA, the source of PD,


or the sink may be wrong. A high potential for errors was found by
misunderstanding of hexadecimal versus decimal numbers...
• There is a second source node on the bus, which send out data for the
same PD port. This leads to repetitive collisions on the bus, which is of
course illegal.
• Wrong physical layer: all nodes must have the same physical layer,
EMD or ESD.
• Device internal noise and/or the ESD end delimiter issue inhibits
successful reception of data (less probable for lab setups).
• The cable attenuation does not match the real line extension.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 38/109 d000656-003145 duagon

System test
Sometimes it sounds a little bit boaring, but it really makes sense:
Check all the details of your system in an isolated way.
• Are variables understood in the same way all around the MVB
system? No byte swapping in “integer” formats? Are all PV variable
definitions correct, i.e. all bits at the right place? Does your device
start with the intended variable defaults or does it take a while until
they settle?
• Is the start up and fail safe behaviour of your device correct?
• A hardware reset must stop MVB transmission immediately.

• The same is true for a watchdog reset.


• Before starting the regular MVB communication, the device
must not be active on the bus. For “power up”, this will be
true in most cases, but also after reset without power-down?
Several companies have introduced “test suites”, which actively scan all possible
aspects of the TCN standard. Usually it pays off to make use of this, even though
it costs a few days of additional work. Finding e.g. misunderstandings in variables
is sometimes a very time consuming job, especially when you are already on a ve-
hicle (and everybody picks on you... ).

Final Performance test


Check your application in a complete system environment (like on the vehicle).
Use test sequences, that emulate the real world as close as possible.
This will give you confidence about the more complex properties, like bandwidth
on application level, latency times, etc.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 39/109

Real world performance


What are realistic performance levels from the point of view of the application
software?
• Of course, this question depends to a high extent on the used
components, i.e. the application CPU, operating system, the driver
software architecture, the hardware interface to the MVB controller,
the MVB controller itself.
• Anyway, some very general numbers help to learn something at least
about the “order of magnitude” for MVB communication.
The base for the examples shown below is an ARM7 RISC CPU with approximately
20 MIPS, running an eCos real time operating system.
The application is a specific type test software, with an emphasis on generating a
high load in PD and MD, i.e. the values do not represent optimistic calculations of
single accesses, but a sustainable average.

Name Value Comment


Access of one PD port via API function
124 µs
call, average value over 1000 accesses.
approx. Same test as before, now access via local
250µs CPU on MVB interface (MVB Server)

PD_access time Same test as before, now access of a PC


500 µs to (AMD 500MHz) via a standard Windows
800 µs COM driver to an MVB Server interface
(see note below)
Same PC as before, now using a specific
up to 300µs
Windows driver.
According to the customer's software ar-
chitecture, the use of semaphores may
OS_delay_semaphor
32 µs become neccessary.
e
Average value over 1000 accesses; ARM7
platform
Tested under heavy load with 26 nodes
sending and receiving data.
Note: for the individual MD link remains
in this case 421 Baud.
11 kBaud
PD allocated to yield an approximate
MD_net_bandwidth PD:MD relationship of 70:30 (usually rec-
Total value for all ommended for high PD load).
MD activity “Classic” BA and RTP implementation.
Same test as before, but now with new
hardware based BA and optimised RTP
100 kBaud software.
Now the individual MD link (1 from 26)
gets 3.8 kBaud.

Note: Using standard Windows drivers is very convenient, since it does not re-
quire to apply a Windows driver yourself. However, the performance is less than
perfect; which is OK in a lot of applications. For demanding applications, we
therefore recommend to use a specific Windows driver.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 40/109 d000656-003145 duagon

Failures, Failures, Failures...


The railway business asks for -
• Availability of operation. The ab-
solute level of the required avail- Availability
ability is higher than what simple
Probability of a system to
equipment can deliver.
The usual strategy to overcome this be ready for operational
situation is the application of redun- use. Includes properties
dancy, i.e. some devices may fail, coming from “failure
but the overall function is still deliv- rate”, but also service and
ered since a second device takes repair times.
over the job.
• Safety of operation. If any part of
Safety
the equipment fails, it must not lead
to a safety critical situation. Statistically determines the
In order to tackle this problem, the extent, how far adverse
failure effects of each part of equip-
events are avoided.
ment have to be investigated and
the internal structure of devices has to be built in a way, that danger-
ous failure effects are avoided.
Usually the failure mechanisms are well known. For each device, the related fail-
ure modes can be estimated by statistical methods. For example, the failure of a
light bulb is in most cases the break of the filament, less often it may be the loss
of vacuum or contact problems.
This knowledge leads to methods, how to avoid unwanted effects. Some success-
ful strategies are:
• Enhance the internal structure of the equipment.
Example: Using LED indicator lights instead of light bulbs is more reli-
able (LEDs simply live longer...) and more safe (LEDs usually fail by
slow reduction of performance, i.e. their complete failure can be
avoided in time by replacement; light bulbs fail suddenly).
Another example is simplicity and/or integration density of equip-
ment. This follows the simple rule: The more you build in, the more
will fail. Older electronic equipment usually requires a lot of compo-
nents to fulfill a certain function. Following the line of technological
progress, newer high integration approches will deliver the same
function more reliable.
• Avoid early failures by burnin.
“Early failures” arise from hidden defects. The defects are there from
the very beginning, but they are hidden, i.e. they are not visible for
test methods. The usual way to find these defects is to stress the de-
vice under heavy load conditions and watch the behaviour. When this
“burn in” is done in the controlled situation of a manufacturing plant,
the failures can be repaired in an easy way, requiring less cost than
repair in the final operation.
• Avoid “wear” failures by controlled replacement.
A good example is the replacement of various parts of a brake before
they fail. Knowing the typical life time of the parts, a “service plan” is
installed, applying regular checks and replacements.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 41/109


Apply functional redundancy:
Add more parts to the system in a way, that the additional parts take
over the function of the other parts in case of failure. Example: the
doors are usually opened by interaction with electronic equipment. If
this fails, it is good to have an additional, mechanical mechanism
which can be used in emergency cases.
A special application of functional redundancy is the multiplication of
existing equipment. If you use just one light bulb, you will sit in the
dark upon failure. If you apply two or more light bulbs, then the fail-
ure of a single light bulb will not be relevant.
• Apply check redundancy:
Add more parts/ functionality in a way, that wrong conclusions can be
avoided.
Example: A “Pt100”- resistor can be Integrity
used for temperature measurement;
a certain resistance relates to a cer- Determines, to what extent
tain temperature. If the cabling fails a systems delivers correct
with e.g. short circuit or with broken data when it sends data.
wires, then a wrong temperature
will be measured. If you add an additional detector for “resistance
close to short circuit” and “resistance close to open circuit”, then the
cable failures can be found. An “invalid” signal will make any users of
“temperature” aware of the fact, that they have to work without “tem-
perature”. They will select a “fallback strategy”; e.g. switch off the air
condition.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 42/109 d000656-003145 duagon

Applying Redundancy in general


If “redundancy” is to be applied, some basic principles should be in mind:

Are failures independent from each other?


Example: Usually, having two light bulbs works very fine. This is due to the fact,
that the most probable failure mode of a light bulb is the break of the filament,
which is an “open circuit”. Assume, the most probable failure mode would be a
“short circuit” (there have been such interesting products on the market...). Then,
the failure of one bulb would make the fuse trip, i.e. the second bulb is dark, too:
Adding a second bulb makes no sense, unless you add a second fuse circuit.
The conclusion is: redundancy works only, if the failure of one part is indepen-
dent from the failure of the redundant parts.

How to use redundant software?


As a matter of fact, also software can fail. There are two ways for successful use of
redundant software:
• With “software diversity”, i.e. two redundant software implementa-
tions, being developped by different teams, with different tools, with
different operating system, checked by several type test approaches,
the outmost level of low “failure rate” is reached. Of course, this is
very expensive, since the implementation is doubled.
• With no software diversity, i.e. the same software, just used in two dif-
ferent instances, the independence between the nodes is lost. The
same failure will occur on both devices at the same time.
Therefore this approach makes sense for getting the benefits from re-
dundant hardware, only.
Please note: Software does not become defective, software is defective: Whatever
the failure is, it is present from the very beginning of operation. There is no way,
that software becomes defective during run time; this is possible for hardware,
only (loss of memory, wrong calculation results, etc,).
From this point of view, the quality of the type testing during the engineering pro-
cess directly influences the “software failure rate” later on. It is highly recom-
mended to invest reasonable time here!

What is the probability for a failure?


It is a common situation, that the failure rate of a certain component is consid-
ered to be too high, but adding a second component of the same type reduces
the failure rate to an acceptable level.
Example: Assume, the probability of failure for a light bulb is p1=0.0001 failures
per hour. The second bulb will have the same probability, p2=p1. Since the both
failures are independent from each other, the probability that both fail at the
same time is p1*p2 = 0.000 000 01 failures per hour (once in 11000 years, like
hitting a jack pot). The result is, that there is still a probability for a complete fail-
ure, but the absolute probability for occurence is very small, i.e. you can forget it
for practical considerations.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 43/109

Conclusion: be aware of -
• the absolute height of the failure rate for your equipment and

• the requirements from your customer about the absolute height of


failure rate. The match of both will determine how far you should go
in applying redundancy, which in turn defines cost.

What happens after the first failure?


Example: When you have two light bulbs, the first one failed already, but it is not
replaced, then the probability for the second one to fail is p2=0.0001. This is af-
ter one year, which is not to be neglected!
Conclusion: A process must be installed, which detects failures and replaces
failed components. Otherwise, there is no real benefit from redundancy.

Are there “single points of failure”?


The usual “redundancy business” is to arrange Single point of failure
components in a way, that their failure rate p1 is
not simply added to the overall failure rate. If Situation, where the fail-
the component is in redundant relationship with ure of a single component
other components, the procuct p1*p2 is added; will stop overall function-
which is usually lower by several orders of mag- ality of a whole device/
nitude.
system.
This leads to the more practical rule of thumb,
that there will not be multiple failures at the same time. This relies on the as-
sumption, that the time to repair is much faster than the time to fail for the sec-
ond, redundant component.
However, it is sometimes not this simple to create structures without single points
of failure. Very often, they are forgotten during the engineering process.
As a check, it is reasonable to actively search for such unwanted situations of
“single points of failure”:
• Usually, they should be avoided by application of clever architectures.
• Sometimes, it is not possible to avoid them. In these cases, the com-
ponents have to be of extremely low failure rate; which usually leads
to the use of very simple mechanisms.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 44/109 d000656-003145 duagon

Applying Redundancy in MVB Based Control Systems


There are several areas within an MVB system which allow redundancy:
• Wire redundancy: please refer to the description of the physical layer, page
57.
• The chapter about “Network Topology” includes information about the use of
redundant bus segments, see page 49.
• The “bus adminstrator” may be redundant, too. See page 32.
In this chapter, lets have a closer look into “safety” and “redundancy of bus
nodes”:

Safety
The basic principles of the MVB allow a “quite safe” operation:
• The integrity of the transmitted data is very high
• The transmission principles are deterministic, i.e. the do not contain
statistical approaches like the collisions in Ethernet
• The API software interface supports and encourages the use of check
mechanisms for variables
• The whole concept integrates redundancy for availability and integrity
at various places.
From this point of view, the MVB includes the basic prerequisites for safety rele-
vant applications. At least, the MVB carries much more “safety features” than oth-
er field busses.

Approval
Unfortunately, the approval for such kind of application is very hard to get: It
would mean, that the complete system with all nodes and all application software
has to be analysed for deterministed behaviour. This is quite complex, especially
since a high amount of the functionality is implemented in software. This requires
to analyse also the operating system and the more general hardware platform
with CPU, timers, memory, etc.
• Therefore, the high complexity makes a complete certification al-
most impossible.
Once having achieved such an approval, it would be void if only one small part
changes. This is a clear contradiction to the required flexibility during the engi-
neering process. Another example: for practical reasons, some people need to
use a Microsoft Windows operating system. Can this be certified for safety? How
to deal with updates once per year? My personal recommendation: better do not
use it for safety critical applications.
However, under certain conditions, the MVB can very well be used in safety critical
applications. Example: The braking system may use the MVB for the operational
braking. As long as there is an emergency brake in parallel, the MVB does not
neccessarily need to be approved for safety.
This means basically, the MVB can be used in functional redundancy with other
devices. The sense of this arrangement lies in the fact, that the MVB delivers a lot
of additional features:
• The safety relevant parts (outside of MVB) will most probably be very
simple. They are reduced to the absolute minimum.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 45/109

• The MVB will bring a lot of “comfort”, “availability” and “cost reduc-
tion” functions. As long as the MVB works, it will be the preferred way
of communication. The MVB will help to solve additional questions
like: How many emergency brakings are allowed until the train has to
go into the repair work shop? How the condition monitoring data is
collected and delivered to the outside?

Personal note from the author


According to my knowledge, there was never an approval for e.g. life critical ap-
plications of the MVB. Under certain conditions, like limited systems with very low
software content, experts have indicated to me, that such an approval could be
possible under reasonable effort. At least as you consider an effort of six man
months to several years “reasonable”. Comments invited!

Redundancy of Bus Nodes


Duplicating bus nodes is simple:
• Bus nodes in a redundant relationship to each other can be connected
to the same MVB segment. The MVB hardware connection almost per-
fectly separates the failure effects from one node to the other.
• Since PD process variables are distributed by broadcasting over the
bus, both nodes will see the identical “sink” ports, on identical ad-
dresses.
• Both nodes have to use different addresses for PD “source” ports and
for device addressing in order not to collide during transmission and
to be recognised as different nodes on the bus.
The different source ports allow a transparent verification of both re-
dundant units, i.e. both units can be checked for failure or disappear-
ance.
• For message data, the involved nodes are “device addressed”, i.e.
they are distinguished from each other.

redundant
Node 0 Node 1

MVB

Note: In some applications, application engineers decide that the “source” ports
are not on separate addresses. Instead, they dynamically enable and disable their
local source configuration in order to become the “active” of the two redundant
nodes.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 46/109 d000656-003145 duagon

Geographical Addressing
The method of “geographical addressing” is very helpful for applications with sev-
eral identical devices as bus nodes. This may be for the purpose of “bus node re-
dundancy”, but also for the more general situation of multiple devices. The exam-
ple below describes the use of several remote IO devices:

When there are sever-


al identical modules in io io io
one MVB system, their
MVB addresses must
be somehow different. MVB

io io

However, it is very useful to have only one type of module within a vehicle; i.e. all
modules can be exchanged with each other and the correct function remains at
the right place.
Each module must “know”, where it is (i.e. which function is to be performed).
The external wiring tells the module on some special “code” pins, what “index” it
has. The index has a direct influence on the MVB- addresses.

ect
sel ress
selection Index add
by wire

io module

When exchanging modules from one location to the other, the wiring remains at
the right place and selects the correct functionality:

Index Index Index


1 2 3

Index Index
4 5

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 47/109

There is a remaining single point of failure, with a relatively small, but existing
probability:
+ Failure!
Wiring Wiring
- - - - - - - +

redundant
Node 0 Node 1

MVB

A failure of the input may make both devices operate on the same addresses. This
causes usually a loss of functionality on both devices.
In order to avoid this single point of failure: define the geographical addressing in
a way, that a single failure (wire break, short circuit) does not select an existing
other node:
+ Failure!
Wiring Wiring
- - + - - - - +

redundant
Node 2 Node 1

MVB

In this example, the failure on the input pin causes Node 2 to work on address
“3” instead of “2”. This makes the device inoperable. However, the other node is
not disturbed and may work on address “1”.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 48/109 d000656-003145 duagon

Decision making
Each of the two redundant bus nodes will distribute its own source ports. From the
functional point of view, both ports deliver the same information.
Everybody, who is listening to these ports, has to take a decision: which one to
take?
Example:
Two vehicle control units are redundant to each other. If one of them fails, the
one still being good shall be used for valid output data.
Under normal conditions, i.e. when both vehicle control units are up and working,
they will send PD telegrams to the listener. They will have different PD source port
addresses, called in this example 1 and 2.

redundant
Node 2 Node 1
status: OK status defective

MVB

Sink ports
1:?? Use 2!
2:OK
Listener

The listener must decide now, which one of two different PD telegrams controls its
outputs.
• The most simple approach takes the “freshness” from the sink time
supervision. This approach assumes, that a failure of a redundant
node is expressed in its missing source ports. This is a natural fact for
popular hardware errors like missing power, broken internal logic
and similar.
• More elaborate approaches may additionally use check variables and
the like. By this way, the listener may distingiush more information
about the kind of failure.
In any case, the listener has to report an error, if one of the redundant nodes is
missing: This should lead to repair activity for the defective node.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 49/109

Network Topology
Single Segment
The most simple MVB system is just one segment, and a number of nodes con-
nected to it. Some of the nodes will be in a redundant relationship to each other,
some not.

Redundant
pairs

The redundant device pairs are used to implement critical functions. Example:
Minimum of control elements on the driver´s desk in order to “limp home”.
Nodes without a redundant partner will implement functions not being vital: com-
fort equipment, diagnostic devices, devices with the ability for manual interaction.
This configuration requires the MVB wire redundancy to be used: otherwise, the
one MVB line would be a single point of failure.
Note: All devices have to be of the same type, ESD or EMD (since there is one
segment, only).

Cable Length Limitation


The single segment length may hit its allowed maximum: when going in and out
to all device mounting locations, a high amount of cable length may become nec-
cessary. This is particularly true when using a “cable duct”: Real examples have
shown a cable length of up to 200m within a vehicle of 20m length!

Cable
duct

Therefore a very general hint:


• When having more than 10 MVB nodes distributed over a vehicle,
check the length of the cable segment.
• For more than 20 MVB nodes, it may become difficult to implement
the cabling within the 200m- limit for one cable segment.
• The full number of up to 32 nodes is possible with optimised cable
routing and “clustering” of nodes, only.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 50/109 d000656-003145 duagon

Double Segment
This topology is very often used, since it relates very close to the properties of
symmetric vehicles:

Bus
repeater

There is one bus repeater, which connects the both segments.


This approach has a very interesting property: The two segments may be imple-
mented without wire redundancy. Since all of the “redundant pairs” are connect-
ed to different bus segments, never both to the same segment, a complete seg-
ment may fail and the vehicle is still operational: the remaining “good” segment
reaches all important and half of the remaining devices.
The bus repeater has the job to -
• pass information flow between the segments during regular opera-
tion,
• block any destructive influence from a defective segment to the good
one.
Interesting: The bus repeater itself does not need to be redundant. In case of a
failure, both segments may even work on their own, completely independent.
Note: Theoretically, the devices of the two segments could be of different type,
ESD and EMD. However, this is obviously a not very favorable solution: It is better
to have one type of bus and for repair purposes keep all nodes exchangable with
their redundant partner.
The cable length limitations are a little bit more relaxed compared to the single
segment structure; two segments may serve twice as many nodes. However, for
complex vehicles, it may not be sufficient: follow the recommendations of the
“single segment” approach; now for each segment separately.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 51/109

Star Topology
This structure is a very general approach and supports a huge amount of bus seg-
ments.
• Usually, the number of the bus repeaters (and therefore the number
of segments) is minimised in order to reduce their cost.
• The segments are easily adapted to different physical layers (ESD or
EMD).
• Since the single segment cable is shorter compared to a single seg-
ment, it may become a cheaper cable (more attenuation, operation
less sensitive to EMI).

Star coupler

Bus
repeaters
Back bone

The single segments may have wire redundancy or not. The bus repeaters will fol-
low this decision on their segment side.
The back bone and the repeaters may be concluded into one device, a “star cou-
pler”. In this case, the back bone may disappear completely within the new de-
vice.
Please note, that this more general star coupler may serve several nodes on each
segment. A classically pure “star coupler” would serve just one node on each seg-
ment; as it is the case for the OGF (Optical Glass Fibre).
The application will most probably require, that the various segments are not sep-
arated in case of failure. Following this, the back bone must have wire redundan-
cy, or the complete star coupler must be redundant.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 52/109 d000656-003145 duagon

This approach puts the emphasis on the cabling in a different way:


• A single segment is routed from the star coupler to a mounting
location, where one or more nodes are served.
• Defects in the cable can be found more deterministic, since the failure
is already allocated to one segment with a reduced number of nodes.
• Segment cable length limitations usually do not play a role with this
approach.

Star
coupler

It depends upon the particular application, whether the star approach pays off or
not. Costs for cables, commercial availability of EMD versus ESD+- nodes, cable
diagnostic efforts during life time, cost and failure rate for the star coupler itself
account to a complex situation, which should be resolved for each project
separately.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 53/109

Physical Layers
There are three separate physical layers available:
• ESD: Electrical short distance bus,
• EMD: Electrical middle distance bus, and
• OGF: Optical glass fiber bus. Due to the fact, that the OGF is very
rarely used, it is not described in detail, here.
All these physical layers can be mixed within an MVB system by the use of re-
peaters, switches or gateways. However, nodes of different physics cannot mixed
within one bus segment.

Termination
A common property of the wire- based physical layers is their need for
termination in order to keep clear signal wave forms (what happens if the
terminators are forgotten show the measurements on page 98):

T T

• The transmission medium is linear, i.e. it does not allow to have


branches, where the signal may travel into several separate
directions.
• The transmission line has to be terminated at both ends in order to
avoid reflection from an open end. The termination must match the
characteristic impedance of the transmission line.
Please note: Depending on the cabling concept, it is typically required to have
two types of terminators: one with a male SUB-D- connector and one with a
female connector.

Bias voltage
For the ESD bus, the terminator takes over an additional role: it delivers a bias
voltage to the transmission line. „Bias“ is a voltage, which is applied between the
signal lines at any time, i.e. also during idle times.
The basic idea of the bias voltage is to reject noise: the receivers detect signal
level changes in the area around the differential zero voltage. With a bias
voltage, any noise must be higher than this bias in order to be recognised. Of
course, the signal itself must be higher than the bias voltage, too.
The „bias“ is not applicable for the EMD bus. The transformers, being intended to
deliver the galvanic insulation to the node logic, do not conduct DC. This leads to
the fact, that noise rejection has to be done in a different way.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 54/109 d000656-003145 duagon

Insulation Concepts
In general, the maximum insulation withstand voltage is 500 VAC for any galvanic
insulation.

Insulation ESD+
The insulation separates the node logic (the MVB controller chips, CPU, other
electronics) and the RS485- transceivers. Usually, the insulation must be crossed
by power (a small DC/DC- converter) and signal lines (opto couplers).
One additional galvanic insulation separates the two MVB lines A and B and their
related terminator power supply lines, too. This is not required by the TCN stan-
dard, but may be of benefit under certain conditions.

A
MVB Transceiver

MVB
DC
node
power
logic

MVB B Transceiver

Note: There are some devices on the market, which do not separate the Line_A
and Line_B. This still complies to the standard and is a cost effective solution. We
recommend that application engineers do not require the galvanic insulation be-
tween the MVB line A and B. By this way, exchangeability with all products is kept
and the cost figures may become optimised for high volume projects.
Note: The classic ESD- version without galvanic insulation (see below) is intended
for use within small areas (e.g. within a rack) or with external interfaces to the
OGF.
A
MVB Transceiver

MVB
DC
node
power logic

MVB B Transceiver

Insulation EMD
The two MVB lines are insulated to the logic and to each other.

A
MVB Transceiver

MVB
node
logic

MVB B Transceiver

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 55/109

Shielding Concept
There are basically two different shielding concepts used in applications.
• The most popular concept connects the shield to the cases. This is
easy to implement, the shell of the used SUB- D- connectors are di-
rectly attached to the device´s housing.
• An alternate concept allows to have potential differences between the
housings. This requires to insulate the shield from the node´s housing
– which is sometimes difficult to achieve.
The shielding concept has an influence to the way, how the nodes must be built
into housings; i.e. the device integration must adapt to the shielding concept used
for the particular application.

“Shielding on case” Concept


The main properties of this concept are:
• The cable shield is connected to the device housing.
• The cable shield has in all nodes the same connection to the device
housing.

MVB node logic MVB node logic

This has as a consequence, that all housings are connected together. Within the
vehicle concept it must be ensured, that there are no ground potential differences
that may harm the cable shield or the connectors.
The connection between the cable shield and the device housing is done via the
cable connector housing and the fixing screw / cable lock (as prescribed by the
TCN standard).

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 56/109 d000656-003145 duagon

“Insulated Shielding” Concept

This concept separates the cable shield from the device housing:

MVB node logic MVB node logic

Insulation

This concept has the benefit, that


• there is no ground potential difference problem any more (assumed,
the ground potential differences are below the insulation withstand
voltage within the MVB nodes).
This concept has the disadvantage, that
• the SUB-D- connectors must be mounted insulated with respect to the
device housing and
• there must be means to connect the cable shield well- defined in one
point to ground.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 57/109

Wires & Redundancy


Introduction to wire redundancy
The railway market asks for solutions with a high availability; a single wire break
must not stop the train.
Usual field bus approaches use just the minimum of electrical conductors required
for their function. If only one conductor break occurs, communication is stopped,
which in turn will stop the train operation. This is not accepted by the train opera-
tors!
Being the most probable failure model, the break of a conductor was focused on:
this could be the break of a real wire, a contact or any attachment technique
(crimp, solder, etc.).
In contrast, the loss of a complete cable (with several wires included), was consid-
ered to be less probable. A complete cable loss would be e.g. the cut of all wires
at the same time.
Note: this consideration is valid for the MVB with its static installation within one
vehicle. In contrast, for the WTB Train Bus, the cut of a complete cable is consid-
ered to be of statistical relevance; there we have redundant cables, not just re-
dundant wires.
As a conclusion, it was decided for the IEC61375 standard to operate the MVB
with redundant wires and accept, that the redundant wires are routed within one
cable.
The wire redundancy is available for all physical layers, in principle: ESD, EMD,
and OGF. Due to the specific properties of the OGF, optical wire redundancy was
almost never used in the market. The reason is, that the OGF segment is not a
real “bus”, but more a point- to- point connection. When compared to the electri-
cal layers, a single point of failure has less influence to the failure of the complete
system.
Wire redundancy in general is optional from the point of the standard. In princi-
ple, highly available control systems may also be built with non-redundant wires:
in this case, e.g. two segments of non-redundant MVB may be used (see page 50
“double segment topology). However, the majority of end customers like to have
wire redundancy.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 58/109 d000656-003145 duagon

General working principle

MVB

Manchester encoder Manchester decoder

• When transmitting data, every node sends out data on


both Line_A and Line_B.
• When receiveing data, every node is able to receive
data either on Line_A or Line_B.
By this way, either Line_A or Line_B may be inoperable. The other line is still able
to carry the full amount of communication over the MVB.
The process of “select the line which is to be taken” is called “line switchover”.
Any failures must be reported, even if the communication is still working over the
redundant line. This enables a repair before the second line may also fail.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 59/109

Failure model
In the early days of standardisation, the failure model was pretty simple: If a
break of a wire occurs, then communication passing over this failure location is
not possible.

MVB

The idea was, that a receiver will not receive anything after a wire break. “Noth-
ing” is easily detected; and the second line, receiving “something”, gets priority
very easily.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 60/109 d000656-003145 duagon

Obviously, this point of view is a little bit too simple. In practical life, more or less
the opposite is true: when a single break of a wire occurs, then some devices can
communicate over the failure point, others cannot:

3 1

MVB

!?!

The reason for this behaviour is mainly the fact, that the second wire of the twist-
ed pair of wires is still intact and generates a signal on the far side, which is very
difficult to keep under “theoretical control”.
• Effect 1 is a capacitive voltage divider from the intact wire to the
shield. This induces a signal waveform on the defective wire, travel-
ling to the receiving nodes. This signal is usually big enough to be
recognised.
• Effect 2 lets the signal waveform on the intact wire run through the
termination resistor on the far end, attenuate it there, and come back
to the break: There it is reflected at an “open end”. This yields a dis-
torted signal, which may confuse the receiver.
Interesting: If the cable length on the right side of the failure is rather
small, the termination resistor shifts the properties of the capacitive
divider (Effect 1) a little bit, but the frames are still readable.
• Effect 3 is a simple reflection at the “open end”. This may cause other
receivers to fail (on the left side of the failure, not shown here in the
picture).
Will the receiver on the right side understand the original waveform or
not? Sometimes yes, sometimes no. The situation is mainly dominated by the ge-
ographical situation of all involved nodes and the signal reflections at the failure
point.
To keep control, one would have to calculate the communication ability for all
node- to- node combinations. This relates not only to the communication through
the point of failure, but also between the nodes on the same side.
Since this kind and amount of work is not possible in practical life, obviously no-
body makes use of this theoretically deterministic method.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 61/109

Line switchover
Unfortunately, several details of the MVB specification have been defined follow-
ing the early “simple failure model”:
The Line A-B switchover is defined in a way, that the receiver recognises either
Line A or Line B, but not both at the same time. It is not possible to dynamically
switch to the other line during frame reception. This way, validly present data may
be lost.
The receiver is supposed to detect various general states of a line: “Weird” wave-
forms from a cable break should be rejected in order to identify the cable break.
“Idle” and “Collisions” must be distinguished from each other in order to allow
the recommended event arbitration follow the correct sequence. “Valid frames”
must be recognised in presence of noise. It is quite a challenge to fulfill all these
classifications reliably. The recognition is always a statistical aproach, it cannot be
deterministic.

Personal note from the author


Did you fully undestand the specification in the standard about line switchover? I
did not. I tried of course, and my feeling of having it understood was not bad. But
later, when I had funny effects from my real world measurements, I failed to ex-
plain it from the specification architecture. The result was, that I decided to solve
my problem in a different way, not by using information from the line switching.
This would have costed several additional days of work, and time is what we all
do not have...

MVBC01 and “line redundancy”


The MVBC01 was the first MVB controller chip available for the MVB market. It
was designed before the finalisation of the IEC standard, and therefore has some
“differences” to the standard, especially in relationship with “line redundancy”:
It has a different “line switchover” strategy. There have been cases reported,
where certain failures on one line could also impair communication on the other
line: This is an absolute “must not” for high availability control systems! If you
need to debug MVBC01- systems, anyway: Make sure, you use the MVBC01
datasheet, not the IEC standard.
When the MVBC is working as BA, and an external Line is short circuited (the
MVBC01 cannot read back what it sends out), it may happen that the MVBC01
stops operation completely. This hang-up may be recognised by software and the
chip may be restarted, but depending on your software latency time, this may
leave the MVB in an idle state for more than 1.3ms. This may start other, redun-
dant BAs, which later on yields collisions on the bus. Therefore: when doing de-
bugging with an MVBC01 as BA, be sure to have only one of them or be prepared
to get funny phenomena.
When being the BA, the information of the RLD, LAT- bits has to be moved by
software from the received ports to the own Device Status Report. This procedure,
if it would have to be perfect, would require software latency times in the range of
down to a few microseconds, which is not possible for usual CPUs.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 62/109 d000656-003145 duagon

Implementing a better failure model


The early implementations according to the “simple failure model” have led to
quite confusing situations during the debugging of real vehicles. As a conse-
quence, the next generation of MVB controller chips implemented a different be-
haviour. The result was a much better behaviour in practical life, but a partial
non- compliance to the standard.
The original architecture was a node containing exactly one decoder for receiving
data. This decoder could be switched to watch either the Line_A, or Line_B. The
specifications for how to switch between the two lines are quite complicated.
Quite a lot of trouble arises from the fact, that when the decoder watches Line_A,
then incoming data on Line_B will not be recognised. The decoder will usually
switch to Line_B afterwards, which is too late for this frame.
This situation is in particular tricky, when the engineers try to locate a failure by
removing nodes from the bus. This is an adequate technique for a lot of other sit-
uations. On MVB, the missing of some process data sources will completely
change the dynamic behaviour on the bus and thus the line switching. The result
was often enough perfect confusion...
Therefore, the new failure model must allow for each received frame a new deci-
sion between Line_A and Line_B. By this way, the result seen on the node (suc-
cessful reception or not) can be used as an independent input for debugging; i.e.
it is not dependent from earlier activities.
Since the decision for Line_A or Line_B is taken at a quite late point in time, this
dynamic redundancy switching has also a positive effect on noise robustness (be-
yond the specs from the standard).
The status bits LAT “Line A trusted” and RLD “Redundant Line disturbed” are still
used to mark the status of the node. However, due to their tight relationsship to
the old line switching technique, the underlying definition has changed.
These bits are distributed on MVB by the “Device Status Requests” from time to
time; with some few or up to thousands of other frames in between. By the old
way, it was impossible to draw reasonable conclusions from them: which one of
the thousand activities was the failing one?

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 63/109

MVB

Manchester Manchester
decoder decoder

Manchester encoder

The result from this situation was a new design of the decoder and the line
switching. Now, there are basically two decoders (instead of only one), and they
watch both lines at the same time. By this way, a valid telegram on either line will
be recognised in any case. The decision, which line is “the prettiest one”, is taken
dynamically and does not depend on any state from before of the telegram under
question.
Now, LAT and RLD are the result from the reception of the “Device Status Re-
quest” Master Frame for the Device Status Report being sent, including RLD and
LAT.
This way, there is a clear geographic relationship of the result: the location of the
BA and the scanned device is known, and there is no hidden info included.
Since the BA scans all devices, the list of all DSWs gives an overview about the
general situation. This overview is available on all nodes (if they are able to re-
ceive DSWs at all).

Personal note from the author


In principle, it would make sense to propose these changes to the IEC working
group in order to get the situation simplified for new releases. However, this
would make a lot of “political noise”: it may happen, that existing systems loose
their “standard compliance”. Due to the fact, that (at least to my knowledge,
comments invited) there is no perfect complying solution on the market, I will re-
lax and see what comes...

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 64/109 d000656-003145 duagon

How to find cable faults by wire redundancy information


The “wire redundancy” as described in the previous section has the task to ensure
successful communication even if one line fails.
There is a second task to be performed: In case a failure exists, you should find it
and fix it. It makes sense to use the information gained from “wire redundancy
handling” and generate from it a statement about the health of the two lines.

Cable diagnostic according to IEC61375


Following the rules of the line switching, a
failure of one line will set the RLD bit in the LAT RLD Global
Device Status Report. The LAT bit indicates statement
which line is still “trusted”, therefore the
other must be the failing one. 0 0 OK. There is no
difference be-
In addition, two error counters accumulate
errors; seperately for both lines.
tween the two
1 0 combinations!
Both facts together allow some conclusions:
0 1 Failure Line_A
• If there is a failure, it will be
detected by RLD=1. 1 1 Failure Line_B
• If there is a failure, it will be The two combinations for OK
detected by all devices in a sim- will toggle from time to time
ilar way. If only one node re- according to the line switch-
ports errors, then this node has
ing rules; but this does not
probably lost one of its line re-
include any new information.
ceivers.
Unfortunately, some interesting conclusions are hard to find:
• If a single node is failing (one line transmitter defect), there is no way
to identify it, e.g. by its device address.
• The absolute height of the error counters does not really give some
information about the kind of failure: the definition is made in a way,
that severe wiring errors have the same effect as one single failing
node.
IEC61375 is a little bit fuzzy in the definition, which of the two coun-
ters is to be incremented. Obviously, incrementing is intended only in
case, the respective line is the trusted one. Since the line switching
will move the trusted line away from the found failure, the failure will
not generate additional counting. Thus, there is no additional infor-
mation beyond the “RLD” bit.
Intensive counting is possible only with more than one single failure
(which is not probable) or with collisions found. The main reason for
collisions is a wrong address configuration of a node, which should be
excluded by type testing beforehand.

Conclusion Derive the


Imagine
easily found influence upon
a failure
RLD, LAT bits

Find
Conclusion Measure the
failure
very tricky ! RLD, LAT bits
location

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 65/109

Cable diagnostics, next step


In order to give more information to the
field service people, another approach was LAT RLD The DSR-MF
choosen for newer MVB controller imple- was...
mentations (e.g. Duagon products; see also
“error counters for duagon products” on 0 0 OK. There is no
page 105): difference be-
tween the two
• The RLD and LAT bits are gen-
1 0 combinations!
erated during reception of the
Device Status Request Master 0 1 ...failed on A
Frame and transmitted during
the Device Status Report Slave 1 1 ...failed on B
Frame immediately following it.
Usually, there is no toggling
• During reception of both DSR between the two OK- combi-
and PD slave frames, an infor- nations any more.
mation about both lines is
stored individually. For the du-
agon products, the two bits are
called SINK_A and SINK_B. SINK PD or DSR slave
frame was ...
• The error counters are incre- A B
mented during the application
controlled read of DSR or PD ...not received
sink ports, using the mentioned 0 0 since last read
SINK_A and SINK_B bits.
This has the effect, that during ...not received
regular applications the error 1 0 on B
counter will measure faults rel-
evant to the own device, only. ...not received
Nodes, which are not involved 0 1 on A
in any trouble, will not report
...successfully re-
failures due to error counters.
ceived over both
The conclusions to be taken from this: 1 1 lines.
• Since the RLD and LAT bits are
derived from the transmission
of exactly one Master Frame, the information contained is related to a
clear geographic situation, since the location of the BA and the node
in question is known.
• This is also true for the nodes watching the DSR slave frame. They
may use the SINK_A- and SINK_B- bit and there is a defined geo-
graphic situation, too: Between the node sending out the device status
report and the watching node.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 66/109 d000656-003145 duagon

Based on these facts, diagnostic software may take various different conclusions:
• Consumer oriented (recommended for all nodes)
A simple check of the error counters allows to state, whether or not
the node is directly involved in trouble for the incoming data.
• Global focus 1 (a must for at least one node)
Combine all DSRs together: If at least one RLD bit is set, or if the error
counter>0, then there is a failure on a global perspective.
Note: reading the RLD bit will have the side effect, that any trouble
found by the SINK_A/SINK_B information is accumulated in the error
counters.
Check also, whether the number of intended devices equals the num-
ber of validly found DSRs.
• Cable diagnostics 1 (information derived from “Global focus 1”)
Diagnostic software may perform an automatic identification of failing
nodes via the device address.
• Global focus 2 (recommended for at least one node)
The measures taken in “Global focus 1” may take a while due to the
scan rate of DSRs on MVB. The scan rate depends on the BA's scan
strategy and may take up to 32s (following the IEC
recommendations).
A faster failure detection (less than 1s) relies on PD sink ports:
• Scan the error counters in a faster sequence than for “Global
focus 1”. This will find errors quite fast.
• The focus may be set to the PD ports used in the local appli-
cation anyways (this is achieved automatically) or the focus
may be extended to all PD ports being defined vehicle wide
(simply add dummy reads of these extra ports).
• Cable diagnostics 2 (information derived from “Global focus 2”)
In order to achieve the same speed for the identification of single fail-
ing devices, a mapping from PD ports to Devices may be implement-
ed.
• Cable diagnostics 3 (may be implemented in software running on a
node, running on a seperate PC with a diagnostic tool, or even by
hand)
Collecting all the RLD, LAT, SINK_A and SINK_B information from all
nodes, a pattern can be derived for “critical communication partners”,
which enables the user to develop probable failure models for the
specific case.
• Cable diagnostics 4 (implemented in software running on a node or
on a seperate PC with a diagnostic tool)
Elaborate diagnostic software may even focus the attention on one
particular transmission path (repetetively read a specific PD port, only;
and nothing else: Watch the error counter). By the height of the error
counters you will get a fast reaction upon mechanical influences. This
way you will find loose contacts or other dynamic failures.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 67/109

Practical example: How to find cable faults by DSRs


The procedure proposed here is basically valid for up- to- date duagon products
after 2002. Be aware, that other nodes (especially with old MVB controller chips)
may not fully support this kind of taking conclusions.
For this example, the bus structure was as follows:

1 16 17 18 32 256
BA d412

First step: Collect all Device Status Reports from all existing devices.
You may get this info from every node, which is able to receive DSRs at all. This
could be the Bus Administrator or any other node. This procedure does not need
neccessarily the correct BA list for your application; it requires simply the DSR scan
of an almost “empty” BA list.
Another way is to use a diagnostic tool. The printout below was generated by a
“d412 Diagnostic Tool” from duagon; the command was “List all devices found
during device scan on MVB”:
mvbMON>svd –a
number of devices: 5
---------------------------------------------------------------
| | | | C C C C | L R S S E F D S |
| device | device | S B G M | S S S S | A L S D R R N E |
| address | status | P A W D | 0 1 2 3 | T D D D D C R R |
---------------------------------------------------------------
| 0x001 ( 1) | 0x5380 | 0 1 0 1 | 0 0 1 1 | 1 0 0 0 0 0 0 0 |
| 0x010 ( 16) | 0x1080 | 0 0 0 1 | 0 0 0 0 | 1 0 0 0 0 0 0 0 |
| 0x012 ( 18) | 0x1080 | 0 0 0 1 | 0 0 0 0 | 1 0 0 0 0 0 0 0 |
| 0x020 ( 32) | 0x1040 | 0 0 0 1 | 0 0 0 0 | 0 1 0 0 0 0 0 0 |
| 0x100 ( 256) | 0x0042 | 0 0 0 0 | 0 0 0 0 | 0 1 0 0 0 0 1 0 |
---------------------------------------------------------------
mvbMON>

Everybody online?
Compare the number of received DSRs with the intended number of available
nodes. By this way you may find nodes being off-line.
In this example, obviously one device (address= 17) is missing. A
very common reason is that this device is switched off.
After having it switched on, the DSR scan looks like this:
mvbMON>svd –a
number of devices: 6
---------------------------------------------------------------
| | | | C C C C | L R S S E F D S |
| device | device | S B G M | S S S S | A L S D R R N E |
| address | status | P A W D | 0 1 2 3 | T D D D D C R R |
---------------------------------------------------------------
| 0x001 ( 1) | 0x5380 | 0 1 0 1 | 0 0 1 1 | 1 0 0 0 0 0 0 0 |
| 0x010 ( 16) | 0x1080 | 0 0 0 1 | 0 0 0 0 | 1 0 0 0 0 0 0 0 |
| 0x011 ( 17) | 0x1080 | 0 0 0 1 | 0 0 0 0 | 1 0 0 0 0 0 0 0 |
| 0x012 ( 18) | 0x1080 | 0 0 0 1 | 0 0 0 0 | 1 0 0 0 0 0 0 0 |
| 0x020 ( 32) | 0x1040 | 0 0 0 1 | 0 0 0 0 | 0 1 0 0 0 0 0 0 |
| 0x100 ( 256) | 0x0042 | 0 0 0 0 | 0 0 0 0 | 0 1 0 0 0 0 1 0 |
---------------------------------------------------------------
mvbMON>
Now, all six devices from the bus structure can be found in the
DSR list, i.e. no device is offline.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 68/109 d000656-003145 duagon

Are any RLDs set?


Check, whether all DSRs show perfect results: Good devices should deliver valid
DSRs, RLD=0; LAT is not important, it may be 0 or 1.
Example
Some of the existing devices have LAT RLD
RLD set: try to locate the fault.
Make a drawing with the BA and 0 0 OK.
all other devices on the bus with
1 0
the correct sequence as they really
have on the bus. This may give you 0 1 Failure Line_A
a closer impression about where
the fault must be located: always 1 1 Failure Line_B
consider the path between the BA
and the device in question.

RLD=1
Failure

RLD=0
OK

1 16 17 18 32 256
BA d412

Not the case in our example and not very probable, but still possible:
• Sometimes it is possible to contact nodes passing through a
faulty location.
• It may also be, that the cabling between the BA and a failing
node is ok, but the communication is still not possible (effect
of reflections).

Repair the fault !


You now may replace MVB cables and/ or short nodes (take them away from the
MVB by shorting the MVB- cables just in front of them). Watch, whether the failure
disappears and take your conclusions.

1 16 17 18 32 256
BA d412

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 69/109

Bus Administrators and their own DSR


Sometimes, bus administrators perform a little bit unexpected with regard to their
own DSR . In order to understand this, lets have a look into the details of how a
BA issues a DSR request to itself and how it replies with a DSR report.
Successful DSR sequence

1.
BA sends
MF
MVB
wire pair 2.
MF asks
for DSR
RS485
transceiver
3.
DSR-SF
is sent

• In a first step, the BA issues a master frame, containing a DSR request


with its own address. This frame is placed on the MVB by the RS485
drivers.
• In a second step, the MF, which was sent from the BA node, is re-
ceived from the MVB lines through the RS485 receiver. The node
recognises that it is addressed with the own device address and has to
reply.
Note: There is no shortcut within the BA node, which routes the
MF “silently” to the DSR response logic.
• Now the DSR response logic prepares the DSR report, which includes
generation of the LAT and RLD bits. The completed report is then dis-
tributed over the MVB lines.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 70/109 d000656-003145 duagon

What happens with failures


As long as there is no failure on the wires, the MF sent out has a reasonable
waveform on MVB (green shape):

1.
Short BA sends
circuit MF
MVB
wire pair 2.
MF asks
for DSR
RS485
transceiver
3.
DSR-SF
is sent

In case there is a short circuit on the outside, this waveform will be distorted.
Close to the short, the voltage will be zero (by definition), which would deliver a
flat zero line. However, back at the RS485 transceiver chip, a small remainder of
the original waveform can be seen (red shape).

In addition to a short circuit, also broken wires may introduce distorted wave-
forms. For an example, see page 98. However it is not very probable, that these
interferences will make the transmission of one device unreadable by the same
device.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 71/109

Will the red waveform be recognised?


The short spikes of the red waveform may exceed the RS485- receivers internal
hysteresis or not, depending on the involved physical parameters like line
impedances, speed and strength of driver chip, absolute level of receiver thresh-
old and the like. Therefore the MF may be recognised or not.
This is where the surprise starts:
• If the MF is recognised, then the DSR response logic will prepare an
OK (RLD=0).
The expected behaviour for a short circuit would be to have all de-
vices report an error, but the BA is excluded because he is still able to
communicate with himself.
• If the MF on the shorted line is not recognised, and usually the second
line successfully receives the MF, then the DSR response logic will pre-
pare a failure report (with RLD=1), as expected.
This failure reports is successfully distributed over the MVB (the second
line has no short-circuit! ). The BA and all other devices will be able to
receive it.
In the unusual situation, when both lines have a short:
• If the MF is recognised on one or both lines, then the own BA- node
will send a DSR- SF, which is received on the BA- node.
All other nodes will not see all this.
• If both lines are not recognised, then also the BA- node will not re-
ceive the own DSR.
Conclusion: If you are sitting on a BA- node, never use your own DSR to take
conclusions about cable failures.
Note: The older MVBC01 has some additional confusing properties which have
an influence on LAT/RLD generation; see page 61.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 72/109 d000656-003145 duagon

How to find cable faults by other checks


The previously described procedure to find cable faults “by redundancy informa-
tion” assumes that at least certain parts of the MVB cables are working correct.
Sometimes, an MVB installation does not work at all or the redundancy informa-
tion does not lead to any idea about the fault. In these cases, it is time to go back
to the basics and do some checks with the cable.
This is a short (and uncomplete) list of simple practical measurements to be taken:

All single cables checked?


See also the general cable structure on page 82.
• Each cable must show a connection between the two sides on pin
1,2,4,5 and Shield.
• The pins 6 and 7 must have a connection on ESD (potential equalisa-
tion lines); they must not have a connection on EMD (otherwise the
terminators are disturbed by extra wires).
• The pins 3, 8, 9 must not have a connection.

Measure the bias voltage with a multimeter (ESD only)


Switch the equipment on (at least the two end nodes) and measure the bias volt-
age.
• It must be 0.75V between pins 1,2 with being pin 2 being the more
positive one.
• For redundant wires: Same for pins 4,5 with 5 being the more positive
one.

Measure the two termination resistors with a multimeter (ESD only)


Switch off all equipment and measure the DC resistance between pins 1 and 2 (4
and 5). As result, you must see the approximate 120 Ohms of the terminator on
each side. You may have to add some extra for the wire copper resistance (realis-
tic order of magnitude up to 20 Ohms).

Measure the two termination resistors with a multimeter (EMD only)


If you measure DC resistance of an EMD wire pair, you will most probably see al-
most zero Ohms. This is due to the transformers, which have at DC just the cop-
per resistance of the primary winding. This does not give very much information.
You may pull out the cables at all nodes and connect the cables in a sequence.
Then, the resistance must be an “open” line, since there is no terminator at the
end.

Measure the cable length with a multimeter


Sometimes, the cable length is not known in a project because of last-minute
changes, due to e.g. routing in ducts. However, with the length being too high, a
limit may be exceeded.
Switch off all equipment. On one end, connect all wires together and measure the
capacitance against shield. Dependent on the cable type, you will find a capacity
of very roughly 75pF/m. You should calibrate your measurement with a piece of
cable with known length (e.g. 10m).
See also “cable characteristics” on page 83 and “cable attenuation calculation”
on page 84.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 73/109

Measure the cable length with TDR equipment


Cable length measurement is much easier to measure with TDR equipment (which
is by far more costly).
Please see also the chapters about “reflections” on page 88 and about “cable at-
tenuation calculation” on page 84.

Check the cable attenuation


By using a wrong cable type, the signal levels may be attenuated in an excessive
way. This has more or less the same effect as using a too long cable.
See also “cable attenuation calculation” on page 84.

Check wire allocation


During cable manufacturing, sometimes the allocation of wires to pairs is made in
the wrong way. This will lead to hard- to- detect effects like crosscoupling be-
tween the wire pairs. If you have simple tools, only: Open up the connector hous-
ing and check the allocation of wires compared to the cable data sheet.
Please note, that this type of manufacturing fault may be hidden for a long time
on a running vegicle: The high crosscoupling between the lines may not appear
as a problem during normal operation. However, the way to find an extra fault,
e.g. a single wire break, may become extremely tricky.
See also “wire allocation” on page 84.

All nodes EMD or ESD?


Of course, all nodes must comply to the same physical layer.
However, under certain conditions, nodes of different type may exchange data
with each other. Usually, it is a “one way”: ESD devices understand EMD tele-
grams (they check for the short end delimiter, only). EMD devices will not under-
stand ESD telegrams, since the NH part of the end delimiter is missing.
If you have such one-way phenomena, check the EMD/ESD- type of all nodes.

All nodes same redundancy level?


It is not allowed to add a non-redundant node to an MVB- segment, which is sup-
posed to run “redundant”. However, there are MVB products on the market,
which support non-redundant configurations, only.
• Duagon products would be tolerant to such a situation; they would
simply point to the node which is not able to transmit on both lines
(see the previous paragraphs). There is no loss of other functionality:
all other nodes will be recognised as redundant and the dynamic line
switching handles subsequent faults on either line.
• Nodes complying to the standard with respect to line switching will
encounter a general “Line B fault” and seriously loose data by any ad-
ditional failure.
Since a vehicle contains always a mixture of different MVB controller manufactur-
ers, we highly recommend to keep the principle “all node on same redundancy
level”.
Note: adding a redundant node to a non-redundant MVB- segment is usually no
problem: no other node will care about this fact; and on the added node you can
configure the node by software in a way, that it behaves like a non-redundant de-
vice.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 74/109 d000656-003145 duagon

Comparison EMD – ESD+


The decision for one of the physical layers has an influence on the hardware and
the MVB controller chip; but for all upper layers, it does not make any difference.
From this point, the application engineer is free to decide between EMD and
ESD+ as long as he is able to purchase all equipment of the selected type.
However, there are some small, but sometimes important issues, that make a dif-
ference between the two physical layer choices.
Please find below a table with the conclusions. The remarks and explanations for
the detailed items are in the following paragraphs.

Issue EMD ESD+


Max.bus length 200m+ *) 200m- *)
Robustness against noise Yes *) Yes *)
End delimiter NL + NH symbol NL or less *)
Cable wires 1 pair 1 pair + 1 GND *)
(redundant) (2 pairs) +(2 pairs + 2 GND)
* = see comments below.

Bus length EMD


The requirement from the IEC standard is to have at maximum 8dB attenuation
between any two nodes: 1.5V minimum driver amplitude minus 8dB delivers ap-
prox. 0.6V. Since the sensitivity of usual receiver chips is much better (200mV),
there is plenty of safety margin. See also measurements for “EMD full bus load”
on page 100.

Bus length ESD+


Due to the biasing of the line with 0.75V, the attenuated driver signal is going to
disappear at the far end of the line. Thus, the required 8dB seems not to be en-
sured in all cases. See also measurements for “ESD full bus load” on page 99.

Noise rejection
The IEC61375 paragraph 3.2.5.10.6 specifies the “noise rejection” of an EMD re-
ceiver. This feature is type tested on the more modern MVB controller chips (e.g.
duagon). During the early times of EMD, especially the common mode noise spec
was not fulfilled.
There is no paragraph in the IEC61375 about ESD noise rejection. This issue is
believed to be covered by the line biasing (the 0.75V on an idle line). By this way,
any noise must be higher than this bias in order to become a detectable noise
signal.
A drawback of this concept is the fact, that it requires both end nodes to be validly
powered (see measurements on page 102). If one end node is switched off, the
terminator will not deliver the bias voltage any more, i.e. the bias voltage will
drop to 50%. If also the second end node is powered down, then there is no bias
voltage any more and the receiver is now open for any noise being higher than
the 50mV receiver hysteresis (which is the same situation as for the EMD).
However, this is a problem for old MVB controller designs, only: e.g. MVBC01.
This design relies on the fact, that the noise is filtered out before the digital logic.
Newer designs, as for example the duagon products, apply the same digital filter-

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 75/109

ing algorithms in internal logic for EMD and ESD. By this way, they do not require
a bias voltage any more.
Conclusion: if it is required from the application to work reliably also with un-
powered end nodes, be sure to have all nodes equipped with digital filter algo-
rithms that are able to fulfill the EMD- noise- rejection- type tests.

ESD end delimiter


The specification of the ESD end delimiter leaves room for trouble in practical life.
See also the chapter “MVBC01 and ESD end delimiter” on page 93.

Cables
The cable specification for ESD requires to have additional “potential equalisation
lines, which makes the cables slightly more expensive and less handy. See also
pages 82, 101 for “potential equalisation lines” and page 77 for “terminator sup-
ply”.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 76/109 d000656-003145 duagon

Electrical Short Distance Bus ESD, ESD+


Introduction to ESD
The ESD physical layer equals basically RS485, with some minor differences.
When run with the 1.5MBit/sec, the length of one segment is up to 20m (including
a reasonable safety margin for noise, following RS485).By this way, the name
“short distance” was introduced.
Historically, this was the very first physical layer proposal before the IEC standard-
isation was finalised; the original idea was to use it in small areas, only: e.g. with-
in one rack of electronic equipment or within the driver´s cab. As a complement,
the OGF was intended to be used for longer distances.
The specification for the ESD in the IEC61375 essentially reflects this early phase
of MVB development. In a later phase, the ESD was enhanced by introducing gal-
vanic insulations for all nodes. This helped to reduce the common mode noise on
the line by breaking up ground loops. Since the definition of an idle bias voltage
reduced differential noise compared to RS485, the practical use was extended to
applications of up to 200m of segment length. This is the same application range
as for the EMD!
Today, the ESD is available in this enhanced version, only. It is very often called
“ESD+”, and it reflects the IEC standard with additional galvanic insulation of the
node transceivers. Due to this fact of the market situation, the “ESD+” is often un-
derstood to be the generic “ESD”.
The move from ESD to ESD+ (and EMD) had also another effect: the OGF, previ-
ously intended for the long distance (up to 2000m) is more or less disappeared
from the market. Even though the optical concept has some very nice technical
features, there is almost no market volume for it.

Typical Node Structure ESD+

DC
power
MVB IC
lines data in
OC
data out
RS485 SF
transceiver enable
Galvanic
insulation

The picture shows the basic elements of a typical ESD+ - node:


• The RS485 transceiver chip is directly coupled to the MVB lines.
• All signals, as well as electrical power, have to be delivered passing a
galvanic insulation. This insulation is not required for ESD, it essen-
tially makes the “+” within “ESD+”.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 77/109

Terminators ESD+
When the MVB line is linearly
5V.term built up with cables between the
390 Ohm various nodes, two connectors,
A.data.n each at the very end of the line,
150 Ohm Line A
remain open.
A.data.p
390 Ohm The two terminators are mount-
0V.term ed on these connectors and de-
livers the correct line termina-
5V.term tion.
390 Ohm
The resistors inside will bias an
B.data.n
„idle“ line when not driven by a
150 Ohm Line B
B.data.p node transmitter. The effective
390 Ohm line termination matches the rec-
0V.term ommended cable impedance of
120 Ohms.

Pin definition ESD+

Input / Output as
SUB-D
Pin shortcut seen from the Description
Pin #
node
1 A.data.P non- inverted MVB bus line,
with RS485- level
bidirectional
2 A.data.N inverted MVB bus line,
with RS485- level
3 NC - Not connected
4 B.data.P non- inverted MVB bus line,
with RS485- level
bidirectional
5 B.data.N inverted MVB bus line,
with RS485- level
6 A.0V.term
8 A.5V.term Terminator supply:
Power output Power from node to external ter-
7 B.0V.term minator
9 B.5V.term
shell Shield Connection to shield resp. hous-
-
ing.

According to the TCN standard, pin 3 may optionally be used for a “TxE signal”.
This signal is intended for controlling bus couplers (for example interface from
ESD+ to EMD). However, this function has not found introduction to the market.
Within a node, all signals and the shield of the two connectors are connected to
each other.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 78/109 d000656-003145 duagon

Terminator Supply ESD+

Item Value Unit Remarks


Output voltage 5 V +/-5% tolerance
Short circuit current limitation 300 mA See note
Maximum output current 70 mA when terminator driven „ac-
tive“

The main intention for the short circuit current limitation is to avoid any fire haz-
ard in case due to overheated wires.

Note: The Terminator supply pins 8 and 9 must not be connected within a cable.
This may lead to back- powering the node´s local supply from another node and
may impair proper functionality or even damage devices!
Note: There are cases, where the output current specification is not sufficient.
Some OGF interfaces (Optical Glass Fiber) require a supply current of approx.
100mA. For this application, we recommend to bridge the normal galvanic insula-
tion and directly use the Vcc power line from the local logic power supply (ESD in-
stead of ESD+). This leads to a higher possible current (close to what the power
supply can deliver), but the “short circuit current limitation” spec (see IEC61375) is
not kept any more.

MVB Cable Attachment ESD+

The figure shows the recommended


cable attachment.
The dotted lines are the “potential
equalisation lines”. They have the in-
tention to connect all MVB nodes to-
gether.
5 4 3 2 1

9 8 7 6

Please note: Pin 3, 8 and 9 are not connected on the outside. Do not use cables
where all pins are connected, this may impair proper functionality or even dam-
age devices!

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 79/109

Electrical Middle Distance Bus EMD


Introduction to EMD
The EMD specification was derived from the early ESD definition. The intention
was to introduce a galvanic insulation of the node electronics by a transformer.
During standardisation, there was a political fight about the implementation of
the galvanic insulation: by transformer (EMD) or by DC/DC-converter and opto
couplers (ESD+). In order to resolve this conflict, the standard was finally written
in a way, that it will allow both parties to use their preferred solution. This is why
we have today ESD+ and EMD in the same application area (remark: usually, it is
the intention during standardisation to prefer one technical solution).
From the technical situation, the EMD is supposed to be the cheaper solution (a
transformer is usually cheaper than a DC/DC- converter plus opto couplers).
However, what makes EMD more tricky to implement: the EMD cannot make use
of a bias voltage on the line. On the ESD+, the bias voltage delivers an implicit
noise reduction, being understood to work this good, that there is no need for ad-
ditional specification. Unfortunately, transformers do not conduct bias voltages
(DC!); i.e. the noise robustness of the EMD had to be proven by other means. This
was the reason, why in the standard there are detailed specifications about noise
behaviour for the EMD, but not for the ESD.
During the early days of EMD, it was difficult to fully comply to the standard, es-
pecially to the “common mode noise” specification. This issue was resolved by a
new generation of controller chips several years ago. Today, the EMD seems to be
the more attractive solution, even though both ESD+ and EMD are found to be
strong in the market.

Typical Node Structure EMD

DC
power
IC
MVB data in
lines
OC
data out
RS485 SF
transceiver enable
Galvanic
insulation

The picture shows the basic elements of a typical EMD- node:


• The RS485 transceiver chip is coupled to the MVB lines via a trans-
former.
• All signals are directly connected to the MVB controller logic; the elec-
trical power is identical to the power for the local CPU.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 80/109 d000656-003145 duagon

Terminators EMD
The termination resistors itself are located inside the
node; and they define the effective line termination
of 120 Ohms.
The “terminators” for the EMD contain small connec-
tion wires from the signal lines to the termination
resistors, which are located within the node.

Pin definition EMD

Input / Output as
SUB-D
Pin shortcut seen from the Description
Pin #
node
1 A.data.P non- inverted MVB bus line,
with RS485- level
bidirectional
2 A.data.N inverted MVB bus line,
with RS485- level
3 NC - Not connected
4 B.data.P non- inverted MVB bus line,
with RS485- level
bidirectional
5 B.data.N inverted MVB bus line,
with RS485- level
6 Passive resistor (120
A.term
8 Ohm) within node
Termination resistor between the
7 two pins.
Passive resistor (120
B.term
9 Ohm) within node

shell Shield Connection to shield resp. hous-


-
ing.

According to the TCN standard, pin 3 may optionally be used for a “TxE signal”.
This signal is intended for controlling bus couplers (for example interface from
ESD+ to EMD). However, this function has not found introduction to the market.
Within a node, all signals and the shield of the two connectors are connected to
each other.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 81/109

MVB Cable Attachment for EMD

The figure shows the recommended


cable attachment.

5 4 3 2 1

9 8 7 6

Please note: Pin 3 and 6 to 9 are not connected on the outside. Do not use ca-
bles where these pins are connected, this may impair proper functionality or even
damage devices!

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 82/109 d000656-003145 duagon

Cables
The technical properties of the wire- based EMD and ESD- cable are defined with-
in IEC 61375, part 3.

Cable Structure
Dependent from the decisions ESD or EMD respectively line-redundancy or not,
there are four different choices for the internal cable structure:

EMD-S EMD-R ESD-S ESD-R


EMD ESD
Descrip- Signal EMD redundant ESD redundant
tion name single line lines single line lines

Line_A A.data.P X X X X
twisted pair A.data.N X X X X
potential
equalisa- A.bus_gnd X X
tion line A

Line_B B.data.P X X
twisted pair B.data.N X X
potential
equalisa- B.bus_gnd X
tion line B
Shield shield X X X X

Personal note from the author


The “potential equalisation lines” for the ESD are required by the standard. When
you “forget” them, your system will work anyway; refer also to the measurements
on page 101. In fact, for several years of the standardisation process, these lines
were not included; they appeared at a relatively late stage. For me, it is not really
clear, why these lines are included; but: Standard is standard, so I recommend to
include them. Comments invited!

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 83/109

Technical data
These technical requirements are applicable to the twisted pair conductors of all
four different cable structures:

Issue Value
Characteristic impedance measured with sinusoidal signal 120 Ohm
at 750kHz and 3MHz equals... +/- 10%
Cable attenuation measured at 1.5MHz less than ... 15 dB/km
Cable attenuation measured at 3.0MHz less than ... 20 dB/km
Distributed capacitance measured at 1.5MHz not more 46 pF/m
than ...
Capacitive unbalance measured at 1.5MHz to shield not 1.5 pF/m
more than ...
Crosstalk rejection from Line_A to Line_B measured at 45 dB
750kHz to 3MHz higher than...
Shield quality measured at 20 Mhz see IEC 60096-1 (IEC 0,02 Ohm/m
60096-1 mainly addresses coax cables, but it may be
used for twisted pairs considering the short circuited line
pair as the inner conductor and the shield as the outer
conductor.
Transfer impedance less than ...
Differential transfer impedance less than... 0.002 Ohm/m
Twisted pair 12 twists/m
Cross- sectional area of wire recommended... between 0.34mm2
(AWG22) and
0.56mm2 (AWG20)

Personal note from the author


To be honest: I have never seen a cable, that really fulfills all of these specs (You
did? Please tell me...).
Most twisted pair cables on the market do not fulfill the attenuation figures, some
are not “double twisted pair” but “quadruples”, some do not comply to general
railway requirements (what happens to the insulation at -40º Celsius?).
In general, the “cable attenuation” is tough to achieve and this leads to fairly stiff
and heavy cables (I am always joking about “indoor plumbing”). From this point
of view, I understand the wish from the application engineers for slim and flexible
cables.
Please take the following paragraph as a guide for those cases, where you do not
have to fulfill the IEC61375 in perfection. Dependent from the segment length
and the number of nodes, you may get an optimised approach for your specific
application.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 84/109 d000656-003145 duagon

Attenuation calculation
The maximum attenuation for the signal travelling between any two devices is
8dB. This is a requirement for the frequency range between 750kHz and 3MHz.
The total attenuation is usually determined by the attenuation from the cable
length plus the attenuation from the number of nodes (0.15dB per node).
Example: Does a cable with an attenuation of 22dB/km work with 12 nodes and
a cumulated bus cable length of 80m?
Attenuation from the cable: 1.76dB = 22dB/1000m * 80m
Attenuation from the nodes: 1.8dB = 0.15dB/node * 12 nodes
Total attenuation = 3.56dB; which is less than 8dB: Yes, this will work.

Wire allocation

Cables with 2x2 wires ...

The classic cable assembly consists of two pairs Twisted pair


of wire; each of them having the two wires Line_A
twisted around each other. As an option, the
power equalisation is routed as separate wires.
The shield covers all wires together.
Twisted pair
Line_B

Equalisation line
(optional)

Shield

...or with 1x4 wires


Also widely used is the “wire quadruple”. This Twisted pair
assembly method usually yields smaller cables Line_A
and is also available with optional equalisation
lines (not shown in the picture on the right side).
Twisted pair
Note: be sure to have the wires allocated to Line_B
Line_A and Line_B “over cross”; as shown in the
picture. With this arrangement, the unwanted cross coupling between the two
wire pairs is minimised.
If this rule is not fulfilled, there may be problems in the field, which are hard to
locate: the maximum bus length is significantly reduced, and/or the behaviour
with a cable break is completely confusing.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 85/109

SUB-D- connectors

There is a wide variety of different manufacturers for “sub-D” cable connectors.


For the cable connector itself, the user may choose a supplier to his own
requirements: the various versions are selected according to obvious quality level
versus cost considerations. There are no big issues left being special with the use
of the MVB.
However, for the connector hoods, duagon recommends to check some issues
more deep:
• Shield continuity: The MVB requires to have a shield being routed
through the nodes. Therefore the user has to make sure, that the
connector has a good conducting path between the cable shield and
the connector shell.
In this sense, a metallic hood is the best solution. Plastic hoods with
metallisation are less than perfect; pure plastic is recommended for
special purposes, only (e.g. in-rack- cabling, lab use).
Some connectors have “dimples” with the intention to install a
conductive path between the two metal shells. These are of benefit,
but it is good design practice, not to rely completely on these contacts
(almost never, they are specified with e.g. contact resistance). Always
consider the screw cable locks as the main shield contact.
• Mechanical compatibility: The hood must not interfere with the
node´s housing. The main questions are:
• Does the cable connector hood allow to fully mate on the
fixed Sub-D- connector?
• Does the size of the hood allow to plug in both MVB
connectors at the same time? The distance of the two MVB-
connectors may be too close to each other.
• Cable locks: The MVB uses M3- thread for the cable locks. Be sure
not to apply the UNC4/40 thread to it; it will damage the thread.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 86/109 d000656-003145 duagon

Cable hood examples


The list of cable connectors below is not complete. This relates both to the number
of manufacturers as well as to the number of different connector types. Since
there are this many numerous options, our best experience is to contact the local
dealer and get a recommendation for your application needs.
Note: the text below contains quoted “keywords”. This is a reasonable way to start
the search on the respective home page (everyone has a different name for
“hood”).

www.ittcannon.com

“Die cast zinc metal backshell” Part number for the hood e.g. 980-2000-345.

www.erni.com
The “cable connector housings” of the series
KSG200 are an interesting mix of plastic hood
with metal shield inserts.

www.harting.com
Full metal and metallised thermoplastic
“hoods”.
Top entry and side entry versions. Some
of the side entry versions have only one
lock screw: please check, whether the
reduced mechanical stability suits your
application.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 87/109

www.3m.com
“Metal EMI junction shell”, 3357-92xx series.

connect.amp.com
Look for “cable clamps”, they have a wide variety. AMP is now within “Tyco
Electronics”.

www.mhconnectors.com
For example “Mhulti Sub D Hood System”.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 88/109 d000656-003145 duagon

Reflections

What they are useful for...


“Reflections” are used in TDR “time domain reflectometers” in order to measure
the impedance of a transmission line over its length. As a measurement result, a
chart is generated showing either the “characteristic impedance” or the “reflection
factor” over the length of the line.
In general, it is good to have a smooth 120Ohm as specified for the cable, all
over the whole line, including all connectors and node transceivers.
However, due to the generic properties of connectors and mainly RS485-
transceiver chips, it is not possible to get a perfect transmission line: real world
nodes always show a certain mismatch into the “capacitive” direction.
Using a TDR makes sense for checking the cable integrity in general. You will see
the length of the transmission line, the nodes distributed on it and the amount of
reflections/ impedance mismatch.
A practical question: Where is the threshold to decide between “still good” and
“already bad”? Unfortunately, the absolute height of the “impedance mismatch”
depends on the bandwidth of the TDR equipment: a perfect device, with unlimited
bandwidth, would find an impedance of 0 Ohm (capacitive behaviour!) respec-
tively 100% reflection. From this point, it is recommended to collect some experi-
ence with the particular TDR equipment in use, and define your own limits be-
tween “good” and “bad”.
Unfortunately, it is not this easy to get an idea, where this limit should be. Practi-
cal life experience shows, that even examples with excessive mismatch (80 Ohm /
20% reflection) still work fine.

... and what they are bad for...


“Reflections” are also generated during normal operation by the MVB signal
frames. In principle, reflections could also disturb the communication. But before
going to the conclusions, let´s have the basics first:

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 89/109

What are reflections?


• A signal transmitter drives a transmission line with a defined wave form.
• The signal wave travels along the transmission line.
• When there is an impedance mismatch, then the wave is reflected, travelling
backwards in direction to the transmitter.
• The reflected wave depends upon the type of impedance mismatch.
Examples for reflections are „open end“, „short circuit end“ and „capacitive“, as
found on typical MVB nodes.

This picture shows a simplified MVB with the TDR (=transmitter and receiver) on
the left side; the point of reflection in the middle is the MVB device under test. The
far end, shown here as a termination resistor, could also be an open end: this has
no influence on the measurement of the MVB device, the reflection from the far
end can be distinguished by its later arrival back at the TDR receiver.

Please note, that all the pictures shown in this text are made with a waveform be-
ing 8 times faster than normal MVB waveforms (42ns instead of 333ns). This was
chosen for better visibility of the effects under discussion.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 90/109 d000656-003145 duagon

Open end

Original wave and its reflection from an open end, i.e. reflection = 100%.
Cable length 20m.
The cable shows a clear low pass behaviour. The edges are smoothed significant-
ly. The reason for this is the increasing cable attenuation with frequency; main
contributor is the skin effect on conductors.

Short circuit

Original wave and its reflection from a short circuited end; 100% reflection.
Cable length 20m.
As a main difference to the open end, the polarity of the reflection has changed.
Note: Independent from “open” or “short” test setup: This simple test is also a
nice way to find out the cable attenuation: As you can see, the reflected wave is a
little bit smaller than the exciting waveform. In this example, it is very roughly
-2dB on 40m of cable. However, be aware that this attenuation relates to the fair-
lay high frequencies (beyond 12MHz) used in this test. The MVB- standard defines
attenuation at 0.75 to 3 MHz.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 91/109

Capacitive Mismatch

Measuring an MVB device with fairly high reflections.


The exciting wave form comes from a high bandwidth source, like a TDR device.
The reflection has the same polarity as short circuit, this relates to a capacitive be-
haviour (short circuit for high frequencies).
The reflection clearly shows high pass behaviour: Just the edges of the original
waveform are reflected. The main spectral contribution of the exciting waveform
(here: 12MHz) is not reflected at all.

Same setup as before, but now the exciting wave form is generated by a real-
world- RS485- tranceiver chip (MAX3088): Due to the reduced bandwidth of the
sender, the reflection is smaller: 0.260V instead of 0.600V.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 92/109 d000656-003145 duagon

TDR measurement conclusions


• TDR equipment will find the MVB node transceivers and the T-stubs
from the cable attachment. This is an implicit property of the MVB ar-
chitecture with multiple nodes on one cable segment.
• TDR equipment checks the wiring at high frequencies: Usual TDR de-
vices are located in the range of 300MHz and beyond. This leads to
the fact, that the MVB nodes with their capacitive behaviour will yield
more “impressive mismatches” than applicable.
• The frequency range, being relevant for the MVB communication, is
between 0.75MHz and 3MHz. This is far below the tested bandwidth
from the TDR. Reflections are far lower at these frequencies.
Therefore, TDR equipment can be used very well for cable continuity checks, but
not very well for defining an absolute level for good/bad- decision.
Note: This situation is completely different for e.g. 100MBit/s- Ethernet: There,
the higher frequencies are really used for communication; reflections are there-
fore critical. And: they use twisted pair wires in a point-to-point- arrangement, i.e.
there are no nodes in the middle of a transmission line! By this way, there are no
capacitive reflections from transceiver chips or from T- stubs.

Interference by reflections
Reflections, when travelling in the opposite direction of their originating frame,
may disturb communication.
There are basically two different causes for reflections: the terminators at the very
end of the line and the nodes with their capacitive behaviour.
• The terminator and the cable impedance are specified with 10% tolerance.
When two terminators and the cable impedance use their tolerances to the
worst, reflections of up to 20% amplitude are generated (10% reflection by
mismatch from one end, superposition from both ends). Without the cable at-
tenuation, an exciting waveform of 5V amplitude will generate reflections of
1V, which is by far too high. Unfortunately, a mismatch in termination will
yield reflections also in the interesting frequency range of up to 3MHz.
• As a remedy, we highly recommend to specify the terminators to a
closer tolerance than 10%. For EMD, it seems practical to use 1% re-
sistors; for ESD the proposed combination of 390Ohm and 150Ohm
resistors with 1% tolerance has also yielded good results from the
field experience.
• The reflections from the nodes mainly consist of high frequency contributions.
Due to the higher cable attenuation for these frequencies, an effect can only
be seen in the close proximity of the transmitting node. As a result, the reflec-
tions disappear within a short time, usually within less than the interframe
spacing.
• For the EMD, the frame decoder will neglect the remaining interfer-
ence: This feature is basically type tested by the different topic “noise
rejection” of the MVB standard (see there paragraph 3.2.5.10.6).
• For the ESD, there are no specifications with regard to the decoder´s
robustness against noise, i.e. all noise with an amplitude beyond
0.75V may become critical.
As a remedy, we recommend to use a frame decoder design, which
filters noise in the same way as the EMD- counterpart. This way, high
frequency noise is reliably filtered out.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 93/109

Note: Unfortunately, the popular MVBC01 controller chip does not support this
kind of filtering. On top of that, due to a lack in specification, it is excessively sen-
sitive for noise at the end delimiter. If it is not possible to avoid the use of
MVBC01- based devices at all, we recommend to have a closer look on communi-
cation stability.

ESD end delimiter


About the details...
In the IEC61375, Part 3 "MVB", there are statements that look like a contradiction
in itself:
• In clause 3.2.4.8.4, the statement for the "end of frame" is, that the "transmit-
ter shall drive the line actively towards the LOW state for at least 0.125mi-
croseconds and at most 1.0BT".
After this time, the transmitter will stop driving actively, and the line will go
back to the idle status, i.e. the 0.75V bias voltage as defined by the termina-
tors (see 3.2.4.2.4).
• In clause 3.3.1.6 "End Delimiter" it is written, that the transmitter shall "append
an NL symbol and cease transmission as specified in 3.2.4.8.4". How to under-
stand this? An "NL symbol" is the same as "1.0BT low level": A device, that
sends "NL" complies to both clauses. A device, that sends only for 0.125mi-
croseconds complies to the first statement, to the second not.

In this picture, the red and green signals represent the two different points in
time, where the transmitter switches off (becomes high impedance).
• The usual interpretation of this issue is, that the MVB line, when becoming in-
active will have the status "low level" automatically, i.e. the "NL" is not neces-
sarily to be driven.
This interpretation finds its application within the widely used MVBC01 chip: The
transmitter stalls driving after the minimum time of 0.125microseconds.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 94/109 d000656-003145 duagon

On the other side, all MVB controllers check the existence of the NL symbol and
will not recognise a frame as valid if there is something else as NL. Again, this is
not a problem, as long as the idle line shows a valid low level (= idle state by bias
voltage).
• A potential problem occurs now under non-ideal conditions. Since the MVB
line is not driven any more during the end delimiter, the line is to a higher ex-
tent subject to interference: this could be any general EMI, but also reflections
from other nodes, that propagate backwards on the line. In the picture from
before, this is represented by the “red” and “green” disturbances: Obviously,
for the same size of disturbance, it is easier to cross to the high level from the
bias voltage (-0.75V) than from the transmitter voltage (-1.5V to -5.0V).

...and the consequences


The critical situation is, when interference becomes bigger than the bias voltage,
i.e. 0.75V. This could be by means of reflections or other differential mode noise,
but also by common mode noise (typically by high EMI levels within the node elec-
tronics). “Common mode” type of noise will be suppressed to a certain ratio, but
will still contribute to the differential figure.

How to deal with missing frames?


The usual effect from this MVBC01- issue are statistically missing frames (in most
cases found out by missing PD frames). When you encounter such a situation, try
to make measurements with a scope on the involved nodes: Have a close look to
the received end delimiters. When the signal level is “high” or at least close to
“high”, then you should have a tight look to the general noise situation of your
system: reflections, node internal noise, e.g. by DC/DC- converter, etc.
A substitution of the MVBC01 by a better MVB- controller will enhance noise re-
jection approximately by a factor of 5.
Note 1: For example, the non-MVBC01- duagon products always transmit frames
with the full end delimiter. This leads to the fact, that such a device transmitting
data to all other nodes is highly reliable.
The problem rises only in case a MVBC01 chip sends a frame to any other node.
Note 2: the EMD bus is not influenced by this discussion. There are completely
different end delimiters as well as another strategy against noise (no bias
voltage).

Personal note from the author


Obviously, the specification within the IEC61375 for the ESD end delimiter is less
than perfect. It unneccessarily reduces noise rejection, especially for reflections.
My recommendation would be: Fix the end delimiter to “transmission of NL” and
do not allow “cease transmission after 125ns”.
However, this would have the effect, that existing (and basically working!) solu-
tions would not be compliant any more: does everybody agree?
My silent hope is, that any new controller designs will always “send NL”.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 95/109

Oscilloscope Checks
Using an oscilloscope helps a lot during debugging of physical layer issues.
However, the pictures you get from a simple attachment to the MVB lines are of-
ten very confusing.
The following examples of oscilloscope printouts may help to understand your
own measurements much better.

Scope attachment
Channel 1 and Channel 2 represent the MVB lines as they are attached to the
node. In order to keep the symmetric properties of the MVB lines, do not use e.g.
Data.P for the signal tap and Data.N for the ground strap! The respective ground
line is connected to the local ground of the RS485 transceiver chip.
The mathematics trace M is the difference between Channel 1 and 2. The RS485-
receiver detects the difference between the two inputs, i.e. the M trace is effec-
tively the signal waveform being relevant for the receiver.
Channel 3 is sometimes used for trigger purposes. “SF” is the signal, which en-
ables the RS485- transmitter; this is ideal to trigger on transmission from the own
node.

DC
M= power
CH1 - CH2
IC
Data.P data in
Data.N OC
data out
CH2 CH1
SF
enable
Local CH3
ground

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 96/109 d000656-003145 duagon

Everything OK
MVB MVB
50m 50m
T 1 2 T

CH2 CH1

This is a perfect looking start of a frame, in this case sent out from node 1 and
measured at the same place.
Ch1 and CH2 are working inverted to each other.
Before the frame starts, there is a “bias” voltage between the lines (ESD!). The
nominal value is -0.75V.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 97/109

Everything OK
MVB MVB
50m 50m
T 1 2 T

CH2 CH1

In this case the frame is sent out from node 1 and measured at node 2.
This is still a perfect looking frame, but now after 50m of cable. The “square
wave” suffered a little bit from the low pass behaviour of the cable.
Note: there are no other nodes on the cable between node 1 and 2. If this would
be the case, the low pass effect would be much higher.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 98/109 d000656-003145 duagon

Terminator missing
MVB MVB
50m 50m
T 1 2

T
CH2 CH1

Oops! Communication is not possible any more. What happened?


This is the same measurement as before, but now the bus terminator at the far
end is missing. Obviously, there is a reason for using terminators.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 99/109

Full Bus Load ESD+


MVB MVB
150m 50m
T 1 2 T

C C
CH2 CH1
CH3=
local IC

In this test setup, the total bus segment length was increased to the maximum of
200m. In addition, a capacitive load was introduced in order to simulate the ef-
fect of alltogether 32 nodes.
Remark: The RS485 transceivers introduce mainly a capacitive load to the bus
lines. There is also a resistive load, but this does not play a role at the typical MVB
frequencies.
The attachment of nodes increases the “low pass” filter effect of the cable drasti-
cally.
The signal shown in the picture is well understood; i.e. it is still normal. This is re-
flected by the digital input to the MVB controller (IC), Ch3: It is a clear wave form.
However, a certain trend can be seen:
• The signal is attenuated, showing a triangle wave form.
• The RS485 receiver detects a level change around the M- zero line.
• Since the bias voltage of the ESD+ shifts the signal wave form to the
negative side, the MVB controller will see a shorter high level resp. a
longer low level.
If the cable would become longer, then the signal wave form would become more
attenuated: the communication will stop, because the signal is lost below the bias
voltage.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 100/109 d000656-003145 duagon

Full Bus Load EMD


MVB MVB
150m 50m
T 1 2 T

C C
CH2 CH1
CH3=
local IC

Basically, this is the same situation as in the previous paragraph.


But now, there is no bias voltage any more: EMD does not use bias and the sig-
nal waveform is centered around zero, by definition.
There is no effect of “signals dropping below bias”, as it was the case for ESD+.
The digital receiver signal Ch3 is much more symmetric than before, but still does
not reflect the perfect high and low times. The main reason for this is the used
RS485- receiver, which has a threshold being shifted to the negative side by man-
ufacturer specification. This effect is introduced on purpose; it avoids noise ringing
during bus idle lines.
Conclusion: For full load situations, the EMD has obviously more safety mar-
gin for reliable operation.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 101/109

ESD+ Power equalisation line


MVB MVB
50m 50m
T 1 2 T

CH2 CH1

This is the same test setup, as it was shown for the “everything OK” case on page
97.
But now, the power equalisation lines have been taken away:
The time scale of the scope was changed to show a sequence of several frames.
The frames come from different nodes. Since there is no connection between the
local grounds of the involved nodes any more, the average voltage with respect to
the local ground will vary:
• As long as the node is not active, the weak resistors within the RS485
receiver pull the local ground in direction to the signal signal lines.
• When the node is active, the average of the signal lines is pulled to
approximately half of the local driver supply, i.e. typically the local
ground is pushed 2.5V to the negative direction.
Conclusion 1: With missing power equalisation lines, the local grounds of the in-
volved nodes, when compared to each other, will bounce up and down.
Conclusion 2: Conclusion 1 does not matter. The relevant issue is the difference
between the two signal lines, see trace M. It is still perfect; no bouncing at all.
Communication is fully operational.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 102/109 d000656-003145 duagon

ESD+ Loss of Bias


MVB MVB
50m 50m
T 1 2 T

CH2 CH1

This is the same setup as shown on page 97 for the “everything OK” case.
First one of the two terminators looses power, then the second one, too.
• The loss of bias can be seen when the lines are idle, i.e. between the
frames. One terminator powered will yield approx. 0.75V/2 =
0.375V. When both terminators are down, no bias is left, i.e. 0V.
• In case, both terminators are without power, the signal lines do not
have their average voltage of around 2.5V to local ground any more.
During idle times, the two lines have around 0V against ground.
However, when a node drives the lines, the average of +2.5V is
forced, again. This leads to an interesting “common mode wave” (see
the right picture above); the wave travels from the transmitting node
to the terminators and via the power equalisation lines back to the
originating node.
Conclusion (similar to the one on page 101): The difference signal M is not
disturbed, communication is up and running – with the exception of the two
unpowered nodes with the terminators., of course.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 103/109

Mixed pickles
This chapter lists some very special issues; intended as “tips and tricks” for the
advanced MVB expert.

Priorities during Event Arbitration


The MVB allows an event arbitration to take place with two levels of priority (low
or high). By this way, it could be possible to select message data faster or slower,
according to its importance.
Unfortunately, the “event arbitration priority“ is a feature of the Link Layer, only. It
is not supported by the RTP upper layers, i.e. there is no way to control this
feature from the application.
Due to this, we recommend not to make use of this feature; use always „LOW
priority“, only.

Base Period Timing Variants


The standard allows also other basic cycle times; like e.g. 1.667ms. The idea
behind it was to synchronise the bus traffic with for example 60Hz power line
frequency (10 base periods * 1.667ms = 16.67ms, which is one cycle of 60Hz).
The potential benefit for this could be, that certain measurements (current,
voltage) can be distributed over the MVB without latency. Fast control loops in
power controllers do not accept very much delay.
However, this is not this simple to implement: how can a bus administrator be
synchronised to an external signal? In addition, the performance figure is not
favourable for both sides, the MVB as well as the power drive: The MVB
bandwidth for general tasks suffers from the high amount of bandwidth required
for the control loops; the control loops suffer from the general traffic.
We recommend not to make use of an other base period as 1.000ms.

MD protocols: transport layer packets


In the IEC61375 document 2 “Real Time Protocols”, paragraph 2.3.6.5, the
transport layer packets are defined. In various packet types, the “control field (cl)”
is used. The definition is: “(cl) shall distinguish a Call (1) from a Reply (0)
message”.
In real life, we have found implementations, that understand this bit differently:
• There is a well-proven implementation (now in the field for more than
10 years), which changes the bit during the course of a “Call” or “Re-
ply”; obviously the understanding is somehow mixed with the “Con-
sumer” versus “Producer” issue.
• Following the text in the standard, the mentioned bit should be con-
stant during the course of a “Call” or “Reply”, respectively. This is the
way, how some newer implementations are built.
As long as there are nodes of the same implementation on one MVB, they will
work.
When connecting nodes with two different understandings, they will fail to com-
municate.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 104/109 d000656-003145 duagon

Device address allocation


In principle, the whole address space for device addresses should be open for all
nodes, i.e. the range from 0 to 4095.
In practice, it is useful to allocate addresses first for the complex Class 2+ nodes:
• The involved bus administrators wait a certain time after power up before they
start operation; the waiting time is derived from the device address: low
device addresses mean less waiting time: allocate the BAs at the lowest
addresses.
• There is a restriction for the RTP implementations, that the “station address”
has a format of “INTEGER8”; which limits the addresses to below 256.
After this, all Class 1 nodes may be allocated at random addresses.

Wire redundancy and two Manchester Decoders


It was mentioned in the previous text, that an MVB-controller implemented to the
IEC61375 standard includes just one Manschester decoder (...and newer imple-
mentations include two of them).
This seems to be a contradiction to the figure shown in Clause 3.1.2. “Structure of
this clause”: There are two decoders shown.
Both statements are “a little bit wrong”: The IEC standard defines one decoder for
reception of data from the “trusted line” and another decoder which monitors the
“observed line” for valid Manchester frames. However, this second decoder is not
able to receive data and can therefore not be used for a dynamic switch of the
trusted and observed line; i.e. it has a reduced functionality. From this point, may
be it would be ok to say “the IEC standard defines 1.5 decoders...”.

EMD insensitivity: Comments to IEC61375


• In paragraph 3.2.5.10.2, the IEC standard asks for the receiver chips
to have a “hysteresis of at least 50mV, but no more than 0,25V”. This
allows a square signal of e.g. 51mV to be correctly recognised.
• In paragraph 3.2.5.10.4, “the receiver shall not detect a valid frame
when the test signal amplitude is less than 0.1V”. On top of this, it is
possible to “increase this threshold in certain applications”.
How to understand this discrepancy? Obviously, the second phrase had the inten-
tion to blank out frame signals being too low; these may occur for example with a
wire fault on the far side. By this way, the paragraph about insensitivity helps to
keep the “simple failure model” working (see page 59); unfortunately, it does not
work perfect.
Personal note from the author
From more practical considerations, the EMD receiver will be one of the RS485 re-
ceivers readily available on the semiconductor market. These devices fulfill the
first paragraph, but not the second. To implement a variable threshold, a specific
solution for the MVB would have to be created; this does not make sense from the
economical point of view.
Assumed, the “simple failure model” is given up (as I propose also for other rea-
sons), then there is no justification for the “variable insensitivity” paragraph. In-
sensitivity should be the implicit 50mV from the RS485- receivers, nothing more.
Whether a frame is recognised to be OK or not, this is decided by other means
(MVB decoder: Manchester coding, CRC calulation etc.), but not by signal level.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 105/109

Appendix A: Error counters for duagon products


One way to find cable faults is by using error counters. In contrast to the proposal
using DSRs only, the error counters will get fine-grained information about com-
munication status between the MVB nodes.
• global error counters will give an overview about the communication
status
• detailed error counters could be made available for all process data
and DSRs used by an application

Line reception status


Duagon's MVB controller provides for each process data sink port (and each de-
vice status port) status information about reception, i.e.:

Status Information Meaning


SINK_A Slave frame was received on MVB Line_A.
SINK_B Slave frame was received on MVB Line_B.

The following information can be get by reading a process data sink port (resp. a
device status port) from the MVB controller:

SINK_A SINK_B Meaning


0 0 No data received from MVB since last read.
0 1 Data received on MVB line B.
1 0 Data received on MVB line A.
1 1 Data received on both MVB lines.

Time reception status


Besides the above described line reception status, duagon's MVB controller pro-
vides for each port (process data as well as DSR, i.e. device status) an "age"-infor-
mation (see "sink time supervision").
Note: The maximum allowed "age" for a port is derived from the BA repetition
rate (a typical application uses 32ms for "fast" and 512ms for "slow" process data).

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 106/109 d000656-003145 duagon

Definition of error counters


The figure on next page shows the algorithm for handling of several error coun-
ters on a node. This algorithm should only applied to process data (sink) ports and
DSRs, which are used by the MVB application.

Error Counter Meaning


General error Nothing has been received at all.
Note: If the check routine for this error counter was
applied to ports, which are used by the MVB applica-
tion, then this error counter indicates a real error on
MVB, e.g. node missing, BA inactive, MVB dead.
Otherwise this error counter will increment and indi-
cates a read access to not used ports.
Typically process data ports are known to an appli-
cation software, the list of nodes on a MVB network
rather not. From this point of view, this error counter
is more suitable for process data ports.
Note: The check routine for this error counter will
indicate each missing reception. An application soft-
ware should use a similar check routine for the max.
accepted "age", e.g. age≤(2*BA_repetition_rate).
Number of try Nothing has been received since last read access.
Note: This error counter does NOT indicate a real
error on MVB. It just indicates, that the application
software is reading a port faster than BA repetition
rate.
Error line B Slave frame was received on MVB line A,
but not on MVB line B.
Error line A Slave frame was received on MVB line B,
but not on MVB line A.
Note: These error counters indicates a real error on
MVB, e.g. cable fault, hardware fault within node.
These error counters are applicable for process data
as well as DSR.

Note: The link layer software should be responsible for handling these error
counters.

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 107/109

Link layer algorithm for handling several error counters on a node:

Read Port

age >
yes increment counter
BA repetition
"General error"
rate

no

SINK_A=0 yes increment counter


SINK_B=0 "Number of try"

no

SINK_A=1 yes increment counter


SINK_B=0 "Error line B"

no

SINK_A=0 yes increment counter


SINK_B=1 "Error line A"

no

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


Page 108/109 d000656-003145 duagon

Index
0V.term.....................................77 Introduction to........................76
5V.term.....................................77 Noise Rejection.......................74
Event arbitration........................31
A
Event phase...............................27
A.data.N..............................77, 80
A.data.P...............................77, 80 F
A.term.......................................80 F-Code......................................25
ANTIVALENT2............................15 Failure Model............................59
Attenuation................................84 Freshness...................................15
Availability.................................40
G
B Galvanic insulation....................54
B.data.N..............................77, 80 Gateways...................................21
B.data.P...............................77, 80 Geographical addressing...........46
B.term.......................................80 Ground potential differences......55
Back bone..................................51
H
Basic Period...............................27
Hood.........................................85
Bus Administrator...........................
How to..........................................
Bus configuration....................13
Deal with missing frames........94
DSR behaviour........................69
Find cable faults......................72
Mastership Transfer.................32
Find Cable faults by DSR´s......67
PD Broadcast..........................12
Put a new node in operation. . .36
Turn.......................................32
Bus Broadcasting........................12 I
Bus repeater...........................50p. Impedance.................................89
Insensitivity..............................104
C
Insulation...................................54
Cable..................................78, 82
Integrity.....................................41
Attenuation.............................83
Characteristic Impedance........83 L
Diagnostic...........................64p. LAT.........................................64p.
Length....................................49 LAT "Line A Trusted"...................62
Structure.................................82 Life Sign....................................16
Technical Data........................83 Line Switchover..........................61
Call...........................................18 Line_A,B....................................58
Capacitive Mismatch..................91
M
Check_Variable..........................15
M3 thread..................................85
Classes......................................33
Macro period.............................32
Client- Server.............................18
Master frame.......................12, 25
D Message Transport Protocol........20
Data Consistency.................14, 23 Messages.....................................9
DC/DC- Converter.....................79 MVBC01........................................
Device housing..........................55 End Delimiter..........................93
Device Status Report..................61 Line Redundancy.....................61
Device Status Request................62 Noise Rejection.................74, 93
DSR.....................................67, 69 Traffic store.............................23
E N
EMD.............................................. Network Topology......................49
Bus Length..............................74
O
Comparison to ESD.................74
Open End..................................90
Introduction to........................79
Opto Couplers...........................79
End Node..................................74
Error Counters...........................64 P
ESD............................................... Periodic phase...........................27
Bus Length..............................74 Periodic Polling..........................30
Comparison to EMD................74 Potential equalisation line..........82
End Delimiter..........................94 Process Data Port.......................11

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com


duagon d000656-003145 Page 109/109

Process Variables.......................10 Sub-D Connector.......................85


Supervisory phase......................27
R
Switchover.................................61
Redundancy...................................
Applying redundancy..............42 T
Bus Administrator....................32 TDR...........................................92
Bus nodes...............................45 TDR “Time Domain Reflectometers”
Devices...................................49 ..............................................88
Wire.......................................50 Terminator...........................74, 80
Wire redundancy.....................57 Timing Structure.........................25
Reflections........................88p., 92 Traffic Store.........................10, 22
Reply.........................................18 Transformer...............................79
Resistor......................................77 Transmission Line.......................89
RLD........................................64p. Transport Layer.......................19p.
RLD "Redundant Line Disturbed". 62 Twisted Pair............................82p.
RS485........................................70 Two page protocol.....................23
TxE signal............................77, 80
S
Safety..................................40, 44 U
Session Layer.............................19 UNC4-40...................................85
Shield........................................55
V
Shield continuity.........................85
Variables.......................................
Short Circuit.........................70, 90
Heart beat..............................16
Single point of failure...........43, 47
Invalid....................................15
SINK_A......................................65
SINK_B......................................65 W
Slave frame.........................12, 25 Wiring.......................................46
Star coupler...............................51 WTB Wire Train Bus......................6
State Variables.............................8

© duagon GmbH • Badenerstr. 21 • CH-8953 Dietikon • www.duagon.com

S-ar putea să vă placă și