Documente Academic
Documente Profesional
Documente Cultură
Introduction
Purpose and scope
Background
S-RBI Overview
Criticality:
Probability:
Consequence:
Remnant Life Calculation:
Confidence Rating:
Maximum Inspection Interval:
Inspection Interval Factor
Applicability of S-RBI
‘Negligible’
‘Extreme’
House Rules Framework
Help Available – Contacts & Documents
Personnel
Documents
Appendix I
RBI Expert Group Framework
Appendix II
RBI Expert Group House Rules – Check List
Appendix III
Examples of existing ‘House Rules’ (N.B. Some guidance is embedded
within DBRA).
a). Central
b). NSP
Rev 0; 130902
Expro RBI Expert Group Handbook
Introduction
Background
S-RBI Overview
This section is intended to provide a brief overview for personnel not fully
familiar with the S-RBI process, and as a refresher for those who have not
participated in Expert Group (EG) sessions for some time.
Criticality Matrix
High Medium High Extreme Extreme Confidence Rating
Medium Low Medium High Extreme Conf in degradation forecast
Low Negligible Low Medium High (S-RBI section 5.5.1)
Negligible Negligible Negligible Low Medium Low Medium High
Negligible Low Medium High
Consequence Assessment
(S-RBI Questionnaire, App. III)
Probability Assessment
(S-RBI Questionnaire, App. IV)
e.g.
120
months X 0.6
= 72 months
Figure 1
For each item to be assessed, the following factors are considered by the
Expert Group;
Criticality: An output of Probability & Consequence (see Figure 1)
Rev 0; 130902
Expro RBI Expert Group Handbook
probability) and 4 (Negligible probability), and the lowest of all the scores is
used to plot the ‘Probability’ axis in the criticality matrix.
N.B. Local variations exist to this questionnaire (onshore/ offshore specific
considerations).
The questionnaire versions and all the responses are stored in the RBI
software, which automatically plots criticality from the probability &
consequence inputs.
Remnant Life Calculation: This is the best estimate of remaining life for the
item (this may vary between different components within the item), and can be
based on the design corrosion allowance or the Minimum Allowable Wall
Thickness according to a suitable FFP calculation.
It is good practice to also apply a ‘retirement delay’ – the amount of time that
would be needed to affect a repair or procure a replacement item is
subtracted from the Remnant Life calculation.
The Remnant Life figure used has a large influence on the final output
‘maximum inspection interval’.
Confidence Rating: This is the confidence that the team has in the
degradation forecast (remnant life), and reflects the volume/ quality of
inspection data, or the confidence in the corrosivity of the fluid in relation to
the materials. This is a subjective judgement, although guidance is given in
the S-RBI manual.
Inspection Interval Factor: This is a look up table (see Figure 1) which works
by plotting the criticality against the confidence rating, to give a factor between
0.2 and 0.8. This leads to assigning inspection intervals that are less than the
remnant life of the item.
Rev 0; 130902
Expro RBI Expert Group Handbook
Applicability of S-RBI
The S-RBI Methodology works most effectively where the criticality has been
assessed as ‘Low’, ‘Medium’ or ‘High’. Outwith this region a decision must be
reached on how the item will be managed, e.g.
‘Negligible’ The Expert Group may conclude that no physical
inspection is required, but that the item should have a desk-based review at a
set interval in order to consider whether any circumstance has changed that
would change the criticality.
‘Extreme’ In this case it is both urgent and important that the
criticality is reduced.
Inspection management will not achieve this and the situation needs to be
managed outwith the S-RBI process.
Currently NSP intend to use the ‘RRM’ guidelines for items falling into this
criticality, as RRM gives a more comprehensive probability and consequence
assessment.
RRM is the updated and enhanced version of S-RBI, which now incorporates
S-RCM and S-IPF. The consequence assessment is common to the three
processes. At the time of writing (September 2002), Expro have NOT
adopted this version, and all RBI assessments should be done according to
the original S-RBI (document 97-30007).
Rev 0; 130902
Expro RBI Expert Group Handbook
Personnel
There are a number of people across the asset groups who have experience
in carrying out the RBI process, primarily the Asset Integrity Team Leaders.
Support is also available from the E&M support group from:
DBRA and ACET application support is available from OIS plc (01224
238000).
Documents
All the following documents are available electronically;
• S-RBI Manual, Report OP 97-30007, Guidelines for Risk Based
Inspection (available via Livelink)
• Code of Practice, Periodic Examination and Testing of Equipment
(Standards One Stop Shop)
• NDT Manual (available via Shell Wide Web link to KSLA server)
• Degradation Library (available via LiveLink)
• NII Manual (available via LiveLink)
Rev 0; 130902
Expro RBI Expert Group Handbook
Appendix I
RBI Expert Group Framework
Rev 0; 130902
Expro RBI Expert Group Handbook
Agree the quorum and whether same personnel are required Section 2 (P7)
at each session, or whether back to backs are acceptable. Identify Safety/ Production Chemistry/ Maintenance etc.
Materials/ corrosion Engineer contacts which may be required occasionally (name, phone
Minimum: Plant Inspector extension).
1.03 Composition of team (quorum)
Materials/ corrosion Engineer Process technologist
Plant Inspector Plant Operator Need to appoint team member who has reporting link to
Process technologist Maintenance Engineer Safety team (ref. 363/2001 B3.5).
Plant Operator Others as required
Obtain management commitment to releasing the required A plan or diary is helpful, along with a benefits/ deliverables
1.04 Commitment of personnel (None)
personnel for the Expert Group sessions. statement for management.
Agree what needs to be done prior to session;
Pre load database with inventory
Pre load database with inspection results
Preparation required prior to Expert Group Aim is to make the sessions more efficient and effective by
1.05 Pre load process/ ops information (None)
sessions taking 'donkey work' offline.
Drawings and reference documents which are required
during the session
Do initial assessment without whole Expert Group?
- Need to plan meetings in order to keep process 'live'
Important that Expert Group take OWNERSHIP of the
- Frequency will be determined by various factors such as:
1.06 Frequency of Expert Group meetings (None) process, and that meetings are held at a frequency which
volume of inspection activity; availability of personnel;
keeps process 'Live'.
management expectations of deliverables etc.
The first review of an item should include a lot of detail A rule of thumb is that the level of detail recorded should be
(Process/ Ops, location, geometry, accessibility etc etc.). sufficient that a completely 'changed out' Expert Group
2.02 Level of detail of assessments (None)
Further reviews should check this for accuracy and update as carrying out an update review on this item, understand clearly
appropriate. A full inspection history should be recorded. the thinking at the time of this review.
5.06 35 Input consequneces back into FCM 30 Associate individual ACET lines with a corrosion loop/circuit
5.07 40 Determine confidence rating
note 1
and populate spreadsheet 40 Associate ACET process streams to corrosion loops/circuits
5.08 45 Input confidence rating back into FCM's
5.09 50 Generate "criticality" by spreadsheet
5.10 55 Input "criticality" back into FCM's
5.11 60 Generate "Interval Factor" by spreadsheet
5.12 70 Transfer all spreadsheet data fields into ACET user defined fields
Determine "remnant life" note 2 by either a) empirical based on inspection
5.13 80 data and CA
note 3
, or b) Theorectical (assumed) CA note 3 via Corrosion 50 This step to coordinate with S-RBI step 80
Engineers and S-RBI giudelines -see attached sheet
Determine the next inspection due date, IF * RL in ACET, - note no HC
5.14 90
system can be greater than 144 months.
5.15 Note 1 Confidence rating as per S-RBI manual section 5.5.1
Remanent life calculations as per S-RBI manual section 5.4.1.1
5.16 note 2
"Calculating Remnant life - Piping".
CA (Corrosion Allowance) is the maximum allowable loss of material to
5.17 note 3
MAWT, NOT the design CA
Appendix II
RBI Expert Group House Rules – Pro Forma
Rev 0; 130902
Expro RBI Expert Group Handbook
1.2 Deliverables
Composition of team
1.3
(quorum)
2.0 Methodology
Maximum permissible
2.1
inspection interval (default)
Level of detail of
2.2
assessments
Confidence Rating
2.3
interpretation
Standards, references,
2.5 procedures etc. to be used;
applicable legislation etc.
Recording of group
3.4 decisions (software & who/
how during session)
Appendix III
Examples of existing ‘House Rules’ (N.B. Some guidance is embedded within
DBRA).
a). Central
b). NSP
Rev 0; 130902
Expro RBI Expert Group Handbook
DBRA
Terms of Reference for “S-RBI Team”
Inspection Mission
“To safeguard the technical integrity of all facilities in such a manner as to assist Asset Owners to
maximise returns and minimise total costs over the life cycle of the company assets” ref. 1
Inspection Vision
Where ever practical Non-Intrusive Inspection techniques (NII) will be adopted in preference to an
intrusive man entry. This approach reduces the risk of unnecessary exposure of personnel and plant to
shutdown conditions, purging and cleaning operations (especially where TENORM may be present).
Appendix IIIa
Expro RBI Expert Group Handbook
Confidence levels
Inspection interval suggested by DBRA tool is considered to be the maximum interval to the next
Thorough inspection. NII or intermediate inspections can be set at shorter intervals and are included to
support the Thorough inspection interval. The final inspection interval will be determined from the “S-
RBI Team” discussions, in principal it should not exceed the DBRA maximum inspection interval
suggestion. This “S-RBI Team” decision of the maximum inspection interval will be accompanied with
and Inspection Reference Plan (Level 3 plan)
Usage
Launcher /receiver usage.
Inspection types 4
• Thorough: A thorough and comprehensive examination of the items and associated safety
equipment. In specific cases this may require an intrusive man entry inspection but wherever
possible NII should be considered. In instances where the S-RBI assessment have identified
item criticality as “Negligible” a review will be used as the Thorough inspection.
Note: The Thorough inspection date is the latest date that the item can be kept in service
without the use of a deferment notice. All items will have a Thorough date imposed.
Appendix IIIa
Expro RBI Expert Group Handbook
Inventory
This is the operational inventory size including all pipework up to the first isolation valve
Deliverables
• SAP- PMR change request required to reflect new inspection reference plan 3.
• CBU Verification and Examination Scheme - Amendment Notice required, for Safety Critical
Elements only.
Inspection Scopes
An inspection reference plan to be devised from the “S-RBI Team”, using a combination of the four main
inspection types, detailing where, when and which inspection procedure should be employed. This will
form the level 3 plan.
References
Appendix IIIa
UEGP/52 SL Expro RBI Expert Group Handbook
The purpose of this document is to provide the Expert Groups (EG’s) and other DBRA users with
background information to record/highlight the assumptions/models/procedures that have been used by
the respective plants in carrying out risk based assessments with the DBRA system. This will also
provide a reference for future users to develop a clearer understanding of historical decisions and to
provide relevant background information to facilitate their own decision-making processes.
These notes are intended as guidelines to provide transparency in decision-making but it is recognised
that other experiences may prove more effective. It is therefore important these are captured within this
document via the custodian Stefan Lewandowski UEGP/52. To this end all Expert Group members are
urged to highlight all learning points so that the guidelines can reflect the most up to date practices.
Originally the procedures were based on St. Fergus and Mossmorran experience. However, in the
interim the DBRA system has been introduced at Bacton and the procedures have been updated to
reflect Bacton experience.
For St. Fergus & FNGL, the first (base line) inspections, usually carried out within ~ 4 years of
commissioning, were excluded from consideration as it was felt that they would not provide a
representative condition statement after such a short operational period. Therefore tags with only a
baseline inspection were given a low confidence rating unless there were compatible vessels with a
more extensive history, which could be used to increase confidence in the condition of the tag, in
question. Refer 3.2 below – “Stratification”.
For Bacton, the majority of tags have been subjected to multiple (intrusive) inspections and therefore a
“high” confidence in the inspection history could be assumed with/without consideration on early
inspections.
St. Fergus & FNGL have developed inspection strategies based on wall thickness (WT) checks, key
points and weld Non Destructive Testing (NDT) whereas Bacton has little such data, having
concentrated efforts on intrusive inspection. However, in future a common strategy between all three
plants will be adopted combining intrusive and non-intrusive inspection techniques.
It is planned that inspection reports will be copied into DBRA by the plant inspectors as a routine. Re
assessment will be performed by the EG . However, findings from interim inspections, such as
“External Visual Inspections” (EVI’s), will be reported by exception (20/3/00).
To determine the level of confidence associated with internal visual/Centest/IRIS inspections of tubes
decide if the number of tubes inspected are </> the statistical model requirements. If > apply a high
confidence factor. If < apply a medium confidence factor. Medium rather than low in order to take
credit for the inspection. Low should only be used where there has been no inspection carried out.
24/6/02 For shell heat exchanger tubes, at all plants, CA is based on tube design thickness based on
the assumption of corrosion to perforation. Several reasons for this approach; TEMA makes no
allowance for “CA” and determination of a CA proved too contentious. On the positive side, only
isolated tubes have exhibited corrosion pitting; to date no corrosion has been found throughout a tube
bundle. Therefore it is highly likely that should corrosion perforation occur it would be due to an
isolated case(s).
Appendix IIIb
UEGP/52 SL Expro RBI Expert Group Handbook
In the case of fin fan (air cooled) tubes where perforations would lead to release to atmosphere this is
considered to be unacceptable. Therefore for the purpose of determining IDD’s, a corrosion allowance
of 25% wall loss will be adopted.
E 1550 – T corrosion degradation to be used as basis for representative corrosion rates for all Bacton
Streams as follows;
On shell side (propane) loss of 0.5mm reported = 0.02 mm/year.
On tube side (methane) 15% wt loss = 0.03 mm/year.
Following also applicable to SS vessels. DBRA cannot provide rate related methods for addressing
Chloride pitting which needs to be considered predominantly for external corrosion. Therefore the
following guidance should be applied;
Austenitic Stainless Steel
Operating Temp (continuous) = /<0 oC – Risk of pitting considered negligible. Coincide coating
checks with external UT. Recommended window for Coating remedial work 4 Years.
Infrequent excursions 0’C >T<50‘C, - Chloride concentration may increase due to evaporation of water
with consequent increased risk of chloride pitting. Classify risk as low. Acceptable coating life
extension 8yrs between inspections. Recommended window for remedial work 2 years.
Continuous 0’C >T<50‘C, - Chloride concentration may increase due to evaporation of water with
consequent increased risk of chloride pitting. Classify risk as low. Acceptable coating life extension
8yrs between inspections. Mandatory remedial work within 2 years.
Operation > 60oC – Risk of pitting considered to be high Acceptable coating life extension between
inspections 4 years, no allowance for stratification. Coating defects require mandatory immediate
remedial action.
22Cr Duplex
25Cr Duplex
Inspection Due Dates (IDD’s) should be determined from consideration of the material grade, operating
temperature, coating type and maintenance history and inspection history.
3.2 Shells/Headers
Appendix IIIb
UEGP/52 SL Expro RBI Expert Group Handbook
At SF & FNGL, with criticalities 1 & 2, confidence factors were restricted to “Medium” in accordance
with S-RBI Guidelines. However, at Bacton the EG considered that Confidence should not be restricted
by the criticality and should be at the discretion/consensus of the EG.
Shell/ header inspection intervals may be different in view of criticality and condition. However, to
facilitate scheduling, the header(s) and shell will be inspected at the same interval.
The process of stratification has been used to boost the confidence factor by taking credit for
inspections carried out on similar vessels. To date stratification has been restricted to reinforce
Confidence Factor by cross-referencing to compatible tags and their histories.
These have been established via the Expert Groups. In the case of heat exchangers, at St Fergus and
FNGL, effort has been concentrated on the shell sides and it has been assumed, for the sake of
expediency, that the criticalities of the headers and tube sides are the same. This may not always be the
case as was proven by Bacton and the criticalities of SF/MM tubes will be re-assessed accordingly.
For Bacton, the RBA EG has carried out separate assessments for tubes/shell/headers. All tags were re-
assessed as analysis of initial work scopes highlighted discrepancies in the original Consequence factor.
Consequence Assessment;
In the course of this exercise a discrepancy between IPF and RBA consequence “Population Hazard”.
The Bacton EG decided to give credit for the control systems in the plant in contrast to the IPF model,
which assumes ignition. The anomaly between the respective models has been highlighted for
reconciliation.
For inventory determination the following model was applied; where specific inventories could be
determined, these were input. For small inventories estimated < 1 tonne, a minimum of 1 tonne was
specified. For inventories estimated > 5 tonnes, a value of 6 tonnes was input with a clarification note
that the inventory was > 5 tonnes.
At St. Fergus and FNGL, vessel inventories were assumed not ESDV inventories =>
credit taken for the isolation systems. At Bacton. inventories were estimated to the
nearest isolation.
Probability Assessment;
The dominant degradation mechanisms for all plants are internal and external corrosion. For
determination of external corrosion probability the following model was used; If the coating
system had been refurbished and there was no evidence of coating breakdown it was assumed
that external corrosion would only occur under upset conditions i.e. when the coating system
deteriorated => a weighting of “3”. Where there was no evidence that the coating had been
refurbished and was breaking down => a weighting of “2”.
20/5/02. It was recognized by the SF RBA EG that, with the predominance of corrosion under
insulation a more detailed analyses of CUI probability should be adopted;
Appendix IIIb
UEGP/52 SL Expro RBI Expert Group Handbook
For fin fanned tubes in carbon steel category 2 assumed – susceptible under normal operating
conditions.
Thermal cycling probability questionnaire – Need to clarify whether the questionnaire refers to
the temperature swing range or absolute temperatures. SF EG agreed to adopt temperature swing
range.
5.0 Queries
It has been agreed that outstanding queries will be given a six-month period for close out from the time
that they are raised. It is recognised that query management should form a key performance indicator
and that there needs to be a dynamic policing and notification system in operation so that the
responsible parties are kept informed which queries need to be closed out as a priority.
In the case of Bacton, three key dates were established 30/11/99, 31/12/99 & 31/3/00. However, in
view of the number of queries raised - ~ 1/tag – it is recognised that it is unlikely that these dates will
be achieved and therefore it is recommended that the above six month deadline should also be the KPI
for close out of all queries raised between Sept – Dec ’99.
Experience has shown that data quality checks must be regarded as a routine procedure of continuous
improvement. In the case SF & FNGL RBA EG it has been recognised that some of the data is
questionable despite best efforts. Therefore it has been agreed that the RBA EG’s will meet quarterly
and as part of the review procedure will re-check the data of at least 25 tags. In the case of Bacton who
are in the process of implementing the RBA DBRA system, data quality checks will be an integral
procedure of the assessment process. On completion of the first pass the level of satisfaction with data
quality will be assessed to determine subsequent level of checking.
It is recommended that the respective EG’s when updating RBA’s with latest inspection histories
routinely review the key edit/design/process/inspection history menus.
Appendix IIIb
UEGP/52 SL Expro RBI Expert Group Handbook
The Bacton EG established the following procedure for base date selection – Where there is evidence
from an inspection history of commencement of corrosion select the day after the previous inspection
date as the base date. Where the inspection history shows no evidence of corrosion, use the date of the
last inspection as the base date.
At Bacton the following procedure was adopted where corrosion allowance (CA) could not be
determined from the design data; where ultrasonic WT data was available, a CA was determined from
the minimum recorded wt less manufacturing tolerance less design thickness. Where there was no CA
from the data base the practice was to assume a minimum of 1.6 mm and raise a query to confirm
CA/Minimum Allowable Wall Thickness followed by re – assessment by the EG.
At SF/FNGL , the EG assumed a minimum of 1 mm CA on the basis that this is the minimum CA that
is applied on these plants.
The Bacton EG discovered that the historical inspection reports tended to record corrosion in either
quantitative or descriptive terms. In the latter case this was usually related to “slight/rough” degrees of
corrosion and the procedure was agreed by which this was defined 0.25-mm wt loss. However, in the
Criticality-Probability determination “slight/rough” degrees are considered as category 3 weightings.
The above is applicable for internal corrosion. However, in the case of external corrosion a default of
0.5mm has been agreed (SL 18/6/02)
In certain cases such as the Bacton desalination units no degradation/failure mechanisms could be
anticipated by the EG. However, where nil inspection was not considered to be an option and therefore
in order to determine a minimum inspection work scope, a theoretical pitting corrosion assumed.
Whereas for unit shell/headers external corrosion is related to fabric condition, for tubes this is
obviously not the case. Although the same descriptions “internal/external” are retained within DBRA
the different interpretation should be noted.
Bacton EG gave consideration to the potential threat(s) on the tube side - defined as “internal” - and
shell side – defined as external corrosion. The same procedure will be applied to SF & FNGL Tubes,
which remain outstanding.
Inspection scopes specify use of Boroscope/IRIS/CENTEST. The inspection scopes do not specify
whether they should be used individually or in combination. This is at the discretion of the inspector
and dependent on the circumstances.
At Bacton both internal and external corrosion were considered at the same time (At SF/MM external
corrosion review is outstanding). However, the DBRA system was designed for internal corrosion
management and as a result it was difficult to clearly demonstrate both internal and external corrosion
on the existing “Criticality Rating and Inspection Frequency” (CR & IF) menu. Therefore, when
external corrosion was the dominant mechanism a clarification note was included in the “Confidence”
note box.
Appendix IIIb
UEGP/52 SL Expro RBI Expert Group Handbook
As a result Nick Curley UESC/9 will expand the CR & IF menu to accommodate both internal and
external corrosion and provide a composite corrosion rate. The new menus will be made available in
March’00. It is planned to progressively update the menus in the course of EG meetings (27/3/00).
(20/3/00)
The external corrosion model was completed in March’00. For all the plants it is intended to
progressively apply the model. However, in the case of Bacton, where both internal/external RBA were
determined, the following default external substrate Inspection Intervals were applied;
Insulated
Uninsulated
• Housing – 15 years
• External – 10 years
This model will be maintained for tags that have fallen within the 2000 & 2001 inspection work scopes.
The DBRA model will be applied to all other tags where external corrosion has been detected.
However, where there is no inspection history and it is not possible to stratify, the above model could
also be used as a default.
The two primary internal corrosion mechanisms experienced in all the plants are described in DBRA
as pitting corrosion and general corrosion. The statistical models call for area scanning techniques
for pitting and key point checks for general corrosion. In order to ensure the likelihood of detecting
corrosion preference has been given to scanning techniques. As a result pitting corrosion has been
designated in preference to general corrosion
In Q’3 1999, the DBRA system was modified to record E G membership and the decisions made per
tag. While the EG decisions for Bacton have been fully recorded, the decisions with respect to the
1998-99 RBA’s of St Fergus and FNGL have not been recorded. The intention is to progressively
record the EG decisions as planned inspections are carried out. This will commence from Dec’99 when
the SF & FNGL EG’s commence inputting 1999 inspection histories and updating the current tag RBA
status. (21/3/00) With each re assessment, the EG decisions will be updated to provide a brief
explanation of the significant change(s).
Assume in general for a full coating system a default of 8 years based on full surface preparation.
Where surfaces have been mechanically prepared 5 years.
For single coated primer application assume as per above where operating temp < - 5oC. Where
operating temperature > -5oC assumes 5 years and 3 years respectively.
Appendix IIIb
UEGP/52 SL Expro RBI Expert Group Handbook
Where there is no inspection history to provide representative corrosion rates, the following default
corrosion rates will be applied;
External
Default CR’s adopted from Excorr RBA . Although this is for pipe work, the CR’s can also be
considered as appropriate for static equipment
The practical difficulties of convening a fully representative EG are recognized and as a consequence
the following EG reviews can be in several phases to ensure that conclusions are fully challenged. An
example is the procedure adopted in 2002 at Bacton;
Plant Inspector and UEGP/52 corrosion engineer carry out initial assessment and record EG decisions.
Advise UEGP/52 Senior Inspector of review.
Senior Inspector reviews and, if necessary challenges decision and/or calls for additional discipline
review.
Senior inspector records resolution.
Appendix IIIb