Sunteți pe pagina 1din 142

STATISTICAL REPORT

Project Name: REPAIR/REHABILITATIONOF SAN JUAN BEACH RESORT HOTEL


Project Location: BRGY. SAN JUAN, PALOMPON, LEYTE
Project Duration: Day 45
Under Contract by: ROY GERMAN ROQUE BUILDERS
STATEMENT OF WORK ACCOMPLISHED
PROGRESS BILLING No. 01
PROG
Item Relative Wt. ACCOMPLISHMENT (in %)
Pay Item as per approved Contract/BOQ Amount
No. %
Previous

1.0 MOBILIZATION/DEMOBILIZATIION 17,500.00 1.83% 0.00%


2.A DEMOLITION & DISPOSAL OF DEBRIS 3,142.00 0.33% 0.00%
2.0 STRUCTURAL WORKS 238,550.86 24.89% 0.00%
3.0 STRUCTURAL WORKS 97,385.23 10.16% 0.00%
4.0 MASONRY WORKS & DRY WALL 136,620.56 14.25% 0.00%
5.0 CEILING WORKS: ( interior & exterior ) 33,589.67 3.50% 0.00%
6.0 DOORS: 17,707.71 1.85% 0.00%
7.0 WINDOWS 6,418.00 0.67% 0.00%
8.0 CARPENTRY WORKS: CABINETRY (kitchen) 36,592.05 3.82% 0.00%
9.0 TILE WORKS 28,884.16 3.01% 0.00%
10.0 SANITARY/PLUMBING WORKS: Water lines, Sewer lines & fixtures 37,720.96 3.93% 0.00%
11.0 ELECTRICAL WORKS: 39,182.78 4.09% 0.00%
12.0 PAINTING WORKS 73,586.98 7.68% 0.00%
13.0 MECHANICAL WORKS - 0.00% 0.00%
14.0 ELECTRONICS AND COMMUNICATION - 0.00% 0.00%
15.0 LANDSCAPING AND SIGNAGE WORKS - 0.00% 0.00%
16.0 II. INDIRECT COST 191,720.24 20.00% 0.00%

TOTAL CONTRACT COST 958,601.18 100.00% 0.00%

Prepared by: Checked by:


ROY G. ROQUE FAUSTINO G. ROQUE Jr.
Contractor Supervising Engineer

Approved by:
Time Elapsed: %
Date:

PROGRESS ACCOMPLISHMENT
ACCOMPLISHMENT (in %) ACCOMPLISHMENT (in Peso)
To Date To Date
This Period Previous This Period
Cummulative Cummulative

0.00% 0.00% - - -
0.00% 0.00% - - -
0.00% 0.00% - - -
0.00% 0.00% - - -
0.00% 0.00% - - -
0.00% 0.00% - - -
0.00% 0.00% - - -
0.00% 0.00% - - -
0.00% 0.00% - - -
0.00% 0.00% - - -
0.00% 0.00% - - -
0.00% 0.00% - - -
0.00% 0.00% - - -
0.00% 0.00% - - -
0.00% 0.00% - - -
0.00% 0.00% - - -
0.00% 0.00% - - -

0.00% 0.00% - - -

Noted by:
SAN JUAN HOTEL AND BEACH RESORT
Owner/Owners Representative

SAN JUAN HOTEL AND BEACH RESORT


Owner
PROJECT : REPAIR/REHABILITATIONOF SAN JUAN BEACH RESORT HOTEL
: BRGY. SAN JUAN, PALOMPON, LEYTE
CON
LOCATION
OWNER : SAN JUAN BEACH RESORT HOTEL
SUBJECT : CP-01 GENERAL CONSTRUCTION WORKS
CONTRACTOR ROY GERMAN ROQUE BUILDERS
WEEK 1
Relative Wt.
Item No. Description Amount
% Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8

1.0 MOBILIZATION/DEMOBILIZATIION 17,500.00 1.83% 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041
2.A DEMOLITION & DISPOSAL OF DEBRIS 3,142.00 0.33% 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05
2.0 STRUCTURAL WORKS 238,550.86 24.89% 0.01185 0.01185 0.01185 0.01185 0.01185 0.01185 0.01185 0.01185
3.0 STRUCTURAL WORKS 97,385.23 10.16%
4.0 MASONRY WORKS & DRY WALL 136,620.56 14.25% 0.00509 0.00509 0.00509 0.00509 0.00509 0.00509 0.00509 0.00509
5.0 CEILING WORKS: ( interior & exterior ) 33,589.67 3.50%
6.0 DOORS: 17,707.71 1.85%
7.0 WINDOWS 6,418.00 0.67%
8.0 CARPENTRY WORKS: CABINETRY (kitchen) 36,592.05 3.82%
9.0 TILE WORKS 28,884.16 3.01%
10.0 SANITARY/PLUMBING WORKS: Water lines, Sewer lines & fixtures 37,720.96 3.93%
11.0 ELECTRICAL WORKS: 39,182.78 4.09%
12.0 PAINTING WORKS 73,586.98 7.68%
13.0 MECHANICAL WORKS - 0.00%
14.0 ELECTRONICS AND COMMUNICATION - 0.00%
15.0 LANDSCAPING AND SIGNAGE WORKS - 0.00%
16.0 II. INDIRECT COST 191,720.24 20.00% 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444

19.6
17.49%
15.30%
13.12%
10.93%
8.75%
TOTAL CONSTRUCTION COST 958,601.18 100.00% 6.56%
4.37%
Daily Accomplishment 0.02
2.19% 0.02 0.02 0.02 0.02 0.02 0.02 0.02
0.00%
Cummulative Accomplishment 0.00% 2.19% 4.37% 6.56% 8.75% 10.93% 13.12% 15.30% 17.49%

Actual Accomplishment 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

% Slippage ( + or - ) -2.19% -4.37% -6.56% -8.75% -10.93% -13.12% -15.30% -17.49%

Calendar Days Day 45 CAL.DAYS 1ST. WEEK


Weekly Accomplishment 100% 15.30%
Weekly Cummulative Accomplishment 15.30%
Weekly Cash Flow 146,706.22
Weekly Cummulative Cash Flow 146,706.22

Prepared by: Checked by:


ROY GERMAN ROQUE BUILDERS ROY GERMAN ROQUE
CONTRACTOR Project Manager-Proprietor
CONSTRUCTION SCHEDULE & S-CURVE

WEEK 2 WEEK 3 WEEK 4 WEEK 5


Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day
Day 9
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36

0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041

7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05 7E-05

0.01185 0.01185 0.01185 0.01185 0.01185 0.01185 0.01185 0.01185 0.01185 0.01185 0.01185 0.01185 0.01185 87.59%
85.62%
83.65%
0.00484 0.00484 0.00484 0.00484 0.00484 0.00484 0.00484 0.00484 0.00484 0.00484 0.00484 0.00484 0.00484 0.00484 0.00484 0.00484 0.00484 0.00484 0.00484 0.00484 0.00484
80.86%
0.00509 0.00509 0.00509 0.00509 0.00509 0.00509 0.00509 0.00509 0.00509 0.00509 0.00509 0.00509 0.00509 0.00509 0.00509 0.00509 0.00509 0.00509 0.00509 0.00509 78.08%
75.29%
0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025
72.50%
69.71%
0.00088 0.00088 0.00088 0.00088 0.00088 0.00088 0.00088 0.00088 0.00088 0.00088 0.00088 0.00088 0.00088 0.00088 0.00088 0.00088 0.00088 0.00088 0.00088 0.00088 0.00088
66.93%
64.14% 0.00096
61.95%
59.76% 0.00545 0.00545 0.00545 0.00545 0.00545 0.00545 0.00545
57.57%
55.38% 0.0043
53.56%
51.74% 0.00562 0.00562 0.00562 0.00562 0.00562 0.00562 0.00562
49.91%
47.16% 0.00584
44.40%
41.64% 0.00366 0.00366 0.00366 0.00366 0.00366 0.00366 0.00366 0.00366 0.00366 0.00366 0.00366 0.00366
38.88%
36.12%
33.37%
30.61%
28.42%
26.24%
0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444
24.05%
21.86%
19.68%
17.49%
%

0.02 0.02 0.02 0.02 0.02 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.02

19.68% 21.86% 24.05% 26.24% 28.42% 30.61% 33.37% 36.12% 38.88% 41.64% 44.40% 47.16% 49.91% 51.74% 53.56% 55.38% 57.57% 59.76% 61.95% 64.14% 66.93% 69.71% 72.50% 75.29% 78.08% 80.86% 83.65% 85.62%

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

-19.68% -21.86% -24.05% -26.24% -28.42% -30.61% -33.37% -36.12% -38.88% -41.64%

2ND. WEEK 3RD. WEEK 4TH. WEEK 5TH. WEEK


15.30% 19.31% 14.23% 19.51%
30.61% 49.91% 64.14% 83.65%
146,706.22 185,070.53 136,364.98 187,035.27
293,412.44 478,482.97 614,847.95 801,883.22

Reviewed by: Noted by: Approved by:


FAUSTINO G. ROQUE Jr.
Site-Technical Officer Owner/Owners Representative
Contract Duration : 126 Calendar Days
Contract Starts : _________________
Contract Ends : ____________________

WEEK 6 WEEK 7
Day Day Day Day Day Day Day Day Day
37 38 39 40 41 42 43 44 45

99.14% 100.00%
97.43% 98.28%
0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041 0.00041
95.46%
93.49%
7E-05 7E-05 7E-05 91.52%7E-05 7E-05 7E-05 7E-05 7E-05 7E-05
89.55%
87.59%
85.62%
%

0.00096 0.00096 0.00096 0.00096 0.00096 0.00096

actual
0.0043 0.0043 0.0043 0.0043 0.0043 0.0043
planned
0.00584 0.00584 0.00584 0.00584 0.00584 0.00584

0.00366 0.00366 0.00366 0.00366 0.00366 0.00366 0.00366 0.00366 0.00366

0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444 0.00444

0.02 0.02 0.02 0.02 0.02 0.02 0.01 0.01 0.01

87.59% 89.55% 91.52% 93.49% 95.46% 97.43% 98.28% 99.14% ###

6TH. WEEK 7TH. WEEK


0.14 0.03
97.43% 100.00%
132,048.05 24,669.91
933,931.27 958,601.18

Owner
REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT H
ACCOMPLISHMENT REPORT DATA
PROJECT TITLE: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL CODE:
CITY/MUNICIPALITY: PALOMPON DATE:
BARANGAY: SAN JUAN BY:
BUILDING TYPE: Reinforced Concrete Structure AREA: 626.685 SQM.
SUBJECT: ACCOMPLISHMENT REPORT DATA SIZE: 24.70 x 11.50 m
OWNER: SAN JUAN BEACH RESORT HOTEL
Item UNIT Relative Wt
SCOPE OF WORKS (DESCRIPTION) QTY UNIT AMOUNT
No. RATE % Qty.

1.0 MOBILIZATION/DEMOBILIZATIION 1.00 LOT 17,500.00 17,500.00 1.83%


1.1 Mobilization/demobilization 1.0 lot 10,000.0 10,000.00 1.04% 0.00
1.2 Insurance, Permit and Lincenses 1.0 lot - - 0.00% 0.00
1.3 Temporary Faciities 1.0 lot 2,500.0 2,500.00 0.26% 0.00
1.4 Safety Requirements and Supervision ( PPE, Scafolding & Safety Device) 1.0 lot 5,000.0 5,000.00 0.52% 0.00
1.5 Testing of Materials 1.0 lot - - 0.00% 0.00
1.6 Hauling & Disposal of Waste Materials 1.0 lot - - 0.00% 0.00
1.7 Billboards 1.0 lot - - 0.00% 0.00
Total General Mobilization/Demobilization 17,500.00 1.83% 0.00

2.A DEMOLITION & DISPOSAL OF DEBRIS 1.00 lot 3,142.00 3,142.00 0.33%
b. Labor:
Total Labor Cost ( B ) 3,142.00 0.33% 0.00

2.0 STRUCTURAL WORKS 7.38 cu.m. 32,322.21 238,550.86 24.89%


a. Materials:
Cement 73.00 bag 260.00 18,980.00 1.98% 0.00
Sand 6.00 cu.m 1,550.00 9,300.00 0.97% 0.00
Gravel 10.00 cu.m 1,550.00 15,500.00 1.62% 0.00
10mm Def.bar (kgs) 508.00 kgs 145.00 73,660.00 7.68% 0.00
8mm Def. Bar (kgs) 173.00 kgs 125.00 21,625.00 2.26% 0.00
#16 GI wire (kgs) 18.00 kgs 70.00 1,260.00 0.13% 0.00
Coco Lumber (bd.ft.) 467.00 bd.ft. 15.00 7,005.00 0.73% 0.00
1/2" Ord.Plywood (sht) 20.00 sht 850.00 17,000.00 1.77% 0.00
Assorted CWN (kgs) 10.00 kgs 70.00 700.00 0.07% 0.00
Sahara water proofing - bag 40.00 - 0.00%
Total Material Cost ( 1 ) 165,030.00 17.22% 0.00
b. Labor:
Total Labor Cost ( B ) 61,281.24 6.39% 0.00
c. Tools and Equipents:
Total Tools & Equipments ( BB ) 11,439.62 1.19% 0.00
d. Delivey & Hauling:
Total Delivery Cost ( I ) 800.00 0.08% 0.00

3.0 STRUCTURAL WORKS 84.00 lm 1,159.35 97,385.23 10.16%


a ROOF & ROOF FRAMING WORKS:
a. Materials:
2.0mm x 2" x 4" C-Purlins ( pcs ) 4.00 pcs. 850.00 3,400.00 0.35% 0.00
2.0mm x 2" x 3" C-Purlins ( pcs ) 12.00 bd.ft. 750.00 9,000.00 0.94% 0.00
1/4" x 2" Flat Bar 3.00 kgs. 450.00 1,350.00 0.14% 0.00
12mm Plain Round Bar 3.00 pcs. 420.00 1,260.00 0.13% 0.00
10mm x 200 x 200mm Gusset plate - pcs. 350.00 - 0.00% 0.00
Welding Electrodes 2.00 pcs. 160.00 320.00 0.03% 0.00
0.40mm GI Roofing 40.00 pcs. 690.00 27,600.00 2.88% 0.00
GI Roof leader 5.00 pcs. 670.00 3,350.00 0.35% 0.00
GI Metal Fascia 5.00 pcs. 550.00 2,750.00 0.29% 0.00
GI Ridge Cap - pcs. 650.00 - 0.00% 0.00
GI Valley Gutter - pcs. 650.00 - 0.00% 0.00
End Wall Flashing 8.00 pcs. 650.00 5,200.00 0.54% 0.00
Fastener - Tex Screw 267.00 pcs. 2.50 667.50 0.07% 0.00
Silicon Sealant 4.00 pcs. 260.00 1,040.00 0.11% 0.00
Insulation Foam 1.00 pcs. 5,500.00 5,500.00 0.57% 0.00
Total Material Cost ( 1 ) 61,437.50 6.41% 0.00
b. Labor:
Total Labor Cost ( B ) 21,797.73 2.27% 0.00
c. Tools and Equipents:
Total Tools & Equipments ( BB ) 6,650.00 0.69% 0.00
d. Delivey & Hauling:
Total Delivery Cost ( I ) 7,500.00 0.78% 0.00

4.0 MASONRY WORKS & DRY WALL 319.76 sq.m. 427.26 136,620.56 14.25%
a. Materials:
4" CHB 1,207.00 pcs 15.00 18,105.00 1.89% 0.00
Cement 147.00 bag 260.00 38,220.00 3.99% 0.00
Sand 5.00 cu.m 1,550.00 7,750.00 0.81% 0.00
Fine Sand 7.00 cu.m 1,550.00 10,850.00 1.13% 0.00
10mm Def.bar (kgs) 273.00 kgs 41.43 11,310.00 1.18% 0.00
#16 GI wire (kgs) 6.00 kgs 70.00 420.00 0.04% 0.00
Sahara (bags) - bag 40.00 - 0.00% 0.00
4.5mm CFB - bot. 260.00 - 0.00% 0.00
M.F. 2"x3"x8ft. ( lm ) - roll 5,500.00 - 0.00% 0.00
Total Material Cost ( 1 ) 86,655.00 9.04%
b. Labor:
Total Labor Cost ( B ) 49,165.56 5.13% 0.00
d. Delivey & Hauling:
Total Delivery Cost ( I ) 800.00 0.08% 0.00

5.0 CEILING WORKS: ( interior & exterior ) 40.00 sq.m. 839.74 33,589.67 3.50%
a. Materials:
4.5mm CFB 14.00 shts. 450.00 6,300.00 0.66% 0.00
M.F. 2"x3"x5m ( pcs ) 37.00 pcs. 110.00 4,070.00 0.42% 0.00
C-carrying Channel ( pcs ) 10.00 pcs. 125.00 1,250.00 0.13% 0.00
1/8x1/2" b.rivet (pcs) 2.00 box 650.00 1,300.00 0.14% 0.00
Moulding ( lm ) 18.00 pcs. 261.00 4,698.00 0.49% 0.00
W-clip 105.00 pcs. 5.00 525.00 0.05% 0.00
10mm insulation foam 0.80 roll 5,500.00 4,400.00 0.46% 0.00
2"x2" Good Lumber (ceiling joist) - roll 40.00 - 0.00% 0.00
Assorted CWN - roll 70.00 - 0.00% 0.00
Total Materials ( 9 ) 22,543.00 2.35%
b. Labor:
Total Labor ( J ) 7,913.33 0.83% 0.00
c. Tools and Equipents:
Total Tools & Equipments ( BB ) 2,333.33 0.24% 0.00
d. Delivey & Hauling:
Total Delivery Cost ( VII ) 800.00 0.08% 0.00

6.0 DOORS: 3.00 sets 5,902.57 17,707.71 1.85%


a. Materials:
Solid Type door 1000 x 2100 - set 7,500.00 - 0.00% 0.00
900 x 2100 Solid type door 1.00 set 7,500.00 7,500.00 0.78% 0.00
800 x 2100 Solid type door - set 7,500.00 - 0.00% 0.00
700 x 2100 Solid type door - set 7,500.00 - 0.00% 0.00
700 x 2100 Flush type door 1.00 set 3,000.00 3,000.00 0.31% 0.00
600 x 2100 Flush type door 1.00 set 2,500.00 2,500.00 0.26% 0.00
1000 x 2100 Metal Door - set 3,500.00 - 0.00% 0.00
Total Materials ( 9 ) 13,000.00 1.36%
b. Labor:
Total Labor ( J ) 3,907.71 0.41% 0.00
d. Delivey & Hauling:
Total Delivery Cost ( VII ) 800.00 0.08% 0.00

7.0 WINDOWS 2.50 Unit 2,567.20 6,418.00 0.67%


a. Materials:
1200x1200 Jalousie type window 1.00 set 1,728.00 1,728.00 0.18% 0.00
1200x600 Jalousie type window 1.50 set 864.00 1,296.00 0.14% 0.00
600x600 Jalousie type window 1.50 set 432.00 648.00 0.07% 0.00
Total Materials ( 9 ) 3,672.00 0.38%
b. Labor:
Total Labor ( J ) 1,946.00 0.20% 0.00
d. Delivey & Hauling:
Total Delivery Cost ( VII ) 800.00 0.08% 0.00

8.0 CARPENTRY WORKS: CABINETRY (kitchen) 21.60 sqm 1,694.08 36,592.05 3.82%
a. Materials:
3/4" Marine Plywood 8.00 shts. 1,450.00 11,600.00 1.21% 0.00
Concealed Hinges 24.00 pcs. 90.00 2,160.00 0.23% 0.00
Drawer Slide 12.00 set 375.00 4,500.00 0.47% 0.00
Cabinet Handle 12.00 pcs. 180.00 2,160.00 0.23% 0.00
Cabinet Locked 12.00 pcs. 150.00 1,800.00 0.19% 0.00
Total Materials ( 9 ) 22,220.00 2.32%
b. Labor:
Total Labor ( J ) 12,089.70 1.26% 0.00
c. Tools and Equipents:
Total Tools & Equipments ( BB ) 1,482.35 0.15% 0.00
d. Delivey & Hauling:
Total Delivery Cost ( VII ) 800.00 0.08% 0.00

9.0 TILE WORKS 34.00 sq.m. 849.53 28,884.16 3.01%


a. Materials:
40 x 40 213.00 pcs. 75.00 15,975.00 1.67% 0.00
Tile Adhesive 6.80 bag 450.00 3,060.00 0.32% 0.00
Tile Grout 2.00 bag 160.00 320.00 0.03% 0.00
Tile Trim (edge) - pcs. 680.00 - 0.00% 0.00
Total Materials ( 9 ) 19,355.00 2.02%
b. Labor:
Total Labor ( J ) 8,729.16 0.91% 0.00
d. Delivey & Hauling:
Total Delivery Cost ( VII ) 800.00 0.08% 0.00

10.0 SANITARY/PLUMBING WORKS: Water lines, Sewer lines & fixtures - - - 37,720.96 3.93%
a. Materials:
Toilet and Bath 12.00 Unit - - 0.00% 0.00
Septic Tank 1.00 lot - - 0.00% 0.00
Grease Trap 1.00 lot - - 0.00% 0.00
Downspout 1.00 lot - - 0.00% 0.00
Catch Basin 1.00 lot - - 0.00% 0.00
Water Tank ( 1500L ) 1.00 lot 22,500.00 22,500.00 2.35% 0.00
Kitchen room 1.00 lot - - 0.00% 0.00
Storm Drainage lines 1.00 lot - - 0.00% 0.00
Water Line system 1.00 lot 5,300.00 5,300.00 0.55% 0.00
Total Materials ( 9 ) 27,800.00 2.90%
b. Labor:
Total Labor ( J ) 9,920.96 1.03% 0.00

11.0 ELECTRICAL WORKS: 1.00 lot 39,182.78 39,182.78 4.09%


a. Materials:
60 Amp.,220V, 2 Poles Main Circuit Breaker 1.00 pcs. 950.00 950.00 0.10% 0.00
30 Amp.,220V, 2 Poles Circuit Breaker (Power Outlet) 1.00 pcs. 550.00 550.00 0.06% 0.00
20 Amp.,220V, 2 Poles Circuit Breaker (Power Outlet) 1.00 pcs. 450.00 450.00 0.05% 0.00
15 Amp.,220V, 2 Poles Circuit Breaker (Lighting & Spare) 1.00 pcs. 450.00 450.00 0.05% 0.00
3/4"Ø PVC Conduit 5.00 pcs. 180.00 900.00 0.09% 0.00
1/2"Ø PVC Conduit 5.00 pcs. 150.00 750.00 0.08% 0.00
3/4"Ø Flexible Conduit - roll - - Err:508 0.00
1/2"Ø Flexible Conduit 1.00 roll 750.00 750.00 0.08% 0.00
1/2"Ø PVC Clip 1.00 box 50.00 50.00 0.01% 0.00
4" Pvc utility box 15.00 pcs. 75.00 1,125.00 0.12% 0.00
#4 Twisted Wire 10.00 mts 25.00 250.00 0.03% 0.00
#10 THHN Stranded Wire 1.00 box 6,450.00 6,450.00 0.67% 0.00
#12 THHN Stranded Wire 1.00 box 4,800.00 4,800.00 0.50% 0.00
#14 THHN Stranded Wire 1.00 box 3,750.00 3,750.00 0.39% 0.00
10-watts LED Bulb 1.00 set 1,250.00 1,250.00 0.13% 0.00
7-watts LED Bulb 1.00 set 950.00 950.00 0.10% 0.00
2-gang switches 2.00 set 550.00 1,100.00 0.11% 0.00
1-gang switches 1.00 set 350.00 350.00 0.04% 0.00
2-gang Convenience Outlet 5.00 set 550.00 2,750.00 0.29% 0.00
Electrical Tape 1.00 roll 30.00 30.00 0.00% 0.00
Emergency Lighting System 1.00 set 2,450.00 2,450.00 0.26% 0.00
Total Materials ( 9 ) 30,105.00 3.14%
b. Labor:
Total Labor ( J ) 8,277.78 0.86% 0.00
d. Delivey & Hauling:
Total Delivery Cost ( VII ) 800.00 0.08% 0.00

12.0 PAINTING WORKS 242.72 sq.m. 303.18 73,586.98 7.68%


a. Materials:
WALLING INTERIOR/EXTERIOR 181.60 sq.m.
Skimcoat 11.00 gal 520.00 5,720.00 0.60% 0.00
Acrytex Primer 9.00 gal 780.00 7,020.00 0.73% 0.00
Acrytex Cast 4.00 gal 550.00 2,200.00 0.23% 0.00
Acrytex Reducer 6.00 gal 450.00 2,700.00 0.28% 0.00
Body Filler 3.00 gal 525.00 1,575.00 0.16% 0.00
Acrytex Semi-gloss Top Coat 4.00 gal 820.00 3,280.00 0.34% 0.00
Semi gloss Latex ( interior walling ) 3.00 gal 680.00 2,040.00 0.21% 0.00
Assorted Paint Brush 2.00 pcs. 105.00 210.00 0.02% 0.00
Roller Brush 9" w/. Pan 2.00 pcs. 160.00 320.00 0.03% 0.00
Assorted Sand Paper 10.00 pcs. 25.00 250.00 0.03% 0.00

CEILING INTERIOR/EXTERIOR 40.00 sq.m.


Acrytex Primer 2.00 gal 780.00 1,560.00 0.16% 0.00
Acrytex Reducer 1.00 gal 450.00 450.00 0.05% 0.00
Flat Latex 2.00 gal 550.00 1,100.00 0.11% 0.00
Body Filler 1.00 gal 525.00 525.00 0.05% 0.00
Marine Epoxy 1.00 lit 250.00 250.00 0.03% 0.00
Joint Tape 2.00 roll 75.00 150.00 0.02% 0.00
QDE for Molding 1.00 gal 620.00 620.00 0.06% 0.00
Assorted Paint Brush 2.00 pcs. 105.00 210.00 0.02% 0.00
Roller Brush 9" w/. Pan 2.00 pcs. 160.00 320.00 0.03% 0.00
Assorted Sand Paper 10.00 pcs. 25.00 250.00 0.03% 0.00

AUTOMOTIVE/VARNISH PAINT ( Cabinets, Closets, Shelfs, Railings & Grills ) 21.12 sq.m.
Auto. Lacquer Primer Surfacer 2.00 gal 695.00 1,390.00 0.15% 0.00
Auto. Lacquer Spot Putty 2.00 gal 680.00 1,360.00 0.14% 0.00
Auto. Lacquer Thinner 2.00 gal 450.00 900.00 0.09% 0.00
Auto. Lacquer Top Coat Gloss 2.00 gal 880.00 1,760.00 0.18% 0.00
Auto. Lacquer Sanding Sealer 2.00 gal 620.00 1,240.00 0.13% 0.00
Auto. Lacquer Flo 2.00 gal 620.00 1,240.00 0.13% 0.00
Auto. Lacquer Dead Flat 2.00 gal 630.00 1,260.00 0.13% 0.00
Auto. Lacquer Clear Gloss 1.00 gal 680.00 680.00 0.07% 0.00
Wood Stain varnish 2.00 gal 650.00 1,300.00 0.14% 0.00
Epoxy Primer 2.00 gal 680.00 1,360.00 0.14% 0.00
Epoxy Enamel 2.00 gal 750.00 1,500.00 0.16% 0.00
Body Filler 2.00 gal 525.00 1,050.00 0.11% 0.00
Assorted Paint Brush 1.00 pcs. 105.00 105.00 0.01% 0.00
Baby Roller Brush 4" 1.00 pcs. 160.00 160.00 0.02% 0.00
Assorted Sand Paper 20.00 pcs. 25.00 500.00 0.05% 0.00

ROOFING PAINTING WORKS: ( Repainting works ) - sqm


Acrylic Paint - gal 860.00 - 0.00% 0.00
Acrylic Thinner - gal 450.00 - 0.00% 0.00
Acrylic Topcoat - gal 830.00 - 0.00% 0.00
Total Materials ( 9 ) 46,555.00 4.86%
b. Labor:
Total Labor ( J ) 21,853.44 2.28% 0.00
c. Tools and Equipents:
Total Tools & Equipments ( BB ) 4,378.54 0.46% 0.00
d. Delivey & Hauling:
Total Delivery Cost ( VII ) 800.00 0.08% 0.00

13.0 MECHANICAL WORKS - Unit #DIV/0! - 0.00%


a. Materials:
CENTRALIZED AIRCONDITION ( HOTEL ROOM ) ( 2HP ) LS - - 0.00% 0.00
WINDOW TYPE AIRCONDITION ( HOTEL ROOM ) ( 2HP) - LS 18,500.00 - 0.00% 0.00
LOUVER STAND TYPE AIRCONDITION ( FUNCTION HALL ) (2HP) - LS 42,500.00 - 0.00% 0.00
REFRIGERATOR ( 5cu.m. ) - LS 16,500.00 - 0.00% 0.00
CHILLER ( 5cu.m. ) - LS 14,500.00 - 0.00% 0.00
FREEZER - LS 16,500.00 - 0.00% 0.00
Total Materials ( 9 ) - 0.00%
b. Labor:
Total Labor ( J ) - 0.00% 0.00
c. Tools and Equipents:
Total Tools & Equipments ( BB ) - 0.00% 0.00
d. Delivey & Hauling:
Total Delivery Cost ( VII ) - 0.00% 0.00

14.0 ELECTRONICS AND COMMUNICATION - Lot #DIV/0! - 0.00%


a. Materials:
CCTV CAMERA ( interior and exterior cctv ) - set 3,500.00 - 0.00% 0.00
FIRE ALARM - set 1,500.00 - 0.00% 0.00
INTERCOM - set 2,000.00 - 0.00% 0.00
TELEPHONE - set 2,000.00 - 0.00% 0.00
2WAY RADIO SYSTEM - set 7,500.00 - 0.00% 0.00
INTERNET SYSTEM ( including Wifi ) - set 7,500.00 - 0.00% 0.00
TV SHOWCASE (21" Flat screen TV ) - set 13,500.00 - 0.00% 0.00
Total Materials ( 9 ) - 0.00%
b. Labor:
Total Labor ( J ) - 0.00% 0.00
c. Tools and Equipents:
Total Tools & Equipments ( BB ) - 0.00% 0.00
d. Delivey & Hauling:
Total Delivery Cost ( VII ) - 0.00% 0.00

15.0 LANDSCAPING AND SIGNAGE WORKS - sqm #DIV/0! - 0.00%


a. Materials:
CARABAO GRASS/VERMUDA - LS 3,500.00 - 0.00% 0.00
VERNACULAR PALM TREE - LS 5,500.00 - 0.00% 0.00
TRAVELLERS PLANT - LS 3,500.00 - 0.00% 0.00
ASSORTED SHURBS - LS 4,500.00 - 0.00% 0.00
ASSORTED FLOWERING PLANTS - LS 5,500.00 - 0.00% 0.00
Total Materials ( 9 ) - 0.00%
b. Labor:
Total Labor ( J ) - 0.00% 0.00
c. Tools and Equipents:
Total Tools & Equipments ( BB ) - 0.00% 0.00
d. Delivey & Hauling:
Total Delivery Cost ( VII ) - 0.00% 0.00

SUMMARY
1 MOBILIZATION/DEMOBILIZATIION 17,500.00 1.83% 0.00%
2.A DEMOLITION & DISPOSAL OF DEBRIS 3,142.00 0.33% 0.00%
2 STRUCTURAL WORKS 238,550.86 24.89% 0.00%
3 STRUCTURAL WORKS 97,385.23 10.16% 0.00%
4 MASONRY WORKS & DRY WALL 136,620.56 14.25% 0.00%
5 CEILING WORKS: ( interior & exterior ) 33,589.67 3.50% 0.00%
6 DOORS: 17,707.71 1.85% 0.00%
7 WINDOWS 6,418.00 0.67% 0.00%
8 CARPENTRY WORKS: CABINETRY (kitchen) 36,592.05 3.82% 0.00%
9 TILE WORKS 28,884.16 3.01% 0.00%
10 SANITARY/PLUMBING WORKS: Water lines, Sewer lines & fixtures 37,720.96 3.93% 0.00%
11 ELECTRICAL WORKS: 39,182.78 4.09% 0.00%
12 PAINTING WORKS 73,586.98 7.68% 0.00%
13 MECHANICAL WORKS - 0.00% 0.00%
14 ELECTRONICS AND COMMUNICATION - 0.00% 0.00%
15 LANDSCAPING AND SIGNAGE WORKS - 0.00% 0.00%
Total Labor & Materials Cost 766,880.94 80.00%

Total Material Cost ( T.M.C. ) = ( 1 - 18 ) 498,372.50 51.99% 0.00%


Total Labour Costs ( T.L.C. ) = ( A - T ) 210,024.60 21.91% 0.00%
I. DIRECT COST Tools and Equiptment ( T.E. ) = ( AA - LL ) 26,283.84 2.74% 0.00%
Delivery & Handling ( T.E. ) = ( AA - LL ) 14,700.00 1.53% 0.00%
Mobilization / Demobilization 17,500.00 1.83% 0.00%
TOTAL DIRECT COST ( T.D.C. ) = ( T.M.C.+ T.L.C. + T.E. + Mob/Demob. ) 766,880.94 80.00% 0.00%
Overhead,Contingency & Miscellaneous ( O.C.M. ) = ( 15% of T.D.C. ) 115,032.14 12.00% 0.00
II. INDIRECT COST Profit ( P ) = ( 10% of T.D.C. ) 76,688.09 8.00% 0.00
Value Added Tax ( V.A.T. ) = ( 12% of T.D.C. + O.C.M. + P )
TOTAL INDIRECT COST ( T.I.C. ) = ( O.C.M. + P + V.A.T. ) 191,720.24 20.00% 0.00
III. Supervision: Including Engineering, Saftey Officer,Project Manager ( S ) = ( 5% of T.D.C. )
IV. Material Cost Variation ( M.C.V. ) = ( 10% of T.M.C. )
TOTAL ESTIMATED CONTRACT COST ( I + II + III + IV ) Ᵽ 958,601.18 100.00% 0.00%

Prepared by: ROY G. ROQUE

Submittd by: ROY GERMAN ROQUE BUILDERS

Position: OWNER-CONTRACTOR/ARCHITECTURAL-DESIGNER

Date: MARCH 15 2016


ACH RESORT HOTEL
T DATA

Contract Ends :
Time of Effectivity:
Time Ellapse:

PREVIOUS REPORT PRESENT TO DATE


Amount % Wt. % Eq. Qty. Amount % Wt. % Eq. Qty. Amount % Wt. % Eq.

- 0% - 0% - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00% 0.00%

- 0% - 0% - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0% - 0% - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00% 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0% - 0% - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00% 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0% - 0% - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% - 0.00% 0% - 0.00% 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0% - 0% - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% - 0.00% 0% - 0.00% 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0% - 0% - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% - 0.00% 0% - 0.00% 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0% - 0% - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% - 0.00% 0% - 0.00% 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0% - 0% - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% - 0.00% 0% - 0.00% 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0% - 0% - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% - 0.00% 0% - 0.00% 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0% - 0% - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% - 0.00% 0% - 0.00% 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0% - 0% - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- Err:508 0.00 - Err:508 0% 0.00 - Err:508
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% - 0.00% 0% - 0.00% 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0% - 0% - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% - 0.00% 0% - 0.00% 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- - -

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% - 0.00% 0% - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- - -

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% - 0.00% 0% -

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- - -

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% - -

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00% - 0.00% 0.00%


- 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00% - 0.00% 0%
- 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00% - 0.00% 0%
- 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00% - 0.00% 0%
- 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00% - 0.00% 0.00%
- 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00% - 0.00% 0.00%
- 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00% - 0.00% 0.00%
- 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00% - 0.00% 0.00%
- 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00% - 0.00% 0.00%
- 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00% - 0.00% 0.00%
- 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00% - 0.00% 0.00%
- 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00% - 0.00% 0.00%
- 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00% - 0.00% 0.00%
- 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00% - 0.00% 0.00%
- 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00% - 0.00% 0.00%
- 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00% - 0.00% 0.00%
- - - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00% 0%


- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00% 0%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00% 0%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00% 0%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00% 0%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00% 0%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%
- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00%

- 0.00% 0.00 - 0.00% 0% 0.00 - 0.00% 0%


- 0.00% 0.00% 0.00 - 0.00% 0.00% 0.00 - 0.00% 0.00%
REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL
( PROGRAMME OF WORKS )
PROJECT TITLE: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL CODE:
CITY/MUNICIPALITY: PALOMPON DATE:
BARANGAY: SAN JUAN PJCT.COST Php 958,601.18
BUILDING TYPE: Reinforced Concrete Structure AREA: 626.685 SQM.
SUBJECT: PROGRAMME OF WORKS SIZE: 24.70 x 11.50 m
OWNER: SAN JUAN BEACH RESORT HOTEL DURATION Day 45 CAL. DAYS
Item UNIT
SCOPE OF WORKS (DESCRIPTION) QTY UNIT AMOUNT
No. RATE

1.0 MOBILIZATION/DEMOBILIZATIION 1.0 LOT 17,500.0 17,500.0


2.A DEMOLITION & DISPOSAL OF DEBRIS 1.00 lot 3,142.00 3,142.00
2.0 STRUCTURAL WORKS 7.38 cu.m. 32,322.21 238,550.86
3.0 STRUCTURAL WORKS 84.00 lm 1,159.35 97,385.23
4.0 MASONRY WORKS & DRY WALL 319.76 sq.m. 427.26 136,620.56
5.0 CEILING WORKS: ( interior & exterior ) 40.00 sq.m. 839.74 33,589.67
6.0 DOORS: 3.00 sets 5,902.57 17,707.71
7.0 WINDOWS 2.50 Unit 2,567.20 6,418.00
8.0 CARPENTRY WORKS: CABINETRY (kitchen) 21.60 sqm 1,694.08 36,592.05
9.0 TILE WORKS 34.00 sq.m. 849.53 28,884.16
10.0 SANITARY/PLUMBING WORKS: Water lines, Sewer lines & fixtures 35.80 sq.m. 1,053.66 37,720.96
11.0 ELECTRICAL WORKS: 1.00 lot 39,182.78 39,182.78
12.0 PAINTING WORKS 242.72 sq.m. 303.18 73,586.98
13.0 MECHANICAL WORKS - Unit - -
14.0 ELECTRONICS AND COMMUNICATION - Lot - -
15.0 LANDSCAPING AND SIGNAGE WORKS - sqm - -

I. TOTAL DIRECT COST TOTAL DIRECT COST ( T.D.C. ) = ( T.M.C.+ T.L.C. + T.E. + Mob/Demob. ) 766,880.94

Overhead,Contingency & Miscellaneous ( O.C.M. ) = ( 15% of T.D.C. ) 115,032.14

II. INDIRECT COST Profit ( P ) = ( 10% of T.D.C. ) 76,688.09

Value Added Tax ( V.A.T. ) = ( 12% of T.D.C. + O.C.M. + P )


TOTAL INDIRECT COST ( T.I.C. ) = ( O.C.M. + P + V.A.T. ) 191,720.24

III. Supervision: Including Engineering, Saftey Officer,Project Manager ( S ) = ( 5% of T.D.C. )


IV. Material Cost Variation ( M.C.V. ) = ( 10% of T.M.C. )
TOTAL ESTIMATED CONTRACT COST ( I + II + III + IV ) Ᵽ 958,601.18

Prepared by: ROY G. ROQUE

Submittd by: ROY GERMAN ROQUE BUILDERS

Position: OWNER-CONTRACTOR/ARCHITECTURAL-DESIGNER

Date: JUNE 06 2016


REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL
( BILL OF QUANTITIES )
PROJECT TITLE: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL CODE:
CITY/MUNICIPALITY: PALOMPON DATE:
BARANGAY: SAN JUAN BY:
BUILDING TYPE: Reinforced Concrete Structure AREA: 626.685 SQM.
SUBJECT: BILL OF QUANTITIES SIZE: 24.70 x 11.50 m.
OWNER: SAN JUAN BEACH RESORT HOTEL
Item UNIT
SCOPE OF WORKS (DESCRIPTION) QTY UNIT AMOUNT
No. RATE

1.0 MOBILIZATION/DEMOBILIZATIION 1.00 LOT 17,500.00 17,500.00


1.1 Mobilization/demobilization 1.0 lot 10,000.0 10,000.00
1.2 Insurance, Permit and Lincenses 1.0 lot - -
1.3 Temporary Faciities 1.0 lot 2,500.0 2,500.00
1.4 Safety Requirements and Supervision ( PPE, Scafolding & Safety Device) 1.0 lot 5,000.0 5,000.00
1.5 Testing of Materials 1.0 lot - -
1.6 Hauling & Disposal of Waste Materials 1.0 lot - -
1.7 Billboards 1.0 lot - -
Total General Mobilization/Demobilization 17,500.00

2.A DEMOLITION & DISPOSAL OF DEBRIS 1.00 lot 3,142.00 3,142.00


b. Labor:
Total Labor Cost ( B ) 3,142.00

2.0 STRUCTURAL WORKS 7.38 cu.m. 32,322.21 238,550.86


a. Materials:
Cement 73.00 bag 260.00 18,980.00
Sand 6.00 cu.m 1,550.00 9,300.00
Gravel 10.00 cu.m 1,550.00 15,500.00
10mm Def.bar (kgs) 508.00 kgs 145.00 73,660.00
8mm Def. Bar (kgs) 173.00 kgs 125.00 21,625.00
#16 GI wire (kgs) 18.00 kgs 70.00 1,260.00
Coco Lumber (bd.ft.) 467.00 bd.ft. 15.00 7,005.00
1/2" Ord.Plywood (sht) 20.00 sht 850.00 17,000.00
Assorted CWN (kgs) 10.00 kgs 70.00 700.00
Total Material Cost ( 1 ) 165,030.00
b. Labor:
Total Labor Cost ( B ) 61,281.24
c. Tools and Equipents:
Total Tools & Equipments ( BB ) 11,439.62
d. Delivey & Hauling:
Total Delivery Cost ( I ) 800.00

3.0 STRUCTURAL WORKS 84.00 lm 1,159.35 97,385.23


a ROOF & ROOF FRAMING WORKS:
a. Materials:
2.0mm x 2" x 4" C-Purlins ( pcs ) 4.00 pcs. 850.00 3,400.00
2.0mm x 2" x 3" C-Purlins ( pcs ) 12.00 bd.ft. 750.00 9,000.00
1/4" x 2" Flat Bar 3.00 kgs. 450.00 1,350.00
12mm Plain Round Bar 3.00 pcs. 420.00 1,260.00
10mm x 200 x 200mm Gusset plate - pcs. 350.00 -
Welding Electrodes 2.00 pcs. 160.00 320.00
0.40mm GI Roofing 40.00 pcs. 690.00 27,600.00
GI Roof leader 5.00 pcs. 670.00 3,350.00
GI Metal Fascia 5.00 pcs. 550.00 2,750.00
End Wall Flashing 8.00 pcs. 650.00 5,200.00
Fastener - Tex Screw 267.00 pcs. 2.50 667.50
Silicon Sealant 4.00 pcs. 260.00 1,040.00
Insulation Foam 1.00 pcs. 5,500.00 5,500.00
Total Material Cost ( 1 ) 61,437.50
b. Labor:
Total Labor Cost ( B ) 21,797.73
c. Tools and Equipents:
Total Tools & Equipments ( BB ) 6,650.00
d. Delivey & Hauling:
Total Delivery Cost ( I ) 7,500.00

4.0 MASONRY WORKS & DRY WALL 319.76 sq.m. 427.26 136,620.56
a. Materials:
4" CHB 1,207.00 pcs 15.00 18,105.00
Cement 147.00 bag 260.00 38,220.00
Sand 5.00 cu.m 1,550.00 7,750.00
Fine Sand 7.00 cu.m 1,550.00 10,850.00
10mm Def.bar (kgs) 273.00 kgs 41.43 11,310.00
#16 GI wire (kgs) 6.00 kgs 70.00 420.00
Sahara (bags) - bag 40.00 -
Total Material Cost ( 1 ) 86,655.00
b. Labor:
Total Labor Cost ( B ) 49,165.56
d. Delivey & Hauling:
Total Delivery Cost ( I ) 800.00

5.0 CEILING WORKS: ( interior & exterior ) 40.00 sq.m. 839.74 33,589.67
a. Materials:
4.5mm CFB 14.00 shts. 450.00 6,300.00
M.F. 2"x3"x5m ( pcs ) 37.00 pcs. 110.00 4,070.00
C-carrying Channel ( pcs ) 10.00 pcs. 125.00 1,250.00
1/8x1/2" b.rivet (pcs) 2.00 box 650.00 1,300.00
Moulding ( lm ) 18.00 pcs. 261.00 4,698.00
W-clip 105.00 pcs. 5.00 525.00
10mm insulation foam 0.80 roll 5,500.00 4,400.00
Total Materials ( 9 ) 22,543.00
b. Labor:
Total Labor ( J ) 7,913.33
c. Tools and Equipents:
Total Tools & Equipments ( BB ) 2,333.33
d. Delivey & Hauling:
Total Delivery Cost ( VII ) 800.00

6.0 DOORS: 3.00 sets 5,902.57 17,707.71


a. Materials:
900 x 2100 Solid type door 1.00 set 7,500.00 7,500.00
700 x 2100 Flush type door 1.00 set 3,000.00 3,000.00
600 x 2100 Flush type door 1.00 set 2,500.00 2,500.00
Total Materials ( 9 ) 13,000.00
b. Labor:
Total Labor ( J ) 3,907.71
d. Delivey & Hauling:
Total Delivery Cost ( VII ) 800.00

7.0 WINDOWS 2.50 Unit 2,567.20 6,418.00


a. Materials:
1200x1200 Jalousie type window 1.00 set 1,728.00 1,728.00
1200x600 Jalousie type window 1.50 set 864.00 1,296.00
600x600 Jalousie type window 1.50 set 432.00 648.00
Total Materials ( 9 ) 3,672.00
b. Labor:
Total Labor ( J ) 1,946.00
d. Delivey & Hauling:
Total Delivery Cost ( VII ) 800.00

8.0 CARPENTRY WORKS: CABINETRY (kitchen) 21.60 sqm 1,694.08 36,592.05


a. Materials:
3/4" Marine Plywood 8.00 shts. 1,450.00 11,600.00
Concealed Hinges 24.00 pcs. 90.00 2,160.00
Drawer Slide 12.00 set 375.00 4,500.00
Cabinet Handle 12.00 pcs. 180.00 2,160.00
Cabinet Locked 12.00 pcs. 150.00 1,800.00
Total Materials ( 9 ) 22,220.00
b. Labor:
Total Labor ( J ) 12,089.70
c. Tools and Equipents:
Total Tools & Equipments ( BB ) 1,482.35
d. Delivey & Hauling:
Total Delivery Cost ( VII ) 800.00

9.0 TILE WORKS 34.00 sq.m. 849.53 28,884.16


a. Materials:
40 x 40 213.00 pcs. 75.00 15,975.00
Tile Adhesive 6.80 bag 450.00 3,060.00
Tile Grout 2.00 bag 160.00 320.00
Total Materials ( 9 ) 19,355.00
b. Labor:
Total Labor ( J ) 8,729.16
d. Delivey & Hauling:
Total Delivery Cost ( VII ) 800.00

10.0 SANITARY/PLUMBING WORKS: Water lines, Sewer lines & fixtures 35.80 sq.m. 1,053.66 37,720.96
a. Materials:
Toilet and Bath 12.00 Unit - -
Septic Tank 1.00 lot - -
Grease Trap 1.00 lot - -
Downspout 1.00 lot - -
Catch Basin 1.00 lot - -
Water Tank ( 1500L ) 1.00 lot 22,500.00 22,500.00
Kitchen room 1.00 lot - -
Storm Drainage lines 1.00 lot - -
Water Line system 1.00 lot 5,300.00 5,300.00
Total Materials ( 9 ) 27,800.00
b. Labor:
Total Labor ( J ) 9,920.96
c. Tools and Equipents:
Total Tools & Equipments ( BB ) -
d. Delivey & Hauling:
Total Delivery Cost ( VII ) -

11.0 ELECTRICAL WORKS: 1.00 lot 39,182.78 39,182.78


a. Materials:
60 Amp.,220V, 2 Poles Main Circuit Breaker 1.00 pcs. 950.00 950.00
30 Amp.,220V, 2 Poles Circuit Breaker (Power Outlet) 1.00 pcs. 550.00 550.00
20 Amp.,220V, 2 Poles Circuit Breaker (Power Outlet) 1.00 pcs. 450.00 450.00
15 Amp.,220V, 2 Poles Circuit Breaker (Lighting & Spare) 1.00 pcs. 450.00 450.00
3/4"Ø PVC Conduit 5.00 pcs. 180.00 900.00
1/2"Ø PVC Conduit 5.00 pcs. 150.00 750.00
1/2"Ø Flexible Conduit 1.00 roll 750.00 750.00
1/2"Ø PVC Clip 1.00 box 50.00 50.00
4" Pvc utility box 15.00 pcs. 75.00 1,125.00
#4 Twisted Wire 10.00 mts 25.00 250.00
#10 THHN Stranded Wire 1.00 box 6,450.00 6,450.00
#12 THHN Stranded Wire 1.00 box 4,800.00 4,800.00
#14 THHN Stranded Wire 1.00 box 3,750.00 3,750.00
10-watts LED Bulb 1.00 set 1,250.00 1,250.00
7-watts LED Bulb 1.00 set 950.00 950.00
2-gang switches 2.00 set 550.00 1,100.00
1-gang switches 1.00 set 350.00 350.00
2-gang Convenience Outlet 5.00 set 550.00 2,750.00
Electrical Tape 1.00 roll 30.00 30.00
Emergency Lighting System 1.00 set 2,450.00 2,450.00
Total Materials ( 9 ) 30,105.00
b. Labor:
Total Labor ( J ) 8,277.78
d. Delivey & Hauling:
Total Delivery Cost ( VII ) 800.00

12.0 PAINTING WORKS 242.72 sq.m. 303.18 73,586.98


a. Materials:
WALLING INTERIOR/EXTERIOR 181.60 sq.m.
Skimcoat 11.00 gal 520.00 5,720.00
Acrytex Primer 9.00 gal 780.00 7,020.00
Acrytex Cast 4.00 gal 550.00 2,200.00
Acrytex Reducer 6.00 gal 450.00 2,700.00
Body Filler 3.00 gal 525.00 1,575.00
Acrytex Semi-gloss Top Coat 4.00 gal 820.00 3,280.00
Semi gloss Latex ( interior walling ) 3.00 gal 680.00 2,040.00
Assorted Paint Brush 2.00 pcs. 105.00 210.00
Roller Brush 9" w/. Pan 2.00 pcs. 160.00 320.00
Assorted Sand Paper 10.00 pcs. 25.00 250.00

CEILING INTERIOR/EXTERIOR 40.00 sq.m.


Acrytex Primer 2.00 gal 780.00 1,560.00
Acrytex Reducer 1.00 gal 450.00 450.00
Flat Latex 2.00 gal 550.00 1,100.00
Body Filler 1.00 gal 525.00 525.00
Marine Epoxy 1.00 lit 250.00 250.00
Joint Tape 2.00 roll 75.00 150.00
QDE for Molding 1.00 gal 620.00 620.00
Assorted Paint Brush 2.00 pcs. 105.00 210.00
Roller Brush 9" w/. Pan 2.00 pcs. 160.00 320.00
Assorted Sand Paper 10.00 pcs. 25.00 250.00

AUTOMOTIVE/VARNISH PAINT ( Cabinets, Closets, Shelfs, Railings & Grills ) 21.12 sq.m.
Auto. Lacquer Primer Surfacer 2.00 gal 695.00 1,390.00
Auto. Lacquer Spot Putty 2.00 gal 680.00 1,360.00
Auto. Lacquer Thinner 2.00 gal 450.00 900.00
Auto. Lacquer Top Coat Gloss 2.00 gal 880.00 1,760.00
Auto. Lacquer Sanding Sealer 2.00 gal 620.00 1,240.00
Auto. Lacquer Flo 2.00 gal 620.00 1,240.00
Auto. Lacquer Dead Flat 2.00 gal 630.00 1,260.00
Auto. Lacquer Clear Gloss 1.00 gal 680.00 680.00
Wood Stain varnish 2.00 gal 650.00 1,300.00
Epoxy Primer 2.00 gal 680.00 1,360.00
Epoxy Enamel 2.00 gal 750.00 1,500.00
Body Filler 2.00 gal 525.00 1,050.00
Assorted Paint Brush 1.00 pcs. 105.00 105.00
Baby Roller Brush 4" 1.00 pcs. 160.00 160.00
Assorted Sand Paper 20.00 pcs. 25.00 500.00

ROOFING PAINTING WORKS: ( Repainting works ) - sqm


Acrylic Paint - gal 860.00 -
Acrylic Thinner - gal 450.00 -
Acrylic Topcoat - gal 830.00 -
Total Materials ( 9 ) 46,555.00
b. Labor:
Total Labor ( J ) 21,853.44
c. Tools and Equipents:
Total Tools & Equipments ( BB ) 4,378.54
d. Delivey & Hauling:
Total Delivery Cost ( VII ) 800.00

13.0 MECHANICAL WORKS - Unit -


a. Materials:
CENTRALIZED AIRCONDITION ( HOTEL ROOM ) ( 2HP ) - LS - -
WINDOW TYPE AIRCONDITION ( HOTEL ROOM ) ( 2HP) - LS 18,500.00 -
LOUVER STAND TYPE AIRCONDITION ( FUNCTION HALL ) (2HP) - LS 42,500.00 -
REFRIGERATOR ( 5cu.m. ) - LS 16,500.00 -
CHILLER ( 5cu.m. ) - LS 14,500.00 -
FREEZER - LS 16,500.00 -
Total Materials ( 9 ) -
b. Labor:
Total Labor ( J ) -
d. Delivey & Hauling:
Total Delivery Cost ( VII ) -

14.0 ELECTRONICS AND COMMUNICATION - Lot -


a. Materials:
CCTV CAMERA ( interior and exterior cctv ) - set 3,500.00 -
FIRE ALARM - set 1,500.00 -
INTERCOM - set 2,000.00 -
TELEPHONE - set 2,000.00 -
2WAY RADIO SYSTEM - set 7,500.00 -
INTERNET SYSTEM ( including Wifi ) - set 7,500.00 -
TV SHOWCASE (21" Flat screen TV ) - set 13,500.00 -
Total Materials ( 9 ) -
b. Labor:
Total Labor ( J ) -
d. Delivey & Hauling:
Total Delivery Cost ( VII ) -

15.0 LANDSCAPING AND SIGNAGE WORKS - sqm -


a. Materials:
CARABAO GRASS/VERMUDA - LS 3,500.00 -
VERNACULAR PALM TREE - LS 5,500.00 -
TRAVELLERS PLANT - LS 3,500.00 -
ASSORTED SHURBS - LS 4,500.00 -
ASSORTED FLOWERING PLANTS - LS 5,500.00 -
Total Materials ( 9 ) -
b. Labor:
Total Labor ( J ) -
d. Delivey & Hauling:
Total Delivery Cost ( VII ) -

SUMMARY
1 MOBILIZATION/DEMOBILIZATIION 17,500.00
2.A DEMOLITION & DISPOSAL OF DEBRIS 3,142.00
2 STRUCTURAL WORKS 238,550.86
3 STRUCTURAL WORKS 97,385.23
4 MASONRY WORKS & DRY WALL 136,620.56
5 CEILING WORKS: ( interior & exterior ) 33,589.67
6 DOORS: 17,707.71
7 WINDOWS 6,418.00
8 CARPENTRY WORKS: CABINETRY (kitchen) 36,592.05
9 TILE WORKS 28,884.16
10 SANITARY/PLUMBING WORKS: Water lines, Sewer lines & fixtures 37,720.96
11 ELECTRICAL WORKS: 39,182.78
12 PAINTING WORKS 73,586.98
13 MECHANICAL WORKS -
14 ELECTRONICS AND COMMUNICATION -
15 LANDSCAPING AND SIGNAGE WORKS -
Total Labor & Materials Cost 766,880.94

Total Material Cost ( T.M.C. ) = ( 1 - 18 ) 498,372.50


Total Labour Costs ( T.L.C. ) = ( A - T ) 210,024.60
I. DIRECT COST Tools and Equiptment ( T.E. ) = ( AA - LL ) 26,283.84
Delivery & Handling ( T.E. ) = ( AA - LL ) 14,700.00
I. DIRECT COST

Mobilization / Demobilization 17,500.00


TOTAL DIRECT COST ( T.D.C. ) = ( T.M.C.+ T.L.C. + T.E. + Mob/Demob. ) 766,880.94
Overhead,Contingency & Miscellaneous ( O.C.M. ) = ( 15% of T.D.C. ) 115,032.14
II. INDIRECT COST Profit ( P ) = ( 10% of T.D.C. ) 76,688.09
Value Added Tax ( V.A.T. ) = ( 12% of T.D.C. + O.C.M. + P )
TOTAL INDIRECT COST ( T.I.C. ) = ( O.C.M. + P + V.A.T. ) 191,720.24
III. Supervision: Including Engineering, Saftey Officer,Project Manager ( S ) = ( 5% of T.D.C. )
IV. Material Cost Variation ( M.C.V. ) = ( 10% of T.M.C. )
TOTAL ESTIMATED CONTRACT COST ( I + II + III + IV ) Ᵽ 958,601.18

Prepared by: ROY G. ROQUE

Submittd by: ROY GERMAN ROQUE BUILDERS

Position: OWNER-CONTRACTOR/ARCHITECTURAL-DESIGNER

Date: JUNE 06 2016


DETAILED ESTIMATES
Supplement to Program of Works

Project Tiltle: LOW COST ROW HOUSING PROJECT


Location: BRGY. LAO, ORMOC CITY, LEYTE

Item No. Work Description Quantity Unit Unit Cost

1 MOBILIZATION/DEMOBILIZATIION 1.00 LOT 17,500.00

A. Material Quantity Unit Unit Cost


Mobilization/demobilization 1.00 lot 10,000.00
Insurance, Permit and Lincenses 1.00 lot
Temporary Faciities 1.00 lot 2,500.00
Safety Requirements and Supervision ( PPE, Scafolding & Safety Device) 1.00 lot 5,000.00
Testing of Materials 1.00 lot -
Hauling & Disposal of Waste Materials 1.00 lot -
Billboards 1.00 lot

MATERIALS COST (Php)

B. Freight and Handling Quantity Unit Unit Cost

FREIGHT AND HANDLING (Php)

C. Name and Capacity of Equipment Number Number of Days Rate / Day

EQUIPMENT COST (Php)

Quantity Manpower Number of


D. Labor Derivation (Subsidiary Work Description)
Required Capability Manpower Assigned

Total Duration(days)

E. Labor Requirement Number Number of Days Rate / Day


Labor Cost (Php)

TOTAL ITEM COST (Php)


UNIT ITEM COST (Php)
DETAILED ESTIMATES
Supplement to Program of Works

Project Tiltle: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL


Location: BRGY. SAN JUAN, PALOMPON, LEYTE

Item No. Work Description Quantity Unit Unit Cost

2.A DEMOLITION & DISPOSAL OF DEBRIS 1.00 lot 3,142.00

A. Material Quantity Unit Unit Cost

MATERIALS COST (Php)

B. Freight and Handling Quantity Unit Unit Cost

FREIGHT AND HANDLING (Php)

C. Name and Capacity of Equipment Number Number of Days Rate / Day

Demolition hammer 1.00 550.00

EQUIPMENT COST (Php)

Quantity Manpower Number of


D. Labor Derivation (Subsidiary Work Description)
Required Capability Manpower Assigned

Demolition works of damage portion


1gang = 1Foreman + 2unskilled + 1electrician + 1plumber 1.00 0.50 2.00
sq.m./day/gang

Total Duration(days)

E. Labor Requirement Number Number of Days Rate / Day

Demolition works of damage portion


Resident/Site Enginer 1.00 1.00 750.00
Foreman 2.00 1.00 550.00
Leadman/Skilled 2.00 1.00 376.00
Unskiled 2.00 1.00 270.00

Labor Cost (Php)

TOTAL ITEM COST (Php)


UNIT ITEM COST (Php)
DETAILED ESTIMATES
Supplement to Program of Works

Project Tiltle: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL


Location: BRGY. SAN JUAN, PALOMPON, LEYTE

Item No. Work Description Quantity Unit Unit Cost

2 STRUCTURAL WORKS 7.38 cu.m. 32,322.21

Material Quantity Unit Unit Cost


Cement 73.00 bag 260.00
Sand 6.00 cu.m 1,550.00
Gravel 10.00 cu.m 1,550.00
10mm Def.bar (kgs) 508.00 kgs 145.00
8mm Def. Bar (kgs) 173.00 kgs 125.00
#16 GI wire (kgs) 18.00 kgs 70.00
Coco Lumber (bd.ft.) 467.00 bd.ft. 15.00
1/2" Ord.Plywood (sht) 20.00 sht 850.00
Assorted CWN (kgs) 10.00 kgs 70.00

MATERIALS COST (Php)

B. Freight and Handling Quantity Unit Unit Cost


1.00 truckload 800.00

FREIGHT AND HANDLING (Php)

C. Name and Capacity of Equipment Number Number of Days Rate / Day

Concrete mixer 1 bagger 1.00 7.38 650.00


Scaffoldings set 1.00 7.38 900.00

EQUIPMENT COST (Php)

Quantity Manpower Number of


D. Labor Derivation (Subsidiary Work Description)
Required Capability Manpower Assigned

Foundation work preparation 7.38 0.18 5.00


(1-gang = Foreman + 1Laborer)
Concrete pouring works 7.38 0.20 5.00
(1-gang = Foreman + 1Laborer)
Total Duration(days)

E. Labor Requirement Number Number of Days Rate / Day

Foundation work preparation


Resident/Site Engineer 1.00 1.00 750.00
Foreman 1.00 8.43 550.00
Skilled Worker 5.00 8.43 376.00
Laborer 5.00 8.43 270.00

Concrete pouring works


Resident/Site Engineer 1.00 1.00 750.00
Foreman 1.00 7.38 550.00
Skilled Worker 5.00 7.38 376.00
Laborer 5.00 7.38 270.00

Labor Cost (Php)

TOTAL ITEM COST (Php)


UNIT ITEM COST (Php)
DETAILED ESTIMATES
Supplement to Program of Works

Project Tiltle: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL


Location: BRGY. SAN JUAN, PALOMPON, LEYTE

Item No. Work Description Quantity Unit Unit Cost

3 STRUCTURAL WORKS 84.00 lm 1,159.35

Material Quantity Unit Unit Cost


a ROOF & ROOF FRAMING WORKS:
2.0mm x 2" x 4" C-Purlins ( pcs ) 4.00 pcs. 850.00
2.0mm x 2" x 3" C-Purlins ( pcs ) 12.00 bd.ft. 750.00
1/4" x 2" Flat Bar 3.00 kgs. 450.00
12mm Plain Round Bar 3.00 pcs. 420.00
Welding Electrodes 2.00 pcs. 160.00
0.40mm GI Roofing 40.00 pcs. 690.00
GI Roof leader 5.00 pcs. 670.00
GI Metal Fascia 5.00 pcs. 550.00
End Wall Flashing 8.00 pcs. 650.00
Fastener - Tex Screw 267.00 pcs. 2.50
Silicon Sealant 4.00 pcs. 260.00
Insulation Foam 1.00 pcs. 5,500.00

MATERIALS COST (Php)

B. Freight and Handling Quantity Unit Unit Cost


From plant to construction site 1.00 truckload 7,500.00

FREIGHT AND HANDLING (Php)

C. Name and Capacity of Equipment Number Number of Days Rate / Day

Assorted Power tools 2.00 3.50 350.00


Welding Machine 1.00 7.64 550.00

EQUIPMENT COST (Php)

Quantity Manpower Number of


D. Labor Derivation (Subsidiary Work Description)
Required Capability Manpower Assigned

Roof Framing Preparation and Layout 84.00 5.50 2.00


(1-gang = Foreman +1Tinthsmith + 1Laborer)
Roofing installation and accessories 84.00 12.00 2.00
(1-gang = Foreman +1Tinthsmith + 1Laborer) sq.m./day/gang

Total Duration(days)

E. Labor Requirement Number Number of Days Rate / Day

Roof Framing Preparation and Layout


Resident/Site Engineer 1.00 1.00 750.00
Foreman 1.00 7.64 550.00
Carpenter 2.00 7.64 400.00
Laborer 2.00 7.64 270.00

Roofing installation and accessories


Foreman 1.00 3.50 550.00
Carpenter 2.00 3.50 400.00
Laborer 2.00 3.50 270.00

Labor Cost (Php)

TOTAL ITEM COST (Php)


UNIT ITEM COST (Php)
DETAILED ESTIMATES
Supplement to Program of Works

Project Tiltle: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL


Location: BRGY. SAN JUAN, PALOMPON, LEYTE

Item No. Work Description Quantity Unit Unit Cost

4 MASONRY WORKS & DRY WALL 319.76 sq.m. 427.26

Material Quantity Unit Unit Cost


a MASONRY WORKS:
4" CHB 1,207.00 pcs 15.00
Cement 147.00 bag 260.00
Sand 5.00 cu.m 1,550.00
Fine Sand 7.00 cu.m 1,550.00
10mm Def.bar (kgs) 273.00 kgs 41.43
#16 GI wire (kgs) 6.00 kgs 70.00

MATERIALS COST (Php)

B. Freight and Handling Quantity Unit Unit Cost


Delivery to Construction site 1.00 truckload 800.00

FREIGHT AND HANDLING (Php)

C. Name and Capacity of Equipment Number Number of Days Rate / Day

7.11
7.11

EQUIPMENT COST (Php)

Quantity Manpower Number of


D. Labor Derivation (Subsidiary Work Description)
Required Capability Manpower Assigned

Wall footing preparation and layout 319.76 12.50 5.00


(1-gang = Foreman +1mason+ 1Laborer)
CHB laying and plastering 319.76 9.00 5.00
(1-gang = Foreman +1mason+ 1Laborer)

Total Duration(days)

E. Labor Requirement Number Number of Days Rate / Day

Wall footing preparation and layout


Resident/Site Engineer 1.00 1.00 750.00
Foreman 1.00 5.12 550.00
Mason 5.00 5.12 400.00
Laborer 5.00 5.12 270.00

CHB laying and plastering


Resident/Site Engineer 1.00 1.00 750.00
Foreman 1.00 7.11 550.00
Mason 5.00 7.11 400.00
Laborer 5.00 7.11 270.00

Labor Cost (Php)

TOTAL ITEM COST (Php)


UNIT ITEM COST (Php)
DETAILED ESTIMATES
Supplement to Program of Works

Project Tiltle: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL


Location: BRGY. SAN JUAN, PALOMPON, LEYTE

Item No. Work Description Quantity Unit Unit Cost

5 CEILING WORKS: ( interior & exterior ) 40.00 sq.m. 839.74

Material Quantity Unit Unit Cost


4.5mm CFB 14.00 shts. 450.00
M.F. 2"x3"x5m ( pcs ) 37.00 pcs. 110.00
C-carrying Channel ( pcs ) 10.00 pcs. 125.00
1/8x1/2" b.rivet (pcs) 2.00 box 650.00
Moulding ( lm ) 18.00 pcs. 261.00
W-clip 105.00 pcs. 5.00
10mm insulation foam 0.80 roll 5,500.00

MATERIALS COST (Php)

B. Freight and Handling Quantity Unit Unit Cost


Delivery 1.00 truckload 800.00

FREIGHT AND HANDLING (Php)

C. Name and Capacity of Equipment Number Number of Days Rate / Day

Electric Drill 4.00 1.67 350.00

EQUIPMENT COST (Php)

Quantity Manpower Number of


D. Labor Derivation (Subsidiary Work Description)
Required Capability Manpower Assigned

Ceiling Framing Preparation 40.00 9.00 2.00


(1-gang = Foreman +1Carpenter + 1Laborer)
Ceiling covering installation 40.00 12.00 2.00
(1-gang = Foreman + Carpenter + 1Laborer) sq.m./day/gang

Total Duration(days)

E. Labor Requirement Number Number of Days Rate / Day

Ceiling Framing Preparation


Resident/Site Engineer 1.00 1.00 750.00
Foreman 1.00 2.22 550.00
Carpenter 2.00 2.22 376.00
Laborer 2.00 2.22 270.00

Ceiling covering installation


Foreman 1.00 1.67 550.00
Carpenter 2.00 1.67 376.00
Laborer 2.00 1.67 270.00

Labor Cost (Php)

TOTAL ITEM COST (Php)


UNIT ITEM COST (Php)
DETAILED ESTIMATES
Supplement to Program of Works

Project Tiltle: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL


Location: BRGY. SAN JUAN, PALOMPON, LEYTE

Item No. Work Description Quantity Unit Unit Cost

6 DOORS: 3.00 sets 5,902.57

Material Quantity Unit Unit Cost


900 x 2100 Solid type door 1.00 set 7,500.00
700 x 2100 Flush type door 1.00 set 3,000.00
600 x 2100 Flush type door 1.00 set 2,500.00

MATERIALS COST (Php)

B. Freight and Handling Quantity Unit Unit Cost


Delivery 1.00 truckload 800.00

FREIGHT AND HANDLING (Php)

C. Name and Capacity of Equipment Number Number of Days Rate / Day

EQUIPMENT COST (Php)

Quantity Manpower Number of


D. Labor Derivation (Subsidiary Work Description)
Required Capability Manpower Assigned

Door Preparation & Door Jamb installation 3.00 1.75 2.00


(1-gang = Foreman + 1Mason + 1Laborer) sq.m./day/gang

Door Installation 3.00 1.75 2.00


(1-gang = Foreman + 1Mason + 1Laborer) sq.m./day/gang

Total Duration(days)

E. Labor Requirement Number Number of Days Rate / Day

Door Preparation & Door Jamb installation


Resident/Site Engineer 1.00 1.00 750.00
Foreman 1.00 0.86 550.00
Mason 2.00 0.86 376.00
Laborer 2.00 0.86 270.00
Door Installation
Foreman 1.00 0.86 550.00
Mason 2.00 0.86 376.00
Laborer 2.00 0.86 270.00

Labor Cost (Php)

TOTAL ITEM COST (Php)


UNIT ITEM COST (Php)
DETAILED ESTIMATES
Supplement to Program of Works

Project Tiltle: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL


Location: BRGY. SAN JUAN, PALOMPON, LEYTE

Item No. Work Description Quantity Unit Unit Cost

7 WINDOWS 2.50 Unit 2,567.20

Material Quantity Unit Unit Cost


1200x1200 Jalousie type window 1.00 set 1,728.00
1200x600 Jalousie type window 1.50 set 864.00
600x600 Jalousie type window 1.50 set 432.00

MATERIALS COST (Php)

B. Freight and Handling Quantity Unit Unit Cost


Delivery 1.00 truckload 800.00

C. Name and Capacity of Equipment Number Number of Days Rate / Day

EQUIPMENT COST (Php)

Quantity Manpower Number of


D. Labor Derivation (Subsidiary Work Description)
Required Capability Manpower Assigned

Windows Preparation & windows framing installation 2.50 2.50 1.00


(1-gang = Foreman + 1Mason + 1Laborer) sq.m./day/gang

Total Duration(days)

E. Labor Requirement Number Number of Days Rate / Day

Windows Preparation & windows framing installation


Resident/Site Engineer 1.00 1.00 750.00
Foreman 1.00 1.00 550.00
Mason 1.00 1.00 376.00
Laborer 1.00 1.00 270.00

Labor Cost (Php)


TOTAL ITEM COST (Php)
UNIT ITEM COST (Php)
DETAILED ESTIMATES
Supplement to Program of Works

Project Tiltle: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL


Location: BRGY. SAN JUAN, PALOMPON, LEYTE

Item No. Work Description Quantity Unit Unit Cost

8 CARPENTRY WORKS: CABINETRY (kitchen) 21.60 sqm 1,694.08

Material Quantity Unit Unit Cost


3/4" Marine Plywood 8.00 shts. 1,450.00
Concealed Hinges 24.00 pcs. 90.00
Drawer Slide 12.00 set 375.00
Cabinet Handle 12.00 pcs. 180.00
Cabinet Locked 12.00 pcs. 150.00

MATERIALS COST (Php)

B. Freight and Handling Quantity Unit Unit Cost


Delivery 1.00 truckload 800.00

FREIGHT AND HANDLING (Php)

C. Name and Capacity of Equipment Number Number of Days Rate / Day

Electric Drill 1.00 4.24 350.00

EQUIPMENT COST (Php)

Quantity Manpower Number of


D. Labor Derivation (Subsidiary Work Description)
Required Capability Manpower Assigned

Cabinets preparation 21.60 4.20 1.00


(1-gang = Foreman +1Carpenter + 1Laborer)
Cabinets installation 21.60 5.10 1.00
(1-gang = Foreman + Carpenter + 1Laborer) sq.m./day/gang

Total Duration(days)

E. Labor Requirement Number Number of Days Rate / Day

Cabinets preparation
Resident/Site Engineer 1.00 1.00 750.00
Foreman 1.00 5.14 550.00
Skilled Worker 1.00 5.14 400.00
Laborer 1.00 5.14 270.00

Cabinets installation
Foreman 1.00 4.24 550.00
Skilled Worker 1.00 4.24 376.00
Laborer 1.00 4.24 270.00

Labor Cost (Php)

TOTAL ITEM COST (Php)


UNIT ITEM COST (Php)
DETAILED ESTIMATES
Supplement to Program of Works

Project Tiltle: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL


Location: BRGY. SAN JUAN, PALOMPON, LEYTE

Item No. Work Description Quantity Unit Unit Cost

9 TILE WORKS 34.00 sq.m. 849.53

Material Quantity Unit Unit Cost


40 x 40 213.00 pcs. 75.00
Tile Adhesive 6.80 bag 450.00
Tile Grout 2.00 bag 160.00

MATERIALS COST (Php)

B. Freight and Handling Quantity Unit Unit Cost


Delivery 1.00 truckload 800.00

FREIGHT AND HANDLING (Php)

C. Name and Capacity of Equipment Number Number of Days Rate / Day

EQUIPMENT COST (Php)

Quantity Manpower Number of


D. Labor Derivation (Subsidiary Work Description)
Required Capability Manpower Assigned

Tile surface preparation 34.00 15.00 1.00


(1-gang = Foreman + 1Mason + 1Laborer) sq.m./day/gang

Tile installation 34.00 9.00 1.00


(1-gang = Foreman + 1Mason + 1Laborer) sq.m./day/gang

Total Duration(days)

E. Labor Requirement Number Number of Days Rate / Day

Tile surface preparation


Resident/Site Engineer 1.00 2.00 750.00
Foreman 1.00 2.27 550.00
Mason 1.00 2.27 376.00
Laborer 1.00 2.27 270.00

Tile installation
Foreman 1.00 3.78 550.00
Mason 1.00 3.78 376.00
Laborer 1.00 3.78 270.00

Labor Cost (Php)

TOTAL ITEM COST (Php)


UNIT ITEM COST (Php)
DETAILED ESTIMATES
Supplement to Program of Works

Project Tiltle: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL


Location: BRGY. SAN JUAN, PALOMPON, LEYTE

Item No. Work Description Quantity Unit Unit Cost

10 SANITARY/PLUMBING WORKS: Water lines, Sewer lines & fixtures 35.80 sq.m. 1,053.66

Material Quantity Unit Unit Cost


Toilet and Bath 12.00 Unit
Septic Tank 1.00 lot
Grease Trap 1.00 lot
Downspout 1.00 lot
Catch Basin 1.00 lot
Water Tank ( 1500L ) 1.00 lot 22,500.00
Kitchen room 1.00 lot
Storm Drainage lines 1.00 lot
Water Line system 1.00 lot 5,300.00

MATERIALS COST (Php)

B. Freight and Handling Quantity Unit Unit Cost


Delivery truckload 800.00

FREIGHT AND HANDLING (Php)

C. Name and Capacity of Equipment Number Number of Days Rate / Day

1.00 3,500.00

EQUIPMENT COST (Php)

Quantity Manpower Number of


D. Labor Derivation (Subsidiary Work Description)
Required Capability Manpower Assigned

Plumbing Preparation & clearing 35.80 9.00 1.00


(1-gang = Foreman + Plumber + 1Laborer) sq.m./day/gang
Plumbing installatiion 35.80 12.00 1.00
(1-gang = Foreman + Plumber + 1Laborer) sq.m./day/gang

Total Duration(days)

E. Labor Requirement Number Number of Days Rate / Day

Plumbing Preparation
Resident/Site Engineer 1.00 2.00 750.00
Foreman 1.00 3.98 550.00
Plumber 1.00 3.98 400.00
Laborer 1.00 3.98 270.00

Plumbing installatiion
Foreman 1.00 2.98 550.00
Plumber 1.00 2.98 376.00
Laborer 1.00 2.98 270.00

Labor Cost (Php)

TOTAL ITEM COST (Php)


UNIT ITEM COST (Php)
DETAILED ESTIMATES
Supplement to Program of Works

Project Tiltle: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL


Location: BRGY. SAN JUAN, PALOMPON, LEYTE

Item No. Work Description Quantity Unit Unit Cost

11 ELECTRICAL WORKS: 1.00 lot 39,182.78

Material Quantity Unit Unit Cost


60 Amp.,220V, 2 Poles Main Circuit Breaker 1.00 pcs. 950.00
30 Amp.,220V, 2 Poles Circuit Breaker (Power Outlet) 1.00 pcs. 550.00
20 Amp.,220V, 2 Poles Circuit Breaker (Power Outlet) 1.00 pcs. 450.00
15 Amp.,220V, 2 Poles Circuit Breaker (Lighting & Spare) 1.00 pcs. 450.00
3/4"Ø PVC Conduit 5.00 pcs. 180.00
1/2"Ø PVC Conduit 5.00 pcs. 150.00
1/2"Ø Flexible Conduit 1.00 roll 750.00
1/2"Ø PVC Clip 1.00 box 50.00
4" Pvc utility box 15.00 pcs. 75.00
#4 Twisted Wire 10.00 mts 25.00
#10 THHN Stranded Wire 1.00 box 6,450.00
#12 THHN Stranded Wire 1.00 box 4,800.00
#14 THHN Stranded Wire 1.00 box 3,750.00
10-watts LED Bulb 1.00 set 1,250.00
7-watts LED Bulb 1.00 set 950.00
2-gang switches 2.00 set 550.00
1-gang switches 1.00 set 350.00
2-gang Convenience Outlet 5.00 set 550.00
Electrical Tape 1.00 roll 30.00
Emergency Lighting System 1.00 set 2,450.00

MATERIALS COST (Php)

B. Freight and Handling Quantity Unit Unit Cost


Delivery 1.00 truckload 800.00

FREIGHT AND HANDLING (Php)

C. Name and Capacity of Equipment Number Number of Days Rate / Day

Meger

EQUIPMENT COST (Php)

Quantity Manpower Number of


D. Labor Derivation (Subsidiary Work Description)
Required Capability Manpower Assigned

Electrical preparation 1.00 0.30 1.00


(1-gang = Foreman + 1Electrician + 1Laborer) sq.m./day/gang

Electrical installation and energized 1.00 0.45 1.00


(1-gang = Foreman + 1Electrician + 1Laborer) sq.m./day/gang

Total Duration(days)

E. Labor Requirement Number Number of Days Rate / Day

Electrical clearing and preparation


Resident/Site Engineer 1.00 2.00 750.00
Foreman 1.00 3.33 550.00
Electrician 1.00 3.33 400.00
Laborer 1.00 3.33 270.00

Electrical installation and energized


Foreman 1.00 2.22 550.00
Electrician 1.00 2.22 400.00
Laborer 1.00 2.22 270.00

Labor Cost (Php)

TOTAL ITEM COST (Php)


UNIT ITEM COST (Php)
DETAILED ESTIMATES
Supplement to Program of Works

Project Tiltle: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL


Location: BRGY. SAN JUAN, PALOMPON, LEYTE

Item No. Work Description Quantity Unit Unit Cost

12 PAINTING WORKS 242.72 sq.m. 303.18

A. Material Quantity Unit Unit Cost


1 WALLING INTERIOR/EXTERIOR 181.60 sq.m.
Skimcoat 11.00 gal 520.00
Acrytex Primer 9.00 gal 780.00
Acrytex Cast 4.00 gal 550.00
Acrytex Reducer 6.00 gal 450.00
Body Filler 3.00 gal 525.00
Acrytex Semi-gloss Top Coat 4.00 gal 820.00
Semi gloss Latex ( interior walling ) 3.00 gal 680.00
Assorted Paint Brush 2.00 pcs. 105.00
Roller Brush 9" w/. Pan 2.00 pcs. 160.00
Assorted Sand Paper 10.00 pcs. 25.00

2 CEILING INTERIOR/EXTERIOR 40.00 sq.m.


Acrytex Primer 2.00 gal 780.00
Acrytex Reducer 1.00 gal 450.00
Flat Latex 2.00 gal 550.00
Body Filler 1.00 gal 525.00
Marine Epoxy 1.00 lit 250.00
Joint Tape 2.00 roll 75.00
QDE for Molding 1.00 gal 620.00
Assorted Paint Brush 2.00 pcs. 105.00
Roller Brush 9" w/. Pan 2.00 pcs. 160.00
Assorted Sand Paper 10.00 pcs. 25.00

3 AUTOMOTIVE/VARNISH PAINT ( Cabinets, Closets, Shelfs, Railings & Grills ) 21.12 sq.m.
Auto. Lacquer Primer Surfacer 2.00 gal 695.00
Auto. Lacquer Spot Putty 2.00 gal 680.00
Auto. Lacquer Thinner 2.00 gal 450.00
Auto. Lacquer Top Coat Gloss 2.00 gal 880.00
Auto. Lacquer Sanding Sealer 2.00 gal 620.00
Auto. Lacquer Flo 2.00 gal 620.00
Auto. Lacquer Dead Flat 2.00 gal 630.00
Auto. Lacquer Clear Gloss 1.00 gal 680.00
Wood Stain varnish 2.00 gal 650.00
Epoxy Primer 2.00 gal 680.00
Epoxy Enamel 2.00 gal 750.00
Body Filler 2.00 gal 525.00
Assorted Paint Brush 1.00 pcs. 105.00
Baby Roller Brush 4" 1.00 pcs. 160.00
Assorted Sand Paper 20.00 pcs. 25.00
4 ROOFING PAINTING WORKS: ( Repainting works ) - sqm
Acrylic Paint - gal 860.00
Acrylic Thinner - gal 450.00
Acrylic Topcoat - gal 830.00

MATERIALS COST (Php)

B. Freight and Handling Quantity Unit Unit Cost


Delivery 1.00 truckload 800.00

FREIGHT AND HANDLING (Php)

C. Name and Capacity of Equipment Number Number of Days Rate / Day

Air Compressor 2.00 2.58 850.00

EQUIPMENT COST (Php)


Quantity Manpower Number of
D. Labor Derivation (Subsidiary Work Description)
Required Capability Manpower Assigned

Painting Preparation: ( All Walling ) 181.60 36.00 1.00


(1-gang = Foreman + 1Paintor + 2Laborer) sq.m./day/gang
Painting Preparation: ( All Ceiling ) 40.00 24.00 1.00
(1-gang = Foreman + 1Paintor + 2Laborer) sq.m./day/gang
Painting Preparation: ( All Cabinets, Closets, Railings , Doors and Jamb & Grills ) 21.12 6.50 1.00
(1-gang = Foreman + 1Paintor + 2Laborer) sq.m./day/gang

Painting Works ( 1st coating to final coating ) 181.60 75.00 1.00


(1-gang = Foreman + 1Paintor + 2Laborer) sq.m./day/gang
Painting Works: Final coating ( All Ceiling ) 40.00 36.00 1.00
(1-gang = Foreman + 1Paintor + 2Laborer) sq.m./day/gang
Painting Works Final coating ( All Cabinets, Closets, Railings , Doors and Jamb & Grills ) 21.12 8.20 1.00
(1-gang = Foreman + 1Paintor + 2Laborer) sq.m./day/gang

Painting Works for Roofing & Roof Framing system - 15.00 1.00
(1-gang = Foreman + 1Paintor + 2Laborer) sq.m./day/gang
Total Duration(days)

E. Labor Requirement Number Number of Days Rate / Day

Painting Preparation: ( All Walling )


Resident/Site Engineer 1.00 3.00 750.00
Foreman 1.00 5.04 550.00
Paintor 1.00 5.04 400.00
Laborer 1.00 5.04 270.00

Painting Preparation: ( All Ceiling )


Foreman 1.00 1.67 550.00
Paintor 1.00 1.67 400.00
Laborer 1.00 1.67 270.00

Painting Preparation: ( All Cabinets, Closets, Railings , Doors and Jamb & Grills )
Foreman 1.00 3.25 550.00
Paintor 1.00 3.25 400.00
Laborer 1.00 3.25 270.00

Painting Works ( 1st coating to final coating )


Foreman 1.00 2.42 550.00
Paintor 1.00 2.42 400.00
Laborer 1.00 2.42 270.00

Painting Works: Final coating ( All Ceiling )


Foreman 1.00 1.11 550.00
Paintor 1.00 1.11 400.00
Laborer 1.00 1.11 270.00
Painting Works Final coating ( All Cabinets, Closets, Railings , Doors and Jamb & Grills )
Foreman 1.00 2.58 550.00
Paintor 1.00 2.58 400.00
Laborer 1.00 2.58 270.00

Painting works: Roofing and Roof Framing System


Foreman 1.00 - 550.00
Paintor 1.00 - 400.00
Laborer 1.00 - 270.00

Labor Cost (Php)

TOTAL ITEM COST (Php)


UNIT ITEM COST (Php)
DETAILED ESTIMATES
Supplement to Program of Works

Project Tiltle: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL


Location: BRGY. SAN JUAN, PALOMPON, LEYTE

Item No. Work Description Quantity Unit Unit Cost

13 MECHANICAL WORKS - Unit #DIV/0!

Material Quantity Unit Unit Cost


CENTRALIZED AIRCONDITION ( HOTEL ROOM ) ( 2HP ) - LS
WINDOW TYPE AIRCONDITION ( HOTEL ROOM ) ( 2HP) - LS 18,500.00
LOUVER STAND TYPE AIRCONDITION ( FUNCTION HALL ) (2HP) - LS 42,500.00
REFRIGERATOR ( 5cu.m. ) - LS 16,500.00
CHILLER ( 5cu.m. ) - LS 14,500.00
FREEZER - LS 16,500.00

MATERIALS COST (Php)

B. Freight and Handling Quantity Unit Unit Cost


Delivery truckload 800.00

FREIGHT AND HANDLING (Php)

C. Name and Capacity of Equipment Number Number of Days Rate / Day

1.00

EQUIPMENT COST (Php)

Quantity Manpower Number of


D. Labor Derivation (Subsidiary Work Description)
Required Capability Manpower Assigned

Appliances Preparation - 2.00 4.00


(1-gang = Foreman + Skilled worker + 1Laborer) sq.m./day/gang

Appliances Installation - 2.00 4.00


(1-gang = Foreman + Skilled worker + 1Laborer) sq.m./day/gang

Total Duration(days)

E. Labor Requirement Number Number of Days Rate / Day

Appliances Preparation
Resident/Site Engineer 1.00 750.00
Foreman 1.00 - 550.00
Skilled worker 4.00 - 400.00
Laborer 4.00 - 270.00

Appliances Installation
Foreman 1.00 550.00
Skilled worker 1.00 - 400.00
Laborer 4.00 - 270.00

Labor Cost (Php)

TOTAL ITEM COST (Php)


UNIT ITEM COST (Php)
DETAILED ESTIMATES
Supplement to Program of Works

Project Tiltle: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL


Location: BRGY. SAN JUAN, PALOMPON, LEYTE

Item No. Work Description Quantity Unit Unit Cost

14 ELECTRONICS AND COMMUNICATION Lot #DIV/0!

Material Quantity Unit Unit Cost


CCTV CAMERA ( interior and exterior cctv ) - set 3,500.00
FIRE ALARM - set 1,500.00
INTERCOM - set 2,000.00
TELEPHONE - set 2,000.00
2WAY RADIO SYSTEM set 7,500.00
INTERNET SYSTEM ( including Wifi ) - set 7,500.00
TV SHOWCASE (21" Flat screen TV ) - set 13,500.00

MATERIALS COST (Php)

B. Freight and Handling Quantity Unit Unit Cost


Delivery truckload 800.00

FREIGHT AND HANDLING (Php)

C. Name and Capacity of Equipment Number Number of Days Rate / Day

1.00

EQUIPMENT COST (Php)

Quantity Manpower Number of


D. Labor Derivation (Subsidiary Work Description)
Required Capability Manpower Assigned

Layouting - 5.50 4.00


(1-gang = Foreman + Skilled worker + 1Laborer) sq.m./day/gang

Installation of fixtures and accessories - 4.50 4.00


(1-gang = Foreman + Skilled worker + 1Laborer) sq.m./day/gang

Total Duration(days)

E. Labor Requirement Number Number of Days Rate / Day

Layouting
Resident/Site Engineer 1.00 750.00
Foreman 4.00 - 550.00
Skilled worker 4.00 - 400.00
Laborer 4.00 - 270.00

Installation of fixtures and accessories


Foreman 1.00 550.00
Skilled worker 4.00 - 400.00
Laborer 4.00 - 270.00

Labor Cost (Php)

TOTAL ITEM COST (Php)


UNIT ITEM COST (Php)
DETAILED ESTIMATES
Supplement to Program of Works

Project Tiltle: REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL


Location: BRGY. SAN JUAN, PALOMPON, LEYTE

Item No. Work Description Quantity Unit Unit Cost

15 LANDSCAPING AND SIGNAGE WORKS - sqm #DIV/0!

Material Quantity Unit Unit Cost


CARABAO GRASS/VERMUDA LS 3,500.00
VERNACULAR PALM TREE LS 5,500.00
TRAVELLERS PLANT LS 3,500.00
ASSORTED SHURBS LS 4,500.00
ASSORTED FLOWERING PLANTS LS 5,500.00

MATERIALS COST (Php)

B. Freight and Handling Quantity Unit Unit Cost


Delivery truckload 800.00

FREIGHT AND HANDLING (Php)

C. Name and Capacity of Equipment Number Number of Days Rate / Day

1.00

EQUIPMENT COST (Php)

Quantity Manpower Number of


D. Labor Derivation (Subsidiary Work Description)
Required Capability Manpower Assigned

Landscaping Preparation - 35.00 4.00


(1-gang = Foreman + Skilled worker + 1Laborer) sq.m./day/gang

Landscaping installation and planting - 40.00 4.00


(1-gang = Foreman + Skilled worker + 1Laborer) sq.m./day/gang

Total Duration(days)

E. Labor Requirement Number Number of Days Rate / Day

Landscaping Preparation
Resident/Site Engineer 1.00 750.00
Foreman 1.00 - 550.00
Skilled worker 4.00 - 400.00
Laborer 4.00 - 270.00
Landscaping installation and planting
Foreman 1.00 550.00
Skilled worker 1.00 - 400.00
Laborer 4.00 - 270.00

Labor Cost (Php)

TOTAL ITEM COST (Php)


UNIT ITEM COST (Php)

Prepared by: Checked by: Noted by:

ROY G. ROQUE FAUSTINO ROQUE Jr. ROY G. ROQUE


Contractor Technical Site Officer Owner
Cost
10,000.00
-
2,500.00
5,000.00
-
-
-

17,500.00

Cost

Cost

Number of Days to
Complete the Work

Cost
-

17,500.00
17,500.00
Cost

Cost

Cost

Number of Days to
Complete the Work

1.00

1.00

Cost

750.00
1,100.00
752.00
540.00

3,142.00

3,142.00
3,142.00

Cost
18,980.00
9,300.00
15,500.00
73,660.00
21,625.00
1,260.00
7,005.00
17,000.00
700.00

165,030.00

Cost
800.00

800.00

Cost

4,797.26
6,642.36

11,439.62

Number of Days to
Complete the Work

8.43

7.38
16.00

Cost

750.00
4,639.11
15,857.32
11,386.90
32,633.33

750.00
4,059.22
13,875.15
9,963.54
28,647.91

61,281.24

238,550.86
32,322.21

Cost

3,400.00
9,000.00
1,350.00
1,260.00
320.00
27,600.00
3,350.00
2,750.00
5,200.00
667.50
1,040.00
5,500.00

61,437.50

Cost
7,500.00

7,500.00

Cost

2,450.00
4,200.00
-
6,650.00

Number of Days to
Complete the Work

7.64

3.50

12.00

Cost

750.00
4,200.00
6,109.09
4,123.64
15,182.73

1,925.00
2,800.00
1,890.00
6,615.00

21,797.73

97,385.23
1,159.35
Cost

18,105.00
38,220.00
7,750.00
10,850.00
11,310.00
420.00

86,655.00

Cost
800.00

800.00

Cost

-
-

Number of Days to
Complete the Work

5.12

7.11

13.00

Cost

750.00
2,813.89
10,232.32
6,906.82
20,703.02

750.00
3,908.18
14,211.56
9,592.80
28,462.53

49,165.56

136,620.56
427.26
Cost
6,300.00
4,070.00
1,250.00
1,300.00
4,698.00
525.00
4,400.00

22,543.00

Cost
800.00

800.00

Cost

2,333.33
-
-
2,333.33

Number of Days to
Complete the Work

2.22

1.67

4.00

Cost

750.00
1,222.22
1,671.11
1,200.00
4,843.33

916.67
1,253.33
900.00
3,070.00

7,913.33

33,589.67
839.74
Cost
7,500.00
3,000.00
2,500.00

13,000.00

Cost
800.00

800.00

Cost

Number of Days to
Complete the Work

0.86

0.86

2.00

Cost

750.00
471.43
644.57
462.86
2,328.86
471.43
644.57
462.86
1,578.86

3,907.71

17,707.71
5,902.57
Cost
1,728.00
1,296.00
648.00

3,672.00

Cost
800.00

800.00

Cost

Number of Days to
Complete the Work

1.00

1.00

Cost

750.00
550.00
376.00
270.00
1,946.00

1,946.00
6,418.00
2,567.20
Cost
11,600.00
2,160.00
4,500.00
2,160.00
1,800.00

22,220.00

Cost
800.00

800.00

Cost

1,482.35
-
-
1,482.35

Number of Days to
Complete the Work

5.14

4.24

10.00

Cost

750.00
2,828.57
2,057.14
1,388.57
7,024.29

2,329.41
1,592.47
1,143.53
5,065.41

12,089.70

36,592.05
1,694.08
Cost
15,975.00
3,060.00
320.00

19,355.00

Cost
800.00

800.00

Cost

Number of Days to
Complete the Work

2.27

3.78

7.00

Cost

1,500.00
1,246.67
852.27
612.00
4,210.93
2,077.78
1,420.44
1,020.00
4,518.22

8,729.16

28,884.16
849.53

Cost
-
-
-
-
-
22,500.00
-
-
5,300.00

27,800.00

Cost
-

Cost

Number of Days to
Complete the Work

3.98
2.98

7.00

Cost

1,500.00
2,187.78
1,591.11
1,074.00
6,352.89

1,640.83
1,121.73
805.50
3,568.07

9,920.96

37,720.96
1,053.66
Cost
950.00
550.00
450.00
450.00
900.00
750.00
750.00
50.00
1,125.00
250.00
6,450.00
4,800.00
3,750.00
1,250.00
950.00
1,100.00
350.00
2,750.00
30.00
2,450.00

30,105.00

Cost
800.00

800.00

Cost

Number of Days to
Complete the Work

3.33
2.22

6.00

Cost

1,500.00
1,833.33
1,333.33
900.00
5,566.67

1,222.22
888.89
600.00
2,711.11

8,277.78

39,182.78
39,182.78
Cost

5,720.00
7,020.00
2,200.00
2,700.00
1,575.00
3,280.00
2,040.00
210.00
320.00
250.00
25,315.00

1,560.00
450.00
1,100.00
525.00
250.00
150.00
620.00
210.00
320.00
250.00
5,435.00

1,390.00
1,360.00
900.00
1,760.00
1,240.00
1,240.00
1,260.00
680.00
1,300.00
1,360.00
1,500.00
1,050.00
105.00
160.00
500.00
15,805.00

-
-
-
-

46,555.00

Cost
800.00

800.00

Cost

4,378.54

4,378.54
Number of Days to
Complete the Work

5.04

1.67

3.25

2.42

1.11

2.58

17.00

Cost

2,250.00
2,774.44
2,017.78
1,362.00

916.67
666.67
450.00

1,787.08
1,299.69
877.29
14,401.62

1,331.73
968.53
653.76

611.11
444.44
300.00
1,416.59
1,030.24
695.41
7,451.83

-
-
-
-

21,853.44

73,586.98
303.18
Cost
-
-
-
-
-
-

Cost
-

Cost

Number of Days to
Complete the Work

Cost

-
-
-
-
-

-
-
-
-

-
#DIV/0!
Cost
-
-
-
-
-
-
-

Cost
-

Cost

Number of Days to
Complete the Work

Cost

-
-
-
-
-

-
-
-
-

-
#DIV/0!
Cost
-
-
-
-
-

Cost
-

Cost

Number of Days to
Complete the Work

Cost

-
-
-
-
-

-
-
-
-

-
#DIV/0!
DETAILED ESTIMATES
Supplement to Program of Works

Name of Proposed Sub-Project: LOW COST ROW HOUSING PROJECT


Location: BRGY. LAO, ORMOC CITY, LEYTE

NUMBER
1 STRUCTURAL WORKS AREA UNIT LENGTH WIDTH DEPTH VOLUME UNIT
PIECES
EXCAVATION WORKS: - LM - cu.m.

TIE BEAM - LM - cu.m.


Tie Beam - sq.m. - cu.m.
- sq.m. - cu.m.

SEPTIC TANK - LM - cu.m.


Septic tank - sq.m. - cu.m.

COLUMN FOOTINGS - LM - cu.m.


Footings - sq.m. - cu.m.
- sq.m. - cu.m.

CANAL/DRAINAGE - LM - cu.m.
- sq.m. - cu.m.
- sq.m. - cu.m.

NUMBER
2 STRUCTURAL WORKS AREA UNIT LENGTH WIDTH DEPTH VOLUME UNIT
PIECES
FOUNDATION 90.94 lm. 7.38 cu.m.
CANAL/DRAINAGE - LM - cu.m
- lm - cu.m
- lm - cu.m

FOOTINGS 0.64 LM 1.15 cu.m


Footings 0.64 lm 0.80 0.80 0.30 6.00 1.15 cu.m
- lm - cu.m

TIE BEAMS - LM - cu.m


Tie beams - lm - cu.m.
- lm - cu.m.

COLUMNS: 23.10 lm. 0.55 cu.m.


From footings to 2nd. Floor level
C1 23.10 lm. 0.20 0.12 3.85 6.00 0.55 cu.m.
C2 - lm. - cu.m.
C3 - lm. - cu.m.
From 2nd. to 3rd. Floor level lm. -
C1 - lm. - cu.m.
C2 - lm. - cu.m.
C3 - lm. - cu.m.

BEAMS 23.60 lm 0.35 cu.m.

Roof Beam 23.60 lm. 0.35 cu.m.


Roof Beam (major beam) 23.60 lm. 0.15 0.10 23.60 1.00 0.35 cu.m.
- cu.m.
Roof Beam (minor beam) - lm. - cu.m.
- cu.m.
Other Beams - lm. - cu.m.
- cu.m.

Parapet roof beams - lm. - cu.m.


-

NUMBER
a STRUCTURAL WORKS AREA UNIT LENGTH WIDTH DEPTH VOLUME UNIT
PIECES
SLAB 43.60 5.32
SOF 34.00 sq.m. 3.40 cu.m.
34.00 sq.m. 6.80 5.00 0.10 1.00 3.40 cu.m.

Ledge/canopy - sq.m. - cu.m.


- sq.m. - cu.m.

Stairs - sq.m. - cu.m.


- sq.m. - cu.m.
- sq.m. - cu.m.

Wall footing 9.60 lm 1.92 cu.m.


WF1 9.60 lm 24.00 0.40 0.20 1.00 1.92 cu.m.
WF2 - lm - cu.m.

DEPTH/F NUMBER
3 STRUCTURAL WORKS AREA UNIT LENGTH WIDTH VOLUME UNIT
ACES PIECES

ROOF & ROOF FRAMING WORKS: 84.00 lm -

1 Roof Leaders 10.00 lm


10.00 lm 5.00 3.00 2.00

2 Ridge Cap - lm
- lm

3 End Wall Flashing 16.00 lm


16.00 lm 8.00 3.00 2.00
4 Valley Gutter - lm
- lm

5 Metal fascia 10.00 lm


10.00 lm 5.00 3.00 2.00

6 Roofing Materials 40.00 lm


1. Main Roof 40.00 lm 8.00 5.00 1.00 1.00

7 Roof Framing works materials 8.00 sqm


Main Roof Framing 8.00 sqm 8.00 5.00 1.00 1.00

DEPTH/F NUMBER
4 MASONRY WORKS & DRY WALL AREA UNIT LENGTH WIDTH VOLUME UNIT
ACES PIECES
MASONRY WORKS: 319.76 sq.m.

CHB WALLING: 92.76 sq.m.


CANAL/DRAINAGE - sq.m. cu.m.
CHB Wall 1 - sq.m. cu.m.
CHB Wall 2 - sq.m. cu.m.

CHB walling ( 1st. Floor ) 81.00 sq.m. cu.m.


CHB Wall 1 56.00 sq.m. 8.00 3.50 2.00 cu.m.
CHB Wall 2 17.50 sq.m. 5.00 3.50 2.00 cu.m.
CHB Wall 3 7.50 sq.m. 3.00 2.50 1.00 cu.m.

SEPTIC TANK 11.76 sq.m.


CHB wall 11.76 sq.m. 9.80 1.20 1.20 1.00 cu.m.

PLASTERING WORKS 227.00 sq.m. -


CANAL/DRAINAGE - sq.m. -
- sq.m.

1ST. FLOOR CHB Wall 200.00 sq.m. -


112.00 sq.m. 8.00 3.50 2.00 2.00
70.00 sq.m. 5.00 3.50 2.00 2.00
18.00 sq.m. 3.00 3.00 2.00 1.00

SEPTIC TANK 27.00 sq.m.


CHB wall 27.00 sq.m. 3.00 3.00 2.00 1.50

NUMBER
5 CEILING WORKS: ( interior & exterior ) AREA UNIT LENGTH WIDTH DEPTH VOLUME UNIT
PIECES
CEILING WORKS 40.00 sq.m. -
CEILING 1ST. FLOOR 40.00 sq.m.
Plain Cover 40.00 sq.m. 8.00 5.00 3.00 1.00
Coffered - sq.m.
Overhang Cover - sq.m.
Overhang Cover - sq.m.

NUMBER
6 DOORS: AREA UNIT LENGTH WIDTH DEPTH VOLUME UNIT
PIECES
DOOR 3.00 sets
1ST FLOOR - DOORS 3.00 sets
Main Door 0.90 2.10 1.00 sets
Dining door sets
Kitchen Door 0.80 2.10 1.00 sets
T&B door 0.70 2.10 1.00 sets

NUMBER
7 WINDOWS AREA UNIT LENGTH WIDTH DEPTH VOLUME UNIT
PIECES
WINDOWS 2.52 sqm. 2.50
0 1ST FLOOR - DOORS 2.52 2.50 sets
FRONT 1.44 sqm. 1.20 1.20 1.00 sets
REAR 1.08 sqm. 0.60 1.20 1.50 sets

NUMBER
8 CARPENTRY WORKS: CABINETRY (kitchen) AREA UNIT LENGTH WIDTH DEPTH LM UNIT
PIECES
CABINETS, CLOSETS & SHELFS 21.60 sqm 6.00
1ST. FLOOR 21.60 6.00
Kitchen Cabinets & Shelfs 21.60 sq.m. 3.00 1.20 0.60 6.00
Shoe Rack - sq.m.
Bar Counter - sq.m.

NUMBER
9 TILE WORKS AREA UNIT LENGTH WIDTH DEPTH VOLUME UNIT
PIECES
TILE WORKS 34.00 sq.m.
1ST. FLOOR 34.00 sq.m.
LIVING AREA 34.00 sq.m. 6.80 5.00 1.00
DINING AREA - sq.m.
KITCHEN AREA - sq.m.
PORCH AREA - sq.m.
HALL WAY - sq.m.
TOILET & BATH - sq.m.
CARPORT - sq.m.
LANAI - sq.m.
WALK WAY/DRIVE WAY - sq.m.
SERVICE AREA - sq.m.
SANITARY/PLUMBING WORKS: Water lines, Sewer lines & NUMBER
10 AREA UNIT LENGTH WIDTH DEPTH VOLUME UNIT
fixtures PIECES
35.80 sq.m. 8.00
1ST. FLOOR 35.80 sq.m. 8.00
KITCHEN AREA 34.00 sq.m. 6.80 5.00 3.00 1.00
COMMON UTILITY TOILET AND BATH 1.80 sq.m. 1.50 1.20 3.00 1.00
SEPTIC TANK - sq.m. 1.00
GREASE TRAP - sq.m. 1.00
CATCH BASIN - sq.m. 4.00

OVER ROOFING WATER TANK STORAGE - sq.m. - cu.m


WATER TANK - sq.m. - cu.m

NUMBER
11 ELECTRICAL WORKS: AREA UNIT LENGTH WIDTH DEPTH Lineal UNIT
PIECES
ELECTRICAL WORKS: 1.00 lot
1ST FLOOR 33.75 4.00 37.00 lm.
LIVING AREA 15.00 sq.m. 3.00 5.00 3.00 1.00 11.00 lm.
KITCHEN AREA 10.00 sq.m. 2.00 5.00 3.00 1.00 10.00 lm.
TOILET & BATH 3.75 sq.m. 1.50 2.50 3.00 1.00 7.00 lm.
SERVICE AREA 5.00 sq.m. 1.00 5.00 3.00 1.00 9.00 lm.

NUMBER
12 PAINTING WORKS AREA UNIT LENGTH WIDTH FACES VOLUME UNIT
PIECES
PAINTING WORKS 242.72 sq.m.
WALLING PAINTING WORKS 181.60 sq.m.
1ST. FLOOR CHB Wall 181.60 sq.m. -
Interior 112.00 sq.m. 8.00 3.50 2.00 2.00
Exterior 66.00 sq.m. 5.50 3.00 2.00 2.00
Exterior 3.60 sq.m. 1.50 1.20 2.00 1.00

NUMBER
a CEMENT FIBER BOARD CEILING AREA UNIT LENGTH WIDTH DEPTH VOLUME UNIT
PIECES
CEMENT FIBER BOARD CEILING 40.00 sq.m.
CEILING 1ST. FLOOR 40.00 sq.m.
PLAIN CEILING 40.00 sq.m. 8.00 5.00 3.00 1.00
COFFERED CEILING
OVER HANG - sq.m.

NUMBER
b VARNISH FINISH/AUTOMOTIVE FINISH AREA UNIT LENGTH WIDTH FACES VOLUME UNIT
PIECES
VARNISH FINISH/AUTOMOTIVE FINISH 21.12 sq.m.
1ST. FLOOR 21.12 sq.m.
DOORS 6.72 sq.m. 2.10 0.80 2.00 2.00
CABINETS & SHELFS 14.40 sq.m. 3.00 2.40 2.00 1.00
STAIR & HANDRAILS - sq.m.

NUMBER
c ARCHITECTURAL WORKS AREA UNIT LENGTH WIDTH FACES VOLUME UNIT
PIECES
ROOFING PAINTING WORKS: - sqm
- sqm
- sqm
- sqm
- sqm

NUMBER
13 MECHANICAL WORKS AREA UNIT LENGTH WIDTH DEPHT VOLUME UNIT
PIECES
AIRCONDITION/REFREGERATION WORKS - sqm -
1ST. FLOOR - -
HOTEL ROOM - sqm - CU.M
KITCHEN ROOM - sqm - CU.M
FUNCTION HALL - sqm - CU.M
LOBBY AND LOUNGE - sqm - CU.M

NUMBER
14 ELECTRONICS AND COMMUNICATION AREA UNIT LENGTH WIDTH FACES VOLUME UNIT
PIECES
INTERNET, CCTV CAMERAS AND ALARM SYSTEMS - sqm
FRONT SIDE - sqm
RIGHT SIDE - sqm
LEFT SIDE - sqm
REAR SIDE - sqm
HOTEL ROOM
FUNCTION HALL
LOBBY AND CHECK-IN COUNTER - sqm
PORCH AND LOUNGE - sqm
HALL WAY - sqm
DRIVE WAY - sqm
SECURITY ROOM -

NUMBER
15 LANDSCAPING AND SIGNAGE WORKS AREA UNIT LENGTH WIDTH FACES VOLUME UNIT
PIECES
LANDSCAPING WORKS: HOTEL FRONT, SIDES AND REAR SIDE - sqm
FRONT SIDE - sqm
RIGHT SIDE - sqm
LEFT SIDE - sqm
REAR SIDE - sqm
Cement Sand Gravel 20mm Def.bar (kgs) 16mm Def.bar (kgs) 12mm Def.bar (kgs)

73.00 6.00 10.00 - 740.00 112.00


- - - - - -
- - - -
- - - -

11.00 1.00 2.00 - - -


11.00 1.00 2.00
- - - -

- - - - - -
- - - -
- - - -

6.00 1.00 1.00 - 366.00 85.00

6.00 1.00 1.00 366.00 85.00


- - - -
- - - -
- - - -
- - - -
- - - -

4.00 1.00 1.00 - 374.00 -

4.00 1.00 1.00 - 374.00 -


4.00 1.00 1.00 374.00
- - - -
- - - -
- - - -
- - - -
- - - -

- - -

Cement Sand Gravel 20mm Def.bar (kgs) 16mm Def.bar (kgs) 12mm Def.bar (kgs)

52.00 3.00 6.00 - - 27.00


33.00 2.00 4.00 - - -
33.00 2.00 4.00

- - - - - -
- - -

- - - - - -
- - - -
- - - -

19.00 1.00 2.00 - - 27.00


19.00 1.00 2.00 27.00
- - - -

1/4" x 1-1/2 x 1-1/2" 2.0mm x 2" x 4" C- 2.0mm x 2" x 3" C-


1/4" x 2 x 2" Angular Bar 1/4" x 2" Flat Bar 12mm Plain Round Bar
Angular Bar Purlins ( pcs ) Purlins ( pcs )

- - 4.00 12.00 3.00 3.00


- - - - - -

- - 4.00 12.00 3.00 3.00


4.00 12.00 3.00 3.00

4" CHB Cement Sand Fine Sand 10mm Def.bar (kgs) #16 GI wire (kgs)

1,207.00 147.00 5.00 7.00 273.00 6.00

1,207.00 52.00 5.00 - 273.00 6.00


- - - - - -
- - -
- - -

1,054.00 45.00 4.00 - 238.00 5.00


728.00 30.00 2.00 164.00 3.00
228.00 10.00 1.00 52.00 1.00
98.00 5.00 1.00 22.00 1.00

153.00 7.00 1.00 - 35.00 1.00


153.00 7.00 1.00 35.00 1.00

- 95.00 - 7.00 - -
- - - - - -
- - -

- 83.00 - 6.00 - -
46.00 - 3.00
29.00 - 2.00
8.00 - 1.00

- 12.00 - 1.00 - -
12.00 - 1.00

C-carrying Channel
4.5mm CFB M.F. 2"x3"x5m ( pcs ) 1/8x1/2" b.rivet (pcs) Moulding ( lm ) W-clip
( pcs )

14.00 37.00 10.00 2.00 18.00 105.00


14.00 37.00 10.00 2.00 18.00 105.00
14.00 37.00 10.00 2.00 18.00 105.00
- - - - - -
- - - - - -
- - - - - -

Solid Type door 1000 x 900 x 2100 Solid type 800 x 2100 Solid type 700 x 2100 Solid type 700 x 2100 Flush type 600 x 2100 Flush type
2100 door door door door door

- 1.00 - - 1.00 1.00


- 1.00 - - 1.00 1.00
1.00
-
1.00
1.00

1800x1200 Awning type 1200x1200 Awning type 600x600 Awning type 600x1500 Fix & Awning 1200x2400mm Fix & 1200x600mm Fix &
window window window type window Awning type Window Awning type Window

- - - - - -
- - - - - -

EXTENSION SLIDE
3/4' MARINE PLYWOOD CONCEALED HINGES CABINET HANDLE CABINET LOCKED HANGER BAR
( DRAWER )

8.00 24.00 12.00 12.00 12.00 -


8.00 24.00 12.00 12.00 12.00 -
8.00 24.00 12.00 12.00 12.00
- - - - -
- - - - - -

30 x 30 40 x 40 60 x 60 Tile Adhessive Tile Grout Tile Trim

378.00 213.00 95.00 6.80 2.00 -


378.00 213.00 95.00 6.80 2.00 -
378.00 213.00 95.00 6.80 2.00
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
SHOWER HEAD AND
WATER CLOSEET LAVATORY SINK URINAL FLOOR DRAIN
VALVE SET

1.00 1.00 1.00 - 1.00 1.00


1.00 1.00 1.00 - 1.00 1.00
1.00
1.00 1.00 1.00 1.00

- - - - - -
- - -

Wires # 8 AWG (box) Wires # 10 AWG (box) Wires # 12 AWG (box) Wires # 14 AWG (box) C.O Duplex ACCU C.O

1.00 1.00 1.00 1.00 5.00 -


0.15 0.49 0.49 0.49 5.00 -
0.15 0.15 0.15 0.15 2.00
0.13 0.13 0.13 2.00
0.09 0.09 0.09
0.12 0.12 0.12 1.00

ACRYTEX ACRYTEX TOPCOAT


SKIMCOAT ACRYTEX PRIMER PENETRATING ACRYTEX REDUCER (ready mix) 2- BODY FILLER
SEALER COATING
11.00 13.00 9.00 10.00 8.00 7.00
8.00 9.00 5.00 6.00 4.00 3.00
8.00 9.00 5.00 6.00 4.00 3.00
4.00 5.00 2.00 3.00 3.00
3.00 3.00 2.00 2.00 3.00
1.00 1.00 1.00 1.00 1.00

PATCHING
BODY FILLER ACRYTEX PRIMER FLAT LATEX FLAT WALL ENAMEL PAINT THINNER
COMPOUND

1.00 2.00 2.00 2.00 2.00 2.00


1.00 2.00 2.00 2.00 2.00 2.00
1.00 2.00 2.00 2.00 2.00 2.00
- - - - - -
- - - - - -

AUTO. LACQ. AUTO. LACQ. GLOSS AUTO. LACQ. DEAD


AUTO. LACQ. SPOT PUTTY LACQUER THINNER SANDING SEALER
PRIMER SURFACER TOP COAT FLAT

2.00 2.00 2.00 2.00 2.00 2.00


2.00 2.00 2.00 2.00 2.00 2.00
1.00 1.00 1.00 1.00 1.00 1.00
1.00 1.00 1.00 1.00 1.00 1.00
- - - - - -

Roof Guard/Roofing
Acrylic Paint Acrylic Thinner Acrylic topcoat
Paint

- - - -
- - -
- - -
- - -
- - -

CENTRALIZE WINDOW TYPE LOUVER STAND


REFRIGERATOR CHILLER FREEZER
AIRCONDITION AIRCONDITION TYPE AIRCONDITION

- - - - - -
- - - - - -
- -
- - - - -
-
- -

INTERNET SYSTEM
CCTV CAMERA FIRE ALARM INTERCOM TELEPHONE 2-WAY RADIO
AND DATABASE

- - - - - -
- -
- -
- -
- -
-

- - - -
-
-
-
- -

CARABAO VERNACULAR PALM ASSORTED


TRAVELLERS PLANT ASSORTED SHURBS
GRASS/VERMUDA TREE FLOWERING PLANTS

- - - -
- - -
- - -
- - -
- - -
10mm Def.bar (kgs) 8mm Def. Bar (kgs) #16 GI wire (kgs) Coco Lumber (bd.ft.) 1/2" Ord.Plywood (sht) Assorted CWN (kgs)

508.00 173.00 18.00 467.00 20.00 10.00


- - - - -
- -
- -

28.00 1.00 1.00 - - -


28.00 1.00 1.00
- -

- - - - - -
- - - - - -
- - - - - -

87.00 6.00 6.00 231.00 10.00 5.00

87.00 6.00 6.00 231.00 10.00 5.00


- - - - - -
- - - - - -
-
- - - - - -
- - - - - -
- - - - - -

276.00 84.00 8.00 236.00 10.00 5.00

276.00 84.00 8.00 236.00 10.00 5.00


276.00 84.00 8.00 236.00 10.00 5.00
- - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
-
-
-

10mm Def.bar (kgs) 8mm Def. Bar (kgs) #16 GI wire (kgs) Coco Lumber (bd.ft.) 1/2" Ord.Plywood (sht) Assorted CWN (kgs)

117.00 82.00 3.00 - - -


100.00 71.00 2.00 - - -
100.00 71.00 2.00

- - - - - -
- - - - - -

- - - - - -
- - - - - -
- - - - - -

17.00 11.00 1.00 - - -


17.00 11.00 1.00
- - -

10mm x 200 x 200mm


Welding Electrodes 0.40mm GI Roofing GI Roof leader GI Metal Fascia GI Ridge Cap
Gusset plate

- 2.00 40.00 5.00 5.00 -

5.00
5.00

-
-

-
-

5.00 -
5.00

- - 40.00 - - -
40.00

- 2.00
2.00

10mm insulation foam


Sahara (bags) 4.5mm CFB M.F. 2"x3"x8ft. ( lm ) 1/8x1/2" b.rivet (pcs)
( lm )
- - - - -

- - - - - -
- - - - -

- - - - -

- - - - -

- - - - - -
- - - - -

- - - - -

- - - - -

2"x2" Good Lumber


10mm insulation foam Assorted CWN
(ceiling joist)

0.80 - -
0.80 - -
0.80
- - -
- - -
- - -

1000 x 2100 Metal Door

-
-

1200x1200 Jalousie type 1200x600 Jalousie type 600x600 Jalousie type


window window window

1.00 1.50 1.50


1.00 1.50 1.50
1.00
1.50 1.50

MOULDING HANDRAIL

- -
- -

Cement

12.00 -
12.00 -
12.00
-
-
-
-
-
-
-
-
-
SHOWER HEAD AND SHOWER HEAD AND SHOWER HEAD AND
FAUCETS FIRE SPRINKLER WATER TANK
VALVE SET VALVE SET VALVE SET

4.00 - 1.00 - - -
4.00 - - - - -
2.00
2.00

- - 1.00 - - -
- 1.00

Motor C.O Special C.O 1 gang Switch 2 gang switch 3 gang switch 3way switch

- - 1.00 2.00 - -
- - 1.00 2.00 - -
1.00
1.00
1.00

PATCHING
ACRYTEX CAST SEMI GLOSS LATEX
COMPOUND
7.00 6.00 2.00
4.00 3.00 -
4.00 3.00 -
3.00
3.00
1.00

QDE (moulding) STIKWIL WOOD GLUE EPOXY ACRYTEX REDUCER JOINT TAPE

1.00 1.00 1.00 1.00 2.00


1.00 1.00 1.00 1.00 2.00
1.00 1.00 1.00 1.00 2.00
- - - - -
- - - - -

CLEAR GLOOS
AUTO. LACQ. FLO WOOD STAIN PAINT THINNER BODY FILLER EPOXY PRIMER
LACQ.TOP COAT

2.00 2.00 1.00 2.00 2.00 2.00


2.00 2.00 1.00 2.00 2.00 2.00
1.00 1.00 1.00 1.00 1.00
1.00 1.00 1.00 1.00 1.00 1.00
- - - - -

- - - -
- - - -

TV SHOWCASE

- -

-
-
-
-

-
Sahara water proofing

-
Sahara water proofing

-
-

-
-

-
-
-

GI Valley Gutter End Wall Flashing Fastener - Tex Screw Silicon Sealant Insulation Foam

- 8.00 267.00 4.00 1.00

8.00
8
-
0

- - 267.00 4.00 1.00


267 4 1.00
SHOWER HEAD AND SHOWER HEAD AND SHOWER HEAD AND SHOWER HEAD
VALVE SET VALVE SET VALVE SET AND VALVE SET

- - - -
- - - -

- - - -

Circuit Breaker (30 Circuit Breaker Circuit Breaker 3/4"Ө PVC 1/2"Ө PVC
L.O (10watt LED set) L.O (7watt LED set)
AMP) (20 AMP) (15 AMP) conduit conduit

3.00 1.00 1.00 1.00 1.00 5.00 5.00


3.00 1.00 1.00 1.00 1.00 5.00 5.00
1.00 1.00 1.00 1.00 2.00 2.00
1.00 1.00 1.00
1.00 1.00 1.00
1.00 1.00 1.00

EPOXY ENAMEL

2.00
2.00
1.00
1.00
-
3/4"Ө Flexible 1/2"Ө Flexible
hose conduit hose conduit

- 1.00
- 0.74
0.22
0.20
0.14
0.18
ROY GERMAN ROQUE BUILDERS
VILLABA, LEYTE
SUB-PROJECT TITLE REPAIR/REHABILITATION OF SAN JUAN BEACH RESORT HOTEL
CATEGORY COMMERCIAL
LOCATION BRGY. SAN JUAN, PALOMPON, LEYTE

LABOR DISTRIBUTION

Labor Cost (Php)


Item Scope of Work Project
Skilled Unskilled Others Total
Supervisor

1 MOBILIZATION/DEMOBILIZATIION 0.00 0.00


2.A DEMOLITION & DISPOSAL OF DEBRIS 750.00 1,852.00 540.00 3,142.00
2 STRUCTURAL WORKS 1,500.00 38,430.80 21,350.44 61,281.24
3 STRUCTURAL WORKS 750.00 15,034.09 6,013.64 21,797.73
4 MASONRY WORKS & DRY WALL 1,500.00 31,165.94 16,499.62 49,165.56
5 CEILING WORKS: ( interior & exterior ) 750.00 5,063.33 2,100.00 7,913.33
6 DOORS: 750.00 2,232.00 925.71 3,907.71
7 WINDOWS 750.00 926.00 270.00 1,946.00
8 CARPENTRY WORKS: CABINETRY (kitchen) 750.00 8,807.60 2,532.10 12,089.70
9 TILE WORKS 1,500.00 5,597.16 1,632.00 8,729.16
10 SANITARY/PLUMBING WORKS: Water lines, Sewer lines & fixtures 1,500.00 6,541.46 1,879.50 9,920.96
11 ELECTRICAL WORKS: 1,500.00 5,277.78 1,500.00 8,277.78
12 PAINTING WORKS 2,250.00 15,264.98 4,338.47 21,853.44
13 MECHANICAL WORKS 0.00 0.00 0.00 0.00
14 ELECTRONICS AND COMMUNICATION 0.00 0.00 0.00 0.00
15 LANDSCAPING AND SIGNAGE WORKS 0.00 0.00 0.00 0.00

Total (Php) 14,250.00 136,193.12 59,581.48 0.00 210,024.60


Percentage (%) 6.78 64.85 28.37 - 100.00

Prepared by: Assisted by:

ROY G. ROQUE FAUSTINO G. ROQUE Jr.


Contractor - Architectural Designer Site Technical Officer
ROY GERMAN ROQUE BUILDERS
VILLABA, LEYTE

DIRECT COST DISTRIBUTION

Item Scope of Work Materials Equipment Labor Handling*

1 MOBILIZATION/DEMOBILIZATIION
2.A DEMOLITION & DISPOSAL OF DEBRIS 0.00 0.00 3,142.00 0.00
2 STRUCTURAL WORKS 165,030.00 11,439.62 61,281.24 800.00
3 STRUCTURAL WORKS 61,437.50 6,650.00 21,797.73 7,500.00
4 MASONRY WORKS & DRY WALL 86,655.00 0.00 49,165.56 800.00
5 CEILING WORKS: ( interior & exterior ) 22,543.00 2,333.33 7,913.33 800.00
6 DOORS: 13,000.00 0.00 3,907.71 800.00
7 WINDOWS 3,672.00 0.00 1,946.00 800.00
8 CARPENTRY WORKS: CABINETRY (kitchen) 22,220.00 1,482.35 12,089.70 800.00
9 TILE WORKS 19,355.00 0.00 8,729.16 800.00
10 SANITARY/PLUMBING WORKS: Water lines, Sewer lines & fixtures 27,800.00 0.00 9,920.96 0.00
11 ELECTRICAL WORKS: 30,105.00 0.00 8,277.78 800.00
12 PAINTING WORKS 46,555.00 4,378.54 21,853.44 800.00
13 MECHANICAL WORKS 0.00 0.00 0.00 0.00
14 ELECTRONICS AND COMMUNICATION 0.00 0.00 0.00 0.00
15 LANDSCAPING AND SIGNAGE WORKS 0.00 0.00 0.00 0.00

498,372.50 26,283.84 210,024.60 14,700.00


Percentage (%) 64.99% 3.43% 27.39% 1.92%

Prepared by: Assisted by:

ROY G. ROQUE FAUSTINO G. ROQUE Jr.


Contractor - Architectural Designer Site Technical Officer
IMPLEMENTATION MODE CONTRACT
SUB-PROJECT COST (Php) 958,601.18
SUB-PROJECT DURATION (W.D.) Day 45

Percentage (%)

Project Remarks
Skilled Unskilled Others Total
Supervisor

0.00% 0.00% 0.00% 0.00% 0.00%


0.36% 0.88% 0.26% 1.50%
0.71% 18.30% 10.17% 29.18%
0.36% 7.16% 2.86% 10.38%
0.71% 14.84% 7.86% 23.41%
0.36% 2.41% 1.00% 3.77%
0.36% 1.06% 0.44% 1.86%
0.36% 0.44% 0.13% 0.93%
0.36% 4.19% 1.21% 5.76%
0.71% 2.66% 0.78% 4.16%
0.71% 3.11% 0.89% 4.72%
0.71% 2.51% 0.71% 3.94%
1.07% 7.27% 2.07% 10.41%
0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00%
0.00% 0.00% 0.00% 0.00%

6.78% 64.85% 28.37% 0.00% 100.00%

Noted:

r. SAN JUAN HOTEL AND BEACH RESORT


Owner/Owner's representative

Others Total % per item % Materials % Labor Remarks

17,500.00 17,500.00 2.28% 0.00% 0.00%


3,142.00 0.41% 0.00% 0.41%
238,550.86 31.11% 21.52% 7.99%
97,385.23 12.70% 8.01% 2.84%
136,620.56 17.82% 11.30% 6.41%
33,589.67 4.38% 2.94% 1.03%
17,707.71 2.31% 1.70% 0.51%
6,418.00 0.84% 0.48% 0.25%
36,592.05 4.77% 2.90% 1.58%
28,884.16 3.77% 2.52% 1.14%
37,720.96 4.92% 3.63% 1.29%
39,182.78 5.11% 3.93% 1.08%
73,586.98 9.60% 6.07% 2.85%
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%
0.00 0.00% 0.00% 0.00%

17,500.00 766,880.94 100.00% 64.99% 27.39%


2.28% 100.00%

Noted:

r. SAN JUAN HOTEL AND BEACH RESORT


Owner/Owner's representative
ITEM DESCRIPTION OF MATERIALS BRAND UNIT PRICE UNIT BRAND UNIT PRICE UNIT
LABOR
Resident/Safety Engineer 750 day
Foreman 550 day
Mason 376 day
Carpenter 376 day
Welder 400 day
Plumber 400 day
Steel man 376 day
Paintor 400 day
Roofing Installer/Latero 400 day
Laborers 270 day
Tile setter 400 day
Electrician 400 day
Skilled worker 400 day

STRUCTURAL MATERIALS:

PORTLAND CEMENT (40KGS) APO 260 Bag


POZOLAND CEMENT (40KGS) APO 250 Bag
WATER PROOFING SAHARA 40 Bag 44
WASHED SAND 1550 Cu.m. 1550
3/4" CRUSHED GRAVEL 1550 Cu.m. 1550
4" x 8" x 20" CHB 15 Pcs. 15
6" x 8" x 20" CHB 22 Pcs. 22
20mm Ɵ DEFORMED BAR (STD) 568 Length 40.5714285714 lm
16mm ϴ DEFORMED BAR (STD) 385 Length 40.5263157895 lm
12mm ϴ DEFORMED BAR (STD) 220 Length 40 lm
10mm ϴ DEFORMED BAR (STD) 145 Length 41.4285714286 lm
8mm ϴ DEFORMED BAR (STD) 125 Length 50 lm
1/4" x 2" x 8" x 20' CHANNEL BAR (STD) Length 0 lm
1/4" x 2" x 6" x 20' CHANNEL BAR (STD) Length 0 lm
1/4" x 2" x 4" x 20' CHANNEL BAR (STD) Length 0 lm
1/4" x 2" x 3" x 20' CHANNEL BAR (STD) Length 0 lm
1/4" x 2" x 2" x 20' CHANNEL BAR (STD) Length 0 lm
2.0mm x 2" x 8" x 20' C-PURLINS (STD) Length 0 lm
2.0mm x 2" x 6" x 20' C-PURLINS (STD) Length 0 lm
2.0mm x 2" x 4" x 20' C-PURLINS (STD) 850 Length 141.6666666667 lm
2.0mm x 2" x 3" x 20' C-PURLINS (STD) 750 Length 125 lm
1.5mm x 2" x 8" x 20' C-PURLINS (STD) 650 Length 108.3333333333 lm
1.5mm x 2" x 6" x 20' C-PURLINS (STD) 550 Length 91.6666666667 lm
1.5mm x 2" x 4" x 20' C-PURLINS (STD) 750 Length 125 lm
1.5mm x 2" x 3" x 20' C-PURLINS (STD) 455 Length 75.8333333333 lm

ARCHITECTURAL STEEL
ANGULAR BAR

1/4" x 3" x 3" x20' ANGULAR BAR Length 0 lm


1/4" x 2-1/2" x 2-1/2" x 20' ANGULAR BAR Length 0 lm
1/4" x 2" x 2" x 20' ANGULAR BAR 960 Length 160 lm
1/4" x 1-1/2" x 1-1/2" x 20' ANGULAR BAR 750 Length 125 lm
1/4" x 1" x 1" x 20' ANGULAR BAR 550 Length 91.6666666667 lm
3/16" x 3" x 3" x 20' ANGULAR BAR (STD) Length 0 lm
3/16" x 2-1/2" x 2_1/2" x 20' ANGULAR BAR (STD) Length 0 lm
3/16" x 2" x 2" x 20' ANGULAR BAR (STD) 850 Length 141.6666666667 lm
3/16" x 1-1/2" x 1-1/2" x 20' ANGULAR BAR (STD) 650 Length 108.3333333333 lm
3/16" x 1" x 1" x 20' ANGULAR BAR (STD) 450 Length 75 lm
lm
FLAT BAR
3/8" x 3" x 20' FLAT BAR (STD) Length lm
3/8" x 2-1/2" x 20' FLAT BAR (STD) Length lm
3/8" x 2" x 20' FLAT BAR (STD) Length lm
3/8" x 1-1/2" x 20' FLAT BAR (STD) Length lm
1/4" x 3" x 20' FLAT BAR (STD) Length lm
1/4" x 2-1/2" x 20' FLAT BAR (STD) Length lm
1/4" x 2" x 20' FLAT BAR (STD) Length lm
1/4" x 1-1/2" x 20' FLAT BAR (STD) 450 Length 75 lm
1/4" x 1" x 20' FLAT BAR (STD) Length lm
3/16" x 3" x 20' FLAT BAR (STD) Length lm
3/16" x 2-1/2" x 20' FLAT BAR (STD) Length lm
3/16" x 2" x 20' FLAT BAR (STD) Length lm
3/16" x 1-1/2" x 20' FLAT BAR (STD) Length lm
3/16" x 1" x 20' FLAT BAR (STD) Length lm
lm
G.I. PIPE S-40
6"ϴ x 20' x S-40 G.I. PIPE (STD) Length
4"ϴ x 20' x S-40 G.I. PIPE (STD) Length
3"ϴ x 20' x S-40 G.I. PIPE (STD) Length
2-1/2" ϴ x 20' x S-40 G.I. PIPE (STD) Length
2"ϴ x 20' x S-40 G.I. PIPE (STD) 1650 Length
1-1/2"ϴ x 20' x S-40 G.I. PIPE (STD) 1220 Length 750 Length
1-1/4"ϴ x 20' x S-40 G.I. PIPE (STD) Length
1"ϴ x 20' x S-40 G.I. PIPE (STD) Length
3/4" ϴ x 20' x S-40 G.I. PIPE (STD) Length
1/2" ϴ x20' x S-40 G.I. PIPE (STD) Length

PLAIN ROUND BAR


16mm ϴ x 20' PLAIN ROUND BAR (STD) 650 Length
12mm ϴ x 20' PLAIN ROUND BAR (STD) 420 Length
10mm ϴ x 20' PLAIN ROUND BAR (STD) 350 Length

SQUARE BAR
20mm x 20' SQUARE BAR (STD) Length
16mm x 20' SQUARE BAR (STD) 450 Length 75 lm
12mm x 20' SQUARE BAR (STD) Length
10mm x 20' SQUARE BAR (STD) Length
SQUARE TUBE & TUBULAR
2.0mm x 4" x 4" x 20' SQUARE TUBE (STD) Length 0 lm
2.0mm x 3" x 3" x 20' SQUARE TUBE (STD) Length 0 lm
2.0mm x 2" x 2" x 20' SQUARE TUBE (STD) 1550 Length 258.3333333333 lm
1.5mm x 3" x 3" x 20' SQUARE TUBE (STD) Length 0 lm
1.5mm x 2" x 2" x 20' SQUARE TUBE (STD) Length 0 lm
1.5mm x 1" x 1" x 20' SQUARE TUBE (STD) Length 0 lm
1.5mm x 1" x 2" x 20' RECTANGULAR TUBE 650 108.3333333333 lm
1.5mm x 2" x 3" x 20' RECTANGULAR TUBE 0 lm
1.5mm x 2" x 4" x 20' RECTANGULAR TUBE 0 lm
2.0mm x 2" x8" x 20' TUBULAR (STD) Length 0 lm
2.0mm x 2" x 4" x20' TUBULAR (STD) 1856 Length 309.3333333333 lm
2.0mm x 2" x 3" x 20' TUBULAR (STD) 1220 Length 203.3333333333 lm
2.0mm x 1" x 2" x 20' TUBULAR (STD) 655 Length 109.1666666667 lm
Welding Electrodes 160 kgs. 26.6666666667

0
GOOD LUMBER & COCO LUMBER
GOOD LUMBER (ANY GOOD LUMBER) 40 Bd. Ft.
COCO LUMBER 15 Bd. Ft.
CEILING MOULDING (8ft) 261 pc 108.75 lm

PLYWOOD & OTHER COVERING BOARD

0 SANTA CLARA 1650 Sht.


3/4" x 4' x 8' MARINE PLYWOOD (STD) 1450 Sht.
1/2" x 4' x 8' MARINE PLYWOOD (STD) 850 Sht.
3/8" x 4' x 8' MARINE PLYWOOD (STD) 650 Sht.
1/4" x 4' x 8' MARINE PLYWOOD (STD) 485 Sht.
3/4" x 4' x 8' ORDINARY PLYWOOD (STD) 1200 Sht.
1/2" x 4' x 8' ORDINARY PLYWOOD (STD) 850 Sht.
3/8" x 4' x 8' ORDINARY PLYWOOD (STD) 650 Sht.
1/4" x 4' x 8' ORDINARY PLYWOOD (STD) 400 Sht.
3/4" 4' x 8' PLYBOARD (STD) 950 Sht.
10mm x 300mm HARDI-SENEPA (FASCIA BOARD) HARDIFLEX/SIERA 360 Sht.
10mm 200mm HARDI-PLANK (WALL CLADDING) HARDIFLEX/SIERA 320 Sht.
10mm x 1200 x 2400mm CEMENT FIBER BOARD HARDIFLEX/SIERA 950 Sht.
4.5mm x 1200 x 2400mm CEMENT FIBER BOARD HARDIFLEX/SIERA 450 Sht.
3.5mm x 1200 x 2400mm CEMENT FIBER BOARD HARDIFLEX/SIERA 400 Sht.
4.5mm x 1200 x 2400mm MEDIUN DENSITY FIBER BOARD Sht.

ROOFING & INSULATION SYSTEM


12mm THICK INSULATION FOAM (1-SIDED) 6500 Roll
10mm THICK INSULATION FOAM (1-SIDED) 5500 Roll 110 lm
5mm THICK INSULATION FOAM (1-SIDED) 3500 Roll
0.6mm GI Long span roofing 690 lm
0.4mm GI Long span roofing 650 lm
GA # 20 x 12ft. CORRUGATED GI SHEET (STD) TAMARAW 585 Sht.
GA # 20 x 10ft. CORRUGATED GI SHEET (STD) TAMARAW 480 Sht.
GA # 20 x 8ft. CORRUGATED GI SHEET (STD) TAMARAW 425 Sht.
GA # 22 x 12ft. CORRUGATED GI SHEET (STD) TAMARAW 575 Sht.
GA # 22 x 10ft. CORRUGATED GI SHEET (STD) TAMARAW 475 Sht.
GA # 22 x 8ft. CORRUGATED GI SHEET (STD) TAMARAW 385 Sht.
GA # 24 x 12ft. CORRUGATED GI SHEET (STD) TAMARAW Sht.
GA # 24 x 10ft. CORRUGATED GI SHEET (STD) TAMARAW Sht.
GA # 24 x 8ft. CORRUGATED GI SHEET (STD) TAMARAW Sht.
GA # 20 x 12ft. CORRUGATED ZINC ALUMINUM SHEET (STD) 685 Sht.
GA # 20 x 10ft. CORRUGATED ZINC ALUMINUM SHEET (STD) 625 Sht.
GA # 20 x 8ft. CORRUGATED ZINC ALUMINUM SHEET (STD) 550 Sht.

ROOFING ACCESSORIES
GI GUTTER 670 lm
GI METAL FASCIA 550 pc
GI RIDGE CAP 650 pc
GI VALLEY GUTTER 650 pc
GI END WALL FLASHING 650 pc
2-1/2" TEX SCREW 2.5 pc
SILICON SEALANT 260 bottle

LIGHT FRAMING MATERIALS (ARCHITECTURAL)


1" x 2" x 5m METAL FURRING JEA MAXX 110 Length 22 lm
1" x 1-1/4" x 5M METAL C-CARRYING CHANNEL JEA MAXX 125 Length 25 lm
W-CLIP JEA MAXX 5 Pc. 5 pcs.
WALL ANGLE JEA MAXX 75 Length 15 lm
METAL STUD 8FT. JEA MAXX 140 Length 58.3333333333 lm
JOINT TAPE 75 Roll

DOOR
0.60m x 2.10m FLUSH TYPE DOOR 2500 set
0.70m x 2.10m FLUSH TYPE DOOR 3000 set
0.80m x 2.10m FLUSH TYPE DOOR 3500 set
0.90m x 2.10m FLUSH TYPE DOOR 3500 set
1.00m x 2.10m FLUSH TYPE DOOR 4500 set
1.00m x 2.10m SOLID TYPE DOOR 7500 set
0.90m x 2.10m SOLID TYPE DOOR 7500 set
0.80m x 2.10m SOLID TYPE DOOR 7500 set
0.70m x 2.10m SOLID TYPE DOOR 7500 set
0.60m x 2.10m SOLID TYPE DOOR 7500 set
METAL DOOR 0

WINDOW
1/4" Brown Glass on analoc frame 3500 sqm
3/8" Brown Glass on analoc frame 5200 sqm
Jalosie type window 1200 sqm
HARDWARES & ACCESSORES
DOOR LOCK (MAIN DOOR) KWICKSET 3750 Set
DOOR LOCK KWICKSET 1250 Set
3-1/2" LOSS PIN HINGES (BRASS) 450 Pcs.
4" LOSS PIN HINGES (BRASS) 550 Pcs.
Assorted CWN 70 Kgs.
# 16 GI WIRE 70 Kgs.
Blind rivet 650 box 0.65 pc.
CONCEALED HINGES 90 Pcs.
EXTENSION SLIDE 375 pair
CABINET HANDLE 180 Pcs.
CABINET LOCKED 150 Pcs.

ITEM DESCRIPTION OF MATERIALS BRAND UNIT PRICE UNIT BRAND UNIT PRICE UNIT

ELECTRICAL FIXTURES & ACCESSORIES


10-HOLES PANEL BOARD EVER 3500 Unit
8-HOLES PANEL BOARD EVER 2400 Unit
100 AMPS. CIRCUIT BREAKER AT (PLUG-IN) EVER/GE/EAGLE 1500 Pc.
60 AMPS. CIRCUIT BREAKER AT (PLUG-IN) EVER/GE/EAGLE 950 Pc.
40 AMPS. CIRCUIT BREAKER AT (PLUG-IN) EVER/GE/EAGLE 750 Pc.
30 AMPS. CIRCUIT BREAKER AT (PLUG-IN) EVER/GE/EAGLE 550 Pc.
20 AMPS. CIRCUIT BREAKER AT (PLUG-IN) EVER/GE/EAGLE 450 Pc.
15 AMPS. CIRCUIT BREAKER AT (PLUG-IN) EVER/GE/EAGLE 450 Pc.
100 AMPS. CIRCUIT BREAKER AT (BOLT ON) EVER/GE/EAGLE Pc.
60 AMPS. CIRCUIT BREAKER AT (BOLT ON) EVER/GE/EAGLE Pc.
40 AMPS. CIRCUIT BREAKER AT (BOLT ON) EVER/GE/EAGLE Pc.
30 AMPS. CIRCUIT BREAKER AT (BOLT ON) EVER/GE/EAGLE Pc.
1-1/2" ϴ RSC PIPE 450 Length
1-1/2" SERVICE ENTRANCE CAP 200 Pc.
1"ϴ PVC CONDUIT PIPE (POLYORANGE) (STD) 210 Length
3/4" ϴ PVC CONDUIT PIPE (POLYORANGE) (STD) 180 Length
1/2" ϴ PVC CONDUIT PIPE (POLYORANGE) (STD) 150 Length
3/4" ϴ FLEXIBLE HOSE CONDUIT (POLYORANGE) 1050 Roll 21
1/2" ϴ FLEXIBLE HOSE CONDUIT (POLYORANGE) 750 Roll
4" X 4" PVC UTILITY BOX 75 Pc.
2" X 4" PVC UTILITY BOX 40 Pc.
4" x 4" PVC JUNCTION BOX 35 Pc.
# 4 TWISTED WIRE 25 mts
14.0mm² THHN STRANDED WIRE (# 6 AWG) PHELPDODGE 9850 Box
8.0mm² THHN STRANDED WIRE (#8 AWG) PHELPDODGE 8850 Box
5.5mm² THHN STRANDED WIRE (#10 AWG) PHELPDODGE 6450 Box
3.5mm² THHN STRANDED WIRE (# 12 AWG) PHELPDODGE 4800 Box
2.0mm² THHN STRANDED WIRE (# 14 AWG) PHELPDODGE 3750 Box
10-WATTS LED LAMP W/ SOCKET (PLASTIC) GE/PHILIPS/OSRAM 1250 Set
7-WATTS LED LAMP W/ SOCKET (PLASTIC) GE/PHILIPS/OSRAM 950 Set
3-WATTS LED LAMP W/ SOCKET (PLASTIC) GE/PHILIPS/OSRAM 750 Set
1-GANG SWITCHES ANAM 350 Set
2-GANG SWITCHES ANAM 550 Set
2-GANG SWITCHES 3-WAY ANAM 650 Set
2-GANG CONVENIENCE OUTLET (UNIVERSAL) ANAM 550 Set
2-GANG WEATHER PROOF CONVENIENCE OUTLET ANAM/EAGLE 850 Set
ELECTRICAL TAPE 30 Roll

PLUMBING FIXTURES & ACCESSORIES


FLUSH TYPE WATER CLOSET & ACCESSORIES (SLOW CLOSER) 4500 Set
LAVATORY W/. PEDESTAL & FAUCET W/. ACCESSORIES 2500 Set
KITCHEN SINK (STAINLESS) 3500 Set
KITCHEN FAUCET (STAINLESS) 2000 Set
HOSE BIB (STAINLESS / BRASS) 1200 Set
6"ϴ x 10' PVC PIPE S-1000 (POLYORANGE) 1450 Length
4"ϴ x 10' PVC PIPE S-1000 (POLYORANGE) 950 Length
3"ϴ x 10' PVC PIPE S-1000 (POLYORANGE) 750 Length
2"ϴ x 10' PVC PIPE S-1000 (POLYORANGE) 550 Length

FITTINGS
6"ϴ PVC COUPLING 90 Pc.
ITEM DESCRIPTION OF MATERIALS BRAND UNIT PRICE UNIT BRAND UNIT PRICE UNIT

6"ϴ PVC ELBOW 90⁰ 90 Pc.


6"ϴ PVC SANITARY TEE 100 Pc.
6"ϴ PVC CLEAN OUT 100 Pc.
4"ϴ PVC WYE 75 Pc.
4-2"ϴ PVC WYE REDUCER 75 Pc.
4"ϴ PVC COUPLING 75 Pc.
4-2"ϴ PVC COUPLING REDUCER 90 Pc.
4"ϴ PVC ELBOW 90⁰ 75 Pc.
4"ϴ PVC ELBOW 45⁰ 75 Pc.
4"ϴ PVC SANITARY TEE 90 Pc.
4-2"ϴ PVC SANITARY TEE REDUCER 90 Pc.
4"ϴ PVC CLEAN OUT 90 Pc.
3"ϴ PVC SANITARY TEE 75 Pc.
3"ϴ PVC CLEAN OUT 75 Pc.
3"ϴ PVC ELBOW 90⁰ 75 Pc.
3"ϴ PVC COUPLING 75 Pc.
2"ϴ PVC SANITARY TEE 75 Pc.
2"ϴ PVC CLEAN OUT 75 Pc.
2"ϴ PVC ELBOW 90⁰ 55 Pc.
2"ϴ PVC COUPLING 55 Pc.
2"ϴ PVC WYE 55 Pc.
2"ϴ PVC P-TRAP 90 Pc.
PVC SOLVENT CEMENT 250 Liter
1"Ө GI TEE
1"Ө GI ELBOW 90⁰
1"Ө GI ELBOW 45⁰
1"Ө GI COUPLING
1"Ө GI STRAIGHT ELBOW 90⁰
1"Ө GI FLAT UNION
1-3/4"Ө GI BUSHING REDUCER
1"Ө GI PLUG
1"Ө x1" GI NIPPLE
1"Ө x2" GI NIPPLE
3/4"Ө GI TEE
3/4"Ө GI ELBOW 90⁰
3/4"Ө GI ELBOW 45⁰
3/4"Ө GI COUPLING
3/4"Ө GI STRAIGHT ELBOW 90⁰
3/4"Ө GI FLAT UNION
3/4-1/2"Ө GI BUSHING REDUCER
3/4"Ө GI PLUG
3/4"Ө x1" GI NIPPLE
3/4"Ө x2" GI NIPPLE
1/2"Ө GI TEE
1/2"Ө GI ELBOW 90⁰
1/2"Ө GI ELBOW 45⁰
1/2"Ө GI COUPLING
1/2"Ө GI STRAIGHT ELBOW 90⁰
1/2"Ө GI FLAT UNION
1/2-3/8"Ө GI BUSHING REDUCER
1/2"Ө GI PLUG
1/2"Ө x1" GI NIPPLE
1/2"Ө x2" GI NIPPLE

TILE & ADHESIVE


TILE ADHESIVE (25 Kgs) ABC 450 Bag
TILE GROUT (2 Kgs) ABC 160 Bag
TILE TRIM (UPVC) 40 Length
TILE TRIM (BRASS) 10ft. 680 Length
30 x 30 FLOOR TILE 45 pcs
40 x 40 FLOOR TILE 75 pcs
60 x 60 FLOOR TILE 195 pcs

WALL CLADDING MATERIALS


STONE CLADDING (PURE)
STONE CLADDING (SYNTHETIC)
ALUMINUM CLADDING

ITEM DESCRIPTION OF MATERIALS BRAND UNIT PRICE UNIT READY MIX PAINT UNIT PRICE UNIT

PAINTING MATERIALS
SKIMCOAT 520 gal.
ACRYTEX SEALER 590 gal. 600
ACRYTEX PRIMER BOYSEN 780 gal. 780 galoon
ACRYTEX REDUCER BOYSEN 450 gal. 450 galoon
ACRYTEX TOP COAT GLOSS BOYSEN 880 gal. 1300 galoon
ACRYTEX TOP COAT SEMI-GLOSS BOYSEN 820 gal. 1300
ACRYTEX CAST BOYSEN 550 gal. 550
GLOSS LATEX BOYSEN/DAVIES 680 gal. 850
SEMI-GLOSS LATEX BOYSEN/DAVIES 680 gal. 850
FLAT LATEX BOYSEN/DAVIES 550 gal. 580
FLAT WALL ENAMEL BOYSEN/DAVIES 580 gal. 580
LOW PROFILE BOYSEN/DAVIES 750 gal.
EPOXY ENAMEL BOYSEN/DAVIES 750 gal.
EPOXY PRIMER BOYSEN/DAVIES 680 gal.
ROOF GUARD BOYSEN 650 gal.
CONCRETE NUETRALIZER MAYON 275 gal.
SANDING SEALER MAYON 620 gal.
QUICK DRYING ENAMEL BOYSEN/DAVIES 620 gal.
LACQUER FLO MAYON 620 gal.
LACQUER DEAD FLAT MAYON 630 gal.
LACQUER PRIMER SURFACER BOYSEN 695 gal.
LACQUER SPOT PUTTY BOYSEN 680 gal.
LACQUER THINNER MAYON 450 gal.
LACQUER WHITE TOP COAT GLOSS BOYSEN 880 gal.
LACQUER CLEAR GLOSS YOP COAT BOYSEN 680 gal.
POLYURETHENE HUDSON 1200 gal.
PAINT THINNER MAYON 350 gal.
PAINT TRAY/PAN 160 pc
ROLLER BRUSH 9" 160 pc
PAINT BRUSH 4" 105 pc
PAINT BRUSH 2-1/2" 105 pc
PAINT REMOVER MAYON 350 gal.
WOOD STAN 650 gal.
BODY FILLER 525 gal.
SAND PAPER 25 pcs
MASKING TAPE 25 roll
PATCHING COMPOUND 15 kgs.
MARINE EPOXY 250 lit
ACRYLIC PAINT 860 gal.
ACRYLIC THINNER 450 gal.
ACRYLIC TOPCOAT 830 gal.
HEAVY EQUIPMENTS

2 BULLDOZER 3.5 cu.m 12,000,000.00 24,000,000.00


3 BACKHOE 1 cu.m 8,000,000.00 24,000,000.00
3 BACKHOE 0.5 cu.m 7,500,000.00 22,500,000.00
2 BACKHOE HI-WAY 0.5 cu.m 7,000,000.00 14,000,000.00
2 GRADER 8,000,000.00 16,000,000.00
2 PAYLOADER 3 cu.m 6,500,000.00 13,000,000.00
2 ROAD ROLLER W/. COMPACTOR 2.5 m 5,500,000.00 11,000,000.00
2 ROAD ROLLER W/. COMPACTOR 1.5 m 3,000,000.00 6,000,000.00
2 GENERATOR SET 150 KVA 500,000.00 1,000,000.00
2 GENERATOR SET 120 KVA 450,000.00 900,000.00
2 PORK LIFT 3 TON 2,500,000.00 5,000,000.00
2 PORK LIFT 1.5 TON 2,000,000.00 4,000,000.00
2 TRANSIT MIXER 10-WHEELERS (FUZO) 50 BAG 2,500,000.00 5,000,000.00
2 TRANSIT MIXER 6-WHEELERS (FUZO) 30 BAG 1,500,000.00 3,000,000.00
2 SELF LOADING TRUCK 10-WHEELERS (FUZO) 2,500,000.00 5,000,000.00
3 DT 10-WHEELERS (FUZO) 10 cu.m 2,000,000.00 6,000,000.00
3 DT 10-WHEELERS (ISUZO) 10 cu.m 2,000,000.00 6,000,000.00
2 MINI DT 6-WHEELERS (FUZO) 5 cu.m 750,000.00 1,500,000.00
2 MINI DT 6-WHEELERS (ISUZO) 5 cu.m 750,000.00 1,500,000.00
2 MINI DT 6-WHEELERS (FUZO) 3 cu.m 550,000.00 1,100,000.00
2 MINI DT 6-WHEELERS (ISUZO) 3 cu.m 550,000.00 1,100,000.00
2 FUZO CANTER PICK UP TRUCK DROPSIDE 6-WHEELERS 4500 kgs 550,000.00 1,100,000.00
2 FUZO CANTER PICK UP TRUCK DROPSIDE 6-WHEELERS 7500 kgs 750,000.00 1,500,000.00
2 FUZO CANTER PICK UP TRUCK DROPSIDE 6-WHEELERS 4X4 W/. BOOM 7500 kgs 850,000.00 1,700,000.00
2 FUZO CANTER PICK UP TRUCK DROPSIDE 4-WHEELERS 2500 kgs 550,000.00 1,100,000.00
1 FR WILDTRUCK 4X4 PICK-UP 1,250,000.00 1,250,000.00
1 TOYOTA HILUX 4X4 PICK-UP 1,250,000.00 1,250,000.00
1 ISUZO D'MAX 4X4 PICK-UP 1,250,000.00 1,250,000.00
1 MITZ STRADA 4X4 PICK-UP 1,250,000.00 1,250,000.00

182,000,000.00

THERMOS 1 250.00 250.00


DC LED BULB 2 350.00 700.00
TRAY SA PLATO 1 800.00 800.00
CABINETS/SHELF 2 8,000.00 16,000.00
LENOLIUM 20 150.00 3,000.00
GAS RANGE 1 3,500.00 3,500.00
REFRIGERATOR 1 14,000.00 14,000.00
WATER DESPENSER 1 1,500.00 1,500.00
DRUM PLASTIC 2 900.00 1,800.00
LEYECO 2 5,000.00 10,000.00
WATER TANK 1 18,000.00 18,000.00
WATER TUB 1 1,500.00 1,500.00
Php 71,050.00

CERELAC 5 100.00 500.00


DIAPER 5 145.00 725.00
MILK 2 1,200.00 2,400.00
ASSORTED VITAMINS 1 500.00 500.00
SAVINGS 1 100.00 100.00
-
-
ASSORTED GROCERIES 1 5,000.00 5,000.00
Php 9,225.00

RENT SA STORE 1 2,500.00 2,500.00


MO.AMORTIZATION PICK UP 1 7,242.00 7,242.00
Php 9,742.00
VARIATION COMPUTATION
Item Amount
Additive Deductive
Based of
Amount Based Amount based Cost of Total Amount
CONTRACT Approved
ITEM SCOPE OF WORK on submitted on submitted Additional per Item of
AMOUNT Contract
Contractors contractors Works ( B-C ) Work
Detailed
estimates ( B ) estimates ( C )
Estimate (A)

Contract Package: Repair/Rehabilitation of Firewall and


additional floor at façade portion
#REF! ### #REF!
#REF! ###
### #REF! #REF! #REF!
### #REF! #REF! #REF!
#REF! ### #REF!
#REF! ###
### #REF! #REF!
### #REF! #REF!

#REF! #REF! Direct Cost #REF!


#REF! #REF! OCM ( 10% ) #REF!
#REF! #REF! Profit ( 10% ) #REF!
VAT ( 12% ) -
Supevision: -
Contract Package: Repair/Rehabilitation of Firewall and #REF! #REF! #REF! #REF!
additional floor at façade portion

#REF! ### #REF!


#REF! ###
### - #REF! #REF!
### - #REF! #REF!
### - #REF! #REF!
### #REF!
#REF! ### #REF!
#REF! ###
### - #REF! #REF!
#REF! ### #REF!
### #REF!
### - #REF! #REF!
### - #REF! - #REF!
### - #REF! - #REF!
- #REF! - Direct Cost #REF!
#REF! - OCM ( 10% ) #REF!
#REF! - Profit ( 10% ) #REF!
- VAT ( 12% ) -
- Supevision: -
TOTAL ADDITIONAL COST ( A-B ) #REF! #REF! - #REF!

TOTAL ADDITIONAL COST #REF!


TOTAL DEDUCTION COST #REF!

TOTAL CONTRACT COST #REF! TOTAL VARIATION COST #REF!

Prepared by: Checked by: Recommended by:


Trifon Ramos Mrs. Nelia O. Dazo
Architectural Designer-Contractor Site Engineer Owner
Conforme:
Roy G. Roque
Contractor
Relative
Weight % of
Additional
Works from
Contract
Cost

#REF!

#REF!

#REF!
ROY GERMAN ROQUE BUILDERS
Villaba Leyte

ADDITIVE/DEDUCTIVE WORKS
PHASE 1
CONTRACT PACKAGE No.
CONTRACTOR: ROY GERMAN ROQUE BUILDERS

Name of Project: Repair/Rehabilitation of Firewall & Roofing and Additional Floor @ Façade portion
Location: Brgy. Alta Vista, Ormoc City, Leyte

Additional
Additional Deduction
Contract Total Amount work
Project Name/Location Works Works Status
Amount (A-B) Percentage
Amount ( A ) Amount ( B )
Total

1. Firewall repair/Additional floor at Façade


#REF! #REF! #REF! #REF! #REF! For approval
Portion

TOTAL COST

Prepared by: Checked by: Recommended by:


Trifon Ramos Mrs. Nelia O. Dazo
Architectural Designer-Contractor Site Engineer Owner

Conforme:
Roy G. Roque
Contractor
Sub-Project Title Construction of Day Care Center
Category: Public Goods
Location Brgy. Balite, Villaba, Leyte

Work Description Time (days) % Amount (Php) Week 1 Week 2

M T W T F S M T W T F S

I BILLBOARDS / SIGNAGES 2 1.64% 9,840.00 1 2


II EARTHWORKS
II.A CLEARING & GRUBBING 1 0.41% 2,470.00 1
II.B EXCAVATION 3 1.15% 6,930.00 1 2 3
II.C BACKFILL& COMPACTING 4 0.48% 2,880.00
II.D SOIL POISONING 1 1.11% 6,670.00 1
III CONCRETE WORKS 4 10.65% 63,920.00 1
IV REINFORCING STEEL BARS 11 12.97% 77,880.00 1 2 3 4 5
V FORMWORKS & SCAFOLDING 4 3.55% 21,294.00 1 2
VI MASONRY WORKS 8 14.66% 88,010.00
VII CARPENTRY WORKS
VII.A ROOF FRAMING & PURLINS 8 11.01% 66,114.00
VII.B CEILING 5 6.80% 40,846.00
VIII DOORS & WINDOWS 4 9.63% 57,800.00
IX ROOFING WORKS 2 5.51% 33,069.00
X PLUMBING WORKS 10 3.56% 21,375.00
XI TILE WORKS 2 2.57% 15,410.00
XII ELECTRICAL WORKS 5 3.73% 22,405.00
XIII PAINTING WORKS 6 4.35% 26,125.00
XIV BASIC FACILITIES/AMENITIES 1 6.21% 37,300.00
Total Direct Cost 81 100.00% 600,338.00

Projected Weekly Accomplishment (%) 4.32% 10.33%

Accumulated Weekly Projected Accomplishment (%) 4.32% 14.65%

Projected Weekly Disbursement (Php) 25,910.00 62,027.00

Accumulated Projected Weekly Disbursement (Php) 25,910.00 87,937.00

Prepared by: Assisted by:


MILA JANET M. LAIGO ENGR. PHILIP ARCON S. BARBANIDA
Project Preparation Team Technical Facilitator

Time
Work Description % Amount (Php) Week 10 Week 11
(days)
M T W T F S M T W T F S

I BILLBOARDS / SIGNAGES 2 1.64% 9,840.00

II EARTHWORKS

II.A CLEARING & GRUBBING 1 0.41% 2,470.00


II.B EXCAVATION 3 1.15% 6,930.00

II.C BACKFILL& COMPACTING 4 0.48% 2,880.00

II.D SOIL POISONING 1 1.11% 6,670.00

III CONCRETE WORKS 4 10.65% 63,920.00

IV REINFORCING STEEL BARS 11 12.97% 77,880.00

VII FORMWORKS & SCAFOLDING 4 3.55% 21,294.00

VI MASONRY WORKS 8 14.66% 88,010.00

VII CARPENTRY WORKS

VII.A ROOF FRAMING & PURLINS 8 11.01% 66,114.00

VII.B CEILING 5 6.80% 40,846.00

VIII DOORS & WINDOWS 4 9.63% 57,800.00

IX ROOFING WORKS 2 5.51% 33,069.00

X PLUMBING WORKS 10 3.56% 21,375.00 3

XI TILE WORKS 2 2.57% 15,410.00 1 2 3 4 5 6 6

XII ELECTRICAL WORKS 5 3.73% 22,405.00 8 9

XIII PAINTING WORKS 6 4.35% 26,125.00 1 2 3 4 5 6 7 8 9

XIV BASIC FACILITIES/AMENITIES 1 6.21% 37,300.00 1

Total Direct Cost 100.00% 600,338.00


Projected Weekly Accomplishment (%) 9.45% 9.62%

Accumulated Weekly Projected Accomplishment (%) 109.45% 119.08%

Projected Weekly Disbursement (Php) 70,138.33 71,383.67

Accumulated Projected Weekly Disbursement (Php) 670,476.33 741,860.00

Prepared by: Assisted by:

Project Preparation Team Deputy Area Coordinator


DEPARTMENT OF SOCIAL WELFARE AND DEVELOPMENT
KALAHI CIDSS - NCDDP
Brgy. Balite, Villaba, Leyte
SUB-PROJECT MONITORING FORM

Implementation Mode Sub-Project Cost:


Community Force Account Sub-Project Duration:
by Contract

GANTT CHARTS

Week 3 Week 4 Week 5 Week 6 Week 7

M T W T F S M T W T F S M T W T F S M T W T F S M T W

1 2 3 4

2 3 4
6 7 8 9 10 11
3 4
1 2 3 4 5 6 7 8

1 2 3 4 5 6 7 8

1 2
1
1 2 3 4 5 6 7 8

1 2 3

12.54% 20.00% 6.68% 10.92% 10.91%

27.18% 47.18% 53.86% 64.78% 75.69%

75,261.25 120,058.75 40,100.00 65,565.50 65,471.70

163,198.25 283,257.00 323,357.00 388,922.50 454,394.20

Noted by: Approved:


ENGR. ORLANDO ROMERO A
Municipal Engineer Head, Barangay Sub-Project Management C

GANTT CHARTS

Week 12 Week 13 Week 14 Week 15 Week 16

M T W T F S M T W T F S M T W T F S M T W T F S M T W
Approved:

oordinator Head, Barangay Sub-Project Management Committee


Php 679,931.62
50.00 Working Days

Week 7 Week 8 Week 9

T F S M T W T F S M T W T F S

1 2 3 4 5
3 4
2
9 10
1 2
4 5
1 2 3 4 5 6
1

10.91% 12.79% 11.52%

75.69% 88.48% 100.00%

65,471.70 76,777.13 69,166.67

454,394.20 531,171.33 600,338.00


APOLINARIO I. LIRASAN
ub-Project Management Committee

Week 16 Week 17 Week 18

T F S M T W T F S M T W T F S

S-ar putea să vă placă și