Documente Academic
Documente Profesional
Documente Cultură
CAPACITY
ACTIVITY
C. SOLID ROCK
C.1 Particulars
1 Unit Air compressor with jackhammer/day
based on perpendicular boring at a maximum
height of 150 meters 100 boreholes
Number of holes required for every 1 cu.m. solid r 2 holes (1 m. depth)
Average no. of dynamite sticks per case 330 (Mayon Brand)
316 (Power Jet Brand)
C.2 Blasting Requirement per cu.m.of solid rock 3 – 4 sticks of dynamite per borehole
2 pcs. Blasting caps per cu.m. of solid rock
4 m. safety fuse per cu.m. of solid rock
C.3 Clearing Provisions
Deduct 0.60 m. Free Haul Distance
Refer to item 101 C Removal of Slides
C.4. Boring Crew Composition Crew Capacity = 100 holes per day
1 licensed blaster
2 skilled laborers
2 laborers
C.5 Blasting Crew Composition Crew Capacity = 100 holes per day
1 licensed blaster
2 skilled laborers
2 laborers
NOTES:
1. Consider reduction of manpower and equipment output for heights of more than 1.50 meters and effect
of heavy traffic.
2. Provide provisions of scaffolds and incidental expenses for height of more than 1.50 meters.
3. All equipments except Dumptrucks and Road Rollers are to be assisted by by a helper or laborer
4. Beyond 30.0 meters include Payloader and Pumptruck for disposal of waste, attached the timespotting
calculation for hauling in the detailed estimates and the dumping area. B406
5. For Rock excavation, using Bulldozer special equipment such as D155A-3, D20P-7 etc., indicate the
equipment output in the detailed estimate to justify the costing; and provide equipment data/
specification on output to support the justification.
eters and effect
e timespotting
ndicate the
ITEM 103 STRUCTURE EXCAVATION
DAILY OUTPUT (in cu.m.)
ACTIVITY
Common ExcavationLoose Rock Hard Rock
A. Labor 1.50 0.50 0.30
B. 0.225 cu.m Backhoe 120
C. Jackhammer 20 ft/hour 8 ft/Hr
Notes:
1. For instances where the excavated materials is to be disposed off to a specified
(Dumping area) computations for such waste disposal shall be considered.
2. Above labor outputs are based on maximum depth excavation of 2.00 meters
for depths of excavation exceeding 2.00 meters, add provisions for hoisting of
double/ multiple handling.
q = q1 x k
Where ql = Heaped capacity of loaded
k = Bucket factor
D. SPEED OF DUMPTRUCK
E. STOCKPILING OF BOULDERS
E.1 From sideslope: (Barring down and stockpiling)
Labor Capacity: 2.00 cu.m./man-day
E.2. Picking and stockpiling from riverbed
Labor Capacity: 2.00 cu.m./man-day
plant
batching
H Std. Specs.
ng off concrete.
CONDITIONS CAPACITY
1. Hammer-THD 22 6-8 meter/hr.depending on type of foundation
ITEM 404 REINFORCING STEEL BARS
2. Piles are spotted
A. MATERIALS
A.1. Tie wires 15 kg wires per ton of steel bars
B. LABOR: (Cutting, bending, fabrication, installation and other miscellaneous works)
B.1. Crew Composition: (Minimum Composition)
1 – Construction Foreman
2 – Skilled Laborers
2 - Steelman
6 - Laborers
Pakyaw projects, include one Civil Engineer and Lab. Tech. in the labor supervision
C. EQUIPMENT REQUIREMENT PER GANG
1 unit Bar Cutter
2 Bar Bender
6” x 8” x 16” CHB
Crew of 2 Masons and 3 Laborers
(Up to 2.0 m. height of structure)
230 pcs/day
Crew of 2 Masons and 5 Laborers
(Above 2.0 m. height of structure)
230 pcs/day
ITEM V FORMWORKS
ACTIVITY CAPACITY