PT. Semen Tonasa, in this case Litbang technique Ministry, is planning to build Coal Unloading
System and Coal Open Yard in Bulu Cindea village, Bungoro subdistrict, Pangkep regency, South
Sulawesi Province, Indonesia.
The facilities of fuel unloading ( coal) as the support of this operational activity, PT. Semen
Tonasa will increase, especially after new cement plant and new power plant were made.
The second jetty which had been built since 1996, no longer capable for coal unloading which
worked as a helper in the process of cement maker. Since that time, there must be lack of coal
supply and back material after the new factory will work and the 965.000 tons of coal in new
power plant.
For more effective and more efficient to manage the coal, it needs an open coal storage (open
yard) with 150.000 tons capacity and coal handling process in the new jetty with >1000
tons/hour capacity.
3. Job Scope
General Scope
1.0 land preparation ( heap = 250m3)
2.0 civil construction
2.1 Jetty unloading
2.2 Trestle conveyor
2.3 Coal open yard storage
3.0 Mechanical & Electrical instrument
3.1 Hopper and emergency hopper
3.2 Coal unloading (grabe or siwertell) 1000 t/h
3.3 Belt Transport 1000 t/h
3.4 Stacker system (Mobile) 1000 t/h
3.5 Bridge reclaimer 500 t/h
3.6 Portal Reclaimer (using Tonasa IV ex limestone reclaimer)
3.7 Electricity & instrument
1.0 General
1.1 Flow Sheet
1.2 Motor and gear list
1.3 Machine Card System documentation list
2.0 Documentation for layout and civil engineering
2.1 Foundation and erection drawing
2.2 Standard foundation and erection drawings
2.3 Separate foundation and erection drawings
2.4 Legends
2.5 Disposition plans
2.6 Supplement
3.0 Documentation for Mechanical engineering
3.1 Compressed air system
3.2 Water System
3.3 Oil and gas system
3.4 Dedusting system
3.5 Insulation
3.6 Fondation bolts
4.0 Documentation for Electrical engineering
4.1 Flow-sheet with instrumentation
4.2 List of instrumentation
4.3 Interlocking Diagram
4.4 Loop Diagram
4.5 Machine integrated electrical equipment
4.6 Drive
4.7 Process instrumentation
5.0 Documentation for Erection, Mode of Operation and maintenance of equipment
6.0 Training
7.0 Spare Part List
b. Engineering Job
The Basic Drawing production
The technical specification production
Detail Drawing Production
As Building Drawing Production
BQ (Bill of Quality) production
This job covers the procurement of Mechanical equipment such as: Coal Unloading System,
Belt Conveyor, Mobile Stacker and Bridge Scrapper
d. Erection Job
e. Commissioning Job
The upgrading PTST team and the relevant work units are going to do a commissioning as
the job scope which being done.
Final report contains the results of the work already done according to the contract.
Mobile Stacker
i. Capacity : 1000 ton/hour
Bridge Scrapper
i. Capacity : 500 ton / hour
Enclosed
5. Implementation period
The implementation period that has been given to finish all the project work is max 13 (thirteen)
months calendar include the final report and presentation
7. Environmental Cleanliness
Contractors must keep the work site free of waste materials and trashes during the project work
include cleaning the construction equipment
The waste of materials and trashes must be collected at a place approved by supervisor and
being transported to landfills
The trashes including the B3 cesspool categories, must be separated and specifically dealt with
the coordination of Tonasa staff.
The activity which has potential to cause environmental damage must be prevented, except it
has been coordinated by supervisor.