Michigan Department of Treasury

3881 (Rev. 09-16)


Completion: Required for Qualification.

Application for Preliminary Qualification of Bonds

School Bond Qualification and Loan Program


for

Lapeer Community Schools

Contents Tab

Certificate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Pg 1-Board Cert

Financial Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pg 2-Financial Summary

Enrollment Projections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pg 3-Enrollment

Project Sheet* . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Pg 4-Proj. Sheet

Building Utilization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pg 5-Bldg Utilization

Utilization Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pg 6-Util Summary

Facility Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pg 7-Facility Summary

Cost Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pg 8-Cost Summary

*Include building floor plans and cost estimates for each project.

For additional information about the School Bond Qualification and Loan Program, visit:
Michigan Department of Treasury
Bureau of State and Authority Finance
School Bond Qualification and Loan Program
430 West Allegan Street
Lansing, Michigan 48922
517-335-0994
517-241-1233 (f)
http://www.michigan.gov/sblf
3881, Page 1

Application for Preliminary Qualification of Bonds


Issued under authority of Public Act 92 of 2005, as amended

Election: November 5, 2019 44 - 010 - 4 - K12 - 09 - 01

District
Lapeer Community Schools 44 - 010
250 Second Street (810) 667-2401
Lapeer, MI 48446

Contact Person: Person to whom questions and correspondence concerning this application should be directed.
Matt Wandrie (810) 667-2401
Superintendent of Schools (810) 667-2411
mwandrie@lapeerschools.org

Mailing Instructions
Return TWO originally signed copies to your bond counsel by OVERNIGHT MAIL.
Return ONE originally signed copy to your financial consultant.
Return ONE originally signed copy to your architectural firm.
Return ONE originally signed copy to your construction management firm, if applicable.
Retain ONE originally signed copy for your files.

Certificate
I, the undersigned, Secretary of the Board of Education, do certify hereby that the Board of Education of this School
District, at a regular meeting of the Board, which was conducted and for which public notice of said meeting was given
pursuant to and in full compliance with Act 276 of the Public Acts of 1976 (Open Meetings Act), on this

26th day of June, 2019 took the following action:


(1) Resolved to apply for preliminary qualification of bonds by the State Treasurer for the purpose of financing the school
construction description in this application.
(2) That said application is presented to the State Treasurer for action prior to the official action of the Board of Education
calling the election on said bond issue.
(3) Resolved that this Board of Education will present a final qualification application to the State Treasurer for qualification of
their bonds after this bond issue has been approved by the electors of said district.
(4) Read this application and approved all statements and representations contained herein as true to the best knowledge and
belief of the Board.
(5) Authorized the Secretary of the Board of Education to sign this Preliminary Application and submit same to the State
Treasurer for review and approval.
IN WITNESS whereof, I have hereunto set my hand this 26th day of June, 2019

Lisa Novak
Secretary, Board of Education Signature of Secretary

Mark Rajter, Assistant Superintendent for Business Matt Wandrie


Treasurer, Board of Education (as designated by School Board) Superintendent of Schools

Miller, Canfield, Paddock and Stone, P.L.C. 150 West Jefferson, Detroit, MI 48226
Bond Counsel Mailing Address

PFM Financial Advisors LLC 555 Briarwood Circle, Ann Arbor, MI 48108
Financial Consultant Mailing Address

French Associates 236 Mill St, Rochester, MI 48307


Architectural Firm Mailing Address

Barton Malow Company 26500 American Drive, Southfield, MI 48034


Construction Management Firm Mailing Address

ATTACH PROPOSED BALLOT LANGUAGE.


OFFICIAL BALLOT

LAPEER COMMUNITY SCHOOLS


COUNTY OF LAPEER
STATE OF MICHIGAN

SCHOOL IMPROVEMENT BOND PROPOSITION

Shall the Lapeer Community Schools, County of Lapeer, State of Michigan, borrow the sum of
not to exceed Ninety-Four Million Nine Hundred Thousand Dollars ($94,900,000) and issue its
general obligation unlimited tax bonds, in one or more series, for the purpose of paying for the
cost of the following projects:

• Erecting, completing, equipping and furnishing additions to the new


High School building;

• Remodeling, equipping, re-equipping, furnishing, re-furnishing


school buildings, playgrounds and other facilities to convert the
current High School building to a Lower Elementary School building
and a current Middle School building to an Intermediate School
building and for other purposes;

• Acquiring and installing instructional technology infrastructure and


equipment in school buildings and other facilities; and

• Preparing, developing and improving sites at school buildings,


playgrounds and other facilities, which will include parking lot
improvements, and the purchase of school buses?

YES

NO

The annual debt millage required to retire all bonds of the School District currently outstanding
and proposed pursuant to this ballot is expected to be at or below 4.69 mills which is a 1.94 mill
increase from the annual debt millage levied in 2019. The maximum number of years any series
of bonds may be outstanding, exclusive of refunding, is not more than twenty-five (25) years; the
estimated millage that will be levied to pay the proposed bonds in the first year is 2.56 mills (which
is equal to $2.56 per $1,000 of taxable value); and the estimated simple average annual millage
that will be required to retire each series of bonds is 3.26 mills annually ($3.26 per $1,000 of
taxable value).

If approved by the voters, the bonds will be guaranteed by the State under the School Bond
Qualification and Loan Program (the “Program”). The School District currently has $38,640,000
of qualified bonds outstanding and $0 of qualified loans outstanding under the Program. The
School District does not expect to borrow from the Program to pay debt service on these bonds.
The estimated computed millage rate required to be levied to pay the proposed bonds may change
in the future based on changes in certain circumstances.

(Pursuant to State law, expenditure of bond proceeds must be audited, and the proceeds cannot be
used for teacher, administrator or employee salaries, repair or maintenance costs or other operating
expenses.)
33717406.2\050827-00080
3881, Page 2

Financial Summary
Lapeer Commuity Schools Financial information provided as of: 6/5/2019

A. Existing Bond Debt: List each outstanding debt issue separately in chronological order by issue date.
Original Bond Issue Current Outstanding Principal Balance Outstanding Principal Balance as of Election Date Millage
Current Current Current Election Date Levied This Tax Estimate Next
Issue Date Purpose Issue Amount Current Total Qualified Non-Qualified Non-Voted
Qualified Non-Qualified Non-Voted Total Year Tax Year
12/4/2013 LTGO School Building and Site Bond 775,000 535,000 535,000 535,000 535,000
6/16/2014 LTGO Building and Site Bonds 500,000 355,000 355,000 355,000 355,000
10/15/2015 LTGO School Building and Site 995,000 815,000 815,000 815,000 815,000
6/23/2016 Refunding Bonds (2007) 40,075,000 38,640,000 38,640,000 38,640,000 38,640,000 2.75 2.13
0 0
0 0
Total 38,640,000 0 1,705,000 40,345,000 38,640,000 0 1,705,000 40,345,000 2.75 2.13
Have proceeds of all existing bonds been spent? Yes (If No, provide status of unspent/unaudited bonds)

B. Proposed Bond Issue: List each ballot proposal separately.


Proposal Amount Bond Term Avg Int Rate Bond Interest SLRF Interest Total Interest Avg Millage Millage Year 1
Proposal 1 94,900,000 24 yrs., 6 mo 4.59% 81,016,288 0 81,016,288 3.26 2.56
Proposal 2
Proposal 3
Proposal 4
Combined Issue 94,900,000 81,016,288 0 81,016,288
(Totals may not foot due to differences in the financial structure of individual proposals and a combined bond issue.)

C. School Bond Loan Participation


School Bond Loan Fund Current Millage Est Amt to be Borrowed
Estimated Estimated
Mandatory Final
SBLF Balance Duration of Proposed
SBLF Loan SBLF Beginning Projected SBLF Estimated SBLF Maximum SFLF Maximum SBLF Initial Computed Existing Bonds Existing Bonds Proposed
as of Election Computed Bonds Interest
Repayment Date Current SBLF Balance Date End Date Interest Rate Balance Balance Year Millage Principal Interest Bonds Principal
Date Millage
n/a 0 0 n/a n/a 5.00% n/a n/a n/a n/a 0 0 0 0

D. Property Tax Assumptions


Current Growth Rate Property Taxes Levied Pending
Material Tax
Prior 5 Year Prior 20 Year Projected Rate Projected Rate
Tax Year Taxable Value Appeals in the
Average Average Years 1 - 5 Years 6+ Winter Summer
District
2019 1,442,372,347 3.25% 2.35% 2.75% 2.35% 100.00% 0.00% No
(If district is aware of any event or circumstance that could significantly affect its future, disclosure must be included.)

E. Millage F. Key Financial Measures


Total Estimated Weighted 120% of Total Current
Proposed Millage Maximum 1st Year Millage Interest to Bond Bonded Debt to Total Debt to Average Maturity Average Useful Bond Debt plus
for Next Tax Year Estimated Duration of Millage Levy Millage Increase Ratio Taxable Value Taxable Value of Bonds Life of Assets School Bond
4.69 26 4.69 1.94 0.85 0.09 0.09 18.59 41.68 40,345,000

G. Bond Issuance H. Certification


Dated Construction Construction
Series The financial impact presented herin is based on certain assumptions regarding interst rates and taxable value growth rates. Actual
Amount Date Fund Beg. Date Fund End Date
millage rates may be subject to adjustment based on differences in these assumptions, actual intersert rates, and future taxable value
1 60,000,000 6/1/2020 6/1/2020 11/1/2022
growth.
2 34,900,000 11/1/2021 11/1/2021 12/1/2024
3 Prepared By Kari L. Blanchett
4 Firm PFM Financial Advisors LLC
5
PQ_v1 2020
$60,000,000
Lapeer Commuity Schools
2020 SCHOOL BUILDING AND SITE BONDS

BOND SIZING SCHEDULE


ESTIMATED BOND ISSUANCE COSTS
Bond Discount 0.750% $450,000 ESTIMATED OTHER COSTS
Bond Insurance 0 Reimbursable Election Costs $49,272
Bond Attorney Fee 78,000 Capitalized Interest 0
Financial Consultant Fee 71,050 Other 0
Credit Rating 71,000 TOTAL OTHER COSTS $49,272
Qualification of Bonds 16,000 BOND SIZING
Official Statement Printing & Mailing 2,500 Total Bond Issuance and Other Costs $739,722
Notice of Sale Publication 0 Total Project Expenditures 60,238,450
Treasury Filing Fee(s) 1,000 Total Project, Issuance & Other Costs 60,978,172
Auditor's Consent Fee 0 Less Original Issue Premium 0
Paying Agent Upfront Fee 500 Less Estimated Construction Fund Earnings (978,172)
Municipal Advisory Council Fee 400 Less Other Adjustments 0
TOTAL BOND ISSUANCE COSTS $690,450 AMOUNT OF BOND ISSUE $60,000,000

PROJECT FUND DRAWS AND EARNINGS SECTION


Estimated Expenditures Average Life = 1.27 years
Project Issuance & Project Fund Estimated Projected
Date Expenditures Other Costs Totals Month Payout % Balance Interest Rate Interest Earned
Jun 20 $60,000,000
Jun 20 $500,157 $739,722 $1,239,879 1 2.03% 58,760,121 1.30% $63,657
Jul 20 1,182,731 1,182,731 2 3.97% 57,641,046 1.30% 62,444
Aug 20 373,048 373,048 3 4.58% 57,330,443 1.30% 62,108
Sep 20 412,310 412,310 4 5.26% 56,980,241 1.30% 61,729
Oct 20 574,996 574,996 5 6.20% 56,466,973 1.30% 61,173
Nov 20 1,251,636 1,251,636 6 8.26% 55,276,510 1.30% 59,883
Dec 20 1,581,477 1,581,477 7 10.85% 53,754,916 1.30% 58,234
Jan 21 1,889,979 1,889,979 8 13.95% 51,923,171 1.30% 56,250
Feb 21 2,172,995 2,172,995 9 17.51% 49,806,426 1.30% 53,957
Mar 21 2,426,757 2,426,757 10 21.49% 47,433,626 1.30% 51,386
Apr 21 2,647,928 2,647,928 11 25.84% 44,837,085 1.30% 48,574
May 21 2,833,650 2,833,650 12 30.48% 42,052,008 1.30% 45,556
Jun 21 3,869,620 3,869,620 13 36.83% 38,227,945 1.30% 41,414
Jul 21 3,089,896 3,089,896 14 41.90% 35,179,462 1.30% 38,111
Aug 21 3,157,365 3,157,365 15 47.07% 32,060,208 1.30% 34,732
Sep 21 3,183,306 3,183,306 16 52.29% 28,911,634 1.30% 31,321
Oct 21 3,167,612 3,167,612 17 57.49% 25,775,343 1.30% 27,923
Nov 21 3,110,747 3,110,747 18 62.59% 22,692,519 1.30% 24,584
Dec 21 3,025,626 3,025,626 19 67.55% 19,691,477 1.30% 21,332
Jan 22 2,913,470 2,913,470 20 72.33% 16,799,339 1.30% 18,199
Feb 22 2,763,780 2,763,780 21 76.86% 14,053,759 1.30% 15,225
Mar 22 2,578,452 2,578,452 22 81.09% 11,490,532 1.30% 12,448
Apr 22 2,359,853 2,359,853 23 84.96% 9,143,127 1.30% 9,905
May 22 2,110,782 2,110,782 24 88.42% 7,042,250 1.30% 7,629
Jun 22 2,722,487 2,722,487 25 92.89% 4,327,392 1.30% 4,688
Jul 22 1,534,389 1,534,389 26 95.40% 2,797,691 1.30% 3,031
Aug 22 1,214,498 1,214,498 27 97.39% 1,586,224 1.30% 1,718
Sep 22 878,898 878,898 28 98.84% 709,044 1.30% 768
Oct 22 531,929 531,929 29 99.71% 177,883 1.30% 193
Nov 22 178,076 178,076 30 100.00% 0 1.30% 0
Dec 22 0 0 31 100.00% 0 1.30% 0
Jan 23 0 0 32 100.00% 0 1.30% 0
Feb 23 0 0 33 100.00% 0 1.30% 0
Mar 23 0 0 34 100.00% 0 1.30% 0
Apr 23 0 0 35 100.00% 0 1.30% 0
May 23 0 0 36 100.00% 0 1.30% 0
Jun 23 0 0 37 100.00% 0 1.30% 0
Jul 23 0 0 38 100.00% 0 1.30% 0
Aug 23 0 0 39 100.00% 0 1.30% 0
$60,238,450 $739,722 $60,978,172 $978,172
AW/KB
PQ_LapeerCS_6.5.19 PQ_v1 2020 Sizing 6/6/2019 4:01 PM
PQ_v1 2021
$34,900,000
Lapeer Commuity Schools
2021 SCHOOL BUILDING AND SITE BONDS

BOND SIZING SCHEDULE


ESTIMATED BOND ISSUANCE COSTS
Bond Discount 1.000% $349,000 ESTIMATED OTHER COSTS
Bond Insurance 0 Reimbursable Election Costs $0
Bond Attorney Fee 58,925 Capitalized Interest 0
Financial Consultant Fee 48,460 Other 0
Credit Rating 29,000 TOTAL OTHER COSTS $0
Qualification of Bonds 10,800 BOND SIZING
Official Statement Printing & Mailing 2,500 Total Bond Issuance and Other Costs $500,585
Notice of Sale Publication 0 Total Project Expenditures 34,892,452
Treasury Filing Fee(s) 1,000 Total Project, Issuance & Other Costs 35,393,037
Auditor's Consent Fee 0 Less Original Issue Premium 0
Paying Agent Upfront Fee 500 Less Estimated Construction Fund Earnings (493,037)
Municipal Advisory Council Fee 400 Less Other Adjustments 0
TOTAL BOND ISSUANCE COSTS $500,585 AMOUNT OF BOND ISSUE $34,900,000

PROJECT FUND DRAWS AND EARNINGS SECTION


Estimated Expenditures Average Life = 0.95 years
Project Issuance & Project Fund Estimated Projected
Date Expenditures Other Costs Totals Month Payout % Balance Interest Rate Interest Earned
Nov 21 $34,900,000
Nov 21 $0 $500,585 $500,585 1 1.41% 34,399,415 1.50% $42,999
Dec 21 0 0 2 1.41% 34,442,414 1.50% 43,053
Jan 22 168,111 168,111 3 1.89% 34,317,356 1.50% 42,897
Feb 22 493,289 493,289 4 3.28% 33,866,964 1.50% 42,334
Mar 22 786,080 786,080 5 5.50% 33,123,217 1.50% 41,404
Apr 22 1,425,749 1,425,749 6 9.53% 31,738,872 1.50% 39,674
May 22 2,340,909 2,340,909 7 16.15% 29,437,637 1.50% 36,797
Jun 22 3,094,939 3,094,939 8 24.89% 26,379,495 1.50% 32,974
Jul 22 4,353,812 4,353,812 9 37.19% 22,058,657 1.50% 27,573
Aug 22 4,340,448 4,340,448 10 49.46% 17,745,783 1.50% 22,182
Sep 22 3,917,898 3,917,898 11 60.53% 13,850,067 1.50% 17,313
Oct 22 2,798,391 2,798,391 12 68.43% 11,068,988 1.50% 13,836
Nov 22 1,910,340 1,910,340 13 73.83% 9,172,485 1.50% 11,466
Dec 22 1,436,259 1,436,259 14 77.89% 7,747,691 1.50% 9,685
Jan 23 1,074,096 1,074,096 15 80.92% 6,683,280 1.50% 8,354
Feb 23 846,259 846,259 16 83.31% 5,845,375 1.50% 7,307
Mar 23 564,864 564,864 17 84.91% 5,287,818 1.50% 6,610
Apr 23 423,644 423,644 18 86.11% 4,870,784 1.50% 6,088
May 23 430,353 430,353 19 87.32% 4,446,519 1.50% 5,558
Jun 23 406,592 406,592 20 88.47% 4,045,485 1.50% 5,057
Jul 23 831,217 831,217 21 90.82% 3,219,325 1.50% 4,024
Aug 23 288,450 288,450 22 91.63% 2,934,899 1.50% 3,669
Sep 23 249,520 249,520 23 92.34% 2,689,048 1.50% 3,361
Oct 23 245,503 245,503 24 93.03% 2,446,906 1.50% 3,059
Nov 23 239,362 239,362 25 93.71% 2,210,603 1.50% 2,763
Dec 23 231,145 231,145 26 94.36% 1,982,221 1.50% 2,478
Jan 24 220,923 220,923 27 94.99% 1,763,776 1.50% 2,205
Feb 24 208,782 208,782 28 95.58% 1,557,198 1.50% 1,946
Mar 24 194,826 194,826 29 96.13% 1,364,319 1.50% 1,705
Apr 24 179,174 179,174 30 96.63% 1,186,850 1.50% 1,484
May 24 161,964 161,964 31 97.09% 1,026,370 1.50% 1,283
Jun 24 143,341 143,341 32 97.50% 884,312 1.50% 1,105
Jul 24 598,048 598,048 33 99.19% 287,369 1.50% 359
Aug 24 102,524 102,524 34 99.48% 185,204 1.50% 232
Sep 24 80,684 80,684 35 99.70% 104,752 1.50% 131
Oct 24 58,139 58,139 36 99.87% 46,744 1.50% 58
Nov 24 35,087 35,087 37 99.97% 11,715 1.50% 15
Dec 24 11,730 11,730 38 100.00% 0 1.50% 0
Jan 25 0 0 39 100.00% 0 1.50% 0
$34,892,452 $500,585 $35,393,037 $493,037
AW/KB
PQ_LapeerCS_6.5.19 PQ_v1 2021 Sizing 6/6/2019 4:01 PM
PQ_v1
Series 2020 Series 2021
$94,900,000 Amount: $60,000,000 $34,900,000
Lapeer Commuity Schools TIC: 4.50% 4.75%
County of Lapeer, State of Michigan Dated Date: Jun 1, 20 Nov 1, 21
2020 & 2021 SCHOOL BUILDING AND SITE BONDS First Payment: May 1, 21 < 11 Months May 1, 22
(GENERAL OBLIGATION - UNLIMITED TAX) First Levy: Dec 1, 20 Dec 1, 21
Capitalized Int: $0 $0 Levy Cycle: December Only
ESTIMATED MILLAGE NEEDED TO RETIRE BONDED DEBT Debt/TV[1]: 6.61% 8.60% Millage Impact Interest Factor
Bond Term: 23 yrs., 11 mo. 24 yrs., 6 mo. Projected 4.69 0.85
1:5 Ratio: TRUE TRUE Current 2.75
Average Life: 18.47 18.78 Net Increase 1.94
120% ProjUsefulLife: 45.65 33.83

Existing Series 2020 Series 2021 Total Use of Funds Proposed and Mills Needed Mills Needed
Tax Payment UT Debt Principal Due Interest Interest Due Interest Due Total Debt Principal Due Total Debt Proposed Capitalized on Hand Existing UT Projected Growth New Bond All Qualified
Year Year $38,640,000 May 1 Rate May 1 Nov 1 Service May 1 Service Debt Interest $1,336,172 Debt Tax Base [2] Rate Avg. 3.26 Debt
2018 2019 $3,365,300 $0 4.500% $0 $0 $0 $0 $0 $0 $0 $492,211 $3,857,511 $1,402,731,178 4.57% 2.75
2019 2020 3,361,800 0 4.500% 0 0 0 0 0 0 0 634,143 3,995,943 1,453,070,040 3.59% 2.75
2020 2021 3,361,000 0 4.500% 2,475,000 1,350,000 3,825,000 0 0 3,825,000 0 (183,692) 7,002,308 1,493,029,466 2.75% 2.56 4.69
2021 2022 3,354,625 400,000 4.500% 1,350,000 1,341,000 3,091,000 75,000 1,730,969 4,821,969 0 (981,722) 7,194,872 1,534,087,776 2.75% 3.14 4.69
2022 2023 3,351,875 400,000 4.500% 1,341,000 1,332,000 3,073,000 75,000 1,727,406 4,800,406 0 (759,551) 7,392,731 1,576,275,190 2.75% 3.05 4.69
2023 2024 3,350,000 400,000 4.500% 1,332,000 1,323,000 3,055,000 75,000 1,723,844 4,778,844 0 (537,561) 7,591,283 1,619,622,757 2.75% 2.95 4.69
2024 2025 3,348,750 100,000 4.500% 1,323,000 1,320,750 2,743,750 75,000 1,720,281 4,464,031 0 0 7,812,781 1,664,162,383 2.75% 2.68 4.69
2025 2026 3,347,875 250,000 4.500% 1,320,750 1,315,125 2,885,875 110,000 1,750,888 4,636,763 0 0 7,984,638 1,703,275,707 2.35% 2.72 4.69
2026 2027 3,347,125 355,000 4.500% 1,315,125 1,307,138 2,977,263 220,000 1,853,050 4,830,313 0 0 8,177,438 1,743,308,324 2.35% 2.77 4.69
2027 2028 3,346,250 530,000 4.500% 1,307,138 1,295,213 3,132,350 275,000 1,896,294 5,028,644 0 0 8,374,894 1,784,281,839 2.35% 2.82 4.69
2028 2029 3,340,125 810,000 4.500% 1,295,213 1,276,988 3,382,200 240,000 1,849,063 5,231,263 0 0 8,571,388 1,826,218,368 2.35% 2.86 4.69
2029 2030 3,333,625 1,055,000 4.500% 1,276,988 1,253,250 3,585,238 255,000 1,852,306 5,437,544 0 0 8,771,169 1,869,140,544 2.35% 2.91 4.69
2030 2031 3,272,875 1,275,000 4.500% 1,253,250 1,224,563 3,752,813 360,000 1,942,700 5,695,513 0 0 8,968,388 1,913,071,533 2.35% 2.98 4.69
2031 2032 3,228,625 1,575,000 4.500% 1,224,563 1,189,125 3,988,688 400,000 1,964,650 5,953,338 0 0 9,181,963 1,958,035,046 2.35% 3.04 4.69
2032 2033 3,121,875 1,715,000 4.500% 1,189,125 1,150,538 4,054,663 690,000 2,228,763 6,283,425 0 0 9,405,300 2,004,055,350 2.35% 3.14 4.69
2033 2034 3,014,125 1,955,000 4.500% 1,150,538 1,106,550 4,212,088 900,000 2,401,000 6,613,088 0 0 9,627,213 2,051,157,284 2.35% 3.22 4.69
2034 2035 2,885,875 2,245,000 4.500% 1,106,550 1,056,038 4,407,588 1,090,000 2,543,738 6,951,325 0 0 9,837,200 2,099,366,269 2.35% 3.31 4.69
2035 2036 2,752,750 2,325,000 4.500% 1,056,038 1,003,725 4,384,763 1,550,000 2,941,038 7,325,800 0 0 10,078,550 2,148,708,325 2.35% 3.41 4.69
2036 2037 2,639,375 2,610,000 4.500% 1,003,725 945,000 4,558,725 1,800,000 3,111,475 7,670,200 0 0 10,309,575 2,199,210,082 2.35% 3.49 4.69
2037 2038 0 5,505,000 4.500% 945,000 821,138 7,271,138 2,065,000 3,284,681 10,555,819 0 0 10,555,819 2,250,898,798 2.35% 4.69 4.69
2038 2039 0 5,730,000 4.500% 821,138 692,213 7,243,350 2,440,000 3,552,688 10,796,038 0 0 10,796,038 2,303,802,370 2.35% 4.69 4.69
2039 2040 0 5,955,000 4.500% 692,213 558,225 7,205,438 2,855,000 3,841,931 11,047,369 0 0 11,047,369 2,357,949,350 2.35% 4.69 4.69
2040 2041 0 6,180,000 4.500% 558,225 419,175 7,157,400 3,200,000 4,043,125 11,200,525 0 0 11,200,525 2,413,368,964 2.35% 4.64 4.64
2041 2042 0 6,205,000 4.500% 419,175 279,563 6,903,738 3,200,000 3,891,125 10,794,863 0 0 10,794,863 2,470,091,123 2.35% 4.37 4.37
2042 2043 0 6,205,000 4.500% 279,563 139,950 6,624,513 3,200,000 3,739,125 10,363,638 0 0 10,363,638 2,528,146,439 2.35% 4.10 4.10
2043 2044 0 6,220,000 4.500% 139,950 0 6,359,950 3,200,000 3,587,125 9,947,075 0 0 9,947,075 2,587,566,248 2.35% 3.84 3.84
2044 2045 0 0 4.500% 0 0 0 3,225,000 3,459,531 3,459,531 0 0 3,459,531 2,648,382,619 2.35% 1.31 1.31
2045 2046 0 0 4.500% 0 0 0 3,325,000 3,403,969 3,403,969 0 0 3,403,969 2,710,628,376 2.35% 1.26 1.26
2046 2047 0 0 4.500% 0 0 0 0 0 0 0 0 0 2,774,337,115 2.35% 0.00
$61,123,850 $60,000,000 $26,175,263 $23,700,263 $109,875,525 $34,900,000 $66,040,763 $175,916,288 $0 ($1,336,172) $235,703,966

[1] Includes $38,640,000 of Existing UT Debt and $1,705,000 of Existing LTNQ Debt
[2] Includes $11,886,008 of equivalent IFT valuations & less DDA/TIFA debt captures of $0 for 2018. AW/KB

PQ_LapeerCS_6.5.19 PQ_v1 6/6/2019 4:01 PM


Lapeer Commuity Schools
County of Lapeer, State of Michigan
EXISTING DEBT BEFORE ADDITIONAL BONDING

2013 LTGO School Building and Site Bonds 2014 LTGO Building and Site Bonds
Tax-Type: Limited Tax Tax-Type: Limited Tax
Original Amount: $775,000 Original Amount: $500,000
Net Interest Cost: 3.353% Net Interest Cost: 2.600%
Call Date: Non-Callable Call Date: Non-Callable
Voter Approved Before 2015: No Voter Approved Before 2015: No
Dated: 12/04/2013 Dated: 06/16/2014

Levy Payment Principal Due Interest Interest Due Interest Due Total Debt Principal Due Interest Interest Due Interest Due Total Debt
Year Year May 1 Rate May 1 Nov 1 Service May 1 Rate May 1 Nov 1 Service
2018 2019 $50,000 1.720% $9,344 $8,914 $68,257 $30,000 2.600% $5,005 $4,615 $39,620
2019 2020 50,000 3.070% 8,914 8,146 67,060 30,000 2.600% 4,615 4,225 38,840
2020 2021 55,000 3.070% 8,146 7,302 70,448 30,000 2.600% 4,225 3,835 38,060
2021 2022 55,000 3.070% 7,302 6,458 68,759 35,000 2.600% 3,835 3,380 42,215
2022 2023 60,000 3.070% 6,458 5,537 71,994 35,000 2.600% 3,380 2,925 41,305
2023 2024 60,000 3.070% 5,537 4,616 70,152 35,000 2.600% 2,925 2,470 40,395
2024 2025 60,000 3.620% 4,616 3,530 68,145 35,000 2.600% 2,470 2,015 39,485
2025 2026 65,000 3.620% 3,530 2,353 70,883 35,000 2.600% 2,015 1,560 38,575
2026 2027 65,000 3.620% 2,353 1,177 68,530 40,000 2.600% 1,560 1,040 42,600
2027 2028 65,000 3.620% 1,177 0 66,177 40,000 2.600% 1,040 520 41,560
2028 2029 0 0.000% 0 0 0 40,000 2.600% 520 0 40,520
2029 2030 0 0.000% 0 0 0 0 0.000% 0 0 0
2030 2031 0 0.000% 0 0 0 0 0.000% 0 0 0
2031 2032 0 0.000% 0 0 0 0 0.000% 0 0 0
2032 2033 0 0.000% 0 0 0 0 0.000% 0 0 0
2033 2034 0 0.000% 0 0 0 0 0.000% 0 0 0
2034 2035 0 0.000% 0 0 0 0 0.000% 0 0 0
2035 2036 0 0.000% 0 0 0 0 0.000% 0 0 0
2036 2037 0 0.000% 0 0 0 0 0.000% 0 0 0
2037 2038 0 0.000% 0 0 0 0 0.000% 0 0 0

Totals: $585,000 $57,373 $48,030 $690,403 $385,000 $31,590 $26,585 $443,175

PQ_LapeerCS_6.5.19, ExDebt Before 6/6/2019, 4:01 PM


Lapeer Commuity Schools
County of Lapeer, State of Michigan
EXISTING DEBT BEFORE ADDITIONAL BONDING

2015 LTGO School Building and Site 2016 Refunding Bonds (2007)
Tax-Type: Limited Tax Tax-Type: Unlimited Tax Qualified
Original Amount: $995,000 Original Amount: $40,075,000
Net Interest Cost: 3.691% Net Interest Cost: 4.972%
Call Date: 05/01/2025 Call Date: 05/01/2026
Voter Approved Before 2015: No Voter Approved Before 2015: Yes
Dated: 10/15/2015 Dated: 06/23/2016 TOTAL UTQ TOTAL LT

Levy Payment Principal Due Interest Interest Due Interest Due Total Debt Principal Due Interest Interest Due Interest Due Total Debt Total Debt Total Debt
Principal Principal
Year Year May 1 Rate May 1 Nov 1 Service May 1 Rate May 1 Nov 1 Service Service Service

2018 2019 $60,000 3.000% $15,356 $14,456 $89,813 $1,435,000 4.000% $979,500 $950,800 $3,365,300 $1,435,000 $3,365,300 $140,000 $197,690
2019 2020 65,000 3.000% 14,456 13,481 92,938 1,490,000 4.000% 950,800 921,000 3,361,800 1,490,000 3,361,800 145,000 198,837
2020 2021 65,000 3.000% 13,481 12,506 90,988 1,550,000 4.000% 921,000 890,000 3,361,000 1,550,000 3,361,000 150,000 199,495
2021 2022 70,000 3.000% 12,506 11,456 93,963 1,615,000 5.000% 890,000 849,625 3,354,625 1,615,000 3,354,625 160,000 204,937
2022 2023 70,000 3.000% 11,456 10,406 91,863 1,695,000 5.000% 849,625 807,250 3,351,875 1,695,000 3,351,875 165,000 205,162
2023 2024 70,000 3.125% 10,406 9,313 89,719 1,780,000 5.000% 807,250 762,750 3,350,000 1,780,000 3,350,000 165,000 200,266
2024 2025 75,000 3.500% 9,313 8,000 92,313 1,870,000 5.000% 762,750 716,000 3,348,750 1,870,000 3,348,750 170,000 199,943
2025 2026 75,000 4.000% 8,000 6,500 89,500 1,965,000 5.000% 716,000 666,875 3,347,875 1,965,000 3,347,875 175,000 198,958
2026 2027 80,000 4.000% 6,500 4,900 91,400 2,065,000 5.000% 666,875 615,250 3,347,125 2,065,000 3,347,125 185,000 202,530
2027 2028 80,000 4.000% 4,900 3,300 88,200 2,170,000 5.000% 615,250 561,000 3,346,250 2,170,000 3,346,250 185,000 195,937
2028 2029 80,000 4.000% 3,300 1,700 85,000 2,275,000 5.000% 561,000 504,125 3,340,125 2,275,000 3,340,125 120,000 125,520
2029 2030 85,000 4.000% 1,700 0 86,700 2,385,000 5.000% 504,125 444,500 3,333,625 2,385,000 3,333,625 85,000 86,700
2030 2031 0 0.000% 0 0 0 2,445,000 5.000% 444,500 383,375 3,272,875 2,445,000 3,272,875 0 0
2031 2032 0 0.000% 0 0 0 2,525,000 5.000% 383,375 320,250 3,228,625 2,525,000 3,228,625 0 0
2032 2033 0 0.000% 0 0 0 2,545,000 5.000% 320,250 256,625 3,121,875 2,545,000 3,121,875 0 0
2033 2034 0 0.000% 0 0 0 2,565,000 5.000% 256,625 192,500 3,014,125 2,565,000 3,014,125 0 0
2034 2035 0 0.000% 0 0 0 2,565,000 5.000% 192,500 128,375 2,885,875 2,565,000 2,885,875 0 0
2035 2036 0 0.000% 0 0 0 2,560,000 5.000% 128,375 64,375 2,752,750 2,560,000 2,752,750 0 0
2036 2037 0 0.000% 0 0 0 2,575,000 5.000% 64,375 0 2,639,375 2,575,000 2,639,375 0 0
2037 2038 0 0.000% 0 0 0 0 0.000% 0 0 0 0 0 0 0

Totals: $875,000 $111,375 $96,019 $1,082,394 $40,075,000 $11,014,175 $10,034,675 $61,123,850 $40,075,000 $61,123,850 $1,845,000 $2,215,972

AW 5/30/19

PQ_LapeerCS_6.5.19, ExDebt Before 6/6/2019, 4:01 PM


BEFORE ADDITIONAL BONDING

Lapeer Commuity Schools


County of Lapeer, State of Michigan
ESTIMATED MILLAGE NEEDED TO RETIRE BONDED DEBT BEFORE ADDITIONAL BONDING

Debt/TV[2]: 3.01% 2018 Debt Levy: 2.75


Collection Cycle
December Levy 100% Total Levy: 2.75

Existing Unlimited Tax Debt & Mills


Use of Funds Delinquency Exempt Pers. Mills
Levy Payment Projected Tax Growth Existing UT on Hand Allowance Property Needed All
Year Year Base[1] Rate Payments $1,336,172 0.00% Receipts[3] Net UT Payments Debt
2018 2019 $1,402,731,178 4.57% $3,365,300 $492,211 $0 $0 $3,857,511 2.75
2019 2020 1,453,070,040 3.59% 3,361,800 634,143 0 0 3,995,943 2.75
2020 2021 1,493,029,466 2.75% 3,361,000 (180,847) 0 0 3,180,153 2.13
2021 2022 1,534,087,776 2.75% 3,354,625 (439,858) 0 0 2,914,767 1.90
2022 2023 1,576,275,190 2.75% 3,351,875 (356,952) 0 0 2,994,923 1.90
2023 2024 1,619,622,757 2.75% 3,350,000 (272,717) 0 0 3,077,283 1.90
2024 2025 1,664,162,383 2.75% 3,348,750 (186,841) 0 0 3,161,909 1.90
2025 2026 1,703,275,707 2.35% 3,347,875 (111,651) 0 0 3,236,224 1.90
2026 2027 1,743,308,324 2.35% 3,347,125 (122,005) 0 0 3,225,120 1.85
2027 2028 1,784,281,839 2.35% 3,346,250 (134,543) 0 0 3,211,707 1.80
2028 2029 1,826,218,368 2.35% 3,340,125 (657,111) 0 0 2,683,014 1.47
2029 2030 1,869,140,544 2.35% 3,333,625 0 0 0 3,333,625 1.78
2030 2031 1,913,071,533 2.35% 3,272,875 0 0 0 3,272,875 1.71
2031 2032 1,958,035,046 2.35% 3,228,625 0 0 0 3,228,625 1.65
2032 2033 2,004,055,350 2.35% 3,121,875 0 0 0 3,121,875 1.56
2033 2034 2,051,157,284 2.35% 3,014,125 0 0 0 3,014,125 1.47
2034 2035 2,099,366,269 2.35% 2,885,875 0 0 0 2,885,875 1.37
2035 2036 2,148,708,325 2.35% 2,752,750 0 0 0 2,752,750 1.28
2036 2037 2,199,210,082 2.35% 2,639,375 0 0 0 2,639,375 1.20
2037 2038 2,250,898,798 2.35% 0 0 0 0 0 0.00

$61,123,850 ($1,336,172) $0 $0 $59,787,678


2019 Debt fund balance is estimated from 2018
[1] Includes $11,886,008 of equivalent IFT valuations & less DDA/TIFA debt captures of $0 for 2018.
[2] Includes principal outstanding: $40,075,000 of unlimited tax bonds and $1,845,000 of limited tax bonds
[3] Based on $0 of Exempt Personal Property for 2018

PQ_LapeerCS_6.5.19, Before Mills 6/6/2019, 4:01 PM


Lapeer Commuity Schools
County of Lapeer, State of Michigan
Taxable Value History

Exempt Adjusted
Levy Taxable Personal Adjusted T.V. T.V. 5 Year 20 Year
Year Value Property Total Change Change Average Average
2019 $1,442,372,347 $0 $1,442,372,347 3.70% 3.70% 3.25% 2.35%
2018 1,390,845,170 0 1,390,845,170 5.12% 4.57% 2.54% 2.48%
2017 1,323,140,354 6,870,620 1,330,010,974 4.84% 3.24% 1.59%
2016 1,262,075,410 26,148,349 1,288,223,759 0.31% 2.39% (0.08)%
2015 1,258,186,994 0 1,258,186,994 2.32% 2.32% (1.85)%
2014 1,229,678,379 0 1,229,678,379 0.20% 0.20% (3.88)%
2013 1,227,209,389 0 1,227,209,389 (0.18)% (0.18)% (4.25)%
2012 1,229,451,486 0 1,229,451,486 (5.11)% (5.11)% (3.76)%
2011 1,295,596,849 0 1,295,596,849 (6.46)% (6.46)% (1.89)%
2010 1,385,091,369 0 1,385,091,369 (7.86)% (7.86)% 0.89%
2009 1,503,231,061 0 1,503,231,061 (1.64)% (1.64)% 3.71%
2008 1,528,364,653 0 1,528,364,653 2.28% 2.28% 5.19%
2007 1,494,364,936 0 1,494,364,936 4.25% 4.25% 5.63%
2006 1,433,419,687 0 1,433,419,687 7.45% 7.45% 6.16%
2005 1,334,044,687 0 1,334,044,687 6.24% 6.24% 6.29%
2004 1,255,663,775 0 1,255,663,775 5.75% 5.75% 6.32%
2003 1,187,443,771 0 1,187,443,771 4.46% 4.46% 6.42%
2002 1,136,790,949 0 1,136,790,949 6.91% 6.91%
2001 1,063,298,154 0 1,063,298,154 8.11% 8.11%
2000 983,546,724 0 983,546,724 6.39% 6.39%
1999 924,470,038 0 924,470,038 6.23% 6.23%
1998 870,290,740 0 870,290,740

PQ_LapeerCS_6.5.19, TV History 6/6/2019, 4:01 PM


3881, Page 3

Enrollment Projections

Lapeer Community Schools 44 - 010

Complete this form after acquiring an enrollment projection report from an approved enrollment projection provider.
Official enrollment projections should be based on the most recent fall membership count.

Prepared By Barton Malow Company

Source Stanfred Consultants

Explanation of Method Selected


Using the 1.5 Projections, expecting enrollment to fall between the Most Likely and Low, much closer
to the Most Likely -- Three times the Most Likely, plus the Low, divided by Four.

Subtotals by Grade:
2013-2014 2018-2019 2023-2024 (Col 4 - Col 3) / Col 3

Preceding 5- Projected
Current Projected 5-Year
Year Enrollment Change
Enrollment Enrollment
Grade Enrollment (%)
1 2 3 4 5
K 312 372 19.15%
1 283 293 3.45%
2 294 289 -1.87%
3 327 287 -12.39%
4 327 306 -6.42%
5 323 289 -10.53%
6 374 311 -16.91%
7 368 283 -23.23%
8 391 314 -19.76%
9 456 331 -27.36%
10 412 329 -20.27%
11 439 307 -30.07%
12 460 351 -23.70%
Total 5,530 4,766 4,059 -14.83%

Subtotals by School District's Grade Configuration: *


K-4 1,866 1,546 -17.18%
5-8 1,133 1,196 5.56%
9-12 1,767 1,318 -25.42%
General Ed Total 5,530 4,766 4,059 -14.83%

*Examples of possible grade configurations


K-5 K-8 K - 12
6-8 5-6 5-8
9 - 12 10 - 12 7 - 12

Non-general ed student count should not be included in the general ed student count listed above unless discussed with
and determined by your enrollment service provider.
3881, Page 4

Project Sheet

Turril Elementary School Project No. 1


Description of Series 1 n/a

Description of Series 2 paving, remodeling, install site lighting, upgrade technology infrastructure, purchase
technology equipment, and purchase furniture

Instructional Tech Description purchase student & teacher devices

Site Work Description add parking, repave parking, improve site drainage

Construction Cost Per Square Foot


New Construction Square Ft 0 Cost per Sq Ft $ -
New Addition Square Ft. 0 Cost per Sq Ft $ -

Statement describing any existing environmental or usability problems the proposed project will address. (ex:
asbestos, energy use, or ADA requirements)
upgrade site lighting for energy savings

Estimated Cost of Proposed Construction Project


Column1 Series 1 Series 2 n/a Total
New Construction $0 $0 $0 $0
Remodeling $0 $378,485 $0 $378,485
Construction Contingencies $0 $50,408 $0 $50,408
Instructional Technology $0 $71,710 $0 $71,710
Loose Furnishing/Equipment $0 $13,656 $0 $13,656
Buses $0 $0 $0 $0
Site Work $0 $261,885 $0 $261,885
Site Acquisition $0 $0 $0 $0
Architectural Fees and Costs $0 $44,051 $0 $44,051
CM Fees and Costs $0 $42,825 $0 $42,825
Estimated Costs $0 $863,020 $0 $863,020

Certificate by Registered Architect


I certify that I have assessed the conditions relative to this facility and the details of the proposed project(s) described above
and the attached detail relative to the construction project(s) are true and correct to the best of my knowledge and belief.

6/6/2019 French Associates, 1301031750


Signature Date Firm Name and License Number

Paul A. Corneliussen, AIA paulc@frenchaia.com (248) 656-1377


Printed Name E-mail Address Phone Number
LAPEER COMMUNITY SCHOOLS Year Built: 1959
2019 FACILITY IMPROVEMENT PLANNING Building Size: 44,749
TURRIL ELEMENTARY SCHOOL Site Size: 15.0
785 Elm Street, Lapeer, MI Grades: PreK-K (currently K-5)
PROJECT WORK LIST Classrooms: 16 Date: 5/30/19

Category Total Total


Subcategory Unit Direct w/ G.C. & w/ Indirect
Work Item Description Qty. Unit Cost Cost Escalation Costs Comments Priority Series

Site Work
Paving Work
construct new parking area 12,000 sqft 6.00 $72,000 $82,610 $99,442 20 staff spaces + circulation 1 2
repave existing west drive and parking 32,500 sqft 4.50 $146,250 $167,802 $201,991 1 2
Paving Work Subtotal: $250,412 $301,433
Site Improvements
improve drainage at northeast area 1 lpsm 10,000.00 $10,000 $11,474 $13,811 1 2
Site Improvements Subtotal: $11,474 $13,811
Site Work Subtotal: $261,885 $315,244

Remodeling Work
Architectural Work
replace corridor exterior door systems 220 sqft 100.00 $22,000 $25,242 $30,385 2 locations 1 2
remodel toilet rooms 350 sqft 175.00 $61,250 $70,276 $84,595 1 2
Flooring
abate & replace vinyl asbestos flooring 10,000 sqft 5.00 $50,000 $57,368 $69,057 1 2
Flooring Subtotal: $57,368 $69,057
Architectural Work Subtotal: $152,886 $184,036
Electrical
Lighting
install site lighting 10 each 7,500.00 $75,000 $86,052 $103,585 1 2
Electrical Work Subtotal: $86,052 $103,585
Construction Subtotal: $238,938 $287,622
Technology Infrastructure
data cabling for renovations 1 each 5,000.00 $5,000 $5,737 $6,737 1 2
network switches - core 1 each 8,000.00 $8,000 $9,179 $10,779 1 2
network switches - edge 5 each 3,250.00 $16,250 $18,645 $21,895 1 2
replace rack UPS's 1 each 2,000.00 $2,000 $2,295 $2,695 1 2
upgrade wireless infrastructure 44,749 sqft 0.50 $22,375 $25,672 $30,147 1 2
upgrade phone system 1 lpsm 25,000.00 $25,000 $28,684 $33,684 1 2
Technology Infrastructure Subtotal: $90,211 $105,937
Technology Safety & Security
install security cameras 20 each 1,200.00 $24,000 $27,537 $32,337 1 2
add access control 3 each 3,000.00 $9,000 $10,326 $12,126 1 2
upgrade PA system 1 lpsm 10,000.00 $10,000 $11,474 $13,474 replace headend equip only 1 2
Safety Infrastructure Subtotal: $49,337 $57,937
Technology/Safety Infrastructure Work Subtotal: $139,547 $163,874
Remodeling Work Subtotal: $378,485 $451,495

Instructional Technology Equipment


Computers and Mobile Devices
purchase teacher computers 40 each 1,250.00 $50,000 $57,368 $65,220 1 2
purchase student desktops 10 each 1,250.00 $12,500 $14,342 $16,305 1 2
Instructional Technology Subtotal: $71,710 $81,525

Furniture, Furnishings & Equipment (F,F,&E)


Non-Instructional Technology Equipment
purchase admin staff computers 5 each 1,400.00 $7,000 $8,032 $9,131 1 2
Non-Instructional Tech Equip Subtotal: $8,032 $9,131
Furniture, Fixtures & Equipment
purchase furniture 1 allo 5,000.00 $5,000 $5,624 $5,624 1 2
F, F, & E Subtotal: $5,624 $5,624
F,F,&E + Non-Inst Tech Equip Subtotal: $13,656 $14,755

Total: $725,736 $863,020


Contingency: $50,408
Design Consultant: $44,051
C.M. Costs: $42,825
BUILDING TOTAL: $863,020
3881, Page 5

Building Utilization

Turril Elementary School Project No. 1

Current Grade Structure K-5


Proposed Grade Structure preK-K

1. List the number of teaching station in appropriate column.


2. Calculate total capacity using the applicable capacity factor.
3. Enter five (5) year projected enrollment.
4. Calculate building utilization rate.
5. Attach floor plan of the building. Show the rooms and category (existing, proposed new, closed).
6. Number the teaching stations in consecutive order.

List # of
Teaching Capacity
Existing Stations Factor Capacity
(K-2) Lower Elementary 16 20 320
(3-5) Upper Elementary 0 25 0
(6-8) Middle School 0 22.5 0
(9-12) High School 0 21.25 0

Subtotal 16 320

List # of List # of
Teaching Capacity Facility to be Teaching Capacity
Proposed New Stations Factor Capacity Closed Stations Factor Capacity
(K-2) Lower Elementary 0 20 0 (K-2) Lower Elementary 0 20 0
(3-5) Upper Elementary 0 25 0 (3-5) Upper Elementary 0 25 0
(6-8) Middle School 0 22.5 0 (6-8) Middle School 0 22.5 0
(9-12) High School 0 21.25 0 (9-12) High School 0 21.25 0
Subtotal 0 0 Total 0 0

Total 16 320

Projected 5-Year Enrollment 372

Utilization Percentage 116%


(Projected 5-Year Enrollment / Total Capacity)

Please transfer applicable information to the Utilization Summary on Page 6 of the application.
PreK 1 2
K K 5
work work K
6
3 4 K
PreK K K
7
K
8
work K

9
K
10
K
11
K
S.E. S.E. 12
K
Gym/
Cafe
16 15 14 13

Turrill Elementary – CR Summary


Grade No. of Capacity Total
Level Rooms per room (students)

Pre-K 4
K 16 20 320
FLOOR PLAN
TOTAL 16 320
3881, Page 4

Project Sheet

New Lapeer Elementary School (current High School) Project No. 2


Description of Series 1 n/a

Description of Series 2 site work, replace roof, interior renovations, mechanical improvements, electrical work,
upgrade technology infrastructure, purchase technology equipment, and purchase
furniture

Instructional Tech Description purchase student & teacher devices

Site Work Description repave parking lot, install playground equipment and replace grandstands with asphalt
play pad

Construction Cost Per Square Foot


New Construction Square Ft 0 Cost per Sq Ft $ -
New Addition Square Ft. 0 Cost per Sq Ft $ -

Statement describing any existing environmental or usability problems the proposed project will address. (ex:
asbestos, energy use, or ADA requirements)
upgrade drinking fountains for ADA, upgrade temperature controls for energy savings,

Estimated Cost of Proposed Construction Project


Column1 Series 1 Series 2 n/a Total
New Construction $0 $0 $0 $0
Remodeling $0 $5,248,662 $0 $5,248,662
Construction Contingencies $0 $463,062 $0 $463,062
Instructional Technology $0 $215,130 $0 $215,130
Loose Furnishing/Equipment $0 $29,719 $0 $29,719
Buses $0 $0 $0 $0
Site Work $0 $1,127,282 $0 $1,127,282
Site Acquisition $0 $0 $0 $0
Architectural Fees and Costs $0 $430,127 $0 $430,127
CM Fees and Costs $0 $426,391 $0 $426,391
Estimated Costs $0 $7,940,373 $0 $7,940,373

Certificate by Registered Architect


I certify that I have assessed the conditions relative to this facility and the details of the proposed project(s) described above
and the attached detail relative to the construction project(s) are true and correct to the best of my knowledge and belief.

6/6/2019 French Associates, 1301031750


Signature Date Firm Name and License Number

Paul A. Corneliussen, AIA paulc@frenchaia.com (248) 656-1377


Printed Name E-mail Address Phone Number
LAPEER COMMUNITY SCHOOLS Year Built: 1975
2019 FACILITY IMPROVEMENT PLANNING Building Size: 165,300
LAPEER HIGH SCHOOL (FUTURE 1-4 ELEMENTARY) Site Size: 69.2
933 South Saginaw Street, Lapeer MI 48446 Grades: 1-4 (currently 10-12)
PROJECT WORK LIST Classrooms: 48 Date: 5/30/19

Category Total Total


Subcategory Unit Direct w/ G.C. & w/ Indirect
Work Item Description Qty. Unit Cost Cost Escalation Costs Comments Priority Series

Site Work
Paving Work
repave north parking lot and drive 85,000 sqft 4.50 $382,500 $438,866 $528,285 1 2
Paving Work Subtotal: $438,866 $528,285
Site Improvements
install playground equipment 1 allo 400,000.00 $400,000 $458,945 $552,454 including surfacing 1 2
replace bleachers with basketball court 1 allo 200,000.00 $200,000 $229,472 $276,227 1 2
Site Improvements Subtotal: $688,417 $828,682
Site Work Subtotal: $1,127,282 $1,356,966

Remodeling Work
Roofing Work
replace roofing 165,300 sqft 12.00 $1,983,600 $2,275,906 $2,739,622 entire roof 20 years old in 2020 1 2
Roofing Work Subtotal: $2,275,906 $2,739,622
Architectural Work
replace corridor doors in music wing 10 each 3,000.00 $30,000 $34,421 $41,434 1 2
replace corridor exterior door systems 900 sqft 100.00 $90,000 $103,263 $124,302 7 locations 1 2
reconstruct entry door wall by weight rm 1 lpsm 10,000.00 $10,000 $11,474 $13,811 replace lintel / reconstruct wall 1 2
replace folding partitions w/ solid walls 9 each 4,500.00 $40,500 $46,468 $55,936 rework ceiling 1 2
replace locker room ceiling tile 3,000 sqft 5.00 $15,000 $17,210 $20,717 humidity resistant type 1 2
replace corridor lay-in ceiling tiles 15,000 sqft 4.00 $60,000 $68,842 $82,868 1 2
replace media center ceiling 5,200 sqft 5.00 $26,000 $29,831 $35,910 1 2
replace chalkboards w/ white boards 45 each 2,000.00 $90,000 $103,263 $124,302 1 2
replace recessed lockers 930 each 150.00 $139,500 $160,057 $192,668 1 2
replace freestanding lockers 320 each 150.00 $48,000 $55,073 $66,295 1 2
install gym divider curtain 1 lpsm 15,000.00 $15,000 $17,210 $20,717 1 2
renovate restrooms 8 each 55,000.00 $440,000 $504,839 $607,700 1 2
paint renovated areas 75,000 sqft 1.25 $93,750 $107,565 $129,482 1 2
create office spaces 1 lpsm 80,000.00 $80,000 $91,789 $110,491 1 2
renovate space for classroom 1 lpsm 89,000.00 $89,000 $102,115 $122,921 1 2
infill overhead doors in shop area 2 each 12,500.00 $25,000 $28,684 $34,528 1 2
add ceilings in old shops/locker rooms 10,000 sqft 5.00 $50,000 $57,368 $69,057 convert to classrooms 1 2
split shop/locker into classrooms 8 each 15,000.00 $120,000 $137,683 $165,736 1 2
Flooring
replace select classroom flooring 15,000 sqft 6.00 $90,000 $103,263 $124,302 1 2
Flooring Subtotal: $103,263 $124,302
Architectural Work Subtotal: $1,780,418 $2,143,178
Mechanical
Plumbing
address plumbing issues at science rooms 1 allo 10,000.00 $10,000 $11,474 $13,811 need to investigate issue 1 2
replace drinking fountains w/ADA type 6 each 5,000.00 $30,000 $34,421 $41,434 w/ bottle fill station 1 2
HVAC system
replace air-conditioning unit 1 lpsm 250,000.00 $250,000 $286,840 $345,284 chiller 1 2
remove dust collection system in shop 1 lpsm 2,000.00 $2,000 $2,295 $2,762 no longer needed 1 2
add A/C to select rooms 1 lpsm 100,000.00 $100,000 $114,736 $138,114 105, 103, 101, 91, 93, locker 1 2
adjust HVAC system for split rooms 15,000 sqft 6.00 $90,000 $103,263 $124,302 1 2
Integrated Automation
upgrade temperature control panel 1 allo 25,000.00 $25,000 $28,684 $34,528 1 2
Mechanical Work Subtotal: $581,712 $700,236
Electrical
Lighting
adjust lighting/switching in select rooms 15,000 sqft 3.00 $45,000 $51,631 $62,151 to divide rooms 1 2
Electronic Safety
upgrade fire alarm system 165,300 sqft 0.75 $123,975 $142,244 $171,226 1 2
Electrical Work Subtotal: $193,875 $233,377
Construction Subtotal: $4,831,911 $5,816,413
Technology Infrastructure
data cabling for renovations 1 each 20,000.00 $20,000 $22,947 $26,948 1 2
create new IDF 1 each 7,500.00 $7,500 $8,605 $10,105 1 2
network switches - core 1 each 22,000.00 $22,000 $25,242 $29,642 1 2
LAPEER COMMUNITY SCHOOLS Year Built: 1975
2019 FACILITY IMPROVEMENT PLANNING Building Size: 165,300
LAPEER HIGH SCHOOL (FUTURE 1-4 ELEMENTARY) Site Size: 69.2
933 South Saginaw Street, Lapeer MI 48446 Grades: 1-4 (currently 10-12)
PROJECT WORK LIST Classrooms: 48 Date: 5/30/19

Category Total Total


Subcategory Unit Direct w/ G.C. & w/ Indirect
Work Item Description Qty. Unit Cost Cost Escalation Costs Comments Priority Series

network switches - edge 15 each 3,250.00 $48,750 $55,934 $65,685 1 2


replace rack UPS's 5 each 2,000.00 $10,000 $11,474 $13,474 1 2
upgrade wireless infrastructure 165,300 sqft 0.50 $82,650 $94,829 $111,361 1 2
upgrade phone system 1 lpsm 40,000.00 $40,000 $45,894 $53,895 1 2
upgrade clock system 165,300 sqft 0.25 $41,325 $47,415 $55,680 GPS system 1 2
Technology Infrastructure Subtotal: $312,340 $366,789
Technology Safety & Security
install security cameras 40
each 1,200.00 $48,000 $55,073 $64,674 1 2
add access control 5
each 3,000.00 $15,000 $17,210 $20,211 1 2
access control headend 2
each 4,000.00 $8,000 $9,179 $10,779 1 2
upgrade PA system 1
lpsm 20,000.00 $20,000 $22,947 $26,948 includes renovation area 1 2
Safety Infrastructure Subtotal: $104,410 $122,611
Technology/Safety Infrastructure Work Subtotal: $416,750 $489,400
Remodeling Work Subtotal: $5,248,662 $6,305,813

Instructional Technology Equipment


Computers and Mobile Devices
purchase teacher computers 65 each 1,250.00 $81,250 $93,223 $105,983 1 2
purchase student desktops 85 each 1,250.00 $106,250 $121,907 $138,593 1 2
Instructional Technology Subtotal: $215,130 $244,576

Furniture, Furnishings & Equipment (F,F,&E)


Non-Instructional Technology Equipment
purchase admin staff computers 15 each 1,400.00 $21,000 $24,095 $27,393 1 2
Non-Instructional Tech Equip Subtotal: $24,095 $27,393
Furniture, Fixtures & Equipment
purchase furniture 1 allo 5,000.00 $5,000 $5,624 $5,624 1 2
F, F, & E Subtotal: $5,624 $5,624
F,F,&E + Non-Inst Tech Equip Subtotal: $29,719 $33,017
Total: $6,620,793 $7,940,373
Contingency: $463,062
Design Consultant: $430,127
C.M. Costs: $426,391
BUILDING TOTAL: $7,940,373
3881, Page 5

Building Utilization

New Lapeer Elementary School (current High School) Project No. 2

Current Grade Structure 10-12


Proposed Grade Structure 1-4

1. List the number of teaching station in appropriate column.


2. Calculate total capacity using the applicable capacity factor.
3. Enter five (5) year projected enrollment.
4. Calculate building utilization rate.
5. Attach floor plan of the building. Show the rooms and category (existing, proposed new, closed).
6. Number the teaching stations in consecutive order.

List # of
Teaching Capacity
Existing Stations Factor Capacity
(K-2) Lower Elementary 24 20 480
(3-5) Upper Elementary 24 25 600
(6-8) Middle School 0 22.5 0
(9-12) High School 0 21.25 0

Subtotal 48 1,080

List # of List # of
Teaching Capacity Facility to be Teaching Capacity
Proposed New Stations Factor Capacity Closed Stations Factor Capacity
(K-2) Lower Elementary 0 20 0 (K-2) Lower Elementary 0 20 0
(3-5) Upper Elementary 0 25 0 (3-5) Upper Elementary 0 25 0
(6-8) Middle School 0 22.5 0 (6-8) Middle School 0 22.5 0
(9-12) High School 0 21.25 0 (9-12) High School 0 21.25 0
Subtotal 0 0 Total 0 0

Total 48 1,080

Projected 5-Year Enrollment 1,174

Utilization Percentage 109%


(Projected 5-Year Enrollment / Total Capacity)

Please transfer applicable information to the Utilization Summary on Page 6 of the application.
Music
Stage

W.L. Aud.
43
42
44
S.E.

45 41
Sci.
46
40 Sci.
47 25
39 36
48 26 22
38 35 27
37 34 23
S.E. 21
4th Grade 33 24
28 20
C.L.
19 C.L.
Gym Robotics
29 S.E.
M.C. 30 18 Cafe
31 17 Off.
32 16 Art
3rd Grade 15 Art
S.E. 12 11
14 10
13
New Elementary (current HS) – CR Summary 5 6 7 9
Kit.
8
Grade No. of Capacity Total 2nd Grade 1 4 Off.
2 3
Level Rooms per room (students)

1-2 24 20 480 1st Grade


3-4 24 25 600
FLOOR PLAN
TOTAL 48 1,080
3881, Page 4

Project Sheet

Rolland-Warner Middle School (future Intermediate School) Project No. 3


Description of Series 1 n/a

Description of Series 2 replace sidewalks, interior renovations, upgrade mechanical system, upgrade technology
infrastructure, purchase technology equipment and purchase furniture

Instructional Tech Description purchase student & teacher devices

Site Work Description replace sidewalks

Construction Cost Per Square Foot


New Construction Square Ft 0 Cost per Sq Ft $ -
New Addition Square Ft. 0 Cost per Sq Ft $ -

Statement describing any existing environmental or usability problems the proposed project will address. (ex:
asbestos, energy use, or ADA requirements)
upgrade geo-thermal system for energy savings

Estimated Cost of Proposed Construction Project


Column1 Series 1 Series 2 n/a Total
New Construction $0 $0 $0 $0
Remodeling $0 $417,502 $0 $417,502
Construction Contingencies $0 $53,902 $0 $53,902
Instructional Technology $0 $207,959 $0 $207,959
Loose Furnishing/Equipment $0 $29,719 $0 $29,719
Buses $0 $0 $0 $0
Site Work $0 $120,473 $0 $120,473
Site Acquisition $0 $0 $0 $0
Architectural Fees and Costs $0 $43,414 $0 $43,414
CM Fees and Costs $0 $35,977 $0 $35,977
Estimated Costs $0 $908,946 $0 $908,946

Certificate by Registered Architect


I certify that I have assessed the conditions relative to this facility and the details of the proposed project(s) described above
and the attached detail relative to the construction project(s) are true and correct to the best of my knowledge and belief.

6/6/2019 French Associates, 1301031750


Signature Date Firm Name and License Number

Paul A. Corneliussen, AIA paulc@frenchaia.com (248) 656-1377


Printed Name E-mail Address Phone Number
LAPEER COMMUNITY SCHOOLS Year Built: 1955
2019 FACILITY IMPROVEMENT PLANNING Building Size: 119,260
ROLLAND-WARNER MS (FUTURE INTERMEDIATE) Site Size: 38.0
3145 W Genesse Road, Lapeer, MI Grades: 5-6 (currently 6-7)
PROJECT WORK LIST Classrooms: 26 Date: 5/30/19

Category Total Total


Subcategory Unit Direct w/ G.C. & w/ Indirect
Work Item Description Qty. Unit Cost Cost Escalation Costs Comments Priority Series

Site Work
Paving Work
replace sidewalks 1 allo 5,000.00 $5,000 $5,737 $6,906 1 2
Paving Work Subtotal: $5,737 $6,906
Site Improvements
add playground equipment 1 allo 100,000.00 $100,000 $114,736 $138,114 for 5th grade 1 2
Site Improvements Subtotal: $114,736 $138,114
Site Work Subtotal: $120,473 $145,019

Remodeling Work
Architectural Work
replace frost slabs 2 each 1,000.00 $2,000 $2,295 $2,762 at early childhood entrance 1 2
install new security door / frame 1 lpsm 5,000.00 $5,000 $5,737 $6,906 at staff lounge 1 2
reconstruct entrance area soffit 700 sqft 25.00 $17,500 $20,079 $24,170 1 2
Architectural Work Subtotal: $28,110 $33,838
Mechanical
HVAC system
upgrade geo-thermal system 1 lpsm 100,000.00 $100,000 $114,736 $138,114 1 2
Mechanical Work Subtotal: $114,736 $138,114
Construction Subtotal: $142,846 $171,951
Technology Infrastructure
network switches - core 1 each 8,000.00 $8,000 $9,179 $10,779 1 2
network switches - edge 15 each 3,250.00 $48,750 $55,934 $65,685 1 2
replace rack UPS's 4 each 2,000.00 $8,000 $9,179 $10,779 1 2
upgrade wireless infrastructure 119,260 sqft 0.50 $59,630 $68,417 $80,344 1 2
upgrade phone system 1 lpsm 45,000.00 $45,000 $51,631 $60,632 1 2
Technology Infrastructure Subtotal: $194,340 $228,218
Technology Safety & Security
install security cameras 35 each 1,200.00 $42,000 $48,189 $56,590 1 2
add access control 6 each 3,000.00 $18,000 $20,653 $24,253 1 2
upgrade PA system 1 lpsm 10,000.00 $10,000 $11,474 $13,474 replace headend equip only 1 2
Safety Infrastructure Subtotal: $80,315 $94,316
Technology/Safety Infrastructure Work Subtotal: $274,655 $322,535
Remodeling Work Subtotal: $417,502 $494,486

Instructional Technology Equipment


Computers and Mobile Devices
purchase teacher computers 60 each 1,250.00 $75,000 $86,052 $97,830 1 2
purchase student desktops 85 each 1,250.00 $106,250 $121,907 $138,593 1 2
Instructional Technology Subtotal: $207,959 $236,424

Furniture, Furnishings & Equipment (F,F,&E)


Non-Instructional Technology Equipment
purchase admin staff computers 15 each 1,400.00 $21,000 $24,095 $27,393 1 2
Non-Instructional Tech Equip Subtotal: $24,095 $27,393
Furniture, Fixtures & Equipment
purchase furniture 1 allo 5,000.00 $5,000 $5,624 $5,624 1 2
F, F, & E Subtotal: $5,624 $5,624
F,F,&E + Non-Inst Tech Equip Subtotal: $29,719 $33,017
Total: $775,653 $908,946
Contingency: $53,902
Design Consultant: $43,414
C.M. Costs: $35,977
BUILDING TOTAL: $908,946
3881, Page 5

Building Utilization

Rolland-Warner Middle School (future Intermediate School) Project No. 3

Current Grade Structure 6-7


Proposed Grade Structure 5-6

1. List the number of teaching station in appropriate column.


2. Calculate total capacity using the applicable capacity factor.
3. Enter five (5) year projected enrollment.
4. Calculate building utilization rate.
5. Attach floor plan of the building. Show the rooms and category (existing, proposed new, closed).
6. Number the teaching stations in consecutive order.

List # of
Teaching Capacity
Existing Stations Factor Capacity
(K-2) Lower Elementary 0 20 0
(3-5) Upper Elementary 12 25 300
(6-8) Middle School 14 22.5 315
(9-12) High School 0 21.25 0

Subtotal 26 615

List # of List # of
Teaching Capacity Facility to be Teaching Capacity
Proposed New Stations Factor Capacity Closed Stations Factor Capacity
(K-2) Lower Elementary 0 20 0 (K-2) Lower Elementary 0 20 0
(3-5) Upper Elementary 0 25 0 (3-5) Upper Elementary 0 25 0
(6-8) Middle School 0 22.5 0 (6-8) Middle School 0 22.5 0
(9-12) High School 0 21.25 0 (9-12) High School 0 21.25 0
Subtotal 0 0 Total 0 0

Total 26 615

Projected 5-Year Enrollment 600

Utilization Percentage 98%


(Projected 5-Year Enrollment / Total Capacity)

Please transfer applicable information to the Utilization Summary on Page 6 of the application.
1
5
2
5
3
5
4
5

8 7
5 6 5
5 5 5
Office
9 10 11 12
5 5 5 5 Music
S.E.
S.E. Cafeteria Stage
M.C.
S.E.

lab

13 17 20 23
6 6 6 6
14 18 21 24 Gym
6 6 6 6
Rolland-Warner Intermediate – CR Summary 15 19 22 25
6 6 6 6
Grade No. of Capacity Total
Level Rooms per room (students)
16 26
6 6
5 12 25 300
lab lab lab lab
6 14 22.5 315
FLOOR PLAN
TOTAL 26 615
3881, Page 4

Project Sheet

Zemmer Middle School Project No. 4


Description of Series 1 n/a

Description of Series 2 replace sidewalks, lockers, upgrade mechanical system, upgrade technology
infrastructure, purchase technology equipment and purchase furniture

Instructional Tech Description purchase student & teacher devices

Site Work Description replace sidewalks

Construction Cost Per Square Foot


New Construction Square Ft 0 Cost per Sq Ft $ -
New Addition Square Ft. 0 Cost per Sq Ft $ -

Statement describing any existing environmental or usability problems the proposed project will address. (ex:
asbestos, energy use, or ADA requirements)
upgrade geo-thermal system for energy savings

Estimated Cost of Proposed Construction Project


Column1 Series 1 Series 2 n/a Total
New Construction $0 $0 $0 $0
Remodeling $0 $420,932 $0 $420,932
Construction Contingencies $0 $49,685 $0 $49,685
Instructional Technology $0 $250,985 $0 $250,985
Loose Furnishing/Equipment $0 $37,750 $0 $37,750
Buses $0 $0 $0 $0
Site Work $0 $5,737 $0 $5,737
Site Acquisition $0 $0 $0 $0
Architectural Fees and Costs $0 $39,132 $0 $39,132
CM Fees and Costs $0 $28,534 $0 $28,534
Estimated Costs $0 $832,755 $0 $832,755

Certificate by Registered Architect


I certify that I have assessed the conditions relative to this facility and the details of the proposed project(s) described above
and the attached detail relative to the construction project(s) are true and correct to the best of my knowledge and belief.

6/6/2019 French Associates, 1301031750


Signature Date Firm Name and License Number

Paul A. Corneliussen, AIA paulc@frenchaia.com (248) 656-1377


Printed Name E-mail Address Phone Number
LAPEER COMMUNITY SCHOOLS Year Built: 1966
2019 FACILITY IMPROVEMENT PLANNING Building Size: 115,240
ZEMMER MIDDLE SCHOOL Site Size: 29.0
1920 Oregon Street, Lapeer, MI Grades: 7-8 (currently 8-9)
PROJECT WORK LIST Classrooms: 29 Date: 5/30/19

Category Total Total


Subcategory Unit Direct w/ G.C. & w/ Indirect
Work Item Description Qty. Unit Cost Cost Escalation Costs Comments Priority Series

Site Work
Paving Work
replace sidewalks 1 allo 5,000.00 $5,000 $5,737 $6,906 1 2
Paving Work Subtotal: $5,737 $6,906
Site Work Subtotal: $5,737 $6,906

Remodeling Work
Architectural Work
reconstruct corridor lockers 1 lpsm 20,000.00 $20,000 $22,947 $27,623 reinforce area 1 2
Architectural Work Subtotal: $22,947 $27,623
Mechanical
HVAC system
upgrade geo-thermal system 1 lpsm 100,000.00 $100,000 $114,736 $138,114 1 2
Mechanical Work Subtotal: $114,736 $138,114
Construction Subtotal: $137,683 $165,736
Technology Infrastructure
network switches - core 1 each 22,000.00 $22,000 $25,242 $29,642 1 2
network switches - edge 13 each 3,250.00 $42,250 $48,476 $56,927 1 2
replace rack UPS's 5 each 2,000.00 $10,000 $11,474 $13,474 1 2
upgrade wireless infrastructure 115,240 sqft 0.50 $57,620 $66,111 $77,636 1 2
upgrade phone system 1 lpsm 45,000.00 $45,000 $51,631 $60,632 1 2
Technology Infrastructure Subtotal: $202,934 $238,310
Technology Safety & Security
install security cameras 40 each 1,200.00 $48,000 $55,073 $64,674 1 2
add access control 4 each 3,000.00 $12,000 $13,768 $16,169 1 2
upgrade PA system 1 lpsm 10,000.00 $10,000 $11,474 $13,474 replace headend equip only 1 2
Safety Infrastructure Subtotal: $80,315 $94,316
Technology/Safety Infrastructure Work Subtotal: $283,249 $332,626
Remodeling Work Subtotal: $420,932 $498,363

Instructional Technology Equipment


Computers and Mobile Devices
purchase teacher computers 45 each 1,250.00 $56,250 $64,539 $73,373 1 2
purchase student desktops 130 each 1,250.00 $162,500 $186,446 $211,966 1 2
Instructional Technology Subtotal: $250,985 $285,339

Furniture, Furnishings & Equipment (F,F,&E)


Non-Instructional Technology Equipment
purchase admin staff computers 20 each 1,400.00 $28,000 $32,126 $36,523 1 2
Non-Instructional Tech Equip Subtotal: $32,126 $36,523
Furniture, Fixtures & Equipment
purchase furniture 1 allo 5,000.00 $5,000 $5,624 $5,624 1 2
F, F, & E Subtotal: $5,624 $5,624
F,F,&E + Non-Inst Tech Equip Subtotal: $37,750 $42,148
Total: $715,405 $832,755
Contingency: $49,685
Design Consultant: $39,132
C.M. Costs: $28,534
BUILDING TOTAL: $832,755
3881, Page 5

Building Utilization

Zemmer Middle School Project No. 4

Current Grade Structure 8-9


Proposed Grade Structure 7-8

1. List the number of teaching station in appropriate column.


2. Calculate total capacity using the applicable capacity factor.
3. Enter five (5) year projected enrollment.
4. Calculate building utilization rate.
5. Attach floor plan of the building. Show the rooms and category (existing, proposed new, closed).
6. Number the teaching stations in consecutive order.

List # of
Teaching Capacity
Existing Stations Factor Capacity
(K-2) Lower Elementary 0 20 0
(3-5) Upper Elementary 0 25 0
(6-8) Middle School 29 22.5 653
(9-12) High School 0 21.25 0

Subtotal 29 653

List # of List # of
Teaching Capacity Facility to be Teaching Capacity
Proposed New Stations Factor Capacity Closed Stations Factor Capacity
(K-2) Lower Elementary 0 20 0 (K-2) Lower Elementary 0 20 0
(3-5) Upper Elementary 0 25 0 (3-5) Upper Elementary 0 25 0
(6-8) Middle School 0 22.5 0 (6-8) Middle School 0 22.5 0
(9-12) High School 0 21.25 0 (9-12) High School 0 21.25 0
Subtotal 0 0 Total 0 0

Total 29 653

Projected 5-Year Enrollment 596

Utilization Percentage 91%


(Projected 5-Year Enrollment / Total Capacity)

Please transfer applicable information to the Utilization Summary on Page 6 of the application.
Cafeteria Stage
3
4
Gym
Spec.
1 2 Ed.

Comp.
5 7 8 Spec. Lab
Ed.
Media Center Comp.
6 Lab

9 10 11 12 13 14 15 16 17

22 23 24 25 26 27 28 29
18 19 20 21 Office

Zemmer Middle School – CR Summary


Grade No. of Capacity Total
Level Rooms per room (students)

7-8 29 22.5 653


FLOOR PLAN
TOTAL 29 653
3881, Page 4

Project Sheet

New High School (current Center for Innovation) Project No. 5


Description of Series 1 demo existing building (except aux gym), build new classroom addition, support space
addition & gym addition, and develop site
Description of Series 2 build auditorium addition & media center addition, pave parking, install technology
infrastructure, purchase technology equipment, and purchase furniture

Instructional Tech Description purchase teacher & student devices, purchase classroom audio/visual systems

Site Work Description paving, site utilities, build storage building, site restoration

Construction Cost Per Square Foot


New Construction Square Ft 0 Cost per Sq Ft $ -
New Addition Square Ft. 226,600 Cost per Sq Ft $ 252.42
*includes escalation for 3 years

Statement describing any existing environmental or usability problems the proposed project will address. (ex:
asbestos, energy use, or ADA requirements)
remove asbestos, build new spaces to full compliance for ADA and new energy code

Estimated Cost of Proposed Construction Project


Column1 Series 1 Series 2 n/a Total
New Construction $45,170,971 $12,027,283 $0 $57,198,255
Remodeling $310,499 $1,339,911 $0 $1,650,410
Construction Contingencies $3,326,349 $1,100,178 $0 $4,426,527
Instructional Technology $0 $1,011,531 $0 $1,011,531
Loose Furnishing/Equipment $0 $451,032 $0 $451,032
Buses $0 $0 $0 $0
Site Work $2,037,796 $1,273,850 $0 $3,311,646
Site Acquisition $0 $0 $0 $0
Architectural Fees and Costs $3,177,851 $1,015,350 $0 $4,193,201
CM Fees and Costs $3,177,851 $979,120 $0 $4,156,971
Estimated Costs $57,201,317 $19,198,255 $0 $76,399,572

Certificate by Registered Architect


I certify that I have assessed the conditions relative to this facility and the details of the proposed project(s) described above
and the attached detail relative to the construction project(s) are true and correct to the best of my knowledge and belief.

6/6/2019 French Associates, 1301031750


Signature Date Firm Name and License Number

Paul A. Corneliussen, AIA paulc@frenchaia.com (248) 656-1377


Printed Name E-mail Address Phone Number
LAPEER COMMUNITY SCHOOLS Year Built: 1960
2019 FACILITY IMPROVEMENT PLANNING Building Size: 146,100 existing note: aux gym: 8,140 sqft to remain
CENTER FOR INNOVATION (FUTURE HIGH SCHOOL) Site Size: 73.0
170 Millville Road, Lapeer, MI 48446 Grades: 9-12 (currently community use)
PROJECT WORK LIST Classrooms: 61 (60 new, plus 1 existig aux gym) Date: 6/6/19

Category Total Total


Subcategory Unit Direct w/ G.C. & w/ Indirect
Work Item Description Qty. Unit Cost Cost Escalation Costs Comments Priority Series

Site Work
Paving Work
repave bus loop 1 lpsm 150,000.00 $150,000 $172,104 $207,170 base good 1 2
repave parking lot 1 lpsm 417,493.00 $417,493 $479,015 $576,615 mill and cap 1 2
expand north parking lot 65,000 sqft 6.00 $390,000 $447,471 $538,643 for auditorium 1 2
Paving Work Subtotal: $1,098,590 $1,322,428
Site Improvements
demolish building 137,960 sqft 5.15 $710,400 $815,085 $981,159 keep aux gym 1 1
site restoration 73 acre 1,750.00 $127,750 $146,575 $176,440 1 2
site development 1 allo 1,065,672.00 $1,065,672 $1,222,711 $1,471,838 grading, utilities 1 1
add outdoor storage for athletic equip. 1 lpsm 25,000.00 $25,000 $28,684 $34,528 track equipment 1 2
Site Improvements Subtotal: $2,213,056 $2,663,966
Site Work Subtotal: $3,311,646 $3,986,394

New Construction
build academic addition 93,150 sqft 220.00 $20,493,000 $23,512,875 $28,303,623 classrooms 1 1
build support space addition 36,392 sqft 220.00 $8,006,240 $9,186,050 $11,057,707 office, commons, kitchen 1 1
build athletics addition 49,410 sqft 220.00 $10,870,200 $12,472,047 $15,013,226 fieldhouse 1 1
build auditorium addition 38,333 sqft 220.00 $8,433,260 $9,675,996 $11,647,480 1 2
build media center 9,315 sqft 220.00 $2,049,300 $2,351,287 $2,830,362 1 2
226,600 New Construction Subtotal: $57,198,255 $68,852,399

Remodeling Work
Architectural Work
abate hazardous material 137,960 sqft 1.60 $220,620 $253,131 $304,706 for building demo 1 1
relocate Wenger music casework 1 allo 10,000.00 $10,000 $11,474 $13,811 from high school 1 2
Architectural Work Subtotal: $264,604 $318,518
Electrical
Power
relocate main service feed 1 allo 50,000.00 $50,000 $57,368 $69,057 1 1
Lighting
add site lighting 20 each 5,000.00 $100,000 $114,736 $138,114 1 2
Electrical Work Subtotal: $172,104 $207,170
Construction Subtotal: $436,709 $525,688
Technology Infrastructure
data cabling for additions/renovations 1 lpsm 70,000.00 $70,000 $80,315 $94,316 1 2
create new IDF 6 each 7,500.00 $45,000 $51,631 $60,632 1 2
reroute WAN fiber 1 each 30,000.00 $30,000 $34,421 $40,421 1 2
install fiber to press box 1 each 30,000.00 $30,000 $34,421 $40,421 1 2
network switches - core 1 each 22,000.00 $22,000 $25,242 $29,642 1 2
network switches - edge 25 each 3,250.00 $81,250 $93,223 $109,474 1 2
replace rack UPS's 6 each 2,000.00 $12,000 $13,768 $16,169 1 2
replace wireless infrastructure 226,600 sqft 0.45 $101,970 $116,996 $137,392 1 2
install new phone system 1 lpsm 100,000.00 $100,000 $114,736 $134,738 1 2
install new clock system 226,600 sqft 0.50 $113,300 $129,996 $152,658 1 2
Technology Infrastructure Subtotal: $694,750 $815,863
Technology Safety & Security
install security cameras 120each 1,200.00 $144,000 $165,220 $194,022 1 2
install security cameras at stadium 15each 1,600.00 $24,000 $27,537 $32,337 1 2
add access control 15each 3,000.00 $45,000 $51,631 $60,632 1 2
access control headend 6each 4,000.00 $24,000 $27,537 $32,337 1 2
install entrance intercom 4each 3,000.00 $12,000 $13,768 $16,169 1 2
install alarm system 1lpsm 90,000.00 $90,000 $103,263 $121,264 1 2
install new PA system 226,600 sqft 0.50 $113,300 $129,996 $152,658 1 2
Safety Infrastructure Subtotal: $518,952 $609,418
Technology/Safety Infrastructure Work Subtotal: $1,213,702 $1,425,280
Remodeling Work Subtotal: $1,650,410 $1,950,968

Instructional Technology Equipment


Computers and Mobile Devices
purchase teacher computers 80 each 1,250.00 $100,000 $114,736 $130,441 1 2
LAPEER COMMUNITY SCHOOLS Year Built: 1960
2019 FACILITY IMPROVEMENT PLANNING Building Size: 146,100 existing note: aux gym: 8,140 sqft to remain
CENTER FOR INNOVATION (FUTURE HIGH SCHOOL) Site Size: 73.0
170 Millville Road, Lapeer, MI 48446 Grades: 9-12 (currently community use)
PROJECT WORK LIST Classrooms: 61 (60 new, plus 1 existig aux gym) Date: 6/6/19

Category Total Total


Subcategory Unit Direct w/ G.C. & w/ Indirect
Work Item Description Qty. Unit Cost Cost Escalation Costs Comments Priority Series

purchase student desktops 200 each 1,250.00 $250,000 $286,840 $326,102 1 2


Audio / Visual
classroom projector 61 each 2,000.00 $122,000 $139,978 $159,138 1 2
classroom sound system 61 each 1,300.00 $79,300 $90,986 $103,439 1 2
document camera 61 each 415.00 $25,315 $29,045 $33,021 1 2
av for collaboration spaces 6 each 35,000.00 $210,000 $240,946 $273,925 1 2
conference room / IEP 1 each 2,500.00 $2,500 $2,868 $3,261 1 2
large group sound system 3 each 25,000.00 $75,000 $86,052 $97,830 café + 2 gyms 1 2
digital signage displays 10 each 1,750.00 $17,500 $20,079 $22,827 1 2
Instructional Technology Subtotal: $1,011,531 $1,149,984

Furniture, Furnishings & Equipment (F,F,&E)


Non-Instructional Technology Equipment
purchase admin staff computers 40 each 1,400.00 $56,000 $64,252 $73,047 includes current admin bldg 1 2
Non-Instructional Tech Equip Subtotal: $64,252 $73,047
Furniture, Fixtures & Equipment
new furnishings 1 allo 343,845.50 $343,846 $386,779 $386,779 1 2
F, F, & E Subtotal: $386,779 $386,779
F,F,&E + Non-Inst Tech Equip Subtotal: $451,032 $459,826
Total: $63,622,874 $76,399,572
Contingency: $4,426,527
Design Consultant: $4,193,201
C.M. Costs: $4,156,971
BUILDING TOTAL: $76,399,572
3881, Page 5

Building Utilization

New High School (current Center for Innovation) Project No. 5

Current Grade Structure n/a


Proposed Grade Structure 9-12

1. List the number of teaching station in appropriate column.


2. Calculate total capacity using the applicable capacity factor.
3. Enter five (5) year projected enrollment.
4. Calculate building utilization rate.
5. Attach floor plan of the building. Show the rooms and category (existing, proposed new, closed).
6. Number the teaching stations in consecutive order.

List # of
Teaching Capacity
Existing Stations Factor Capacity
(K-2) Lower Elementary 0 20 0
(3-5) Upper Elementary 0 25 0
(6-8) Middle School 0 22.5 0
(9-12) High School 1 21.25 21

Subtotal 1 21

List # of List # of
Teaching Capacity Facility to be Teaching Capacity
Proposed New Stations Factor Capacity Closed Stations Factor Capacity
(K-2) Lower Elementary 0 20 0 (K-2) Lower Elementary 0 20 0
(3-5) Upper Elementary 0 25 0 (3-5) Upper Elementary 0 25 0
(6-8) Middle School 0 22.5 0 (6-8) Middle School 0 22.5 0
(9-12) High School 60 21.25 1,275 (9-12) High School 44 21.25 935
Subtotal 60 1,275 Total 44 935

Total 61 1,296

Projected 5-Year Enrollment 1,318

Utilization Percentage 102%


(Projected 5-Year Enrollment / Total Capacity)

Please transfer applicable information to the Utilization Summary on Page 6 of the application.
Lapeer High School 2.0
Lapeer Community Schools Lapeer, Michigan

1200 planned students, grades 9-12 CAPACITY NET SQUARE FEET GROSSING GROSS SQUARE FEET
1500 core capacity students total factor total

A. Area Summary
1. Total Area High School 167,851 nsf 1.350 226,600 gsf
2. Existing Aux Gym 8,140 nsf 8,140 gsf
Total Area High School w/ Aux Gym 175,991 nsf 234,740 gsf

B. Capacity Summary
1. Teaching Stations 60 1,500 students +1 existing (aux gym) 1,525
2. Efficiency Factor 85%
3. Effective Student Capacity 1,275 students 1,296

C. Area Analysis
1. Square feet per student: Planned 1,500 students 151 gsf
2. Square feet per student: Actual 1,275 students 178 gsf

D. Area Comparison
1. Core Academics 41% 69,000 gsf 93,150 gsf
2. Administration 7% 11,256 nsf 15,196 gsf
3. Community 8% 13,300 nsf 17,955 gsf
4. Library / Media 4% 6,900 nsf 9,315 gsf
5. Fitness 22% 36,600 nsf 49,410 gsf
6. Arts 17% 28,395 nsf 38,333 gsf
7. Facility support 1% 2,400 nsf 3,240 gsf
Total GSF 100% 167,851 nsf 226,600 gsf

E. Area Chart

area summary

1
2
3
4
5
6
7

Page 1 Lapeer High 2.0 Program REVISED 6-6-19


137,960 sq ft

Existing building to be demolished,


except auxiliary gymnasium,
New High School to be built

8140 sq ft

1
1

New High School (current CFI) – CR Summary


Grade No. of Capacity per Total
Levels Rooms room (students)
FLOOR PLAN
9-12 61 21.25 1,296
3881, Page 4

Project Sheet

Schickler Elementary School (future Alternative Education) Project No. 6


Description of Series 1 n/a

Description of Series 2 replace paving, upgrade technology infrastructure, and replace technology equipment

Instructional Tech Description purchase teacher computers and student desktop computers

Site Work Description n/a

Construction Cost Per Square Foot


New Construction Square Ft 0 Cost per Sq Ft $ -
New Addition Square Ft. 0 Cost per Sq Ft $ -

Statement describing any existing environmental or usability problems the proposed project will address. (ex:
asbestos, energy use, or ADA requirements)
None

Estimated Cost of Proposed Construction Project


Column1 Series 1 Series 2 n/a Total
New Construction $0 $0 $0 $0
Remodeling $0 $94,025 $0 $94,025
Construction Contingencies $0 $16,481 $0 $16,481
Instructional Technology $0 $18,645 $0 $18,645
Loose Furnishing/Equipment $0 $8,032 $0 $8,032
Buses $0 $0 $0 $0
Site Work $0 $114,736 $0 $114,736
Site Acquisition $0 $0 $0 $0
Architectural Fees and Costs $0 $12,978 $0 $12,978
CM Fees and Costs $0 $13,961 $0 $13,961
Estimated Costs $0 $278,857 $0 $278,857

Certificate by Registered Architect


I certify that I have assessed the conditions relative to this facility and the details of the proposed project(s) described above
and the attached detail relative to the construction project(s) are true and correct to the best of my knowledge and belief.

6/6/2019 French Associates, 1301031750


Signature Date Firm Name and License Number

Paul A. Corneliussen, AIA paulc@frenchaia.com (248) 656-1377


Printed Name E-mail Address Phone Number
LAPEER COMMUNITY SCHOOLS Year Built: 1975
2019 FACILITY IMPROVEMENT PLANNING Building Size: 43,775
SCHICKLER ELEMENTARY (FUTURE ALT ED) Site Size: 20.0
2020 Oregon Street, Lapeer, MI Grades: 9-12 (currently K-5)
PROJECT WORK LIST Classrooms: 8 Date: 5/30/19

Category Total Total


Subcategory Unit Direct w/ G.C. & w/ Indirect
Work Item Description Qty. Unit Cost Cost Escalation Costs Comments Priority Series

Site Work
Paving Work
repave parking lot 20,000 sqft 5.00 $100,000 $114,736 $138,114 some undercuts in drive 1 2
Paving Work Subtotal: $114,736 $138,114
Site Work Subtotal: $114,736 $138,114

Remodeling Work
Technology Infrastructure
network switches - core 1 each 8,000.00 $8,000 $9,179 $10,779 1 2
network switches - edge 1 each 3,250.00 $3,250 $3,729 $4,379 1 2
replace rack UPS's 1 each 2,000.00 $2,000 $2,295 $2,695 1 2
upgrade wireless infrastructure 43,775 sqft 0.45 $19,699 $22,602 $26,542 1 2
upgrade phone system 1 lpsm 15,000.00 $15,000 $17,210 $20,211 1 2
Technology Infrastructure Subtotal: $55,015 $64,605
Technology Safety & Security
install security cameras 15 each 1,200.00 $18,000 $20,653 $24,253 1 2
add access control 2 each 3,000.00 $6,000 $6,884 $8,084 1 2
upgrade PA system 1 lpsm 10,000.00 $10,000 $11,474 $13,474 replace headend equip only 1 2
Safety Infrastructure Subtotal: $39,010 $45,811
Technology/Safety Infrastructure Work Subtotal: $94,025 $110,416
Remodeling Work Subtotal: $94,025 $110,416

Instructional Technology Equipment


Computers and Mobile Devices
purchase teacher computers 3 each 1,250.00 $3,750 $4,303 $4,892 1 2
purchase student desktops 10 each 1,250.00 $12,500 $14,342 $16,305 1 2
Instructional Technology Subtotal: $18,645 $21,197

Furniture, Furnishings & Equipment (F,F,&E)


Non-Instructional Technology Equipment
purchase admin staff computers 5 each 1,400.00 $7,000 $8,032 $9,131 1 2
Non-Instructional Tech Equip Subtotal: $8,032 $9,131
F,F,&E + Non-Inst Tech Equip Subtotal: $8,032 $9,131
Total: $235,437 $278,857
Contingency: $16,481
Design Consultant: $12,978
C.M. Costs: $13,961
BUILDING TOTAL: $278,857
5 C.E.

Community Ed 1 2 3 4 C.E.

C.E.
Community Ed 8 7 6

Gym
Community Ed

Community Ed

Schickler Alternative Education


Grade No. of Capacity per Total
Levels Rooms room (students)
FLOOR PLAN
9-12 8 21.25 170
3881, Page 4

Project Sheet

Administration Building Project No. 7


Description of Series 1 n/a

Description of Series 2 upgrade technology infrastructure and replace technology equipment

Instructional Tech Description n/a

Site Work Description n/a

Construction Cost Per Square Foot


New Construction Square Ft 0 Cost per Sq Ft $ -
New Addition Square Ft. 0 Cost per Sq Ft $ -

Statement describing any existing environmental or usability problems the proposed project will address. (ex:
asbestos, energy use, or ADA requirements)
None

Estimated Cost of Proposed Construction Project


Column1 Series 1 Series 2 n/a Total
New Construction $0 $0 $0 $0
Remodeling $0 $604,558 $0 $604,558
Construction Contingencies $0 $44,568 $0 $44,568
Instructional Technology $0 $0 $0 $0
Loose Furnishing/Equipment $0 $32,126 $0 $32,126
Buses $0 $0 $0 $0
Site Work $0 $0 $0 $0
Site Acquisition $0 $0 $0 $0
Architectural Fees and Costs $0 $24,789 $0 $24,789
CM Fees and Costs $0 $40,430 $0 $40,430
Estimated Costs $0 $746,471 $0 $746,471

Certificate by Registered Architect


I certify that I have assessed the conditions relative to this facility and the details of the proposed project(s) described above
and the attached detail relative to the construction project(s) are true and correct to the best of my knowledge and belief.

6/6/2019 French Associates, 1301031750


Signature Date Firm Name and License Number

Paul A. Corneliussen, AIA paulc@frenchaia.com (248) 656-1377


Printed Name E-mail Address Phone Number
LAPEER COMMUNITY SCHOOLS Year Built: 1952
2019 FACILITY IMPROVEMENT PLANNING Building Size: 25,749
ADMINISTRATION BUILDING Site Size: 10.0
250 2nd Street, Lapeer, MI Grades: n/a
PROJECT WORK LIST Classrooms: n/a Date: 5/30/19

Category Total Total


Subcategory Unit Direct w/ G.C. & w/ Indirect
Work Item Description Qty. Unit Cost Cost Escalation Costs Comments Priority Series

Remodeling Work
Technology Infrastructure
firewall, network mgmt, etc. 1 lpsm 135,000.00 $135,000 $154,894 $181,896 1 2
network switches - core 2 each 22,000.00 $44,000 $50,484 $59,285 1 2
network switches - edge 7 each 3,250.00 $22,750 $26,102 $30,653 1 2
replace rack UPS's 3 each 2,000.00 $6,000 $6,884 $8,084 1 2
upgrade wireless infrastructure 25,749 sqft 0.55 $14,162 $16,249 $19,081 1 2
wireless controller 1 each 100,000.00 $100,000 $114,736 $134,738 not redundant 1 2
upgrade phone system 1 lpsm 150,000.00 $150,000 $172,104 $202,106 1 2
Technology Infrastructure Subtotal: $541,453 $635,842
Technology Safety & Security
video surveillance servers 1 lpsm 55,000.00 $55,000 $63,105 $74,106 1 2
Safety Infrastructure Subtotal: $63,105 $74,106
Technology/Safety Infrastructure Work Subtotal: $604,558 $709,948
Remodeling Work Subtotal: $604,558 $709,948

Furniture, Furnishings & Equipment (F,F,&E)


Non-Instructional Technology Equipment
purchase admin staff computers 20 each 1,400.00 $28,000 $32,126 $36,523 1 2
Non-Instructional Tech Equip Subtotal: $32,126 $36,523
F,F,&E + Non-Inst Tech Equip Subtotal: $32,126 $36,523
Total: $636,684 $746,471
Contingency: $44,568
Design Consultant: $24,789
C.M. Costs: $40,430
BUILDING TOTAL: $746,471
Administration Building
Grade No. of Capacity per Total
Levels Rooms room (students)
FLOOR PLAN
n/a n/a n/a n/a
3881, Page 4

Project Sheet

Bus Garage Project No. 8


Description of Series 1 purchase buses

Description of Series 2 replace paving, replace roofing, remodel facility, plumbing upgrades, electrical upgrades,
technology infrastructure, purchase buses

Instructional Tech Description n/a

Site Work Description replace paving

Construction Cost Per Square Foot


New Construction Square Ft 0 Cost per Sq Ft $ -
New Addition Square Ft. 0 Cost per Sq Ft $ -

Statement describing any existing environmental or usability problems the proposed project will address. (ex:
asbestos, energy use, or ADA requirements)
upgrade parking lot lights for energy efficiency

Estimated Cost of Proposed Construction Project


Column1 Series 1 Series 2 n/a Total
New Construction $0 $0 $0 $0
Remodeling $0 $442,881 $0 $442,881
Construction Contingencies $0 $102,041 $0 $102,041
Instructional Technology $0 $0 $0 $0
Loose Furnishing/Equipment $0 $10,900 $0 $10,900
Buses $3,037,133 $1,012,378 $0 $4,049,510
Site Work $0 $1,003,941 $0 $1,003,941
Site Acquisition $0 $0 $0 $0
Architectural Fees and Costs $0 $95,983 $0 $95,983
CM Fees and Costs $0 $96,756 $0 $96,756
Estimated Costs $3,037,133 $2,764,880 $0 $5,802,013

Certificate by Registered Architect


I certify that I have assessed the conditions relative to this facility and the details of the proposed project(s) described above
and the attached detail relative to the construction project(s) are true and correct to the best of my knowledge and belief.

6/6/2019 French Associates, 1301031750


Signature Date Firm Name and License Number

Paul A. Corneliussen, AIA paulc@frenchaia.com (248) 656-1377


Printed Name E-mail Address Phone Number
LAPEER COMMUNITY SCHOOLS Year Built: 1960
2019 FACILITY IMPROVEMENT PLANNING Building Size: 25,650
BUS GARAGE Site Size: 2.0
532 S. Calhoun Street, Lapeer, MI Grades: n/a
PROJECT WORK LIST Classrooms: n/a Date: 5/30/19

Category Total Total


Subcategory Unit Direct w/ G.C. & w/ Indirect
Work Item Description Qty. Unit Cost Cost Escalation Costs Comments Priority Series

Site Work
Paving Work
repave staff / driver's parking area 25,000 sqft 5.00 $125,000 $143,420 $172,642 west side of lot 1 2
repave bus parking area 125,000 sqft 6.00 $750,000 $860,521 $1,035,852 1 2
Paving Work Subtotal: $1,003,941 $1,208,494
Site Work Subtotal: $1,003,941 $1,208,494

Remodeling Work
Roofing Work
replace roofing 8,800 sqft 10.00 $88,000 $100,968 $121,540 1 2
Roofing Work Subtotal: $100,968 $121,540
Architectural Work
install 2nd exit from driver's lounge 1 lpsm 3,000.00 $3,000 $3,442 $4,143 1 2
upgrade toilet rooms 1 lpsm 5,000.00 $5,000 $5,737 $6,906 1 2
upgrade driver's lounge 1 lpsm 10,000.00 $10,000 $11,474 $13,811 1 2
upgrade director's office for privacy 1 lpsm 2,500.00 $2,500 $2,868 $3,453 1 2
Architectural Work Subtotal: $23,521 $28,313
Mechanical
Plumbing
replace bus wash system 1 lpsm 125,000.00 $125,000 $143,420 $172,642 1 2
Mechanical Work Subtotal: $143,420 $172,642
Electrical
Power
replace bus heater blocks 60 each 550.00 $33,000 $37,863 $45,577 +/- 500 LF underground 1 2
Lighting
replace site lighting 10 each 7,500.00 $75,000 $86,052 $103,585 1 2
Electrical Work Subtotal: $123,915 $149,163
Construction Subtotal: $391,824 $471,658
Technology Infrastructure
network switches - edge 2 each 3,250.00 $6,500 $7,458 $8,758 1 2
replace rack UPS's 1 each 2,000.00 $2,000 $2,295 $2,695 1 2
upgrade wireless infrastructure 1 lpsm 5,000.00 $5,000 $5,737 $6,737 1 2
upgrade phone system 1 lpsm 15,000.00 $15,000 $17,210 $20,211 1 2
Technology Infrastructure Subtotal: $32,700 $38,400
Technology Safety & Security
install security cameras 10 each 1,200.00 $12,000 $13,768 $16,169 1 2
access control headend 1 each 4,000.00 $4,000 $4,589 $5,390 1 2
Safety Infrastructure Subtotal: $18,358 $21,558
Technology/Safety Infrastructure Work Subtotal: $51,058 $59,958
Remodeling Work Subtotal: $442,881 $531,616

Furniture, Furnishings & Equipment (F,F,&E)


Non-Instructional Technology Equipment
purchase admin staff computers 5 each 1,400.00 $7,000 $8,032 $9,131 1 2
conference room / IEP 1 each 2,500.00 $2,500 $2,868 $3,261 1 2
Non-Instructional Tech Equip Subtotal: $10,900 $12,392
F,F,&E + Non-Inst Tech Equip Subtotal: $10,900 $12,392

Transportation
purchase buses 30 each 90,000.00 $2,700,000 $3,037,133 $3,037,133 1 1
purchase buses 10 each 90,000.00 $900,000 $1,012,378 $1,012,378 1 2
40 Transportation Subtotal: $4,049,510 $4,049,510

Total: $5,507,233 $5,802,013


Contingency: $102,041
Design Consultant: $95,983
C.M. Costs: $96,756
BUILDING TOTAL: $5,802,013
Bus Garage
Grade No. of Capacity per Total
Levels Rooms room (students)
FLOOR PLAN
n/a n/a n/a n/a
3881, Page 4

Project Sheet

Maplegrove Center (Community Health) Project No. 9


Description of Series 1 n/a

Description of Series 2 replace roofing

Instructional Tech Description n/a

Site Work Description n/a

Construction Cost Per Square Foot


New Construction Square Ft 0 Cost per Sq Ft $ -
New Addition Square Ft. 0 Cost per Sq Ft $ -

Statement describing any existing environmental or usability problems the proposed project will address. (ex:
asbestos, energy use, or ADA requirements)
None

Estimated Cost of Proposed Construction Project


Column1 Series 1 Series 2 n/a Total
New Construction $0 $0 $0 $0
Remodeling $0 $27,865 $0 $27,865
Construction Contingencies $0 $1,951 $0 $1,951
Instructional Technology $0 $0 $0 $0
Loose Furnishing/Equipment $0 $0 $0 $0
Buses $0 $0 $0 $0
Site Work $0 $0 $0 $0
Site Acquisition $0 $0 $0 $0
Architectural Fees and Costs $0 $1,863 $0 $1,863
CM Fees and Costs $0 $1,863 $0 $1,863
Estimated Costs $0 $33,542 $0 $33,542

Certificate by Registered Architect


I certify that I have assessed the conditions relative to this facility and the details of the proposed project(s) described above
and the attached detail relative to the construction project(s) are true and correct to the best of my knowledge and belief.

6/6/2019 French Associates, 1301031750


Signature Date Firm Name and License Number

Paul A. Corneliussen, AIA paulc@frenchaia.com (248) 656-1377


Printed Name E-mail Address Phone Number
LAPEER COMMUNITY SCHOOLS Year Built: 1966
2019 FACILITY IMPROVEMENT PLANNING Building Size: 40,671 Note: currently rented to
MAPLEGROVE CENTER Site Size: 17.5 Community Health
2020 Imlay City Road, Lapeer, MI Grades: n/a
PROJECT WORK LIST Classrooms: n/a Date: 5/30/19

Category Total Total


Subcategory Unit Direct w/ G.C. & w/ Indirect
Work Item Description Qty. Unit Cost Cost Escalation Costs Comments Priority Series

Remodeling Work
Roofing Work
replace section of roof 5,000 sqft 5.00 $25,000 $27,865 $33,542 1 2
Roofing Work Subtotal: $27,865 $33,542
Construction Subtotal: $27,865 $33,542
Remodeling Work Subtotal: $27,865 $33,542
Total: $27,865 $33,542
Contingency: $1,951
Design Consultant: $1,863
C.M. Costs: $1,863
BUILDING TOTAL: $33,542
Maplegrove Center (Community Health)
Grade No. of Capacity per Total
Levels Rooms room (students)
FLOOR PLAN
n/a n/a n/a n/a
3881, Page 4

Project Sheet

Skinner Lake Property Project No. 10


Description of Series 1 n/a

Description of Series 2 improve site access drive

Instructional Tech Description n/a

Site Work Description road work to improve site access drive

Construction Cost Per Square Foot


New Construction Square Ft 0 Cost per Sq Ft $ -
New Addition Square Ft. 0 Cost per Sq Ft $ -

Statement describing any existing environmental or usability problems the proposed project will address. (ex:
asbestos, energy use, or ADA requirements)
None

Estimated Cost of Proposed Construction Project


Column1 Series 1 Series 2 n/a Total
New Construction $0 $0 $0 $0
Remodeling $0 $0 $0 $0
Construction Contingencies $0 $14,044 $0 $14,044
Instructional Technology $0 $0 $0 $0
Loose Furnishing/Equipment $0 $0 $0 $0
Buses $0 $0 $0 $0
Site Work $0 $200,625 $0 $200,625
Site Acquisition $0 $0 $0 $0
Architectural Fees and Costs $0 $13,417 $0 $13,417
CM Fees and Costs $0 $13,417 $0 $13,417
Estimated Costs $0 $241,502 $0 $241,502

Certificate by Registered Architect


I certify that I have assessed the conditions relative to this facility and the details of the proposed project(s) described above
and the attached detail relative to the construction project(s) are true and correct to the best of my knowledge and belief.

6/6/2019 French Associates, 1301031750


Signature Date Firm Name and License Number

Paul A. Corneliussen, AIA paulc@frenchaia.com (248) 656-1377


Printed Name E-mail Address Phone Number
LAPEER COMMUNITY SCHOOLS Year Built: n/a
2019 FACILITY IMPROVEMENT PLANNING Building Size: 600
SKINNER LAKE PROPERTY Site Size: 80.0
2235 Ferns Road, Lapeer, MI Grades: n/a
PROJECT WORK LIST Classrooms: n/a Date: 6/6/19

Category Total Total


Subcategory Unit Direct w/ G.C. & w/ Indirect
Work Item Description Qty. Unit Cost Cost Escalation Costs Comments Priority Series

Site Work
Paving Work
improve road to access site 1 lpsm 180,000.00 $180,000 $200,625 $241,502 1 2
Paving Work Subtotal: $200,625 $241,502
Site Work Subtotal: $200,625 $241,502

Total: $200,625 $241,502


Contingency: $14,044
Design Consultant: $13,417
C.M. Costs: $13,417
BUILDING TOTAL: $241,502
3881, Page 4

Project Sheet

Lynch Elementary School (building to be demolished) Project No. 11


Description of Proposal/Series 1 n/a

Description of Proposal/Series 2 demolish building & restore site

Instructional Technology Description n/a

Site Work Description building demo and site restoration

Construction Cost Per Square Foot


New Construction Square Ft 0 Cost per Sq Ft $ -
New Addition Square Ft. 0 Cost per Sq Ft $ -

Statement describing any existing environmental or usability problems the proposed project will address. (ex:
asbestos, energy use, or ADA requirements)
abate asbestos prior to building demolition

Estimated Cost of Proposed Construction Project


Column1 Series 1 Series 2 n/a Total
New Construction $0 $0 $0 $0
Remodeling $0 $79,503 $0 $79,503
Construction Contingencies $0 $22,027 $0 $22,027
Instructional Technology $0 $0 $0 $0
Loose Furnishing/Equipment $0 $0 $0 $0
Buses $0 $0 $0 $0
Site Work $0 $235,164 $0 $235,164
Site Acquisition $0 $0 $0 $0
Architectural Fees and Costs $0 $21,043 $0 $21,043
CM Fees and Costs $0 $21,043 $0 $21,043
Estimated Costs $0 $378,780 $0 $378,780

Certificate by Registered Architect


I certify that I have assessed the conditions relative to this facility and the details of the proposed project(s) described above
and the attached detail relative to the construction project(s) are true and correct to the best of my knowledge and belief.

6/6/2019 French Associates, 1301031750


Signature Date Firm Name and License Number

Paul A. Corneliussen, AIA paulc@frenchaia.com (248) 656-1377


Printed Name E-mail Address Phone Number
LAPEER COMMUNITY SCHOOLS Year Built: 1968
2019 FACILITY IMPROVEMENT PLANNING Building Size: 42,553
LYNCH ELEMENTARY SCHOOL Site Size: 13.0
2035 Roods Lake Road, Lapeer, MI Grades: n/a (currently K-5)
PROJECT WORK LIST Classrooms: n/a Date: 5/30/19

Category Total Total


Subcategory Unit Direct w/ G.C. & w/ Indirect
Work Item Description Qty. Unit Cost Cost Escalation Costs Comments Priority Series

Site Work
Site Improvements
demo building 42,553 sqft 4.50 $191,489 $213,430 $256,916 1 2
site restoration 13 acre 1,500.00 $19,500 $21,734 $26,163 after building demo 1 2
Site Improvements Subtotal: $235,164 $283,079
Site Work Subtotal: $235,164 $283,079

Remodeling Work
Architectural Work
abate hazardous material 42,553 sqft 1.50 $63,830 $71,143 $85,639 to demo building 1 2
Architectural Work Subtotal: $71,143 $85,639
Mechanical
Plumbing
disconnect water, sewer & gas 1 allo 5,000.00 $5,000 $5,573 $6,708 to demo building 1 2
Mechanical Work Subtotal: $5,573 $6,708
Electrical
Power
disconnect power 1 allo 2,500.00 $2,500 $2,786 $3,354 to demo building 1 2
Electrical Work Subtotal: $2,786 $3,354
Construction Subtotal: $79,503 $95,701
Remodeling Work Subtotal: $79,503 $95,701

Total: $314,666 $378,780


Contingency: $22,027
Design Consultant: $21,043
C.M. Costs: $21,043
BUILDING TOTAL: $378,780
3881, Page 5

Building Utilization

Lynch Elementary School (building to be demolished) Project No. 11

Current Grade Structure K-5


Proposed Grade Structure n/a

1. List the number of teaching station in appropriate column.


2. Calculate total capacity using the applicable capacity factor.
3. Enter five (5) year projected enrollment.
4. Calculate building utilization rate.
5. Attach floor plan of the building. Show the rooms and category (existing, proposed new, closed).
6. Number the teaching stations in consecutive order.

List # of
Teaching Capacity
Existing Stations Factor Capacity
(K-2) Lower Elementary 0 20 0
(3-5) Upper Elementary 0 25 0
(6-8) Middle School 0 22.5 0
(9-12) High School 0 21.25 0

Subtotal 0 0

List # of List # of
Teaching Capacity Facility to be Teaching Capacity
Proposed New Stations Factor Capacity Closed Stations Factor Capacity
(K-2) Lower Elementary 0 20 0 (K-2) Lower Elementary 8 20 160
(3-5) Upper Elementary 0 25 0 (3-5) Upper Elementary 8 25 200
(6-8) Middle School 0 22.5 0 (6-8) Middle School 0 22.5 0
(9-12) High School 0 21.25 0 (9-12) High School 0 21.25 0
Subtotal 0 0 Total 16 360

Total 0 0

Projected 5-Year Enrollment 0

Utilization Percentage 0%
(Projected 5-Year Enrollment / Total Capacity)

Please transfer applicable information to the Utilization Summary on Page 6 of the application.
Lynch School – TO BE DEMOLISHED
Grade No. of Capacity per Total
Levels Rooms room (students)
3881, Page 4

Project Sheet

Mayfield Elementary School (building to be demolished) Project No. 12


Description of Series 1 n/a

Description of Series 2 demolish building & restore site

Instructional Tech Description n/a

Site Work Description building demo and site restoration

Construction Cost Per Square Foot


New Construction Square Ft 0 Cost per Sq Ft $ -
New Addition Square Ft. 0 Cost per Sq Ft $ -

Statement describing any existing environmental or usability problems the proposed project will address. (ex:
asbestos, energy use, or ADA requirements)
abate asbestos prior to building demolition

Estimated Cost of Proposed Construction Project


Column1 Series 1 Series 2 n/a Total
New Construction $0 $0 $0 $0
Remodeling $0 $30,468 $0 $30,468
Construction Contingencies $0 $20,508 $0 $20,508
Instructional Technology $0 $0 $0 $0
Loose Furnishing/Equipment $0 $0 $0 $0
Buses $0 $0 $0 $0
Site Work $0 $262,506 $0 $262,506
Site Acquisition $0 $0 $0 $0
Architectural Fees and Costs $0 $19,593 $0 $19,593
CM Fees and Costs $0 $19,593 $0 $19,593
Estimated Costs $0 $352,667 $0 $352,667

Certificate by Registered Architect


I certify that I have assessed the conditions relative to this facility and the details of the proposed project(s) described above
and the attached detail relative to the construction project(s) are true and correct to the best of my knowledge and belief.

6/6/2019 French Associates, 1301031750


Signature Date Firm Name and License Number

Paul A. Corneliussen, AIA paulc@frenchaia.com (248) 656-1377


Printed Name E-mail Address Phone Number
LAPEER COMMUNITY SCHOOLS Year Built: 1957
2019 FACILITY IMPROVEMENT PLANNING Building Size: 39,671
MAYFIELD ELEMENTARY SCHOOL Site Size: 38.0
302 Plum Lake Creek Road, Lapeer, MI Grades: n/a (currently K-5)
PROJECT WORK LIST Classrooms: n/a Date: 5/30/19

Category Total Total


Subcategory Unit Direct w/ G.C. & w/ Indirect
Work Item Description Qty. Unit Cost Cost Escalation Costs Comments Priority Series

Site Work
Site Improvements
demo building 39,671 sqft 4.50 $178,520 $198,975 $239,516 1 2
site restoration 38 acre 1,500.00 $57,000 $63,531 $76,476 after building demo 1 2
Site Improvements Subtotal: $262,506 $315,991
Site Work Subtotal: $262,506 $315,991

Remodeling Work
Architectural Work
abate hazardous material 39,671 sqft 0.50 $19,836 $22,108 $26,613 to demo building 1 2
Architectural Work Subtotal: $22,108 $26,613
Mechanical
Plumbing
disconnect water, sewer & gas 1 allo 5,000.00 $5,000 $5,573 $6,708 to demo building 1 2
Mechanical Work Subtotal: $5,573 $6,708
Electrical
Power
disconnect power 1 allo 2,500.00 $2,500 $2,786 $3,354 to demo building 1 2
Electrical Work Subtotal: $2,786 $3,354
Construction Subtotal: $30,468 $36,675
Remodeling Work Subtotal: $30,468 $36,675
Total: $292,973 $352,667
Contingency: $20,508
Design Consultant: $19,593
C.M. Costs: $19,593
BUILDING TOTAL: $352,667
3881, Page 5

Building Utilization

Mayfield Elementary School (building to be demolished) Project No. 12

Current Grade Structure K-5


Proposed Grade Structure n/a

1. List the number of teaching station in appropriate column.


2. Calculate total capacity using the applicable capacity factor.
3. Enter five (5) year projected enrollment.
4. Calculate building utilization rate.
5. Attach floor plan of the building. Show the rooms and category (existing, proposed new, closed).
6. Number the teaching stations in consecutive order.

List # of
Teaching Capacity
Existing Stations Factor Capacity
(K-2) Lower Elementary 0 20 0
(3-5) Upper Elementary 0 25 0
(6-8) Middle School 0 22.5 0
(9-12) High School 0 21.25 0

Subtotal 0 0

List # of List # of
Teaching Capacity Facility to be Teaching Capacity
Proposed New Stations Factor Capacity Closed Stations Factor Capacity
(K-2) Lower Elementary 0 20 0 (K-2) Lower Elementary 9 20 180
(3-5) Upper Elementary 0 25 0 (3-5) Upper Elementary 9 25 225
(6-8) Middle School 0 22.5 0 (6-8) Middle School 0 22.5 0
(9-12) High School 0 21.25 0 (9-12) High School 0 21.25 0
Subtotal 0 0 Total 18 405

Total 0 0

Projected 5-Year Enrollment 0

Utilization Percentage 0%
(Projected 5-Year Enrollment / Total Capacity)

Please transfer applicable information to the Utilization Summary on Page 6 of the application.
Mayfield School – TO BE DEMOLISHED
Grade No. of Capacity per Total
Levels Rooms room (students)
3881, Page 4

Project Sheet

Murphy Elementary School (building to be demolished) Project No. 13


Description of Series 1 n/a

Description of Series 2 demolish building & restore site

Instructional Tech Description n/a

Site Work Description building demo and site restoration

Construction Cost Per Square Foot


New Construction Square Ft 0 Cost per Sq Ft $ -
New Addition Square Ft. 0 Cost per Sq Ft $ -

Statement describing any existing environmental or usability problems the proposed project will address. (ex:
asbestos, energy use, or ADA requirements)
abate asbestos prior to building demolition

Estimated Cost of Proposed Construction Project


Column1 Series 1 Series 2 n/a Total
New Construction $0 $0 $0 $0
Remodeling $0 $85,578 $0 $85,578
Construction Contingencies $0 $20,493 $0 $20,493
Instructional Technology $0 $0 $0 $0
Loose Furnishing/Equipment $0 $0 $0 $0
Buses $0 $0 $0 $0
Site Work $0 $207,178 $0 $207,178
Site Acquisition $0 $0 $0 $0
Architectural Fees and Costs $0 $19,578 $0 $19,578
CM Fees and Costs $0 $19,578 $0 $19,578
Estimated Costs $0 $352,405 $0 $352,405

Certificate by Registered Architect


I certify that I have assessed the conditions relative to this facility and the details of the proposed project(s) described above
and the attached detail relative to the construction project(s) are true and correct to the best of my knowledge and belief.

6/6/2019 French Associates, 1301031750


Signature Date Firm Name and License Number

Paul A. Corneliussen, AIA paulc@frenchaia.com (248) 656-1377


Printed Name E-mail Address Phone Number
LAPEER COMMUNITY SCHOOLS Year Built: 1976
2019 FACILITY IMPROVEMENT PLANNING Building Size: 34,640
MURPHY ELEMENTARY SCHOOL Site Size: 20.0
1100 Pratt Road, Lapeer, MI Grades: n/a (currently K-5)
PROJECT WORK LIST Classrooms: n/a Date: 5/30/19

Category Total Total


Subcategory Unit Direct w/ G.C. & w/ Indirect
Work Item Description Qty. Unit Cost Cost Escalation Costs Comments Priority Series

Site Work
Site Improvements
demo building 34,640 sqft 4.50 $155,880 $173,741 $209,141 1 2
site restoration 20 acre 1,500.00 $30,000 $33,437 $40,250 after building demo 1 2
Site Improvements Subtotal: $207,178 $249,391
Site Work Subtotal: $207,178 $249,391

Remodeling Work
Architectural Work
abate hazardous material 34,640 sqft 2.00 $69,280 $77,218 $92,951 to demo building 1 2
Architectural Work Subtotal: $77,218 $92,951
Mechanical
Plumbing
disconnect water, sewer & gas 1 allo 5,000.00 $5,000 $5,573 $6,708 to demo building 1 2
Mechanical Work Subtotal: $5,573 $6,708
Electrical
Power
disconnect power 1 allo 2,500.00 $2,500 $2,786 $3,354 to demo building 1 2
Electrical Work Subtotal: $2,786 $3,354
Construction Subtotal: $85,578 $103,014
Remodeling Work Subtotal: $85,578 $103,014
Total: $292,756 $352,405
Contingency: $20,493
Design Consultant: $19,578
C.M. Costs: $19,578
BUILDING TOTAL: $352,405
3881, Page 5

Building Utilization

Murphy Elementary School (building to be demolished) Project No. 13

Current Grade Structure K-5


Proposed Grade Structure n/a

1. List the number of teaching station in appropriate column.


2. Calculate total capacity using the applicable capacity factor.
3. Enter five (5) year projected enrollment.
4. Calculate building utilization rate.
5. Attach floor plan of the building. Show the rooms and category (existing, proposed new, closed).
6. Number the teaching stations in consecutive order.

List # of
Teaching Capacity
Existing Stations Factor Capacity
(K-2) Lower Elementary 0 20 0
(3-5) Upper Elementary 0 25 0
(6-8) Middle School 0 22.5 0
(9-12) High School 0 21.25 0
Subtotal 0 0

List # of List # of
Teaching Capacity Facility to be Teaching Capacity
Proposed New Stations Factor Capacity Closed Stations Factor Capacity
(K-2) Lower Elementary 0 20 0 (K-2) Lower Elementary 8 20 160
(3-5) Upper Elementary 0 25 0 (3-5) Upper Elementary 8 25 200
(6-8) Middle School 0 22.5 0 (6-8) Middle School 0 22.5 0
(9-12) High School 0 21.25 0 (9-12) High School 0 21.25 0
Subtotal 0 0 Total 16 360

Total 0 0

Projected 5-Year Enrollment 0

Utilization Percentage 0%
(Projected 5-Year Enrollment / Total Capacity)

Please transfer applicable information to the Utilization Summary on Page 6 of the application.
Murphy School – TO BE DEMOLISHED
Grade No. of Capacity per Total
Levels Rooms room (students)
3881, Page 6

Utilization Summary
Lapeer Community Schools 44 - 010

List ALL district facilities in the following order: elementary schools, junior high/middle schools, high schools, and non-instructional facilities.
Proj. Current Grade Proposed Grade Projected 5-Year Existing Pupil New Pupil Total Pupil Closed Pupil
No. Name of School Facility Structure Structure Enrollment Capacity Capacity Capacity Utilization % Capacity
1 Turril Elementary School K-5 preK-K 372 320 0 320 116% 0
2 Lapeer Elementary (current HS) 10-12 1-4 1,174 1,080 0 1,080 109% 0
3 Rolland-Warner Middle School 6-7 5-6 600 615 0 615 98% 0
4 Zemmer Middle School 8-9 7-8 596 653 0 653 91% 0
5 New High School (current CFI) n/a 9-12 1,318 21 1,275 1,296 102% 935
6 Schickler School (future alt ed) K-5 9-12 0 0 0 0 0% 0
7 Administration Building n/a n/a n/a n/a n/a n/a n/a n/a
8 Bus Garage n/a n/a n/a n/a n/a n/a n/a n/a
- Cramton Center (Homeschool) n/a n/a n/a n/a n/a n/a n/a n/a
9 Maplegrove Center (Health) n/a n/a n/a n/a n/a n/a n/a n/a
10 Skinner Lake Property n/a n/a n/a n/a n/a n/a n/a n/a
11 Lynch Elementary School K-5 n/a 0 0 0 0 0% 360
12 Mayfield Elementary School K-5 n/a 0 0 0 0 0% 405
13 Murphy Elementary School K-5 n/a 0 0 0 0 0% 360

Total preK-12 preK-12 4,059 2,689 1,275 3,964 102% 2,060

Subtotals by School District's Grade Configuration


Current Grade Proposed Grade Projected 5-Year Existing Pupil New Pupil Total Pupil Closed Pupil
Configuration Structure Structure Enrollment Capacity Capacity Capacity Utilization % Capacity
Elementary School K-5 K-4 1,546 1,400 0 1,400 110% 1,125

Middle School 6-8 5-8 1,196 1,268 0 1,268 94% 0

High School 9-12 9-12 1,318 21 1,275 1,296 102% 0

Total preK-12 preK-12 4,059 2,689 1,275 3,964 102% 1,125


3881, Page 7

Facility Summary
Lapeer Community Schools 44 - 010

List ALL district facilities in the following order: elementary schools, junior high/middle schools, high schools, and non-instructional facilities.
1 2 3 4 5 6 7 8 9 10 11
Facility Type* Name of School Facility Address City Year Built Year(s) Remodeled Total Sq.Ft. New Site Bldg In Sq Ft of Disposition of
Proj. (Acres) Use? Y/N Closed Closed Facility**
No. Facility
1 Instructional Turril Elementary 785 S Elm St Lapeer 1959 1965, 1967, 2005 44,749 0 Yes 0 n/a
2 Instructional Lapeer Elementary (current HS) 933 S Saginaw St Lapeer 1960 1975, 2005 165,861 0 Yes 0 n/a
3 Instructional Rolland-Warner Middle School 3145 W Genesee St Lapeer 1955 2007 119,260 0 Yes 0 n/a
4 Instructional Zemmer Middle School 1920 W Oregon St Lapeer 1966 1975, 2008 115,240 0 Yes 0 n/a
5 Instructional New HS (current Center) 170 Millville Rd Lapeer 1960 1964, 1967, 2007 234,740 0 Yes 137,960 4
6 Instructional Schickler School 2020 W Oregon St Lapeer 1975 43,775 0 Yes 0 n/a
7 Non-Instructional Administration Building 250 2nd St Lapeer 1952 2008 25,749 0 Yes 0 n/a
8 Bus Garage Bus Garage 582 S Calhoun St Lapeer 1960 25,650 0 Yes 0 n/a
- Non-Instructional Cramton Center (Homeschool) 1220 Lake Nepessing Rd Lapeer 1969 2012 21,360 0 Yes 0 n/a
9 Non-Instructional Maplegrove Center (Health) 148 Maple Grove Rd Lapeer 1966 1967, 1974, 2009 40,671 0 Yes 0 n/a
10 Non-Instructional Skinner Lake Property 2235 Ferns Road Lapeer n/a 600 0 Yes 0 n/a
11 Instructional Lynch Elementary 2035 Roods Lake Lapeer 1968 1974, 2009 42,553 0 Yes 42,553 1
12 Instructional Mayfield Elementary 302 Plum Creek Lapeer 1957 1964, 1973 39,671 0 Yes 39,671 1
13 Instructional Murphy Elementary 1100 Pratt Metamora 1976 2005 34,640 0 Yes 34,640 1

Total ---------- ---------- --------- ---------- ----- ---------- 954,519 0 ----- 254,824 ------

*Facility Type: **Closed Facility Reference:


Instructional 1. Demolish
Non-Instructional 2. Convert to non-instructional
Bus Garage 3. Sell or lease
Storage 4. Retain for future use
Stadium 5. Undetermined
3881, Page 8

Cost Summary - SERIES 1


Lapeer Community Schools 44 - 010
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Cost per New Cons New Instruct'l Loose Furn Site A/E Fees CM Fees Election/
Proj. # Sq Foot Sq Feet Construct'n Remodel'g Contingency Technology and Equip Buses Site Work Acquisit'n and Costs and Costs Project Costs Issue Costs Total Cost

1 0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0
2 0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0
3 0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0
4 0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0
5 252.42 178,952 45,170,971 310,499 3,326,349 0 0 0 2,037,796 0 3,177,851 3,177,851 57,201,317 702,426 57,903,743
6 0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0
7 0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0
8 0.00 0 0 0 0 0 0 3,037,133 0 0 0 0 3,037,133 37,296 3,074,428

- 0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0
9 0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0
10 0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0
11 0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0
12 0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0
13 0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Total 252.42 178,952 45,170,971 310,499 3,326,349 0 0 3,037,133 2,037,796 0 3,177,851 3,177,851 60,238,450 739,722 60,978,172

17. Funding:
Total Estimated Cost of Project: $60,978,172
LESS:
Estimated Interest Earnings: $978,172
Other (specify):

AMOUNT OF PROPOSED ISSUE


$60,000,000
(Amount to be Qualified)
3881, Page 8

Cost Summary - SERIES 2


Lapeer Community Schools 44 - 010
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Cost per New Cons New Instruct'l Loose Furn Site A/E Fees CM Fees Election/
Proj. # Sq Foot Sq Feet Construct'n Remodel'g Contingency Technology and Equip Buses Site Work Acquisit'n and Costs and Costs Project Costs Issue Costs Total Cost

1 0.00 0 0 378,485 50,408 71,710 13,656 0 261,885 0 44,051 42,825 863,020 12,381 875,402
2 0.00 0 0 5,248,662 463,062 215,130 29,719 0 1,127,282 0 430,127 426,391 7,940,373 113,917 8,054,289
3 0.00 0 0 417,502 53,902 207,959 29,719 0 120,473 0 43,414 35,977 908,946 13,040 921,986
4 0.00 0 0 420,932 49,685 250,985 37,750 0 5,737 0 39,132 28,534 832,755 11,947 844,702
5 252.42 47,648 12,027,283 1,339,911 1,100,178 1,011,531 451,032 0 1,273,850 0 1,015,350 979,120 19,198,255 275,428 19,473,683
6 0.00 0 0 94,025 16,481 18,645 8,032 0 114,736 0 12,978 13,961 278,857 4,001 282,857
7 0.00 0 0 604,558 44,568 0 32,126 0 0 0 24,789 40,430 746,471 10,709 757,181
8 0.00 0 0 442,881 102,041 0 10,900 1,012,378 1,003,941 0 95,983 96,756 2,764,880 39,666 2,804,546

- 0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0
9 0.00 0 0 27,865 1,951 0 0 0 0 0 1,863 1,863 33,542 481 34,023
10 0.00 0 0 0 14,044 0 0 0 200,625 0 13,417 13,417 241,502 3,465 244,967
11 0.00 0 0 79,503 22,027 0 0 0 235,164 0 21,043 21,043 378,780 5,434 384,214
12 0.00 0 0 30,468 20,508 0 0 0 262,506 0 19,593 19,593 352,667 5,060 357,726
13 0.00 0 0 85,578 20,493 0 0 0 207,178 0 19,578 19,578 352,405 5,056 357,461

Total 252.42 47,648 12,027,283 9,170,369 1,959,345 1,775,960 612,933 1,012,378 4,813,377 0 1,781,318 1,739,488 34,892,452 500,585 35,393,037

17. Funding:
Total Estimated Cost of Project: $35,393,037
LESS:
Estimated Interest Earnings: $493,037
Other (specify):

AMOUNT OF PROPOSED ISSUE


$34,900,000
(Amount to be Qualified)
3881, Page 8

Cost Summary - COMBINED SERIES 1 & 2


Lapeer Community Schools 44 - 010
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Cost per New Cons New Instruct'l Loose Furn Site A/E Fees CM Fees Election/
Proj. # Sq Foot Sq Feet Construct'n Remodel'g Contingency Technology and Equip Buses Site Work Acquisit'n and Costs and Costs Project Costs Issue Costs Total Cost

1 0.00 0 0 378,485 50,408 71,710 13,656 0 261,885 0 44,051 42,825 863,020 12,381 875,402
2 0.00 0 0 5,248,662 463,062 215,130 29,719 0 1,127,282 0 430,127 426,391 7,940,373 113,917 8,054,289
3 0.00 0 0 417,502 53,902 207,959 29,719 0 120,473 0 43,414 35,977 908,946 13,040 921,986
4 0.00 0 0 420,932 49,685 250,985 37,750 0 5,737 0 39,132 28,534 832,755 11,947 844,702
5 252.42 226,600 57,198,255 1,650,410 4,426,527 1,011,531 451,032 0 3,311,646 0 4,193,201 4,156,971 76,399,572 977,854 77,377,426
6 0.00 0 0 94,025 16,481 18,645 8,032 0 114,736 0 12,978 13,961 278,857 4,001 282,857
7 0.00 0 0 604,558 44,568 0 32,126 0 0 0 24,789 40,430 746,471 10,709 757,181
8 0.00 0 0 442,881 102,041 0 10,900 4,049,510 1,003,941 0 95,983 96,756 5,802,013 76,962 5,878,975

- 0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0
9 0.00 0 0 27,865 1,951 0 0 0 0 0 1,863 1,863 33,542 481 34,023
10 0.00 0 0 0 14,044 0 0 0 200,625 0 13,417 13,417 241,502 3,465 244,967
11 0.00 0 0 79,503 22,027 0 0 0 235,164 0 21,043 21,043 378,780 5,434 384,214
12 0.00 0 0 30,468 20,508 0 0 0 262,506 0 19,593 19,593 352,667 5,060 357,726
13 0.00 0 0 85,578 20,493 0 0 0 207,178 0 19,578 19,578 352,405 5,056 357,461

Total 252.42 226,600 57,198,255 9,480,868 5,285,694 1,775,960 612,933 4,049,510 6,851,173 0 4,959,169 4,917,339 95,130,902 1,240,307 96,371,209

17. Funding:
Total Estimated Cost of Project: $96,371,209
LESS:
Estimated Interest Earnings: $1,471,209
Other (specify):

AMOUNT OF PROPOSED ISSUE


$94,900,000
(Amount to be Qualified)
3881, Worksheet 1: Useful Life Calculation - SERIES 1
A school district must demonstrate that the weighted average maturity of the qualified bond issue
does not exceed 120% of the average reasonably expected useful life of the facilities, excluding land
and site improvements, being financed with the proceeds of the qualified bonds.
The following table lists the recommended average useful life of the categories of assets that should
be considered in this calculation. If a specific item is not listed, it should be assigned to the most
closely related category.

Useful
Asset Category Life
New School Building 40
Building Improvements - interior and exterior remodeling such as plumbing, electrical,
30
HVAC, fire suppression, security systems, elevators, etc.
Roofing 20
Flooring 10
Furnishings and Equipment - furniture and fixtures that are not a structural component of a
building such as desks, chairs, tables, storage units, office equipment, copiers, fax
10
machines, communications equipment, kitchen equipment and appliances, athletic
equipment, etc.
Technology Infrastructure - cables, networks, etc. 10
Buses 6
Technology (instructional and non-instructional) - computers, printers, scanners, etc. 5

Use the worksheet below to calculate the weighted average useful life of assets included in
projects funded by bond proceeds.

Col. 1 Col. 4 Col. 6 Col. 3


Follow Column
→ Enter + Enter Enter + ÷ x
Instructions
Value Col. 2 Value Value Col. 5 Col. 6 Total Col. 7
Col. 1 Col. 2 Col. 3 Col. 4 Col. 5 Col. 6 Col. 7 Col. 8
Time
between
Average Bonds Allocation of Average
Useful Life Issue Date Useful Life of Asset Related Total Costs Useful Life
of Asset and from Bond Issue Expenditure Professional (Incl. Related % of Total of Assets
Asset Type (in Years) Purchase Date Amount Fees Fees) Cost (in years)

School Buildings 40 0 40 45,170,971 5,872,226 51,043,197 93.78% 37.51

Building
30 0 30 310,499 40,365 350,864 0.64% 0.19
Improvements

Roofing 20 0 20 0 0 0 0.00% 0.00

Flooring 10 0 10 0 0 0 0.00% 0.00

Furnishing/
10 0 10 0 0 0 0.00% 0.00
Equipment
Technology
10 0 10 0 0 0 0.00% 0.00
Infrastructure
Technology
5 0 5 0 0 0 0.00% 0.00
(instr/non-instr)

Buses 6 0 6 3,037,133 0 3,037,133 5.58% 0.33

Total for purposes of determining weighted avg useful life 48,518,603 5,912,591 54,431,194 100.00% 38.04

120% of average useful life of assets → 45.65


3881, Worksheet 1: Useful Life Calculation - SERIES 2
A school district must demonstrate that the weighted average maturity of the qualified bond issue
does not exceed 120% of the average reasonably expected useful life of the facilities, excluding land
and site improvements, being financed with the proceeds of the qualified bonds.
The following table lists the recommended average useful life of the categories of assets that should
be considered in this calculation. If a specific item is not listed, it should be assigned to the most
closely related category.

Useful
Asset Category Life
New School Building 40
Building Improvements - interior and exterior remodeling such as plumbing, electrical,
30
HVAC, fire suppression, security systems, elevators, etc.
Roofing 20
Flooring 10
Furnishings and Equipment - furniture and fixtures that are not a structural component of a
building such as desks, chairs, tables, storage units, office equipment, copiers, fax
10
machines, communications equipment, kitchen equipment and appliances, athletic
equipment, etc.
Technology Infrastructure - cables, networks, etc. 10
Buses 6
Technology (instructional and non-instructional) - computers, printers, scanners, etc. 5

Use the worksheet below to calculate the weighted average useful life of assets included in
projects funded by bond proceeds.

Col. 1 Col. 4 Col. 6 Col. 3


Follow Column
→ Enter + Enter Enter + ÷ x
Instructions
Value Col. 2 Value Value Col. 5 Col. 6 Total Col. 7
Col. 1 Col. 2 Col. 3 Col. 4 Col. 5 Col. 6 Col. 7 Col. 8
Time
between
Average Bonds Allocation of Average
Useful Life Issue Date Useful Life of Asset Related Total Costs Useful Life
of Asset and from Bond Issue Expenditure Professional (Incl. Related % of Total of Assets
Asset Type (in Years) Purchase Date Amount Fees Fees) Cost (in years)

School Buildings 40 0 40 12,027,283 1,563,547 13,590,830 49.45% 19.78

Building
30 0 30 3,527,456 458,569 3,986,026 14.50% 4.35
Improvements

Roofing 20 0 20 2,404,738 312,616 2,717,354 9.89% 1.98

Flooring 10 0 10 160,631 20,882 181,513 0.66% 0.07

Furnishing/
10 0 10 409,277 0 409,277 1.49% 0.15
Equipment
Technology
10 0 10 3,077,544 400,081 3,477,625 12.65% 1.27
Infrastructure
Technology
5 0 5 1,979,617 128,675 2,108,292 7.67% 0.38
(instr/non-instr)

Buses 6 0 6 1,012,378 0 1,012,378 3.68% 0.22

Total for purposes of determining weighted avg useful life 24,598,924 2,884,370 27,483,294 100.00% 28.19

120% of average useful life of assets → 33.83


3881, Worksheet 1: Useful Life Calculation - SERIES 1 & 2
A school district must demonstrate that the weighted average maturity of the qualified bond issue
does not exceed 120% of the average reasonably expected useful life of the facilities, excluding land
and site improvements, being financed with the proceeds of the qualified bonds.
The following table lists the recommended average useful life of the categories of assets that should
be considered in this calculation. If a specific item is not listed, it should be assigned to the most
closely related category.

Useful
Asset Category Life
New School Building 40
Building Improvements - interior and exterior remodeling such as plumbing, electrical,
30
HVAC, fire suppression, security systems, elevators, etc.
Roofing 20
Flooring 10
Furnishings and Equipment - furniture and fixtures that are not a structural component of a
building such as desks, chairs, tables, storage units, office equipment, copiers, fax
10
machines, communications equipment, kitchen equipment and appliances, athletic
equipment, etc.
Technology Infrastructure - cables, networks, etc. 10
Buses 6
Technology (instructional and non-instructional) - computers, printers, scanners, etc. 5

Use the worksheet below to calculate the weighted average useful life of assets included in
projects funded by bond proceeds.

Col. 1 Col. 4 Col. 6 Col. 3


Follow Column
→ Enter + Enter Enter + ÷ x
Instructions
Value Col. 2 Value Value Col. 5 Col. 6 Total Col. 7
Col. 1 Col. 2 Col. 3 Col. 4 Col. 5 Col. 6 Col. 7 Col. 8
Time
between
Average Bonds Allocation of Average
Useful Life Issue Date Useful Life of Asset Related Total Costs Useful Life
of Asset and from Bond Issue Expenditure Professional (Incl. Related % of Total of Assets
Asset Type (in Years) Purchase Date Amount Fees Fees) Cost (in years)

School Buildings 40 0 40 57,198,255 7,435,773 64,634,028 78.90% 31.56

Building
30 0 30 3,837,955 498,934 4,336,889 5.29% 1.59
Improvements

Roofing 20 0 20 2,404,738 312,616 2,717,354 3.32% 0.66

Flooring 10 0 10 160,631 20,882 181,513 0.22% 0.02

Furnishing/
10 0 10 409,277 0 409,277 0.50% 0.05
Equipment
Technology
10 0 10 3,077,544 400,081 3,477,625 4.25% 0.42
Infrastructure
Technology
5 0 5 1,979,617 128,675 2,108,292 2.57% 0.13
(instr/non-instr)

Buses 6 0 6 4,049,510 0 4,049,510 4.94% 0.30

Total for purposes of determining weighted avg useful life 73,117,527 8,796,961 81,914,488 100.00% 34.74

120% of average useful life of assets → 41.68