High Risk of Injury to The procedures to be followed at all times to prevent accidents or injury as a result from contact
employees/public as a result of with road traffic.
collision/contact with vehicles due to Ensure that there are sufficient cones and signs available for the area being worked in. Make
not adhering to traffic management sure that pedestrians and traffic are given maximum notice of work taking place. Where there
procedure might be the possibility of heavy traffic around work zones during the day consideration should
be given to completing the work during the night or on weekends.
Where pedestrian walkway is blocked, direct pedestrians to use the alterative walkway where
available. Where there is no pedestrian walkway, ensure a clear and unobstructed walkway is
provided around the work area using cones.
Ensure that signs are clean, clear and unobstructed at all times, use weights to keep signs in
place if necessary due to the raining season.
Notify local police and the Traffic Management Division of any interference to traffic.
Workers must stay within the defined construction zone so as not to be exposed to oncoming
Rev No. 1.0 Ref No. RA-002-Fibre-CT Rev Issue Date: October 2014 Controller: SHEQ
Uncontrolled if printed or copied Page 1 of 2
Sierra Support Services Group RA-002-FIBRE-CT
General Recommendations Communication must be maintained at all times between crews when setting up signs
Responsibility for Control Sierra management for overall work procedures and work practices.
Responsibility of all trained employees / Contractors.
Rev No. 1.0 Ref No. RA-002-Fibre-CT Rev Issue Date: October 2014 Controller: SHEQ
Uncontrolled if printed or copied Page 2 of 2