DATE: December 04, 2017 DATE: December 05, 2017 DATE: DATE:
Page 1 of 9
S No. Sequence of Steps Potential Hazards Corrective Action/Recomendation
1. Obtain Work Permit and Vehicular Accident Driver shall have SAG license and attended Arkad defensive training course.
meet the S.A. Issuer on Driver shall follow the Speed limit mention on wasit gas plant and on the main road.
the site Vehicle shall properly maintained and schedule periodic inspection shall be follow.
Fatal or permanent disability Passengers & Driver shall wear seatbelt once riding in the vehicle.
Passengers shall inform HSE department if he found the driver are driving unsafely, so
that appropriate disciplinary action shall be taken.
2. Site Preparation & Slip, trip & Fall Hazards- The permit issuer and receiver will conduct a joint site inspection to discuss the hazards
Inspection Injury and precautions required for conducting the job safely.
Obtain work permit as outlined in GI-2.100.Work Permit System
Ensure all workers have access sign by proponent prior to work
A tool box meeting shall be conducted informing also the location of assembly area for
emergency & contact numbers to be posted
In case of any emergency, all activities shall be stop according to emergency response
plan.
Male nurse and Ambulance shall be on site.
Stop work authority signage shall be posted at the jobsite.
Page 2 of 9
3. Mobilization of Tools Accidents by moving Sequence of work shall be discuss during pre-task briefing before the work commence.
& Personnel equipment results in property Work permit and confined space entry permit shall require for all excavations over 1.2
damage & potential caught-in meters in depth in according to the G.I 2.100.Work Permit System.
between/ struck by & crush A joint site inspection shall be conducted by permit issuer and receiver
injury Low bed trailer should be in good condition
Depute a flagman, equipped with reflecting safety vest.
All drivers shall comply with G.I- 6.030 Traffic Control and Vehicle Safety.
Mobilization of property damage Sequence of work shall be discuss during pre-task briefing before the work
4. Equipment to the Site commence.
potential caught-in between/
struck by & crush injury Assign a flagman, equipped with a reflecting safety vest.
Remove excavated soil manually or by using (Only) bob cat, combination
machine JCB with certified operator and spotter wearing reflecting vest.
PWAS shall be installed in the equipment’s and operators knows how to
operate.
Heavy equipment dump truck not allowed working inside fence
Back up alarm shall be fixed in all heavy equipment especially (Dump Trucks)
All equipment needs to keep 2 meters away from the excavation.
All equipment shall be inspected on a daily basis prior to use
Only SA / SPSP Certified operators shall operate equipment.
STOP Work authority sign posted on site.
Page 3 of 9
5 Excavation by hand Personal Injury All employees shall wear job required proper PPE (FRC ,helmet, Safety Glass, Safety
Shoes and appropriate gloves etc.) and experienced enough to do the job
Unauthorized personnel’s shall not allowed at the work area
First aid kit and first aider will available at site.
Damage to underground Location plan and work method statement which is prepared by the
facilitates (communication Project Engineer shall be submit to the concerned department for review and approval.
cables/electrical or The surveyor should survey the area prior to start of marking the lines.
Government cables) Pre-excavation checklist shall be filled-up and approved prior to any excavation.
Pre – task meeting will conduct by site supervisor and foreman.
Check the underground utilities using location map and detector if necessary
Daily excavation checklist shall be complete prior to permit issuance.
Any excavation more than 1.2m (4ft.) consider as a confined space should be arrange
Cave in (collapse of side
confined space permit and gas test from concern dept.
walls)
Unauthorized personnel shall not enter the work location.
Shoring/sloping of excavation according to soil condition.
Excavation and Shoring guide, refer to Aramco Standard
7 Housekeeping Health Hazard -Regular disposal of waste, debris and scrap materials shall carried-out.
-Trash bin for waste, used paper cups, scrap and debris shall be provide.
-Drinking containers shall be in good sanitary, tightly capped, and clearly marked for
Page 4 of 9
use and cup dispensers shall be provide.
Page 5 of 9
Supervisor responsible for explaining contents of this JSA
Name: Signature: Date:
Page 6 of 9
Sign On: I confirm that the JSA has been explained and its contents are clearly understood and accepted. I also confirm that my
required qualifications to undertake this activity are current and approved. I clearly understand the controls in this JSA must be applied as
documented; otherwise work is to cease immediately and a review is to be completed and work can recommence.