PRESUPUESTO - OBRAS CIVILES

OBRA : CONSTRUCCION DE VIVIENDA MULTIFAMILIAR


MODALIDAD: : A TODO COSTO
CLIENTE GINA MARTEL OSORIO
LUGAR VILLA MARIA DEL TRIUNFO -LIMA FECHA 12/02/2019

ITEM DESCRIPCION und. MET P-U PARCIAL S/.


1 OBRAS PRELIMINARES
1.01 MOVIMIENTO DE TIERRAS
1.01.01 ESCAVACION PARA ZAPATA TERRENO NATURAL m3 25.55 35.00 894.25
1.01.02 ESCAVACION PARA CIMENTACION TERRENO NATURAL m3 15.06 35.00 527.10
EXCAVACION VIGA CIMENTACION TERRENO NATURAL M3 0.84 35.00 29.40
1.01.03 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 15 km M3 49.75 40.00 1,990.00
2 CONCRETO ARMADO
2.01 ZAPATA
2.01.01 CONCRETO EN ZAPATAS FC=210KG/CM2 m3 10.95 380.00 4,161.00
2.01.02 ACERO KG 224.80 4.90 1,101.52
2.01.03 SOLADO PARA ZAPATA m3 0.65 240.00 156.00
2.02 VIGAS DE CIMENTACION
2.02.01 CONCRETO EN ZAPATAS FC=210KG/CM2 m3 1.58 320.00 505.60
2.02.02 ACERO KG 250.52 4.80 1,202.50
2.02.03 SOLADO PARA VIGA CIMENTACION m3 0.35 240.00 84.00
2.02.04 ENCONFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 12.62 32.00 403.84
2.3 COLUMNAS
2.03.01 ACERO DE REFUERZO Fy=4200KG/CM2, GRADO 60 PARA COLUMNAS kg 1,480.00 4.90 7,252.00
2.03.02 ENCONFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 98.40 35.00 3,444.00
2.03.03 CONCRETO EN COLUMNAS FC=210KG/CM2 m3 6.89 380.00 2,618.20
2.4 VIGAS

2.04.01 ENCONFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 39.16 32.00 1,253.12


2.04.02 ACERO CORRUGADO FY=4200KG/CM2 GRADO 60 PARA VIGAS kg
952.45 4.80 4,571.76
2.04.03 CONCRETO F/C=210KG/CM2 EN VIGAS m3 8.20 380.00 3,116.00
2.5 LOSAS ALIGERADAS

2.05.01 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS m2


149.00 37.10 5,527.90
LADRILLO HUECO DE ARCILLA 15X30X30 cm PARA TECHO ALIGERADO und.
2.05.02
1,341.00 2.24 3,003.84
2.05.03 kg 648.00 4.90
ACERO FY=4200KG/CM2 GRADO 60 PARA LOSA ALIGERADA 3,175.20
2.05.04 CONCRETO EN LOSAS ALIGERADAS FC=210KG/CM2 m3 19.40 380.00 7,372.00
3.00 ALBAÑILERIA - MURO

3.01 MURO DE LADRILLO KK 18 HCOS - SOGA M2 194.20 64.00 12,428.80


4.00 PISO Y PAVIMENTOS

4.01 FALSO PISO DE CONCRETO FROTACHADO E=4" EN 1ER PISO M2 74.00 46.00 3,404.00
4.02 SOBREPISO e=2" FROTACHADO EN 2DO PISO M2 68.00 36.00 2,448.00
5.00 MUROS DE CONCRETO ARMADO

5.01 ENCONFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 128.00 35.00 4,480.00


PRESUPUESTO - OBRAS CIVILES

OBRA : CONSTRUCCION DE VIVIENDA MULTIFAMILIAR


MODALIDAD: : A TODO COSTO
CLIENTE GINA MARTEL OSORIO
LUGAR VILLA MARIA DEL TRIUNFO -LIMA FECHA 12/02/2019

ITEM DESCRIPCION und. MET P-U PARCIAL S/.


5.02 ACERO CORRUGADO FY=4200KG/CM2 GRADO 60 PARA VIGAS kg
840.20 4.90 4,116.98
5.03 CONCRETO F/C=210KG/CM2 EN VIGAS m3 11.46 380.00 4,354.80
5.00 INSTALACIONES ELECTRICAS
5.01 TABLERO METALICO Und. 2.00 280.00 560.00
5.02 SALIDA DE TECHO CON CAJA METALICA PESADA PTO 22.00 60.00 1,320.00
5.03 SALIDA PARA TOMACORRIENTES PTO 23.00 60.00 1,380.00
5.04 SALIDA PARA INTERRUPTORES PTO 16.00 60.00 960.00
5.05 TUBERIAS PVC SAP (ELECTRICAS) D=3/4" ML 60.00 6.00 360.00
6.00 SISTEMA DE DESAGUE
6.01 CAJAS DE DESAGUE Und. 1.00 120.00 120.00
6.02 SALIDAS DE PVC SAL PARA DESAGUE DE 2" pto 12.00 55.00 660.00
6.03 SALIDAS DE PVC SAL PARA DESAGUE DE 4" pto 10.00 65.00 650.00
6.05 TUBERIA DE PVC SAL 2" m 30.00 12.00 360.00
6.06 TUBERIA DE PVC SAL 4" m 30.00 18.00 540.00
7.00 SISTEMA DE AGUA
7.01 VALVULA DE 3/4" Und. 2.00 140.00 280.00
7.02 VALVULA DE 1/2" Und. 5.00 120.00 600.00
7.04 RED DE AGUA 1/2" ML 25.00 8.00 200.00
7.06 SALIDA DE AGUA 1/2" PTO 14.00 60.00 840.00
7.07 SALIDA DE AGUA CALIENTE 1/2" PTO 7.00 70.00 490.00
7.08 RED DE AGUA CALIENTE 1/2" ML 35.00 10.00 350.00

COSTO DIRECTO EN SOLES ( NO INCLUYE IGV)


VALIDEZ DE OFERTA 15 DIAS
TIEMPO DE EJECUCION 45 DIAS
FORMA DE PAGO 50% A LA FIRMA DEL CONTRATO
50 % POR VALORIZACION SEMANAL
GARANTIA 7 AÑOS
PERSONAL DE CONTACTO GRABIEL SANCHEZ/ 995084708-998845436
EL PERSONAL QUE PARTICIPA EN LAS ACTIVIDADES CUENTA CON EPP Y SCTR.
EL PRESUPUESTO SE ELABORO TENIENDO EN CUENTA LAS CARACTERISTICAS FISICAS EXISTENTES.

NOTA:
1. El presupuesto que se adjunta contempla la construccion de Sotano y 1er Piso, teniendo en cuenta los
planos proporcionados. no se considera acabados. (tarrajeo, puertas, ventanas, otros).
2. No se considera corte de terreno, no hay plano de corte y por las fotos evidencia que si habra corte y
nivelacion de terreno.
3. El precio de excavacion es en terreno natural, de existir roca se tendra que modificar el precio
4. No se considera acarreo de materiales mayores a 20m de distancia.
5. El presupuesto esta calculado a todo Costo (materiales y mano de Obra), si se quiere desagregar la
mano de Obra asciende al 50% del Total.
TOTAL S/.

3,440.75

5,418.52

2,195.94

13,314.20

8,940.88

19,078.94

12,428.80

5,852.00

12,951.78
TOTAL S/.

4,580.00

2,330.00

1,920.00

92,451.81

EZ/ 995084708-998845436

y 1er Piso, teniendo en cuenta los


entanas, otros).
os evidencia que si habra corte y

ra que modificar el precio

bra), si se quiere desagregar la

S-ar putea să vă placă și