Republic of the Philippines

DEPARTMENT OF EDUCATION
Region 02-Schools Division of Isabela
QUEZON DISTRICT
CALLANGIGAN ELEMENTARY SCHOOL-103565
Quezon

PROJECT: CONSTRUCTION OF WASHING FACILITY OWNER: DEPARTMENT OF EDUCATION


SCHOOL: CALLANGIGAN ELEMENTARY SCHOOL SUBJECT: APPROVED AGENCY ESTIMATE
LOCATION: Callangigan, Quezon, Isabela
ITEM DESCRIPTION UNIT QTY UNIT COST TOTAL COST GRAND
NO. MATERIAL LABOR MATERIAL LABOR TOTAL
GENERAL REQUIREMENTS
Mobilization/Temporary
Structures, Utilities and
Services/Demobilization
A Earthworks
Mixed Gravel and Sand load 3 3,500 10,500.00 10,500.00
Sub-Total 10,500.00

B Concreting Works
Portland Cement bag 40 240.00 9,600.00 9,600.00
Sub-Total 9,600.00

C Rebar Works
10mm x 6mm RSB Pc 30 138.00 4,140.00 4,140.00
9mm x 6mm RSB Pc 30 110.00 3,300.00 3,300.00
Sub-Total 7,440.00

D Form Works

Sub-Total

E Masonry Works
#16 Tie Wire Kg 6 80.00 480.00 480.00
Sub-total 480.00

F Roofing Works

Sub-total

G Tile Works

Sub-total

H Plumbing Works

Sub-Total

I. MATERIALS 28,020.00
II. LABOR
III. TOTAL COST (I II) 28,020.00
Prepared by: Recommending Approval: Approved:

OLIVIA L. BOLEYLEY FILFLOR T. DUQUE JESUS D. ANTONIO


Head Teacher 3 Division Engineer Chief, School Governance
& Operations Division
Republic of the Philippines
DEPARTMENT OF EDUCATION
Region 02-Schools Division of Isabela
QUEZON DISTRICT
CALLANGIGAN ELEMENTARY SCHOOL-103565
Quezon

PROGRAM OF WORKS
DepEd – CY 2018 - Region 02 – Schools Division of Isabela

School: Callangigan Elementary School Date:


Budget Allocation: 28,020.00
Region: 02 Estimated Government Expenses: 28,020.00
Division: Isabela Approved Budget for Contract: 28,020.00
Project Title: Completion Period: March-June 2019
Minimum Required Manpower:
Flooring of Covered Court General Foreman Carpenter
Helper Mason
Plan: DepED Plans Minimum Required Equipment:
Location: CALLANGIGAN, Quezon, Isabela Hand Tools

Item I.D. Item Description % of Total Unit Quantity Total Cost Remarks
I. DIRECT COST
General Requirements
A Earthworks lot 1 10,500.00
B Concreting Works lot 1 9,600.00
C Rebar Works lot 1 7,4400.00
D Masonry Works lot 1 480.00
E

II. TOTAL COST 28,020.00

Prepared by: Recommending Approval: Approved:

OLIVIA L. BOLEYLEY FILFLOR T. DUQUE JESUS D. ANTONIO


Head Teacher 3 Division Engineer Chief, School Governance
& Operations Division