ST.

MARY’S POLYTECHNIC COLLEGE, PALAKKAD


(Under The Patronage of Diocese of Palakkad)
Approved by AICTE and affiliated to DTE, Kerala

DEPARTMENT OF CIVIL ENGINEERING


REPORT
ON
INDUSTRIAL TRAINING
AT
MARY MATHA CONSTRUCTION COMPANY
(November 2019)

Presented By
GROUP4

Name: juwel Thomas Reg


no:17011545
Akhil chandran 17011514
T.S harikrishnan 17011570
Chandhu K.T 17011529
Vimal shaju 17011571

ST.MARY’S POLYTECHNIC COLLEGE, PALAKKAD


(Under The Patronage of Diocese Palakkad)
Approved by AICTE and affiliated to DTE Kerala

DEPARTMENT OF CIVIL ENGINEERING

CERTIFICATE

This is to certify that the Seminar Report is the bonafide work done by ​GROUP4 (REG NO:
********) of Fifth semester Civil Engineering, in partial fulfilment of the requirement for
the award of Diploma in Engineering course under DTE Kerala during the course period
2017-2020.

Faculty in-charge Head of Section

Internal Examiner External Examiner


Date …………...
Place …………..

GROUP​ ​MEMBERS

Name Reg No.


JUWEL THOMAS 17011545
VIMAL SHAJU 17011571
T.S HARIKRISHNAN 17011570
CHANDHU K.T 17011529
AKHIL CHANDRAN 17011514
​ACKNOWLEDGEMENT

I am glad to present my Industrial Visit Report which was prepared as a part of my Diploma programme in
Civil Engineering. With profound sense of indebtedness, I use this opportunity to express my sincere thanks
to our beloved principal Mr. Raimon Francis for all the help and guidance rendered during the preparation of
Industrial Visit Report. I express my sincere gratitude to Mrs.Betsy M V (Head of Section, Civil
Engineering) for his healthy cooperation, constant encouragement and inspiration. I wish to extend my
thanks to my guide, Mr Anurag M (Lecturer in Civil Engineering) for his kind interest, valuable guidance
and support rendered. Last but not the least I extend my sincere thanks to ​Mary matha construction
company and specially Mr.paul francis (Assistant Executive Engineer) and Mr. jayaraj k.m (Assistant
Engineer) for their help and support.
ABSTRACT

A​ccording to the promises and commitments of the Kerala government, MARY MATHA has been time
and again proving itself as a pioneer of development, creating a state-of-the-art city of substance. PWD has
been working on widening all main roads, construction of overbridges, under bridges and flyovers to
regulate the traffic on roads,minimize pollution, and ensure public convenience and safety. PWD firmly
believes in bridging the gap and reaching out to its citizensand to provide them with quick and hassle-free
service.
CONTENTS
NO CHAPTER PAGE
NO

1 INTRODUCTION
2 SITE DETAILS

2.1 Site location

2.2 Company profile

2.3 Work details

3 DAILY WORK LOG

4 TECHNICAL CONTENTS

4.1 Details of structure

4.2 QA/QC lab

4.3 Safety at site

4.4 Process

4.5

4.6

5 CONCLUSION
​INTRODUCTION

The​ ​practical experiences are improvised for students​ to ​discover the working environment.The Industrial
visit really exposes students to industry based skills student of tertiary institution the opportunity of being
familiarized and exposed to the needed experienced in handling the skills in the field of construction which
are usually not available in the educational institutions.we have assigned ​MARYMATHA
CONSTRUCTION COMPANY

​We have great fortune to visit the sites which is not usually possible.The project was kundanoor
flyover,a fly over which is situated at the kundanoor junction with a 701 meter long six lane on the fly over
and the estimated cost is 74.45 core.Finally we also had a chance to watch the slab errection in the site.this
report gives the summary of the work experience and the knowledge we acquired during 10 days training
period.
SITE DETAILS

2.1 ​Site location

Site situated 4km from vyttila hub


2.2 ​Company profile
​Marymatha Construction ​Company​ is a partnership firm and a leading reputed construction
company in Kerala Registered in 1992. The registered office of the Company is situated at Muvattupuzha,
Ernakulam District. The company has obtained Class ‘A’ license for this purpose from the Government of
Kerala. The floating of this company by the partners of the firm was with the intention of corporatizing their
construction contract work business, to achieve goals and ambitions in the challenging scenario of
globalization and professionalization quality and efficiency in operations. The company is very much
confident for undertaking any major work by ensuring thanks to the proven ability and track record of the
partners. The company’s formation was on 01/11/1992, by our visionary Mr. M.P. Cherian, a dedicated and
idealistic person, who is the guiding lamp of the company ever since its formation. The Partnership Deed
was signed on 01/11/1992 and amended on 01/04/2004. The company became registered on 14/05/1999.
During the period of 2000 – 2001 the turnover was 1.19 Crores and then it expanded to 27.34 crore during
the period 2007-2008 and later it rose to 68 crore during 2013-2014 within a short span and again during
2015-2016 it became 119.76 cr. We achieved this only because of the thoughtful perceptions of our Founder
Sri. M.P. Cherian, Managing Partner Sabu Cherian, Partners Sen Cherian, and Sibu Cherian. And now with
a projected turnover of Rs. 360 crore the company is engaging in versatile nature of civil construction works
such as Barrage Construction, Regulator cum Bridges, Water Treatment Plant, Over-head reservoirs,
Multi-storied green and smart buildings, protection works in water beds such as Kuttanad paddy fields, Land
development works, highways, Pipe laying works, Canal works, etc.

2.3 ​Work details


​CONSTRUCTION OF FLYOVER AT KUNDANOOR,VYTTILA

Owner department : public work department(PWD0

Contractor : Mary matha construction company


Contractor amount : 74.45 cores

Area : 701 meters lane


​DAILY WORK LOG

Date Activities
20/5/2019 Foundation
21/5/2019 Piling
22/5/2019 Concreteing the girder
23/5/2019 Grouting the girder
24/5/2019 Reinforcement off abutment
25/5/2019 Tenstioning of girder
27/5/2019 Erection of slab on girder
28/5/2019 Pier cap construction
29/5/2019 Concreting the girder using boom
spacer
30/5/2019 Stress applied in the girder

​TECHNICAL CONTENTS

4.1 ​DETAILS OF STRUCTURE


1.​ ​Pile cap​: • ​Formation of pile- pile cap= R.L of existing ground level-cut off level Pile cap is formed
by combination of pile and then binding the steel followed by shuttering • Dimension of pile caps- for
P1 to P15: length= 16m, breadth=5.2m, height=1.8m for P16 to P19: length= 12.4m, breadth= 5.2m,
height= 1.8m for P21, P23, P24, P26, P27, P29, P30, P32, P33, P21A, P20A, P23A, P20
length=breadth= 5.2m, height=1.8m for P22,P25, P28, P28, P31, P22A length= 8.8m, breadth= 5.2m,
height= 1.8m After piling completion, soil is excavated for construction of pile cap. For proper pile cap
P.C.C. Is provided for separation from mud. At site 75mm thick PCC is carried out for control over
seepage​. 
2. ​Reinforcement steel in Pile cap​ ​• ​Grade of concrete used M35 S.no. BARS 1. 20mm
@140mm c/c 2. 16mm @140mm c/c 3. 32mm @90mm c/c 4. 32mm @180mm c/c 5. 16mm @180mm
c/c
3. PIER SHAFT​ ​A pier shaft is a raised structure provided mostly at the centre of the pile cap
which supports the structure and transfer the several types of load to the foundation. DIMENSION
OF THE SHAFT: length= 2m, breadth= 2m, height= and length= 1.5m, breadth= 1.5m, height=
REINFORCEMENTS IN SHAFT: S.no. BARS 1. 4 sides 17 NOS. 32mm 2. 4 sides 10mm @100
c/c 3. 4 sides 10mm @200 c/c 4. 16mm @100 c/c 5. 12mm @200 c/c 6. Links 10mm @200 c/c 
4.  ​PIER CAP​- ​Pier caps are the topmost structure of the substructure. Above these the​ ​superstructures
(segments & girders) are placed. DIMENSIONS OF PIER CAPS: For P1 to P14: Length= 6m,
Breadth= 3.3m For P23, P26, P29, P32, P33, P20A : Length= 5.4m, Breadth= 2.8m For P21, P24,
P27, P30, P31, P21A : Length= 5.4m, Breadth= 1.9m For P15, P19 : Length= 11.4m, Breadth=
2.8m For P16 to P18 : Length= 11.4m, Breadth= 2.4m GRADE OF CONCRETE FOR CASTING
M 35 Except pier 17 ,where M 40 is used​. 
5. REINFORCEMENT USED IN PIER CAPS​.no. BARS 1. 12mm @150 c/c 2. 25 nos.
32mm ,top bar 3. 2*5 16mm 4. 12mm @150mm c/c, LV bar 5. 17 nos. 20mm, hunch bar 6. 25mm
@125 c/c, Loop 7. 5 nos. 16mm @125mm c/c, Ring 8. 3 nos. 16mm @200mm c/c, Ring 9. 12mm
@150mm c/c, bottom bar 10. 24 nos. 20mm @435 c/c in four layers, 6 in each layer
6.  ​BEARINGS, PEDESTALS, SEISMIC STOPPERS​ ​After the accumulation of all the
reinforcements in pier cap a surface is formed over which Bearings, Pedestals and Seismic stoppers
are provided as per the design. Seismic stopper: The current designs of seismically designs as a
second line of defence. These structures allow development of in-service moments of the deck,
without transmitting loads on pier and foundation, while during earthquake they resist the entire
seismic action. Height of stopper= 1.2m LV bars are used of 400mm & 700mm ,16mm​ ​dia.
 

4.2 ​LAB DETAILS


1​.SLUMP TEST
​Concrete slump test is to determine the workability or consistency of concrete mix prepared at the
Laboratory or the construction site during the progress of the work.Concrete slump test is carried

Out from batch to batch to check the uniform quality of concrete during construction.

​2.​ ​COMPACTION FACTOR TEST

​Compaction factor test is the workability test for concrete conducted in laboratory. The
compaction factor is the ratio of weights of partially compacted to fully compacted concrete. It was
developed by Road Research Laboratory in United Kingdom and is used to determine the
workability of concrete
The compaction factor test is used for concrete which have low workability for which

slump test is not suitable​.


4.3 ​SAFETY AT SITE
​ ersonal protective equipment (PPE​)​ are supplied to all the personnel’s working on site and
P
even for the personal who are temporary visiting to the site
Personal protective equipment (PPE) can be classified as:

o Minimum Personal protective equipment (PPE)


o Protective gloves
o Hearing protection
o Full face shields when cutting, grinding, or chipping
o Chemical splash goggles
o Respiratory protection
o Fall protection equipment when working above 6 feet
o Specific protective clothing such as welding leathers when welding or FR clothing when working
with live electric
o

o Additional Personal protective equipment (PPE)


4.4 ​PROCESS
​ ​ he construction process is also a lot faster because of the introduction of a multitude of different
T
heavy construction equipment.Many stages involved in the construction of a flyover.we were reached on the
second stage of the process which includes.

​First of all, the alignment of the flyover is laid out and the pier and abutment locations are located. If there
are piles for the abutments or piers, they will excavate to the appropriate depth and begin by driving pile.

If they are shallow footings, then they will excavate to the appropriate depth, compact the subgrade material,
and possibly build a leveling, or rat slab. The picture below is of a rat slab for a pile foundation. There were
64 pile for each pier location on this project​.

The rat slab provides a level place to start tying your rebar. A shallow foundation is pictured below.

The concrete is then placed on the bottom portion of the foundation, within formwork, or using the ground
as a form.

The pier column or abutment concrete is then placed.

The place steel or precast girders, or box girders, etc.


Then we work on building our deck with either precast slabs or by placing a concrete deck

Then,we builded roadway and paint pavement markings and the work is done.
CONCLUSION

The main aim of studies within this project was to investigate how a flyover is constructed within the desired
properties.We get knowledge about the basic and advanced techniques of flyover construction as well as saw
the challenges which a civil engineer have to face during construction i.e. labour problems,cost
management,envitomental challenges etc.We cleared our many doubts regarding flyover construction.
During the period of 14 days the company staff helped us a lot to provide all the information about the project.So we
are grateful to all staff of ​MARY MATHA CONSTRUCTION COMPANY.​As well as we are so thankful to
our Civil engineers for their kind support.