Sunteți pe pagina 1din 30

PT.

Prima Energi Consult


Engineering & Consulting
Vision & Mission
VISION MISSION
• Extending network of highly qualified
professional to build up competencies and
“Aspire to be a Global expertise
Engineering & Consulting • Build up strong base in capability and
flexibility in embracing need of clients
Company in Energy Industry” • Providing innovative solution in engineering
and consulting services to fulfill industry
needs
Key Personel
• Dr.Ir. Djuanda N Ibrahim, MM // Corporate Senior • Djoko Trijardi // Senior Civil Engineer
Advisor – >15 years experience & Expert in Civil/
– Former BOD PT. PLN architectural projects.
– Former CEO PT. Rekadaya Elektrika • Erman Stefri Malotu // Senior Electrical Engineer
• Ir. Imam Mashud // Technical Senior Advisor – >15 years experience & Expert electrical and
– Former Head of T&D Division of PT. PLN Inspector for several fossil & Renewable
– Former CEO PT. PLN Enjiniring (PLNE) Project/Studies,Substation and Transmission
• Ir. Widyaka Kartanegara, MM.(Jack) // President • Elyasta Winanta // Senior Mechanical Engineer
Commissioner – >25 years experience as Senior Project
– Former Energy Technical Service for Engineer (Project Engineering)
International Consultant – Have qualification for Gas to Power &
– Co-Founder of PEC Pipeline Project
Capabilities & Competencies
• PEC engaged mainly Energy Industry
• We provide consultation in:
– For Owner/ IPP/ Developer • For EPC
• Pre-Feasibility Study (Pre-FS) • Engineering Estimate
• Feasibility Study (FS) • Detail Engineering Design (DED)
– Topography & Soil Investigation
– Special Facilities Study
– Interconnection & Grid Impact Study
• Front End Engineering Design (FEED)
• Owners Estimate (OE)
• Other services:
• Tender/ Bidding Document • Technical Due Diligence of Power Plant
• Design Review Asset Take Over
• Construction Supervision • Operation & Maintenance
Certificate of Enterprises and Classification Company
Licenses & Certificates
Exclusive Appointment from MEGAJOULE

PEC as Country Exclusive Partners for


Consultancy and Assessment Services in Wind
& Solar Energy

• International renewable energy consultant


based on Portugal
• Leader in wind resource assessment in
Portugal & one of the leading
European markets for wind energy
• Has made more than 25 GW of wind and 3
GW of solar studies worldwide
• Has supported wind farm development in 25
countries worldwide
• Has installed or operated more than 400 met
masts
Foot Print
Coal Handling
Gurimbang

Coal Handling
Tuhupan

Coal Handling
PLTU Suralaya

Coal Handling
Paiton
• MINING PROJECT
DED OPCC (Out-of-Pit Crushing & Conveying
System) Tutupan

Owner: PT. Adaro Indonesia (PT.Adaro Energy, Tbk)


Main Client: PT.Sanggar Sarana Baja & PT.Korindo (FLSmidth subs)
Project: Detail Engineering Design (DED), Jabodetabek
Duration: 5 months (2012)
Description:
Vendor for Detailed Engineering Design (DED) service include Construction
Drawing & Shop Drawing in Fabricators.
Scope include detailing for Conveyor, Carbody, Gimble and Suspension to be
weld and fabricate in the workshop

-
QA/QC Services OPCC (Out-of-Pit Crushing
Conveying) Tutupan

Owner: PT. Adaro Indonesia (PT.Adaro Energy, Tbk)


Main Client: FLSmidth
Project: QA QC Services during Fabrication Process for OCCS
Tutupan
Duration: 13months (Feb 2012 – March 2013)
Description:
Send our QA/QC engineer to several location example: Cigading,
Jagat Baja, SSB, Korindo etc to supervise and check the fabrication
result before send out Delivery Certificate.

-
Engineering Support EPC CHP/CHF & Jetty
Project

Owner: PT.Nusantara Energy


Main Client: GS E&C (South Korea)
Project: Enginering Support to EPC Consortium (PPE-PEC)
Duration: 3 months (2018)
Description:
• Preliminary Site Survey
• Engineering Detailed Survey and Reporting
• Basic Engineering Design (BED)
• Detailed Design Engineering (DED)
• Technical Proposal of Supply
• Concept Design
• Material Process Flow Diagram (PFD)
• Main Equipment Specification
• Balance Of Plant (BOP) Equipment
• Civil and Building Works Key Specification

-
Feasibility Study for Improvement in Coal
Handling & Coal Shelter PLTU Paiton 1 & 2

Owner: PT.Pembangkitan Jawa Bali (PJB)


Main Client: PT.Reconsult
Project:Engineering Study Coal Handling Yard & Coal Shelter
PLTU Paiton 1 & 2 Situbondo East Jawa.
Duration: March 2019
Description:
• Preliminary Site Survey
• Engineering Detailed Survey and Reporting
• Basic Engineering Design (BED)
• Technical Proposal of Supply
• Concept Design
• Material Process Flow Diagram (PFD)
• Main Equipment Specification
• Balance Of Plant (BOP) Equipment
• Civil and Building Works Key Specification
• Owner Engineering Estimate

-
Feasibility Study for Coal Terminal
Investment

Owner: Yayasan Dana Pensiun PLN


Main Client: PT.Reconsult
Project:Feasbility Study for Coal Terminal in Kalimantan
to Supply PLTU Eastern Indonesia
Duration: March 2019
Description:
• Preliminary Site Survey & Selection
• Engineering Detailed Survey and Reporting
• Basic Engineering Design (BED)
• Technical Proposal of Supply
• Concept Design
• Material Process Flow Diagram (PFD)
• Main Equipment Specification
• Balance Of Plant (BOP) Equipment
• Civil and Building Works Key Specification
• Owner Engineering Estimate

-
• OTHER PROJECT
Detail Engineering Design
Gas Engine Power Plant
(Central Kalimantan)
Owner: PT. PLN
Main contractor: PT. Pembangunan Perumahan (PP)
consortium with Wartsila (Finland)
Project: Gas Engine Power Plant (GEPP) Stage #2 140
MW, Bangkanai, Central Kalimantan
Duration: 2017 - present
Description:
• Sub-contractor for Detailed Engineering Design
(DED) service for GEPP owned by State Electricity
Company (PLN). Where the Gas Engine
Generator are 16 x 9,7 MW 20V34DF type.
• The scope include As Built Drawing service
during construction.
Special Facilities Study
Renewable Energy
(Solar PV Power Plant – Bali)
Owner: PT. Infrastruktur Terbarukan Dinamika (Equis Group)
Project: Special Facilities Study for East Bali 50MWp Solar Farm
Duration: 4 months (Dec 2017 - March 2018)
Description:
Facilities Study applies in identifying the necessary equipment for the
connection of the proposed project to the PLN 150KV Bali Transmission
system Line and Substation. Specifically the study presents the
following:
• 150KV Connection Strategy
• Substations & Transmission equipment specification
• Identify the appropriate Routing, Tower Schedule +/-20km, 150 kV
transmission line plan and design of Substation of Power plant and
Extension of PLN Bay.
Grid Impact Study
Renewable Energy
(Solar PV Power Plant – West Java)
Owner: PT. Sinar Energi Indonesia
Project: Grid Impact Study for West Java 1MWp Solar
Farm
Duration: 1 month (May 2018 - Present)
Description:
This study was made to find out alternatives point of
connection and the interconnection scenario for each
alternatives.
Also to know the impact that will be caused by the
additional connection of the new plant to PLN system.
Finally the purpose of this study is to know the
feasibility of Solar PV Plant development both from
technical and financial view.
Special Facilities Study
Renewable Energy
(Wind Power – South Sulawesi)
Owner: PT. Energi Bayu Jeneponto (Equis Group)
Project: Special Facilities Study for Tolo1 Wind Farm Power Plant 60
MW, South Sulawesi
Duration: 3 months (2016-2017)
Description:
Facilities Study applies the findings in the S/S in identifying the
necessary equipment for the connection of the proposed project to the
transmission system. Specifically the study presents the following:
• 150KV Connection Strategy
• Substations & Transmission equipment specification
• Identify the appropriate telecommunication and protection facility
for 3.1 km, 150 kV transmission line plan, profile and design.
Design Review
Renewable Energy
(Wind Power – South Sulawesi)
Owner: PT. Energi Bayu Jeneponto (Equis Group)
Main consultant: PT. WorleyParsons Indonesia
Project: Design Review for Detailed Engineering Design of Tolo1
Wind Farm Power Plant 60 MW, South Sulawesi
Duration: 2017-present
Description:
• Sub-consultant for Design Review for Wind Farm Power
Plant 60MW owned by Independent Power Producer (EBJ)
• Scope including Electrical, Civil and Mechanical Design
Review of Power Plant Substation, OHL/ transmission line
150kV and PLN Substation
Engineering Estimate
Substation & Transmission Line
(Coal-Fired – North Sumatera)
Owner: PT. Rekadaya Elektrika
Project: Engineering Estimate Package Transmission & GITET
275KV PLTU Sumut 2
Duration: 3 months (October 2017 - December 2017)
Description:
• 275 kV Power Plant Substation; 4 diameters
• 275 kV Medan Barat (Helvetia Substation); 2 diameters
• 150kV Medan Barat (Helvetia Substation); 6 bays
• IBT (Interbus Transformator) 275/150 kV; 500 MVA; 2
units
• 275 kV Medan Timur (Percut) Substation; 4 diameters
• 275 kV Transmision Line, 2 cct ACSR 4x430mm2, from
Power Plant to Medan Barat Substation; 19KM
• 275 kV Transmision Line, 2 cct ACSR 4x430mm2, from
Power Plant to Medan Timur Substation; 14.2KM
• Crossing Works
Feasibility Study
Underground Cable for Transmission
(East Java)
Owner: PT. Prima Layanan Nasional Enjiniring (PLNE)
Project: Feasibility Study of 500KV Transmission
Underground Cable in Grati - Surabaya Selatan
Duration: 2 months (September 2017 - October 2017)
Description:
Joint partners with PT. Tractebel Engineering Indonesia
(Engie Group)
Joint site survey, geotechical analysis, transmission capacity
analysis, Options development, method selection, cost
investigation, HVAC Design, tunneling & HDD research and
design & drafting.
FEED & Construction Supervision
Renewable Energy
(Geothermal – South Sumatera)
Owner: PT. Pertamina Geothermal Energy (PGE)
Main consultant: Electroconsult (ELC)
Project: Geothermal Power Plant (GPP) 2 x 55 MW,
Lumut Balai, South Sumatera
Duration: 2011 - present
Description:
• Part of joint consultant for FEED, Construction
Supervision and Quality Assurance/Quality Control
(QA/ QC).
• Sub-Surface Geoscience Engineering, confirming
previous study of Steam Reservoir, Process Design,
Mechanical Design, Structure & Civil Design, I&C
Design and Environmental Study.
Pre Feasibility Study
Coal Fired Power Plant
(East Kalimantan)
Owner: WUHUAN – SNS Consortium
Project: Pre-Feasibility Study for Kaltim3 & Kaltim6
Coal-Fired Steam Power Plant (CFSPP) 1x200 MW,
East Kalimantan
Duration: 3 months (2016-2017)
Description:
The result of this Pre-Feasibility Study is to produce a
valuation report on the technical aspects and the
environment.
In order the studies can be used by employers in the
decision whether feasible or not to construct the power
plants.
It is also used as a part of bid document for the
Procurement of power supply purchase (1X200 MW)
Kaltim3 & Kaltim6 Coal-Fired Steam Power Plant (CFSPP)
Independent Power Producer project.
Construction Supervision
Coal Fired Power Plant
(South Sulawesi)
Owner: PT. Rekadaya Elektrika
Project: Construction Supervision & Quality Assurance/ Quality
Control Coal-Fired Power Plant Asam-Asam 2x65 MW Unit 3 & 4
Duration: 5 years (2010-2014)
Description:
PEC was appointed as joint consultant for construction supervision
and QA/QC for CFPP owned by PT. PLN. Supervise joint contractor
from Indonesia and China.
Schedule monitoring, witnessing on behalf of owners, supervise
commissioning and installation, review TOC document.
Construction Supervision
CNG Marine Plant
(East Java)
Owner: PT. Prima Layanan Nasional Enjiniring
Project: Construction Supervision Service for CNG Marine Gresik-Lombok
Facilities
Duration: 2014 - present
Description: CNG Marine project is construction of compressing station where the
gas is compressed into marine vessel at Gresik, East Java and transported to
decompression station at Lombok, West Nusa Tenggara.
The decompressed gas then used for Peaking Gas Power Plant.
PEC provide supervision in:
• Gas Process Engineer
• Process Safety Engineer
• Safety Engineer
• Mechanical, Electrical and I & C Inspectors
FEED (Front End Engineering Design)
Gas Pipeline
East Kalimantan
Owner: PT. PLN (Persero)
Main consultant: PT. Prima Layanan Nasional Enjiniring (PLNE)
Project: 55 km Gas Pipeline for Power Plant, East Kalimantan
Duration: 3 months (2015)
Description:
• Conduct field survey for Soil Investigation & Topography Survey
• Gather information and data for Feasibility Study (FS) preparation in terms
of Technical, Social Environment, Financial Study, etc.
• Conduct documents for tender preparation such as FEED, Owner Estimate
(OE), and Bidding Document.
• 55 km pipeline from Nilam Central Facilities (PK 52) to Tanjung Batu CCPP in
Tenggarong Seberang.
Other Experiences
1. Design Engineering for PLTD 120 MW & Geothermal 5 MW, PT. Quatra Power Engineering
2. Design Engineering Review services for Add On Gas Turbine Power Plant 40 MW, PT. Betasurya Tatagraha
3. Proposal Engineering for Subsea Pipeline Project (Design Engineering & Street Analysis), PT. Pacific Process engineering
4. Detail Engineering of Design Civil service for Coal Fired Steam Power Plant 2x10 MW, PT. Wijaya Karya
5. Structural Engineering for New Condensate & Diesel Tanks BP Tangguh, PT. Wijaya Karya
6. Civil Engineering Design Service for Coal Fired Steam Power Plant 2x25 MW, PT. Soma Daya Utama
7. Civil Engineering Design Service for Gas Fired Steam Power Plant 2x235 MW
8. Quality Assurance/ Quality Control Engineering Mining Fabrication, PT. FLSmidth Indonesia.
9. Quality Assurance/ Quality Control Engineering Oil & Gas Fabrication, Pt. Sanggar Sarana Baja.
10. Technical Assessment of Cathodic Protection System Coal-Fired Power Plant 660 MW, PT. Rekadaya Elektrika.
11. Technical Assessment for Power Generation Asset (PLTD Pontianak & PLTD Medan), PT. Global Karya Inti.
12. Remaining Life Assessment of Boiler Service for Coal-Fired Steam Power Plant 15 MW, PT. Energi Alamraya Semesta.
Reference Letter
Thank You

S-ar putea să vă placă și