WORK METHOD STATEMENT

METHOD STATEMENT FOR SCAFFOLDING


(ERECTION AND DISMANTLE) #
(GT AREA,GIS,CCW BSDG,AIR COMPRESSOR
AREA, HRSG, PRDS,STG,CT,MED,LIMESTONE&
BOP AREA,CO2 PLANT,PORTABLE WATER
PUMP HOUSE)
WORK METHOD STATEMENT

1. Scope & Purpose

SCAFFOLDING (ERECTION AND DISMANTLE) # (GT AREA, GIS, CCW


BSDG, AIR COMPRESSOR AREA, HRSG, PRDS,STG,CT,MED,LIMESTONE& BOP
AREA,CO2 PLANT,PORTABLE WATER PUMP HOUSE)
Work Procedures

 General planning
 Tool box talks
 Transport and lifting of scaffolding
 Erection of base frames/standards and bracing
 Erection of working platforms
 Erection of ladder and toe boards
 Dismantle and modification
 House keeping

2. Safety Control Measures


 Qualified and sufficient skills person used for scaffolding erection
 Different scaffolding not mixed together
 Appropriate type of scaffold used foe job
 Visual checking and inspection every week
 Safety audits
 Lifting equipment’s and gear must be inspected regularly
 Boom truck must be check regularly sole boards to be correct length
for soft ground
 No climbing unbraced scaffold
 2 persons used for pass materials to higher lifts
 Handrail positioned not below 900mm and above 1100mm the
working platforms on all sides
 Clear proper access
 Store hand tools in designated places
 Emergency number 44306666
WORK METHOD STATEMENT

3. Tools Requirement

 Tube
 Board
 Clamp
 Ladder
 3 ton pick up
 Forklift
 Hand spanner tools

4. Attachments

 JOB SAFETY ANALYSIS