TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES

Ayala Blvd., Ermita, Manila

COLLEGE OF ENGINEERING
Civil Engineering Department

PROJECT TITLE: PROPOSED FIVE-STOREY RESIDENTIAL BUILDING WITH ROOF DECK


OWNER/S: Sps. LEON T. TAPEL Jr, & IMELDA L. TAPEL
LOCATION: BACLARAN, PARANAQUE CITY

DURATION START FINISH


MARK ACTIVITY FLOAT
DAYS EARLY LATE EARLY LATE
A MOBILIZATION 7 0 0 7 7 0
B SITE CLEANING 5 5 8 10 13 3
C LAYOUT & STAKING 7 10 12 17 19 2
D EXCAVATION OF COLUMN FOOTING 5 20 20 25 25 0
E EXCAVATION OF WALL FOOTING 7 33 36 40 43 3
F SOIL POISINING 7 40 43 47 50 3
G FORMWROKS FOR COLUMN 175 50 50 225 225 0
H POURING OF CONCRETE FOR COLUMN FOOTING 20 55 55 75 75 0
I POURING OF CONCRETE FOR WALL FOOTING 20 55 55 75 75 0
J ASSEMBLY & CUTTING OF REBARS FOR COLUMN FOOTING 200 60 60 260 260 0
K ASSEMBLY & CUTTING OF REBARS FOR WALL FOOTING 200 60 60 260 260 0
L POURING OF CONCRETE FOR COLUMN 180 75 75 255 255 0
M POURING OF CONCRETE FOR SLAB ON FILL 180 75 75 255 255 0
N FORMWORKS FOR BEAMS & SLABS 150 75 77 225 227 2

Prepared By: Approved:

MACAIRAN, RICCA ANNE G. ENGR. MARJUN B. MACASILHIG


BSCE - 4C INSTRUCTOR
TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES
Ayala Blvd., Ermita, Manila

COLLEGE OF ENGINEERING
Civil Engineering Department

PROJECT TITLE: PROPOSED FIVE-STOREY RESIDENTIAL BUILDING WITH ROOF DECK


OWNER/S: Sps. LEON T. TAPEL Jr, & IMELDA L. TAPEL
LOCATION: BACLARAN, PARANAQUE CITY

DURATION START FINISH


MARK ACTIVITY FLOAT
DAYS EARLY LATE EARLY LATE
O ASSEMBLY & CUTTING OF REBARS FOR STAIRS 170 100 100 270 270 0
P FORMWORKS FOR STAIRS 150 120 125 270 275 5
Q INSTALLATION OF TILES AND FINISHING 170 145 150 315 320 5
R INSTALLATION OF PLUMBING 160 155 160 315 320 5
S INSTALLATION OF SEPTIC TANK 20 170 170 190 190 0
T INSTALLATION OF ELECTRICAL 165 185 185 350 350 0
U ASSEMBLY & CUTTING OF REBARS SLAB ON FILL 50 225 230 275 280 5
V LAYING OF CONCRETE HOLLOW BLOCK 10 273 275 283 285 2
W INSTALLATION OF HAND RAILS 50 270 270 320 320 0
X INSATLLATION OF DOORS & WINDOWS 50 270 270 320 320 0
Y PAINTING 80 270 270 350 350 0
Z INSTALLATION OF HARDWARE 70 298 300 368 370 2
AA FIRE PROOFING & WATER PROOFING 40 347 350 387 390 3
AB CLEANING & TURNOVER' 20 390 390 410 410 0
CRITICAL PATH: A-D-G-H-I-J-K-L-M-O-S-T-W-X-Y-AB
Prepared By: Approved:

MACAIRAN, RICCA ANNE G. ENGR. MARJUN B. MACASILHIG


BSCE - 4C INSTRUCTOR
MOBILIZATION SITE CLEANING
DURATION DURATION
10 days 5 days
START FINISH START FINISH
EARLY LATE A EARLY LATE EARLY LATE B EARLY LATE
0 0 7 7 5 8 10 13
TOTAL FLOAT TOTAL FLOAT
10 days 3 days
LAYOUT & STAKING EXCAVATION OF COLUMN FOOTING
DURATION DURATION
7 days 5 days
START FINISH START FINISH
EARLY LATE C EARLY LATE EARLY LATE D EARLY
10 12 17 19 20 20 25
TOTAL FLOAT TOTAL FLOAT
2 days 0 days
COLUMN FOOTING EXCAVATION OF WALL FOOTING SOIL POISONING
ATION DURATION DURATION
days 7 days 7 days
FINISH START FINISH START
LATE EARLY LATE E EARLY LATE EARLY LATE F
25 33 36 40 43 40 43
L FLOAT TOTAL FLOAT TOTAL FLOAT
days 3 days 3 days
CONCRETE POURING (CF)
DURATION
20 days
START
EARLY LATE
55 55
TOTAL FLOAT
SOIL POISONING FORMWORKS FOR COLUMN 0 days
DURATION DURATION
7 days 175 days
FINISH START FINISH
EARLY LATE EARLY LATE G EARLY LATE
47 50 50 50 225 225
TOTAL FLOAT TOTAL FLOAT
3 days 0 days CONCRETE POURING (WF)
DURATION
20 days
START
EARLY LATE
55 55
TOTAL FLOAT
0 days
CONCRETE POURING (CF) REBARS ASSEMBLY & CUTTING (CF)
DURATION DURATION
20 days 200 days
FINISH START FINISH

H EARLY LATE EARLY LATE J EARLY LATE


75 75 60 60 260 260
TOTAL FLOAT TOTAL FLOAT
0 days 0 days

CONCRETE POURING (WF) REBARS ASSEMBLY & CUTTING (WF)


DURATION DURATION
20 days 200 days
FINISH START FINISH
I EARLY LATE EARLY LATE K EARLY LATE
75 75 60 60 260 260
TOTAL FLOAT TOTAL FLOAT
0 days 0 days
CONCRETE POURING (COLUMNS)
DURATION
180 days
START FINISH
EARLY LATE L EARLY LATE
75 75 255 255
TOTAL FLOAT
0 days

CONCRETE POURING (SLABS) REBARS ASSEMBLY & CUTTING (STAIRS)


DURATION DURATION
180 days 170 days
START FINISH START
EARLY LATE M EARLY LATE EARLY LATE O
75 75 255 255 100 100
TOTAL FLOAT TOTAL FLOAT
0 days 0 days

FORMWORKS (BEAMS & SLABS)


DURATION
150 days
START FINISH
EARLY LATE N EARLY LATE
75 77 225 227
TOTAL FLOAT
2 days
SEMBLY & CUTTING (STAIRS) FORMWORKS (STAIRS) TILES INSTALLATION AND FINISHIN
DURATION DURATION DURATION
170 days 150 days 170 days
FINISH START FINISH START
EARLY LATE EARLY LATE P EARLY LATE EARLY LATE
270 270 120 125 270 275 145 150
TOTAL FLOAT TOTAL FLOAT TOTAL FLOAT
0 days 5 days 5 days
LES INSTALLATION AND FINISHING PLUMBING INSTALLATION SEPTIC TANK INSTALL
DURATION DURATION DURATION
170 days 160 days 20 days
FINISH START FINISH START
Q EARLY LATE EARLY LATE R EARLY LATE EARLY
315 320 155 160 315 320 170
TOTAL FLOAT TOTAL FLOAT TOTAL FLOAT
5 days 5 days 0 days
SEPTIC TANK INSTALLATION ELECTRICAL INSTALLATION
DURATION DURATION
20 days 165 days
START FINISH START FINISH
LATE S EARLY LATE EARLY LATE T EARLY LATE
170 190 190 185 185 350 350
TOTAL FLOAT TOTAL FLOAT
0 days 0 days
REBARS ASSEMBLY & CUTTING (SLAB) LAYING OF CHB
DURATION DURATION
50 days 10 days
START FINISH START FINISH
EARLY LATE U EARLY LATE EARLY LATE V EARLY LATE
225 230 275 280 273 275 283 285
TOTAL FLOAT TOTAL FLOAT
5 days 2 days
HANDRAILS INSTALLATION
DURATION
50 days
START FINISH
EARLY LATE W EARLY LATE
270 270 320 320
TOTAL FLOAT
0 days

D&W INSTALLATION HARDWARE INSTALLATION


DURATION DURATION
50 days 70 days
START FINISH START FINISH
EARLY LATE X EARLY LATE EARLY LATE Z EARLY LATE
270 270 320 320 298 300 368 370
TOTAL FLOAT TOTAL FLOAT
0 days 2 days

PAINTING
DURATION
80 days
START FINISH
EARLY LATE Y EARLY LATE
270 270 350 350
TOTAL FLOAT
0 days
FIRE AND WATER PROOFING CLEANING & TURNOVER
DURATION DURATION
40 days 20 days
START FINISH START FINISH
EARLY LATE AA EARLY LATE EARLY LATE AB EARLY LATE
347 350 387 390 390 390 410 410
TOTAL FLOAT TOTAL FLOAT
3 days 0 days