Documente Academic
Documente Profesional
Documente Cultură
Prepared By - Reviewed By -
Rev No. 00
Dtd: Commissioning Commissioning Project
Name
Sign
Approved By :
HEAD – Steering Committee
Copy No:
Issued To:
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./027
Plant Area: Turbine
2.0 OBJECTIVE
3.0 PROPOSAL
8.0 METHOD
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./027
Plant Area: Turbine
SL.NO
STATUS
a. STATOR
Stator Frame
End Shields
Stator Core
Stator winding
Hydrogen coolers
b. ROTOR
Rotor Shaft
Rotor windings
Rotor Retaining Rings
Field Connections
c. BEARINGS
d. SHAFT SEALS
1.2 The two pole generator is designed with direct water cooling for the
stator winding, phase connectors and bushings and direct Hydrogen
cooling for rotor winding. Generator losses, such as iron losses,
windage losses and stray losses are also dissipated through hydrogen.
The generator frame is pressure – resistant, gastight and equipped with
major components mentioned above. The hydrogen coolers are
arranged vertically inside the turbine end stator end field.
1.3 The Generator is provided with the following auxiliaries which are
essential for generator operation.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./027
Plant Area: Turbine
SL.NO
STATUS
1.5 Technical Specification of Generator are given below.
Generator Type THDF 115/59
Main Excitor Type ELR 70/90 – 30/6-20
Pilot Excitor Type ELP 50/42-30/16
Generator Apparent Power 588 MVA
Generator Active Power 500 MW
Current 16.166 KA
Voltage 21KV + 1.05KV
Speed 3000 RPM
Freqency 50HZ
Power Factor 0.85 (Lag)
Hydrogen Pressure 3.5 bar
Rated Field Voltage 340 V
Rated Field Current 4040 A
2.0 OBJECTIVE
3.0 PROPOSAL
3.2 Testing of pipe between Hydrogen Bottle rack and Hydrogen Unit at a
pressure of 4.8 bar of Nitrogen gas for 2 Hrs.
3.3 Testing of Pipe between Nitrogen Bottle rack and P.W. Tank at a
pressure of 5.0 bar of Nitrogen gas for 2 Hrs.
3.4 Leakage Test of Generator along with Gas System using air at 4.0 bar
for 72 Hrs
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./027
Plant Area: Turbine
SL.NO STATUS
4.3 Availability of
Test pressure gauge of range 0-6 KSC with least scale division
of 0.01 KSC
Mercury Manometer with mm scale
Generator winding Temp Indicator/Recorder in UCB.
Water ‘U’ Manometer
6.2 The test team should know well about the procedures to be adopted in
case of damage to machinery or injury to personnel connected to the
activity.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./027
Plant Area: Turbine
SL.NO
STATUS
7.0 STATE OF THE PLANT
7.2 Seal oil system commissioned and put into operation for continuous
running.
7.6 Stator winding filled with primary water and primary water tank kept
pressure less. All the valves closed in P.W. System. Connect a ‘U’
Tube manometer in Waste gas line of P.W. Tank after valve MKF91 AA
505 and close valve MKF91 AA 506. Open valve MKF91 AA 513 and
AA 505. It is also required to observe for any leakage into primary water
system through stator windings during air leakage test.
7.7 Instrument air supply connected before valve MKG25 AA 501. Air for
filling should be free from moisture, oil and any mechanical impurity.
7.10 Soap solution kept ready to check the leakages during test.
7.11 All the instruments in gas system are mounted as per scheme.
7.12 All the valves provided in H2 Unit are kept open so that all the lines are
pressurized during air filling. All valves connected to vents are kept
closed.
7.13 Valves provided in Generator oil drain lines are opened as follows:
(Liquid detector rack)
MKA 21 AA 501, MKA 22 AA 501, MKA 23 AA 501, MKA 24 AA 501,
MKA 23 AA 511, MKA 24 AA 511.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./027
Plant Area: Turbine
SL.NO
STATUS
7.14 Vent valves provided in oil drain lines are closed viz., MKA21 AA 502,
MKA 22 AA 502, MKA 23 AA 502, MKA 23 AA 512, MKA 24 AA 502.
7.15 Valves provided in gas impulse line for valve A1, A2 in seal Oil system
are opened.
7.16 Values MKG69 AA 504 and MKG69 AA 501 are opened to take dryers
in service.
8.0 METHOD
8.1 Disconnect pipe lines at isolating flanges Nos. 96 and 97. Keep valve
MKG 59 AA 507 open. Blank one end of this pipe line by a temporary
flange. Pressurise the pipe line by N2 gas to a Pr. Of 4.8 bar and
observe the leakage rate for 2 hrs. There should not be any pressure
drop. (Subject to temperature condition remaining same).
Disconnect pipe lines at isolating flange Nos. 94 and 95. Blank one end
8.2
of this pipe line by a temporary flange. Pressurise this pipe by N2 gas
to a pressure of 4.8 bar. Observe the leakage rate for 2 Hrs. There
should not be any pressure drop in pipe line. Check for any leakage
during this period by means of soap solution at all welding joints and
rectify any leakage. Connect back the pipe lines in system after
successful completion of test.
Disconnect pipe lines at isolating flange No. 312 and primary water
tank. Blank one end of this pipe line by a temporary flange. Keep valve
(MKP91 AA 502 open. Pressurise this pipe by N2 gas to a Pr. Of 5 bar.
Observe the leakage rate for 2 Hrs. There should not be any pressure
drop in pipe line. Check for any leakage during this test by means of
soap solution at all weld joints and rectify any leakage. Connect back
the pipe lines in system after successful completion of test.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./027
Plant Area: Turbine
SL.NO
STATUS
8.4 Leakage Test of Generator along with Gas System using Air.
Open valve MKG25 AA 501 and fill air in generator and gas piping upto
pressure of 4 Bar. During filling observe the performance of pressure
regulating valve of seal oil system and maintain the H2 and air side seal
oil Pressure as recommended. Close valve MKG25 AA 501 as soon as
pressure in the casing reaches 4 bar.
I During the air leakage test, apply Soap Solution at all joints for
checking leakages in following areas:
Sealing joints provided for taking out the stator winding Temp.
terminals.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./027
Plant Area: Turbine
SL.NO
STATUS
III Observe for any pressure rise in P.W. tank during test by means of
Water ‘U’ manometer provided for this purpose. If any increase is
observed, stator winding system should be checked for leakage.
IV Continue the test till the rate is well within specified limit. If no leakage
is observed, pressure drop should be checked for 72 hrs. continuously.
Z 273+T1 273 + T2
VG = Generator volume, m3
T2 =
Temp. of the gaseous atmosphere at end of leakage Test
0
C.
9.0 COMPLETION CRITERIA
Leakage test should be carried out for 72 hrs at 4 bar and average air
loss should be calculated. The permissible air loss for a gas tight
system is below 2.4m3 at N.T.P. / 24 Hrs.
If air loss is higher, checks should be carried out for detecting the
leakage areas.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./027
Plant Area: Turbine
Signatures
JPL BHEL