Prepared By - Reviewed By -
Rev No. 00
Dtd: Commissioning Commissioning Project
Name
Sign
Approved By :
HEAD – Steering Committee
Copy No:
Issued To:
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SLNO
LIST OF CONTENTS
2.0 OBJECTIVE
3.0 PROPOSAL
8.0 METHOD
10.0 APPENDICES
a) LOG SHEET
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SL.NO STATUS
The Boiler Feed system consists of three Boiler Feed Pump sets
for each unit of JPL (2 Turbine Driven and 1 motor driven). Each
pump set is of 50% capacity, which takes suction from the de-
aerator and discharge the Feed Water to series of HP heaters,
economizer and finally to boiler drum.
2.0 OBJECTIVE
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SL.NO STATUS
3.0 PROPOSAL
3.3 Steam rolling and actual over speeding of turbine (solo run of turbine)
4.1 Availability of manpower with required tools for attending any leak,
cleaning of filter and for adjustment of turbine governing system.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SL.NO STATUS
5.3 Operation of local start / stop push button shall be ensured for
perfect operation to facilitate for stopping of equipment in case of
necessity.
5.7 Safety appliances like helmet, hand gloves available for operating
personnel.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SL.NO STATUS
7.0 STATE OF THE PLANT
7.2 Acid cleaning and oil flushing completed for lube oil and working
oil, Jacking oil and governing oil piping as per test procedure
No………. and lines are normalized.
7.5 De-aerator filled with fresh DM water with proper level indication
and instrumentation completed.
7.8 Erection of turbine complete and log sheets are filled, signed by
concerned agencies.
7.10 Steam blowing of live steam line complete and steam piping
normalized.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SL.NO STATUS
7.11 Erection of gland steam supply piping complete. Supports, steam
blowing and insulation complete.
7.12 Turbine drain piping and all steam piping drain lines are
complete. For initial rolling orifice plates in drains are removed to
avoid chocking.
7.18 Governing valves erected and protection devices like over speed
trip device, hand trip device are mounted properly.
7.21 Instrument and service air line for the Feed pump system erected
and the air is made available for operation.
7.22 All local and remote instrumentation for the system is complete.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SL.NO STATUS
a) Recirculation line of main pump.
b) Suction and discharge line of booster pump and main pump.
c) Main pump and booster pump body.
8.0 METHOD
8.1 Commissioning of Oil System and Turning Gear Operation of BFP Turbine
8.1.1 Ensure oil flushing of lube oil system completed and piping are
normalized.
8.1.2 Ensure that the turbine is disconnected from gear box and main pump.
8.1.3 Ensure completion of lube oil inlet lines with throttles / orifices pressure
gauges and return lines with view glass and temperature gauges
8.1.6 Ensure the completion of Jacking Oil of lines with throttle valve, NRV
and isolating valve.
8.1.7 Ensure healthy filter elements in MOP, AOP, EOP suction lines, MOP,
AOP and EOP discharge lines and JOP suction line.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SL.NO STATUS
8.1.9 Keep open the vents of lube oil coolers and filters.
8.1.10 Keep the changeover valve of lube oil cooler and filter in such a way
that only one cooler ad filter will be in service.
8.1.12 Start one of the oil vapour fans with its suction valve open
condition.
8.1.13 Start one of the lube oil pumps ensuring flow through
recirculation.
8.1.14 Adjust lube oil header pressure control valve to maintain lube oil
pressure of 2.5 kg/cm2 after control station.
8.1.17 Check the lube oil flow to the bearing of turbine, main pump and
booster pump.
8.1.19 Stop the pump and start other lube oil pump and check its
discharge safety valve popping and adjust if required.
8.1.21 Ensure adequate lube oil pressure and flow. Keep DC EOP
running for 4 hours to check the healthiness.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SL.NO STATUS
8.1.23 Charge the suction line of JOP from lube oil header.
8.1.24 Start JOP and adjust the safety relief valve to …. kg/cm2.
8.1.26 Adjust the throttle valves in Jacking oil supply to front and rear
journal bearings such that the rotor lifts around 0.05 to 0.1 mm.
Stop JOP and start again. Check and record the Jacking oil
pressures and rotor lifts in the turbine front and rear journal
bearings.
8.1.27 Check and ensure the freeness of rotor for rotation by engaging
hand barring lever and then stop JOP.
8.1.31 Charge cooling water to cooler and ensure oil temperature control
valve auto operation.
8.1.33 Once the rotor picks up speed, turning gear valve may be closed
for checking the rotor for possible rubbing at end gland seals,
heat shields, oil guards etc., while coasting down.
8.1.34 If the rotor is found smooth till it comes to standstill, turning gear
valve may be opened full.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SL.NO STATUS
8.1.35 Ensure turning gear speed of around ... RPM and smooth
running.
8.1.37 Run for 8 hours. stop turning gear and observe coasting down.
8.2.2 Ensure main and auxiliary control valves lift reference indicator is
fixed and set to zero position.
8.2.3 Check the damping valve in HP and LP secondary oil lines are
kept open by few turns.
8.2.4 Check the filter elements at the control rack of the duplex filter
are clean and healthy.
8.2.7 Ensure lube oil pump in service and charge governing oil to the
governing system.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SL.NO STATUS
8.2.11.1 Ensure power supply for solenoids …. and …. (It will be normally
in de energized condition)
8.2.11.2 Ensure no steam available ahead of ESV and live steam isolating
valve in closed condition.
8.2.11.3 Give open command to ESV and observe the following sequential
operation of solenoid valves ….. And ……..
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SL.NO STATUS
8.2.12 Reset the turbine from remote by energising solenoid ….. Ensure
the same solenoid gets automatically de energised when trip oil
pressure raises more than …kg/cm2 through pressure switch.
8.2.15 Ensure HP sec. Oil pressure of … kg/cm2. If not set the pressure
to …. kg/cm2 by adjusting potentiometer XO in I/H convertor.
8.2.16 Check that the control valve servomotor pilot is rotating freely and
having a slight up and down movements.
8.2.17 Check the main control valve servomotor is just opened, by 0.2
mm. The start of opening can be measured by fixing dial gauge
on servomotor.
8.2.18 If the start of opening is not correct adjust the adjustment screw
of the pilot slide to achieve the start of opening.
8.2.19 Raise the current to I/H convertor to 20 mA. Observe HP sec oil
pressure increases to …. kg/cm2. If not adjust the potentiometer
X1 of I/H convertor to achieve the pressure.
8.2.20 Check the main control valve servomotor lift is maximum. If the lift
is not correct adjust feed back angle to obtain the full lift.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SL.NO STATUS
8.2.23 Compare the characteristics and ensure these are in line with
governing adjustment diagram/ shop floor test protocol.
8.2.24 Operate the tester for ESV and ensure partial closing of ESV and
put back the tester in normal position, ESV opens back to full
open position.
8.2.25 Energies the remote trip solenoid ….. ./ …… and ensure the
following.
a) ESV closed.
b) Main control valve is closed
c) Auxiliary control valve is closed.
d) Trip oil pressure is zero.
8.3 Steam rolling and actual over speeding of Turbine (solo run
of turbine)
8.3.1 Ensure that Gear box and main pump are disconnected from the
turbine.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SL.NO STATUS
8.3.5 Check that all the temporary supports are removed from turbine
casing, steam lines, oil lines etc.,
8.3.6 Ensure that the TD BFP foundation is separated from the main
turbine foundation all around and the support spring assembly of
TD BFP is properly placed.
8.3.7 Start oil system. Keep the turbine on hydraulic barring. Record
the measurements of oil system and turbo visory.
8.3.8 Installs dial gauges for checking even expansion of the casing
and pedestal.
8.3.10 Keep open casing drain and balance piston loop drain valves.
8.3.12 Keep the gland steam controller on auto and observe that it
maintains properly.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SL.NO STATUS
a)
Trip oil pressure very low
b)
Bearing temperatures very high
c)
Vibrations very high.
d)
Turbine speed very high.
e)
Turbine axial shift very high
f)
Any other protection as applicable and provided in the
system.
Keep open all drain valves in extraction 4 to TDBFP, CRH to
8.3.15
TDBFP and auxiliary steam to TDBFP lines.
8.3.17 Warm up the steam inlet line to turbine (Steam supply can be
taken from any one of the available sources)
8.3.19 Reset the turbine and observe the trip oil pressure is available.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SL.NO STATUS
8.2.25 Soak the turbine at …. rpm for about 30 minutes observe the
parameters are stabilized.
8.2.26 Raise the speed of the turbine gradually to rated speed as per
start up curve, given in O & M manual.
8.2.28 At rated speed soak the machine for 15 minutes, observe for all
parameters. Adjust lube oil flow to bearings if required.
8.2.29 Carry out oil injection test of over speed governor for few times to
check repeatability of the action.
8.2.30 Keep exhaust hood spray system on auto. Ensure its operation.
8.2.32 If actual over speed trip does not occur at required value, hand
trip the turbine and adjustment to be done at emergency
governor.
8.4.1 Ensure alignment readings are logged and cleared for coupling.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SL.NO STATUS
8.4.2 Couple turbine with BFP and Gearbox. Couple gearbox with
booster pump.
8.4.3 Crack open feed water suction isolating valve and vent out air in
all the vents.
8.4.4 Flush and shut the booster pump casing drain and BFP drain and
interconnecting pipe drain.
8.4.5 Check all the instrument tapping point isolating valves are open
and that all drain and equalizing valves are shut.
8.4.6 Gradually open suction isolating valve keeping watch on the trend
of differential temperature of top and bottom of the main pump
casing.
8.4.7 Check mechanical seal water control isolating valves are open for
Booster pump and BFP.
8.4.8 Check magnetic separator isolating valves for BFP seal water are
open.
8.4.10 Ensure isolating valves in recirculation line and leak off line are
open.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
SL.NO STATUS
8.4.12 Ensure all flanged joints are tightened properly with proper
gaskets.
8.4.13 Ensure proper clearance at the holding down bolts of the booster
pump and main pump.
8.4.17 Check the freeness of Turbine rotor along with booster pump and
main pump by hand barring.
8.4.18 Disengage the main pump and keep the turbine on hydraulic
barring and prepare the turbine for steam rolling.
8.4.19 When the turbine is ready for steam rolling, stop the turbine and
engage the main pump with turbine.
8.4.20 Keep the turbine along with main pump and booster pump on
hydraulic barring.
8.4.21 Raise the speed of the TDBFP to rated speed as per start up
curve.
8.4.22 Keep the pump on recirculation flow of approximately 250 T/hr for
8 hours to observe and record performance.
8.4.23 Check lubes oil flow through return oil sight glasses.
8.4.24 Check for any undue noise, vibration in bearings, seals and
pumps,
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
STATUS
SL.NO
8.4.25 Check the speed control and pressure variations during operation
of BFP for drum level control.
8.4.27 Stop TDBFP after trial run, put turbine on hydraulic barring
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
10 LOG SHEET 1
Date:
PROJECT :
UNIT :
EQUIPMENT : BFP TURBINE
ACTIVITY :
Speed Lub oil Oil pressure to Bearings Bearing temperatures Oil temperature
Time Hdr.
Hrs Pressure Front Front Rear Front Front Rear Bef. After
Journal Thrust Journal Journal Thrust Journal cooler cooler
LOG SHEET 2
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./036
Date:
PROJECT :
UNIT :
EQUIPMENT : BFP TURBINE
ACTIVITY :
Vibrations
LP sec oil pr
HP valve lift
LP valve lift
Axial shift
Time Hrs
Speed
Front
Rear
Signatures