Documente Academic
Documente Profesional
Documente Cultură
Prepared By - Reviewed By -
Rev No. 00
Dtd: Commissioning Commissioning Project
Name
Sign
Approved By :
HEAD – Steering Committee
Copy No:
Issued To:
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
SLNO
3.0 PROPOSAL
10.0 APPENDICES
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
SLNO STATUS
1.0 PLANT DETAILS:
1.1.3 Coolers 2 Nos to cool the oil, one working and the other standby.
1.1.4 Duplex filter in the oil line to thrust bearing, one for service and the other
is standby.
1.1.6 Throttles at the entry to each bearing, to regulate the oil flow to the
bearings.
1.1.7 Required instrumentation.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
SLNO STATUS
2.0 OBJECTIVE:
To flush the complete lube oil and jacking oil system to remove
mechanical impurities, dirt, welding slag etc. by circulating
approximately 150% of service oil flow rate at an temperature
above the normal operating conditions of plant.
3.0 PROPOSAL:
1. Manpower with required tools for attending to any leak, cleaning the
oil filter and to adjust throttles.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
SLNO STATUS
7.0 STATE OF THE PLANT:
1. All erection activities in lube oil, control oil, jacking oil, oil
purification circuit should be completed. CARD BOARD
BURSTING of oil lines have been completed as per
procedures annexed.
2. Temporary supports should be removed. & arrangements made
for knocking at the pipe lines in order to loosen the impurities
adhering to the walls & have them discharged with the flows
3. AOPs (Auxiliary Oil Pump) and jacking oil pumps are available
for running.
4. Oil Purification System should be available for operation.
5. Service air should be available near filters for cleaning of filters.
6. Cooling water at oil cooler should be available.
7. All temporary loops are made as per schemes given in this
procedure.
8. Waste oil system piping should be completed.
9. A telephone should be available near by and the telephone
numbers of hospital, ambulance and fire brigade is displayed.
10. Fire fighting equipments shall be made available.
11. The operating personnel shall be aware of the procedure.
12. Provision for emergency stopping of oil pumps from Local /
Main Control Room has to be made.
13. Sufficient quantity of safety appliances such as helmets, face
mark, hand gloves, Crum boots, Apron, nose breather are made
available for use at site.
14. The team for this operation shall be aware of this procedure for
oil flushing and shall act at the time of any emergency.
15. The team should be aware of first aid to be followed in case of
accident involving injury to personnel.
16. The team should be aware of operating procedures of fire
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
METHOD:
8.0 Preparation
a. Oil throttle internals in oil supply line to bearings are to be removed
and are provided dummy plates on top of the throttle body. These
dummy plates are provided with oil flushing material.
b. Oil throttle before oil coolers need not to be removed, also provide a
temporary pipeline between inlet and outlet of the cooler.
c. Duplex filter elements provided in the supply line to thrust bearing are
to be removed. These elements are to be put back in position during
the final stage of flushing.
d. The regular adaptors in the bearing pedestals for supply are replaced
with flushing device so that oil is deflected to bearing-to-bearing
pedestal instead of going to the bearings.
e. MOP (Main Oil Pump) is to be completely removed and a flushing
device is to be placed in position.
f. Blind flange dummy is to be provided at flange as indicated in the
scheme in section 3.11.
g. The jacking oil pumps are disconnected at the discharge flanges of the
pumps and rotates as required and oil supply pipe to be connected
through a temporary valve (of high pressure duty) to the dummy flange
in the AOP discharge header.
h. The header of the jacking oil supply line has a dummy flange at the
exciter side. From this a temporary connection is run to the oil return
pipe blank flanges of flushing, with an isolating valve.
i. Pressure regulating valve of JOP (Jacking Oil Pump) discharge line to
be removed and spool piece to be erected for connecting JOP
discharge header and relief drains is to be blanked.
j. The hose connections of JOP lines inside the bearing pedestals are
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
h. After initial cleaning of oil lines, throttles in the oil supply line to bearings
are to be put in position. Oil flushing should then be continued for some
bearing at a time (keeping the throttles full open condition and closing the
throttles of the remaining bearings), therefore, ensuring flushing with
maximum possible flow in the oil return lines.
i. The flushing operation is to be continued by undertaking the above
exercise in rotation so that bearing oil supply lines are thoroughly flushed.
j. Turning gear line is to be flushed by opening the gate-gearing valve in such
a way that AOP motor does not get overloaded. This should be done daily
once for ½ hour.
Jacking Oil Lines:
a. The jacking oil system flushing can be started after initial dirt / muck
of Lube oil system is cleared.
b. Oil flushing is done by using the temporary connection from AOP
discharge header.
c. Initially the jacking oil header is to be flushed by using the
connection i.e. from header dead end to drain header.
d. After using above circuit for about sometimes the above connection
is to be closed and then the lines to the individual bearing are to be
flushed, say 2 or 3 lines at a time for effective flushing.
Restoration Of The System:
a. On completion of flushing, hydraulic test of the system is to be done.
Then the system is normalized.
b. When the oil is drained into the drain tanks provided, the drain tank,
which accepts oil, must be clean. The oil contained in the system,
main oil tank and oil coolers are to be completely drained using
purifier & MOT drain lines.
c. The MOT (Main Oil Tank) is carefully cleaned and inspected as
done earlier before flushing. Jacking oil lines are to be normalized.
d. The cooler tube nest should be withdrawn for inspection and
cleaning of the coolers should be done. Taking care so that O-rings
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
After hydraulic test drain the system & normalize system. On filling the
Fresh oil start system commissioning.
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
10.0 APPENDICES:
(a) Schemes
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
D
E F
J G
H
Sheet 2
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Schedule of Check Lists for Lube Oil System and jacking oil system
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Checklist STG-LO-01
INSTALLATION OF ORIFICES
Date:
SL Orifice Identification Orifice Diameter. Orifice Installed
No (Yes/No)
1
2
3
4
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Checklist STG-LO-02
INSTALLATION OF DEVICES
Date:
SL. Tag No Description Installed
No. Yes/No
1. 37 micron filter cartridges in LO
2. 37micron filter cartridges IN JO
3. MOT level indicator
4. MOT level high switch
5. MOT level low switch
6. AOP discharge pressure indicators
7. DC LOP discharge pressure indicator
8. Lube oil inlet to cooler1 local temperature indicator.
9. Lube oil inlet to cooler 2 local temperature indicators.
10. Lube oil outlet from cooler 1 local temperature indicator.
11. Lube oil outlet from cooler 2 local temperature indicators.
12. Lube oil temperature after cooler - temperature element
13. Differential pressure indicator for lube oil filters
14. Differential pressure switch for lube oil filters
15. Lube oil header pressure indicator
16. Lube oil header pressure transmitter
17. Lube oil header pressure low – switch
18. Lube oil header pressure low-low – switch
19. Lube oil header pressure low-low switch
20. Lube oil header pressure low-low – switch
21. Lube oil header pressure low-low switch
22. Lube oil header pressure low-low – switch
23. MOP discharge header pressure low - switch
24. MOP discharge header pressure indicator
25. MOP suction pressure – indicator
26. Lube oil pressure to thrust bearing - indicator
27. Lube oil pressure to turbine bearing 1 – test indicator
28. Lube oil pressure to turbine bearing 2- test indicator
29. Lube oil pressure to turbine bearing 3- test indicator
30. Lube oil pressure to turbine bearing 4- test indicator
31. Return oil temperature indicator – bearing 1 pedestal
32. Return oil temperature indicator – bearing 2 pedestal
33. Return oil temperature indicator – bearing 3 pedestal
34. Return oil temperature indicator – bearing 4 pedestal
35. Return oil temperature indicator – bearing 5 pedestal
36. Return oil temperature indicator – bearing 6 pedestal
37. Return oil temperature indicator – bearing 7 pedestal
38. Lube oil pressure test indicator exciter rear bearing
Refer for Tag no, set points & other details :INSTRUMENT LIST
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Checklist STG-LO-03
ON SITE CALIBRATION OF DEVICES
Date:
Sl. no. Device Tag no Range / Set Checked OK /
Point NOT OK
1. MOT level indicator
2. MOT level high switch
3. MOT level low switch
4. AOP discharge pressure indicators
5. DC LOP discharge pressure indicator
6. Lube oil inlet to cooler local temperature
indicator.
7. Lube oil inlet to cooler local temperature
indicator.
8. Lube oil outlet from cooler local
temperature indicator.
9. Lube oil outlet from cooler local
temperature indicator.
10. Lube oil temperature after cooler -
temperature element
11. Differential pressure indicator for lube oil
filters
12. Differential pressure switch for lube oil
filters
13. Lube oil header pressure indicator
14. Lube oil header pressure transmitter
15. Lube oil header pressure low – switch
16. Lube oil header pressure low-low – switch
17. Lube oil header pressure low-low switch
18. Lube oil header pressure low-low – switch
19. Lube oil header pressure low-low switch
20. Lube oil header pressure low-low – switch
21. MOP discharge header pressure low –
switch
22. MOP discharge header pressure indicator
23. MOP suction pressure - indicator
24. Lube oil pressure to thrust bearing –
indicator
25. Return oil temperature indicators
26. Oil pressure to barring gear – indicator
27. Oil pressure to barring gear low – switch
Refer for Tag no, set points & other details :INSTRUMENT LIST
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Checklist STG-LO-04
MAIN OIL TANK READINESS
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Checklist STG-LO-05
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Checklist STG-LO-06
TIME
DATA UNIT
Motor Current Amps
Vibration at Microns /
Motor CE mm/sec
Vibration at Microns /
Motor FE mm/sec
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Checklist STG-LO-07
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Checklist STG-LO-08
AUXILIARY OIL PUMPs COMMISSIONING
Equipment tag number …………………………….
System Description………………………….
P&ID Number ……………………………….
Manufacturer’s Name ……………………………….
Name Plate details ……………………………………
Date
SLNo Description Remarks
1 Bearing lubricated as recommended
2 Rotor free in its bearings
3 Review motor winding insulation resistance values
4 Check Motor earthing
5 Power supply switchgear checked and ready for
charging
6 Pump bumped and rotation proved
7 Instrumentation & protection devices checked
8 Holding-down bolts fitted securely
TIME
DATA UNIT
Motor Current Amps
Pump discharge pressure Kg/cm2
Vibration at Motor CE Microns /
mm/sec
Vibration at Motor FE Microns /
mm/sec
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Checklist STG-LO-09
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Checklist STG-LO-10
Date:
Ref: BHEL SOE List :
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Refer for Tag no , set points & other details :INSTRUMENT LIST
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Checklist STG-LO-11
Checklist STG-LO-12
Refer for Tag no , set points & other details :INSTRUMENT LIST
Checklist STG-LO-13
SL NO Activity Remarks
1 Valve operation OK / NOT OK
2 Temperature control setting 45 degC
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Checklist STG-JO-01
INSTALLATION OF DEVICES
Date:
Refer for Tag no , set points & other details :INSTRUMENT LIST
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Checklist STG-JO-02
Date:
Sl Tag no Device Range / set Calibrated
no point yes/no
1 JOP discharge header transmitter
2 JOP discharge header pressure low
3 JOP Discharge header to Turning gear
interlock
Refer for Tag no , set points & other details :INSTRUMENT LIST
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Checklist STG-JO-03
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
TIME
DATA UNIT
Motor Current Amps
Vibration at Microns /
Motor CE mm/sec
Vibration at Microns /
Motor FE mm/sec
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Pump set is ready for trial run.. Set Jacking Oil Header Pressure at 150 kg/cm2.
Jacking Oil pumps Trial Data
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Signatures
JPL BHEL
Station: JPL, Tamnar JPL Reference no:
Sheet 1 of
Stage II: (4X600 MW) Turbine/Comm./016
Plant Area: Turbine
Procedure for Lube Oil & Jacking Oil system flushing & Commissioning
Signatures
JPL BHEL