STANDARD FINAL AMENITIES LIST FOR PROJECTS (BTS)

ITEMS DESCRIPTION SPECIFICATIONS REFERENCE OF BOQ ITEMS LOCATIONS Remarks

A PRELIMINARY WORKS AND ENABLING WORKS


NOTE :
1. All Approvals (Statutory requirements) to be obtained by Developer for carrying out Borewell Works.
2. Temporary Power connection for required Load for ASL to be provided by Developer; Temporary Power to be disconnected only after written confirmation of ASL.
3. All necessary Tests to be carried out by the Developer as per the Relavant IS Codes.
4. All works will have to be carried out as per BOQ Specifications, Latest GFC Drawings, Contract Agreement Document and Relavant IS Codes.
5. The Developer will have to ensure Green Building Certification Compliances.
6. The Developer will have to ensure HSE Compliances as per ASL HSE Specifications.
7. The Developer will have to carryout the Lab Test of the Construction Water as per the Relavant IS Codes, to find its suitabilty.

1 Survey Topographical & Contour Survey in line with TILR Records Topographical and Contour Survey Drawing, Superimpose Drawing with TILR
2 Soil Investigation works Boreholes - 05 No's, Trial Pit - 03 No's All works, Test has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. Soil Investigation Works BOQ Items

3 Borewell Borewell (2 Nos.) with Pump Capacity 5 HP or more As per capacity required for supply for Construction Works / Activities, Toilets, Staff Rooms, Food Court, Lunch Rooms etc. Borewell BOQ Items
(Kirloskar Make) Borewells to be maintained by Developer in working condition till the completion of ASL Scope of work.

4 Temporary Barrication Providing, fixing & removal of Temporary Barrication of 3m Height All works will have to be carried out as per BOQ Specifications, Latest GFC Drawings and Contract Agreement Document. Temporary Barrication BOQ Items 1. Plot Barrication including Door
at all periphery of plot including Barrication Door, Temporary 2. Security Room
Security Room (GI sheet with Alternate Colour Green matching with 3. For Covering Temporary Power Connection
DMart shade & with Offwhite)

B CIVIL WORKS
NOTE :
1. All works will have to be carried out as per BOQ Specifications, Latest GFC Drawings, Contract Agreement Document and Relavant IS Codes.
2. All License / Approvals (Statutory requirements) to be obtained by Developer for carrying out Construction Works / Activities.
3. Temporary Power connection for required Load for ASL to be provided by Developer; Temporary Power to be disconnected only after written confirmation of ASL.
4. All Tests as per IS Codes to be carried out by Developer.
5. The Developer will have to carryout the Lab Test of the Construction Water as per the Relavant IS Codes, to find its suitabilty.
6. Anti Termite Treatment to be carried out by PCI only.
7. The Developer will have to provide 10 Years Warantee against the Anti Termite Treatment Works in Legal Bond Paper.
8. The Developer will have to ensure Green Building Certification Compliances.
9. The Developer will have to ensure HSE Compliances as per ASL HSE Specifications
1 Earthworks Excavation in all type of Soil, Soft Rock and Hard Rock; Backfilling All works will have to be carried out as per BOQ Specifications, Latest GFC Drawings and Contract Agreement Document. CIVIL WORKS BOQ Item No's - A.1, A.2, 1)Main Building,
with Approved Murrum; All necessary Tests as per IS Codes to be carried out by Developer as Proctor Density Test, Sand Replacement Method / Core Cutter A.3, A.4, A.6 2)External Development,
Soling works Method, Water Absorption for filling etc. 3)Compound Wall,
4) MEP Works such as Substation, DG area, Pump Room,
STP Room, Under Ground & Above Ground Services etc.

2 Anti-Termite Treatment Anti-Termite Treatment (ATT by Pest Control of India) All works will have to be carried out as per BOQ Specifications, Latest GFC Drawings and Contract Agreement Document. CIVIL WORKS BOQ Item No. - A.5 1) ATT works to be provided at all area where the Soil is
in contact with RCC structure
Example - Footings, Otla, Grade Slab, etc as per the GFC
Drawings.

3 Concrete Plain Cement Concrete (Grade M15 or Above), Damp proof All works will have to be carried out as per BOQ Specifications, Latest GFC Drawings and Contract Agreement Document. CIVIL WORKS BOQ Item No's - B.1, B.3, 1)Main Building including Otla,
course(DPC), Reinforced Cement Concrete (Grade M30 or Above) C.1 2)External Development,
Standard Concrete Only RMC to be used. 3) Compound Wall,
Mix Design Approval to be obtained from ASL. 4) MEP Works
Cement - OPC 53 Grade, RMC shall be from Ultratech / ACC / RMC India / Lafarge only. 5)Lift Shafts - Except Front Wherever the lift door
Site Mix concrete not to be used for any type of Concrete works opens, all the sides of Lift walls shall be in RCC
All necessary Tests to be carried out by the Developer for - Brick Masonry for Lift Walls shall not be allowed
Slump Test, Compressive Strength of Concrete cubes, Aggregate Test etc. as per the Relavant IS Codes (IS 456, SP-23, IS10262, etc.). and
6) Any Other Areas as shown in GFC Drawings

As per GFC drawing


4 Steel Reinforcement HYSD Fe 500D - Conforming to IS 1786 All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. CIVIL WORKS BOQ Item No's - D.1 1)Main Building including Otla,
Make TATA / SAIL steel (No Other Make of reinforcement Steel to be used except as mentioned) 2)External Development,
All Tests to be carried out by the Developer for Physical & Chemical Properties of the Reinforcement Steel (Tensile Test, Torsion 3) Compound Wall,
Test, Bending Test, Rolling Margin etc. ) as per the Relavant IS Codes. 4) MEP Works and
5)Any Other Areas as shown in GFC Drawings

5 Centering / Shuttering Fully Densified Film Face Ply Shuttering only to be used for all All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. CIVIL WORKS BOQ Item No's - B.1, B.3, All PCC & RCC Works / Structures
Formworks. MS Steel Scaffolds, MS Props to be used for the Execution. C.1
Steel Plate Shuttering will not be allowed. Wooden Bamboo Scaffolds, Props will not be allowed.

6 Masonry Works Random Rubble Masonry in cement sand mortar 1:6 All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. CIVIL WORKS BOQ Item No. - F.1 1) Main Building,
2)External Development,
3) Compound Wall

1 of 13
STANDARD FINAL AMENITIES LIST FOR PROJECTS (BTS)
ITEMS DESCRIPTION SPECIFICATIONS REFERENCE OF BOQ ITEMS LOCATIONS Remarks

Burnt brick masonry walls 230mm / 350mm thick (only for Otla) in All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. CIVIL WORKS BOQ Item No. - F.2 1)External Development,
cement sand mortar (Ratio 1:5) All Tests as per IS Codes to be carried out by Developer. 2)Compound Wall,
3)Soak Pits,
4)Chambers,
5)Waterproofing Works
AAC Blocks of thickness 200/150mm in cement sand mortar (Ratio All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. CIVIL WORKS BOQ Item No's. - F.3, F.4 1)Main Building - External walls, Internal walls as
1:5) (Aerocon Make) (RCC band 100mm thick to be provided at All Tests as per IS Codes to be carried out by Developer. specfied in drawings ,
every 1.2m in height and Mullions (200x200mm) to be provided if 2)External Development - Services Rooms,
span of wall is more than 6 m) Miscellaneous Civil works such as Pump Room, STP
Room, Metering Room, Lunch Room, Staff Locker Room,
Scrap Room, Sub-Station Area, DG Area and
3) Other Areas as shown in GFC Drawings

Any Masonry Works to be carried out with the Natural River Sand.
In case Natural River Sand couldn’t be available, then, M. Sand could be used with prior Proper Approval from the ASL Structural
Consultant.

All Tests to be carried out by the Developer for -


Soundness, Compressive Strength, Absorption Test, Shape and Size etc.
as per the Relavant IS Codes.

7 Plastering Works Internal surfaces of masonry walls with 12 mm thk. cement mortar All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. CIVIL WORKS BOQ Item No. - G.1 1) Main Building - Internal walls, Ducts, Lift Shafts and
(Hacking at Junction of all RCC Members to be 1:4 mortar mixed with WPC of Dr. Fixit LW+ Other areas as specfied in drawings, 2) Gutter plaster
done and Chicken Mesh at Junction of all RCC
Members & Masonry Walls)
External surface of block masonry walls/brick masonry wall/RCC All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. CIVIL WORKS BOQ Item No's. - G.2, G.3, 1) Main Building - External walls and Other areas
members in two layers consisting 15mm thk. first layer in 1:4 G.5 specfied in drawings,
cement mortar and 10mm thk second layer of 1:4 cement mortar 2) Compound Wall
mixed with WPC of Dr. Fixit LW+ 3)Miscellaneous Civil works such as Pump Room, STP
Room, Metering Room, Lunch Room, Staff Locker Room,
Scrap Room, Sub-Station Area, DG Area and Other
Areas as shown in GFC Drawings
4) Gutter Plaster

Water proof plaster 15mm thk first layer in 1:4 cement mortar and All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. CIVIL WORKS BOQ Item No. - G.4 1) Main Building - Under Ground Water Tank, Over
10mm thk second layer of 1:4 cement mortar mixed with Dr. Fixit Head Water Tank, Septic Tank, Sewage Treatment Plant.
LW+
Any Plastering Works to be carried out with the Natural River Sand.
In case Natural River Sand couldn’t be available, then, M. Sand could be used with prior Proper Approval from the ASL Structural
Consultant.
All Tests to be carried out by the Developer for -
Silt Content, Grading of Sand, Specific Gravity, etc. as per the Relavant IS Codes.

8 Tremix works Tremix 150mm thick M25 Grade with Hardner (4 Kg / Sqm) with All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. CIVIL WORKS BOQ Item No. - B.2 1)Main Building - Basement Floor (Smooth Finish),
nominal steel of as per the GFC Drawing (8mm dia. At 300mm C/c.). 2)External Development, Driveway, Parking area,
Approach Road, Ramps shall have alternate 6 inch strips
of Broom Finish and Smooth Finish.

C WATERPROOFING WORKS
NOTE :
1. All works will have to be carried out as per BOQ Specifications, Latest GFC Drawings, Contract Agreement Document and Relavant Applicable Codes / IS Codes.
2. All Tests to be carried out by the Developer as per Relavant Applicable Codes / IS Codes.
3. The Developer will have to provide 10 Years Warantee against the WaterProofing Works in Legal Bond Paper.
4. The Developer will have to ensure Green Building Certification Compliances.
5. The Developer will have to ensure HSE Compliances as per ASL HSE Specifications
1 BOX TYPE WATER PROOFING Waterproofing with Laying Shahbad Stone (25mm & above All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. WATERPROOFING WORKS BOQ Item Main Building - 1) Footing, 2)Raft, 3)Below Grade Slab,
thickness) using Dr Fixit Water Proofing Chemical (LW+) No. - 1 4)Retaining Walls, 5)Lift Shafts, 6)Sumps and 7)Other
Areas as shown in GFC Drawings, 8) Under Ground
Water Tank , 9)Septic Tank, 10)Sewage Treatment
Plant.

2 BRICK BAT COBA WATER PROOFING Waterproofing consisting of brickbat (From Burnt Clay Bricks) & All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. WATERPROOFING WORKS BOQ Item 1)Building Terrace Area, 2)Toilet Areas
Cement Mortar in layers (450mm thick for Toilet Area and 150mm The Developer will have to carry out the Ponding Test to ensure the Zero Leakage, as per the Relavant IS Codes. No's - 2.1,2.2
thick average for Terrace Area) as specified in drawings.

3 CHINA MOSAIC China Mosaic for terrace water proofing with Cement Sand Mortar All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. WATERPROOFING WORKS BOQ Item 1)Building Terrace Area and 2)Other Areas as shown in
Bed. (Only White Color Tiles to be used) No's - 2.1a GFC Drawings
4 EXTENDED BASEMENT ROOF SLAB WATER URP Waterproofing Application as per ASL specifications All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. WATERPROOFING WORKS BOQ Item 1) Extended Basement Roof Slab Top Area, 2)UG Tank /
PROOFING No. - 3 STP / Septic Tank Top Slab Area and 3) Other Areas as
shown in GFC Drawings

5 KRYSTALLINE WATER PROOFING Waterproofing Application as per ASL specifications All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. WATERPROOFING WORKS BOQ Item 1) Grade Slab and 2) Other Areas as shown in GFC
No. - 4 Drawings
6 NOZZLE GROUTING Waterproofing Application as per ASL specifications All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. WATERPROOFING WORKS BOQ Item 1) Basement Retaining Wall, 2)Raft Slab, 3) UG Tank
No. - 5 and 4)Other Areas as shown in GFC Drawings

D MISCELLANEOUS WORKS

2 of 13
STANDARD FINAL AMENITIES LIST FOR PROJECTS (BTS)
ITEMS DESCRIPTION SPECIFICATIONS REFERENCE OF BOQ ITEMS LOCATIONS Remarks

NOTE :
1. All Applicable Miscllaneous works will have to be carried out as per BOQ and BOQ Specifications, Latest GFC Drawings, Contract Agreement Document.
2. All Tests to be carried out by the Developer as per the Relavant IS Codes.
3. The Developer will have to ensure Green Building Certification Compliances.
4. The Developer will have to ensure HSE Compliances as per ASL HSE Specifications
1 G.I. pipe ( C Class ) inserts, MS Rungs for Ladder R.C.C. tank G.I. pipe (C Class) inserts of 600mm length with Puddle All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. CIVIL WORKS BOQ Item No. - H.7 1) Main Building - Under Ground Water Tank, Over
Plates 6mm thick of required dia. for overflow drain, inlet and outlet Head Water Tank, Septic Tank, Sewage Treatment Plant.
of required diameters, threaded wherever required.
PVC Coated MS rungs of size 450 x 300mm clear, made out of
16mm Sq. Bar at 300mm C/c in RCC wall

2 Manhole Cover 600 mm dia DI circular double sealed heavy duty manhole cover All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. CIVIL WORKS BOQ Item No. - H.11a 1) Main Building - Under Ground Water Tank, Over
and frame fixed to RCC cover slab with handles and locking Head Water Tank, Septic Tank, Sewage Treatment Plant,
arrangement as per the Local Approval Authority / Municipal Soak Pit, Rainwater Harvesting Pit / Recharge Pit
Corporation rules.
DI COVER ITEM CODE=MC14 , GRADE=C250
Note-Chamber & Cover must competent to carry the Dynamic Load
of Fire Tender Movement

3 Aggregate laying in Sub-Station area 40mm aggregate layer All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. CIVIL WORKS BOQ Item No. - H.15 1) Sub-Station Area, DG Area

4 Demolition Works Demolition of existing Structures - Underground and Above Ground CIVIL WORKS BOQ Item No. - H.24
to facilitate the Construction of New Building, External Development
and Compound Wall.

E WATER TANKS
NOTE :
1. All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document.
2. Any Revision in GFC drawings need to be executed by Developer.
3. The Developer will have to ensure Green Building Certification Compliances.
4. The Developer will have to ensure HSE Compliances as per ASL HSE Specifications
1 Under Ground Tank Minimum requirement of 1,20,000 Litres subject to fulfillment Water-tank will be constructed as an seprate structure without any common walls with the basement & compound wall. Both Refer GFC Drawings for Execution
of Fire and OC Norms (1,00,000 Litres for Fire purpose and basement & Water tank shall be water tight structures. To be designed to accommodate fire requirement. UG tank shall be designed
50,000 Litres for Domestic purpose) such that domestic & Fire tank shall be interconnected so as to avoid stagnent water whereas flushing tank shall be seperate,
chamber within the water tank. Also, the top of water tank shall be @ 150mm above from the finish floor level of external
development, & top slab shall be designed to take vehicular loads & tappered at the ends to obtain smooth driveway.

2 Over Head water Tank As per Fire Norms, Minimum 10,000 Litres for Domestic, 20,000 Normally provided designed above the main staricase. To be designed to accommodate fire requirement, Domestic & Flushing all Refer GFC Drawings for Execution
Litres for Flushing, 20,000 Litres for Fire purposes - Total Capacity having different inlets & outlets.
40000 lit.
3 Septic Tank / STP Refer GFC Drawings for Execution

4 Soak Pit Refer GFC Drawings for Execution

5 Recharge Pit / Rain water Harvesting pit Refer GFC Drawings for Execution

F LIFTS
NOTE :
1. All Approvals (Statutory requirements) to be obtained by Developer for carrying out Supply and Installation of Lift Works and License For Operating the Lifts.
2. The Developer will have to Provide Power connection for required Load for the Lift Vendor (Otis).
3. All necessary Tests to be carried out by the Developer as per the Relavant IS Codes.
4. All works will have to be carried out as per OTIS Specification, ASL BOQ Specifications, Latest GFC Drawings, Contract Agreement Document and Relavant Applicable Codes and Standards.
5. The Developer will have to ensure Green Building Certification Compliances.
6. The Developer will have to ensure HSE Compliances as per ASL HSE Specifications
1 Lifts Automatic Lift of Otis make with SS finish for car body and facia wall The Developer will have to install Lifts as per the ASL BOQ Specifications, GFC Drawings and Contract Agreement Document - As per ASL GFC drawings.
& jambs of lifts to be claded with 18mm thick black granite for Full 1. Make - OTIS
Length and height . 2. Capacity - 17 Passenger: (Load: 1088KGs minimum)
3. Speed:1.0MPS minimum
The Developer will have to carryout placing of the order as per 4. SS Trolley guard on 3 Sides of the Car (150 mm (Depth) X 30 mm (Thickness)) @ 0.150 Meter above Finish Floor Level
Approved Shop Drawing from ASL. 5. SS Hand Rail on 3 Sides of the Car (150 mm (Depth) X 30 mm (Thickness)) @ 0.9 Meter above Finish Floor Level of Lift
6. Door Operator - Automatic & Multiray Electronic Door Detector system,
7. Automatic Rescue Device,
8. Firemans Switch,
9. Baterry operated alaram bell AND Emergency Light
10. ARD (Automatic Rescue Device with battery backup)
11. Internal Lighting (LED- white light)
12. Fresh Air Fan (Concealed at Ceiling)
13. Combined Luminous hall button with 16 segment hall position indicators at all levels,
14. Car operating panel,
15. Intercom, Braille, hand-rail and audio assistance in lifts for visually impaired people,
16. Flooring as specified by ASL.

FINISHES
G PAINTING WORKS

3 of 13
STANDARD FINAL AMENITIES LIST FOR PROJECTS (BTS)
ITEMS DESCRIPTION SPECIFICATIONS REFERENCE OF BOQ ITEMS LOCATIONS Remarks

NOTE :
1. All works will have to be carried out as per ASL BOQ specifications, GFC drawings and Contract Agreement Document.
2. Any Revision in GFC drawings need to be executed by Developer.
3. The Developer will have to ensure Green Building Certification Compliances.
4. The Developer will have to ensure HSE Compliances as per ASL HSE Specifications.
5. The Developer will have to submit the Test Certificates of all the Materials used in line with the Manufacturer's Specifications and Relavant IS Codes.

1 External Wall Colour Code: Dr. Fixit Raincoat EGG SHELL RW 364 2 Coat Primer + 3 Coat Dr. Fixit Raincoat from Pidilite EXTERNAL PAINTING BOQ Item no. - A.1 Building - External Wall including Chajja (Top & Bottom
Surface) As per approved elevation drawing by DMART

Colour Code: Dr. Fixit Raincoat, Sandtex Matt (SM6) DMART 2 Coat Primer + 3 Coat Dr. Fixit from Pidilite EXTERNAL PAINTING BOQ Item no. - A.2 Chajja (Front Face), Bands, Coping in Elevation
GREEN As per approved elevation drawing by DMART

2 Internal Wall Colour Code : RAL NO. 7876 2 coat Primer of Asian Make +2 coat Birla putty + 3 coats Asian Apcolite Acrylic EmulsionPaint INTERNAL PAINTING BOQ Item no.- A.1 Building - Internal Walls

3 Ceiling Colour Code : Brilliant White 2 coat Primer +2 coat Birla putty + 3 coats Asian Apcolite Acrylic EmulsionPaint INTERNAL PAINTING BOQ Item no. - Building - Ceiling
A.1
4 Basement Parking Colour Code : White 1 Coat Primer + 1 Coat Touchup Putty + 3 coats of Water Proof Cement paint of Snowcem / Asianpaint Make INTERNAL PAINTING BOQ Item no. - 1) Building - Basement Parking,
A.2 2) Lift Shafts - Internal Surface,
3)Service Ducts - Internal Surface
5 Compound Wall Colour Code: Dr. Fixit Raincoat EGG SHELL RW 364 2 Coat Primer + 3 Coat Dr. Fixit from Pidilite EXTERNAL PAINTING BOQ Item no. - Compound Wall
A.3
H FLOORING WORKS
Note :
1. All works will have to be carried out as per ASL BOQ specifications, GFC drawings and Contract Agreement Document.
2. Any Revision in GFC drawings need to be executed by Developer.
3. The Developer will have to ensure Green Building Certification Compliances.
4. The Developer will have to ensure HSE Compliances as per ASL HSE Specifications.
5. The Developer will have to submit the Test Certificates of all the Materials used in line with the Manufacturer's Specifications and Relavant IS Codes.
6. All Damaged Tiles, Granite, Kota Flooring till the time of D'Mart Store Opening, to be replaced by Developer without any cost to ASL
7. Developer has to handover 10 No. of Boxes of Full Body Vitrified Tiles of HR Johnson Make to ASL after the completion of work
8. All External Wall Windows, Cutouts will have Double Leaf patti Granite Frame on all sides and all Internal wall Cutouts will have Single Leaf Granite patti on all sides
1 Full Body Vitrified Tile Flooring Providing, Laying & Fixing Flooring with Full Body Vitrified tile 1)Flooring - Laying in cement paste over average 35mm to 50mm thick cement mortar 1:4, including installation of PVC spacers, FLOORING BOQ - Item No's 1)Retail Area, The Line and Level of Flooring works
(Make - HR Johnson ) with 600mm x 600mm x 9.50mm thick, IVORY curing, cleaning and pointing as per instructions of ASL Project-In-Charge. A.1,A.2,A.3,A.4,C.2, F.1 2)Office Area, shall ensured.
SF 2)Skirting - 100mm / 300mm high laid over cement paste of minimum 10 mm Thk. 3)Lunch Room (if specified in drawing)
with Epoxy grouting for the Joints (Make - Pidilite Roff Grouting Note-Skirting Outer Surface shall flush with Plaster surface. 4)Scrap room (if specified in drawing),
Material, Colour - Black) at 9 m c/c joint 5 mm wide and 9.5 mm 3) Staircase Risers - Tile size width of 600mm, laid in cement paste over minimum 20mm thick cement Paste. 5)Risers of Staircase in all Retail Area,
deep 6)Water Cooler (Floor and Dado Area) and
and covering entire floor area with bubble sheet (Make - Cello or 7)any other area specified in BOQ and GFC Drawing.
Approved by ASL, Colour - White, Thk - 5 MM, Sheet Size - 4' x 6' )
using Cello Tape (50 mm wide).

2 Toilet Flooring Providing, Laying and fixing flooring of 600mm x 600mm x 9.50 Flooring - Laying in cement paste over average 35mm thk cement mortar 1:4, in proper slope & at all levels and heights including FLOORING BOQ - Item No. B.1 All Toilets The Line and Level of Flooring works
mm thick - Antiskid tiles (Make - Johnson, Code - ASH MONTE ) Tile Joint Filling with White Cement mixed with Matching Colour Pigment including curing, cleaning by Acid Wash. shall ensured.

3 Toilet Dado Providing, Laying and fixing Glazed ceramic tiles of 600 X 600mm Dado - Fixing with 12 mm thk cement Paste at all levels, curing, cleaning by Acid wash FLOORING BOQ - Item No. B.2 All Toilets The Line and Level of Flooring works
(Make - Johnson) for Toilet Dado • Height of Dado will be as per ASL GFC drawings. shall ensured.
(Make - Johnson, Code - BEIGE BOTHOCHINO)

3a Mirrors 5mm thick Mirrors of Saint gobain / Modiguard Make fixed to 6mm All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. GLAZING BOQ Item no's. - A.16 1)All Toilet Areas
thick ply backing, fixed on SS Studs

4 Kota Flooring Providing, Laying & Fixing Kota stone using 20mm thk Approved 1)Flooring - Laying with proper joints over a bed of average 35mm thk cement mortar 1:4 & cement slurry laid to pattern Or over FLOORING BOQ - Item No's. 1) Basement Godown Area, 2)Pump Room, 3)Staircase The Line and Level of Flooring works
Quality Slabs : FABRICATED PLATFORM WITH ADHESIVE (CHEMICAL ARALDITE) (Wherever Applicable) A.5,A.6,A.7,A.8,C.5,C.6,C.7,C.8,C.9 Area as per GFC drawing, 4)Otla Area, 5)Mumty Room, shall ensured.
1) Kota stone flooring (Size - 600x600mm). 6)Lift Machine Room 7) All Godown Area at all Floors
2) 100 / 300mm high and 600mm wide Kota stone skirting. 2) Skirting - Laying with machine cut edges & with paper joints over 12 mm thk cement Paste laid to pattern. and 8) any other area specified in BOQ and GFC
3) Pre-Polished Kota stone as Tread & Riser using (treads & risers drawings
should be of full length) 3)Tread & Riser of uniform colour - Laying cut edges laid with proper joints over 35mm thk cement mortar 1:4 & cement slurry
laid to pattern including Groove cutting, Chamfering and Moulding.

4 of 13
STANDARD FINAL AMENITIES LIST FOR PROJECTS (BTS)
ITEMS DESCRIPTION SPECIFICATIONS REFERENCE OF BOQ ITEMS LOCATIONS Remarks

5 Polished Granite Works Providing & Fixing Approved Z Black Granite 17-18mm thick as All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. FLOORING BOQ - Item No's. C.1,C.3,C.4, 1) Lift Side Frame And Water Cooler Bund Top ---- Size - The Line and Level of Flooring works
specified in GFC drawings. D1 to D6,E.4, E.5, F.2 230 mm Wide (Single Leaf Granite) shall ensured.
2) Lifts Façade, Entry, Exit, E.Exit ---- Size - 300 mm
Wide with V groove (Single Leaf Granite)
3) Air Lock Bund (on all sides) ---- Size - as specified in
GFC drawing (Single Leaf Granite)
4) For internal Toilet Door Frame
Size - 230 mm Wide (Double Leaf Granite)
5) Toilet Ventilators, Exhaust Fan Cutouts, Fresh Air
CutOuts, Toilet Main Doors, Staicase Windows, All Duct
Doors, All Elevational Windows & Doors
Size - 300 mm Wide (Double Leaf Granite)
6) Staircase Treads - Full length Granite piece to be
used, Skirtings, Midlanding. Otla Risers
7) Urinal Partitions

6 Flammed Granite works Providing and fixing River polished flammed black Granite slab 17 - All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. FLOORING BOQ - E.2, E.3, E.6, E.7, 1) Otla Steps - Treads The Line and Level of Flooring works
18mm thick as specified in GFC drawings. E.8.E.9,E.10,E.11 2) Otla Ramps shall ensured.

I GLAZING & PARTITION WORKS


Note :
1. All works will have to be carried out as per ASL BOQ specifications, GFC drawings and Contract Agreement Document.
2. Any Revision in GFC drawings need to be executed by Developer.
3. The Developer will have to ensure Green Building Certification Compliances.
4. The Developer will have to ensure HSE Compliances as per ASL HSE Specifications.
5. The Developer will have to submit the Test Certificates of all the Materials used in line with the Manufacturer's Specifications and Relavant IS Codes.
6. All Aluminium Section will be of Jindal Make and anodized (20 Micron ) - Silver Coating
7. All Hardner Sheet Panel 5mm thick - Make - Bakelite, Color - 4001 off-white MT
8. All Glass panel will be of Saint Gobain Make
9. All Mirrors will be of Modi Guard / Saint Gobain Make
10. All Fixtures shall be as per ASL BOQ Specifications and Make.
2 Sliding Doors Toughened Glass 10mm thick for Fixed Panel All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. GLAZING BOQ Item no.- A.20 1)Main Entry, Main Exit, Main Emergency Exit,
and 6mm thick Toughen glass with Aluminium frame for Sliding 2)Emergency Night Access Door
Panel. (Glass Make - Saint Gobain)
4 Elevational Windows Toughen Glass 10mm thick clear with Aluminium frame (Glass Make All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. GLAZING BOQ Item no's.- A.12, A.13 1)All Elevational Doors and Windows,
- Saint Gobain) 2)Fire Escape Windows,
3)ODU Access doors at all levels,
and
4)Any Other External Areas as shown in GFC Drawings

5 Toilet Ventilators Aluminium Frame with Glass Louvers, Fixed Glass panel and All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. GLAZING BOQ Item no. - A.15 All Toilet Areas
Exhaust Fan Cutout panel.
6 Aluminium Louvers Aluminium Frame with Aluminium Louvers All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. GLAZING BOQ Item no. - A.14 All External Locations

9 Airlock Partitions Toughen Glass 10mm thick (Make - Saint Gobain)and all remaining All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. GLAZING BOQ Item no. - A.23 Otla Area - Main Entry, Main Exit for Customer
sides to be fixed with ACP Sheet (Silver Colour - Alto Bond - Silver The developer shall be responsible for Structural Stability of Air lock works. FABRICATION BOQ Item no.. - I.8
101) with MS Structural framework The Joints to be filled with Silicon Sealant matching the color of ACP Sheets.
Support for Airlock Partition

12 Flush Doors for Toilets Toilets Single shutter flush doors - P&F 35mm thick single shutter flush doors (Make - Century) with laminated sheet (1mm thick) (Merino Laminates (Code : Frosty FURNITURE BOQ Item no's. - 1) All Toilet Doors
Toilet Doors (Main Doors will have additional items specifications - White)) (Shutters to be fixed with beading patti 12mm thick - Dark Brown Polishing ) fixed to granite frame for toilets as per A.30,A.31,A.32,A.33,A.34,A.35
Aluminium Louvers, Dead lock (Godrej Make), Heavy Duty Dorma drawing complete with 4" hinges (SS), MS Handle with SS coating (4" length), 3" aluminium tower bolt, holdfast,& 2 hooks behind
door closer) each Door. etc.complete - (Make of hardware shall be Kich or equivalent as approved by Project - in - charge)

J FABRICATION WORKS
Note :
1. All works will have to be carried out as per ASL BOQ specifications, GFC drawings and Contract Agreement Document.
2. Any Revision in GFC drawings need to be executed by Developer.
3. The Developer will have to ensure Green Building Certification Compliances.
4. The Developer will have to ensure HSE Compliances as per ASL HSE Specifications.
5. The Developer will have to submit the Test Certificates of all the Materials used in line with the Manufacturer's Specifications and Relavant IS Codes.
6. The Developer will have to ensure the Correct Alignment of Fabrication Works (Line & Level) and Quality of Weld Joints.

5 of 13
STANDARD FINAL AMENITIES LIST FOR PROJECTS (BTS)
ITEMS DESCRIPTION SPECIFICATIONS REFERENCE OF BOQ ITEMS LOCATIONS Remarks

1 Rolling Shutters including Fabrication Painting Providing and fixing pull & push type 18 Guage GI Rolling shutters All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. FABRICATION BOQ Item no.
- 1) Main Entry, Exit, Emergency Exit door,
including necessary MS supports, manually gear box with operating A.1,A.2,A.3,A.4,A.5,A.6 2)Emergency Night Access Door,
handle, Rolling Shutter Hood Covers, Side Locks. Painting Details with Brush Application - 1 Coat of Red Oxide Primer (Asian Make) + 3 Coats of Synthetic Enamel Paint of 3)All External Windows and External Doors at all
Asianpaint Make, Color - Silver Color INTERNAL PAINTING BOQ Item no. A.5 Floors,
4)Basement Ramp Entry

2 MS Doors including Fabrication Painting Providing & Fixing MS Doors with necessary supports All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. FABRICATION BOQ Item no's. - B.3 1)Staircase Headroom Door,
2)LMR door at Terrace Level.
Painting Details with Brush Application - 1 Coat of Red Oxide Primer (Asian Make) + 3 Coats of Synthetic Enamel Paint of INTERNAL PAINTING BOQ Item no. A.5 3) All Staircase Entry at all Levels
Asianpaint Make, Color - Ivory Color

4 MS Collapsible gate including Fabrication Providing, fabricating & Fixing MS Collapsible gate with necessary All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. FABRICATION BOQ Item no. - F.3 1)Receiving Area,
Painting supports 2)Staff Entry,
INTERNAL PAINTING BOQ Item no. A.5 3)ODU Access Doors,
Painting Details with Brush Application - 1 Coat of Red Oxide Primer (Asian Make) + 3 Coats of Synthetic Enamel Paint of 4)Fire Escape Window,
Asianpaint Make, Color - Ivory Color 5)All Staircase Doors at all levels,
and
6)Any Other Areas as shown in GFC Drawings

5 MS Partitions, MS partitions + chain link fencing, Providing & Fixing MS Partitions, MS partitions + chain link fencing, All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. FABRICATION BOQ Item no's. - B.1, B.2, 1)Pump Room,
MS chainlink fencing, MS Shed, MS Doors MS chainlink fencing, MS Shed, MS Door with necessary supports G.2 2)STP Room,
including Fabrication Painting 3)Metering Room,
Painting Details with Brush Application - 1 Coat of Red Oxide Primer (Asian Make) + 3 Coats of Synthetic Enamel Paint of INTERNAL PAINTING BOQ Item no. A.5 4) Sub-Station Area, DG Area
Asianpaint Make, Color - Ivory Color

7 MS Railling including Fabrication Painting Providing & Fixing MS Railing with necessary supports including All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. FABRICATION BOQ Item no's
- 1) MS Railings On Internal Staircases (where there is no
Anchor Fasteners C.1,C.5,C.6 Customer Movement), at Otlas, Otla Steps, Ramp, Fire
Escape Staircase, Otla Ramps..
Painting Details with Brush Application - 1 Coat of Red Oxide Primer (Asian Make) + 3 Coats of Synthetic Enamel Paint of INTERNAL PAINTING BOQ Item no. A.5 2)MS Railing mounted on floor at Parking Area, MS
Asianpaint Make, Color - Black Colour with Matt Finish Angle Guards for Recieving Dock, Ramps
and Other Areas as shown in GFC Drawings

7.1 SS RAILING / SS GUARD WORKS Providing & Fixing SS Railing with necessary supports including All works has to be carried out as per BOQ specifications, GFC drawings and Contract Agreement Document. SS RAILING BOQ 1) SS Railing (SS-304 Grade) On Internal Staircases
Anchor Fasteners (where there is Customer Movement)
2) SS Guard (SS-304 Grade) at All Lift Entry, Main Entry
/ Exit, Chiller, Bed Freezer Guard
3) SS Railing (SS-304 Grade) for Trolley Guard

10 MS Ladders including Fabrication Painting Providing, fabricating & Fixing M.S ladder with necessary supports All works has to be carried out as per ASL specifications and GFC drawings. FABRICATION BOQ Item no. - D.1,D.2 For Access to
1) Over Head Water Tank ,
INTERNAL PAINTING BOQ Item no. A.5 2) AC ODU Platforms,
Painting Details with Brush Application - 1 Coat of Red Oxide Primer (Asian Make) + 3 Coats of Synthetic Enamel Paint of 3) LMR Rooms.
Asianpaint Make, Color - Black Colour

6 of 13
STANDARD FINAL AMENITIES LIST FOR PROJECTS (BTS)
ITEMS DESCRIPTION SPECIFICATIONS REFERENCE OF BOQ ITEMS LOCATIONS Remarks

11 MS Grills and GI Mesh including Fabrication Providing, fabricating & Fixing M.S Grills, GI Mesh with necessary All works has to be carried out as per ASL specifications and GFC drawings. FABRICATION BOQ Item no. - E.1,E.2 1)For Staircase Windows,
Painting supports 2)Toilet windows, Ventilators,
INTERNAL PAINTING BOQ Item no. A.5 3) All Ventilation Cutouts, Fresh Air Cutouts, AHU Room
Painting Details with Brush Application - 1 Coat of Red Oxide Primer (Asian Make) + 3 Coats of Synthetic Enamel Paint of Cutouts, Exhaust Fan Cutouts
Asianpaint Make, Color - Ivory Colour 4)For Covering DB, For Covering Exhaust Fan Cutouts
and
5) Any Other Areas as shown in GFC Drawings

12 MS Gratings including Fabrication Painting Providing, fabricating & Fixing MS Grating with necessary supports All works has to be carried out as per ASL specifications and GFC drawings. FABRICATION BOQ Item no. - For Basements Trench. External Development Trench,
E.3,E.4,E.5,E.6,E.7 Sumps.

Painting Details with Brush Application - 1 Coat of Red Oxide Primer (Asian Make) + 3 Coats of Synthetic Enamel Paint of INTERNAL PAINTING BOQ Item no. A.5
Asianpaint Make, Color - Black Colour

13 MS ODU Platform including MS railing for AC Providing, fabricating & Fixing MS ODU Platforms with necessary All works has to be carried out as per ASL specifications and GFC drawings. FABRICATION BOQ Item no's. - At specified floors, Other Areas as shown in GFC
including Fabrication Painting supports H.7,H.8,H.8a,H.9 Drawings

Painting Details with Brush Application - 1 Coat of Red Oxide Primer (Asian Make) + 3 Coats of Synthetic Enamel Paint of INTERNAL PAINTING BOQ Item no. A.5
Asianpaint Make, Color - Silver Colour

14 MS Platforms including Fabrication Painting Providing, fabricating & Fixing MS Platforms with necessary All works has to be carried out as per ASL specifications and GFC drawings. FABRICATION BOQ Item no. - H.11, H.18 1)For Receiving Area, Main Otla,
supports 2) At Overhead Storage at Godown area and 3) Any
INTERNAL PAINTING BOQ Item no. A.5 Other Areas as shown in GFC Drawings
Painting Details with Brush Application - 1 Coat of Red Oxide Primer (Asian Make) + 3 Coats of Synthetic Enamel Paint of
Asianpaint Make,

15 MS Pipe Height Barrier including Fabrication Providing, fabricating & Fixing MS Pipe Height Barrier with All works has to be carried out as per ASL specifications and GFC drawings. FABRICATION BOQ Item no. - H.13 Basement Ramp Entry and Exit
Painting necessary supports
INTERNAL PAINTING BOQ Item no. A.5
Painting Details with Brush Application - 1 Coat of Red Oxide Primer (Asian Make) + 3 Coats of Synthetic Enamel Paint of
Asianpaint Make, Color - Yellow+Black Colour

16 MS Canopy including Fabrication Painting Providing, fabricating & Fixing MS Canopy with necessary supports All works has to be carried out as per ASL specifications and GFC drawings. FABRICATION BOQ Item no. - H.14 1) For Receiving Area Entry,
2) Above All External Windows, Exhaust Fan cutouts,
INTERNAL PAINTING BOQ Item no. A.5 Fresh Air Cutouts,
Painting Details with Brush Application - 1 Coat of Red Oxide Primer (Asian Make) + 3 Coats of Synthetic Enamel Paint of 3)Staircase Headroom Doors, LMR Doors
Asianpaint Make, Color - Ivory Colour 4) over External Area Openings wherever RCC Chajja is
not provided,
5)Above Open to Sky Ramps going to Basement, and
6)Any Other Areas as shown in GFC Drawings

20 MS Framework with Cover (10mm thick plate) for Providing, fabricating & Fixing MS Framework with Cover for All works has to be carried out as per ASL specifications and GFC drawings. FABRICATION BOQ Item no. - I.9 At External Development
Earthing Pit including Fabrication Painting Earthing Pit with necessary supports
INTERNAL PAINTING BOQ Item no. A.5
Painting Details with Brush Application - 1 Coat of Red Oxide Primer (Asian Make) + 3 Coats of Synthetic Enamel Paint of
Asianpaint Make, Color - Black Colour

21 Compound Wall Items such as MS Sliding Gate at Providing, fabricating & Fixing MS Sliding Gate at Entry, Exit, MS All works has to be carried out as per ASL specifications and GFC drawings. FABRICATION BOQ Item no. - F.1, For Compound Wall
Entry, Exit, Barbed Wire Fencing with Concertina Openable Gate, Barbed Wire Fencing with Concertina Coil, MS Grill F.2,F.4,G.1,G.4,H.10
Coil & Y angle, MS Grill Fencing including Fencing with necessary supports
Fabrication Painting Painting Details with Brush Application - 1 Coat of Red Oxide Primer (Asian Make) + 3 Coats of Synthetic Enamel Paint of INTERNAL PAINTING BOQ Item no. A.5
Asianpaint Make, Color - Black Colour

K MISCELLANEOUS WORKS

L ELEVATIONS
All Floors. Elevation to be mutually approved.
Staircase

7 of 13
STANDARD FINAL AMENITIES LIST FOR PROJECTS (BTS)
ITEMS DESCRIPTION SPECIFICATIONS REFERENCE OF BOQ ITEMS LOCATIONS Remarks

Staircase running from Floor to Floor as per ASL Design Staircases as per ASL Design

Minimum width of Staircase shall be 2.5m & minimum width of central staircase shall be 3.0m. Any increase/ decrease in width
shall be governed based on the floor plate, building size & depth, All as per ASL design

Floor Height
Floor to Floor Height :- Floors as per ASL Design
Floor to Floor Height as per ASL Design

Space for multiple Signages in Elevation to be provided by developer. As per Dmart Specifications. Front signage in Hindi shall be
minimum 10 ft X 30 ft background in Ivory. ACP or RCC/Brick wall background in Ivory colour to be provided to Dmart and Dmart
letters will be provided and installed by ASL. Other signages will have to be 20 ft X 8 ft dimension each. The locations should ensure
visibility from long distance (500 mt to 1 km) in all directions

M DUCTS / CUTOUTS
Provision for Shafts for Fire, Electrical, HVAC, Plumbing & DG Proper cutouts and PVC pipes for duct sleeve and electric conducting shall be additionally provided if required & the same should
Exhaust shall be planned wherever required. be filled with waterproofing compound after Electric & HVAC work

Ducts The developer shall ensure that there shall be no shafts / Ducts running from the store Frontage.
Any internal shafts / ducts for Dmart purpose only can be planned from the store as per the agreed Layout.

N Submission drawings
Occupancy certificate drawings Developer to provide certified true copy of the Occupancy certificate received for the builidng

O Test Reports
Test reports for Steel, Concrete, soil etc. as required by consultants
also Building stability certificate to be provided by the Builder

All the final architectural & strucutral drawings shall be shared for
prood checking purpose.
All the drawings shall have clearly mentioned the design load in case of foundation drawing design pressures & loads considered shall be mentioned.
considered while designing.

In case of any discrepencies observed in the drawings the same shall


be informed to the Architect as well as Owner and all the drawings
issued for Architectural & sturctural shall reflect the same
dimensions.

P Construction Errors
All the errors in the construction work would be rectified as per the
structural consultant's advice for e.g. Honeycombing, verticality
alignment and horizontal alignment, Centring. Good quality of ply
should be used. All waterproofing leakages shall be rectified to
obtain an water tight structure.

Q Liasioning Cost
Power Release

Comencement Certficate All costs including Liasioning cost in


developers scope.

Revision of Plan (If required) All costs including Liasioning cost in


developers scope.

Completion certificate (Occupation Certifciate) All costs including Liasioning cost in


Pre-Fire NOC developers scope.
Final Fire NOC
Lift PWD License
Property Tax Compliances

8 of 13
STANDARD FINAL AMENITIES LIST FOR PROJECTS (BTS)
ITEMS DESCRIPTION SPECIFICATIONS REFERENCE OF BOQ ITEMS LOCATIONS Remarks

Approval of Layout for Substation & HT Equipment All costs including Liasioning cost in
developers scope.

Municipal Water Supply Connection

Removal and Replantaion of existing trees in and around proximity


of the property

Removal and relocation of electric poles and electrical lines (HT) in


and around proximitty of the property.

Removal and diversion of existing culverts and sewer lines/water


lines.

R Certified Soft and Hard Copies of Drawings


1. All Floor Plans as built

2. All Floor Structure Drawing As Built including Foundation details.

3. All Floor Plans CC Drawings

4. All Floor Plans OC Drawings

5. South Side Elevation

6. East Side Elevation

7. West Side Elevation

8. North Side Elevation

9. Section AA

10. Section BB

11. Plumbing Drawing

12.All Services Drawings

14. Survey & Topography detailled drawings.

S Other Details
Soil Test Reports The Same shall be provided to Dmart
for their Records.

Design Basis Report The Same shall be provided by


Dmart and bounding on developer
for their Records.

Structural Analysis Report The Same shall be provided by


Dmart and bounding on developer
for their Records.

Structural Stability Certificate. The Same shall be provided by


Dmart and bounding on developer
for their Records.

T Fire Fighting
Entire Fire Liasoning would be in Developer scope. It is Developer's responsibility to get unconditional Fire NOC for the project from Fire Officer.
Developer has to get and provide Pre ?ire NOC to D-Mart.

24 Fire NOC Necessary Fire NOC to be arranged by the Developer for enabling the Occupation of Building.

U Electrical

9 of 13
STANDARD FINAL AMENITIES LIST FOR PROJECTS (BTS)
ITEMS DESCRIPTION SPECIFICATIONS REFERENCE OF BOQ ITEMS LOCATIONS Remarks

Entire HT work from DP structure to VCB ,from VCB to Transformer including HT cabling along with Humme pipe & chamber ,earthing will be under developer scope .All HT equipments ,Transformer /VCB /Metering will be under developer scope as per ASLapproved specfication /Boq /layout.

1 Power Lisoning Entire Liasoning will be under Developers scope. Power sanction will be in the name of Avenue Supermarts Ltd. D-Mart to provide
Load sheet for the same. All CEIG approvals for all equipments to be taken by developer.

2 Substation Space & Foundation ( 18mtr X 4 mtr ) Developer to provide dedicated substation space for D-Mart of 10mtr X 3.5mtr & 8mtr X 3.5 mtr for DG & Diesel storage . All civil
foundations and cable trenches required for Metering, VCB, Transformer, DG & LT Panel to be provided by developer as per D-
Mart's approved layout. Developer to provide HT metering room as per ASLapproved layout .

3 HT Metering Unit Developer to provide dedicated HT power with separate HT meter for ASLwith connection brought till dedicated D-Mart's
Substation.
4 HT Cabling CABLE MAKE - POLYCAB - SITC of Entire HT CABLING and HT TERMINATIONS AT ALL POINTS would be under Developer's scope.
HT Cabling strictly to be laid in RCC Hume pipes with heavy duty chambers till inside the building premises.

5 Vaccum Circuit Breaker MAKE ABB / SCHINDER - SITC of VCB, 11KV/22KV, 400A. As per D-mart's approved specifications

6 SITC of Transformer MAKE - VOLTAMP / ESSENNAR - SITC of Oil /Dry Type Transformer as per site requirement. Developer need to send the Data
Sheet of Transformer Prior ordering for approval from Dmart.
7 Substation Earthing / Chamber Cover MAKE - ASHLOK - Chemical Bore Earthing. Earthing Model – ASEEL 19 CP(100μ) - 2 mtr & 3 mtr Earthing to be provided as per D-
mart's requirement. Along with Chamber cover Neco make model MS2 C -250 size 300x 300 mm

8 LIFTS Entire lift electrification work alongwith required Earth Pits, Earth Strips, Bulkhead fixtures and switch sockets in the shaft, CU
cables for Power, CU cables for Lighting, ELCB with MCB's will be under developers scope . Developer to lay all cables in perforated
cable tray (color code KEP 8334/12) till D-mart's main electrical panel as per site condition.

9 LIFT Earthings MAKE - ASHLOK - Chemical Bore Earthing. Earthing Model – ASEEL 19 CP(100μ) - 2 mtr Earthigns to be provided as per D-mart's
requirement.

10 Test cetificate & Documentation All test certificate and Documents / Warranty certificate /manual of all equipments need to be provided by the developer . The
entire system need to be test along with ASL engineer before handing over the same to ASL

11 Temporary Power Suppply for execution Temporary electrical power supply with meter for execution of services work will be under developer scope.
12 Fire Pannel Integration From Dmart's FAPA panel to developers Main fire ALARM PANEL panel ,integartion to be done by developer. which includes
cabling and other control circuits if required.
13 Common Area Where ever there is common area shared by devloper & ASL the lighting & power of the same need to be installed & maintain by
developer .
V Plumbing
Supply & Installation of entire Plumbing work including external & internal strom water drain , sewer line with chambers as per ASLspecification,boq,layout and contract documents . All floors Internal & external toilet plumbing & drainage work including sanitary fixtures will be under developer scope . As per ASLlatest GFC drawing & specfications .
Developer need to provide shop drawing for approval from ASL.

1 Municipal Water connection Liasoning for water meter connection will be under developer scope .Developer will provide commerical water connection of
minimun inlet size 40mm dia with water meter exclusive for Dmart. Developer will further lay pipe from water meter upto ASL
UG tank . ASL will only provide documents as per requirement .
2 Municipal sewer connection Developer need to connect ASL sewer line to main muncipal sewer line .
necessary approval with municipal to be done by developer.Necessary document will be shared by Dmart if required.

3 External Piping for Strom water line RCC NP-2 Class ISI marked pipe of required size with collar jointing & pipes laid to required alignment and slopes with joints in CM
1:1 ,providing 1:3:6 ,150 mm thick concrete bedding and benching, Depth up to1500 mm .

4 Inspection Chamber for Strom line Constructing inspection chamber of required size in 230mm brick masonary for depth upto 1mtr and 350mm brick masonary
for depth above 1mtr of chamber in CM1:5 with 150 mm thk. 1:2:4 PCC bedding, necessary benching in PCC 1:2:4 and 20mm
thk.cement plaster 1:4 and neat cement finished smooth inside & rough cement plaster outside,CI steps as necessary for heavy
duty air-tight, water tight Cover
5 Chamber Cover Ductile Iron Chamber covers Neco make Grade C - 250 = 25.0 MT (HD) . For sewer lines & terrave roof water drain the cover will be
without grating , and for strom water drain the cover will be with grating .

6 External Piping for Sewer line RCC NP-2 Class ISI marked pipe of required size with collar jointing & pipes laid to required alignment and slopes with joints in CM
1:1 ,providing 1:3:6 ,150 mm thick concrete bedding and benching, Depth up to1500 mm .

7 Inspection Chamber for Sewer line Constructing inspection chamber of required size in 230mm brick masonary for depth upto 1mtr and 350mm brick masonary
for depth above 1mtr of chamber in CM1:5 with 150 mm thk. 1:2:4 PCC bedding, necessary benching in PCC 1:2:4 and 20mm
thk.cement plaster 1:4 and neat cement finished smooth inside & rough cement plaster outside,CI steps as necessary for heavy
duty air-tight, water tight Cover

10 of 13
STANDARD FINAL AMENITIES LIST FOR PROJECTS (BTS)
ITEMS DESCRIPTION SPECIFICATIONS REFERENCE OF BOQ ITEMS LOCATIONS Remarks

8 Gully Trap Chamber 450x450 mm diameter stoneware gully traps with cement mortar 1:1 & 1:2:4 concrete around including constructing 450x450
mm clear size chamber in 230mm brick masonry 1:5 CM with 20mm thk. Smooth plaster and neat cement finish internally
complete with 450x450 Ductile iron cover & frame of approved make.

9 Gully Trap Chamber Cover Ductile Iron Chamber covers Neco make Grade C - 250 = 25.0 MT (HD) . For sewer lines & terrave roof water drain the cover will be
without grating , and for strom water drain the cover will be with grating .

10 Nanhni Trap & Urnial trap Astral , Supreme, Prince Make 110 x 75 mm , 110 x 110 mm PVC deep seal nahani traps with long long arm, C P heavy grating with
or without vent connection as required.
11 Soil Waste /Vent/ Anitisyphonage pipe Astral , Supreme, Prince Make UPVC Pipes of size as required for Soil waste / Vent / Antisyphonage pipes to withstand continous
internal hydraulic pressure of 6 kg/cm sq including necessary fittings and joining with rubber rings and lubricants as per standard
practice with holder bats; PVC clamps, dash fasteners fixed to walls,beams, or ceiling as required slope and necessary special heavy
detachable MS bracket and Testing as per standard Practice .

12 Ran water Pipe with bell mouth Rigid P.V.C. pipes of 110/ 160/200 mm B class Astral ,Supreme, Prince make including all fittings like offsets, shoes, bends etc with
MS bracket support on walls/celing with PVC or Special M.S. clamps .With bell mouth as per required size of Astral,Supreme
,Prince , make

13 Constructing inspection chamber of required size in 230mm brick masonary for depth upto 1mtr and 350mm brick masonary
for depth above 1mtr of chamber in CM1:5 with 150 mm thk. 1:2:4 PCC bedding, necessary benching in PCC 1:2:4 and 20mm
thk.cement plaster 1:4 and neat cement finished smooth inside & rough cement plaster outside,CI steps as necessary for heavy
duty air-tight, water tight Cover

Sanitary Fixtures
14 EWC FLOOR MOUNTED Floor Mounted European type WC Pan make parryware model number C0278(P) / C0297(S) PARRYWARE WHITE WC cover &
Seat C8094 WHITE

Floor Mounted EWC make Jaguar model ESC - WHT -551PN with seat cover

15 FLUSH VALVE Jaguar make FLUSH VALVE DUAL FLV 1085G Flush Valve 32 mm dia with male adapter of brass fitting along with all accessories .

16 ORRISA PAN 23" Parryware make ORISSA WC PAN 23" WHITE C0117 porcelain Chinaware P or S trap C2101
Jaguar make model number ECS- WHT -451
17 WASH BASIN Parryware make Wash Basin C0471(CTH)& C8151 ,Parry ware INDUS C 0471 ( CTH)72 .CP brass waste coupling T9911A1 , CP
brass bottle trap T3202A1 (Make Parryware ) CP brass heavy quality angle stop cock t9939a1

CP brass pillar tap FLR 5011NGD (Jaquar) CP brass heavy grade flexible inlet connection flr 5053n (Jaquar) ESC- WHT-801-JAGUAR
INCLUSIVE OF ALL ACESSORIES

18 URINAL Parryware make - Porcelain China ware-cat. No.Aquaseal - N / C 0578 white ,CP brass flush Valve, spreaders etc C8095 , CP brass
bottle trap T3202A1

Jaguar PRS 077G , URS - WHT - 13261

19 COAT HOOK SS Parryware - SS coat hook T6006A1


20 SOAP DISPENSER - CP BRASS Parryware - CP brass liquid soap dispensers T6514A1
21 BIB COCK Jaguar - 15mm CP brass bib cockFLR 5041NGD
22 TOILET PAPER HOLDER Parryware - Toilet paper holder T6514A1
23 HEALTH FAUCET WITH ANGLE COOK Jaguar - T9940A1 Allied , ALD - 577GD
24 Rain Water Harvesting Developer to provide the same as per D-Mart's approved layout. Bore Drilling with pneumatic rig in all types of Soil & rock with
installation of casing pipe.
-(300 mm Drill with 40 ft 6"dia 6 Kg PVC Perforated Pipe) .Providing of 5’ dia precast concrete ring. Providing & fixing of heavy
duty unbreakable ductile iron 24” dia frame & heavy duty cover for man hole at top of the filtration pit ( To withstand load of fire
tender vechile ) with PCC work. Providing of double section S.S. Screen as per specification and ASLdrawing . Providing of
filtration media : Gravels, Rubbles & Sand as required. Providing of M.S.Clamp for holding the PVC pipe & for use as a foot rest.
Providing of heavy duty precast concrete cover at top of the filtration pit

25 Water distribution system for Flushing & Domestic UPVC ASTM D- 1785, Schedule - 80, ASTRAL(Aquarius)
26 Domestic & Flushing Valves Astral /Supreme /Prince
27 Over Head tank Separate Over Head Tank ,capacity 10000 ltrs for firefighting ,10000 ltrs for Domestic , 10000 lts for Flushing , 5000 ltrs for STP
treated water . For RCC structure . For PEB /Roof structure Sintex make triple layered water tank of capcaity 10000 ltrs for
domestic , 10000ltrs for Flushing , 5000ltrs for treated water tank to be provided exclusive for ASL. Tank to be constructed as per
ASLapproved drawing .
28 Under ground tank Exclusive UGT of capacity 100000 ltrs for fire fighting , 20000 ltrs for Domestic for ASLto be provided by the developer .Tank to be
constructed as per ASLapproved drawing .

Developer need to provide domestic water of 20mm dia UPVC pipe with tap as per layout provided by ASL for AC odu cleaning
and terrace cleaning .
29 Water cooler point Developer need to provide domestic water of 20mm dia UPVC pipe with tap & drain point as per layout provided by ASL for
water cooler .

30 Crate Wasing point Developer need to provide Water tap & drain point for Crate washing as per location provided by ASL

31 CHILLER /FREEZER DRAIN Developer need to provide individual 40mm dia UPVC pipe for chiller & freezer drain as per the ASLapproved drawing .

32 SS SINK 24" diagonal nerali make sink with tray


33 PUMP SUB 250LPM 35MTRH ( Domestic Tank ) Submersible pump for Domestic water supply ( Kirloskar Model no. KDS-550+) 2 nos - 1 working & 1 standby

11 of 13
STANDARD FINAL AMENITIES LIST FOR PROJECTS (BTS)
ITEMS DESCRIPTION SPECIFICATIONS REFERENCE OF BOQ ITEMS LOCATIONS Remarks

34 PUMP PANEL 1W+1S WITH CO+LC SWITCH Composite control panel Kirloskar make for 2 x 3 HP Pumps for domestic . Along with sensor & sensor wire in PVC pipe &
accessories from panel to UGT and from UGT to OHT.

35 PUMP SUB 250LPM 35MTRH ( Flushing Tank ) Submersible pump for Flushing water supply (Kirloskar Model no. KDS-550+) 2 nos - 1 working & 1 standby

36 PUMP PANEL 1W+1S WITH CO+LC SWITCH Composite control panel Kirloskar make for 2 x 3 HP Pumps for domestic . Along with sensor & sensor wire in PVC pipe &
accessories from panel to UGT and from UGT to OHT.

37 BOREWELL (2 NOS.) Developer to provde bore well pump . The capacity will be as per site requirment & geotech survey .

38 BOREWELL PANEL (2 NOS.) Automated Borewell Starter panel. Along with sensor & sensor wire in PVC pipe & accessories from panel to Borewell & Panel to
OHT.
39 PUMP SUB 6LPS 10MTRH FOR BASEMENT (2 NOS.) Submersible motors of 1450RPM WITH VIBRATION ALTERNATOR vertical type & approved make all ISI Certified etc.6Ltrs/lps
discharge at about 10 mtr head against all losses at about 3HP motor (Muddy water pumps)Model no 2200CW Make Kirloskar. 2
nos of Pump 1 working 1 standby

39.i PUMP SUB 37 LPS 10-12 MTR H FOR storm water at RAMP (2 Submersible motors WITH VIBRATION ALTERNATOR vertical type & approved make all ISI Certified etc.36Ltrs/lps discharge at
NOS.) about (10-12) mtr head against all losses at about 10HP motor (Muddy water pumps)Model no Eterna CW 7500CW Make Kirloskar.
2 nos of Pump 1 working 1 standby

40 PUMP PANEL 1W+1S WITH CO+LC SWITCH for Basement. (2 NOS.) Composite control panel (COMMON FOR TWO PUMPS) of approved make star/Delta starter with auxillary contacts for indicating
lamps,level switches,changeover facility,on/off level probe switches switches,low & high level probe switches,auto
operation(rombus pen)& control circuit fuses as per electrical for above sump pump(all accesories should be suitable for damp &
humid area.including suitable cabling from panel to pump.(2 nos 3HP motor)

40.i PUMP PANEL 1W+1S WITH CO+LC SWITCH for storm water at Composite control panel (COMMON FOR TWO PUMPS) of approved make star/Delta starter with auxillary contacts for indicating
Ramp. (2 NOS.) lamps,level switches,changeover facility,on/off level probe switches switches,low & high level probe switches,auto
operation(rombus pen)& control circuit fuses as per electrical for above sump pump(all accesories should be suitable for damp &
humid area.including suitable cabling from panel to pump.(2 nos 10HP motor)

41 GUN METAL NON RETURN VALVE 80MM 80 mm horizontal /verertical typeGun metal non return valve tested to 21kg/sqcm with flanged type connection.(Make-Zoloto
/LM/Leder)

LV Piping

42 HDPE pipe HDPE Class pipe of 80/100 mm .Depth up to1500 mm

43 Inspection Chamber Constructing rectangular inspection chamber 450X450 mm clear size in brick masonary in CM1:5 with 150 mm thk. 1:2:4 PCC
bedding, necessary benching in PCC 1:2:4 and 20mm thk.cement plaster 1:4 and neat cement finished smooth inside & rough
cement plaster outside

44 Chamber Cover Neco Make - DI COVER ITEM CODE=MS4 , GRADE=B125

45 STP System Developer to provide RCC tanks for STP of 10 kld SBR type exclusive for ASL as per approved Specification & drawing from D
Mart . A bypass line from STP to Soak pit need to be provided by developer .

46 Septic Tank Developer to provide Septic tank as per ASLapproved layout

47 Soak pit Developer to provide soak pit as per ASLapproved layout

12 of 13
STANDARD FINAL AMENITIES LIST FOR PROJECTS (BTS)
ITEMS DESCRIPTION SPECIFICATIONS REFERENCE OF BOQ ITEMS LOCATIONS Remarks

48 Test cetificate & Documentation All test certificate and Documents / Warranty certificate /manual of all equipments need to be provided by the developer . The
entire system need to be test along with ASL engineer before handing over the same to ASL

NOTE: 1 Clear Land Survey drawings to be provided. 2. Proposed building to be incorporated in survey drawing.3. Structural drawings with Loading to be Provided. 4. Structural Foundation details to be provided.