Documente Academic
Documente Profesional
Documente Cultură
Accessed by account: (UCR) Universidad de Costa Rica | Date: Sun Oct 29 20:38:18 2017 | IP address: 163.178.101.228
Standard Practice for
1. INTRODUCTION
1.1. This standard practice presents specific details necessary to effectively control the production and
placement of hot mix asphalt (HMA).
1.2. This standard practice may involve hazardous materials, operations, and equipment. This
standard practice does not purport to address all of the safety concerns associated with its use. It
is the responsibility of the user of this standard practice to establish appropriate safety and health
practices and to determine the applicability of regulatory limitations prior to use.
2. SCOPE
2.1. This standard practice provides the necessary quality assurance plan for control, verification, and
acceptance of HMA pavement. It contains requirements for both quality control and acceptance.
2.1.1. This standard practice provides framework for a quality control plan that establishes minimum
requirements and activities for a contractor’s quality control (QC) system related to HMA
production and placement. These requirements include a listing of the inspections and tests
necessary to substantiate material and product conformance to the specifications. The primary
method of field quality control employs the use of the Superpave gyratory compactor and
evaluation of the volumetric properties of the mix.
2.1.2. This standard practice also provides framework for a plan that establishes acceptance requirements
for an agency’s assessment and acceptance of an HMA project.
3. REFERENCED DOCUMENTS
3.1. AASHTO Standards:
M 320, Performance-Graded Asphalt Binder
M 323, Superpave Volumetric Mix Design
M 332 Performance-Graded Asphalt Binder Using Multiple Stress Creep Recovery (MSCR)
Test
R 9, Acceptance Sampling Plans for Highway Construction
4. TERMINOLOGY
4.1. The terminology used in this standard is in accordance with R 10 unless otherwise specified.
4.2. hot mix asphalt (HMA)—a mixture of aggregate and asphalt binder produced from an HMA plant.
4.3. design mix formula (DMF)—the single point target value for percent passing designated sieve
sizes and volumetric properties developed in the laboratory before the start of production.
4.4. job mix formula (JMF)—the single point target value for percent passing designated sieve sizes
and volumetric properties established after the initial production process to be used by the
contractor for production quality control.
4.5. performance-graded asphalt binder (PGAB)—an asphalt-based cement that is produced from
petroleum residue either with or without the addition of nonparticulate organic modifiers graded to
temperature regimes and performance.
4.6. quality assurance (QA)—planned and systematic actions necessary to provide confidence that a
product is in conformance with agency plans and specifications. It contains both QC and
acceptance as two separate functions.
4.7. quality control (QC)—planned and systematic actions and considerations to control the level of
quality being produced.
4.9. acceptance—sampling, testing, and assessment of test results to determine whether produced
material and construction operation are in conformance with agency plans and specifications.
4.10. independent assurance program (IAP)—program developed by the agency to evaluate personnel
and equipment used in the acceptance process on a project or system-wide basis.
4.12. Definitions of many common terms relating to HMA are contained in ASTM D8.
4.13. Definitions of terms used in reference to other Standards are as defined therein.
4.14. Definitions of terms used in mathematical expressions are as generally used in standard practice.
Unique terms are defined in the section containing the first presentation of such terms.
5. SUMMARY
5.1. This standard presents a procedure containing minimum requirements for QC and QA plans
applicable to the production, placement, and acceptance of HMA. It incorporates the use of other
available standards, which are appropriate to the accomplishment of this task. The requirements
allow tailoring to accommodate the needs of an individual agency.
6.2. This standard is used to aid in the completion of tasks noted in Sections 6.2.1 and 6.2.2.
6.3. QC and acceptance plans conforming to this standard practice are applicable to HMA pavement
construction projects. If an inconsistency exists between the contract documents and either plan,
the contract documents should govern.
7. APPARATUS
7.1. Laboratory Requirements:
7.1.1. Personal safety equipment required by the laboratory or OSHA for work in the HMA design and
testing areas.
7.1.3. All other laboratory apparatus needed to control the quality of HMA production and placement in
accordance with project specifications.
7.2.2. Field apparatus listed in standards referenced as requirements in this standard practice.
7.2.3. All other field apparatus needed to control the quality of HMA production and placement in
accordance with project specifications.
7.3. Apparatus required in Sections 7.1 and 7.2 should be furnished in the quantity necessary to assure
that the materials and products used can be shown to conform to the HMA specification
requirements without undue delay of the production and placement process.
7.4. Additional apparatus required for use by agency representatives for verification and acceptance
activities should be provided by the agency unless otherwise specified.
8. STANDARDIZATION
8.1. Agency and contractor laboratories conducting work should satisfactorily participate in the
AASHTO Materials Reference Laboratory (AMRL) proficiency sample program and should also
be AMRL inspected. Alternately, a non-AASHTO laboratory qualification program that meets the
same requirements could be used. Inspections or tests not covered by AMRL should comply with
the applicable requirements of R 18 and ASTM D3666.
8.2. Sampling and testing personnel should be qualified through procedures developed by the agency
for obtaining samples, processing samples, inspection of work, operation of testing equipment,
and test equipment validation.
8.3. Verify the calibration of the nuclear density gauge(s) using ASTM D2950/D2950M or another
system approved by the agency.
8.4. Records demonstrating compliance with the equipment, personnel, and QC requirements should
be available during construction for agency review.
9.1.1. The agency should review and approve HMA volumetric mix designs proposed by the contractor
and assess the adequacy of the contractor’s QC plans. A reasonable time for review should be
specified. The agency or a representative of the agency is responsible for all acceptance testing.
9.2. Contractor:
9.2.1. The contractor should be responsible for the development and formulation of the DMF using
M 323, R 35, and T 312, which should be submitted to the agency for approval. The contractor
should be responsible for the QC of all materials during the handling, blending, mixing, and
placing operations. In addition, contractor tests may be used in the acceptance decision when a
contractor acceptance program is developed by the agency in accordance with Section 14.5.
10. SAMPLING
10.1. Initial Production Samples:
10.1.1. The contractor and the agency should obtain samples of HMA from plant-produced materials in
accordance with T 168 and the applicable procedures contained in Section 12.3 and Appendix X1.
Samples should be reduced to testing size in accordance with R 76 or ASTM C702/C702M.
Procedures for oven conditioning or reheating of samples should be established.
10.1.2. The contractor and the agency should select sample locations on the control strip in accordance
with Section 12.3 and Appendix X1. These locations are used for in-place density testing.
10.2.1. The contractor should obtain samples for QC in accordance with T 168, using a stratified random
sampling plan in accordance with Section 13.3 for determining lot sizes and Appendix X1 or
ASTM D3665 for sample location. Samples should be reduced to testing size in accordance with
R 76 or ASTM C702/C702M.
10.2.2. The agency should obtain samples for acceptance in accordance with T 168, using a stratified
random sampling plan in accordance with Section 13.3 for determining lot sizes and Appendix X1
or ASTM D3665 for sample location. Samples should be reduced to testing size in accordance
with R 76 or ASTM C702/C702M.
10.3.1. The agency representative should select in-place sample locations in accordance with Section 13.3
for determining lot sizes, Appendix X1 for sample location, and when cores are required, ASTM
D5361/D5361M for sampling.
Note 1—In addition to the random number tables in Appendix X1, ASTM D3665 also contains a
table of random numbers, including instructions for use. R 9 and ASTM E105, E122, and E141
contain additional information concerning sampling practices.
11.1.2. Quality control of PGAB from all suppliers should be in accordance with R 26 or other programs
approved by the agency.
11.2. Aggregates:
11.2.1. The agency should develop a testing program to ensure that aggregates meet specification
requirements. The contractor’s QC plan should include, as a minimum, discussion on the proposed
processing, transportation, stockpiling, and plant charging operations.
12.1.1. During initial plant start-up, adjustments may be made during the initial lot production to assure
the plant-produced HMA will meet the design requirements.
12.1.2. The contractor should be responsible for the operation of the HMA plant and the production of the
HMA within the DMF limits in Table 1. The limits in Table 1 are also used to control the amount
of deviation from the DMF that the contractor may use when declaring a JMF. The declared JMF
should meet the requirements of M 323.
12.2.1. At the beginning of production of each mixture required in the contract, an initial production lot
should be used to evaluate the DMF. The initial production lot should be divided into four sublots
as specified in Table 2 depending on the mixture type. The properties of the sublots will be
measured and compared to the DMF. If the deviation in air voids in any sublot exceeds
±2.0 percent or in any two sublots exceeds ±1.5 percent, the production should cease and a new
12.2.2. The last sample in the lot should be within the limits of Table 1. The initial production lot should
be closed out and the contractor should declare a JMF. The lot should be accepted with a pay
factor of 1.00. For material produced outside the tolerances of Section 12.2.1, the agency should
determine if the material should be left in place. The agency should require that a JMF be declared
after the initial production lot. Only one initial production lot should be allowed.
12.3.1. The contractor should obtain, using the methods required by Section 10, a sample of plant-
produced HMA from each sublot. Samples should be obtained from the mat behind the screed or
from the haul trucks at the plant. Because the evaluation criteria are based on in-place
measurements, it is recommended that QC testing be completed on road samples.
Note 2—If acceptance testing is performed on road samples, and the QC testing is based on truck
samples taken at the HMA plant, the contractor should develop appropriate correlation factors.
12.3.1.1. Determine asphalt binder content and combined aggregate gradation of the HMA samples in
accordance with T 164 and T 30, or T 308, or T 287 and T 30 (on cold feed material).
12.3.1.2. Determine maximum theoretical specific gravity of the HMA samples in accordance with T 209.
12.3.1.3.1. Determine bulk specific gravity, Gmb, in accordance with T 166, Method A.
12.3.1.3.2. Determine the air void content in accordance with R 35 at Nini and Ndes gyrations.
12.3.1.4. Determine the VMA and the VFA in accordance with R 35.
12.4.1. A process control chart is needed to determine whether the manufacturing process is in control.
Individual data points and moving averages are plotted. The individual data points indicate
variability and the moving average indicates conformance to the target value. Control charts
should comply with the requirements of Appendix X2.
12.4.3. Control charts are used to graphically represent the continuous control process. They include the
target value that is to be achieved for a certain material property and acceptable upper and lower
limits. When a measured value is determined and plotted on the control chart, it should fall within
the control limits. Mixture adjustment can be made in response to the values plotted on these
control charts.
12.4.4. Control limits are established based on statistical concepts that assume the material parameter in
question follows a normal distribution. Typically, the upper and lower control limits (UCL and
LCL) are based on ±2s (warning control limits) and ±3s (action control limits), where s is the
typical industry standard deviation listed in Table X3.1.
12.5.1. The contractor should place and compact the mixture produced during the initial production lot in
order to establish that the equipment and the processes planned for placement and compaction are
satisfactory.
12.5.2. The final compacted thickness of the HMA control strip should be the thickness required by the
pavement cross-section.
12.5.3. The control strip should be a minimum of 150 m (500 ft) long.
12.5.4. After compaction is completed, ten cores should be taken at locations selected in accordance with
Appendix X1. Density of the cores will be determined in accordance with T 166.
12.5.5. The control strip will be considered acceptable when the average core density meets or exceeds
contract specifications. The agency should specify limits for the number of control strips to
be allowed.
12.5.6. The agency should determine a minimum density (e.g., 91.0 percent of T 209) above which the
HMA in the control strip is allowed to remain in place and paid for with a pay factor of 1.00. For
HMA with a density less than the minimum density, the agency should determine if the HMA
should be left in place.
13.1.1. The contractor should provide and maintain a QC system that will provide reasonable assurance
that all materials and products conform to the specification requirements whether manufactured
or processed by the contractor or procured from suppliers or subcontractors. The contractor should
perform or have performed the inspection and tests required to substantiate product conformance
to the HMA design requirements, and should also perform or have performed all inspections and
tests otherwise required by the project specifications. The contractor’s QC procedures, inspections,
and proposed testing should be documented in a written QC plan (see Appendix X3). The plan
should be approved by the agency and be available for review through the life of the contract.
13.1.2. The contractor’s QC plan should be based on tests performed to determine compliance of the
HMA with the JMF. The tests should be performed on samples obtained using statistically sound,
randomized sampling procedures in accordance with Section 10.
13.1.4. QC testing will be based on samples from individual sublots and lots.
13.1.5. In accordance with agency requirements, the contractor should record the quantities of asphalt
binder, aggregate, mineral filler, and fibers (if required), as well as the quantities of HMA
produced, and the production temperature.
13.2.1. The QC plan should be contract-specific and state how the contractor proposes to control the
materials, equipment, and operations of the project. The agency should specify minimum
information for the QC plan such as: personnel, plant operation, HMA transportation, roadway
operations, and compaction operations.
13.3.1. The QC plan should indicate lot and sublot size for initial production and production lots.
13.3.2. Production lots will be based on HMA as delivered to the roadway. Recommended lot will be
defined for 19.0-mm nominal maximum aggregate size or larger mixture designs and for 12.5-mm
or smaller mixture designs. Lots will be further subdivided into equal sublots not to exceed
1000 Mg (1000 tons) for 19.0-mm or larger mixture designs or 600 Mg (600 tons) for 12.5-mm or
smaller mixture designs. Typically, four or more sublots constitute a lot. Partial sublots of 100 Mg
(100 tons) or less can be added to the previous sublot. Partial sublots greater than 100 Mg
(100 tons) can constitute a full sublot. Lots that contain a single sublot could be combined with the
previous lot for acceptance purposes.
13.4.1. The HMA producer should provide and maintain a laboratory for QC testing. The laboratory
should have the necessary space, equipment, and supplies for the tests to be performed. The
laboratory testing equipment should meet the requirements of the test methods identified for the
required sampling and testing. The agency should have the right to observe all QC testing.
13.5.1. The test equipment furnished by the contractor should be properly calibrated or verified and
maintained in accordance with Appendix X3.2 and R 18.
13.6.1. The contractor should designate the sampling and sample reduction procedures, sampling
locations, and size of samples necessary for testing. Sampling should be performed on each sublot.
Sample locations should be selected randomly according to Appendix X1. The contractor may
select random numbers independent of agency locations or may match the agency locations, but
samples should not be split. If contractor tests are to be used for acceptance, Section 14.5 should
govern the sampling requirements.
13.6.2. The contractor should use QC charts that show test results for critical sieves, asphalt binder
content, maximum theoretical specific gravity, air voids, VMA, and VFA to identify variability in
13.7.1. The contractor should control the HMA placement and compaction process to ensure compliance
with the project specifications. Details regarding QC for roadway operations are located in
Appendix X3.
13.8. Documentation:
13.8.1. The contractor should maintain adequate records of all tests. The records should indicate the test
results and the nature of corrective action taken as appropriate. All charts and records
documenting the contractor’s QC operations and tests should be available to the agency during the
performance and upon the completion of the work. The contractor should keep the test results on
file for a minimum period of three years following completion of the work.
13.8.2. Test properties for the various materials and mixtures should be charted on forms or other
appropriate means in accordance with the applicable requirements of the agency.
13.8.3. If production is terminated in accordance with Appendix X3.4.4 or X3.5.5, the cause and
resolution should be documented.
14.1.1. Acceptance sampling and testing of HMA involves stratified random sampling that is applied to a
series of sublots of HMA. The objective of acceptance testing is to verify that the product meets
contract specifications.
14.1.2. The agency will obtain, using the methods required by Section 10, a sample of HMA from
each sublot.
14.1.3. HMA properties for acceptance typically include the asphalt binder content, air voids, VMA, and
other requirements of the agency. Target values for these HMA properties should be those from
the JMF. Acceptance testing also includes density on the roadway.
14.1.4. Acceptance testing will be based on independent samples from the same sublots that are used for
QC and, in fact, may include different properties. Lots and sublots will be based on mixture as
delivered to the roadway.
14.1.5. The method of acceptance should be statistically based to evaluate the acceptability of the HMA.
Statistically based methods, such as percent within limits using standard deviation, should be used.
See Appendix X4.
14.2. Acceptance for Mixture Properties (Air Voids, VMA, Asphalt Content):
14.2.1. Point of Sampling—The agency representative should obtain stratified random acceptance samples
in accordance with Section 10.2. The samples should be obtained from the HMA behind the
screed prior to initial rolling.
Note 3—If a correlation factor between samples taken from a truck at the plant and samples from
the roadway behind the screed has been developed, the sample may be taken from the haul truck at
the plant.
14.2.3. Lot Size—Lots will be defined for 19.0-mm nominal maximum aggregate size or larger mixture
designs and for 12.5-mm or smaller mixture designs. Lots will be further subdivided into equal
sublots not to exceed 1000 Mg (1000 tons) for 19.0-mm or larger mixture or 600 Mg (600 tons)
for 12.5-mm or smaller mixture. Typically, four or more sublots constitute a lot. Partial sublots of
100 Mg (100 tons) or less can be added to the previous sublot. Partial sublots greater than 100 Mg
(100 tons) can constitute a full sublot. Lots that contain a single sublot could be combined with the
previous lot for acceptance purposes.
14.2.4. If a delay of more than four calendar days occurs in any one sublot, a partial sublot should be
declared and a new sublot should start when production resumes.
14.3. Acceptance for In-Place Density, Percent Theoretical Maximum Density (%Gmm):
14.3.1. Point of Sampling—The agency representative should determine stratified random acceptance
sample locations in accordance with Section 10.3. The locations should be determined after rolling
operations are completed.
14.3.2. Number of Tests—Two core samples or two nondestructive in-place tests per sublot are used in
accordance with Section 10.3.1.
14.3.3. Lot Size—Lot and sublot sizes are to be the same as the HMA lots and sublots in accordance with
Section 14.2.3.
14.3.4. Acceptance Testing—Obtain cores in accordance with ASTM D5361/D5361M from each location
and transport the cores to a laboratory for testing. From the HMA sample in each sublot,
determine the maximum specific gravity (Gmm). For each core, measure the bulk specific gravity
(Gmb) in accordance with T 166, and calculate density as a percent of theoretical maximum density
(%Gmm). Alternately, if the variability of test results is acceptable to the agency, a calibrated
nuclear density gauge can be used to determine the bulk specific gravity at each location, in
accordance with ASTM D2950/D2950M, and used to calculate density as a percent of theoretical
maximum density (%Gmm).
14.4.1. The agency will determine acceptable quality limits for HMA properties and in-place density.
14.4.2. Smoothness is also an important acceptance property. The agency should select a method of
measuring smoothness (e.g., rolling straightedge, lightweight or high-speed profilometers) and
will develop specific acceptance criteria.
14.4.3. The agency may also use subjective measures such as segregation to determine the acceptability of
the HMA. The agency may add specific criteria that may not be statistically based.
14.5.1. The use of contractor tests for project acceptance is permitted when the agency has developed an
Acceptance Program in accordance with Section 14.1.5 that includes independent verification and
statistical evaluation of the contractor’s test results. Contractor and agency sample locations will
be selected independently.
14.5.2. The contractor should maintain an acceptance testing program that includes the use of a qualified
laboratory and qualified testing personnel, established material sampling frequencies and testing
14.5.3. The agency should establish a verification sampling and testing program that includes testing of
materials by a qualified laboratory and qualified testing personnel on samples taken independently
of the contractor’s acceptance tests but within the same production period, quantity, area, etc. as
the contractor’s tests.
14.5.4. The agency should develop a statistical method of comparing the contractor’s acceptance and the
agency’s verification tests to verify the contractor’s acceptance test results, such as a comparison
of means and standard deviations.
14.5.5. The agency should develop a dispute resolution system in accordance with Section 15 that
addresses the disposition of discrepancies occurring between the contractor acceptance and the
agency verification tests.
14.5.6. The agency’s independent assurance program should include the evaluation of the contractor’s
qualified laboratory and qualified testing personnel.
14.6.1. The agency should develop a table of pay factors, pay equations, or pay curves based on the
method of acceptance.
14.7. Documentation:
14.7.1. The agency should maintain adequate records of all acceptance tests. The records should indicate
the test results and the acceptance decisions.
14.7.2. Contractor test results that are used for acceptance should be available to the agency during the
performance of the work. Test results should be submitted to the agency on forms or other
appropriate means in accordance with agency requirements.
15.1.1. The definition of dissimilar is typically based on the difference between reported values for split
samples as related to the number of standard deviations (d2s) for the test. The agency should use
AASHTO or ASTM test procedures to determine the range of allowable results between two
laboratories. Other valid procedures include statistical tests that compare means and variability of
the acceptance and verification tests results.
15.1.2. The specification should indicate the process by which a backup sample will be taken. Backup
samples should be taken at the same time as the original sample.
15.1.3. The dispute resolution process should address the length of time during which an appeal can be
made, who will do testing on backup samples, and how the retest values will be used to resolve
the dispute.
APPENDIXES
(Nonmandatory Information)
X1.1.1. This method outlines the procedures for selecting sampling sites in accordance with appropriate
random sampling techniques. Random sampling is the selection of a sample in such a manner that
every portion to be sampled has an equal chance of being selected as the sample. It is intended that
all samples, regardless of size, type, or purpose, should be selected in an unbiased manner, based
entirely on chance.
X1.2.1. Samples should be taken as directed by the contractor’s representative for QC purposes and the
agency representative for acceptance purposes.
X1.3.1. For test results or measurements to be meaningful, it is necessary that the material to be sampled
or measured be selected at random using a table of random numbers. Table X1.1 has been devised
for this purpose. To use the table in selecting sample locations, proceed as follows.
X1.3.1.1. Determine the lot size and stratify the lot into a number of sublots per lot for the material being
sampled.
X1.3.1.2. For each lot, use consecutive two-digit random numbers from Table X1.1. For example, if the
specification requires five sublots per lot and the number 15 is randomly selected as the starting
point from Column X (or Column Y) for the first lot, numbers 15 through 19 would be the five
consecutive two-digit random numbers. For the second lot, another random starting point, number
91, for example, is selected and the numbers 91 through 95 are used for the five consecutive
two-digit random numbers. The same procedure is used for additional lots.
X1.3.1.3. For samples taken from the roadway, use the decimal values in Column X and Column Y to
determine the coordinates of the sample locations.
X1.3.1.4. In situations where coordinate locations do not apply (i.e., plant samples, stockpile samples, etc.),
use those decimal values from Column X or Column Y.
X1.4.1. A random number table is a collection of random digits. The random numbers that are presented in
Table X3.1 are shown in a two-place decimal format. Note that there are two columns, labeled X
and Y. The numbers in either column can be used to locate a random sample when only a single
dimension is required to locate the sample (e.g., time, tonnage, and units). When two dimensions
are required to locate the sample, the number in the X column is used to calculate the longitudinal
location, and the number in the Y column is used to calculate the transverse location. In the Y
column, each number is preceded by an L or R, designating that the sample increment is to be
located transversely from the left or right edge of the pavement. Figure X1.1 illustrates the
procedure. An example demonstrating the use of the random sampling technique follows:
X1.5.1. HMA must be sampled to determine the asphalt binder content and other mixture-related criteria.
The definitions that define the lot and sublot size are located in Sections 13.3.2 and 14.2.3. The
total tonnage for the example project is 21 700 Mg (tons).
X1.5.2. First, identify the lot size and then determine the number of lots, sublot size, and, finally, the point
at which samples will be obtained.
X1.5.3. Lot Size and Number of Lots—For example, with a 19.0-mm nominal maximum aggregate size
mixture, the lot size is 5000 Mg (tons). Assuming there are 21 700 Mg (tons) of HMA required for
the project, the total number of lots is:
21 700 Mg (tons)
Number of Lots = = 5 lots
5000 Mg (tons)/lots
X1.5.4. Sublot Size—Based on Section 14.2.3, the sublot size is 1000 Mg (tons). The relationship between
lot and sublot size is shown in Figure X1.2. The actual number and size of sublots in a lot could
depend on specific conditions if partial sublots are declared during construction.
X1.5.5. Sublot Samples—For example, for HMA property samples, the number of samples per lot is five,
one per sublot. Five random numbers are selected from the table of random numbers. A block of
numbers from the random number table (Table X1.1) is reproduced below.
Sequence Number X Y
67. 0.93 R 0.17
68. 0.40 R 0.50
69. 0.44 R 0.15
70. 0.03 L 0.60
71. 0.19 L 0.37
X1.5.6. Select random numbers from the Y column only (disregard the L or R). These numbers are 0.17,
0.50, 0.15, 0.60, and 0.37. Multiply the numbers by the size of each sublot as follows to determine
the megagram (ton) to be sampled in the sublot.
X1.5.6.1. The technician must obtain the first sample at approximately the 170th Mg (ton) of the first sublot.
The technician must then wait until the first sublot is completed, 1000 Mg (tons), before selecting
the second sample at the 500th Mg (ton) of the second sublot. The same sequence is followed for
obtaining the remaining three samples.
X1.5.6.2. The sampling sequence for the lot of 5000 Mg (tons) should be:
Sublot 1: 170th Mg (ton)
Sublot 2: 1000 + 500 = 1500th Mg (ton)
Sublot 3: 2000 + 150 = 2150th Mg (ton)
Sublot 4: 3000 + 600 = 3600th Mg (ton)
Sublot 5: 4000 + 370 = 4370th Mg (ton)
X2.1.1. The process control procedure recommended is the use of control charts, particularly statistical
control charts. Control charts provide a means of verifying that a process is in control. It is
important to understand that statistical control charts do not get or keep a process under control.
The plant or construction personnel must still control the process. Control charts simply provide a
visual warning mechanism to identify when the contractor or material supplier should look for
possible problems with the process.
X2.1.2. Variation of construction materials is inevitable. The purpose of control charts, then, is not to
eliminate variability, but to distinguish between the inherent or chance causes of variability and a
system of assignable causes. Chance causes are a part of every process and can be reduced but
generally not eliminated. Assignable causes are factors that can be eliminated, thereby reducing
variability. Chance causes are something that cannot be eliminated, but it may be possible to
reduce their effects. The second cause of variation, assignable causes, can create major problems.
However, assignable causes can be eliminated if they can be identified. Examples of assignable
causes might be when the gradation for an aggregate blend goes out of specification because of a
hole in one of the sieves or because the cold feed conveyor setting is incorrectly adjusted.
X2.1.3. The statistical control chart enables the contractor to distinguish between chance and assignable
causes. Based on statistical theory, construction materials, when under production control, exhibit
a “bell-shaped” or normal distribution curve.
X2.1.4. The data, therefore, can be assumed to be within ±3 standard deviations (σ of the mean or target)
when the process is in control and only chance causes (variability that the contractor cannot
control) are acting on the system. Statistical control charts for average or means rely on the fact
that, for a normal distribution, essentially all of the values fall within ±3 standard deviations from
the mean. A normal distribution can be used because the distribution of sample means is normally
distributed.
X2.1.5. A statistical control chart can be viewed as a normal distribution curve on its side (Figure X2.1).
For a normal curve, only about 0.27 percent (1 out of 370) of the measurements should fall outside
±3 standard deviations from the average or mean. Therefore, control limits (indicating that an
investigation for an assignable cause should be conducted) are set at +3σ and –3σ.
X2.1.6. A statistical control chart includes a target value, control limits, and a series of data points that are
plotted. As shown in Figure X2.2, the target value is either the production mean or design value,
and the control limits are established based on the standard deviation of the properties.
X2.2.1. There are many forms of statistical control charts, but the form recommended in this standard
practice for construction materials and processes is a control chart that shows individual test data
points and a moving average. This process control chart is typically used to control the production
process about the target value. Highly variable, individual test data points indicate variability in
the process even though the moving average may be acceptable.
X2.2.2. For HMA, the process control chart for the moving average has five reference lines that are
defined as follows:
upper action limit is the target value plus three standard deviations (Table X3.1) divided by
the square root of the number of samples in the moving average. Typically, five samples are
used.
upper warning limit is the target value plus two standard deviations (Table X3.1) divided by
the square root of the number of samples in the moving average. Typically, five samples are
used.
target value is the value of the property from the declared JMF.
X2.2.3. Figure X2.3 shows a process control chart for asphalt binder content. The target value for asphalt
binder content, 5.7 percent, is obtained from the JMF.
X2.2.3.1. From Table X1.1 the standard deviation for asphalt binder content determined by extraction
is 0.25 percent.
X2.2.3.2. The deviation from the target value for the warning limits for a moving average of five samples is
= 2 × 0.25 / ( 5 )
= 0.22
X2.2.3.4. The deviation from the target value for the action limits for a moving average of five samples is
= 3 × 0.25/( 5 )
= 0.33
X2.2.4. The individual test data points from each sublot are plotted on the chart and connected. This series
of data points provides a visual indication of variability. If variability is high, the process can be
refined to reduce variability. The moving average of five data points is calculated starting with the
fifth data point and plotted on the chart. The moving average data points provide a visual
indication of conformance with the target value. It is also possible to detect trends in the
production and adjust the operation to bring the moving average closer to the target.
X3.1.1. This appendix provides the details for contractor QC activities for HMA.
X3.2.1.2. Identification of the calibration equipment used, e.g., standard weights, proving rings,
thermometers, etc;
X3.3.1. Sampling should be performed on each sublot on a random basis. The test methods and minimum
frequencies of the QC tests for each HMA design should be designated. Test results should be
rounded in accordance with ASTM E29, using the rounding method.
X3.3.2.1. Batch Plants—The blended aggregate gradation should be determined by calculating the
combined gradation of the aggregate from each hot bin.
X3.3.2.2. Drum Plants—The blended aggregate gradation should be determined using aggregate samples
from the cold feed belt after all materials are placed on the belt. The moisture content of the
samples should be determined in accordance with T 255.
X3.3.3. Recycled Materials—A minimum of one sample for each 1000 kg (1000 tons) of recycled asphalt
materials should be obtained and tested for asphalt binder content in accordance with T 164,
gradation in accordance with T 30, and moisture content in accordance with T 255. Asphalt binder
content may be determined with T 308 if a calibration factor to T 164 has been determined.
X3.3.4. Hot Mix Asphalt—As a minimum, samples should be obtained to determine the asphalt binder
content, air voids, and VMA of the HMA. The sample should be obtained in accordance with
Section 10.2. The sample should be reduced to testing size in accordance with R 76 or ASTM
C702/C702M, Method B. Place the test specimen mass into a heated mold, compact to Ndes in
accordance with T 312, and determine the bulk specific gravity (Gmb) in accordance with T 166. If
the HMA requires reheating to achieve the compaction temperature, it should be placed in a
loosely sealed, covered container. Oven temperature and time in the oven should be controlled, as
defined by the agency, to prevent a significant change in asphalt absorption and theoretical
maximum specific gravity. The maximum specific gravity (Gmm) should be determined in
accordance with T 209. One sample should be tested for moisture content in accordance with
T 255, asphalt binder content in accordance with T 164 or T 308, and gradation in accordance with
T 30. Alternately, the asphalt binder content may be determined in accordance with T 287, in
which case the gradation should be determined from the combined cold feed aggregates in
accordance with T 27. The aggregate consensus properties, coarse aggregate angularity (ASTM
D5821), fine aggregate angularity (T 304), flat and elongated particles (ASTM D4791), and sand
equivalent (T 176) may be required as determined by the agency.
X3.4.1. The contractor should use control charts for critical sieves, asphalt binder content, maximum
theoretical specific gravity, bulk specific gravity of the compacted HMA, air voids, and VMA to
identify variability in the HMA production process. All test results should be recorded on the
control chart the same day the tests are conducted. The charts are to be used to determine if the
HMA production is in control.
X3.4.2. Target values and warning and action limits for the control charts are determined from the JMF
HMA properties and plotted on the control charts. The warning and action limits are determined
using typical industry standard deviations for HMA properties as shown in Table X3.1.
X3.4.3. Individual test results and the moving average of the five most current test results should be
plotted. Five consecutive individual test results plotted on either side of the target value indicate
an HMA composition change. If a HMA compositional change has occurred, modifications should
be made to adjust the HMA property back to the target value. If a HMA compositional change has
occurred in a non-pay element, the contractor may elect to change the target value instead of
adjusting the HMA property back to the target value.
X3.4.4. For a pay element, if one moving average point falls outside the warning limits, an investigation
should be completed and adjustments made to bring the property back within the warning limits.
The adjustment should be documented. If two consecutive moving average points fall outside the
Table X3.1—Typical Industrya Standard Deviations for Hot Mix Asphalt Properties (Mixture Composition,
Gyratory Properties, and In-Place Density)b
Nuclear Ignition Cold
HMA Composition Property Extraction Gauge Furnace Feed
Asphalt Binder Content (Pb), % ±0.25 ±0.18 ±0.13 —
Gradation Passing 4.75-mm and Larger Sieves, % ±3 NA ** ±3
Passing 2.36-mm to 0.150-mm Sieve, % ±2 NA ** ±2
Passing 0.075-mm Sieve, % ±0.7 NA ** ±0.7
Maximum Theoretical Specific Gravity (Gmm) ±0.015
Gyratory Compacted HMA Property
Air Voids (Va), % ±1.0
Voids in Mineral Aggregate (VMA), % ±1.0
Voids Filled with Asphalt (VFA), % ±5
Bulk Specific Gravity (Gmb) ±0.022
In-Place Density
Roadway Core Density (%Gmm), % ±1.4
a
Agency-specific standard deviations may be developed in lieu of the industry standard deviation.
b
NCHRP 9-7 did not develop standard deviations for gradation of aggregate recovered from the ignition furnace; however, the standard deviation is expected to be
the same as for cold feed or solvent-extracted aggregates.
X3.4.5. For a non-pay element, if one moving average point falls outside the warning limit, the contractor
may elect to change the target value or adjust the property back to the target value. Mixture
production should be adjusted within the limits of Table 1, Section 12.1.2. If, after making the
adjustment, the mixture property remains outside the warning limit, a new DMF should be
developed in accordance with Section 9.2.1.
X3.5.1. At the beginning of roadway operations the contractor should establish a rolling pattern to
meet the minimum specified density. A control strip should be constructed in accordance with
Section 12.5. Density will increase up to a certain point, after which a very small increase in
density can be obtained with additional roller passes. At this point the density is presumed to
have reached its maximum and is then considered to have peaked when additional rolling does not
increase the density by more than 20 kg/m3 (1 lb/ft3).
X3.5.2. The contractor should use control charts for roadway density to identify variability in the HMA
compaction process. All test results should be recorded on the control chart the same day the
tests are conducted. The charts are to be used to determine if the HMA compaction process is
in control.
X3.5.3. Target values and warning and action limits for the control charts are determined from the
control strip described in Section 12.5 and plotted on the control charts. The warning and action
X3.5.4. Individual test results and the moving average of the five most current test results should be
plotted. If an HMA compositional change occurs and a new control strip is established, the target
value would be changed.
X3.5.5. If one moving average point falls outside the warning limits, an investigation should be completed
and adjustments made to bring the property back within the warning limits. The adjustment should
be documented. If two consecutive moving average points fall outside the warning limit or one
moving average point falls outside the action limit, the contractor should terminate production.
Prior to resuming production, the contractor should provide the agency with the assignable cause
for the unsatisfactory density test results and develop a new control strip in accordance with
Section 12.5.
X3.5.6. For purposes of QC for in-place density, lots and sublots should be in accordance with
Section 13.3.2. Location of in-place sample or test sites should conform to the requirements of
Appendix X1 in each sublot. The contractor should use standard nondestructive industry
equipment and procedures to provide suitable estimates of the in-place density.
X3.6.1. The contractor should develop a QC plan that is expected to be specific to operations in use at any
given time. The contractor should be able to make changes as required to respond to changes in
the operation. A plan should not be so general as to cover all expected situations. The plan should
be contract-specific and should include the following:
X3.6.1.1. Personnel including management personnel and plant and roadway technicians;
X3.6.1.2. Plant operations including stockpile management, material feed systems, HMA storage and truck
loading procedures, materials and finished product sampling, and testing procedures;
X3.6.1.3. Transportation of HMA including truck types, release agents, load cover, and truck discharge
procedures;
X3.6.1.4. Roadway operations including use of material transfer devices or windrow pickup machines, paver
setup such as paver speed, slope and grade control, and screed extensions; and
X3.6.1.5. Compaction operations including roller type and number, roller setup (e.g., amplitude, frequency,
or tire pressure), and roller speed.
X4.1.1. This appendix provides the procedure for determination of the percent of material that is within
the specification limits established for the HMA using the mean and standard deviation of the lot.
X4.2.1. The PWL is a calculation used in the agency acceptance plan to determine the acceptability of
materials on the project.
X4.3.1. Because the PWL procedure is an estimate of the population based on small sample distribution,
the agency should set upper and lower specification limits relative to the desired mean and
standard deviation. The mean is the target value established by the JMF and the standard deviation
is one typically found from test data for the property. Proposed specification limits are evaluated
for reasonableness to ensure constructability and performance. Table X4.1 provides typical
industry standard deviation values.
Note X2—Agency may use historical standard deviation within the state. At a minimum, the
standard deviation should be no greater than the typical industry standard deviations in Table X4.1
that were developed during NCHRP 9-7.
X4.3.2. Determine the specification limits and acceptable quality level (AQL). The AQL is usually set to
be 90 PWL, which means the specification limits will be ±1.645 standard deviations from the
target.
X4.3.3. The specification limits are determined from the target JMF value and typical standard deviation.
For example, if the standard deviation of asphalt binder content is 0.2 percent, HMA within
the AQL would be as shown in Figure X4.1. The specification limits are: JMF ± (1.645 × 0.20) =
JMF ± 0.33, rounded to ±0.35.
X4.3.4. In another example, if the agency requires two cores per sublot and sets the specification limits for
in-place density with an AQL of 90, the specification limits become 1.645 × 1.4 or ±2.3 percent.
For these two examples it would be possible to produce materials within these specification limits,
and the performance is expected to be satisfactory.
X4.3.5. For air voids, VMA, and asphalt binder content, the upper and lower specification limits (USL and
LSL) are calculated in Section X4.3.2. For in-place density, the LSL may be determined using a
target value and offsetting three standard deviations. The target may be obtained from the control
strip (Section 12.5) or may be predetermined as a desirable average density. Alternately, the LSL
may be set at a predetermined value of desirable minimum density such as 92.0 percent Gmm.
X4.4.1. Estimate the PWL in accordance with Sections X4.4.1.1 through X4.4.1.9.
X4.4.1.1. Locate n sampling positions in the sublot by use of Appendix X1 or other appropriate random
number tables.
X4.4.1.2. Perform tests on each sample taken behind the screed (HMA properties) and each core taken from
the roadway (density).
X4.4.1.3. For each test property, determine the average, x , the lot measurements where n is the number of
samples in the lot.
n
xi
x =∑ (X4.1)
i =1 n
X4.4.1.4. For each test property, determine the standard deviation, s, of the lot.
n
∑( x − x ) i
2
s= i =1
(X4.2)
n −1
X4.4.1.5. For air voids, VMA, and asphalt binder content, calculate both upper and lower quality indices
and the associated PWL. For in-place density, calculate the lower quality index and the associated
PWL. The method to determine the quality indices follows:
X4.4.1.5.1. Determine the upper quality index, QU, by subtracting the average ( x ) of the measurements from
the USL and dividing the result by s.
USL − x
QU = (X4.3)
s
X4.4.1.5.2. Determine the lower quality index, QL, by subtracting the LSL from the average ( x ) and dividing
the result by s.
x − LSL
QL = (X4.4)
s
X4.4.1.6. For PWLU, estimate the percentage of material that will fall within the upper tolerance limit
by entering Table X4.3 with QU using the column appropriate to the total number of
measurements, n.
X4.4.1.7. For PWLL, estimate the percentage of material that will fall within the lower tolerance limit by
entering Table X4.3 with QL using the column appropriate to the total number of measurements, n.
X4.4.1.8. For air voids, VMA, and asphalt binder content, where both upper and lower limits are used,
determine the percent of material that will fall within the limits by adding the percent within the
upper specification limit (PWLU) to the percent within the lower specification limit (PWLL), and
subtracting 100 from the sum.
Total PWL = (PWLU + PWLL) – 100 (X4.5)
X4.4.1.9. For in-place density, determine the percent of material that will fall above the lower specification
limit (PWLL).
X4.5.1. Determine the PWL for air voids, where the average air voids ( x ) of the lot is 3.7 percent, the
standard deviation is 0.6 percent, and the number of samples is five. The range of allowable air
voids is 2.4 percent to 5.6 percent.
X4.5.2. Calculate an upper and lower quality index value (QU and QL) using the following:
X4.5.3. Determine an upper and lower PWL using Table X4.3 with the number of the samples and the
calculated values of QU and QL.
For n = 5 and QU =4.00, the PWLU = 100.
Note X3—Because the value of QU exceeds the highest value under the column of n = 5, the
PWLU equals 100.
Next, for n = 5 and QL = 3.00, the PWLL = 100.
Then, the combined PWLU and PWLL is:
where:
s = sample standard deviation;
QL = lower quality index value;
QU = upper quality index value;
PWLU = percent within limits on the upper side of the specification;
PWLL = percent within limits on the lower side of the specification; and
PWL = total percent within limits.
EXAMPLE SPECIFICATION
HMA.01 DESCRIPTION
This work shall consist of one or more courses of HMA base, intermediate, or surface mixtures
constructed on prepared foundations and shall be in reasonably close conformance with the lines,
grades, cross sections, dimensions, and material requirements, including tolerances, shown on the
plans or indicated in the specifications.
HMA Producer Requirements. The producer takes responsibility for all aspects of the
production of quality HMA in accordance with the contract requirements, and the agency monitors
the producer’s production, methods of sampling, testing, calibration, verification, inspection
procedures, and anticipated frequencies of each. The HMA producer’s requirements include the
following:
1. The producer’s personnel shall include a qualified technician who shall compact and analyze
the HMA specimens and perform the maximum specific gravity test. The technician shall
supervise all other sampling and testing of materials, the maintenance of control charts, and
the maintenance of the project diary.
2. The producer shall provide and maintain a laboratory for process control testing. The
laboratory shall have the necessary space, equipment, and supplies for the tests to be
performed. The laboratory testing equipment shall meet the requirements of the test methods
identified for the required sampling and testing, except that an electronic balance shall be
QC Plan for Roadway Operations. The contractor shall identify their process to control the
HMA placement and compaction processes to ensure compliance with the project specifications.
As a minimum:
1. The contractor shall provide a qualified technician who shall conduct QC testing for
temperature, density, and smoothness, and monitor paving operations and joint construction.
2. The QCP shall include the contractor’s methodology for balancing the operation including
plant production, transportation, placement, and compaction.
3. The QCP shall also include delivery truck management, procedures for unloading the HMA
and residue materials from the truck, and material transfer vehicle operations including plans
for crossing bridge structures.
4. The paving plan shall include procedures for the material feed system, grade and slope
controls, joint construction, HMA sampling and testing plan, temperature, rolling, density,
coring, and smoothness testing.
5. The QCP shall also include documentation of all QC testing and equipment used in the HMA
operations. The contractor should maintain adequate records of all tests. The records should
indicate the test results and the nature of corrective action taken as appropriate. All charts and
records documenting the contractor’s QC operations and tests should be available to the
agency during the performance and upon the completion of the work. The contractor should
keep the test results on file for a minimum period of three years following completion of the
work. Test properties for the various materials and HMA should be charted on forms or other
appropriate means that are in accordance with the applicable requirements of the agency.
QC Plan for Asphalt Binder Materials. QC of asphalt binder materials from all suppliers shall
be in accordance with R 26 and the following:
1. The supplier shall prepare and submit a QCP that covers the manufacture, storage, shipping,
and handling of all materials.
2. The supplier shall conduct testing in a laboratory that has been approved by the agency.
Participation in the AMRL equipment inspection and proficiency sample programs with
satisfactory ratings will be the basis for approval.
3. Specification compliance testing and complete AASHTO testing shall be accomplished at the
frequency outlined in the QCP per grade of binder and at least once following feed stock
changes. After initial testing, the minimum frequency for specification compliance testing
shall be once per month.
QC Plan for Aggregate Production. The agency should develop a testing program to ensure that
aggregates meet specification requirements. The contractor’s QCP should include, as a minimum,
discussion on the proposed processing, transportation, stockpiling, and plant charging operations
and the following:
1. The producer’s personnel shall include a qualified technician who shall perform the pertinent
duties during critical activities to meet the requirements of the QCP. The technician shall
supervise the sampling and testing of materials, the maintenance of control charts, and the
maintenance of the project diary.
2. The producer shall provide and maintain a laboratory for process control testing. The
laboratory shall have the necessary space, equipment, and supplies for the tests to be
performed. The laboratory testing equipment shall meet the requirements of the test methods
identified for the required sampling and testing, except that an electronic balance shall be
provided. The test equipment furnished by the producer shall be properly calibrated or
verified and maintained within the limits described in the applicable test method.
3. Sampling and testing of all materials that require control for aggregate gradation, decantation,
deleterious, and crushed particles shall be in conformance with the AASHTO and agency
requirements. Sampling shall be performed on uniform tonnage increments in an unbiased
manner, and testing of the samples shall be accomplished in such time as to assure that
process control is maintained. Testing shall be performed in accordance with the respective
test methods unless otherwise stated by the agency.
4. The producer shall maintain control charts at the aggregate laboratory. All control test results
shall be recorded on the control charts the same day the tests are conducted. As a minimum,
the charts shall be maintained until 30 test data points have been plotted. Subsequent to that
time, at least 30 test data points shall be continuously displayed.
5. The producer’s control charts shall include the critical sieve(s) for each aggregate size from
stockpile samples and critical sieve(s) for each blended aggregate.
6. The producer shall retain the QC test results for a minimum period of three years.
MATERIAL
HMA.03 MATERIALS
Materials shall be in accordance with the following:
Performance-Graded Asphalt Binder AASHTO M 320
Coarse Aggregates Agency Requirements
Fine Aggregates Agency Requirements
The single percentage of aggregate passing each required sieve shall be within the limits of
AASHTO M 323.
Dust/calculated effective asphalt binder ratio shall be from 0.6 to 1.2 when the aggregate gradation
passes above the primary control sieve control point and 0.8 to 1.6 when the aggregate gradation
passes below the control point. The optimum asphalt binder content for dense-graded mixtures
shall produce 4.0 percent air voids at Ndes. The design shall have at least four points, including a
minimum of two points above and one point below the optimum. The maximum specific gravity
of the uncompacted mixture shall be determined in accordance with AASHTO T 209.
Dense-graded mixtures shall be tested for moisture susceptibility in accordance with AASHTO
T 283. The minimum tensile strength ratio (TSR) shall be 80 percent. The 150-mm (6-in.) mixture
specimens shall be compacted in accordance with AASHTO T 312. If anti-stripping additives are
added to the HMA to meet the minimum TSR requirements, the dosage rate shall be submitted
with the DMF.
Changes in the source or types of aggregates shall require a new DMF. A new DMF shall be
submitted to the engineer for approval one week prior to use.
The HMA design compaction temperature for the specimens shall be in accordance with the
asphalt binder supplier’s recommendations or determined from a temperature–viscosity curve
based on AASHTO T 316.
Design criteria for each HMA shall be based on the ESAL value shown in the contract documents.
Air void, VMA, and VFA criteria shall be in accordance with AASHTO M 323 and R 35.
During initial plant start-up, adjustments may be made to assure the plant-produced HMA will
meet the design requirements. For the initial production lot, the contractor shall produce HMA
within the limits in the table below. The DMF may be adjusted to bring the DMF into compliance
with the requirements of AASHTO M 323. The maximum adjustment should be within the
following limits:
By the end of the lot, the HMA should be within the limits of the above table. The initial
production lot shall be closed out, and the contractor shall declare a JMF.
For all lots except the initial production lot, HMA will be accepted for asphalt binder content,
VMA at Ndes, and air voids at Ndes based on tests performed by the engineer. Acceptance testing
for surface mixtures will include tests for moisture content. The engineer will randomly select a
location within each sublot for sampling. An acceptance sample will consist of two plate samples
with the first being at the random location and the second 0.6 m (2 ft) ahead. A backup sample
consisting of two plate samples shall be located 0.6 m (2 ft) towards the center of the mat from the
acceptance sample. An additional sample for moisture content shall be located 0.6 m (2 ft) back
from the random sample location.
The maximum percent of moisture in the mixture shall not exceed 0.10 from plate samples. Air
voids, asphalt binder content, and VMA values will be reported to the nearest 0.1 percent.
Moisture and draindown test results will be rounded to the nearest 0.01 percent.
In the event that an acceptance sample is not available to represent a sublot(s), all test results of
the previous sublot will be used for acceptance. If the previous sublot is not available, the
subsequent sublot will be used for acceptance.
The engineer’s acceptance test results for each sublot will be available when the testing is
complete. The contractor may request an appeal of the engineer’s test results in accordance with
HMA.21.
Determine percent within limits (PWL) and pay factors in accordance with HMA.20.
CONSTRUCTION REQUIREMENTS
HMA.11 GENERAL
Equipment for HMA operations shall be in accordance with agency requirements.
Fuel oil, kerosene, or solvents shall not be transported in open containers on equipment. Cleaning
of equipment and small tools shall not be accomplished on the pavement or shoulder areas.
Segregation, flushing, or bleeding of HMA will not be permitted. Corrective action shall be taken
to prevent continuation of these conditions. Segregated, flushed, or bleeding HMA shall be
removed if directed. All areas showing an excess or deficiency of asphalt binder shall be removed
and replaced.
All HMA that has become loose and broken, mixed with dirt, or is in any way defective shall be
removed and replaced.
HMA.16 JOINTS
Longitudinal joints in the surface shall be at the lane lines of the pavement. Longitudinal joints
below the surface shall be offset from previously constructed joints by approximately 150 mm
(6 in.) and be located within 300 mm (12 in.) of the lane line.
Transverse joints shall be constructed by exposing a nearly vertical, full-depth face of the previous
course. For areas inaccessible to rollers, other mechanical devices shall be used to achieve the
required density.
If constructed under traffic, temporary transverse joints shall be feathered to provide a smooth
transition to the driving surface.
HMA.17 DENSITY
Acceptance will be based on lots and sublots in accordance with HMA.08.
Density of the compacted dense-graded HMA will be determined from cores based on samples
obtained from two random locations selected by the engineer within each sublot. One core shall be
cut at each random location. The transverse core location will be located so that the edge of the
∑( x − x ) i
2
s= i =1
n −1
For air voids, asphalt binder content, and VMA, calculate the upper quality index, QU, by
subtracting the average ( x ) of the measurements from the upper specification limit (USL) and
dividing the results by s. Limits are listed in the table of specification limits (see Table X1).
USL − x
QU =
s
Estimate the percentage of material that will fall within the upper tolerance limit by entering the
table of quality index values with QU using the column appropriate to the total number of
measurements, n.
For air voids, asphalt binder content, VMA, and in-place density, calculate the lower quality
index, QL, by subtracting the lower specification limit (LSL) from the average ( x ) and dividing
the result by s.
x − LSL
QL =
s
Estimate the percentage of material that will fall within the lower tolerance limit by entering the
table of quality index values with QL using the column appropriate to the total number of
measurements, n.
For air voids, asphalt binder content, and VMA, where both upper and lower limits are used,
determine the percent of material that will fall within the limits by adding the percent within the
upper specification limit (PWLU) to the percent within the lower specification limit (PWLL), and
subtracting 100 from the sum.
Pay factors are calculated for each property, air voids at Ndes, asphalt binder content, VMA at Ndes,
and in-place density (%Gmm). The appropriate pay factor for each property is calculated as follows:
Estimated PWL greater than 78:
PF = 0.045(PWL) + 96.5
Estimated PWL greater than or equal to 42 and less than or equal to 78:
PF = –0.006(PWL)2 + 1.4(PWL) + 27.3
If the pay factor for any one of the properties is less than 75, the engineer will determine if the
material will be required to be removed, other corrective action is to be taken, or if it will be left in
place at a further reduced pay factor.
For all lots other than the initial production lot, a composite pay factor is determined for each lot
based on test results for HMA properties and density in a weighted formula as follows:
CPF = 0.20(PFBINDER) + 0.35(PFVOIDS) + 0.10(PFVMA) + 0.35(PFDENSITY)
where:
CPF = lot combined pay factor for mixture and density;
PFBINDER = lot pay factor for asphalt binder content;
PFVOIDS = lot pay factor for air voids at Ndes;
PFVMA = lot pay factor for VMA at Ndes; and
PFDENSITY = lot pay factor for density.
The quality assurance adjustment points for smoothness will be calculated in accordance with the
following:
When the pavement smoothness is tested with a profilograph, payment will be based on the final
profile index (PI0.0) in accordance with the following table:
A quality assurance pay factor for smoothness (PFs) will apply to the typical section including the
aggregate base and the HMA base, intermediate, and surface courses. The quality assurance
adjustment for each section will include the total area of each pavement lane excluding shoulders
for a 0.16-km (0.1-mi) long section represented by the profile index calculated by the following
formula:
n
S
qs = ( PFs − 1.00)∑ A × × U
i =1 T
where:
qs = quality assurance adjustment for smoothness for one section;
PFs = pay factor for smoothness;
n = number of layers;
A = area of the section, m2 (yd2);
S = spread rate for the material, kg/m2 (lb/yd2);
T = conversion factor: 1000 kg/Mg (2000 lb/ton); and
U = unit price for the material, $/Mg ($/ton).
For the entire contract, the quality assurance adjustment for smoothness, QS, will be the total of the
quality assurance adjustments for smoothness, qs, on each section by the following formula:
Qs = ∑ q s
HMA.21 APPEALS
If the QC test results do not agree with the acceptance test results, a request, along with the QC
test results, may be made in writing for additional testing. Additional testing may be requested for
one or more of the following tests: Gmm, Gmb of the gyratory specimens, asphalt binder content, or
bulk specific gravity of the density cores. The request for the appeal for Gmm, Gmb of gyratory
specimens, asphalt binder content, or bulk specific gravity of the density cores shall be submitted
within seven calendar days of receipt of the agency’s written results for that lot. The lot, sublot,
and specific test(s) shall be specified at the time of the appeal. Upon approval of the appeal, the
engineer will perform additional testing as follows:
The backup sample(s) or new cores will be tested in accordance with the applicable test method
for the test requested.
Gmm. The backup Gmm sample will be tested in accordance with AASHTO T 209, Section 9.5.1.
Gmb of the Gyratory Specimen. New gyratory specimens will be prepared and tested in
accordance with AASHTO T 312 from the backup sample.
Asphalt Binder Content. The backup asphalt binder content sample will be prepared and tested
in accordance with the test method that was used for acceptance.
Bulk Specific Gravity of the Density Core. Additional cores shall be taken within seven calendar
days unless otherwise directed. Additional core locations will be determined by adding 0.3 m
(1.0 ft) longitudinally to the site of the cores tested using the same transverse offset. The appeal
density cores will be tested in accordance with AASHTO T 166.
The appeal results will replace all previous test result(s) for acceptance of HMA in accordance
with HMA.10 and density in accordance with HMA.17. The results will be furnished to
the contractor.
Preparation of surfaces to be overlaid shall be included in the cost of other pay items.
Coring and refilling of the core holes shall be included in the cost of other pay items within this
section.
No payment will be made for additional anti-stripping additives, appeal coring, or traffic control
expenditures related to coring operations.
Corrections for pavement smoothness shall be included in the cost of other pay items within this
section.
The price for profilograph, HMA, will be full compensation regardless of how often the
profilograph is used or how many profilograms are produced.
1
Formerly AASHTO Provisional Standard PP 52. First published as a full standard in 2006.