Sunteți pe pagina 1din 14

Environmental and Social

Impact Assessment

Fort George, Mauritius


2017

5
lkhkjhkj
5 Project description

49
Environmental and Social
Impact Assessment

Fort George, Mauritius


2017

1 INTRODUCTION
This chapter provides information on the principal elements of the CCGT project. A description of the
existing project site and surrounding area is provided. The main plant components, processes and
materials used are identified.
In line with its objective to ensure security of electricity supply, the CEB is contemplating to set up a
thermal power plant based on combined cycle gas turbine technology, at Fort George, Mauritius. The
site which has been selected lies next to the current Fort George Power Station (FGPS). It will be a
Combined Cycle Gas Turbine (CCGT) that will successively work with DFO and in Open Cycle in
Section 1, and with Natural Gas and in Combined Cycle in Section 2.
This chapter elaborates on the technical design of the plant.

2 PROJECT SITE
The project site is situated at Chaussée Tromelin, Fort George, Mer Rouge, Port Louis, Mauritius and is
within the boundary limits of the Port Area. It is easily accessible by a two-way tarred road. The project
site is adjoined by Fort George (The Fortress) on the North West, Fort George Power Station on the
north, a tarred access road on its east, and bounded by Mauritius Chemical and Fertilizer Industry
Limited (MCFI).
This site has been selected due to the proximity of the Fort George power station (FGPS) and 66kV
transmission lines. The site earmarked for the proposed undertaking covers an area of 2 Ha and it is
classified as state land that falls under the present jurisdiction of the Mauritius Port Authority (MPA).
The proposed CCGT power plant will be located opposite to FGPS and next to the premises of the
MCFI Group. The new power plant will be around 1 km from the nearest residential zone.

Photo 1 Project site area (view from FGPS)

Poonam Tatayah
Ecology Consultant
Biodiversity Consulting Ltd
River view Lane, Verdun.
BRN: C 15130202 50
Environmental and Social
Impact Assessment

Fort George, Mauritius 2017

Map 2 Site location and its surrounding

Poonam Tatayah
Ecology Consultant
Biodiversity Consulting Ltd
River view Lane, Verdun. 51
BRN: C 15130202
Environmental and Social
Impact Assessment

Fort George, Mauritius 2017

Figure 4 Additional plot of land at Fort George from MPA

Poonam Tatayah
Ecology Consultant
Biodiversity Consulting Ltd
River view Lane, Verdun. 52
BRN: C 15130202
Environmental and Social
Impact Assessment

Fort George, Mauritius


2017

3 GENERAL CONFIGURATION OF THE CCGT


The Fort George Combined Cycle Gas Turbine (CCGT) power plant project consists of the installation
and commissioning of two heavy duty dual fuel gas turbines and one steam turbine in a combined
cycle arrangement. The CCGT power plant will successively operate with different fuels/ technologies:
• Section 1: Open cycle (OCGT) on Diesel Fuel oil (DFO)
The OCGT power plant will be used for peaking purpose
• Section 2: Combined cycle (CCGT) on Natural Gas (NG), DFO remain as a back-up fuel.
The CCGT power plant will be used for base load operation and will be rated between 105 - 120MW
when operating on DFO and be capable of producing up to 140MW when operating on Natural Gas.
The Fort George OCGT shall run on DFO initially and after implementation of the 2nd section
(conversion from OCGT to CCGT) (i.e. between 2-3 years after completion of Section 1), the CCGT
will be commissioned and operated on NG.

3.1 COMBINED CYCLE TECHNOLOGY ADOPTED


The Combined Cycle technology is based on the use of gas turbine(s) fired with either Liquid or Gas
fuel combined with a steam turbine which is driven by steam produced from waste heat from the gas
turbine(s), in order to increase efficiency and electrical output.
The general configuration considered is a combined cycle plant based on two cycles, namely
the Gas Turbine (Brayton) cycle and the Water/Steam (Rankine) cycle. The CCGT at Fort
George, will include two Gas Turbines (GT), each associated with one Heat Recovery Steam
Generator (HRSG), and only one common steam turbine fed by the steam flows from both
HRSG`s. This choice is driven by the power output desired, to maximize the efficiency of the
combined cycle power plant, even at part load and considering the limitation of power output per
generator imposed by Mauritius network constraints. This combined cycle technology allows reaching
the highest efficiency among all electricity production technologies from thermal sources, with an
estimated efficiency of over 54 %.

The gas turbines will operate in open cycle mode (OCGT) after implementation of Section 1. The estimated
operation as OCGT is between 2-3 Years. After implementation of Section 2 and commissioning of the
CCGT plant, in case of necessity (unavailability of either one or two HRSG or the steam turbine), it will still be
possible to operate the gas turbines as OCGT using the bypass stacks.

The gas turbine rating between 35-40MW considered for the present project rejects less heat from the
exhaust diffuser as compared to gas turbine ratings, typically 125 -375MW, used in CCGT Power
plants of higher capacity. Based on analysis of all possible configurations for the CCGT, it is
recommended to consider HRSG`s with 2 pressure levels, without reheat, which is the market
standard design for such rating of CCGT Power Plant.

3.2 MAIN COMPONENTS


Combined Cycle Gas Turbine power plants are generally manufactured by Original Equipment
Manufacturers (OEM`s) as a standard reference plant with pre-engineered packages designed to plug
together, thus minimizing onsite erection time. The major equipment such as the gas turbines (GT),
steam turbine (ST), generators and step up (GSU) transformers are shipped to the site in a pre-
assembled or pre-engineered modular compartments and factory tested. The Heat Recovery Steam

Poonam Tatayah
Ecology Consultant
Biodiversity Consulting Ltd
River view Lane, Verdun.
BRN: C 15130202 53
Environmental and Social
Impact Assessment

Fort George, Mauritius


2017

Generators (HRSG) are also shipped in pre-engineered, modularized sections and are designed for
easy tube welding and assembly.

3.2.1 Gas (Combustion) turbine


In basic terms, the combustion turbine also known as the gas turbine consists of three main sections:
the compressor, the combustion chambers and the turbine sections. Filtered air enters the
compressor section, which compresses the air and draws it to the combustion chambers. Fuel is then
mixed to the compressed air and ignited. The combustion process is carried out at constant pressure.
Thereafter, the continuous hot combustion gases are directed towards the turbine section where they
expand through the turbine blades to perform work that provides the power to drive the compressor
section as well as to spin the Generator, for generation of electricity. After the hot gases exit the
turbine they are directed to the exhaust section and flow through a heat recovery steam generator
(HRSG) to produce steam, which is then fed to the steam turbine.
The gas turbine type earmarked for the project is the Heavy Duty / Industrial Gas Turbine which will
have a net output of between 35-40MW, at site conditions.

Figure 5 Combustion gas turbine fundamental structure3

3.2.2 Steam turbine


The Fort George CCGT will be equipped with 1 steam turbine.
The steam turbine will be designed to have a minimum permitted operation load as low as possible as
and not higher than 25%, and each gas turbine is expected to have a minimum operating load of
around 50 %. At this minimum load, the ST shall be designed to run without limitation. The ST will be
equipped with a fully automatic shaft turning device. Gland steam sealing system will be provided to
prevent air from exiting the ST. The entire ST will be designed to avoid leak of lube oil or control fluid
as well as to reduce risk of inflammability. The steam turbine drains will be collected, where required,
cooled down and sent back to the condenser well.

3.2.3 Heat recovery steam generators


Two (2) Heat Recovery Steam Generators will be installed. The following parameters have been
estimated for each HRSG:

3
African development bank group, 2015. Project Damanhour combined cycle power plant project.

Poonam Tatayah
Ecology Consultant
Biodiversity Consulting Ltd
River view Lane, Verdun.
BRN: C 15130202 54
Environmental and Social
Impact Assessment

Fort George, Mauritius


2017

• Diesel (DFO) fired: First LP Economizer inlet temperature: 95°C (recirculation pumps are
necessary);
• Diesel (DFO) fired: Flue gas minimum exhaust temperature: 85°C;
• Natural gas Fired: First LP Economizer inlet temperature: 55°C.
Due to the limited area, available on site, vertical HRSG’s are expected to be used.

3.3 MAIN RESOURCE REQUIREMENTS


3.3.1 Diesel Fuel Oil (DFO)
The DFO to be considered for the project has a Lower Heating Value (LHV) of 42 500 kJ/kg. The site
DFO values are detailed hereafter.

Table 12 DFO delivery contract requirements

Delivery contract
Unit Criteria Site DFO value
requirement
Ash % Mass Max 0.01 0.01
Pour point °C Max -9 -9
Kinematic viscosity @ 40°C cSt Min -Max 2.0 – 5.0 3.5
Density @15°C Kg/m3 Min -Max 820 – 860 840
Sulfur content Mg/kg Max 50 50
Water content % volume Max 0.05 0.05

3.3.2 Natural Gas


The Fort George CCGT will use regasified LNG obtained under a long-term supply contract and for
which the seller is expected to responsible for the sourcing, procurement, transport, unloading, storage
as well as distribution of NG to the CCGT Plant.
The table below present three typical LNG compositions as detailed in the norm NF EN ISO 16903
issued in September 2015.

Table 13 Typical LNG characteristics, according to norm NF EN ISO 16903

Characteristics @ Flash point, 1


Unit Example 1 Example 2 Example 3
atm
N2 % mol/mol 0.1399.8 1.79 0.36
CH4 % mol/mol 0.07 93.9 87.2
C2H6 % mol/mol - 3.26 8.61
C3H8 % mol/mol - 0.69 2.74
C4H10 % mol/mol - 0.27 1.07
C5H12 % mol/mol - 0.09 0.02
Molar mass Kg/kmol -16.07 17.07 18.52
Flash point °C 161.9 -166.5 -161.3

3.3.3 Raw water


Potable water terminal point of the existing Fort George Power Station (FGPS) will be used to feed a
new raw water tank appropriately sized to store raw water for the CCGT plant, for an autonomy of 1
day at maximum water consumption, in case of water supply shortage from CWA.

Poonam Tatayah
Ecology Consultant
Biodiversity Consulting Ltd
River view Lane, Verdun.
BRN: C 15130202 55
Environmental and Social
Impact Assessment

Fort George, Mauritius


2017

Note: The quantity of water required for the daily operation of the steam turbine is yet to be
determined.

3.4 CCGT PROCESS


3.4.1 General process diagram
A compressor adds pressure to fresh air and draws it to the combustion chamber.
Then, fuel is mixed with the compressed air and ignited to produce hot combustion gases, at
constant pressure. The temperature of hot gas is between 1,300-1,500 °C.
The hot combustion gases expand inside the turbine section, and spins the rotor.
The turbine is coupled to a generator which generates electricity. The gases exiting the turbine still
have some remaining thermal energy which can be further extracted. In the HRSG, the heat transfer
from the hot exhaust gases (temperature between 550 - 650 °C),
results in production of steam from the water of the circuit 1.
This steam spins the steam turbine which is coupled to an alternator, thereby generating electricity.
The steam is then transformed into water in the condenser by a circuit 2 of cooling (water cooling or
air-cooled condenser)
The water of the condenser is sent towards the circuit 1 and towards HRSG (returns to stage 5).
Both generators produce electricity at 11,000 Volts which will then be transformed to 66,000 Volts
and exported to the grid, by means of transmission lines.

Poonam Tatayah
Ecology Consultant
Biodiversity Consulting Ltd
River view Lane, Verdun.
BRN: C 15130202 56
Environmental and Social
Impact Assessment

Fort George, Mauritius


2017

Figure 6 CCGT process (Source EDF, edited by Biotope)

Poonam Tatayah
Ecology Consultant
Biodiversity Consulting Ltd
River view Lane, Verdun.
BRN: C 15130202 57
Environmental and Social
Impact Assessment

Fort George, Mauritius


2017

3.5 TYPICAL SCOPE OF WORK


The scope of work for this project includes the design, engineering, procurement, supply and
transportation of material and equipment, installation, erection and construction, testing and
commissioning, and putting into service the CCGT power plant.
The scope of supply will include but not be limited to the following:

3.5.1 Mechanical
• 2 Gas turbines;
• 2 Heat Recovery Steam Generators;
• 1 Steam Turbine;
• Air cooled condenser;
• Closed circuit cooling water system;
• Water treatment plant;
• Waste water treatment plant;
• Waste treatment disposal system;
• Fire & gas protection & detection system;
• Compressed air system;
• DFO storage area.

3.5.2 Electrical
• Network grounding systems;
• New 66kV Substation based on GIS technology to connect the power plant to the grid;
• Generators;
• Generator circuit breakers;
• Power transformers;
• Generator and transformer protection system and other protective relay equipment;
• MV and LV cabling, cable tray, trenches, cable ducts etc;
• DC and emergency power supply;
• Diesel generators (for emergency and black start supply);
• MV and LV motors;
• Cables and accessories;
• Lightning & earthing system;
• Exhaust gases and Water emissions monitoring equipment;
• General control system & supervision from main control room (on existing FGPS) and
local technical rooms.

3.5.3 Civil
• Site preparation (site clearance, excavation, landfill, leveling and grading of construction
sites);
• Site access roads;

Poonam Tatayah
Ecology Consultant
Biodiversity Consulting Ltd
River view Lane, Verdun.
BRN: C 15130202 58
Environmental and Social
Impact Assessment

Fort George, Mauritius


2017

• Utilities pipes work;


• Pipes and cables racks;
• Storm, oily and plant drainage systems;
• Fencing and gates and site services;
• Underground services;
• Steam Turbine & Generator Hall;
• Gas Turbines & generators Hall;
• Electrical rooms & control rooms;
• Chemical Building and Laboratory;
• Instrument and Service Air Compressor Building;
• Warehouse;
• Foundations for required components.

3.6 CCGT STRUCTURES, BUILDINGS AND OTHER SYSTEM


3.6.1 Turbine halls, CCR and associated building, gatehouse
The gas turbines and steam turbine will be installed in separate, turbine halls to protect the equipment
from ambient conditions, to ease maintenance of the turbines/generators, and auxiliaries. The turbine
halls will as well serve as efficient noise barriers.
The gas turbines have been arranged at right angle to the dominant winds in the area
(Northwest/South-East in both directions depending on the time of the year) to avoid recirculation of
the flue gas to the gas turbine compressor inlet.
Due to the limited space, available for the construction of the CCGT and to optimize investment, the
new plant will share the following facilities with the existing Fort George thermal Power Station
(FGPS):
• Central Control Room;
• Parking lot;
• Main DFO storage (conversion of existing HFO tank(s));
• Firefighting storage and pump house;
• Waste water treatment (a part) and discharge channel.
The gatehouse will include a reception and visitor front office, an office for security personnel (3
permanent people) with restroom, and the necessary space for intrusion monitoring system and CCTV
system. At least one emergency gate will be provided to allow a second access to the site in case of
emergency (e.g. firefighting brigade) and to ease access for the movement of heavy equipment.
The Fort George road separating the existing FGPS and the CCGT sites will converted to a controlled
access* road. Access control, will be managed by CEB. (*Subject to approval by the MPA).

Poonam Tatayah
Ecology Consultant
Biodiversity Consulting Ltd
River view Lane, Verdun.
BRN: C 15130202 59
Environmental and Social
Impact Assessment

Fort George, Mauritius


2017

3.6.2 Effluent and Waste Treatment Facility

Oily effluents and oil filled transformers


• Potentially oil contaminated wastewater shall be collected into oily water separators. After
oil separation and quality control, effluents shall be discharged in the wastewater
collecting network.
• The skimmed oil shall be collected in an oil tank and then forwarded to the existing FGPS
plant for treatment.
Oil filled transformers shall be installed on concrete bases having a containment pit designed to collect
oil spillage, rainwater and firefighting flows. The pit shall be designed to contain an oil spill and allow
excess retained water to be drained. Drainage of the pit shall be connected to the oily water
connection (with water oil separators). Fire barriers devices shall be provided to prevent fire from
spreading to the oily water connection.

Wastewater discharge
The wastewater discharge terminal point will be located at the north-west of the site and will be
connected to the discharge system of the existing FGPS. A new trench or duct will be required for
linking the existing channel to the new system. The CCGT waste water discharge is expected to be
around 2 m³/h, which is compatible with the current design of the FGPS discharge channel.

Rainwater
Rainfall run-off collected from undisturbed areas shall be diverted and prevented from entering the
sanitary sewer, contaminated drains or chemical drains. The undisturbed areas shall include areas
with no equipment or equipment that does not contain any chemicals or oil that may leak. As far as
possible, non-potentially polluted rainwater shall be re-used on site, or disposed of, in compliance with
applicable Laws.
Rainfall run-off from active areas is to be collected in a dedicated drain system. This wastewater shall
be treated, as necessary, prior to discharge in compliance with Applicable Laws. A soakaway pit (or
Storm Basin) shall be provided as last pollution barrier before the final discharge. If effluents rejection
pumps are required, 2 x 100% redundancy shall be applied. Pumps operation shall be completed to
level in the soak away pit and to effluents quality. The soakaway pit shall be sized to be able to
manage rainfall rate as per worst site conditions.

Chemicals/ process effluents


Chemical / process wastewater, when only pH adjustment is needed to comply with applicable Laws,
shall be collected into the neutralization pit to adjust the pH to the required values. After quality control,
effluents shall be discharged either in a wastewater collecting network or directly out of the Site in
compliance with applicable Laws. Hot process effluents such as HRSG blow down, steam lines drain
or feed water, shall be cooled to bring back their temperature to an acceptable level.

Poonam Tatayah
Ecology Consultant
Biodiversity Consulting Ltd
River view Lane, Verdun.
BRN: C 15130202 60
Environmental and Social
Impact Assessment

Fort George, Mauritius


2017

Figure 7 Site configuration (Source : EDF 2017))

Poonam Tatayah
Ecology Consultant
Biodiversity Consulting Ltd
River view Lane, Verdun. 61
BRN: C 15130202
Environmental and Social
Impact Assessment

Fort George, Mauritius


2017

4 CONCLUSION
This chapter of the ESIA gives an overview of the project, details the technologies used for
generation of electricity as well as the basic design of the power plant. Major components/equipment
which will comprise the CCGT power plant are detailed. A site plan detailing an indicative
arrangement of the power plant is also provided.

Poonam Tatayah
Ecology Consultant
Biodiversity Consulting Ltd
River view Lane, Verdun.
BRN: C 15130202 62

S-ar putea să vă placă și