1 Site clearance incl. removal of grass, trees, dispose off site. 1,510.00 m2 12,500 18,875,000
Cutting Soil
Excavation for Leveling Building Floor 3,020.00 m3 85,000 256,700,000
Filling Soil
Filling up at Villa Building 240.35 m3 165,000 39,658,130
Bill No.2.1/3
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
I STRUCTURE
I.1 SUBSTRUCTURE
1 Bowplank 210.00 m 49,000 10,290,000
2 Bored pile
-MOB-DEMOB 1.00 ls
-PDA test 1.00 ls Already included in Already included in the
-Kentledge test 1.00 ls the main building main building
-Lateral Loading test 1.00 ls
-Boring, 400mm diameter from bottom level to proposed bored
196.00 m 295,000 57,820,000
pile level including blind boring, lining.
-Concrete filling K-300 (fc' = 25 Mpa), to 300mm diameter pile 24.62 m 3
1,075,000 26,466,500
-General reinforcing bar; deformed high tensile steel BJTS 40, D-16mm
2,027.96 kg 12,500 25,349,500
-Spiral stirrups; high tensile steel BJTD 24, ø-8mm 909.34 kg 12,500 11,366,750
-Remove surplus excavated material/soil disposal from site 24.62 m3 49,500 1,218,690
3 Excavation
-Excavation for continuous fondation 958.65 m3 34,000 32,594,100
-Excavation for footing foundation 450.02 m3 34,000 15,300,680
-Excavation for tiebeam 101.79 m3 34,000 3,460,860
4 Soil disposal and backfilling
-Back fill Beside Of Foundation, Tiebeam 606.03 m3 26,500 16,059,795
-Remove surplus excavated material/soil disposal from site 904.43 m3 49,500 44,769,285
5 Compacted sand bedding
-100 mm thick compacted sand layer under footing foundation 25.86 m3 243,000 6,283,980
-100 mm thick compacted sand layer under slab&beam 120.64 m3 243,000 29,315,520
6 Termite prevention
-Termiban or Prevail 100EC or equal approved termite protection m2
applied to building platform and surfaces of excavation 1,265.72 11,000 13,922,920
7 Vapour barrier
-Plastic sheet 0.2mm thick under floor slab 1,206.43 m2 6,200 7,479,866
8 Lean concrete
-50 mm thick concrete under footing foundation 12.93 m3 720,000 9,309,600
-50 mm thick concrete under slab and beam 60.32 m3 720,000 43,430,400
9 River stone foundation 659.21 m3 750,000 494,407,500
10 Supply and install formwork as specified :
-Concrete block formwork including cement mortar
-To sides of pile cap 323.24 m2 85,000 27,475,400
-To Sides and soffits of tie beam 476.76 m2 85,000 40,524,600
-Formwork w/ plywood 9 mm, including timber frames support
- To sides of retaining wall 576.61 m2 142,000 81,878,620
- To sides of coloumn 456.71 m2 92,000 42,017,320
- To sides of slab 100mm high 180.95 m' 24,450 4,424,228
- To sides of Wall Lift 200mm thk 315.92 m2 142,000 44,860,640
- To sides of Wall pond 88.22 m2 142,000 12,527,240
Bill No.2.2/4
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
SUBSTRUCTURE
Supply and install grade BJTD-40 (fy = 400 Mpa) hot rolled deformed
10 bar, reinforcement and BJTD -24 (fy = 240 Mpa) plain bar
reinforcement in the following
-General reinforcing bars in pile caps 12,251.95 kg 12,500 153,149,375
-General reinforcing bars in tie beam 13,991.29 kg 12,500 174,891,125
-Wiremesh M9 for 3rd terrace slab (2 layer) 729.74 m2 95,000 69,325,300
-General reinforcing bars in retaining wall 6,371.44 kg 12,500 79,643,000
-General reinforcing bars in coloumn 10,237.63 kg 12,500 127,970,375
-General reinforcing bars in wall lift 4,086.72 kg 12,500 51,084,000
-General reinforcing bars in wall pond 714.58 kg 12,500 8,932,250
11 K-300 (fc' = 25 Mpa) reinforced concrete to :
-Concrete Pilecaps 149.89 m3 1,075,000 161,131,750
-Concrete Tie beam 50.93 m3 1,075,000 54,749,750
-Concrete 2nd Terrace slab 200mm thk with integral waterprofing 72.97 m3 1,325,000 96,685,250
-Concrete retaining wall with integral waterprofing 41.64 m3 1,325,000 55,173,000
-Concrete coloumn 39.75 m3 1,075,000 42,731,250
-Concrete wall lift 29.43 m3 1,075,000 31,637,250
3
-Concrete wall pond 5.29 m 1,075,000 5,686,750
Bill No.2.2/5
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
Bill No.2.2/6
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
UPPER STRUCTURE
Supply and install grade BJTD-40 (fy = 400 Mpa) hot rolled
deformed bar, reinforcement and BJTD -24 (fy = 240 Mpa) plain bar
reinforcement in the following
b. 1st Terrace Floor
- General reinforcing bars in coloumn 17,979.39 kg 12,500 224,742,375
- General reinforcing bars in stair 461.30 kg 12,500 5,766,277
- General reinforcing bars in beam 10,152.90 kg 12,500 126,911,250
- Wiremesh M7 for 1st terrace slab (2 layer) 334.94 m2 72,000 24,115,680
- Wiremesh M6 for 1st terrace slab (1 layer) 1,434.90 m2 54,000 77,484,600
- Wiremesh M9 for 1st terrace slab (2 layer) 156.78 m2 92,000 14,423,760
- General reinforcing bars in wall pond 794.45 m2 12,500 9,930,625
c. Lobby Floor
- General reinforcing bars in coloumn 17,104.83 kg 12,500 213,810,375
- General reinforcing bars in stair 461.30 kg 12,500 5,766,277
- General reinforcing bars in beam 18,904.52 kg 12,500 236,306,500
- Wiremesh M6 for Lobby floor slab (1 layer) 141.75 m2 72,000 10,206,000
- Wiremesh M7 for Lobby floor slab (2 layer) 1,957.77 m2 77,000 150,748,290
- Wiremesh M8 for Lobby floor slab (2 layer) 80.00 m2 85,000 6,800,000
- Wiremesh M9 for Lobby floor slab (2 layer) 147.44 m2 92,000 13,564,480
- Wiremesh M10 for lobby slab (2 layer) 89.54 m2 105,000 9,401,700
- General reinforcing bars in Wall pond 1,765.93 kg 12,500 22,074,125
d. 1st Upper Floor
- General reinforcing bars in coloumn 12,025.18 kg 12,500 150,314,750
- General reinforcing bars in stair 461.30 kg 12,500 5,766,277
- General reinforcing bars in beam 20,961.64 kg 12,500 262,020,500
- Wiremesh M7 for 1st upper floor slab (2 layer) 1,537.99 m2 72,000 110,735,280
- Wiremesh M9 for 1st upper floor slab (2 layer) 845.90 m2 92,000 77,822,800
- General reinforcing bars in Wall pond 3,066.83 kg 12,500 38,335,375
e. 2nd Upper Floor
- General reinforcing bars in coloumn 6,684.84 kg 12,500 83,560,500
- General reinforcing bars in stair 461.30 kg 12,500 5,766,277
- General reinforcing bars in beam 11,815.56 kg 12,500 147,694,500
- Wiremesh M7 for 2nd upper floor slab (2 layer) 1,144.84 m2 72,000 82,428,480
f. Top Roof Floor
- General reinforcing bars in coloumn 247.98 kg 12,500 3,099,726
- General reinforcing bars in stair 461.30 kg 12,500 5,766,277
- General reinforcing bars in beam 5,935.66 kg 12,500 74,195,750
- Wiremesh M7 for top roof floor slab (2 layer) 561.48 m2 72,000 40,426,560
g. Roof Beam Floor
- General reinforcing bars in beam 1,251.38 kg 12,500 15,642,250
- Wiremesh M7 for top roof floor slab (2 layer) 93.68 m2 72,000 6,744,960
Bill No.2.2/7
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
Bill No.2.2/8
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
Bill No.2.2/9
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
1 100 mm thick light brick masonry ex "Hebel", laid in stretcher bond with
mortar including lintel beams,practical column, and control joints.
Bill No.2.2/10
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
Recapitulation
Bill No.2.2/11
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
I STRUCTURE
I.1 SUBSTRUCTURE
8 Vapour barrier
-Plastic sheet 0.2mm thick under floor slab 264.76 m2 6,200 1,641,500.00
9 Lean concrete
-50 mm thick concrete under footing foundation 2.22 m3 720,000 1,601,300.00
-50 mm thick concrete under slab and beam 13.09 m3 720,000 9,427,700.00
10 Supply and install formwork as specified :
-Concrete block formwork including cement mortar
-To sides of pile cap 53.76 m2 85,000 4,569,600.00
-To Sides of tie beam 75.64 m2 85,000 6,429,300.00
-Formwork w/ plywood 9 mm, including timber frames support
-To sides of pedestal coloumn 41.75 m2 92,000 3,841,000.00
-To sides of slab 100 ~120mm high 71.40 m' 19,560 1,396,600.00
-To sides of coloumn 105.30 m2 92,000 9,687,500.00
Supply and install grade BJTD-40 (fy = 400 Mpa) hot rolled deformed
11 bar, reinforcement and BJTD -24 (fy = 240 Mpa) plain bar
reinforcement in the following
-General reinforcing bars in pile caps 1,344.55 kg 12,500 16,806,900.00
-General reinforcing bars in tie beam 1,839.67 kg 12,500 22,995,900.00
-General reinforcing bars in pedestal coloumn 693.35 kg 12,500 8,666,800.00
-Wiremesh M6 for ground slab (1 layer) 261.88 m2 55,000 14,403,600.00
-General reinforcing bars in coloumn 1,434.57 kg 12,500 17,932,100.00
Bill No.2.3/12
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
SUBSTRUCTURE
Bill No.2.3/13
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
1 Supply and install Formwork w/ plywood 9 mm, including timber frames support
-To Sides and soffits of suspended beam 167.01 m2 156,500 26,136,700.00
-To soffits of slab 142.99 m2 147,000 21,019,500.00
-To sides of slab 100 ~120mm high 110.00 m' 19,560 2,151,600.00
Supply and install grade BJTD-40 (fy = 400 Mpa) hot rolled deformed
2 bar, reinforcement and BJTD -24 (fy = 240 Mpa) plain bar
reinforcement in the following
-General reinforcing bars in beam 2,850.73 kg 12,500 35,634,100.00
-Wiremesh M6 for ground slab (2 layer) 285.98 m2 55,000 15,728,900.00
3 K-300 (fc' = 25 Mpa) reinforced concrete to :
-Concrete Beam 11.21 m3 1,075,000 12,048,900.00
-Concrete Roof Slab 100mm 14.30 m3 1,075,000 15,371,400.00
Bill No.2.3/14
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
1 100 mm thick light brick masonry ex "Hebel", laid in stretcher bond with
mortar including lintel beams,practical column, and control joints.
-Wall at Ground floor 545.46 m2 185,736 101,310,600
Bill No.2.3/15
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
Recapitulation
Bill No.2.3/16
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
I STRUCTURE
I.1 SUBSTRUCTURE
I.1.1 CONCRETE STRUCTURE
1 Bowplank 48.00 m 49,000 2,352,000.00
2 Bored pile
-MOB-DEMOB 1.00 ls
-PDA test 1.00 ls Already included in Already included in the
-Kentledge test 1.00 ls the main building main building
-Lateral Loading test 1.00 ls
-Boring, 300mm diameter from bottom level to proposed bored
49.00 m 145,000 7,105,000.00
pile level including blind boring, lining.
-Concrete filling K-300 (fc' = 25 Mpa), to 300mm diameter pile 3.46 m3 1,075,000 3,721,500.00
-General reinforcing bar; deformed high tensile steel BJTD 40, D-13mm 328.47 kg 12,500 4,105,900.00
-Spiral stirrups; high tensile steel BJTP 24, ø-8mm 173.09 kg 12,500 2,163,600.00
-Remove surplus excavated material/soil disposal from site 3.46 m3 49,500 171,400.00
3 Excavation
-Excavation for footing foundation 27.97 m3 34,000 950,900.00
-Excavation for river stone foundation 11.52 m3 34,000 391,700.00
4 River Stone Foundation 19.20 m3 603,000 11,577,600.00
5 Soil disposal and backfilling
-Back Fill Beside Of Foundation 16.53 m3 26,500 438,000.00
-Backfilling with excavated material to build up platform 46.58 m3 49,500 2,305,700.00
6 Compacted sand bedding
-100 mm thick compacted sand layer under footing foundation 2.18 m3 243,000 528,800.00
-100 mm thick compacted sand layer under river stone foundation 1.44 m3 243,000
349,900.00
-100 mm thick compacted sand layer under slab beam 5.48 m3 243,000 1,331,600.00
6 Termite prevention
-Termiban or Prevail 100EC or equal approved termite protection m2
applied to building platform and surfaces of excavation 57.16 11,000 628,700.00
7 Vapour barrier
-Plastic sheet 0.2mm thick under floor slab 57.16 m2 6,200 354,400.00
8 Lean concrete
-50 mm thick concrete under footing foundation 1.09 m3 720,000 783,400.00
-50 mm thick concrete under slab and beam 2.74 m3 720,000 1,972,800.00
9 Supply and install formwork as specified :
-Concrete block formwork including cement mortar
-To sides of pile cap 28.28 m2 85,000 2,403,800.00
-To Sides and soffits of beam 66.96 m2 85,000 5,691,500.00
-Formwork w/ plywood 9 mm, including timber frames support
-To sides of pedestal coloumn 39.55 m2 92,000 3,638,600.00
-To sides of slab 120 ~ 200mm high 24.20 m' 32,600 788,900.00
-To sides of coloumn 28.02 m2 92,000 2,577,800.00
-To sides of concrete retaining wall 36.00 m2 142,000 5,112,000.00
Bill No.2.4/17
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
Supply and install grade BJTD-40 (fy = 400 Mpa) hot rolled deformed
10 bar reinforcement and BJTP -24 (fy = 240 Mpa) plain bar
reinforcement in the following :
-General reinforcing bars in pile caps 696.31 kg 12,500 8,703,900
-General reinforcing bars in beam 1,582.04 kg 12,500 19,775,600
-General reinforcing bars in pedestal coloumn 821.36 kg 12,500 10,267,000
-Wiremesh M7 for ground slab (2 layer) 109.74 m2 72,000 7,901,300
-General reinforcing bars in coloumn 325.48 kg 12,500 4,068,500
-Concrete retaining wall 315.90 kg 12,500 3,948,800
11 K-300 (fc' = 25 Mpa) reinforced concrete to :
-Concrete Pilecaps 7.84 m3 1,075,000 8,428,000
-Concrete Beam 5.20 m3 1,075,000 5,586,500
-Concrete Pedestal Coloumn 2.47 m3 1,075,000 2,657,300
-Concrete ground slab 120mm thk 6.58 m3 1,075,000 7,078,200
-Concrete Coloumn 1.01 m3 1,075,000 1,085,500
-Concrete retaining wall 2.34 m3 1,075,000 2,515,500
Bill No.2.4/18
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
Bill No.2.4/19
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
Recapitulation
SUB BILL NO. 2.4 : COURTYARD VILLA (7 UNIT) TOTAL FOR 4 NO VILLA 1,513,292,200
Bill No.2.4/20
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
I STRUCTURE
I.1 SUBSTRUCTURE
I.1.1 CONCRETE STRUCTURE
1 Bowplank 95.00 m 49,000 4,655,000
2 River stone retaining wall
-Excavation for river stone masonry 1.00 ls
Already included in
-100 mm thick compacted sand layer under river stone masonry 1.00 Already included in the
ls the land gradding
land gradding work
work
-River Stone masonry 1.00 ls
3 Bored pile
-MOB-DEMOB 1.00 ls
Already included in
-PDA test 1.00 ls Already included in the
the main building
-Kentledge test 1.00 ls main building work
work
-Lateral Loading test 1.00 ls
-Boring, 300mm diameter from bottom level to proposed bored
203.00 m 145,000 29,435,000
pile level including blind boring, lining.
-Concrete filling K-300 (fc' = 25 Mpa), to 300mm diameter pile 3
14.34 m 1,075,000 15,418,000
-General reinforcing bar; deformed high tensile steel BJTD 40, D-13mm
1,360.82 kg 12,500 17,010,000
-Spiral stirrups; high tensile steel BJTP 24, ø-8mm 717.09 kg 12,500 8,964,000
-Remove surplus excavated material/soil disposal from site 14.34 m3 49,500 710,000
4 Excavation
-Excavation for footing foundation 44.18 m3 34,000 1,502,000
-Excavation for river stone foundation 21.60 m3 34,000 735,000
5 River Stone Foundation 29.70 m3 603,000 17,911,000
6 Soil disposal and backfilling
-Back Fill Beside Of Foundation 3.51 m3 26,500 93,000
-Backfilling with excavated material to build up platform 65.10 m3 26,500 1,725,000
-Remove surplus excavated material/soil disposal from site 127.38 m3 49,500 6,305,000
7 Compacted sand bedding
-100 mm thick compacted sand layer under footing foundation 9.49 m3 243,000 2,305,000
-100 mm thick compacted sand layer under river stone foundation 1.35 m3 243,000
328,000
6 Termite prevention
-Termiban or Prevail 100EC or equal approved termite protection
applied to building platform and surfaces of excavation 254.76 m2 11,000 2,802,000
Bill No.2.6/24
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
Bill No.2.6/25
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
14 Supply and install on the Basement 1 with grade BJTD-40 (fy = 400
Mpa) hot rolled deformed bar reinforcement and BJTP -24 (fy = 240
Mpa) plain bar reinforcement in the following :
-General reinforcing bars in pile caps 354.14 kg 12,500 4,427,000
-General reinforcing bars in beam & tie beam 523.84 kg 12,500 6,548,000
-Wiremesh M7 for ground slab (2 layer) 55.46 m2 72,000 3,993,000
-General reinforcing bars in coloumn 72.16 kg 12,500 902,000
-General reinforcing bars in retaining wall 695.42 kg 12,500 8,693,000
15 Supply and install on the Basement 2 with grade BJTD-40 (fy = 400
Mpa) hot rolled deformed bar reinforcement and BJTP -24 (fy = 240
Mpa) plain bar reinforcement in the following :
-General reinforcing bars in pile caps 421.71 kg 12,500 5,271,000
-General reinforcing bars in beam & tie beam 648.74 kg 12,500 8,109,000
-Wiremesh M7 for ground slab (2 layer) 55.46 m2 72,000 3,993,000
-General reinforcing bars in coloumn 175.02 kg 12,500 2,188,000
-General reinforcing bars in retaining wall 1,445.97 kg 12,500 18,075,000
16 Supply and install on the Basement 3 with grade BJTD-40 (fy = 400
Mpa) hot rolled deformed bar reinforcement and BJTP -24 (fy = 240
Mpa) plain bar reinforcement in the following :
-General reinforcing bars in pile caps 714.20 kg 12,500 8,928,000
-General reinforcing bars in beam & tie beam 710.38 kg 12,500 8,880,000
-Wiremesh M6 for ground slab (1 layer) 27.72 m2 55,000 1,525,000
-Wiremesh M9 for ground slab (2 layer) 17.30 m2 95,000 1,644,000
-General reinforcing bars in coloumn 82.74 kg 12,500 1,034,000
-General reinforcing bars in retaining wall 1,088.01 kg 12,500 13,600,000
17 K-300 (fc' = 25 Mpa) reinforced concrete on the Ground Floor to :
-Concrete pilecaps 0.67 m3 1,075,000 722,000
-Concrete beam & tie beam 2.34 m3 1,075,000 2,515,000
-Concrete ground slab 120mm thk 6.67 m3 1,075,000 7,173,000
-Concrete coloumn 1.09 m3 1,075,000 1,175,000
18 K-300 (fc' = 25 Mpa) reinforced concrete on the Basement 1 to :
-Concrete pilecaps 3.91 m3 1,075,000 4,205,000
-Concrete beam & tie beam 2.29 m3 1,075,000 2,460,000
-Concrete ground slab 120mm thk 3.33 m3 1,075,000 3,577,000
-Concrete coloumn 0.33 m3 1,075,000 360,000
-Concrete retaining wall 4.57 m3 1,075,000 4,912,000
19 K-300 (fc' = 25 Mpa) reinforced concrete on the Basement 2 to :
-Concrete pilecaps 5.12 m3 1,075,000 5,504,000
-Concrete beam & tie beam 2.91 m3 1,075,000 3,132,000
-Concrete ground slab 120mm thk 3.33 m3 1,075,000 3,577,000
-Concrete coloumn 0.55 m3 1,075,000 591,000
-Concrete retaining wall 10.21 m3 1,075,000 10,974,000
Bill No.2.6/26
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
1 100 mm thick light brick masonry ex "Hebel", laid in stretcher bond with
mortar including lintel beams,practical column, and control joints.
-Lobby area 45.01 m2 185,736 8,360,000
-Salon & meni pedi area 48.72 m2 185,736 9,049,000
-Spa 1 8.28 m3 185,736 1,538,000
-Spa 2 8.28 m3 185,736 1,538,000
-Spa 3 8.28 m3 185,736 1,538,000
Bill No.2.6/27
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
Bill No.2.6/28
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
c Spa 1
18 100X100x1800mm size bengkirai wood to balinese timber post
1.00 unit 353,000 353,000
(tugeh)
19 5x10cm size bengkirai wood to ring beam 13.10 m' 118,404 1,551,000
20 5x12cm size bengkirai wood to beam (balinese T beams at the
12.50 m' 118,404 1,480,000
bottom "lambang" )
21 5x14cm size bengkirai wood to beam (balinese T beams at the top
12.50 m' 148,005 1,850,000
"sineb")
22 5x11cm size bengkirai wood to beam (balinese expose rafter located
15.60 m' 118,404 1,847,000
in the middle of truss "Pemade")
23 5x11cm size bengkirai wood to beam (balinese expose rafter located
15.60 m' 118,404 1,847,000
in the corner of truss "Pemucu")
23 Round bamboo ø-50mm with termite protection treatment to rafter 56.34 m2 99,450 5,603,000
24 2x35cm size bengkirai wood as cover ceiling corner (dedeleg) 2.40 m' 128,500 308,000
25 2,5x25cm size bengkirai wood as cover ceiling corner (dedeleg) 2.40 m' 125,000 300,000
26 2,5x15cm size bengkirai wood as cover ceiling corner (dedeleg) 2.40 m' 81,000 194,000
26 3x5cm size bengkirai wood to (balinese wooden trim located in the
29.20 m' 31,000 905,000
middle of the rafter "Apit-apit")
27 1,5x5cm size bengkirai wood to (balinese wooden trim located in the
29.20 m' 21,500 628,000
middle of the rafter "Apit-apit")
28 5x11cm size bengkirai wood to pascia 18.60 m' 118,404 2,202,000
29 3x7cm size bengkirai wood to pascia 18.60 m' 44,800 833,000
c Spa 2
30 5x10cm size bengkirai wood to ring beam 12.70 m' 118,404 1,504,000
31 5x12cm size bengkirai wood to beam (balinese T beams at the
12.20 m' 118,404 1,445,000
bottom "lambang" )
32 5x14cm size bengkirai wood to beam (balinese T beams at the top
12.20 m' 148,005 1,806,000
"sineb")
33 Round bamboo ø-50mm with termite protection treatment to rafter 51.75 m2 99,450 5,147,000
d Spa 3
34 100X100x1800mm size bengkirai wood to balinese timber post
1.00 unit 353,000 353,000
(tugeh)
35 5x10cm size bengkirai wood to ring beam 13.10 m' 118,404 1,551,000
36 5x12cm size bengkirai wood to beam (balinese T beams at the
20.20 m' 118,404 2,392,000
bottom "lambang" )
37 5x14cm size bengkirai wood to beam (balinese T beams at the top
20.20 m' 148,005 2,990,000
"sineb")
38 5x11cm size bengkirai wood to beam (balinese expose rafter located
15.60 m' 118,404 1,847,000
in the middle of truss "Pemade")
39 5x11cm size bengkirai wood to beam (balinese expose rafter located
15.60 m' 118,404 1,847,000
in the corner of truss "Pemucu")
39 Round bamboo ø-50mm with termite protection treatment to rafter 56.34 m2 99,450 5,603,000
40 2x35cm size bengkirai wood as cover ceiling corner (dedeleg) 2.40 m' 128,500 308,000
41 2,5x25cm size bengkirai wood as cover ceiling corner (dedeleg) 2.40 m' 125,000 300,000
42 2,5x15cm size bengkirai wood as cover ceiling corner (dedeleg) 2.40 m' 81,000 194,000
42 3x5cm size bengkirai wood to (balinese wooden trim located in the
29.20 m' 31,000 905,000
middle of the rafter "Apit-apit")
43 1,5x5cm size bengkirai wood to (balinese wooden trim located in the
29.20 m' 21,500 628,000
middle of the rafter "Apit-apit")
44 5x11cm size bengkirai wood to pascia 18.60 m' 118,404 2,202,000
45 3x7cm size bengkirai wood to pascia 18.60 m' 44,800 833,000
Bill No.2.6/29
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
Recapitulation
Bill No.2.6/30
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
I STRUCTURE
I.1 SUBSTRUCTURE
I.1.1 CONCRETE STRUCTURE
1 Bowplank 42.00 m 49,000 2,058,000
2 River stone retaining wall
-Excavation for river stone masonry 1.00 ls Already included in
Already included in the
-100 mm thick compacted sand layer under river stone masonry 1.00 ls the land gradding
land gradding work
-River Stone masonry 1.00 ls work
3 Bored pile
-MOB-DEMOB 1.00 ls
Already included in
-PDA test 1.00 ls Already included in the
the main building
-Kentledge test 1.00 ls main building work
work
-Lateral Loading test 1.00 ls
-Boring, 300mm diameter from bottom level to proposed bored
56.00 m 145,000 8,120,000
pile level including blind boring, lining.
-Concrete filling K-300 (fc' = 25 Mpa), to 300mm diameter pile 3
3.96 m 1,075,000 4,253,000
-General reinforcing bar; deformed high tensile steel BJTD 40, D-13mm 375.40 kg 12,500 4,692,000
-Spiral stirrups; high tensile steel BJTP 24, ø-8mm 197.82 kg 12,500 2,473,000
-Remove surplus excavated material/soil disposal from site 3.96 m3 49,500 196,000
4 Excavation
-Excavation for footing foundation 13.43 m3 34,000 456,000
-Excavation for river stone foundation 4.26 m3 34,000 145,000
5 River Stone Foundation 6.75 m3 603,000 4,067,000
6 Soil disposal and backfilling
-Back Fill Beside Of Foundation 9.04 m3 26,500 240,000
-Backfilling with excavated material to build up platform to 4.83 m3 26,500 128,000
bathroom area
-Remove surplus excavated material/soil disposal from site 3.81 m3 49,500 189,000
7 Compacted sand bedding
-100 mm thick compacted sand layer under footing foundation 6.56 m3 243,000 1,594,000
-100 mm thick compacted sand layer under river stone foundation 0.36 m3 243,000
86,000
6 Termite prevention
-Termiban or Prevail 100EC or equal approved termite protection
applied to building platform and surfaces of excavation 18.66 m2 11,000 205,000
Bill No.2.7/31
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
10 Supply and install grade BJTD-40 (fy = 400 Mpa) hot rolled deformed
bar reinforcement and BJTP -24 (fy = 240 Mpa) plain bar
reinforcement in the following :
-General reinforcing bars in pile caps 331.37 kg 12,500 4,142,000
-General reinforcing bars in beam 1,057.14 kg 12,500 13,214,000
-General reinforcing bars in pedestal coloumn 246.42 kg 12,500 3,080,000
-Wiremesh M7 for ground slab (2 layer) 131.76 m2 72,000 9,487,000
-General reinforcing bars in coloumn 135.57 kg 12,500 1,695,000
-General reinforcing bars in 30 cm thk concrete wall ("shear wall") 6,601.50 kg 12,500 82,519,000
11 K-300 (fc' = 25 Mpa) reinforced concrete to :
-Concrete Pilecaps 2.88 m3 1,075,000 3,096,000
-Concrete Beam 3.82 m3 1,075,000 4,112,000
-Concrete Pedestal Coloumn 0.88 m3 1,075,000 943,000
-Concrete ground slab 120mm thk 7.91 m3 1,075,000 8,499,000
-Concrete Coloumn 0.58 m33 1,075,000 619,000
-30 cm thk concrete wall ("shear wall") 29.34 m 1,075,000 31,541,000
I.1.2 WALL STRUCTURE
1 100 mm thick light brick masonry ex "Hebel", laid in stretcher bond with
mortar including lintel beams,practical column, and control joints.
-Wall at 1st floor 21.30 m2 185,736 3,956,000
Bill No.2.7/32
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
Bill No.2.7/33
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
Recapitulation
Bill No.2.7/34
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
I STRUCTURE
I.1 SUBSTRUCTURE
7 Vapour barrier
-Plastic sheet 0.2mm thick under floor slab 385.51 m2 6,200 2,390,200
8 Lean concrete
-50 mm thick concrete under pilecaps 4.92 m3 720,000 3,543,900
-50 mm thick concrete under slab and beam 10.68 m3 720,000 7,692,100
9 Supply and install formwork as specified :
-Concrete block formwork including cement mortar
-To sides of pile cap 136.54 m2 85,000 11,606,100
-To Sides of tie beam 103.49 m2 85,000 8,796,300
-Formwork w/ plywood 9 mm, including timber frames support
-To sides of pedestal coloumn 85.20 m2 92,000 7,838,100
-To sides of Retaining Wall 98.56 m2 156,500 15,424,600
Supply and install grade BJTD-40 (fy = 400 Mpa) hot rolled deformed
10 bar, reinforcement and BJTD -24 (fy = 240 Mpa) plain bar
reinforcement in the following
-General reinforcing bars in pile caps 4,185.41 kg 12,500 52,317,600
-General reinforcing bars in tie beam 4,256.68 kg 12,500 53,208,600
-General reinforcing bars in pedestal coloumn 1,743.26 kg 12,500 21,790,800
-Wiremesh M6 for ground slab (1 layer) 213.68 m2 55,000 11,752,400
-Wiremesh M10 for ground slab (2 layer) 442.32 m2 55,000 24,327,600
-General reinforcing bars in retaining wall 1,574.85 kg 12,500 19,685,600
11 K-300 (fc' = 25 Mpa) reinforced concrete to :
-Concrete Pilecaps 41.77 m3 1,075,000 44,905,500
-Concrete Tie Beam 11.71 m3 1,075,000 12,590,800
-Concrete Pedestal Coloumn 5.54 m3 1,075,000 5,953,400
-Concrete Pool Dinning slab 100mm thk 21.37 m3 1,075,000 22,970,600
-Concrete Pool Slab 200 mm thk 88.46 m3 1,075,000 95,098,800
-Concrete Retaining Wall 200 mm thk 9.86 m3 1,075,000 10,595,200
Bill No.2.8/35
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
1 100 mm thick light brick masonry ex "Hebel", laid in stretcher bond with
mortar including lintel beams,practical column, and control joints.
-Wall at Dinning Bar & Toilet 51.12 m2 185,736 9,494,100
Bill No.2.8/36
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
Recapitulation
SUB BILL NO. 2.8 : POOL & DINNING BAR TOTAL 631,589,000
Bill No.2.8/37
BILL OF QUANTITY
Tanadewa Resort & SPA Ubud, Bali Project
Package 01 : Structure & Architecture Works
SUMMARY
SUB BILL NO. 2.8 : POOL & DINNING BAR Rp. 631,589,000