Q2
WEEK CREW YARDS PRODUCTIVITY
SIZE
1 4 96 24
2 3 72 24
3 4 92 23
4 2 50 25
5 3 69 23
6 2 52 26
Q5
MATERIAL COST TOTAL COST MULTI FACTOR
2700 9900 3.03
2820 11220 2.99
2760 11160 2.89
2880 12480 2.84
Q6
Current productivity =160/40 = 4 hour
Previous productivity =138/30 = 3.83 hour
Productivity growth =
Current - Previous productivity/ Previous productivity * 100
4-3.83/3.83 *100 = 4.44%
7.
UNIT EMPLOYEE DAY LABOUR OVERHEAD MAT. T C LAB. MULTI
COST COST PRODUCTIVITY FACTOR
A 4 36 800 800 180 1780 9 0.0202
B 5 40 1000 1000 200 2200 8 0.01818
C 8 60 1600 1600 300 3500 7.50 0.01714
D 3 20 600 600 100 1300 6.67 0.01538