No Detail Of Works
A. PRELIMINARIES/INDIRECT COST
- Mobilization and Demobilization
- Direction Kit
- Shop Drawing & As Built Drawing
- TKBT Training, Administration & Report
- Health, Safety, Cleaning, Security & Health Insurance
- Electrical Temporary (STPM Standard)
- Scafolding
2 Valve Erection
a. Gate Valve (107 Unit)
b. Ball Valve (276 Unit)
c. Check Valve (102 Unit)
d. Expantion Joint (24 Unit)
e. Y-Strainer (20 Unit)
3 Instrument Erection
a. Control Valve (34 Unit)
b. Actuator Valve (70 Unit)
c. Flow meter
4 Support Pipe
a. Pipe Shoes
- Pipe 1 1/2" Type SP02
- Pipe 3" Type SP04
- Pipe 4" Type SP04
- Pipe 6" Type SP04
b. Support Pipe
Angle Bar 75x75x6mm x6m
UNP CS 100x50x5mm x6m
UNP CS 150x75x6.5mm x6m
UNP CS 200x80x7.5mm x6m
Plat Bar 32x6mm x6m
Sandblast & Painting
2 Valve Erection
a. Gate Valve (131 Unit)
b. Ball Valve (402 Unit)
c. Check Valve (195 Unit)
d. Expansion Joint (40 Unit)
e. Y-Strainer (38 Unit)
3 Instrument Erection
a. Control Valve (45 Unit)
b. Actuator Valve (113 Unit)
c. Flow meter
4 Support Pipe
a. Pipe Shoes
- Pipe 1 1/2" Type SP02
- Pipe 2" Type SP04
- Pipe 2 1/2" Type SP04
- Pipe 3" Type SP04
- Pipe 4" Type SP04
- Pipe 6" Type SP04
b. Support Pipe
Angle Bar 75x75x6mm x6m
UNP CS 100x50x5mm x6m
UNP CS 150x75x6.5mm x6m
UNP CS 200x80x7.5mm x6m
Plat Bar 32x6mm x6m
Sandblast & Painting
D. Utility Lines
15 Valve Erection
a. Butterfly Valve (312 Unit)
b. Ball Valve (645 Unit)
c. Gate Valve (35 Unit)
d. Globe Valve (114 Unit)
c. Check Valve (131 Unit)
d. Expantion Joint (85 Unit)
e. Basket Strainer (14 Unit)
f. Y- Strainer (56 Unit)
g. Steam Check Valve (12 Unit)
h. Steam Strainer (9 Unit)
i Steam Trap (9 Unit)
j. Foot Valve (7 Unit)
k. Floating Valve (6 Unit)
l. Pressure Regulating Valve (45 Unit)
m. Pressure Safety Valve (4 Unit)
16 Instrument Erection
a. Control Valve (8 Unit)
b. Actuator Valve (32 Unit)
c. Flow meter
18 Pipe Support
a. Pipe Shoes
- Pipe 2" Type SP04
- Pipe 2 1/2" Type SP04
- Pipe 3" Type SP04
- Pipe 4" Type SP04
- Pipe 5" Type SP04
- Pipe 6" Type SP04
- Pipe 8" Type SP05
- Pipe 10" Type SP05
- Pipe 12" Type SP05
- Pipe 14" Type SP06
- Pipe 18" Type SP06
- Pipe 20" Type SP06
- Pipe 2" Type SP08
- Pipe 3" Type SP08
- Pipe 4" Type SP08
- Pipe 10" Type SP09
- Pipe 12" Type SP09
- Pipe 14" Type SP09
b. Support Pipe
Angle Bar 75x75x6mm x6m
UNP CS 100x50x5mm x6m
UNP CS 150x75x6.5mm x6m
UNP CS 200x80x7.5mm x6m
WF 250x125x6x9mm x6m
Plat Bar 32x6mm x6m
Sandblast & Painting
DURASI KERJA
- Waktu Durasi Kerja
GRAND TOTAL
PT. MNA SERANG
Unit Volume
Material Labour Total
1,736,500,000
45,623,461,736
Days 120.00
47,359,961,736
SS Pipe
21,819 GTAW 1 Welder : 56 dia.inch/day
23,639 GTAW 22 Welder : 1,232 dia.inch/day
2513 GTAW 45 days : 55,440 dia.inch/day
5366 GTAW : 189,000 Rp dia.inch/day
1800 GTAW : 10,478,160,000
429 GTAW
55,566 Dia.inch
410,412 Rp/Dia.inch
dia.inch/day
dia.inch/day
dia.inch/day
Rp dia.inch/day
dia.inch/day 1
dia.inch/day 8
dia.inch/day 60
Rp dia.inch/day
Rp/Dia.inch