EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
NOTES:
A. Walkthrough for Final punchlisting shall be conducted using the P&ID.
B. Provide specific identification and locations on items that are not conforming with the listed checkpoints. This shall be
written on the Final Punch List (Re-Instatement) Form for Contractor, (and on FEIL-Saudi Aramco Form 6133 for PID).
C. Y/N Designation: Y - Required for start-up and Safety concern
N - Not required for Start-up
Y/N - designation depends on the specifics of the deficient item.
D. Walkthrough of pumps installation normally coincides with the piping system.
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A Y/N RE-INSP DATE
No.
A. Documentation:
Saudi Aramco Test and Inspection Plan (SATIP), with the applicable
GI-2.710,
A2 Checklists for field installation as detailed in SATIP-G-115-01 and have Y
Para. 4.1.1.2
been verified to be complete and accepted.
All non-conformance reports and worksheets have been resolved to the GI-2.710,
A3 Y
satisfaction of Inspection Department. Para. 4.1.1.4
All log book entries have been resolved to the satisfaction of Inspection GI-2.710,
A4 Y/N
Department. Para. 4.1.1.4
All equipment fabrication documents, inspection record books,
GI-2.710,
A5 Equipment Instrument Schedules (EIS), and S.I.S, are available for Y
Para. 4.1.1.6
review/Verification, (refer to SAIC-G-2002).
All operation and Maintenance (O & M) manuals have been submitted to
the proponent for review four (4) weeks prior to MC. GI-2.710,
A6 Y/N
Note: Process O&M manuals for facilities must be approved by the Para. 4.1.1.7
Proponent before Mechanical Completion (MC).
Page 1 of 3
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Final Inspection / Walkthrough of Lubrication, Shaft Sealing
SAIC-G-2015 25-May-05 MECH-
and Control Oil Systems
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A Y/N RE-INSP DATE
No.
Mechanical and Chemical Cleaning of the lube and/or seal oil systems SAES-G-115,
B6 Y
have been performed, (Refer to SAIC-G-2017). Para 5.8
GI-2.710
B7 Pipe inlet and outlet spools were pressure tested. Supplement 6 Y
Para 4-a
Identification is stenciled on major components such as, but not limited to:
(Note: Identification shall follow Equipment identification number
designated on the P&ID).
a. Identification number for pumps
SAES-L-350,
B8 b. Strainer N
Sec. 20
c. Flow element/flow meter
d. Control Valves
e. MOV's
f. Relief Valves
Relief valves were calibrated, tagged and form 3099A was completed, per
B9 Y
SATIP-J-600-01.
If pumps were used for flushing, verify that temporary packing were
GI-2.710,
B10 installed if permanent packing or mechanical seal were not suitable for Y
Item 5.7 c
flushing.
A 6 mm weep hole shall be drilled for all dummy supports. The weep hole
SAES-L-350,
B11 shall be located near the base plate for all vertical dummy supports, and N
Para. 13.2.3
near the run pipe at 6 o'clock position for all horizontal dummy supports.
Pipe shall be in full contact with the supports. Shims shall be provided if SAES-L-310,
B12 N
required Para. 14.2.2
P&ID #
B13 Pressure gages installed are of the same range as shown in the P&ID. Y
____________
Pressure gages are installed with block and bleed valves. SAES-J-200,
B14 Y
NOTE: The bleed valve shall be plugged. Para. 6.1 & 6.4
P&ID #
B15 Temperature Gages installed are of the same range as shown in the P&ID. Y
____________
Thermowells are provided with chained plug and plug installed where
SAES-J-400,
B16 temperature indicators are not provided, (Std. Dwg. N
Para. 5.2.5
AB-36019).
Insertion length of thermowells has been verified to conform with the
SAES-J-400,
B17 standard drawing #AB-036019 for threaded ones and PIP, PCFTE0000 for Y
Para. 5.2.8
flanged ones and meets wake Calculations
P&ID #
B18 All vents and drains are provided with bar stock plugs or blinds. N
____________
Flow direction of Control valves and globe valves (where applicable) follow P&ID #
B19 Y
the process flow direction. ____________
P&ID #
B20 Flow direction of check valves follow the process flow direction. Y
____________
C. Auxiliary Piping:
Page 2 of 3
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Final Inspection / Walkthrough of Lubrication, Shaft Sealing
SAIC-G-2015 25-May-05 MECH-
and Control Oil Systems
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A Y/N RE-INSP DATE
No.
D. Structural Items:
E. Painting:
REMARKS:
REFERENCE DOCUMENTS:
1. G.I.-2.710 -- Mechanical Completion and Performance Acceptance of Facilities, 13 July, 2004
2. Saudi Aramco Pre-Commissioning Form # G-005
3. SAES-L-108 -- Selection of Valves, 31 July, 2004
4. SAES-M-001 -- Structural Design Criteria for Non-Building Structures, 30 June, 2004
5. SAES-L-350 -- Construction of Plant Piping, 30 September, 2003
6. SAES-J-200 -- Pressure, 31 May, 2003
7. SAES-B-054 -- Access, Egress, and Materials Handling for Plant Facilities, 31 March, 2001
8. SAES-B-067 -- Safety Identifications and Safety Colors, 30 November, 2003
9. SAES-J-400 -- Temperature, (31 May, 2004)
11. 01-SAMSS-017 -- Auxiliary Piping For Mechanical Equipment30 November, 1998
12. 12-SAMSS-007 -- Fabrication of Structuraland Miscellaneous Steel, 28 April, 2004
Page 3 of 3